West Building Programmes Update
- 1. West Building ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
$BCP$4 FinalColumn #
40998 M340 M350 M360 M370 M380 M390 M400 M410 M420 M430 M440 M450
29/04/11
30/04/11
27/05/11
28/05/11
24/06/11
25/06/11
29/07/11
30/07/11
02/09/11
03/09/11
30/09/11
01/10/11
28/10/11
29/10/11
25/11/11
26/11/11
30/12/11
31/12/11
03/02/12
04/02/12
02/03/12
03/03/12
30/03/12
31/03/12
15/02/13
ACT Title OD Start Finish (*)Dur(*)Tota(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)TotWBS 1 Level 1 Level 2 Level 3 Level 4 Level 5 Level 6 Most CriMost CritMost CritMost Most Cr
COSPMZ0620 Structural elements up to Mezz. floo 10/06/09 30/07/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP010620 Structural elements up to 1st floor (I 17/06/09 27/08/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP020620 Structural elements up to 2nd floor ( 27/07/09 24/09/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP030620 Structural elements up to 3rd floor ( 13/08/09 06/10/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP040620 Structural elements up to 4th floor ( 25/08/09 15/10/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP050620 Structural elements up to 5th floor ( 16/09/09 27/10/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP060620 Structural elements up to 6th floor ( 28/09/09 08/11/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP070620 Structural elements up to 7th floor ( 17/10/09 17/11/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP080620 Structural elements up to 8th floor ( 24/10/09 01/12/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP090620 Structural elements up to 9th floor ( 04/11/09 10/12/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP100620 Structural elements up to 10th floor 15/11/09 22/12/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP110620 Structural elements up to 11th floor 25/11/09 06/01/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP120620 Structural elements up to 12th floor 13/12/09 18/01/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP130620 Structural elements up to 13th floor 30/12/09 28/01/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP140620 Structural elements up to 14th floor 09/01/10 11/02/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP150620 Structural elements up to 15th floor 21/01/10 25/02/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSPRF0620 Structural elements up to RF floor (In 07/02/10 15/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSPUR0620 Structural elements up to UR floor & 20/02/10 14/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COMF011830 MEP 2nd fixes 12/11/09 12/12/11 75 ‐247 77 ‐249 78 ‐265 80 ‐283 80 ‐303 84 ‐321 87.2 ‐337 95.2 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 1 2 3 4 5
COMF011835 Plaster to column 20/03/10 07/01/12 80 ‐253 80 ‐255 80 ‐271 85 ‐288 85 ‐308 85 ‐324 85 ‐339 90 ‐354 90 ‐342 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011840 Office Fitout (1st & 2nd Fix Trades) 18/04/10 04/04/12 1 ‐242 1 ‐244 1 ‐260 5 ‐279 5 ‐299 5 ‐315 5 ‐331 15 ‐342 20 ‐350 80 ‐343 90 ‐352 90 ‐362 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011845 Basecoat Painting works 26/04/10 16/01/12 36 ‐253 36 ‐255 36 ‐271 36 ‐288 36 ‐308 36 ‐324 36 ‐339 36 ‐354 36 ‐350 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011850 Stone Work @ lift lobby 12/09/10 05/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011860 Ceramic tiles ‐ Wet area 27/10/10 14/01/12 80 ‐211 80 ‐213 80 ‐229 80 ‐246 80 ‐266 80 ‐282 80 ‐297 80 ‐313 80 ‐308 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011865 Testing & clearance prior to false cei 03/05/11 10/01/12 0 ‐213 16 ‐214 16 ‐230 16 ‐247 16 ‐267 16 ‐274 16.7 ‐287 16.7 ‐303 16 ‐297 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 5
COMF011935 MEP final fixes to lift lobby/Corrid./W 13/09/11 26/06/12 0 ‐258 0 ‐250 0 ‐266 0 ‐283 0 ‐303 2 ‐319 2.44 ‐335 3 ‐349 2 ‐355 45 ‐361 90 ‐375 90 ‐390 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 1 2 3 4 5
COMF011925 Ceiling works to lift lobby & bulkhea 18/09/11 10/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 0 ‐275 60 ‐282 80 ‐293 80 ‐309 80 ‐297 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011855 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 24/09/11 15/01/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 70 ‐324 78 ‐339 85 ‐354 85 ‐350 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011895 Ceiling Installation @ Corridore area 26/09/11 11/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 0 ‐267 30 ‐271 30 ‐287 45 ‐288 45 ‐308 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011920 Stone Floor @ Corridore area 08/11/11 14/01/12 0 ‐258 0 ‐249 0 ‐264 0 ‐274 0 ‐286 0 ‐302 0 ‐314 90 ‐330 90 ‐315 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011870 Screed work @ Corridore area 08/11/11 15/11/11 0 ‐187 0 ‐203 0 ‐219 0 ‐239 0 ‐259 0 ‐271 0 ‐287 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011875 Floor Trunking & Raised Floor Install 23/11/11 15/01/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 5 ‐354 37 ‐350 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011915 Threshold & Door Install‐ Wet area 29/12/11 20/02/12 0 ‐222 0 ‐223 0 ‐239 0 ‐259 0 ‐279 0 ‐295 0 ‐311 0 ‐327 0 ‐341 90 ‐347 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011905 Final Ceiling Tiles install ‐ Tenant Are 02/01/12 05/02/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 0 ‐354 0 ‐359 85 ‐349 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011885 Suspended Ceiling‐ Wet area 02/01/12 16/01/12 0 ‐222 0 ‐221 0 ‐237 0 ‐255 0 ‐266 0 ‐282 0 ‐298 0 ‐314 0 ‐329 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011890 Plumbing Fixture Install & Mirror‐ W 03/01/12 11/03/12 0 ‐222 0 ‐223 0 ‐239 0 ‐259 0 ‐279 0 ‐295 0 ‐311 0 ‐327 0 ‐341 90 ‐347 90 ‐360 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011900 MEP final fixes to Tenant Area 14/01/12 26/06/12 0 ‐250 0 ‐250 0 ‐266 0 ‐283 0 ‐303 0 ‐319 0 ‐335 0 ‐349 0 ‐355 50 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 1 2 3 4 5
COMF011910 Door Installation ‐ Tenant area 16/01/12 23/01/12 0 ‐249 0 ‐249 0 ‐265 0 ‐282 0 ‐302 0 ‐318 0 ‐334 0 ‐348 0 ‐345 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011940 Door Installation @Corrid. & Plant R 16/01/12 02/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐309 0 ‐323 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011945 Final Painting works to Tenant Area 04/02/12 11/03/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 0 ‐354 0 ‐359 0 ‐350 80 ‐351 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011950 Sliding Door @ Lift Lobby 04/02/12 09/02/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 0 ‐320 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011930 Final Painting/Vinyl wall paper works 11/02/12 15/06/12 0 ‐256 0 ‐247 0 ‐263 0 ‐276 0 ‐296 0 ‐312 0 ‐328 0 ‐342 0 ‐347 0 ‐361 30 ‐370 80 ‐384 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011880 Installation of Cubicle ‐ Wet area 28/05/12 13/06/12 0 ‐217 0 ‐223 0 ‐239 0 ‐259 0 ‐279 0 ‐295 0 ‐311 0 ‐327 0 ‐341 0 ‐347 0 ‐360 0 ‐375 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011955 Snagging & Keys 27/06/12 13/07/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 0 ‐354 0 ‐359 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF021820 MEP 2nd fixes 27/11/09 03/12/11 85 ‐243 95 ‐254 95 ‐270 95 ‐287 95 ‐307 97 ‐322 98.7 ‐338 98.7 ‐354 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF023230 Plaster to column & lift lobby 20/03/10 28/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF023220 Office Fitout (1st & 2nd Fix Trades) 08/04/10 05/04/12 66 ‐257 95 ‐248 95 ‐264 95 ‐274 95 ‐289 95 ‐302 95.3 ‐317 95.3 ‐333 95 ‐353 95 ‐364 95 ‐375 95 ‐390 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF023260 Basecoat Painting works 05/05/10 15/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022420 Ceramic tiles 13/05/10 15/05/11 90 ‐203 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022620 Stone Work @ lift lobby 01/08/10 07/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF024810 Screed work @ Corridore area 14/02/11 20/02/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF024730 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 17/02/11 02/07/11 75 ‐257 81 ‐250 95 ‐266 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF024750 MEP final fixes to Tenant Area 15/03/11 09/04/12 25 ‐237 25 ‐240 25 ‐241 35 ‐259 45 ‐282 45 ‐298 45 ‐314 45 ‐330 45 ‐349 90 ‐360 90 ‐375 95 ‐390 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF022550 Ceramic tiles ‐ Wet area (Balance/Re 15/03/11 26/07/11 83 ‐221 83 ‐231 98 ‐246 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF022160 Testing & clearance prior to false cei 15/03/11 21/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022980 Suspended Ceiling‐ Wet area 22/03/11 02/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF024740 Floor Trunking & Raised Floor Install 25/03/11 09/08/11 25 ‐244 25 ‐246 85 ‐242 95 ‐261 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024760 Final Ceiling Tiles install ‐ Tenant Are 25/03/11 03/01/12 25 ‐244 30 ‐246 35 ‐245 70 ‐258 95 ‐283 95 ‐298 95 ‐315 95 ‐331 95 ‐350 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024780 Final Painting works to Tenant Area 28/03/11 18/02/12 30 ‐240 76 ‐236 75 ‐235 75 ‐253 75 ‐279 75 ‐295 75 ‐311 75 ‐327 75 ‐346 95 ‐353 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024770 Door Installation ‐ Tenant area 28/03/11 15/01/12 25 ‐238 25 ‐241 25 ‐241 25 ‐261 25 ‐287 25 ‐303 25 ‐319 25 ‐335 25 ‐354 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF024830 Stone Floor @ Corridore area 01/04/11 07/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF024800 Sliding Door @ Lift Lobby 20/04/11 24/07/11 0 ‐231 50 ‐225 50 ‐241 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022990 Plumbing Fixture Install & Mirror‐ W 27/04/11 14/01/12 0 ‐221 90 ‐225 90 ‐241 95 ‐260 95 ‐280 95 ‐296 95 ‐312 95 ‐328 95 ‐341 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF023000 Threshold & Door Install‐ Wet area 30/04/11 13/02/12 0 ‐221 16 ‐225 15 ‐241 15 ‐260 15 ‐280 15 ‐296 15 ‐312 15 ‐328 30 ‐341 90 ‐357 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024820 Ceiling Installation @ Corridore area 02/05/11 07/01/12 0 ‐258 20 ‐255 50 ‐270 50 ‐280 60 ‐292 85 ‐308 85 ‐322 85 ‐338 85 ‐353 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024790 Ceiling works to lift lobby & bulkhea 02/05/11 23/07/11 0 ‐243 28 ‐248 30 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024850 MEP final fixes to lift lobby/Corrid./W 09/05/11 09/04/12 0 ‐237 21 ‐240 25 ‐249 30 ‐269 40 ‐287 40 ‐298 40 ‐314 59 ‐330 59 ‐349 90 ‐360 90 ‐375 97 ‐390 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF024840 Final Painting/Vinyl wall paper works 01/09/11 10/03/12 0 ‐235 0 ‐236 0 ‐249 0 ‐269 5 ‐287 35 ‐297 35 ‐313 35 ‐329 35 ‐344 70 ‐358 90 ‐370 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024860 Door Installation @Corrid. & Plant R 28/12/11 28/01/12 0 ‐239 0 ‐241 0 ‐253 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐354 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022970 Installation of Cubicle ‐ Wet area 11/02/12 13/02/12 0 ‐221 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 0 ‐343 0 ‐357 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
1 of 7
- 2. West Building ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
COMF029165 Snagging & Keys 09/04/12 25/04/12 0 ‐240 0 ‐236 0 ‐244 0 ‐264 0 ‐283 0 ‐296 0 ‐312 0 ‐328 0 ‐345 0 ‐357 0 ‐369 0 ‐384 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF031940 MEP 2nd fixes 12/12/09 04/12/11 64 ‐253 95 ‐255 95 ‐271 95 ‐288 95 ‐308 95 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF033250 Plaster to column & lift lobby 20/03/10 20/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF033340 Office Fitout (1st & 2nd Fix Trades) 27/04/10 06/04/12 62 ‐257 90 ‐250 90 ‐265 90 ‐279 90 ‐293 90 ‐306 90 ‐321 90 ‐337 90 ‐357 95 ‐364 95 ‐373 95 ‐389 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF033270 Basecoat Painting works 05/05/10 27/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF032540 Ceramic tiles 01/06/10 17/05/11 90 ‐203 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF032740 Stone Work @ lift lobby 09/08/10 12/10/11 93 ‐227 93 ‐243 96 ‐259 96 ‐256 98 ‐270 98 ‐286 98 ‐302 98 ‐318 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034670 Screed work @ Corridore area 21/02/11 27/02/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034590 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 24/02/11 07/07/11 75 ‐257 81 ‐250 90 ‐266 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 1 2 3 4 5
COMF032150 Testing & clearance prior to false cei 15/03/11 12/05/11 83 ‐244 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF032745 Ceramic tiles ‐ Wet area (Balance/Re 15/03/11 17/05/11 75 ‐227 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 4 5
COMF032940 Suspended Ceiling‐ Wet area 26/03/11 14/08/11 27 ‐225 47 ‐223 50 ‐239 70 ‐258 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034640 Final Painting works to Tenant Area 01/05/11 18/02/12 0 ‐257 76 ‐247 76 ‐239 76 ‐255 76 ‐282 76 ‐298 76.9 ‐314 76.9 ‐330 76 ‐350 80 ‐353 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034660 Sliding Door @ Lift Lobby 02/05/11 02/01/12 0 ‐233 20 ‐226 20 ‐242 20 ‐252 20 ‐272 45 ‐288 50 ‐304 50 ‐320 50 ‐334 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034680 Ceiling Installation @ Corridore area 10/05/11 08/01/12 0 ‐258 20 ‐249 25 ‐264 25 ‐274 35 ‐286 70 ‐302 70 ‐313 70 ‐329 72 ‐349 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034600 Floor Trunking & Raised Floor Install 26/05/11 14/08/11 0 ‐257 0 ‐257 80 ‐247 95 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034690 Stone Floor @ Corridore area 28/06/11 14/07/11 0 ‐258 0 ‐249 0 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034620 Final Ceiling Tiles install ‐ Tenant Are 23/07/11 02/01/12 0 ‐257 0 ‐257 0 ‐249 60 ‐259 85 ‐283 85 ‐299 85 ‐316 85 ‐332 85 ‐352 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034650 Ceiling works to lift lobby & bulkhea 23/07/11 07/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐272 70 ‐288 70 ‐304 70 ‐320 98 ‐334 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034610 MEP final fixes to Tenant Area 06/08/11 13/04/12 0 ‐250 0 ‐250 0 ‐242 0 ‐264 13 ‐288 30 ‐300 30 ‐316 40 ‐330 40 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 1 2 3 4 5
COMF034710 MEP final fixes to lift lobby/Corrid./W 21/08/11 13/04/12 0 ‐250 0 ‐250 0 ‐253 0 ‐269 7 ‐288 10 ‐300 11 ‐316 53 ‐330 53 ‐350 90 ‐360 90 ‐375 96 ‐390 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 1 2 3 4 5
COMF032950 Plumbing Fixture Install & Mirror‐ W 08/11/11 09/01/12 0 ‐227 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 70 ‐331 70 ‐343 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF032960 Threshold & Door Install‐ Wet area 03/12/11 18/02/12 0 ‐227 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 30 ‐343 90 ‐356 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034720 Door Installation @Corrid. & Plant R 28/12/11 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034630 Door Installation ‐ Tenant area 02/01/12 16/01/12 0 ‐251 0 ‐249 0 ‐241 0 ‐263 0 ‐289 0 ‐305 0 ‐321 0 ‐337 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034700 Final Painting/Vinyl wall paper works 21/01/12 04/04/12 0 ‐246 0 ‐243 0 ‐252 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 70 ‐358 80 ‐370 80 ‐384 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF032930 Installation of Cubicle ‐ Wet area 30/03/12 17/04/12 0 ‐227 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 0 ‐343 0 ‐356 0 ‐369 0 ‐385 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF039155 Snagging & Keys 17/04/12 03/05/12 0 ‐257 0 ‐246 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 0 ‐349 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF041930 MEP 2nd fixes 27/12/09 04/12/11 81 ‐253 95 ‐255 95 ‐271 95 ‐288 95 ‐308 95 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043250 Plaster to column & lift lobby 20/03/10 11/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF043330 Office Fitout (1st & 2nd Fix Trades) 04/05/10 05/04/12 65 ‐256 95 ‐247 95 ‐263 95 ‐279 95 ‐294 95 ‐307 95.3 ‐320 95.3 ‐336 95 ‐356 95 ‐368 95 ‐373 95 ‐389 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043270 Basecoat Painting works 06/05/10 23/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF042530 Ceramic tiles 05/06/10 19/05/11 90 ‐203 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF042730 Stone Work @ lift lobby 14/08/10 14/10/11 93 ‐222 93 ‐238 96 ‐254 98 ‐265 98 ‐275 98 ‐290 98 ‐306 98 ‐322 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF044540 Screed work @ Corridore area 28/02/11 16/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF043950 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 03/03/11 14/07/11 75 ‐257 81 ‐250 85 ‐266 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 1 2 3 4 5
COMF042140 Testing & clearance prior to false cei 16/03/11 01/05/11 83 ‐241 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF043955 Ceramic tiles ‐ Wet area (Balance/Re 16/03/11 02/08/11 75 ‐225 75 ‐226 75 ‐242 98 ‐261 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF042900 Suspended Ceiling‐ Wet area 30/03/11 14/08/11 20 ‐225 50 ‐223 50 ‐239 70 ‐258 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF044010 Sliding Door @ Lift Lobby 03/05/11 04/01/12 0 ‐234 20 ‐231 20 ‐247 20 ‐254 20 ‐274 20 ‐290 20 ‐305 20 ‐321 20 ‐334 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF044550 Ceiling Installation @ Corridore area 10/05/11 08/01/12 0 ‐258 20 ‐245 25 ‐260 25 ‐274 35 ‐286 35 ‐302 60 ‐311 60 ‐326 70 ‐345 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043970 Final Ceiling Tiles install ‐ Tenant Are 10/05/11 03/01/12 0 ‐257 10 ‐257 15 ‐249 60 ‐259 85 ‐283 85 ‐299 90 ‐316 90 ‐332 90 ‐352 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043960 Floor Trunking & Raised Floor Install 05/06/11 14/08/11 0 ‐257 0 ‐252 60 ‐248 95 ‐262 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF044560 Stone Floor @ Corridore area 28/06/11 14/07/11 0 ‐258 0 ‐249 0 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF044000 Ceiling works to lift lobby & bulkhea 24/07/11 08/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐274 70 ‐290 70 ‐305 70 ‐321 95 ‐334 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF044530 MEP final fixes to Tenant Area 06/08/11 19/04/12 0 ‐250 0 ‐250 0 ‐243 0 ‐264 13 ‐288 27 ‐300 27 ‐316 37 ‐330 37 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 1 2 3 4 5
COMF044570 MEP final fixes to lift lobby/Corrid./W 22/08/11 19/04/12 0 ‐250 0 ‐250 0 ‐254 0 ‐269 4 ‐288 8 ‐300 8.54 ‐316 43 ‐330 43 ‐350 90 ‐361 90 ‐375 98 ‐390 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 1 2 3 4 5
COMF042910 Plumbing Fixture Install & Mirror‐ W 08/11/11 08/01/12 0 ‐227 0 ‐233 0 ‐249 0 ‐269 0 ‐289 0 ‐305 0 ‐321 70 ‐330 70 ‐342 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF042920 Threshold & Door Install‐ Wet area 04/12/11 18/02/12 0 ‐227 0 ‐233 0 ‐249 0 ‐269 0 ‐289 0 ‐305 0 ‐321 0 ‐330 30 ‐342 90 ‐356 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF043990 Final Painting works to Tenant Area 02/01/12 20/02/12 0 ‐257 0 ‐257 0 ‐249 0 ‐262 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 70 ‐353 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043980 Door Installation ‐ Tenant area 02/01/12 16/01/12 0 ‐251 0 ‐248 0 ‐245 0 ‐262 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF044580 Door Installation @Corrid. & Plant R 02/01/12 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF044020 Final Painting/Vinyl wall paper works 11/02/12 10/04/12 0 ‐247 0 ‐243 0 ‐253 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF042890 Installation of Cubicle ‐ Wet area 04/04/12 20/04/12 6 ‐227 6 ‐233 6 ‐249 6 ‐269 6 ‐289 6 ‐305 6.25 ‐321 6.25 ‐330 6 ‐342 6 ‐356 0 ‐369 0 ‐385 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF049145 Snagging & Keys 23/04/12 09/05/12 0 ‐257 0 ‐256 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF051920 MEP 2nd fixes 11/01/10 04/12/11 83 ‐253 95 ‐255 95 ‐271 95 ‐288 95 ‐308 95 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF053250 Plaster to column & lift lobby 10/04/10 28/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053270 Basecoat Painting works 08/05/10 19/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053320 Office Fitout (1st & 2nd Fix Trades) 17/05/10 05/04/12 58 ‐257 95 ‐246 95 ‐262 95 ‐280 95 ‐295 95 ‐308 95.3 ‐314 95.3 ‐330 95 ‐349 95 ‐364 95 ‐370 95 ‐386 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF052520 Ceramic tiles ‐ Wet area 20/06/10 19/05/11 90 ‐224 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF052720 Stone Work @ lift lobby 04/10/10 16/10/11 93 ‐222 93 ‐238 96 ‐253 98 ‐265 98 ‐275 98 ‐290 98 ‐306 98 ‐322 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF054490 Screed work @ Corridore area 07/03/11 20/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053860 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 10/03/11 02/08/11 75 ‐257 81 ‐250 85 ‐266 98 ‐280 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 1 2 3 4 5
COMF052130 Testing & clearance prior to false cei 20/03/11 02/05/11 50 ‐241 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF052860 Suspended Ceiling‐ Wet area 05/04/11 14/08/11 16 ‐225 47 ‐223 50 ‐239 70 ‐258 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF053900 Final Painting works to Tenant Area 09/05/11 20/02/12 0 ‐257 60 ‐257 60 ‐249 60 ‐262 60 ‐289 60 ‐305 60.9 ‐320 60.9 ‐336 60 ‐356 70 ‐353 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF054500 Ceiling Installation @ Corridore area 10/05/11 08/01/12 0 ‐257 27 ‐239 27 ‐255 27 ‐274 30 ‐286 30 ‐302 60 ‐311 60 ‐326 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF053880 Final Ceiling Tiles install ‐ Tenant Are 11/05/11 03/01/12 0 ‐257 10 ‐257 10 ‐253 20 ‐260 85 ‐283 85 ‐299 85 ‐315 88 ‐332 90 ‐352 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF053870 Floor Trunking & Raised Floor Install 16/06/11 15/08/11 0 ‐257 0 ‐248 35 ‐253 70 ‐260 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF054510 Stone Floor @ Corridore area 30/06/11 13/07/11 0 ‐258 0 ‐249 0 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053910 Ceiling works to lift lobby & bulkhea 24/07/11 08/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐275 70 ‐291 70 ‐306 70 ‐322 95 ‐334 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF054480 MEP final fixes to Tenant Area 08/08/11 25/04/12 0 ‐250 0 ‐250 0 ‐248 0 ‐264 10 ‐288 24 ‐300 24 ‐316 35 ‐330 35 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 1 2 3 4 5
COMF054520 MEP final fixes to lift lobby/Corrid./W 11/09/11 25/04/12 0 ‐250 0 ‐250 0 ‐255 0 ‐269 0 ‐288 6 ‐300 6.1 ‐316 38 ‐330 37 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 1 2 3 4 5
COMF052870 Plumbing Fixture Install & Mirror‐ W 08/11/11 08/01/12 0 ‐225 0 ‐232 0 ‐248 0 ‐268 0 ‐288 0 ‐304 0 ‐320 70 ‐329 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF052880 Threshold & Door Install‐ Wet area 04/12/11 19/02/12 0 ‐225 0 ‐232 0 ‐248 0 ‐268 0 ‐288 0 ‐304 0 ‐320 0 ‐329 30 ‐341 90 ‐354 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053920 Sliding Door @ Lift Lobby 04/01/12 07/01/12 0 ‐235 0 ‐236 0 ‐252 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053890 Door Installation ‐ Tenant area 07/01/12 16/01/12 0 ‐252 0 ‐241 0 ‐245 0 ‐254 0 ‐283 0 ‐299 0 ‐314 0 ‐330 0 ‐349 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053940 Door Installation @Corrid. & Plant R 07/01/12 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053930 Final Painting/Vinyl wall paper works 11/02/12 16/04/12 0 ‐247 0 ‐243 0 ‐254 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
2 of 7
- 3. West Building ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
COMF052850 Installation of Cubicle ‐ Wet area 09/04/12 25/04/12 0 ‐225 0 ‐232 0 ‐248 0 ‐268 0 ‐288 0 ‐304 0 ‐320 0 ‐329 0 ‐342 0 ‐354 0 ‐367 0 ‐383 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF059135 Snagging & Keys 30/04/12 15/05/12 0 ‐257 0 ‐256 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF061910 MEP 2nd fixes 14/01/10 05/12/11 83 ‐253 97 ‐255 99 ‐271 99 ‐288 99 ‐308 99 ‐324 99 ‐339 99 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF063270 Plaster to column & lift lobby 15/04/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063290 Basecoat Painting works 09/05/10 29/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063310 Office Fitout (1st & 2nd Fix Trades) 23/05/10 06/04/12 55 ‐257 95 ‐245 95 ‐261 95 ‐278 95 ‐296 95 ‐309 95 ‐315 95 ‐329 95 ‐347 95 ‐361 95 ‐367 95 ‐383 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF062510 Ceramic tiles ‐ Wet area 17/07/10 19/05/11 95 ‐222 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF062710 Stone Work @ lift lobby 28/10/10 18/10/11 87 ‐219 93 ‐235 99 ‐250 99 ‐265 99 ‐275 99 ‐290 99 ‐304 99 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF064440 Screed work @ Corridore area 14/03/11 23/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063770 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 17/03/11 26/09/11 75 ‐257 81 ‐250 81 ‐266 95 ‐280 98 ‐296 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 1 2 3 4 5
COMF062120 Testing & clearance prior to false cei 21/03/11 04/05/11 30 ‐239 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF062820 Suspended Ceiling‐ Wet area 10/04/11 09/01/12 16 ‐225 47 ‐223 50 ‐239 70 ‐258 85 ‐269 85 ‐285 88 ‐300 88 ‐314 88 ‐329 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF063810 Final Painting works to Tenant Area 12/05/11 20/02/12 0 ‐257 53 ‐257 53 ‐259 53 ‐264 55 ‐289 55 ‐305 55 ‐320 55 ‐336 55 ‐356 70 ‐353 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF063780 Floor Trunking & Raised Floor Install 20/06/11 15/12/11 0 ‐257 0 ‐250 0 ‐266 40 ‐270 80 ‐269 80 ‐296 85 ‐309 85 ‐324 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF064460 Stone Floor @ Corridore area 02/07/11 10/12/11 0 ‐258 0 ‐249 0 ‐264 50 ‐269 50 ‐286 50 ‐302 95 ‐314 98 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF063820 Ceiling works to lift lobby & bulkhea 25/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐257 70 ‐272 70 ‐288 70 ‐304 70 ‐320 95 ‐330 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF064430 MEP final fixes to Tenant Area 07/08/11 01/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐264 10 ‐288 25 ‐300 25 ‐316 35 ‐330 35 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 1 2 3 4 5
COMF063790 Final Ceiling Tiles install ‐ Tenant Are 15/08/11 04/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 55 ‐280 55 ‐299 60 ‐315 65 ‐331 65 ‐351 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF064450 Ceiling Installation @ Corridore area 27/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 26 ‐286 30 ‐302 60 ‐311 60 ‐326 70 ‐337 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF064470 MEP final fixes to lift lobby/Corrid./W 11/09/11 01/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐269 0 ‐288 6 ‐300 6.1 ‐316 38 ‐330 37 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 1 2 3 4 5
COMF062830 Plumbing Fixture Install & Mirror‐ W 12/11/11 09/01/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 70 ‐328 70 ‐340 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF062840 Threshold & Door Install‐ Wet area 04/12/11 19/02/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 30 ‐340 90 ‐354 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063800 Door Installation ‐ Tenant area 28/12/11 16/01/12 0 ‐252 0 ‐239 0 ‐255 0 ‐260 0 ‐269 0 ‐294 0 ‐308 0 ‐324 0 ‐345 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063850 Door Installation @Corrid. & Plant R 02/01/12 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063830 Sliding Door @ Lift Lobby 02/01/12 05/01/12 0 ‐236 0 ‐237 0 ‐253 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063840 Final Painting/Vinyl wall paper works 04/02/12 20/04/12 0 ‐248 0 ‐243 0 ‐255 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF062810 Installation of Cubicle ‐ Wet area 12/04/12 30/04/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 0 ‐342 0 ‐354 0 ‐367 0 ‐383 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF069125 Snagging & Keys 04/05/12 21/05/12 0 ‐257 0 ‐256 0 ‐258 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF071900 MEP 2nd fixes 11/01/10 05/12/11 80 ‐253 90 ‐255 90 ‐271 90 ‐288 90 ‐308 91 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073250 Plaster to column & lift lobby 15/04/10 01/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073270 Basecoat Painting works 18/05/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073300 Office Fitout (1st & 2nd Fix Trades) 25/05/10 05/04/12 54 ‐251 95 ‐240 95 ‐256 95 ‐273 95 ‐290 95 ‐306 95.3 ‐313 95.3 ‐327 95 ‐342 95 ‐354 95 ‐360 95 ‐376 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF072500 Ceramic tiles ‐ Wet area 04/10/10 19/05/11 90 ‐222 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF072700 Stone Work @ lift lobby 01/12/10 23/10/11 81 ‐216 87 ‐232 96 ‐248 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073680 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 10/03/11 27/09/11 59 ‐257 75 ‐250 75 ‐266 83 ‐280 98 ‐296 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 1 2 3 4 5
COMF074390 Screed work @ Corridore area 21/03/11 27/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF072780 Suspended Ceiling‐ Wet area 28/04/11 09/01/12 0 ‐225 47 ‐223 50 ‐239 60 ‐258 80 ‐269 80 ‐285 80 ‐300 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF072110 Testing & clearance prior to false cei 30/04/11 04/05/11 0 ‐237 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073690 Floor Trunking & Raised Floor Install 22/06/11 09/11/11 0 ‐257 0 ‐250 0 ‐266 55 ‐263 75 ‐270 80 ‐296 85 ‐310 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF074410 Stone Floor @ Corridore area 03/07/11 10/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 97 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073730 Ceiling works to lift lobby & bulkhea 25/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐270 70 ‐286 70 ‐302 70 ‐318 90 ‐327 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073700 Final Ceiling Tiles install ‐ Tenant Are 04/08/11 04/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 30 ‐280 60 ‐299 80 ‐315 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF074380 MEP final fixes to Tenant Area 08/08/11 07/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐264 6 ‐288 24 ‐300 24 ‐316 31 ‐330 31 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 1 2 3 4 5
COMF074400 Ceiling Installation @ Corridore area 16/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐279 30 ‐294 60 ‐307 60 ‐322 60 ‐334 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF074420 MEP final fixes to lift lobby/Corrid./W 11/09/11 07/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐269 0 ‐288 6 ‐300 6.1 ‐316 35 ‐330 35 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 1 2 3 4 5
COMF072790 Plumbing Fixture Install & Mirror‐ W 12/11/11 09/01/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 70 ‐328 70 ‐342 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073740 Sliding Door @ Lift Lobby 29/12/11 03/01/12 0 ‐237 0 ‐237 0 ‐253 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF072800 Threshold & Door Install‐ Wet area 29/12/11 19/02/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 0 ‐342 90 ‐354 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073710 Door Installation ‐ Tenant area 02/01/12 17/01/12 0 ‐252 0 ‐244 0 ‐260 0 ‐257 0 ‐270 0 ‐296 0 ‐310 0 ‐329 0 ‐347 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073720 Final Painting works to Tenant Area 14/01/12 20/02/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 50 ‐353 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073760 Door Installation @Corrid. & Plant R 14/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073750 Final Painting/Vinyl wall paper works 04/02/12 26/04/12 0 ‐249 0 ‐243 0 ‐255 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF072770 Installation of Cubicle ‐ Wet area 17/04/12 03/05/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 0 ‐342 0 ‐354 0 ‐367 0 ‐383 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF079115 Snagging & Keys 08/05/12 25/05/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF081890 MEP 2nd fixes 16/01/10 05/12/11 80 ‐253 89 ‐255 90 ‐271 90 ‐288 90 ‐308 91 ‐324 92.8 ‐339 92.8 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083270 Plaster to column & lift lobby 15/04/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083290 Office Fitout (1st & 2nd Fix Trades) 29/05/10 06/04/12 54 ‐252 80 ‐246 80 ‐262 80 ‐282 80 ‐299 80 ‐318 80 ‐326 85 ‐332 85 ‐352 90 ‐359 95 ‐361 95 ‐377 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083310 Basecoat Painting works 12/06/10 02/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF082490 Ceramic tiles ‐ Wet area 11/10/10 03/08/11 90 ‐195 90 ‐210 90 ‐226 98 ‐246 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF082690 Stone Work @ lift lobby 02/12/10 25/10/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF084340 Screed work @ Corridore area 26/03/11 30/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083610 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 15/04/11 10/12/11 9 ‐257 53 ‐250 53 ‐266 75 ‐282 75 ‐299 75 ‐318 98 ‐326 98 ‐332 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 1 2 3 4 5
COMF082740 Suspended Ceiling‐ Wet area 01/05/11 09/01/12 0 ‐225 47 ‐223 50 ‐239 50 ‐258 80 ‐269 80 ‐285 80 ‐300 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF082100 Testing & clearance prior to false cei 03/05/11 09/01/12 0 ‐234 66 ‐231 66 ‐247 66 ‐258 80 ‐267 80 ‐283 80 ‐299 80 ‐315 80 ‐323 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 4 5
COMF084360 Stone Floor @ Corridore area 12/07/11 11/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083210 Ceiling works to lift lobby & bulkhea 27/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 50 ‐258 70 ‐268 70 ‐284 70 ‐300 70 ‐316 95 ‐323 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083620 Floor Trunking & Raised Floor Install 28/07/11 14/11/11 0 ‐257 0 ‐250 0 ‐266 10 ‐279 75 ‐272 75 ‐288 80 ‐303 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF084350 Ceiling Installation @ Corridore area 16/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐274 30 ‐290 60 ‐303 60 ‐318 60 ‐330 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 3 4 5
COMF083630 Final Ceiling Tiles install ‐ Tenant Are 22/08/11 03/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐279 30 ‐280 50 ‐299 75 ‐315 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF084330 MEP final fixes to Tenant Area 06/09/11 11/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐272 0 ‐288 22 ‐300 24 ‐316 31 ‐330 31 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 1 2 3 4 5
COMF084370 MEP final fixes to lift lobby/Corrid./W 12/09/11 11/05/12 0 ‐251 0 ‐250 0 ‐259 0 ‐272 0 ‐288 6 ‐300 6.1 ‐316 35 ‐330 35 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 1 2 3 4 5
COMF082750 Plumbing Fixture Install & Mirror‐ W 14/11/11 09/01/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 70 ‐327 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083640 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐252 0 ‐244 0 ‐260 0 ‐273 0 ‐272 0 ‐288 0 ‐303 0 ‐316 0 ‐352 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083220 Sliding Door @ Lift Lobby 29/12/11 03/01/12 0 ‐238 0 ‐238 0 ‐254 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF082760 Threshold & Door Install‐ Wet area 02/01/12 19/02/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐327 0 ‐341 90 ‐353 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083670 Door Installation @Corrid. & Plant R 07/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083650 Final Painting works to Tenant Area 15/01/12 03/03/12 0 ‐257 0 ‐257 0 ‐266 0 ‐279 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 50 ‐353 90 ‐354 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083660 Final Painting/Vinyl wall paper works 04/02/12 02/05/12 0 ‐250 0 ‐243 0 ‐256 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF082730 Installation of Cubicle ‐ Wet area 20/04/12 08/05/12 0 ‐224 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐328 0 ‐342 0 ‐353 0 ‐366 0 ‐382 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
3 of 7
- 4. West Building ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
COMF089105 Snagging & Keys 15/05/12 30/05/12 0 ‐257 0 ‐257 0 ‐266 0 ‐278 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF091880 MEP 2nd fixes 21/01/10 06/12/11 80 ‐253 85 ‐255 85 ‐271 85 ‐288 85 ‐308 90 ‐324 91.9 ‐339 91.9 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093250 Plaster to column & lift lobby 15/04/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093280 Office Fitout (1st & 2nd Fix Trades) 31/05/10 06/04/12 54 ‐249 89 ‐240 90 ‐256 90 ‐273 90 ‐291 90 ‐310 90 ‐317 90 ‐327 90 ‐345 90 ‐356 95 ‐357 95 ‐373 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093270 Basecoat Painting works 19/06/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF092480 Ceramic tiles ‐ Wet area 14/10/10 26/11/11 90 ‐219 90 ‐220 92 ‐236 92 ‐253 95 ‐273 95 ‐289 98 ‐304 98 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF092680 Stone Work @ lift lobby 04/12/10 01/11/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF094290 Screed work @ Corridore area 29/03/11 04/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF092090 Testing & clearance prior to false cei 03/05/11 09/01/12 0 ‐231 50 ‐229 50 ‐245 50 ‐257 50 ‐267 80 ‐281 80 ‐296 80 ‐312 80 ‐321 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF092700 Suspended Ceiling‐ Wet area 08/05/11 09/01/12 0 ‐225 47 ‐223 50 ‐239 55 ‐258 70 ‐269 70 ‐285 70 ‐300 70 ‐314 70 ‐329 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093550 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 10/05/11 01/10/11 0 ‐257 6 ‐252 40 ‐266 60 ‐282 90 ‐299 95 ‐318 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF094310 Stone Floor @ Corridore area 11/07/11 11/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093180 Ceiling works to lift lobby & bulkhea 26/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐257 70 ‐267 70 ‐282 70 ‐298 70 ‐314 80 ‐321 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093560 Floor Trunking & Raised Floor Install 15/08/11 14/11/11 0 ‐257 0 ‐252 0 ‐266 0 ‐282 50 ‐286 75 ‐288 85 ‐317 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF094300 Ceiling Installation @ Corridore area 27/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐270 30 ‐286 60 ‐299 60 ‐314 60 ‐327 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 3 4 5
COMF093570 Final Ceiling Tiles install ‐ Tenant Are 03/09/11 03/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐282 0 ‐286 60 ‐299 85 ‐315 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF094320 MEP final fixes to lift lobby/Corrid./W 12/09/11 17/05/12 0 ‐252 0 ‐250 0 ‐259 0 ‐275 0 ‐288 6 ‐300 6.1 ‐316 24 ‐330 24 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 1 2 3 4 5
COMF094280 MEP final fixes to Tenant Area 17/09/11 17/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐275 0 ‐288 22 ‐300 24 ‐316 31 ‐330 31 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 1 2 3 4 5
COMF092710 Plumbing Fixture Install & Mirror‐ W 14/11/11 09/01/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 70 ‐327 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093580 Door Installation ‐ Tenant area 27/12/11 17/01/12 0 ‐252 0 ‐246 0 ‐260 0 ‐276 0 ‐280 0 ‐288 0 ‐317 0 ‐332 0 ‐349 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093190 Sliding Door @ Lift Lobby 29/12/11 05/01/12 0 ‐239 0 ‐239 0 ‐255 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093200 Door Installation @Corrid. & Plant R 08/01/12 02/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF092720 Threshold & Door Install‐ Wet area 14/01/12 20/02/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐327 0 ‐341 90 ‐352 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093590 Final Painting works to Tenant Area 15/01/12 04/03/12 0 ‐257 0 ‐257 0 ‐266 0 ‐282 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 50 ‐353 90 ‐354 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093600 Final Painting/Vinyl wall paper works 05/02/12 08/05/12 0 ‐250 0 ‐243 0 ‐257 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF092690 Installation of Cubicle ‐ Wet area 25/04/12 11/05/12 0 ‐223 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐328 0 ‐342 0 ‐352 0 ‐365 0 ‐381 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF099095 Snagging & Keys 18/05/12 05/06/12 0 ‐257 0 ‐257 0 ‐266 0 ‐282 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF021150 2nd Floor 14/11/09 06/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF031160 3rd Floor 25/11/09 07/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF041170 4th Floor 06/12/09 17/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF051180 5th Floor 19/12/09 27/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF061190 6th Floor 06/01/10 29/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF071200 7th Floor 17/01/10 04/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF081210 8th Floor 03/02/10 08/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF091220 9th Floor 09/02/10 10/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF101230 10th Floor 14/02/10 13/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF111410 11th Floor 24/02/10 03/05/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMFMZ1040 Mezzanine Floor 01/03/10 10/07/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF121420 12th Floor 08/03/10 10/05/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMFGF1030 Ground Floor 13/03/10 10/07/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF131600 13th Floor 21/03/10 20/05/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF141780 14th Floor 07/04/10 24/07/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF151040 15th Floor 18/04/10 05/09/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF161050 16th Floor 06/05/10 25/09/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF101870 MEP 2nd fixes 23/01/10 06/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 90 ‐324 91.9 ‐339 91.9 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103250 Plaster to column & lift lobby 15/04/10 16/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103270 Office Fitout (1st & 2nd Fix Trades) 01/06/10 13/04/12 50 ‐246 80 ‐237 80 ‐253 80 ‐273 80 ‐293 85 ‐309 85 ‐319 85 ‐329 85 ‐348 90 ‐353 90 ‐358 90 ‐374 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103290 Basecoat Painting works 26/06/10 07/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF102470 Ceramic tiles ‐ Wet area 17/10/10 26/11/11 90 ‐215 90 ‐217 90 ‐233 92 ‐250 92 ‐270 92 ‐286 92 ‐301 92 ‐315 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF102670 Stone Work @ lift lobby 05/12/10 02/11/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF104240 Screed work @ Corridore area 02/04/11 07/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF102080 Testing & clearance prior to false cei 03/05/11 09/01/12 0 ‐228 66 ‐226 66 ‐242 66 ‐256 80 ‐263 80 ‐279 80 ‐295 80 ‐311 80 ‐317 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 4 5
COMF102620 Suspended Ceiling‐ Wet area 03/05/11 10/01/12 0 ‐222 50 ‐221 50 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 3 4 5
COMF103490 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 27/05/11 27/09/11 0 ‐255 0 ‐249 40 ‐263 40 ‐279 70 ‐299 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF104260 Stone Floor @ Corridore area 11/07/11 12/12/11 0 ‐258 0 ‐249 0 ‐264 60 ‐269 60 ‐286 95 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103150 Ceiling works to lift lobby & bulkhea 26/07/11 14/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐257 70 ‐264 70 ‐280 70 ‐296 70 ‐312 80 ‐317 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF104250 Ceiling Installation @ Corridore area 28/08/11 10/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 26 ‐270 30 ‐281 60 ‐295 60 ‐310 60 ‐324 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103500 Floor Trunking & Raised Floor Install 30/08/11 03/01/12 0 ‐255 0 ‐249 0 ‐263 0 ‐279 5 ‐298 45 ‐314 60 ‐319 75 ‐326 85 ‐340 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF104270 MEP final fixes to lift lobby/Corrid./W 12/09/11 23/05/12 0 ‐253 0 ‐250 0 ‐259 0 ‐275 0 ‐293 2 ‐312 2.44 ‐318 21 ‐330 20 ‐350 75 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 1 2 3 4 5
COMF103510 Final Ceiling Tiles install ‐ Tenant Are 17/09/11 21/01/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 40 ‐314 60 ‐318 70 ‐331 70 ‐351 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 1 2 3 4 5
COMF104230 MEP final fixes to Tenant Area 01/10/11 23/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐275 0 ‐293 0 ‐312 12 ‐318 23 ‐330 23 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 1 2 3 4 5
COMF142670 Plumbing Fixture Install & Mirror‐ W 15/11/11 10/01/12 0 ‐222 0 ‐226 0 ‐242 0 ‐262 0 ‐282 0 ‐298 0 ‐314 70 ‐323 70 ‐337 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103160 Sliding Door @ Lift Lobby 28/12/11 04/01/12 0 ‐239 0 ‐240 0 ‐256 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103520 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐249 0 ‐243 0 ‐258 0 ‐274 0 ‐292 0 ‐311 0 ‐319 0 ‐326 0 ‐340 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF102680 Threshold & Door Install‐ Wet area 02/01/12 20/02/12 0 ‐222 0 ‐226 0 ‐242 0 ‐262 0 ‐282 0 ‐298 0 ‐314 0 ‐323 0 ‐337 90 ‐349 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103170 Door Installation @Corrid. & Plant R 09/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103530 Final Painting works to Tenant Area 15/01/12 04/03/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 55 ‐350 90 ‐351 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103540 Final Painting/Vinyl wall paper works 05/02/12 14/05/12 0 ‐251 0 ‐243 0 ‐258 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF102610 Installation of Cubicle ‐ Wet area 30/04/12 16/05/12 0 ‐220 0 ‐226 0 ‐242 0 ‐262 0 ‐282 0 ‐298 0 ‐314 0 ‐328 0 ‐342 0 ‐349 0 ‐362 0 ‐378 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF109085 Snagging & Keys 24/05/12 11/06/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF111860 MEP 2nd fixes 01/03/10 06/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 90 ‐324 90.3 ‐339 90.8 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF113250 Plaster to column & lift lobby 02/05/10 08/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113260 Office Fitout (1st & 2nd Fix Trades) 02/06/10 13/04/12 50 ‐243 80 ‐236 80 ‐252 80 ‐270 80 ‐290 80 ‐311 80 ‐322 80 ‐332 80 ‐352 90 ‐350 90 ‐355 90 ‐371 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF113275 Basecoat Painting works 03/07/10 08/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF112460 Ceramic tiles ‐ Wet area 21/10/10 27/11/11 90 ‐215 90 ‐216 90 ‐232 95 ‐249 98 ‐268 98 ‐284 98 ‐300 98 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF112660 Stone Work @ lift lobby 06/12/10 05/11/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF114190 Screed work @ Corridore area 05/04/11 11/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF112580 Suspended Ceiling‐ Wet area 04/05/11 10/01/12 0 ‐222 47 ‐221 20 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 90 ‐329 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 3 4 5
COMF112070 Testing & clearance prior to false cei 09/05/11 09/01/12 0 ‐226 40 ‐225 40 ‐241 40 ‐258 80 ‐262 80 ‐278 80 ‐293 80 ‐309 80 ‐312 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
4 of 7
- 5. West Building ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
COMF113430 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 29/05/11 13/09/11 0 ‐255 0 ‐249 35 ‐263 55 ‐279 98 ‐299 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF114210 Stone Floor @ Corridore area 10/07/11 12/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF113120 Ceiling works to lift lobby & bulkhea 02/08/11 16/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐258 70 ‐262 70 ‐278 70 ‐294 70 ‐310 90 ‐312 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF114200 Ceiling Installation @ Corridore area 17/08/11 10/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐268 30 ‐278 60 ‐291 60 ‐306 60 ‐321 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 4 5
COMF113440 Floor Trunking & Raised Floor Install 31/08/11 21/11/11 0 ‐255 0 ‐249 0 ‐263 0 ‐279 5 ‐298 45 ‐309 55 ‐318 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 1 2 3 4 5
COMF113450 Final Ceiling Tiles install ‐ Tenant Are 12/09/11 28/01/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 50 ‐314 85 ‐318 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF114220 MEP final fixes to lift lobby/Corrid./W 12/09/11 29/05/12 0 ‐254 0 ‐250 0 ‐260 0 ‐275 0 ‐293 2 ‐312 2.44 ‐318 21 ‐330 20 ‐350 75 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 1 2 3 4 5
COMF114180 MEP final fixes to Tenant Area 02/10/11 29/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐275 0 ‐293 0 ‐312 14 ‐318 23 ‐330 23 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 1 2 3 4 5
COMF112590 Plumbing Fixture Install & Mirror‐ W 15/11/11 11/01/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 35 ‐326 70 ‐335 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF112600 Threshold & Door Install‐ Wet area 17/12/11 20/02/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐326 30 ‐335 95 ‐348 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113460 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐249 0 ‐243 0 ‐258 0 ‐274 0 ‐292 0 ‐308 0 ‐318 0 ‐324 0 ‐344 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113130 Sliding Door @ Lift Lobby 29/12/11 05/01/12 0 ‐240 0 ‐241 0 ‐257 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113140 Door Installation @Corrid. & Plant R 10/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113470 Final Painting works to Tenant Area 16/01/12 05/03/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 45 ‐350 85 ‐351 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF113480 Final Painting/Vinyl wall paper works 05/02/12 18/05/12 0 ‐252 0 ‐243 0 ‐259 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF112570 Installation of Cubicle ‐ Wet area 03/05/12 21/05/12 0 ‐219 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐328 0 ‐342 0 ‐348 0 ‐361 0 ‐377 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF119075 Snagging & Keys 30/05/12 15/06/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF121850 MEP 2nd fixes 22/03/10 07/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 90 ‐324 90.3 ‐339 90.8 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123255 Plaster to column & lift lobby 04/05/10 30/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF123250 Office Fitout (1st & 2nd Fix Trades) 03/06/10 13/04/12 34 ‐254 80 ‐235 80 ‐251 80 ‐268 80 ‐288 80 ‐313 80 ‐324 80 ‐334 80 ‐352 90 ‐346 90 ‐355 90 ‐371 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 1 2 3 4 5
COMF123280 Basecoat Painting works 10/07/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122450 Ceramic tiles ‐ Wet area 26/10/10 27/11/11 90 ‐214 90 ‐215 90 ‐231 92 ‐248 95 ‐268 95 ‐284 95 ‐299 95 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122650 Stone Work @ lift lobby 08/12/10 07/11/11 80 ‐213 80 ‐229 94 ‐245 95 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF124140 Screed work @ Corridore area 06/04/11 12/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122060 Testing & clearance prior to false cei 04/05/11 09/01/12 0 ‐224 66 ‐221 66 ‐237 66 ‐254 80 ‐260 80 ‐276 80 ‐291 80 ‐307 80 ‐311 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122530 Suspended Ceiling‐ Wet area 04/05/11 10/01/12 0 ‐222 16 ‐221 16 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 3 4 5
COMF123370 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 13/06/11 28/09/11 0 ‐255 0 ‐251 10 ‐264 20 ‐279 98 ‐299 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF124160 Stone Floor @ Corridore area 11/07/11 13/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123090 Ceiling works to lift lobby & bulkhea 03/08/11 29/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐258 70 ‐260 70 ‐276 70 ‐292 70 ‐308 70 ‐311 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF124150 Ceiling Installation @ Corridore area 30/08/11 10/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 15 ‐267 30 ‐274 60 ‐287 60 ‐302 60 ‐318 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 4 5
COMF124170 MEP final fixes to lift lobby/Corrid./W 13/09/11 04/06/12 0 ‐254 0 ‐250 0 ‐261 0 ‐275 0 ‐295 2 ‐317 2.44 ‐325 19 ‐330 19 ‐350 70 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 1 2 3 4 5
COMF123390 Final Ceiling Tiles install ‐ Tenant Are 24/09/11 29/01/12 0 ‐255 0 ‐254 0 ‐264 0 ‐279 0 ‐299 85 ‐314 85 ‐320 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123380 Floor Trunking & Raised Floor Install 27/09/11 03/01/12 0 ‐255 0 ‐251 0 ‐264 0 ‐279 0 ‐299 10 ‐317 20 ‐326 80 ‐321 90 ‐336 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF124130 MEP final fixes to Tenant Area 16/10/11 04/06/12 0 ‐250 0 ‐250 0 ‐260 0 ‐275 0 ‐295 0 ‐317 10 ‐325 21 ‐330 21 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 1 2 3 4 5
COMF122540 Plumbing Fixture Install & Mirror‐ W 15/11/11 11/01/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 20 ‐327 60 ‐337 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123100 Sliding Door @ Lift Lobby 27/12/11 04/01/12 0 ‐241 0 ‐241 0 ‐257 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF123400 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐249 0 ‐246 0 ‐259 0 ‐274 0 ‐294 0 ‐316 0 ‐326 0 ‐321 0 ‐336 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122550 Threshold & Door Install‐ Wet area 29/12/11 20/02/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐327 0 ‐337 90 ‐347 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF123110 Door Installation @Corrid. & Plant R 10/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐309 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF123410 Final Painting works to Tenant Area 17/01/12 24/04/12 0 ‐255 0 ‐254 0 ‐264 0 ‐279 0 ‐299 0 ‐316 0 ‐326 0 ‐334 0 ‐354 40 ‐350 85 ‐351 90 ‐358 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123420 Final Painting/Vinyl wall paper works 11/02/12 24/05/12 0 ‐253 0 ‐244 0 ‐259 0 ‐269 0 ‐288 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF122520 Installation of Cubicle ‐ Wet area 08/05/12 24/05/12 0 ‐218 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐328 0 ‐342 0 ‐347 0 ‐361 0 ‐377 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF129065 Snagging & Keys 05/06/12 21/06/12 0 ‐255 0 ‐254 0 ‐264 0 ‐279 0 ‐299 0 ‐316 0 ‐326 0 ‐335 0 ‐354 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF131840 MEP 2nd fixes 23/03/10 07/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 89 ‐324 89.9 ‐339 90.2 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133270 Plaster to column & lift lobby 02/05/10 28/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133240 Office Fitout (1st & 2nd Fix Trades) 12/06/10 13/04/12 34 ‐250 72 ‐235 73 ‐251 75 ‐268 75 ‐288 80 ‐304 80 ‐323 80 ‐336 80 ‐352 80 ‐352 90 ‐355 90 ‐371 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF132440 Ceramic tiles ‐ Wet area 28/10/10 28/11/11 90 ‐214 90 ‐215 90 ‐231 92 ‐248 95 ‐268 95 ‐284 95 ‐299 95 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF132640 Stone Work @ lift lobby 14/03/11 09/11/11 34 ‐213 75 ‐229 94 ‐245 96 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF134080 Screed work @ Corridore area 07/04/11 13/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF132050 Testing & clearance prior to false cei 05/05/11 14/01/12 0 ‐221 60 ‐219 60 ‐235 60 ‐252 60 ‐262 60 ‐278 60 ‐291 70 ‐306 70 ‐308 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF132490 Suspended Ceiling‐ Wet area 02/07/11 21/01/12 0 ‐222 0 ‐221 0 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 3 4 5
COMF134100 Stone Floor @ Corridore area 13/07/11 13/12/11 0 ‐258 0 ‐249 0 ‐264 50 ‐269 55 ‐286 55 ‐302 80 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133060 Ceiling works to lift lobby & bulkhea 04/08/11 22/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 70 ‐275 70 ‐290 70 ‐304 70 ‐320 70 ‐308 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133280 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 08/08/11 16/10/11 0 ‐255 0 ‐251 0 ‐267 0 ‐284 90 ‐299 95 ‐307 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF134090 Ceiling Installation @ Corridore area 06/09/11 11/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 0 ‐267 30 ‐273 60 ‐285 60 ‐298 60 ‐315 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 4 5
COMF134110 MEP final fixes to lift lobby/Corrid./W 13/09/11 08/06/12 0 ‐255 0 ‐250 0 ‐262 0 ‐279 0 ‐295 2 ‐317 2.44 ‐325 11 ‐331 10 ‐350 70 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 1 2 3 4 5
COMF133340 Final Ceiling Tiles install ‐ Tenant Are 01/10/11 18/02/12 0 ‐255 0 ‐254 0 ‐267 0 ‐284 0 ‐299 0 ‐309 80 ‐319 80 ‐330 80 ‐350 98 ‐352 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133310 Floor Trunking & Raised Floor Install 02/10/11 14/01/12 0 ‐255 0 ‐251 0 ‐267 0 ‐284 0 ‐299 0 ‐307 20 ‐323 43 ‐332 65 ‐341 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF134120 MEP final fixes to Tenant Area 17/10/11 08/06/12 0 ‐250 0 ‐250 0 ‐262 0 ‐279 0 ‐295 0 ‐317 10 ‐325 10 ‐331 10 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 1 2 3 4 5
COMF132500 Plumbing Fixture Install & Mirror‐ W 21/11/11 11/01/12 0 ‐222 0 ‐224 0 ‐240 0 ‐260 0 ‐280 0 ‐296 0 ‐312 20 ‐326 60 ‐336 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133350 Door Installation ‐ Tenant area 27/12/11 22/01/12 0 ‐249 0 ‐246 0 ‐261 0 ‐278 0 ‐294 0 ‐302 0 ‐323 0 ‐332 0 ‐341 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133070 Sliding Door @ Lift Lobby 29/12/11 04/01/12 0 ‐242 0 ‐242 0 ‐258 0 ‐262 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF132510 Threshold & Door Install‐ Wet area 29/12/11 20/02/12 0 ‐222 0 ‐224 0 ‐240 0 ‐260 0 ‐280 0 ‐296 0 ‐312 0 ‐326 0 ‐336 90 ‐346 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133080 Door Installation @Corrid. & Plant R 11/01/12 02/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐309 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133360 Final Painting works to Tenant Area 17/01/12 27/04/12 0 ‐255 0 ‐254 0 ‐267 0 ‐284 0 ‐299 0 ‐316 0 ‐325 0 ‐334 0 ‐354 35 ‐350 85 ‐351 90 ‐358 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133330 Final Painting/Vinyl wall paper works 12/02/12 30/05/12 0 ‐254 0 ‐245 0 ‐260 0 ‐272 0 ‐288 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF132480 Installation of Cubicle ‐ Wet area 11/05/12 29/05/12 0 ‐218 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐328 0 ‐342 0 ‐347 0 ‐361 0 ‐377 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF139055 Snagging & Keys 11/06/12 27/06/12 0 ‐255 0 ‐254 0 ‐267 0 ‐284 0 ‐299 0 ‐316 0 ‐326 0 ‐335 0 ‐355 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF141830 MEP 2nd fixes 24/03/10 07/12/11 77 ‐253 79 ‐255 80 ‐271 80 ‐288 80 ‐308 83 ‐324 84.1 ‐339 84.1 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 2 3 4 5
COMF143290 Plaster to column & lift lobby 02/05/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF143230 Office Fitout (1st & 2nd Fix Trades) 14/06/10 13/04/12 47 ‐236 80 ‐234 80 ‐250 80 ‐267 80 ‐287 80 ‐303 80 ‐318 80 ‐338 80 ‐352 80 ‐348 90 ‐355 90 ‐371 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 1 2 3 4 5
COMF142430 Ceramic tiles ‐ Wet area 02/11/10 28/11/11 90 ‐212 90 ‐214 90 ‐230 92 ‐246 95 ‐266 95 ‐282 95 ‐298 95 ‐313 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF142630 Stone Work @ lift lobby 20/03/11 12/11/11 34 ‐213 83 ‐229 90 ‐245 95 ‐265 95 ‐275 95 ‐290 95 ‐304 95 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 2 3 4 5
COMF144050 Screed work @ Corridore area 09/04/11 14/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF142040 Testing & clearance prior to false cei 03/05/11 15/01/12 0 ‐219 33 ‐218 40 ‐234 40 ‐251 40 ‐266 40 ‐281 40 ‐295 70 ‐308 70 ‐307 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF144070 Stone Floor @ Corridore area 11/07/11 11/01/12 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 95 ‐314 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 2 3 4 5
COMF142450 Suspended Ceiling‐ Wet area 27/07/11 22/01/12 0 ‐222 0 ‐221 0 ‐237 41 ‐255 60 ‐266 70 ‐282 70 ‐298 70 ‐314 70 ‐329 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 3 4 5
COMF143030 Ceiling works to lift lobby & bulkhea 09/08/11 22/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 70 ‐267 70 ‐282 70 ‐296 70 ‐311 70 ‐307 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF143240 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 21/08/11 16/11/11 0 ‐255 0 ‐252 0 ‐268 0 ‐285 70 ‐299 95 ‐307 98 ‐318 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 1 2 3 4 5