On Thursday, January 19, construction law area chair + attorney Don Gregory presented a seminar on minimizing your risk and avoiding legal problems. This seminar discussed contract language, conditional bids, and killer contract clauses such as contingent payment, no damage for delay, waiver of lien + bond rights, and unconditional lien waivers before payment.
4. z
Did You Condition Your Bid?
This bid is conditioned upon
the use of the ConsensusDOCS
750, AIA A401 or other
subcontract language
acceptable to subcontractor
“
“
5. z
Use ASA bid proposal form or
similar language:
Favorable Conditions of
Proposal:
+ Beginning work constitutes acceptance of bid
+ Change in material price by 5% or more
warrants equitable adjustment
+ Not required to name additional insureds
+ Favorable payment terms
6. z
Use ASA bid proposal form or
similar language:
Favorable Conditions of
Proposal:
+ Entitled to equitable adjustments for
modifications to schedule, delays outside
sub’s control
+ Entitled to rely on contract documents
+ Lien waivers exclude retainage and unbilled
changes/claims
18. z
Why have a mechanic’s
lien statute when it can
be defeated with a
Pay-If-Paid clause?
19. z
Lehrer McGovern
Bovis, Inc. v. Bullock
Insulation, Inc.
Lien waiver and pay-if-paid
provisions are unenforceable based
upon public policy favoring the
statutory right to a mechanic's lien
22. z
Practical Pointers
Look for contracts with
good payment terms
(Fixed payment terms, pay-when-paid)
Try to Insert Pay-When-
Paid Language
(Use AIA A401 or ConsensusDOCS 750)
Modify Pay-If-Paid
Language
26. z
Sole remedy is a
time extension
Generally unenforceable if –
statute/case considers it against
public policy or extent or nature
of delay was not foreseeable
36. z
Change Orders
IN WRITING
Avoid provisions that:
allow one to direct additional
work without agreement on price
make payment for additional work
contingent upon payment by owner
allow “backcharges” without notice
(ConsensusDOCS 750)
38. z
Would love to perform the
work without delay, but
YOUR contract makes me
stop to get a change order
signed in advance!
39. z
LANGUAGE
To Protect Yourself
“Unless you indicate otherwise, we
will proceed with the additional work
as we were directed in the progress
meeting earlier today and this e-mail
shall serve as continued notice of our
intention to receive additional
compensation for this change”
41. z
BE CAREFUL
When Signing Change Orders
Change Orders should just waive
costs for that specific change rather
than all possible extra costs through
the date of the change order
42. z
Questions?
Donald W. Gregory, Director
Kegler Brown Hill + Ritter
dgregory@keglerbrown.com
keglerbrown.com/gregory
614-462-5416