SlideShare a Scribd company logo
1 of 7
Download to read offline
West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
$BCP$4 FinalColumn #
40998 M340 M350 M360 M370 M380 M390 M400 M410 M420 M430 M440 M450
29/04/11
30/04/11
27/05/11
28/05/11
24/06/11
25/06/11
29/07/11
30/07/11
02/09/11
03/09/11
30/09/11
01/10/11
28/10/11
29/10/11
25/11/11
26/11/11
30/12/11
31/12/11
03/02/12
04/02/12
02/03/12
03/03/12
30/03/12
31/03/12
15/02/13
ACT Title OD Start Finish (*)Dur(*)Tota(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)TotWBS 1 Level 1 Level 2 Level 3 Level 4 Level 5 Level 6 Most CriMost CritMost CritMost Most Cr
COSPMZ0620 Structural elements up to Mezz. floo 10/06/09 30/07/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP010620 Structural elements up to 1st floor (I 17/06/09 27/08/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP020620 Structural elements up to 2nd floor ( 27/07/09 24/09/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP030620 Structural elements up to 3rd floor ( 13/08/09 06/10/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP040620 Structural elements up to 4th floor ( 25/08/09 15/10/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP050620 Structural elements up to 5th floor ( 16/09/09 27/10/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP060620 Structural elements up to 6th floor ( 28/09/09 08/11/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP070620 Structural elements up to 7th floor ( 17/10/09 17/11/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP080620 Structural elements up to 8th floor ( 24/10/09 01/12/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP090620 Structural elements up to 9th floor ( 04/11/09 10/12/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP100620 Structural elements up to 10th floor  15/11/09 22/12/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP110620 Structural elements up to 11th floor  25/11/09 06/01/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP120620 Structural elements up to 12th floor  13/12/09 18/01/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP130620 Structural elements up to 13th floor  30/12/09 28/01/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP140620 Structural elements up to 14th floor  09/01/10 11/02/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSP150620 Structural elements up to 15th floor  21/01/10 25/02/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSPRF0620 Structural elements up to RF floor (In 07/02/10 15/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COSPUR0620 Structural elements up to UR floor & 20/02/10 14/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure
COMF011830 MEP 2nd fixes 12/11/09 12/12/11 75 ‐247 77 ‐249 78 ‐265 80 ‐283 80 ‐303 84 ‐321 87.2 ‐337 95.2 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 1 2 3 4 5
COMF011835 Plaster to column 20/03/10 07/01/12 80 ‐253 80 ‐255 80 ‐271 85 ‐288 85 ‐308 85 ‐324 85 ‐339 90 ‐354 90 ‐342 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011840 Office Fitout (1st & 2nd Fix Trades) 18/04/10 04/04/12 1 ‐242 1 ‐244 1 ‐260 5 ‐279 5 ‐299 5 ‐315 5 ‐331 15 ‐342 20 ‐350 80 ‐343 90 ‐352 90 ‐362 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011845 Basecoat Painting works 26/04/10 16/01/12 36 ‐253 36 ‐255 36 ‐271 36 ‐288 36 ‐308 36 ‐324 36 ‐339 36 ‐354 36 ‐350 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011850 Stone Work @ lift lobby 12/09/10 05/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011860 Ceramic tiles ‐ Wet area 27/10/10 14/01/12 80 ‐211 80 ‐213 80 ‐229 80 ‐246 80 ‐266 80 ‐282 80 ‐297 80 ‐313 80 ‐308 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011865 Testing & clearance prior to false cei 03/05/11 10/01/12 0 ‐213 16 ‐214 16 ‐230 16 ‐247 16 ‐267 16 ‐274 16.7 ‐287 16.7 ‐303 16 ‐297 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 5
COMF011935 MEP final fixes to lift lobby/Corrid./W 13/09/11 26/06/12 0 ‐258 0 ‐250 0 ‐266 0 ‐283 0 ‐303 2 ‐319 2.44 ‐335 3 ‐349 2 ‐355 45 ‐361 90 ‐375 90 ‐390 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 1 2 3 4 5
COMF011925 Ceiling works to lift lobby & bulkhea 18/09/11 10/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 0 ‐275 60 ‐282 80 ‐293 80 ‐309 80 ‐297 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011855 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 24/09/11 15/01/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 70 ‐324 78 ‐339 85 ‐354 85 ‐350 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011895 Ceiling Installation  @ Corridore area 26/09/11 11/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 0 ‐267 30 ‐271 30 ‐287 45 ‐288 45 ‐308 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011920 Stone Floor @ Corridore area 08/11/11 14/01/12 0 ‐258 0 ‐249 0 ‐264 0 ‐274 0 ‐286 0 ‐302 0 ‐314 90 ‐330 90 ‐315 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011870 Screed work @ Corridore area 08/11/11 15/11/11 0 ‐187 0 ‐203 0 ‐219 0 ‐239 0 ‐259 0 ‐271 0 ‐287 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011875 Floor Trunking & Raised Floor Install 23/11/11 15/01/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 5 ‐354 37 ‐350 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011915 Threshold & Door Install‐ Wet area 29/12/11 20/02/12 0 ‐222 0 ‐223 0 ‐239 0 ‐259 0 ‐279 0 ‐295 0 ‐311 0 ‐327 0 ‐341 90 ‐347 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011905 Final Ceiling Tiles install ‐ Tenant Are 02/01/12 05/02/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 0 ‐354 0 ‐359 85 ‐349 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011885 Suspended Ceiling‐ Wet area 02/01/12 16/01/12 0 ‐222 0 ‐221 0 ‐237 0 ‐255 0 ‐266 0 ‐282 0 ‐298 0 ‐314 0 ‐329 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011890 Plumbing Fixture Install & Mirror‐ W 03/01/12 11/03/12 0 ‐222 0 ‐223 0 ‐239 0 ‐259 0 ‐279 0 ‐295 0 ‐311 0 ‐327 0 ‐341 90 ‐347 90 ‐360 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5
COMF011900 MEP final fixes to Tenant Area 14/01/12 26/06/12 0 ‐250 0 ‐250 0 ‐266 0 ‐283 0 ‐303 0 ‐319 0 ‐335 0 ‐349 0 ‐355 50 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 1 2 3 4 5
COMF011910 Door Installation ‐ Tenant area 16/01/12 23/01/12 0 ‐249 0 ‐249 0 ‐265 0 ‐282 0 ‐302 0 ‐318 0 ‐334 0 ‐348 0 ‐345 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011940 Door Installation @Corrid. & Plant R 16/01/12 02/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐309 0 ‐323 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011945 Final Painting works to Tenant Area 04/02/12 11/03/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 0 ‐354 0 ‐359 0 ‐350 80 ‐351 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011950 Sliding Door @ Lift Lobby 04/02/12 09/02/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 0 ‐320 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011930 Final Painting/Vinyl wall paper works 11/02/12 15/06/12 0 ‐256 0 ‐247 0 ‐263 0 ‐276 0 ‐296 0 ‐312 0 ‐328 0 ‐342 0 ‐347 0 ‐361 30 ‐370 80 ‐384 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011880 Installation of Cubicle ‐ Wet area 28/05/12 13/06/12 0 ‐217 0 ‐223 0 ‐239 0 ‐259 0 ‐279 0 ‐295 0 ‐311 0 ‐327 0 ‐341 0 ‐347 0 ‐360 0 ‐375 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF011955 Snagging & Keys 27/06/12 13/07/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 0 ‐354 0 ‐359 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor
COMF021820 MEP 2nd fixes 27/11/09 03/12/11 85 ‐243 95 ‐254 95 ‐270 95 ‐287 95 ‐307 97 ‐322 98.7 ‐338 98.7 ‐354 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF023230 Plaster to column & lift lobby 20/03/10 28/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF023220 Office Fitout (1st & 2nd Fix Trades) 08/04/10 05/04/12 66 ‐257 95 ‐248 95 ‐264 95 ‐274 95 ‐289 95 ‐302 95.3 ‐317 95.3 ‐333 95 ‐353 95 ‐364 95 ‐375 95 ‐390 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF023260 Basecoat Painting works 05/05/10 15/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022420 Ceramic tiles 13/05/10 15/05/11 90 ‐203 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022620 Stone Work @ lift lobby 01/08/10 07/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF024810 Screed work @ Corridore area 14/02/11 20/02/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF024730 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 17/02/11 02/07/11 75 ‐257 81 ‐250 95 ‐266 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF024750 MEP final fixes to Tenant Area 15/03/11 09/04/12 25 ‐237 25 ‐240 25 ‐241 35 ‐259 45 ‐282 45 ‐298 45 ‐314 45 ‐330 45 ‐349 90 ‐360 90 ‐375 95 ‐390 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF022550 Ceramic tiles ‐ Wet area (Balance/Re 15/03/11 26/07/11 83 ‐221 83 ‐231 98 ‐246 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF022160 Testing & clearance prior to false cei 15/03/11 21/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022980 Suspended Ceiling‐ Wet area 22/03/11 02/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF024740 Floor Trunking & Raised Floor Install 25/03/11 09/08/11 25 ‐244 25 ‐246 85 ‐242 95 ‐261 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024760 Final Ceiling Tiles install ‐ Tenant Are 25/03/11 03/01/12 25 ‐244 30 ‐246 35 ‐245 70 ‐258 95 ‐283 95 ‐298 95 ‐315 95 ‐331 95 ‐350 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024780 Final Painting works to Tenant Area 28/03/11 18/02/12 30 ‐240 76 ‐236 75 ‐235 75 ‐253 75 ‐279 75 ‐295 75 ‐311 75 ‐327 75 ‐346 95 ‐353 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024770 Door Installation ‐ Tenant area 28/03/11 15/01/12 25 ‐238 25 ‐241 25 ‐241 25 ‐261 25 ‐287 25 ‐303 25 ‐319 25 ‐335 25 ‐354 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF024830 Stone Floor @ Corridore area 01/04/11 07/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF024800 Sliding Door @ Lift Lobby 20/04/11 24/07/11 0 ‐231 50 ‐225 50 ‐241 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022990 Plumbing Fixture Install & Mirror‐ W 27/04/11 14/01/12 0 ‐221 90 ‐225 90 ‐241 95 ‐260 95 ‐280 95 ‐296 95 ‐312 95 ‐328 95 ‐341 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF023000 Threshold & Door Install‐ Wet area 30/04/11 13/02/12 0 ‐221 16 ‐225 15 ‐241 15 ‐260 15 ‐280 15 ‐296 15 ‐312 15 ‐328 30 ‐341 90 ‐357 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024820 Ceiling Installation  @ Corridore area 02/05/11 07/01/12 0 ‐258 20 ‐255 50 ‐270 50 ‐280 60 ‐292 85 ‐308 85 ‐322 85 ‐338 85 ‐353 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024790 Ceiling works to lift lobby & bulkhea 02/05/11 23/07/11 0 ‐243 28 ‐248 30 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024850 MEP final fixes to lift lobby/Corrid./W 09/05/11 09/04/12 0 ‐237 21 ‐240 25 ‐249 30 ‐269 40 ‐287 40 ‐298 40 ‐314 59 ‐330 59 ‐349 90 ‐360 90 ‐375 97 ‐390 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5
COMF024840 Final Painting/Vinyl wall paper works 01/09/11 10/03/12 0 ‐235 0 ‐236 0 ‐249 0 ‐269 5 ‐287 35 ‐297 35 ‐313 35 ‐329 35 ‐344 70 ‐358 90 ‐370 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5
COMF024860 Door Installation @Corrid. & Plant R 28/12/11 28/01/12 0 ‐239 0 ‐241 0 ‐253 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐354 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF022970 Installation of Cubicle ‐ Wet area 11/02/12 13/02/12 0 ‐221 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 0 ‐343 0 ‐357 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
1 of 7
West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
COMF029165 Snagging & Keys 09/04/12 25/04/12 0 ‐240 0 ‐236 0 ‐244 0 ‐264 0 ‐283 0 ‐296 0 ‐312 0 ‐328 0 ‐345 0 ‐357 0 ‐369 0 ‐384 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor
COMF031940 MEP 2nd fixes 12/12/09 04/12/11 64 ‐253 95 ‐255 95 ‐271 95 ‐288 95 ‐308 95 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF033250 Plaster to column & lift lobby 20/03/10 20/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF033340 Office Fitout (1st & 2nd Fix Trades) 27/04/10 06/04/12 62 ‐257 90 ‐250 90 ‐265 90 ‐279 90 ‐293 90 ‐306 90 ‐321 90 ‐337 90 ‐357 95 ‐364 95 ‐373 95 ‐389 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF033270 Basecoat Painting works 05/05/10 27/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF032540 Ceramic tiles 01/06/10 17/05/11 90 ‐203 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF032740 Stone Work @ lift lobby 09/08/10 12/10/11 93 ‐227 93 ‐243 96 ‐259 96 ‐256 98 ‐270 98 ‐286 98 ‐302 98 ‐318 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034670 Screed work @ Corridore area 21/02/11 27/02/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034590 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 24/02/11 07/07/11 75 ‐257 81 ‐250 90 ‐266 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 1 2 3 4 5
COMF032150 Testing & clearance prior to false cei 15/03/11 12/05/11 83 ‐244 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF032745 Ceramic tiles ‐ Wet area (Balance/Re 15/03/11 17/05/11 75 ‐227 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 4 5
COMF032940 Suspended Ceiling‐ Wet area 26/03/11 14/08/11 27 ‐225 47 ‐223 50 ‐239 70 ‐258 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034640 Final Painting works to Tenant Area 01/05/11 18/02/12 0 ‐257 76 ‐247 76 ‐239 76 ‐255 76 ‐282 76 ‐298 76.9 ‐314 76.9 ‐330 76 ‐350 80 ‐353 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034660 Sliding Door @ Lift Lobby 02/05/11 02/01/12 0 ‐233 20 ‐226 20 ‐242 20 ‐252 20 ‐272 45 ‐288 50 ‐304 50 ‐320 50 ‐334 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034680 Ceiling Installation  @ Corridore area 10/05/11 08/01/12 0 ‐258 20 ‐249 25 ‐264 25 ‐274 35 ‐286 70 ‐302 70 ‐313 70 ‐329 72 ‐349 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034600 Floor Trunking & Raised Floor Install 26/05/11 14/08/11 0 ‐257 0 ‐257 80 ‐247 95 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034690 Stone Floor @ Corridore area 28/06/11 14/07/11 0 ‐258 0 ‐249 0 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034620 Final Ceiling Tiles install ‐ Tenant Are 23/07/11 02/01/12 0 ‐257 0 ‐257 0 ‐249 60 ‐259 85 ‐283 85 ‐299 85 ‐316 85 ‐332 85 ‐352 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034650 Ceiling works to lift lobby & bulkhea 23/07/11 07/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐272 70 ‐288 70 ‐304 70 ‐320 98 ‐334 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF034610 MEP final fixes to Tenant Area 06/08/11 13/04/12 0 ‐250 0 ‐250 0 ‐242 0 ‐264 13 ‐288 30 ‐300 30 ‐316 40 ‐330 40 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 1 2 3 4 5
COMF034710 MEP final fixes to lift lobby/Corrid./W 21/08/11 13/04/12 0 ‐250 0 ‐250 0 ‐253 0 ‐269 7 ‐288 10 ‐300 11 ‐316 53 ‐330 53 ‐350 90 ‐360 90 ‐375 96 ‐390 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 1 2 3 4 5
COMF032950 Plumbing Fixture Install & Mirror‐ W 08/11/11 09/01/12 0 ‐227 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 70 ‐331 70 ‐343 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF032960 Threshold & Door Install‐ Wet area 03/12/11 18/02/12 0 ‐227 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 30 ‐343 90 ‐356 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034720 Door Installation @Corrid. & Plant R 28/12/11 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034630 Door Installation ‐ Tenant area 02/01/12 16/01/12 0 ‐251 0 ‐249 0 ‐241 0 ‐263 0 ‐289 0 ‐305 0 ‐321 0 ‐337 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF034700 Final Painting/Vinyl wall paper works 21/01/12 04/04/12 0 ‐246 0 ‐243 0 ‐252 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 70 ‐358 80 ‐370 80 ‐384 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5
COMF032930 Installation of Cubicle ‐ Wet area 30/03/12 17/04/12 0 ‐227 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 0 ‐343 0 ‐356 0 ‐369 0 ‐385 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF039155 Snagging & Keys 17/04/12 03/05/12 0 ‐257 0 ‐246 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 0 ‐349 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor
COMF041930 MEP 2nd fixes 27/12/09 04/12/11 81 ‐253 95 ‐255 95 ‐271 95 ‐288 95 ‐308 95 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043250 Plaster to column & lift lobby 20/03/10 11/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF043330 Office Fitout (1st & 2nd Fix Trades) 04/05/10 05/04/12 65 ‐256 95 ‐247 95 ‐263 95 ‐279 95 ‐294 95 ‐307 95.3 ‐320 95.3 ‐336 95 ‐356 95 ‐368 95 ‐373 95 ‐389 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043270 Basecoat Painting works 06/05/10 23/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF042530 Ceramic tiles 05/06/10 19/05/11 90 ‐203 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF042730 Stone Work @ lift lobby 14/08/10 14/10/11 93 ‐222 93 ‐238 96 ‐254 98 ‐265 98 ‐275 98 ‐290 98 ‐306 98 ‐322 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF044540 Screed work @ Corridore area 28/02/11 16/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF043950 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 03/03/11 14/07/11 75 ‐257 81 ‐250 85 ‐266 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 1 2 3 4 5
COMF042140 Testing & clearance prior to false cei 16/03/11 01/05/11 83 ‐241 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF043955 Ceramic tiles ‐ Wet area (Balance/Re 16/03/11 02/08/11 75 ‐225 75 ‐226 75 ‐242 98 ‐261 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF042900 Suspended Ceiling‐ Wet area 30/03/11 14/08/11 20 ‐225 50 ‐223 50 ‐239 70 ‐258 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF044010 Sliding Door @ Lift Lobby 03/05/11 04/01/12 0 ‐234 20 ‐231 20 ‐247 20 ‐254 20 ‐274 20 ‐290 20 ‐305 20 ‐321 20 ‐334 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF044550 Ceiling Installation  @ Corridore area 10/05/11 08/01/12 0 ‐258 20 ‐245 25 ‐260 25 ‐274 35 ‐286 35 ‐302 60 ‐311 60 ‐326 70 ‐345 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043970 Final Ceiling Tiles install ‐ Tenant Are 10/05/11 03/01/12 0 ‐257 10 ‐257 15 ‐249 60 ‐259 85 ‐283 85 ‐299 90 ‐316 90 ‐332 90 ‐352 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043960 Floor Trunking & Raised Floor Install 05/06/11 14/08/11 0 ‐257 0 ‐252 60 ‐248 95 ‐262 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF044560 Stone Floor @ Corridore area 28/06/11 14/07/11 0 ‐258 0 ‐249 0 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF044000 Ceiling works to lift lobby & bulkhea 24/07/11 08/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐274 70 ‐290 70 ‐305 70 ‐321 95 ‐334 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF044530 MEP final fixes to Tenant Area 06/08/11 19/04/12 0 ‐250 0 ‐250 0 ‐243 0 ‐264 13 ‐288 27 ‐300 27 ‐316 37 ‐330 37 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 1 2 3 4 5
COMF044570 MEP final fixes to lift lobby/Corrid./W 22/08/11 19/04/12 0 ‐250 0 ‐250 0 ‐254 0 ‐269 4 ‐288 8 ‐300 8.54 ‐316 43 ‐330 43 ‐350 90 ‐361 90 ‐375 98 ‐390 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 1 2 3 4 5
COMF042910 Plumbing Fixture Install & Mirror‐ W 08/11/11 08/01/12 0 ‐227 0 ‐233 0 ‐249 0 ‐269 0 ‐289 0 ‐305 0 ‐321 70 ‐330 70 ‐342 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF042920 Threshold & Door Install‐ Wet area 04/12/11 18/02/12 0 ‐227 0 ‐233 0 ‐249 0 ‐269 0 ‐289 0 ‐305 0 ‐321 0 ‐330 30 ‐342 90 ‐356 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF043990 Final Painting works to Tenant Area 02/01/12 20/02/12 0 ‐257 0 ‐257 0 ‐249 0 ‐262 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 70 ‐353 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF043980 Door Installation ‐ Tenant area 02/01/12 16/01/12 0 ‐251 0 ‐248 0 ‐245 0 ‐262 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF044580 Door Installation @Corrid. & Plant R 02/01/12 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF044020 Final Painting/Vinyl wall paper works 11/02/12 10/04/12 0 ‐247 0 ‐243 0 ‐253 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF042890 Installation of Cubicle ‐ Wet area 04/04/12 20/04/12 6 ‐227 6 ‐233 6 ‐249 6 ‐269 6 ‐289 6 ‐305 6.25 ‐321 6.25 ‐330 6 ‐342 6 ‐356 0 ‐369 0 ‐385 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5
COMF049145 Snagging & Keys 23/04/12 09/05/12 0 ‐257 0 ‐256 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor
COMF051920 MEP 2nd fixes 11/01/10 04/12/11 83 ‐253 95 ‐255 95 ‐271 95 ‐288 95 ‐308 95 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF053250 Plaster to column & lift lobby 10/04/10 28/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053270 Basecoat Painting works 08/05/10 19/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053320 Office Fitout (1st & 2nd Fix Trades) 17/05/10 05/04/12 58 ‐257 95 ‐246 95 ‐262 95 ‐280 95 ‐295 95 ‐308 95.3 ‐314 95.3 ‐330 95 ‐349 95 ‐364 95 ‐370 95 ‐386 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF052520 Ceramic tiles ‐ Wet area 20/06/10 19/05/11 90 ‐224 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF052720 Stone Work @ lift lobby 04/10/10 16/10/11 93 ‐222 93 ‐238 96 ‐253 98 ‐265 98 ‐275 98 ‐290 98 ‐306 98 ‐322 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF054490 Screed work @ Corridore area 07/03/11 20/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053860 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 10/03/11 02/08/11 75 ‐257 81 ‐250 85 ‐266 98 ‐280 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 1 2 3 4 5
COMF052130 Testing & clearance prior to false cei 20/03/11 02/05/11 50 ‐241 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF052860 Suspended Ceiling‐ Wet area 05/04/11 14/08/11 16 ‐225 47 ‐223 50 ‐239 70 ‐258 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF053900 Final Painting works to Tenant Area 09/05/11 20/02/12 0 ‐257 60 ‐257 60 ‐249 60 ‐262 60 ‐289 60 ‐305 60.9 ‐320 60.9 ‐336 60 ‐356 70 ‐353 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF054500 Ceiling Installation  @ Corridore area 10/05/11 08/01/12 0 ‐257 27 ‐239 27 ‐255 27 ‐274 30 ‐286 30 ‐302 60 ‐311 60 ‐326 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF053880 Final Ceiling Tiles install ‐ Tenant Are 11/05/11 03/01/12 0 ‐257 10 ‐257 10 ‐253 20 ‐260 85 ‐283 85 ‐299 85 ‐315 88 ‐332 90 ‐352 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF053870 Floor Trunking & Raised Floor Install 16/06/11 15/08/11 0 ‐257 0 ‐248 35 ‐253 70 ‐260 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF054510 Stone Floor @ Corridore area 30/06/11 13/07/11 0 ‐258 0 ‐249 0 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053910 Ceiling works to lift lobby & bulkhea 24/07/11 08/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐275 70 ‐291 70 ‐306 70 ‐322 95 ‐334 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF054480 MEP final fixes to Tenant Area 08/08/11 25/04/12 0 ‐250 0 ‐250 0 ‐248 0 ‐264 10 ‐288 24 ‐300 24 ‐316 35 ‐330 35 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 1 2 3 4 5
COMF054520 MEP final fixes to lift lobby/Corrid./W 11/09/11 25/04/12 0 ‐250 0 ‐250 0 ‐255 0 ‐269 0 ‐288 6 ‐300 6.1 ‐316 38 ‐330 37 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 1 2 3 4 5
COMF052870 Plumbing Fixture Install & Mirror‐ W 08/11/11 08/01/12 0 ‐225 0 ‐232 0 ‐248 0 ‐268 0 ‐288 0 ‐304 0 ‐320 70 ‐329 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
COMF052880 Threshold & Door Install‐ Wet area 04/12/11 19/02/12 0 ‐225 0 ‐232 0 ‐248 0 ‐268 0 ‐288 0 ‐304 0 ‐320 0 ‐329 30 ‐341 90 ‐354 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053920 Sliding Door @ Lift Lobby 04/01/12 07/01/12 0 ‐235 0 ‐236 0 ‐252 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053890 Door Installation ‐ Tenant area 07/01/12 16/01/12 0 ‐252 0 ‐241 0 ‐245 0 ‐254 0 ‐283 0 ‐299 0 ‐314 0 ‐330 0 ‐349 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053940 Door Installation @Corrid. & Plant R 07/01/12 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF053930 Final Painting/Vinyl wall paper works 11/02/12 16/04/12 0 ‐247 0 ‐243 0 ‐254 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5
2 of 7
West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
COMF052850 Installation of Cubicle ‐ Wet area 09/04/12 25/04/12 0 ‐225 0 ‐232 0 ‐248 0 ‐268 0 ‐288 0 ‐304 0 ‐320 0 ‐329 0 ‐342 0 ‐354 0 ‐367 0 ‐383 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF059135 Snagging & Keys 30/04/12 15/05/12 0 ‐257 0 ‐256 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor
COMF061910 MEP 2nd fixes 14/01/10 05/12/11 83 ‐253 97 ‐255 99 ‐271 99 ‐288 99 ‐308 99 ‐324 99 ‐339 99 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF063270 Plaster to column & lift lobby 15/04/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063290 Basecoat Painting works 09/05/10 29/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063310 Office Fitout (1st & 2nd Fix Trades) 23/05/10 06/04/12 55 ‐257 95 ‐245 95 ‐261 95 ‐278 95 ‐296 95 ‐309 95 ‐315 95 ‐329 95 ‐347 95 ‐361 95 ‐367 95 ‐383 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF062510 Ceramic tiles ‐ Wet area 17/07/10 19/05/11 95 ‐222 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF062710 Stone Work @ lift lobby 28/10/10 18/10/11 87 ‐219 93 ‐235 99 ‐250 99 ‐265 99 ‐275 99 ‐290 99 ‐304 99 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF064440 Screed work @ Corridore area 14/03/11 23/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063770 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 17/03/11 26/09/11 75 ‐257 81 ‐250 81 ‐266 95 ‐280 98 ‐296 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 1 2 3 4 5
COMF062120 Testing & clearance prior to false cei 21/03/11 04/05/11 30 ‐239 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF062820 Suspended Ceiling‐ Wet area 10/04/11 09/01/12 16 ‐225 47 ‐223 50 ‐239 70 ‐258 85 ‐269 85 ‐285 88 ‐300 88 ‐314 88 ‐329 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF063810 Final Painting works to Tenant Area 12/05/11 20/02/12 0 ‐257 53 ‐257 53 ‐259 53 ‐264 55 ‐289 55 ‐305 55 ‐320 55 ‐336 55 ‐356 70 ‐353 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF063780 Floor Trunking & Raised Floor Install 20/06/11 15/12/11 0 ‐257 0 ‐250 0 ‐266 40 ‐270 80 ‐269 80 ‐296 85 ‐309 85 ‐324 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF064460 Stone Floor @ Corridore area 02/07/11 10/12/11 0 ‐258 0 ‐249 0 ‐264 50 ‐269 50 ‐286 50 ‐302 95 ‐314 98 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF063820 Ceiling works to lift lobby & bulkhea 25/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐257 70 ‐272 70 ‐288 70 ‐304 70 ‐320 95 ‐330 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF064430 MEP final fixes to Tenant Area 07/08/11 01/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐264 10 ‐288 25 ‐300 25 ‐316 35 ‐330 35 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 1 2 3 4 5
COMF063790 Final Ceiling Tiles install ‐ Tenant Are 15/08/11 04/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 55 ‐280 55 ‐299 60 ‐315 65 ‐331 65 ‐351 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF064450 Ceiling Installation  @ Corridore area 27/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 26 ‐286 30 ‐302 60 ‐311 60 ‐326 70 ‐337 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF064470 MEP final fixes to lift lobby/Corrid./W 11/09/11 01/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐269 0 ‐288 6 ‐300 6.1 ‐316 38 ‐330 37 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 1 2 3 4 5
COMF062830 Plumbing Fixture Install & Mirror‐ W 12/11/11 09/01/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 70 ‐328 70 ‐340 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF062840 Threshold & Door Install‐ Wet area 04/12/11 19/02/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 30 ‐340 90 ‐354 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063800 Door Installation ‐ Tenant area 28/12/11 16/01/12 0 ‐252 0 ‐239 0 ‐255 0 ‐260 0 ‐269 0 ‐294 0 ‐308 0 ‐324 0 ‐345 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063850 Door Installation @Corrid. & Plant R 02/01/12 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063830 Sliding Door @ Lift Lobby 02/01/12 05/01/12 0 ‐236 0 ‐237 0 ‐253 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF063840 Final Painting/Vinyl wall paper works 04/02/12 20/04/12 0 ‐248 0 ‐243 0 ‐255 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5
COMF062810 Installation of Cubicle ‐ Wet area 12/04/12 30/04/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 0 ‐342 0 ‐354 0 ‐367 0 ‐383 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF069125 Snagging & Keys 04/05/12 21/05/12 0 ‐257 0 ‐256 0 ‐258 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor
COMF071900 MEP 2nd fixes 11/01/10 05/12/11 80 ‐253 90 ‐255 90 ‐271 90 ‐288 90 ‐308 91 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073250 Plaster to column & lift lobby 15/04/10 01/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073270 Basecoat Painting works 18/05/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073300 Office Fitout (1st & 2nd Fix Trades) 25/05/10 05/04/12 54 ‐251 95 ‐240 95 ‐256 95 ‐273 95 ‐290 95 ‐306 95.3 ‐313 95.3 ‐327 95 ‐342 95 ‐354 95 ‐360 95 ‐376 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF072500 Ceramic tiles ‐ Wet area 04/10/10 19/05/11 90 ‐222 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF072700 Stone Work @ lift lobby 01/12/10 23/10/11 81 ‐216 87 ‐232 96 ‐248 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073680 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 10/03/11 27/09/11 59 ‐257 75 ‐250 75 ‐266 83 ‐280 98 ‐296 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 1 2 3 4 5
COMF074390 Screed work @ Corridore area 21/03/11 27/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF072780 Suspended Ceiling‐ Wet area 28/04/11 09/01/12 0 ‐225 47 ‐223 50 ‐239 60 ‐258 80 ‐269 80 ‐285 80 ‐300 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF072110 Testing & clearance prior to false cei 30/04/11 04/05/11 0 ‐237 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073690 Floor Trunking & Raised Floor Install 22/06/11 09/11/11 0 ‐257 0 ‐250 0 ‐266 55 ‐263 75 ‐270 80 ‐296 85 ‐310 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF074410 Stone Floor @ Corridore area 03/07/11 10/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 97 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073730 Ceiling works to lift lobby & bulkhea 25/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐270 70 ‐286 70 ‐302 70 ‐318 90 ‐327 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073700 Final Ceiling Tiles install ‐ Tenant Are 04/08/11 04/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 30 ‐280 60 ‐299 80 ‐315 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF074380 MEP final fixes to Tenant Area 08/08/11 07/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐264 6 ‐288 24 ‐300 24 ‐316 31 ‐330 31 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 1 2 3 4 5
COMF074400 Ceiling Installation  @ Corridore area 16/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐279 30 ‐294 60 ‐307 60 ‐322 60 ‐334 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF074420 MEP final fixes to lift lobby/Corrid./W 11/09/11 07/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐269 0 ‐288 6 ‐300 6.1 ‐316 35 ‐330 35 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 1 2 3 4 5
COMF072790 Plumbing Fixture Install & Mirror‐ W 12/11/11 09/01/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 70 ‐328 70 ‐342 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073740 Sliding Door @ Lift Lobby 29/12/11 03/01/12 0 ‐237 0 ‐237 0 ‐253 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF072800 Threshold & Door Install‐ Wet area 29/12/11 19/02/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 0 ‐342 90 ‐354 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073710 Door Installation ‐ Tenant area 02/01/12 17/01/12 0 ‐252 0 ‐244 0 ‐260 0 ‐257 0 ‐270 0 ‐296 0 ‐310 0 ‐329 0 ‐347 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073720 Final Painting works to Tenant Area 14/01/12 20/02/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 50 ‐353 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF073760 Door Installation @Corrid. & Plant R 14/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF073750 Final Painting/Vinyl wall paper works 04/02/12 26/04/12 0 ‐249 0 ‐243 0 ‐255 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5
COMF072770 Installation of Cubicle ‐ Wet area 17/04/12 03/05/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 0 ‐342 0 ‐354 0 ‐367 0 ‐383 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF079115 Snagging & Keys 08/05/12 25/05/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor
COMF081890 MEP 2nd fixes 16/01/10 05/12/11 80 ‐253 89 ‐255 90 ‐271 90 ‐288 90 ‐308 91 ‐324 92.8 ‐339 92.8 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083270 Plaster to column & lift lobby 15/04/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083290 Office Fitout (1st & 2nd Fix Trades) 29/05/10 06/04/12 54 ‐252 80 ‐246 80 ‐262 80 ‐282 80 ‐299 80 ‐318 80 ‐326 85 ‐332 85 ‐352 90 ‐359 95 ‐361 95 ‐377 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083310 Basecoat Painting works 12/06/10 02/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF082490 Ceramic tiles ‐ Wet area 11/10/10 03/08/11 90 ‐195 90 ‐210 90 ‐226 98 ‐246 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF082690 Stone Work @ lift lobby 02/12/10 25/10/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF084340 Screed work @ Corridore area 26/03/11 30/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083610 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 15/04/11 10/12/11 9 ‐257 53 ‐250 53 ‐266 75 ‐282 75 ‐299 75 ‐318 98 ‐326 98 ‐332 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 1 2 3 4 5
COMF082740 Suspended Ceiling‐ Wet area 01/05/11 09/01/12 0 ‐225 47 ‐223 50 ‐239 50 ‐258 80 ‐269 80 ‐285 80 ‐300 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF082100 Testing & clearance prior to false cei 03/05/11 09/01/12 0 ‐234 66 ‐231 66 ‐247 66 ‐258 80 ‐267 80 ‐283 80 ‐299 80 ‐315 80 ‐323 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 4 5
COMF084360 Stone Floor @ Corridore area 12/07/11 11/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083210 Ceiling works to lift lobby & bulkhea 27/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 50 ‐258 70 ‐268 70 ‐284 70 ‐300 70 ‐316 95 ‐323 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083620 Floor Trunking & Raised Floor Install 28/07/11 14/11/11 0 ‐257 0 ‐250 0 ‐266 10 ‐279 75 ‐272 75 ‐288 80 ‐303 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF084350 Ceiling Installation  @ Corridore area 16/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐274 30 ‐290 60 ‐303 60 ‐318 60 ‐330 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 3 4 5
COMF083630 Final Ceiling Tiles install ‐ Tenant Are 22/08/11 03/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐279 30 ‐280 50 ‐299 75 ‐315 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF084330 MEP final fixes to Tenant Area 06/09/11 11/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐272 0 ‐288 22 ‐300 24 ‐316 31 ‐330 31 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 1 2 3 4 5
COMF084370 MEP final fixes to lift lobby/Corrid./W 12/09/11 11/05/12 0 ‐251 0 ‐250 0 ‐259 0 ‐272 0 ‐288 6 ‐300 6.1 ‐316 35 ‐330 35 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 1 2 3 4 5
COMF082750 Plumbing Fixture Install & Mirror‐ W 14/11/11 09/01/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 70 ‐327 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083640 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐252 0 ‐244 0 ‐260 0 ‐273 0 ‐272 0 ‐288 0 ‐303 0 ‐316 0 ‐352 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083220 Sliding Door @ Lift Lobby 29/12/11 03/01/12 0 ‐238 0 ‐238 0 ‐254 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF082760 Threshold & Door Install‐ Wet area 02/01/12 19/02/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐327 0 ‐341 90 ‐353 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083670 Door Installation @Corrid. & Plant R 07/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF083650 Final Painting works to Tenant Area 15/01/12 03/03/12 0 ‐257 0 ‐257 0 ‐266 0 ‐279 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 50 ‐353 90 ‐354 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF083660 Final Painting/Vinyl wall paper works 04/02/12 02/05/12 0 ‐250 0 ‐243 0 ‐256 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5
COMF082730 Installation of Cubicle ‐ Wet area 20/04/12 08/05/12 0 ‐224 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐328 0 ‐342 0 ‐353 0 ‐366 0 ‐382 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
3 of 7
West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
COMF089105 Snagging & Keys 15/05/12 30/05/12 0 ‐257 0 ‐257 0 ‐266 0 ‐278 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor
COMF091880 MEP 2nd fixes 21/01/10 06/12/11 80 ‐253 85 ‐255 85 ‐271 85 ‐288 85 ‐308 90 ‐324 91.9 ‐339 91.9 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093250 Plaster to column & lift lobby 15/04/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093280 Office Fitout (1st & 2nd Fix Trades) 31/05/10 06/04/12 54 ‐249 89 ‐240 90 ‐256 90 ‐273 90 ‐291 90 ‐310 90 ‐317 90 ‐327 90 ‐345 90 ‐356 95 ‐357 95 ‐373 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093270 Basecoat Painting works 19/06/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF092480 Ceramic tiles ‐ Wet area 14/10/10 26/11/11 90 ‐219 90 ‐220 92 ‐236 92 ‐253 95 ‐273 95 ‐289 98 ‐304 98 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF092680 Stone Work @ lift lobby 04/12/10 01/11/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF094290 Screed work @ Corridore area 29/03/11 04/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF092090 Testing & clearance prior to false cei 03/05/11 09/01/12 0 ‐231 50 ‐229 50 ‐245 50 ‐257 50 ‐267 80 ‐281 80 ‐296 80 ‐312 80 ‐321 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF092700 Suspended Ceiling‐ Wet area 08/05/11 09/01/12 0 ‐225 47 ‐223 50 ‐239 55 ‐258 70 ‐269 70 ‐285 70 ‐300 70 ‐314 70 ‐329 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093550 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 10/05/11 01/10/11 0 ‐257 6 ‐252 40 ‐266 60 ‐282 90 ‐299 95 ‐318 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF094310 Stone Floor @ Corridore area 11/07/11 11/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093180 Ceiling works to lift lobby & bulkhea 26/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐257 70 ‐267 70 ‐282 70 ‐298 70 ‐314 80 ‐321 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093560 Floor Trunking & Raised Floor Install 15/08/11 14/11/11 0 ‐257 0 ‐252 0 ‐266 0 ‐282 50 ‐286 75 ‐288 85 ‐317 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF094300 Ceiling Installation  @ Corridore area 27/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐270 30 ‐286 60 ‐299 60 ‐314 60 ‐327 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 3 4 5
COMF093570 Final Ceiling Tiles install ‐ Tenant Are 03/09/11 03/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐282 0 ‐286 60 ‐299 85 ‐315 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF094320 MEP final fixes to lift lobby/Corrid./W 12/09/11 17/05/12 0 ‐252 0 ‐250 0 ‐259 0 ‐275 0 ‐288 6 ‐300 6.1 ‐316 24 ‐330 24 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 1 2 3 4 5
COMF094280 MEP final fixes to Tenant Area 17/09/11 17/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐275 0 ‐288 22 ‐300 24 ‐316 31 ‐330 31 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 1 2 3 4 5
COMF092710 Plumbing Fixture Install & Mirror‐ W 14/11/11 09/01/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 70 ‐327 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093580 Door Installation ‐ Tenant area 27/12/11 17/01/12 0 ‐252 0 ‐246 0 ‐260 0 ‐276 0 ‐280 0 ‐288 0 ‐317 0 ‐332 0 ‐349 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093190 Sliding Door @ Lift Lobby 29/12/11 05/01/12 0 ‐239 0 ‐239 0 ‐255 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093200 Door Installation @Corrid. & Plant R 08/01/12 02/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF092720 Threshold & Door Install‐ Wet area 14/01/12 20/02/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐327 0 ‐341 90 ‐352 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF093590 Final Painting works to Tenant Area 15/01/12 04/03/12 0 ‐257 0 ‐257 0 ‐266 0 ‐282 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 50 ‐353 90 ‐354 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF093600 Final Painting/Vinyl wall paper works 05/02/12 08/05/12 0 ‐250 0 ‐243 0 ‐257 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5
COMF092690 Installation of Cubicle ‐ Wet area 25/04/12 11/05/12 0 ‐223 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐328 0 ‐342 0 ‐352 0 ‐365 0 ‐381 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF099095 Snagging & Keys 18/05/12 05/06/12 0 ‐257 0 ‐257 0 ‐266 0 ‐282 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor
COMF021150 2nd Floor 14/11/09 06/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF031160 3rd Floor 25/11/09 07/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF041170 4th Floor 06/12/09 17/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF051180 5th Floor 19/12/09 27/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF061190 6th Floor 06/01/10 29/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF071200 7th Floor 17/01/10 04/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF081210 8th Floor 03/02/10 08/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF091220 9th Floor 09/02/10 10/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF101230 10th Floor 14/02/10 13/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF111410 11th Floor 24/02/10 03/05/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMFMZ1040 Mezzanine Floor 01/03/10 10/07/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF121420 12th Floor 08/03/10 10/05/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMFGF1030 Ground Floor 13/03/10 10/07/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF131600 13th Floor 21/03/10 20/05/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF141780 14th Floor 07/04/10 24/07/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF151040 15th Floor 18/04/10 05/09/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF161050 16th Floor 06/05/10 25/09/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions
COMF101870 MEP 2nd fixes 23/01/10 06/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 90 ‐324 91.9 ‐339 91.9 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103250 Plaster to column & lift lobby 15/04/10 16/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103270 Office Fitout (1st & 2nd Fix Trades) 01/06/10 13/04/12 50 ‐246 80 ‐237 80 ‐253 80 ‐273 80 ‐293 85 ‐309 85 ‐319 85 ‐329 85 ‐348 90 ‐353 90 ‐358 90 ‐374 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103290 Basecoat Painting works 26/06/10 07/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF102470 Ceramic tiles ‐ Wet area 17/10/10 26/11/11 90 ‐215 90 ‐217 90 ‐233 92 ‐250 92 ‐270 92 ‐286 92 ‐301 92 ‐315 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF102670 Stone Work @ lift lobby 05/12/10 02/11/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF104240 Screed work @ Corridore area 02/04/11 07/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF102080 Testing & clearance prior to false cei 03/05/11 09/01/12 0 ‐228 66 ‐226 66 ‐242 66 ‐256 80 ‐263 80 ‐279 80 ‐295 80 ‐311 80 ‐317 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 4 5
COMF102620 Suspended Ceiling‐ Wet area 03/05/11 10/01/12 0 ‐222 50 ‐221 50 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 3 4 5
COMF103490 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 27/05/11 27/09/11 0 ‐255 0 ‐249 40 ‐263 40 ‐279 70 ‐299 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF104260 Stone Floor @ Corridore area 11/07/11 12/12/11 0 ‐258 0 ‐249 0 ‐264 60 ‐269 60 ‐286 95 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103150 Ceiling works to lift lobby & bulkhea 26/07/11 14/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐257 70 ‐264 70 ‐280 70 ‐296 70 ‐312 80 ‐317 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF104250 Ceiling Installation  @ Corridore area 28/08/11 10/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 26 ‐270 30 ‐281 60 ‐295 60 ‐310 60 ‐324 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103500 Floor Trunking & Raised Floor Install 30/08/11 03/01/12 0 ‐255 0 ‐249 0 ‐263 0 ‐279 5 ‐298 45 ‐314 60 ‐319 75 ‐326 85 ‐340 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF104270 MEP final fixes to lift lobby/Corrid./W 12/09/11 23/05/12 0 ‐253 0 ‐250 0 ‐259 0 ‐275 0 ‐293 2 ‐312 2.44 ‐318 21 ‐330 20 ‐350 75 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 1 2 3 4 5
COMF103510 Final Ceiling Tiles install ‐ Tenant Are 17/09/11 21/01/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 40 ‐314 60 ‐318 70 ‐331 70 ‐351 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 1 2 3 4 5
COMF104230 MEP final fixes to Tenant Area 01/10/11 23/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐275 0 ‐293 0 ‐312 12 ‐318 23 ‐330 23 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 1 2 3 4 5
COMF142670 Plumbing Fixture Install & Mirror‐ W 15/11/11 10/01/12 0 ‐222 0 ‐226 0 ‐242 0 ‐262 0 ‐282 0 ‐298 0 ‐314 70 ‐323 70 ‐337 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103160 Sliding Door @ Lift Lobby 28/12/11 04/01/12 0 ‐239 0 ‐240 0 ‐256 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103520 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐249 0 ‐243 0 ‐258 0 ‐274 0 ‐292 0 ‐311 0 ‐319 0 ‐326 0 ‐340 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF102680 Threshold & Door Install‐ Wet area 02/01/12 20/02/12 0 ‐222 0 ‐226 0 ‐242 0 ‐262 0 ‐282 0 ‐298 0 ‐314 0 ‐323 0 ‐337 90 ‐349 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103170 Door Installation @Corrid. & Plant R 09/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF103530 Final Painting works to Tenant Area 15/01/12 04/03/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 55 ‐350 90 ‐351 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF103540 Final Painting/Vinyl wall paper works 05/02/12 14/05/12 0 ‐251 0 ‐243 0 ‐258 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5
COMF102610 Installation of Cubicle ‐ Wet area 30/04/12 16/05/12 0 ‐220 0 ‐226 0 ‐242 0 ‐262 0 ‐282 0 ‐298 0 ‐314 0 ‐328 0 ‐342 0 ‐349 0 ‐362 0 ‐378 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF109085 Snagging & Keys 24/05/12 11/06/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor
COMF111860 MEP 2nd fixes 01/03/10 06/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 90 ‐324 90.3 ‐339 90.8 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF113250 Plaster to column & lift lobby 02/05/10 08/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113260 Office Fitout (1st & 2nd Fix Trades) 02/06/10 13/04/12 50 ‐243 80 ‐236 80 ‐252 80 ‐270 80 ‐290 80 ‐311 80 ‐322 80 ‐332 80 ‐352 90 ‐350 90 ‐355 90 ‐371 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF113275 Basecoat Painting works 03/07/10 08/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF112460 Ceramic tiles ‐ Wet area 21/10/10 27/11/11 90 ‐215 90 ‐216 90 ‐232 95 ‐249 98 ‐268 98 ‐284 98 ‐300 98 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF112660 Stone Work @ lift lobby 06/12/10 05/11/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF114190 Screed work @ Corridore area 05/04/11 11/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF112580 Suspended Ceiling‐ Wet area 04/05/11 10/01/12 0 ‐222 47 ‐221 20 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 90 ‐329 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 3 4 5
COMF112070 Testing & clearance prior to false cei 09/05/11 09/01/12 0 ‐226 40 ‐225 40 ‐241 40 ‐258 80 ‐262 80 ‐278 80 ‐293 80 ‐309 80 ‐312 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
4 of 7
West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green
COMF113430 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 29/05/11 13/09/11 0 ‐255 0 ‐249 35 ‐263 55 ‐279 98 ‐299 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF114210 Stone Floor @ Corridore area 10/07/11 12/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF113120 Ceiling works to lift lobby & bulkhea 02/08/11 16/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐258 70 ‐262 70 ‐278 70 ‐294 70 ‐310 90 ‐312 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF114200 Ceiling Installation  @ Corridore area 17/08/11 10/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐268 30 ‐278 60 ‐291 60 ‐306 60 ‐321 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 4 5
COMF113440 Floor Trunking & Raised Floor Install 31/08/11 21/11/11 0 ‐255 0 ‐249 0 ‐263 0 ‐279 5 ‐298 45 ‐309 55 ‐318 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 1 2 3 4 5
COMF113450 Final Ceiling Tiles install ‐ Tenant Are 12/09/11 28/01/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 50 ‐314 85 ‐318 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF114220 MEP final fixes to lift lobby/Corrid./W 12/09/11 29/05/12 0 ‐254 0 ‐250 0 ‐260 0 ‐275 0 ‐293 2 ‐312 2.44 ‐318 21 ‐330 20 ‐350 75 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 1 2 3 4 5
COMF114180 MEP final fixes to Tenant Area 02/10/11 29/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐275 0 ‐293 0 ‐312 14 ‐318 23 ‐330 23 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 1 2 3 4 5
COMF112590 Plumbing Fixture Install & Mirror‐ W 15/11/11 11/01/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 35 ‐326 70 ‐335 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF112600 Threshold & Door Install‐ Wet area 17/12/11 20/02/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐326 30 ‐335 95 ‐348 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113460 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐249 0 ‐243 0 ‐258 0 ‐274 0 ‐292 0 ‐308 0 ‐318 0 ‐324 0 ‐344 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113130 Sliding Door @ Lift Lobby 29/12/11 05/01/12 0 ‐240 0 ‐241 0 ‐257 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113140 Door Installation @Corrid. & Plant R 10/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF113470 Final Painting works to Tenant Area 16/01/12 05/03/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 45 ‐350 85 ‐351 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF113480 Final Painting/Vinyl wall paper works 05/02/12 18/05/12 0 ‐252 0 ‐243 0 ‐259 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5
COMF112570 Installation of Cubicle ‐ Wet area 03/05/12 21/05/12 0 ‐219 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐328 0 ‐342 0 ‐348 0 ‐361 0 ‐377 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF119075 Snagging & Keys 30/05/12 15/06/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor
COMF121850 MEP 2nd fixes 22/03/10 07/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 90 ‐324 90.3 ‐339 90.8 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123255 Plaster to column & lift lobby 04/05/10 30/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF123250 Office Fitout (1st & 2nd Fix Trades) 03/06/10 13/04/12 34 ‐254 80 ‐235 80 ‐251 80 ‐268 80 ‐288 80 ‐313 80 ‐324 80 ‐334 80 ‐352 90 ‐346 90 ‐355 90 ‐371 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 1 2 3 4 5
COMF123280 Basecoat Painting works 10/07/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122450 Ceramic tiles ‐ Wet area 26/10/10 27/11/11 90 ‐214 90 ‐215 90 ‐231 92 ‐248 95 ‐268 95 ‐284 95 ‐299 95 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122650 Stone Work @ lift lobby 08/12/10 07/11/11 80 ‐213 80 ‐229 94 ‐245 95 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF124140 Screed work @ Corridore area 06/04/11 12/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122060 Testing & clearance prior to false cei 04/05/11 09/01/12 0 ‐224 66 ‐221 66 ‐237 66 ‐254 80 ‐260 80 ‐276 80 ‐291 80 ‐307 80 ‐311 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122530 Suspended Ceiling‐ Wet area 04/05/11 10/01/12 0 ‐222 16 ‐221 16 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 3 4 5
COMF123370 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 13/06/11 28/09/11 0 ‐255 0 ‐251 10 ‐264 20 ‐279 98 ‐299 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF124160 Stone Floor @ Corridore area 11/07/11 13/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123090 Ceiling works to lift lobby & bulkhea 03/08/11 29/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐258 70 ‐260 70 ‐276 70 ‐292 70 ‐308 70 ‐311 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF124150 Ceiling Installation  @ Corridore area 30/08/11 10/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 15 ‐267 30 ‐274 60 ‐287 60 ‐302 60 ‐318 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 4 5
COMF124170 MEP final fixes to lift lobby/Corrid./W 13/09/11 04/06/12 0 ‐254 0 ‐250 0 ‐261 0 ‐275 0 ‐295 2 ‐317 2.44 ‐325 19 ‐330 19 ‐350 70 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 1 2 3 4 5
COMF123390 Final Ceiling Tiles install ‐ Tenant Are 24/09/11 29/01/12 0 ‐255 0 ‐254 0 ‐264 0 ‐279 0 ‐299 85 ‐314 85 ‐320 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123380 Floor Trunking & Raised Floor Install 27/09/11 03/01/12 0 ‐255 0 ‐251 0 ‐264 0 ‐279 0 ‐299 10 ‐317 20 ‐326 80 ‐321 90 ‐336 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF124130 MEP final fixes to Tenant Area 16/10/11 04/06/12 0 ‐250 0 ‐250 0 ‐260 0 ‐275 0 ‐295 0 ‐317 10 ‐325 21 ‐330 21 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 1 2 3 4 5
COMF122540 Plumbing Fixture Install & Mirror‐ W 15/11/11 11/01/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 20 ‐327 60 ‐337 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123100 Sliding Door @ Lift Lobby 27/12/11 04/01/12 0 ‐241 0 ‐241 0 ‐257 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF123400 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐249 0 ‐246 0 ‐259 0 ‐274 0 ‐294 0 ‐316 0 ‐326 0 ‐321 0 ‐336 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF122550 Threshold & Door Install‐ Wet area 29/12/11 20/02/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐327 0 ‐337 90 ‐347 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF123110 Door Installation @Corrid. & Plant R 10/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐309 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF123410 Final Painting works to Tenant Area 17/01/12 24/04/12 0 ‐255 0 ‐254 0 ‐264 0 ‐279 0 ‐299 0 ‐316 0 ‐326 0 ‐334 0 ‐354 40 ‐350 85 ‐351 90 ‐358 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF123420 Final Painting/Vinyl wall paper works 11/02/12 24/05/12 0 ‐253 0 ‐244 0 ‐259 0 ‐269 0 ‐288 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5
COMF122520 Installation of Cubicle ‐ Wet area 08/05/12 24/05/12 0 ‐218 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐328 0 ‐342 0 ‐347 0 ‐361 0 ‐377 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF129065 Snagging & Keys 05/06/12 21/06/12 0 ‐255 0 ‐254 0 ‐264 0 ‐279 0 ‐299 0 ‐316 0 ‐326 0 ‐335 0 ‐354 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor
COMF131840 MEP 2nd fixes 23/03/10 07/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 89 ‐324 89.9 ‐339 90.2 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133270 Plaster to column & lift lobby 02/05/10 28/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133240 Office Fitout (1st & 2nd Fix Trades) 12/06/10 13/04/12 34 ‐250 72 ‐235 73 ‐251 75 ‐268 75 ‐288 80 ‐304 80 ‐323 80 ‐336 80 ‐352 80 ‐352 90 ‐355 90 ‐371 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF132440 Ceramic tiles ‐ Wet area 28/10/10 28/11/11 90 ‐214 90 ‐215 90 ‐231 92 ‐248 95 ‐268 95 ‐284 95 ‐299 95 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF132640 Stone Work @ lift lobby 14/03/11 09/11/11 34 ‐213 75 ‐229 94 ‐245 96 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF134080 Screed work @ Corridore area 07/04/11 13/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF132050 Testing & clearance prior to false cei 05/05/11 14/01/12 0 ‐221 60 ‐219 60 ‐235 60 ‐252 60 ‐262 60 ‐278 60 ‐291 70 ‐306 70 ‐308 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF132490 Suspended Ceiling‐ Wet area 02/07/11 21/01/12 0 ‐222 0 ‐221 0 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 3 4 5
COMF134100 Stone Floor @ Corridore area 13/07/11 13/12/11 0 ‐258 0 ‐249 0 ‐264 50 ‐269 55 ‐286 55 ‐302 80 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133060 Ceiling works to lift lobby & bulkhea 04/08/11 22/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 70 ‐275 70 ‐290 70 ‐304 70 ‐320 70 ‐308 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133280 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 08/08/11 16/10/11 0 ‐255 0 ‐251 0 ‐267 0 ‐284 90 ‐299 95 ‐307 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF134090 Ceiling Installation  @ Corridore area 06/09/11 11/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 0 ‐267 30 ‐273 60 ‐285 60 ‐298 60 ‐315 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 4 5
COMF134110 MEP final fixes to lift lobby/Corrid./W 13/09/11 08/06/12 0 ‐255 0 ‐250 0 ‐262 0 ‐279 0 ‐295 2 ‐317 2.44 ‐325 11 ‐331 10 ‐350 70 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 1 2 3 4 5
COMF133340 Final Ceiling Tiles install ‐ Tenant Are 01/10/11 18/02/12 0 ‐255 0 ‐254 0 ‐267 0 ‐284 0 ‐299 0 ‐309 80 ‐319 80 ‐330 80 ‐350 98 ‐352 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133310 Floor Trunking & Raised Floor Install 02/10/11 14/01/12 0 ‐255 0 ‐251 0 ‐267 0 ‐284 0 ‐299 0 ‐307 20 ‐323 43 ‐332 65 ‐341 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF134120 MEP final fixes to Tenant Area 17/10/11 08/06/12 0 ‐250 0 ‐250 0 ‐262 0 ‐279 0 ‐295 0 ‐317 10 ‐325 10 ‐331 10 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 1 2 3 4 5
COMF132500 Plumbing Fixture Install & Mirror‐ W 21/11/11 11/01/12 0 ‐222 0 ‐224 0 ‐240 0 ‐260 0 ‐280 0 ‐296 0 ‐312 20 ‐326 60 ‐336 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133350 Door Installation ‐ Tenant area 27/12/11 22/01/12 0 ‐249 0 ‐246 0 ‐261 0 ‐278 0 ‐294 0 ‐302 0 ‐323 0 ‐332 0 ‐341 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133070 Sliding Door @ Lift Lobby 29/12/11 04/01/12 0 ‐242 0 ‐242 0 ‐258 0 ‐262 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF132510 Threshold & Door Install‐ Wet area 29/12/11 20/02/12 0 ‐222 0 ‐224 0 ‐240 0 ‐260 0 ‐280 0 ‐296 0 ‐312 0 ‐326 0 ‐336 90 ‐346 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133080 Door Installation @Corrid. & Plant R 11/01/12 02/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐309 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF133360 Final Painting works to Tenant Area 17/01/12 27/04/12 0 ‐255 0 ‐254 0 ‐267 0 ‐284 0 ‐299 0 ‐316 0 ‐325 0 ‐334 0 ‐354 35 ‐350 85 ‐351 90 ‐358 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF133330 Final Painting/Vinyl wall paper works 12/02/12 30/05/12 0 ‐254 0 ‐245 0 ‐260 0 ‐272 0 ‐288 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5
COMF132480 Installation of Cubicle ‐ Wet area 11/05/12 29/05/12 0 ‐218 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐328 0 ‐342 0 ‐347 0 ‐361 0 ‐377 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF139055 Snagging & Keys 11/06/12 27/06/12 0 ‐255 0 ‐254 0 ‐267 0 ‐284 0 ‐299 0 ‐316 0 ‐326 0 ‐335 0 ‐355 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor
COMF141830 MEP 2nd fixes 24/03/10 07/12/11 77 ‐253 79 ‐255 80 ‐271 80 ‐288 80 ‐308 83 ‐324 84.1 ‐339 84.1 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 2 3 4 5
COMF143290 Plaster to column & lift lobby 02/05/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF143230 Office Fitout (1st & 2nd Fix Trades) 14/06/10 13/04/12 47 ‐236 80 ‐234 80 ‐250 80 ‐267 80 ‐287 80 ‐303 80 ‐318 80 ‐338 80 ‐352 80 ‐348 90 ‐355 90 ‐371 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 1 2 3 4 5
COMF142430 Ceramic tiles ‐ Wet area 02/11/10 28/11/11 90 ‐212 90 ‐214 90 ‐230 92 ‐246 95 ‐266 95 ‐282 95 ‐298 95 ‐313 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF142630 Stone Work @ lift lobby 20/03/11 12/11/11 34 ‐213 83 ‐229 90 ‐245 95 ‐265 95 ‐275 95 ‐290 95 ‐304 95 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 2 3 4 5
COMF144050 Screed work @ Corridore area 09/04/11 14/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF142040 Testing & clearance prior to false cei 03/05/11 15/01/12 0 ‐219 33 ‐218 40 ‐234 40 ‐251 40 ‐266 40 ‐281 40 ‐295 70 ‐308 70 ‐307 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF144070 Stone Floor @ Corridore area 11/07/11 11/01/12 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 95 ‐314 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 2 3 4 5
COMF142450 Suspended Ceiling‐ Wet area 27/07/11 22/01/12 0 ‐222 0 ‐221 0 ‐237 41 ‐255 60 ‐266 70 ‐282 70 ‐298 70 ‐314 70 ‐329 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 3 4 5
COMF143030 Ceiling works to lift lobby & bulkhea 09/08/11 22/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 70 ‐267 70 ‐282 70 ‐296 70 ‐311 70 ‐307 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor
COMF143240 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 21/08/11 16/11/11 0 ‐255 0 ‐252 0 ‐268 0 ‐285 70 ‐299 95 ‐307 98 ‐318 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 1 2 3 4 5
5 of 7
West Building Programmes Update
West Building Programmes Update

More Related Content

What's hot

Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
JURNAL ILMIAH (ANALISIS KINERJA RUAS JALAN DIPONEGORO AKIBAT BANGKITAN PERJAL...
JURNAL ILMIAH (ANALISIS KINERJA RUAS JALAN DIPONEGORO AKIBAT BANGKITAN PERJAL...JURNAL ILMIAH (ANALISIS KINERJA RUAS JALAN DIPONEGORO AKIBAT BANGKITAN PERJAL...
JURNAL ILMIAH (ANALISIS KINERJA RUAS JALAN DIPONEGORO AKIBAT BANGKITAN PERJAL...Mira Pemayun
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2danieljohn810
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
Facebook のデータを Power BI で見てみると…~セルフマーケティングに活用できるかも!?~
Facebook のデータを Power BI で見てみると…~セルフマーケティングに活用できるかも!?~Facebook のデータを Power BI で見てみると…~セルフマーケティングに活用できるかも!?~
Facebook のデータを Power BI で見てみると…~セルフマーケティングに活用できるかも!?~Yugo Shimizu
 
13f93 modul 6_analisis_koefisien
13f93 modul 6_analisis_koefisien13f93 modul 6_analisis_koefisien
13f93 modul 6_analisis_koefisiengabylahusa
 
Asta Powerproject: Business Case
Asta Powerproject: Business CaseAsta Powerproject: Business Case
Asta Powerproject: Business CaseCisco
 
Power Appsで Excel関数を利用する3つの方法
Power Appsで Excel関数を利用する3つの方法Power Appsで Excel関数を利用する3つの方法
Power Appsで Excel関数を利用する3つの方法Nagao Hiroaki
 
Teamsを真に活用するための秘訣を教えます
Teamsを真に活用するための秘訣を教えますTeamsを真に活用するための秘訣を教えます
Teamsを真に活用するための秘訣を教えますmokudai masayuki
 
2007 07-pekerjaan tanah
2007 07-pekerjaan tanah2007 07-pekerjaan tanah
2007 07-pekerjaan tanahahmad fuadi
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?SHAZEBALIKHAN1
 
Microsoft project training manual
Microsoft project training manualMicrosoft project training manual
Microsoft project training manualKhalid Mahmood
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowSHAZEBALIKHAN1
 
6 TUGAS TANGGUNG JAWAB & WEWENANG.pptx
6 TUGAS TANGGUNG JAWAB & WEWENANG.pptx6 TUGAS TANGGUNG JAWAB & WEWENANG.pptx
6 TUGAS TANGGUNG JAWAB & WEWENANG.pptxFitraRamadhanFisman
 

What's hot (20)

Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
JURNAL ILMIAH (ANALISIS KINERJA RUAS JALAN DIPONEGORO AKIBAT BANGKITAN PERJAL...
JURNAL ILMIAH (ANALISIS KINERJA RUAS JALAN DIPONEGORO AKIBAT BANGKITAN PERJAL...JURNAL ILMIAH (ANALISIS KINERJA RUAS JALAN DIPONEGORO AKIBAT BANGKITAN PERJAL...
JURNAL ILMIAH (ANALISIS KINERJA RUAS JALAN DIPONEGORO AKIBAT BANGKITAN PERJAL...
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Facebook のデータを Power BI で見てみると…~セルフマーケティングに活用できるかも!?~
Facebook のデータを Power BI で見てみると…~セルフマーケティングに活用できるかも!?~Facebook のデータを Power BI で見てみると…~セルフマーケティングに活用できるかも!?~
Facebook のデータを Power BI で見てみると…~セルフマーケティングに活用できるかも!?~
 
13f93 modul 6_analisis_koefisien
13f93 modul 6_analisis_koefisien13f93 modul 6_analisis_koefisien
13f93 modul 6_analisis_koefisien
 
Asta Powerproject: Business Case
Asta Powerproject: Business CaseAsta Powerproject: Business Case
Asta Powerproject: Business Case
 
Power Appsで Excel関数を利用する3つの方法
Power Appsで Excel関数を利用する3つの方法Power Appsで Excel関数を利用する3つの方法
Power Appsで Excel関数を利用する3つの方法
 
Teamsを真に活用するための秘訣を教えます
Teamsを真に活用するための秘訣を教えますTeamsを真に活用するための秘訣を教えます
Teamsを真に活用するための秘訣を教えます
 
2007 07-pekerjaan tanah
2007 07-pekerjaan tanah2007 07-pekerjaan tanah
2007 07-pekerjaan tanah
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Kurva s jasa konsultansi
Kurva s jasa konsultansiKurva s jasa konsultansi
Kurva s jasa konsultansi
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?
 
MS Project
MS ProjectMS Project
MS Project
 
Microsoft project training manual
Microsoft project training manualMicrosoft project training manual
Microsoft project training manual
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must know
 
6 TUGAS TANGGUNG JAWAB & WEWENANG.pptx
6 TUGAS TANGGUNG JAWAB & WEWENANG.pptx6 TUGAS TANGGUNG JAWAB & WEWENANG.pptx
6 TUGAS TANGGUNG JAWAB & WEWENANG.pptx
 

Similar to West Building Programmes Update

BLOCK5 - Programme with updates superimposed one with all sorts - Critical Path
BLOCK5 - Programme with updates superimposed one with all sorts - Critical PathBLOCK5 - Programme with updates superimposed one with all sorts - Critical Path
BLOCK5 - Programme with updates superimposed one with all sorts - Critical PathJeremy Fearnsides
 
Schiedel Metaloterm MFflue system
Schiedel Metaloterm MFflue systemSchiedel Metaloterm MFflue system
Schiedel Metaloterm MFflue systemSchiedel UK
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
Term schedule for 201308.htm the data you see here may
Term schedule for 201308.htm the data you see here may Term schedule for 201308.htm the data you see here may
Term schedule for 201308.htm the data you see here may mayank272369
 
SW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptxSW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptxLeDuc49898
 
Ejemplo real p&id 25635-220-m6-0310-00001
Ejemplo real p&id 25635-220-m6-0310-00001Ejemplo real p&id 25635-220-m6-0310-00001
Ejemplo real p&id 25635-220-m6-0310-00001lizandro cabello
 
BoSS Mobile Access Product Guide
BoSS Mobile Access Product GuideBoSS Mobile Access Product Guide
BoSS Mobile Access Product GuideStuart Harling
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxabirsengupta9
 
Labour-and-Equipment-Productivity.pdf
Labour-and-Equipment-Productivity.pdfLabour-and-Equipment-Productivity.pdf
Labour-and-Equipment-Productivity.pdfKothandaraman T
 
Tuladhar
TuladharTuladhar
Tuladharhlksd
 
Residence addition _ Structural plans and details
Residence addition _ Structural plans and detailsResidence addition _ Structural plans and details
Residence addition _ Structural plans and detailsTeresa Seasons
 
Ground Lug - Conecteur
Ground Lug - ConecteurGround Lug - Conecteur
Ground Lug - ConecteurConecteur
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
ABB POLIM-D High Voltage Surge Arresters AC 4kV - 36kV - AC Surge Arresters ...
ABB POLIM-D High Voltage Surge Arresters AC 4kV - 36kV -  AC Surge Arresters ...ABB POLIM-D High Voltage Surge Arresters AC 4kV - 36kV -  AC Surge Arresters ...
ABB POLIM-D High Voltage Surge Arresters AC 4kV - 36kV - AC Surge Arresters ...Thorne & Derrick International
 
CMP E1W32 LSF Brass Cable Gland (Zero Halogen) - 22.9-33.9mm
CMP E1W32 LSF Brass Cable Gland (Zero Halogen) - 22.9-33.9mm CMP E1W32 LSF Brass Cable Gland (Zero Halogen) - 22.9-33.9mm
CMP E1W32 LSF Brass Cable Gland (Zero Halogen) - 22.9-33.9mm Thorne & Derrick International
 
CMP E1W63S LSF Brass Cable Gland (Zero Halogen) - 45.6-59.4mm
CMP E1W63S LSF Brass Cable Gland (Zero Halogen) - 45.6-59.4mmCMP E1W63S LSF Brass Cable Gland (Zero Halogen) - 45.6-59.4mm
CMP E1W63S LSF Brass Cable Gland (Zero Halogen) - 45.6-59.4mmThorne & Derrick International
 
CMP E1W63 LSF Brass Cable Gland (Zero Halogen) - 54.6-65.9mm
CMP E1W63 LSF Brass Cable Gland (Zero Halogen) - 54.6-65.9mmCMP E1W63 LSF Brass Cable Gland (Zero Halogen) - 54.6-65.9mm
CMP E1W63 LSF Brass Cable Gland (Zero Halogen) - 54.6-65.9mmThorne & Derrick International
 
CMP E1W25 LSF Brass Cable Gland (Zero Halogen) - 17-26.2mm
CMP E1W25 LSF Brass Cable Gland (Zero Halogen) - 17-26.2mmCMP E1W25 LSF Brass Cable Gland (Zero Halogen) - 17-26.2mm
CMP E1W25 LSF Brass Cable Gland (Zero Halogen) - 17-26.2mmThorne & Derrick International
 
CMP E1W20 LSF Brass Cable Gland (Zero Halogen) - 12.5-20.9mm
CMP E1W20 LSF Brass Cable Gland (Zero Halogen) - 12.5-20.9mm CMP E1W20 LSF Brass Cable Gland (Zero Halogen) - 12.5-20.9mm
CMP E1W20 LSF Brass Cable Gland (Zero Halogen) - 12.5-20.9mm Thorne & Derrick International
 
CMP E1W20SS LSF Brass Cable Gland (Zero Halogen) - 6-13.4mm
CMP E1W20SS LSF Brass Cable Gland (Zero Halogen) - 6-13.4mmCMP E1W20SS LSF Brass Cable Gland (Zero Halogen) - 6-13.4mm
CMP E1W20SS LSF Brass Cable Gland (Zero Halogen) - 6-13.4mmThorne & Derrick International
 

Similar to West Building Programmes Update (20)

BLOCK5 - Programme with updates superimposed one with all sorts - Critical Path
BLOCK5 - Programme with updates superimposed one with all sorts - Critical PathBLOCK5 - Programme with updates superimposed one with all sorts - Critical Path
BLOCK5 - Programme with updates superimposed one with all sorts - Critical Path
 
Schiedel Metaloterm MFflue system
Schiedel Metaloterm MFflue systemSchiedel Metaloterm MFflue system
Schiedel Metaloterm MFflue system
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Term schedule for 201308.htm the data you see here may
Term schedule for 201308.htm the data you see here may Term schedule for 201308.htm the data you see here may
Term schedule for 201308.htm the data you see here may
 
SW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptxSW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptx
 
Ejemplo real p&id 25635-220-m6-0310-00001
Ejemplo real p&id 25635-220-m6-0310-00001Ejemplo real p&id 25635-220-m6-0310-00001
Ejemplo real p&id 25635-220-m6-0310-00001
 
BoSS Mobile Access Product Guide
BoSS Mobile Access Product GuideBoSS Mobile Access Product Guide
BoSS Mobile Access Product Guide
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptx
 
Labour-and-Equipment-Productivity.pdf
Labour-and-Equipment-Productivity.pdfLabour-and-Equipment-Productivity.pdf
Labour-and-Equipment-Productivity.pdf
 
Tuladhar
TuladharTuladhar
Tuladhar
 
Residence addition _ Structural plans and details
Residence addition _ Structural plans and detailsResidence addition _ Structural plans and details
Residence addition _ Structural plans and details
 
Ground Lug - Conecteur
Ground Lug - ConecteurGround Lug - Conecteur
Ground Lug - Conecteur
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
ABB POLIM-D High Voltage Surge Arresters AC 4kV - 36kV - AC Surge Arresters ...
ABB POLIM-D High Voltage Surge Arresters AC 4kV - 36kV -  AC Surge Arresters ...ABB POLIM-D High Voltage Surge Arresters AC 4kV - 36kV -  AC Surge Arresters ...
ABB POLIM-D High Voltage Surge Arresters AC 4kV - 36kV - AC Surge Arresters ...
 
CMP E1W32 LSF Brass Cable Gland (Zero Halogen) - 22.9-33.9mm
CMP E1W32 LSF Brass Cable Gland (Zero Halogen) - 22.9-33.9mm CMP E1W32 LSF Brass Cable Gland (Zero Halogen) - 22.9-33.9mm
CMP E1W32 LSF Brass Cable Gland (Zero Halogen) - 22.9-33.9mm
 
CMP E1W63S LSF Brass Cable Gland (Zero Halogen) - 45.6-59.4mm
CMP E1W63S LSF Brass Cable Gland (Zero Halogen) - 45.6-59.4mmCMP E1W63S LSF Brass Cable Gland (Zero Halogen) - 45.6-59.4mm
CMP E1W63S LSF Brass Cable Gland (Zero Halogen) - 45.6-59.4mm
 
CMP E1W63 LSF Brass Cable Gland (Zero Halogen) - 54.6-65.9mm
CMP E1W63 LSF Brass Cable Gland (Zero Halogen) - 54.6-65.9mmCMP E1W63 LSF Brass Cable Gland (Zero Halogen) - 54.6-65.9mm
CMP E1W63 LSF Brass Cable Gland (Zero Halogen) - 54.6-65.9mm
 
CMP E1W25 LSF Brass Cable Gland (Zero Halogen) - 17-26.2mm
CMP E1W25 LSF Brass Cable Gland (Zero Halogen) - 17-26.2mmCMP E1W25 LSF Brass Cable Gland (Zero Halogen) - 17-26.2mm
CMP E1W25 LSF Brass Cable Gland (Zero Halogen) - 17-26.2mm
 
CMP E1W20 LSF Brass Cable Gland (Zero Halogen) - 12.5-20.9mm
CMP E1W20 LSF Brass Cable Gland (Zero Halogen) - 12.5-20.9mm CMP E1W20 LSF Brass Cable Gland (Zero Halogen) - 12.5-20.9mm
CMP E1W20 LSF Brass Cable Gland (Zero Halogen) - 12.5-20.9mm
 
CMP E1W20SS LSF Brass Cable Gland (Zero Halogen) - 6-13.4mm
CMP E1W20SS LSF Brass Cable Gland (Zero Halogen) - 6-13.4mmCMP E1W20SS LSF Brass Cable Gland (Zero Halogen) - 6-13.4mm
CMP E1W20SS LSF Brass Cable Gland (Zero Halogen) - 6-13.4mm
 

West Building Programmes Update

  • 1. West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green $BCP$4 FinalColumn # 40998 M340 M350 M360 M370 M380 M390 M400 M410 M420 M430 M440 M450 29/04/11 30/04/11 27/05/11 28/05/11 24/06/11 25/06/11 29/07/11 30/07/11 02/09/11 03/09/11 30/09/11 01/10/11 28/10/11 29/10/11 25/11/11 26/11/11 30/12/11 31/12/11 03/02/12 04/02/12 02/03/12 03/03/12 30/03/12 31/03/12 15/02/13 ACT Title OD Start Finish (*)Dur(*)Tota(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)Tot(*)Dur(*)TotWBS 1 Level 1 Level 2 Level 3 Level 4 Level 5 Level 6 Most CriMost CritMost CritMost Most Cr COSPMZ0620 Structural elements up to Mezz. floo 10/06/09 30/07/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP010620 Structural elements up to 1st floor (I 17/06/09 27/08/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP020620 Structural elements up to 2nd floor ( 27/07/09 24/09/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP030620 Structural elements up to 3rd floor ( 13/08/09 06/10/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP040620 Structural elements up to 4th floor ( 25/08/09 15/10/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP050620 Structural elements up to 5th floor ( 16/09/09 27/10/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP060620 Structural elements up to 6th floor ( 28/09/09 08/11/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP070620 Structural elements up to 7th floor ( 17/10/09 17/11/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP080620 Structural elements up to 8th floor ( 24/10/09 01/12/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP090620 Structural elements up to 9th floor ( 04/11/09 10/12/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP100620 Structural elements up to 10th floor  15/11/09 22/12/09 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP110620 Structural elements up to 11th floor  25/11/09 06/01/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP120620 Structural elements up to 12th floor  13/12/09 18/01/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP130620 Structural elements up to 13th floor  30/12/09 28/01/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP140620 Structural elements up to 14th floor  09/01/10 11/02/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSP150620 Structural elements up to 15th floor  21/01/10 25/02/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSPRF0620 Structural elements up to RF floor (In 07/02/10 15/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COSPUR0620 Structural elements up to UR floor & 20/02/10 14/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.SP Super structure M450 C1 O SP Super structure COMF011830 MEP 2nd fixes 12/11/09 12/12/11 75 ‐247 77 ‐249 78 ‐265 80 ‐283 80 ‐303 84 ‐321 87.2 ‐337 95.2 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 1 2 3 4 5 COMF011835 Plaster to column 20/03/10 07/01/12 80 ‐253 80 ‐255 80 ‐271 85 ‐288 85 ‐308 85 ‐324 85 ‐339 90 ‐354 90 ‐342 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5 COMF011840 Office Fitout (1st & 2nd Fix Trades) 18/04/10 04/04/12 1 ‐242 1 ‐244 1 ‐260 5 ‐279 5 ‐299 5 ‐315 5 ‐331 15 ‐342 20 ‐350 80 ‐343 90 ‐352 90 ‐362 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5 COMF011845 Basecoat Painting works 26/04/10 16/01/12 36 ‐253 36 ‐255 36 ‐271 36 ‐288 36 ‐308 36 ‐324 36 ‐339 36 ‐354 36 ‐350 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5 COMF011850 Stone Work @ lift lobby 12/09/10 05/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011860 Ceramic tiles ‐ Wet area 27/10/10 14/01/12 80 ‐211 80 ‐213 80 ‐229 80 ‐246 80 ‐266 80 ‐282 80 ‐297 80 ‐313 80 ‐308 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011865 Testing & clearance prior to false cei 03/05/11 10/01/12 0 ‐213 16 ‐214 16 ‐230 16 ‐247 16 ‐267 16 ‐274 16.7 ‐287 16.7 ‐303 16 ‐297 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 5 COMF011935 MEP final fixes to lift lobby/Corrid./W 13/09/11 26/06/12 0 ‐258 0 ‐250 0 ‐266 0 ‐283 0 ‐303 2 ‐319 2.44 ‐335 3 ‐349 2 ‐355 45 ‐361 90 ‐375 90 ‐390 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 1 2 3 4 5 COMF011925 Ceiling works to lift lobby & bulkhea 18/09/11 10/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 0 ‐275 60 ‐282 80 ‐293 80 ‐309 80 ‐297 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011855 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 24/09/11 15/01/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 70 ‐324 78 ‐339 85 ‐354 85 ‐350 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5 COMF011895 Ceiling Installation  @ Corridore area 26/09/11 11/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 0 ‐267 30 ‐271 30 ‐287 45 ‐288 45 ‐308 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011920 Stone Floor @ Corridore area 08/11/11 14/01/12 0 ‐258 0 ‐249 0 ‐264 0 ‐274 0 ‐286 0 ‐302 0 ‐314 90 ‐330 90 ‐315 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011870 Screed work @ Corridore area 08/11/11 15/11/11 0 ‐187 0 ‐203 0 ‐219 0 ‐239 0 ‐259 0 ‐271 0 ‐287 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011875 Floor Trunking & Raised Floor Install 23/11/11 15/01/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 5 ‐354 37 ‐350 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5 COMF011915 Threshold & Door Install‐ Wet area 29/12/11 20/02/12 0 ‐222 0 ‐223 0 ‐239 0 ‐259 0 ‐279 0 ‐295 0 ‐311 0 ‐327 0 ‐341 90 ‐347 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011905 Final Ceiling Tiles install ‐ Tenant Are 02/01/12 05/02/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 0 ‐354 0 ‐359 85 ‐349 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011885 Suspended Ceiling‐ Wet area 02/01/12 16/01/12 0 ‐222 0 ‐221 0 ‐237 0 ‐255 0 ‐266 0 ‐282 0 ‐298 0 ‐314 0 ‐329 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011890 Plumbing Fixture Install & Mirror‐ W 03/01/12 11/03/12 0 ‐222 0 ‐223 0 ‐239 0 ‐259 0 ‐279 0 ‐295 0 ‐311 0 ‐327 0 ‐341 90 ‐347 90 ‐360 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 2 3 4 5 COMF011900 MEP final fixes to Tenant Area 14/01/12 26/06/12 0 ‐250 0 ‐250 0 ‐266 0 ‐283 0 ‐303 0 ‐319 0 ‐335 0 ‐349 0 ‐355 50 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor 1 2 3 4 5 COMF011910 Door Installation ‐ Tenant area 16/01/12 23/01/12 0 ‐249 0 ‐249 0 ‐265 0 ‐282 0 ‐302 0 ‐318 0 ‐334 0 ‐348 0 ‐345 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011940 Door Installation @Corrid. & Plant R 16/01/12 02/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐309 0 ‐323 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011945 Final Painting works to Tenant Area 04/02/12 11/03/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 0 ‐354 0 ‐359 0 ‐350 80 ‐351 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011950 Sliding Door @ Lift Lobby 04/02/12 09/02/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 0 ‐320 100 0 100 0 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011930 Final Painting/Vinyl wall paper works 11/02/12 15/06/12 0 ‐256 0 ‐247 0 ‐263 0 ‐276 0 ‐296 0 ‐312 0 ‐328 0 ‐342 0 ‐347 0 ‐361 30 ‐370 80 ‐384 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011880 Installation of Cubicle ‐ Wet area 28/05/12 13/06/12 0 ‐217 0 ‐223 0 ‐239 0 ‐259 0 ‐279 0 ‐295 0 ‐311 0 ‐327 0 ‐341 0 ‐347 0 ‐360 0 ‐375 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF011955 Snagging & Keys 27/06/12 13/07/12 0 ‐255 0 ‐255 0 ‐271 0 ‐288 0 ‐308 0 ‐324 0 ‐339 0 ‐354 0 ‐359 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.01 1st Floor M450 C1 O MF 01 1st Floor COMF021820 MEP 2nd fixes 27/11/09 03/12/11 85 ‐243 95 ‐254 95 ‐270 95 ‐287 95 ‐307 97 ‐322 98.7 ‐338 98.7 ‐354 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF023230 Plaster to column & lift lobby 20/03/10 28/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF023220 Office Fitout (1st & 2nd Fix Trades) 08/04/10 05/04/12 66 ‐257 95 ‐248 95 ‐264 95 ‐274 95 ‐289 95 ‐302 95.3 ‐317 95.3 ‐333 95 ‐353 95 ‐364 95 ‐375 95 ‐390 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5 COMF023260 Basecoat Painting works 05/05/10 15/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF022420 Ceramic tiles 13/05/10 15/05/11 90 ‐203 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF022620 Stone Work @ lift lobby 01/08/10 07/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF024810 Screed work @ Corridore area 14/02/11 20/02/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF024730 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 17/02/11 02/07/11 75 ‐257 81 ‐250 95 ‐266 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5 COMF024750 MEP final fixes to Tenant Area 15/03/11 09/04/12 25 ‐237 25 ‐240 25 ‐241 35 ‐259 45 ‐282 45 ‐298 45 ‐314 45 ‐330 45 ‐349 90 ‐360 90 ‐375 95 ‐390 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5 COMF022550 Ceramic tiles ‐ Wet area (Balance/Re 15/03/11 26/07/11 83 ‐221 83 ‐231 98 ‐246 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF022160 Testing & clearance prior to false cei 15/03/11 21/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF022980 Suspended Ceiling‐ Wet area 22/03/11 02/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF024740 Floor Trunking & Raised Floor Install 25/03/11 09/08/11 25 ‐244 25 ‐246 85 ‐242 95 ‐261 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF024760 Final Ceiling Tiles install ‐ Tenant Are 25/03/11 03/01/12 25 ‐244 30 ‐246 35 ‐245 70 ‐258 95 ‐283 95 ‐298 95 ‐315 95 ‐331 95 ‐350 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF024780 Final Painting works to Tenant Area 28/03/11 18/02/12 30 ‐240 76 ‐236 75 ‐235 75 ‐253 75 ‐279 75 ‐295 75 ‐311 75 ‐327 75 ‐346 95 ‐353 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF024770 Door Installation ‐ Tenant area 28/03/11 15/01/12 25 ‐238 25 ‐241 25 ‐241 25 ‐261 25 ‐287 25 ‐303 25 ‐319 25 ‐335 25 ‐354 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5 COMF024830 Stone Floor @ Corridore area 01/04/11 07/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF024800 Sliding Door @ Lift Lobby 20/04/11 24/07/11 0 ‐231 50 ‐225 50 ‐241 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF022990 Plumbing Fixture Install & Mirror‐ W 27/04/11 14/01/12 0 ‐221 90 ‐225 90 ‐241 95 ‐260 95 ‐280 95 ‐296 95 ‐312 95 ‐328 95 ‐341 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF023000 Threshold & Door Install‐ Wet area 30/04/11 13/02/12 0 ‐221 16 ‐225 15 ‐241 15 ‐260 15 ‐280 15 ‐296 15 ‐312 15 ‐328 30 ‐341 90 ‐357 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF024820 Ceiling Installation  @ Corridore area 02/05/11 07/01/12 0 ‐258 20 ‐255 50 ‐270 50 ‐280 60 ‐292 85 ‐308 85 ‐322 85 ‐338 85 ‐353 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF024790 Ceiling works to lift lobby & bulkhea 02/05/11 23/07/11 0 ‐243 28 ‐248 30 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF024850 MEP final fixes to lift lobby/Corrid./W 09/05/11 09/04/12 0 ‐237 21 ‐240 25 ‐249 30 ‐269 40 ‐287 40 ‐298 40 ‐314 59 ‐330 59 ‐349 90 ‐360 90 ‐375 97 ‐390 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 2 3 4 5 COMF024840 Final Painting/Vinyl wall paper works 01/09/11 10/03/12 0 ‐235 0 ‐236 0 ‐249 0 ‐269 5 ‐287 35 ‐297 35 ‐313 35 ‐329 35 ‐344 70 ‐358 90 ‐370 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 2 3 4 5 COMF024860 Door Installation @Corrid. & Plant R 28/12/11 28/01/12 0 ‐239 0 ‐241 0 ‐253 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐354 100 0 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF022970 Installation of Cubicle ‐ Wet area 11/02/12 13/02/12 0 ‐221 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 0 ‐343 0 ‐357 100 0 100 0 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor 1 of 7
  • 2. West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green COMF029165 Snagging & Keys 09/04/12 25/04/12 0 ‐240 0 ‐236 0 ‐244 0 ‐264 0 ‐283 0 ‐296 0 ‐312 0 ‐328 0 ‐345 0 ‐357 0 ‐369 0 ‐384 M450.C1.O.MF.02 2nd Floor M450 C1 O MF 02 2nd Floor COMF031940 MEP 2nd fixes 12/12/09 04/12/11 64 ‐253 95 ‐255 95 ‐271 95 ‐288 95 ‐308 95 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF033250 Plaster to column & lift lobby 20/03/10 20/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF033340 Office Fitout (1st & 2nd Fix Trades) 27/04/10 06/04/12 62 ‐257 90 ‐250 90 ‐265 90 ‐279 90 ‐293 90 ‐306 90 ‐321 90 ‐337 90 ‐357 95 ‐364 95 ‐373 95 ‐389 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF033270 Basecoat Painting works 05/05/10 27/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF032540 Ceramic tiles 01/06/10 17/05/11 90 ‐203 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF032740 Stone Work @ lift lobby 09/08/10 12/10/11 93 ‐227 93 ‐243 96 ‐259 96 ‐256 98 ‐270 98 ‐286 98 ‐302 98 ‐318 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF034670 Screed work @ Corridore area 21/02/11 27/02/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF034590 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 24/02/11 07/07/11 75 ‐257 81 ‐250 90 ‐266 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 1 2 3 4 5 COMF032150 Testing & clearance prior to false cei 15/03/11 12/05/11 83 ‐244 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF032745 Ceramic tiles ‐ Wet area (Balance/Re 15/03/11 17/05/11 75 ‐227 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 4 5 COMF032940 Suspended Ceiling‐ Wet area 26/03/11 14/08/11 27 ‐225 47 ‐223 50 ‐239 70 ‐258 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF034640 Final Painting works to Tenant Area 01/05/11 18/02/12 0 ‐257 76 ‐247 76 ‐239 76 ‐255 76 ‐282 76 ‐298 76.9 ‐314 76.9 ‐330 76 ‐350 80 ‐353 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF034660 Sliding Door @ Lift Lobby 02/05/11 02/01/12 0 ‐233 20 ‐226 20 ‐242 20 ‐252 20 ‐272 45 ‐288 50 ‐304 50 ‐320 50 ‐334 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF034680 Ceiling Installation  @ Corridore area 10/05/11 08/01/12 0 ‐258 20 ‐249 25 ‐264 25 ‐274 35 ‐286 70 ‐302 70 ‐313 70 ‐329 72 ‐349 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF034600 Floor Trunking & Raised Floor Install 26/05/11 14/08/11 0 ‐257 0 ‐257 80 ‐247 95 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF034690 Stone Floor @ Corridore area 28/06/11 14/07/11 0 ‐258 0 ‐249 0 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF034620 Final Ceiling Tiles install ‐ Tenant Are 23/07/11 02/01/12 0 ‐257 0 ‐257 0 ‐249 60 ‐259 85 ‐283 85 ‐299 85 ‐316 85 ‐332 85 ‐352 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF034650 Ceiling works to lift lobby & bulkhea 23/07/11 07/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐272 70 ‐288 70 ‐304 70 ‐320 98 ‐334 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF034610 MEP final fixes to Tenant Area 06/08/11 13/04/12 0 ‐250 0 ‐250 0 ‐242 0 ‐264 13 ‐288 30 ‐300 30 ‐316 40 ‐330 40 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 1 2 3 4 5 COMF034710 MEP final fixes to lift lobby/Corrid./W 21/08/11 13/04/12 0 ‐250 0 ‐250 0 ‐253 0 ‐269 7 ‐288 10 ‐300 11 ‐316 53 ‐330 53 ‐350 90 ‐360 90 ‐375 96 ‐390 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 1 2 3 4 5 COMF032950 Plumbing Fixture Install & Mirror‐ W 08/11/11 09/01/12 0 ‐227 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 70 ‐331 70 ‐343 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF032960 Threshold & Door Install‐ Wet area 03/12/11 18/02/12 0 ‐227 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 30 ‐343 90 ‐356 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF034720 Door Installation @Corrid. & Plant R 28/12/11 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF034630 Door Installation ‐ Tenant area 02/01/12 16/01/12 0 ‐251 0 ‐249 0 ‐241 0 ‐263 0 ‐289 0 ‐305 0 ‐321 0 ‐337 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF034700 Final Painting/Vinyl wall paper works 21/01/12 04/04/12 0 ‐246 0 ‐243 0 ‐252 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 70 ‐358 80 ‐370 80 ‐384 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor 2 3 4 5 COMF032930 Installation of Cubicle ‐ Wet area 30/03/12 17/04/12 0 ‐227 0 ‐234 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 0 ‐343 0 ‐356 0 ‐369 0 ‐385 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF039155 Snagging & Keys 17/04/12 03/05/12 0 ‐257 0 ‐246 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐331 0 ‐349 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.03 3rd Floor M450 C1 O MF 03 3rd Floor COMF041930 MEP 2nd fixes 27/12/09 04/12/11 81 ‐253 95 ‐255 95 ‐271 95 ‐288 95 ‐308 95 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF043250 Plaster to column & lift lobby 20/03/10 11/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF043330 Office Fitout (1st & 2nd Fix Trades) 04/05/10 05/04/12 65 ‐256 95 ‐247 95 ‐263 95 ‐279 95 ‐294 95 ‐307 95.3 ‐320 95.3 ‐336 95 ‐356 95 ‐368 95 ‐373 95 ‐389 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF043270 Basecoat Painting works 06/05/10 23/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF042530 Ceramic tiles 05/06/10 19/05/11 90 ‐203 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF042730 Stone Work @ lift lobby 14/08/10 14/10/11 93 ‐222 93 ‐238 96 ‐254 98 ‐265 98 ‐275 98 ‐290 98 ‐306 98 ‐322 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF044540 Screed work @ Corridore area 28/02/11 16/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF043950 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 03/03/11 14/07/11 75 ‐257 81 ‐250 85 ‐266 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 1 2 3 4 5 COMF042140 Testing & clearance prior to false cei 16/03/11 01/05/11 83 ‐241 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF043955 Ceramic tiles ‐ Wet area (Balance/Re 16/03/11 02/08/11 75 ‐225 75 ‐226 75 ‐242 98 ‐261 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF042900 Suspended Ceiling‐ Wet area 30/03/11 14/08/11 20 ‐225 50 ‐223 50 ‐239 70 ‐258 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF044010 Sliding Door @ Lift Lobby 03/05/11 04/01/12 0 ‐234 20 ‐231 20 ‐247 20 ‐254 20 ‐274 20 ‐290 20 ‐305 20 ‐321 20 ‐334 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF044550 Ceiling Installation  @ Corridore area 10/05/11 08/01/12 0 ‐258 20 ‐245 25 ‐260 25 ‐274 35 ‐286 35 ‐302 60 ‐311 60 ‐326 70 ‐345 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF043970 Final Ceiling Tiles install ‐ Tenant Are 10/05/11 03/01/12 0 ‐257 10 ‐257 15 ‐249 60 ‐259 85 ‐283 85 ‐299 90 ‐316 90 ‐332 90 ‐352 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF043960 Floor Trunking & Raised Floor Install 05/06/11 14/08/11 0 ‐257 0 ‐252 60 ‐248 95 ‐262 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF044560 Stone Floor @ Corridore area 28/06/11 14/07/11 0 ‐258 0 ‐249 0 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF044000 Ceiling works to lift lobby & bulkhea 24/07/11 08/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐274 70 ‐290 70 ‐305 70 ‐321 95 ‐334 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF044530 MEP final fixes to Tenant Area 06/08/11 19/04/12 0 ‐250 0 ‐250 0 ‐243 0 ‐264 13 ‐288 27 ‐300 27 ‐316 37 ‐330 37 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 1 2 3 4 5 COMF044570 MEP final fixes to lift lobby/Corrid./W 22/08/11 19/04/12 0 ‐250 0 ‐250 0 ‐254 0 ‐269 4 ‐288 8 ‐300 8.54 ‐316 43 ‐330 43 ‐350 90 ‐361 90 ‐375 98 ‐390 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 1 2 3 4 5 COMF042910 Plumbing Fixture Install & Mirror‐ W 08/11/11 08/01/12 0 ‐227 0 ‐233 0 ‐249 0 ‐269 0 ‐289 0 ‐305 0 ‐321 70 ‐330 70 ‐342 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF042920 Threshold & Door Install‐ Wet area 04/12/11 18/02/12 0 ‐227 0 ‐233 0 ‐249 0 ‐269 0 ‐289 0 ‐305 0 ‐321 0 ‐330 30 ‐342 90 ‐356 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF043990 Final Painting works to Tenant Area 02/01/12 20/02/12 0 ‐257 0 ‐257 0 ‐249 0 ‐262 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 70 ‐353 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF043980 Door Installation ‐ Tenant area 02/01/12 16/01/12 0 ‐251 0 ‐248 0 ‐245 0 ‐262 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF044580 Door Installation @Corrid. & Plant R 02/01/12 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF044020 Final Painting/Vinyl wall paper works 11/02/12 10/04/12 0 ‐247 0 ‐243 0 ‐253 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF042890 Installation of Cubicle ‐ Wet area 04/04/12 20/04/12 6 ‐227 6 ‐233 6 ‐249 6 ‐269 6 ‐289 6 ‐305 6.25 ‐321 6.25 ‐330 6 ‐342 6 ‐356 0 ‐369 0 ‐385 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor 2 3 4 5 COMF049145 Snagging & Keys 23/04/12 09/05/12 0 ‐257 0 ‐256 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.04 4th Floor M450 C1 O MF 04 4th Floor COMF051920 MEP 2nd fixes 11/01/10 04/12/11 83 ‐253 95 ‐255 95 ‐271 95 ‐288 95 ‐308 95 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF053250 Plaster to column & lift lobby 10/04/10 28/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF053270 Basecoat Painting works 08/05/10 19/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF053320 Office Fitout (1st & 2nd Fix Trades) 17/05/10 05/04/12 58 ‐257 95 ‐246 95 ‐262 95 ‐280 95 ‐295 95 ‐308 95.3 ‐314 95.3 ‐330 95 ‐349 95 ‐364 95 ‐370 95 ‐386 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF052520 Ceramic tiles ‐ Wet area 20/06/10 19/05/11 90 ‐224 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF052720 Stone Work @ lift lobby 04/10/10 16/10/11 93 ‐222 93 ‐238 96 ‐253 98 ‐265 98 ‐275 98 ‐290 98 ‐306 98 ‐322 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF054490 Screed work @ Corridore area 07/03/11 20/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF053860 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 10/03/11 02/08/11 75 ‐257 81 ‐250 85 ‐266 98 ‐280 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 1 2 3 4 5 COMF052130 Testing & clearance prior to false cei 20/03/11 02/05/11 50 ‐241 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF052860 Suspended Ceiling‐ Wet area 05/04/11 14/08/11 16 ‐225 47 ‐223 50 ‐239 70 ‐258 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF053900 Final Painting works to Tenant Area 09/05/11 20/02/12 0 ‐257 60 ‐257 60 ‐249 60 ‐262 60 ‐289 60 ‐305 60.9 ‐320 60.9 ‐336 60 ‐356 70 ‐353 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF054500 Ceiling Installation  @ Corridore area 10/05/11 08/01/12 0 ‐257 27 ‐239 27 ‐255 27 ‐274 30 ‐286 30 ‐302 60 ‐311 60 ‐326 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF053880 Final Ceiling Tiles install ‐ Tenant Are 11/05/11 03/01/12 0 ‐257 10 ‐257 10 ‐253 20 ‐260 85 ‐283 85 ‐299 85 ‐315 88 ‐332 90 ‐352 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF053870 Floor Trunking & Raised Floor Install 16/06/11 15/08/11 0 ‐257 0 ‐248 35 ‐253 70 ‐260 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF054510 Stone Floor @ Corridore area 30/06/11 13/07/11 0 ‐258 0 ‐249 0 ‐264 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF053910 Ceiling works to lift lobby & bulkhea 24/07/11 08/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐275 70 ‐291 70 ‐306 70 ‐322 95 ‐334 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF054480 MEP final fixes to Tenant Area 08/08/11 25/04/12 0 ‐250 0 ‐250 0 ‐248 0 ‐264 10 ‐288 24 ‐300 24 ‐316 35 ‐330 35 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 1 2 3 4 5 COMF054520 MEP final fixes to lift lobby/Corrid./W 11/09/11 25/04/12 0 ‐250 0 ‐250 0 ‐255 0 ‐269 0 ‐288 6 ‐300 6.1 ‐316 38 ‐330 37 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 1 2 3 4 5 COMF052870 Plumbing Fixture Install & Mirror‐ W 08/11/11 08/01/12 0 ‐225 0 ‐232 0 ‐248 0 ‐268 0 ‐288 0 ‐304 0 ‐320 70 ‐329 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 COMF052880 Threshold & Door Install‐ Wet area 04/12/11 19/02/12 0 ‐225 0 ‐232 0 ‐248 0 ‐268 0 ‐288 0 ‐304 0 ‐320 0 ‐329 30 ‐341 90 ‐354 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF053920 Sliding Door @ Lift Lobby 04/01/12 07/01/12 0 ‐235 0 ‐236 0 ‐252 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF053890 Door Installation ‐ Tenant area 07/01/12 16/01/12 0 ‐252 0 ‐241 0 ‐245 0 ‐254 0 ‐283 0 ‐299 0 ‐314 0 ‐330 0 ‐349 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF053940 Door Installation @Corrid. & Plant R 07/01/12 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF053930 Final Painting/Vinyl wall paper works 11/02/12 16/04/12 0 ‐247 0 ‐243 0 ‐254 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor 2 3 4 5 2 of 7
  • 3. West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green COMF052850 Installation of Cubicle ‐ Wet area 09/04/12 25/04/12 0 ‐225 0 ‐232 0 ‐248 0 ‐268 0 ‐288 0 ‐304 0 ‐320 0 ‐329 0 ‐342 0 ‐354 0 ‐367 0 ‐383 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF059135 Snagging & Keys 30/04/12 15/05/12 0 ‐257 0 ‐256 0 ‐250 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.05 5th Floor M450 C1 O MF 05 5th Floor COMF061910 MEP 2nd fixes 14/01/10 05/12/11 83 ‐253 97 ‐255 99 ‐271 99 ‐288 99 ‐308 99 ‐324 99 ‐339 99 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF063270 Plaster to column & lift lobby 15/04/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF063290 Basecoat Painting works 09/05/10 29/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF063310 Office Fitout (1st & 2nd Fix Trades) 23/05/10 06/04/12 55 ‐257 95 ‐245 95 ‐261 95 ‐278 95 ‐296 95 ‐309 95 ‐315 95 ‐329 95 ‐347 95 ‐361 95 ‐367 95 ‐383 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF062510 Ceramic tiles ‐ Wet area 17/07/10 19/05/11 95 ‐222 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF062710 Stone Work @ lift lobby 28/10/10 18/10/11 87 ‐219 93 ‐235 99 ‐250 99 ‐265 99 ‐275 99 ‐290 99 ‐304 99 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF064440 Screed work @ Corridore area 14/03/11 23/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF063770 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 17/03/11 26/09/11 75 ‐257 81 ‐250 81 ‐266 95 ‐280 98 ‐296 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 1 2 3 4 5 COMF062120 Testing & clearance prior to false cei 21/03/11 04/05/11 30 ‐239 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF062820 Suspended Ceiling‐ Wet area 10/04/11 09/01/12 16 ‐225 47 ‐223 50 ‐239 70 ‐258 85 ‐269 85 ‐285 88 ‐300 88 ‐314 88 ‐329 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF063810 Final Painting works to Tenant Area 12/05/11 20/02/12 0 ‐257 53 ‐257 53 ‐259 53 ‐264 55 ‐289 55 ‐305 55 ‐320 55 ‐336 55 ‐356 70 ‐353 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF063780 Floor Trunking & Raised Floor Install 20/06/11 15/12/11 0 ‐257 0 ‐250 0 ‐266 40 ‐270 80 ‐269 80 ‐296 85 ‐309 85 ‐324 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF064460 Stone Floor @ Corridore area 02/07/11 10/12/11 0 ‐258 0 ‐249 0 ‐264 50 ‐269 50 ‐286 50 ‐302 95 ‐314 98 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF063820 Ceiling works to lift lobby & bulkhea 25/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐257 70 ‐272 70 ‐288 70 ‐304 70 ‐320 95 ‐330 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF064430 MEP final fixes to Tenant Area 07/08/11 01/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐264 10 ‐288 25 ‐300 25 ‐316 35 ‐330 35 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 1 2 3 4 5 COMF063790 Final Ceiling Tiles install ‐ Tenant Are 15/08/11 04/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 55 ‐280 55 ‐299 60 ‐315 65 ‐331 65 ‐351 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF064450 Ceiling Installation  @ Corridore area 27/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 26 ‐286 30 ‐302 60 ‐311 60 ‐326 70 ‐337 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF064470 MEP final fixes to lift lobby/Corrid./W 11/09/11 01/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐269 0 ‐288 6 ‐300 6.1 ‐316 38 ‐330 37 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 1 2 3 4 5 COMF062830 Plumbing Fixture Install & Mirror‐ W 12/11/11 09/01/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 70 ‐328 70 ‐340 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF062840 Threshold & Door Install‐ Wet area 04/12/11 19/02/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 30 ‐340 90 ‐354 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF063800 Door Installation ‐ Tenant area 28/12/11 16/01/12 0 ‐252 0 ‐239 0 ‐255 0 ‐260 0 ‐269 0 ‐294 0 ‐308 0 ‐324 0 ‐345 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF063850 Door Installation @Corrid. & Plant R 02/01/12 31/01/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF063830 Sliding Door @ Lift Lobby 02/01/12 05/01/12 0 ‐236 0 ‐237 0 ‐253 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF063840 Final Painting/Vinyl wall paper works 04/02/12 20/04/12 0 ‐248 0 ‐243 0 ‐255 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor 2 3 4 5 COMF062810 Installation of Cubicle ‐ Wet area 12/04/12 30/04/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 0 ‐342 0 ‐354 0 ‐367 0 ‐383 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF069125 Snagging & Keys 04/05/12 21/05/12 0 ‐257 0 ‐256 0 ‐258 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.06 6th Floor M450 C1 O MF 06 6th Floor COMF071900 MEP 2nd fixes 11/01/10 05/12/11 80 ‐253 90 ‐255 90 ‐271 90 ‐288 90 ‐308 91 ‐324 96 ‐339 96 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF073250 Plaster to column & lift lobby 15/04/10 01/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF073270 Basecoat Painting works 18/05/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF073300 Office Fitout (1st & 2nd Fix Trades) 25/05/10 05/04/12 54 ‐251 95 ‐240 95 ‐256 95 ‐273 95 ‐290 95 ‐306 95.3 ‐313 95.3 ‐327 95 ‐342 95 ‐354 95 ‐360 95 ‐376 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF072500 Ceramic tiles ‐ Wet area 04/10/10 19/05/11 90 ‐222 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF072700 Stone Work @ lift lobby 01/12/10 23/10/11 81 ‐216 87 ‐232 96 ‐248 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF073680 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 10/03/11 27/09/11 59 ‐257 75 ‐250 75 ‐266 83 ‐280 98 ‐296 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 1 2 3 4 5 COMF074390 Screed work @ Corridore area 21/03/11 27/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF072780 Suspended Ceiling‐ Wet area 28/04/11 09/01/12 0 ‐225 47 ‐223 50 ‐239 60 ‐258 80 ‐269 80 ‐285 80 ‐300 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF072110 Testing & clearance prior to false cei 30/04/11 04/05/11 0 ‐237 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF073690 Floor Trunking & Raised Floor Install 22/06/11 09/11/11 0 ‐257 0 ‐250 0 ‐266 55 ‐263 75 ‐270 80 ‐296 85 ‐310 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF074410 Stone Floor @ Corridore area 03/07/11 10/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 97 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF073730 Ceiling works to lift lobby & bulkhea 25/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐258 70 ‐270 70 ‐286 70 ‐302 70 ‐318 90 ‐327 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF073700 Final Ceiling Tiles install ‐ Tenant Are 04/08/11 04/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 30 ‐280 60 ‐299 80 ‐315 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF074380 MEP final fixes to Tenant Area 08/08/11 07/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐264 6 ‐288 24 ‐300 24 ‐316 31 ‐330 31 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 1 2 3 4 5 COMF074400 Ceiling Installation  @ Corridore area 16/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐279 30 ‐294 60 ‐307 60 ‐322 60 ‐334 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF074420 MEP final fixes to lift lobby/Corrid./W 11/09/11 07/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐269 0 ‐288 6 ‐300 6.1 ‐316 35 ‐330 35 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 1 2 3 4 5 COMF072790 Plumbing Fixture Install & Mirror‐ W 12/11/11 09/01/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 70 ‐328 70 ‐342 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF073740 Sliding Door @ Lift Lobby 29/12/11 03/01/12 0 ‐237 0 ‐237 0 ‐253 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF072800 Threshold & Door Install‐ Wet area 29/12/11 19/02/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 0 ‐342 90 ‐354 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF073710 Door Installation ‐ Tenant area 02/01/12 17/01/12 0 ‐252 0 ‐244 0 ‐260 0 ‐257 0 ‐270 0 ‐296 0 ‐310 0 ‐329 0 ‐347 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF073720 Final Painting works to Tenant Area 14/01/12 20/02/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 50 ‐353 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF073760 Door Installation @Corrid. & Plant R 14/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF073750 Final Painting/Vinyl wall paper works 04/02/12 26/04/12 0 ‐249 0 ‐243 0 ‐255 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor 2 3 4 5 COMF072770 Installation of Cubicle ‐ Wet area 17/04/12 03/05/12 0 ‐225 0 ‐231 0 ‐247 0 ‐267 0 ‐287 0 ‐303 0 ‐319 0 ‐328 0 ‐342 0 ‐354 0 ‐367 0 ‐383 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF079115 Snagging & Keys 08/05/12 25/05/12 0 ‐257 0 ‐257 0 ‐266 0 ‐270 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.07 7th Floor M450 C1 O MF 07 7th Floor COMF081890 MEP 2nd fixes 16/01/10 05/12/11 80 ‐253 89 ‐255 90 ‐271 90 ‐288 90 ‐308 91 ‐324 92.8 ‐339 92.8 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF083270 Plaster to column & lift lobby 15/04/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF083290 Office Fitout (1st & 2nd Fix Trades) 29/05/10 06/04/12 54 ‐252 80 ‐246 80 ‐262 80 ‐282 80 ‐299 80 ‐318 80 ‐326 85 ‐332 85 ‐352 90 ‐359 95 ‐361 95 ‐377 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF083310 Basecoat Painting works 12/06/10 02/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF082490 Ceramic tiles ‐ Wet area 11/10/10 03/08/11 90 ‐195 90 ‐210 90 ‐226 98 ‐246 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF082690 Stone Work @ lift lobby 02/12/10 25/10/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF084340 Screed work @ Corridore area 26/03/11 30/03/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF083610 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 15/04/11 10/12/11 9 ‐257 53 ‐250 53 ‐266 75 ‐282 75 ‐299 75 ‐318 98 ‐326 98 ‐332 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 1 2 3 4 5 COMF082740 Suspended Ceiling‐ Wet area 01/05/11 09/01/12 0 ‐225 47 ‐223 50 ‐239 50 ‐258 80 ‐269 80 ‐285 80 ‐300 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF082100 Testing & clearance prior to false cei 03/05/11 09/01/12 0 ‐234 66 ‐231 66 ‐247 66 ‐258 80 ‐267 80 ‐283 80 ‐299 80 ‐315 80 ‐323 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 4 5 COMF084360 Stone Floor @ Corridore area 12/07/11 11/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF083210 Ceiling works to lift lobby & bulkhea 27/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 50 ‐258 70 ‐268 70 ‐284 70 ‐300 70 ‐316 95 ‐323 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF083620 Floor Trunking & Raised Floor Install 28/07/11 14/11/11 0 ‐257 0 ‐250 0 ‐266 10 ‐279 75 ‐272 75 ‐288 80 ‐303 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF084350 Ceiling Installation  @ Corridore area 16/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐274 30 ‐290 60 ‐303 60 ‐318 60 ‐330 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 3 4 5 COMF083630 Final Ceiling Tiles install ‐ Tenant Are 22/08/11 03/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐279 30 ‐280 50 ‐299 75 ‐315 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF084330 MEP final fixes to Tenant Area 06/09/11 11/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐272 0 ‐288 22 ‐300 24 ‐316 31 ‐330 31 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 1 2 3 4 5 COMF084370 MEP final fixes to lift lobby/Corrid./W 12/09/11 11/05/12 0 ‐251 0 ‐250 0 ‐259 0 ‐272 0 ‐288 6 ‐300 6.1 ‐316 35 ‐330 35 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 1 2 3 4 5 COMF082750 Plumbing Fixture Install & Mirror‐ W 14/11/11 09/01/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 70 ‐327 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF083640 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐252 0 ‐244 0 ‐260 0 ‐273 0 ‐272 0 ‐288 0 ‐303 0 ‐316 0 ‐352 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF083220 Sliding Door @ Lift Lobby 29/12/11 03/01/12 0 ‐238 0 ‐238 0 ‐254 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF082760 Threshold & Door Install‐ Wet area 02/01/12 19/02/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐327 0 ‐341 90 ‐353 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF083670 Door Installation @Corrid. & Plant R 07/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF083650 Final Painting works to Tenant Area 15/01/12 03/03/12 0 ‐257 0 ‐257 0 ‐266 0 ‐279 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 50 ‐353 90 ‐354 100 0 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF083660 Final Painting/Vinyl wall paper works 04/02/12 02/05/12 0 ‐250 0 ‐243 0 ‐256 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 2 3 4 5 COMF082730 Installation of Cubicle ‐ Wet area 20/04/12 08/05/12 0 ‐224 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐328 0 ‐342 0 ‐353 0 ‐366 0 ‐382 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor 3 of 7
  • 4. West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green COMF089105 Snagging & Keys 15/05/12 30/05/12 0 ‐257 0 ‐257 0 ‐266 0 ‐278 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.08 8th Floor M450 C1 O MF 08 8th Floor COMF091880 MEP 2nd fixes 21/01/10 06/12/11 80 ‐253 85 ‐255 85 ‐271 85 ‐288 85 ‐308 90 ‐324 91.9 ‐339 91.9 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF093250 Plaster to column & lift lobby 15/04/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF093280 Office Fitout (1st & 2nd Fix Trades) 31/05/10 06/04/12 54 ‐249 89 ‐240 90 ‐256 90 ‐273 90 ‐291 90 ‐310 90 ‐317 90 ‐327 90 ‐345 90 ‐356 95 ‐357 95 ‐373 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF093270 Basecoat Painting works 19/06/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF092480 Ceramic tiles ‐ Wet area 14/10/10 26/11/11 90 ‐219 90 ‐220 92 ‐236 92 ‐253 95 ‐273 95 ‐289 98 ‐304 98 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF092680 Stone Work @ lift lobby 04/12/10 01/11/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF094290 Screed work @ Corridore area 29/03/11 04/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF092090 Testing & clearance prior to false cei 03/05/11 09/01/12 0 ‐231 50 ‐229 50 ‐245 50 ‐257 50 ‐267 80 ‐281 80 ‐296 80 ‐312 80 ‐321 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF092700 Suspended Ceiling‐ Wet area 08/05/11 09/01/12 0 ‐225 47 ‐223 50 ‐239 55 ‐258 70 ‐269 70 ‐285 70 ‐300 70 ‐314 70 ‐329 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF093550 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 10/05/11 01/10/11 0 ‐257 6 ‐252 40 ‐266 60 ‐282 90 ‐299 95 ‐318 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF094310 Stone Floor @ Corridore area 11/07/11 11/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF093180 Ceiling works to lift lobby & bulkhea 26/07/11 09/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐257 70 ‐267 70 ‐282 70 ‐298 70 ‐314 80 ‐321 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF093560 Floor Trunking & Raised Floor Install 15/08/11 14/11/11 0 ‐257 0 ‐252 0 ‐266 0 ‐282 50 ‐286 75 ‐288 85 ‐317 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF094300 Ceiling Installation  @ Corridore area 27/08/11 09/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐270 30 ‐286 60 ‐299 60 ‐314 60 ‐327 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 3 4 5 COMF093570 Final Ceiling Tiles install ‐ Tenant Are 03/09/11 03/01/12 0 ‐257 0 ‐257 0 ‐266 0 ‐282 0 ‐286 60 ‐299 85 ‐315 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF094320 MEP final fixes to lift lobby/Corrid./W 12/09/11 17/05/12 0 ‐252 0 ‐250 0 ‐259 0 ‐275 0 ‐288 6 ‐300 6.1 ‐316 24 ‐330 24 ‐350 90 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 1 2 3 4 5 COMF094280 MEP final fixes to Tenant Area 17/09/11 17/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐275 0 ‐288 22 ‐300 24 ‐316 31 ‐330 31 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 1 2 3 4 5 COMF092710 Plumbing Fixture Install & Mirror‐ W 14/11/11 09/01/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 70 ‐327 70 ‐341 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF093580 Door Installation ‐ Tenant area 27/12/11 17/01/12 0 ‐252 0 ‐246 0 ‐260 0 ‐276 0 ‐280 0 ‐288 0 ‐317 0 ‐332 0 ‐349 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF093190 Sliding Door @ Lift Lobby 29/12/11 05/01/12 0 ‐239 0 ‐239 0 ‐255 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF093200 Door Installation @Corrid. & Plant R 08/01/12 02/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF092720 Threshold & Door Install‐ Wet area 14/01/12 20/02/12 0 ‐225 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐327 0 ‐341 90 ‐352 100 0 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF093590 Final Painting works to Tenant Area 15/01/12 04/03/12 0 ‐257 0 ‐257 0 ‐266 0 ‐282 0 ‐289 0 ‐305 0 ‐320 0 ‐336 0 ‐356 50 ‐353 90 ‐354 100 0 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF093600 Final Painting/Vinyl wall paper works 05/02/12 08/05/12 0 ‐250 0 ‐243 0 ‐257 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor 2 3 4 5 COMF092690 Installation of Cubicle ‐ Wet area 25/04/12 11/05/12 0 ‐223 0 ‐230 0 ‐246 0 ‐266 0 ‐286 0 ‐302 0 ‐318 0 ‐328 0 ‐342 0 ‐352 0 ‐365 0 ‐381 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF099095 Snagging & Keys 18/05/12 05/06/12 0 ‐257 0 ‐257 0 ‐266 0 ‐282 0 ‐290 0 ‐306 0 ‐322 0 ‐336 0 ‐356 0 ‐357 0 ‐369 0 ‐385 M450.C1.O.MF.09 9th Floor M450 C1 O MF 09 9th Floor COMF021150 2nd Floor 14/11/09 06/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF031160 3rd Floor 25/11/09 07/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF041170 4th Floor 06/12/09 17/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF051180 5th Floor 19/12/09 27/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF061190 6th Floor 06/01/10 29/03/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF071200 7th Floor 17/01/10 04/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF081210 8th Floor 03/02/10 08/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF091220 9th Floor 09/02/10 10/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF101230 10th Floor 14/02/10 13/04/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF111410 11th Floor 24/02/10 03/05/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMFMZ1040 Mezzanine Floor 01/03/10 10/07/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF121420 12th Floor 08/03/10 10/05/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMFGF1030 Ground Floor 13/03/10 10/07/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF131600 13th Floor 21/03/10 20/05/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF141780 14th Floor 07/04/10 24/07/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF151040 15th Floor 18/04/10 05/09/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF161050 16th Floor 06/05/10 25/09/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.1 Blockwork ParM450 C1 O MF 1 Blockwork Partitions COMF101870 MEP 2nd fixes 23/01/10 06/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 90 ‐324 91.9 ‐339 91.9 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5 COMF103250 Plaster to column & lift lobby 15/04/10 16/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF103270 Office Fitout (1st & 2nd Fix Trades) 01/06/10 13/04/12 50 ‐246 80 ‐237 80 ‐253 80 ‐273 80 ‐293 85 ‐309 85 ‐319 85 ‐329 85 ‐348 90 ‐353 90 ‐358 90 ‐374 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5 COMF103290 Basecoat Painting works 26/06/10 07/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF102470 Ceramic tiles ‐ Wet area 17/10/10 26/11/11 90 ‐215 90 ‐217 90 ‐233 92 ‐250 92 ‐270 92 ‐286 92 ‐301 92 ‐315 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF102670 Stone Work @ lift lobby 05/12/10 02/11/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5 COMF104240 Screed work @ Corridore area 02/04/11 07/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF102080 Testing & clearance prior to false cei 03/05/11 09/01/12 0 ‐228 66 ‐226 66 ‐242 66 ‐256 80 ‐263 80 ‐279 80 ‐295 80 ‐311 80 ‐317 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 4 5 COMF102620 Suspended Ceiling‐ Wet area 03/05/11 10/01/12 0 ‐222 50 ‐221 50 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 3 4 5 COMF103490 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 27/05/11 27/09/11 0 ‐255 0 ‐249 40 ‐263 40 ‐279 70 ‐299 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5 COMF104260 Stone Floor @ Corridore area 11/07/11 12/12/11 0 ‐258 0 ‐249 0 ‐264 60 ‐269 60 ‐286 95 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5 COMF103150 Ceiling works to lift lobby & bulkhea 26/07/11 14/01/12 0 ‐244 0 ‐245 0 ‐261 70 ‐257 70 ‐264 70 ‐280 70 ‐296 70 ‐312 80 ‐317 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF104250 Ceiling Installation  @ Corridore area 28/08/11 10/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 26 ‐270 30 ‐281 60 ‐295 60 ‐310 60 ‐324 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF103500 Floor Trunking & Raised Floor Install 30/08/11 03/01/12 0 ‐255 0 ‐249 0 ‐263 0 ‐279 5 ‐298 45 ‐314 60 ‐319 75 ‐326 85 ‐340 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5 COMF104270 MEP final fixes to lift lobby/Corrid./W 12/09/11 23/05/12 0 ‐253 0 ‐250 0 ‐259 0 ‐275 0 ‐293 2 ‐312 2.44 ‐318 21 ‐330 20 ‐350 75 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 1 2 3 4 5 COMF103510 Final Ceiling Tiles install ‐ Tenant Are 17/09/11 21/01/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 40 ‐314 60 ‐318 70 ‐331 70 ‐351 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 1 2 3 4 5 COMF104230 MEP final fixes to Tenant Area 01/10/11 23/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐275 0 ‐293 0 ‐312 12 ‐318 23 ‐330 23 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 1 2 3 4 5 COMF142670 Plumbing Fixture Install & Mirror‐ W 15/11/11 10/01/12 0 ‐222 0 ‐226 0 ‐242 0 ‐262 0 ‐282 0 ‐298 0 ‐314 70 ‐323 70 ‐337 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5 COMF103160 Sliding Door @ Lift Lobby 28/12/11 04/01/12 0 ‐239 0 ‐240 0 ‐256 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF103520 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐249 0 ‐243 0 ‐258 0 ‐274 0 ‐292 0 ‐311 0 ‐319 0 ‐326 0 ‐340 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF102680 Threshold & Door Install‐ Wet area 02/01/12 20/02/12 0 ‐222 0 ‐226 0 ‐242 0 ‐262 0 ‐282 0 ‐298 0 ‐314 0 ‐323 0 ‐337 90 ‐349 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF103170 Door Installation @Corrid. & Plant R 09/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF103530 Final Painting works to Tenant Area 15/01/12 04/03/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 55 ‐350 90 ‐351 100 0 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5 COMF103540 Final Painting/Vinyl wall paper works 05/02/12 14/05/12 0 ‐251 0 ‐243 0 ‐258 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor 2 3 4 5 COMF102610 Installation of Cubicle ‐ Wet area 30/04/12 16/05/12 0 ‐220 0 ‐226 0 ‐242 0 ‐262 0 ‐282 0 ‐298 0 ‐314 0 ‐328 0 ‐342 0 ‐349 0 ‐362 0 ‐378 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF109085 Snagging & Keys 24/05/12 11/06/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.10 10th Floor M450 C1 O MF 10 10th Floor COMF111860 MEP 2nd fixes 01/03/10 06/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 90 ‐324 90.3 ‐339 90.8 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 COMF113250 Plaster to column & lift lobby 02/05/10 08/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF113260 Office Fitout (1st & 2nd Fix Trades) 02/06/10 13/04/12 50 ‐243 80 ‐236 80 ‐252 80 ‐270 80 ‐290 80 ‐311 80 ‐322 80 ‐332 80 ‐352 90 ‐350 90 ‐355 90 ‐371 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 COMF113275 Basecoat Painting works 03/07/10 08/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF112460 Ceramic tiles ‐ Wet area 21/10/10 27/11/11 90 ‐215 90 ‐216 90 ‐232 95 ‐249 98 ‐268 98 ‐284 98 ‐300 98 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF112660 Stone Work @ lift lobby 06/12/10 05/11/11 80 ‐213 87 ‐229 96 ‐245 98 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 COMF114190 Screed work @ Corridore area 05/04/11 11/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF112580 Suspended Ceiling‐ Wet area 04/05/11 10/01/12 0 ‐222 47 ‐221 20 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 90 ‐329 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 3 4 5 COMF112070 Testing & clearance prior to false cei 09/05/11 09/01/12 0 ‐226 40 ‐225 40 ‐241 40 ‐258 80 ‐262 80 ‐278 80 ‐293 80 ‐309 80 ‐312 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 4 of 7
  • 5. West Building  ‐ Block 5 ‐ M340 to M460 Update Programmes ‐ Most Critical In Red and Critical within 20 days in Green COMF113430 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 29/05/11 13/09/11 0 ‐255 0 ‐249 35 ‐263 55 ‐279 98 ‐299 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 COMF114210 Stone Floor @ Corridore area 10/07/11 12/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 COMF113120 Ceiling works to lift lobby & bulkhea 02/08/11 16/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐258 70 ‐262 70 ‐278 70 ‐294 70 ‐310 90 ‐312 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF114200 Ceiling Installation  @ Corridore area 17/08/11 10/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 30 ‐268 30 ‐278 60 ‐291 60 ‐306 60 ‐321 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 4 5 COMF113440 Floor Trunking & Raised Floor Install 31/08/11 21/11/11 0 ‐255 0 ‐249 0 ‐263 0 ‐279 5 ‐298 45 ‐309 55 ‐318 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 1 2 3 4 5 COMF113450 Final Ceiling Tiles install ‐ Tenant Are 12/09/11 28/01/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 50 ‐314 85 ‐318 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 COMF114220 MEP final fixes to lift lobby/Corrid./W 12/09/11 29/05/12 0 ‐254 0 ‐250 0 ‐260 0 ‐275 0 ‐293 2 ‐312 2.44 ‐318 21 ‐330 20 ‐350 75 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 1 2 3 4 5 COMF114180 MEP final fixes to Tenant Area 02/10/11 29/05/12 0 ‐250 0 ‐250 0 ‐259 0 ‐275 0 ‐293 0 ‐312 14 ‐318 23 ‐330 23 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 1 2 3 4 5 COMF112590 Plumbing Fixture Install & Mirror‐ W 15/11/11 11/01/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 35 ‐326 70 ‐335 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 COMF112600 Threshold & Door Install‐ Wet area 17/12/11 20/02/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐326 30 ‐335 95 ‐348 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF113460 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐249 0 ‐243 0 ‐258 0 ‐274 0 ‐292 0 ‐308 0 ‐318 0 ‐324 0 ‐344 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF113130 Sliding Door @ Lift Lobby 29/12/11 05/01/12 0 ‐240 0 ‐241 0 ‐257 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF113140 Door Installation @Corrid. & Plant R 10/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐306 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF113470 Final Painting works to Tenant Area 16/01/12 05/03/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 45 ‐350 85 ‐351 100 0 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 COMF113480 Final Painting/Vinyl wall paper works 05/02/12 18/05/12 0 ‐252 0 ‐243 0 ‐259 0 ‐269 0 ‐287 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor 2 3 4 5 COMF112570 Installation of Cubicle ‐ Wet area 03/05/12 21/05/12 0 ‐219 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐328 0 ‐342 0 ‐348 0 ‐361 0 ‐377 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF119075 Snagging & Keys 30/05/12 15/06/12 0 ‐255 0 ‐254 0 ‐263 0 ‐279 0 ‐298 0 ‐311 0 ‐319 0 ‐334 0 ‐354 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.11 11th Floor M450 C1 O MF 11 11th Floor COMF121850 MEP 2nd fixes 22/03/10 07/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 90 ‐324 90.3 ‐339 90.8 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5 COMF123255 Plaster to column & lift lobby 04/05/10 30/11/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF123250 Office Fitout (1st & 2nd Fix Trades) 03/06/10 13/04/12 34 ‐254 80 ‐235 80 ‐251 80 ‐268 80 ‐288 80 ‐313 80 ‐324 80 ‐334 80 ‐352 90 ‐346 90 ‐355 90 ‐371 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 1 2 3 4 5 COMF123280 Basecoat Painting works 10/07/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF122450 Ceramic tiles ‐ Wet area 26/10/10 27/11/11 90 ‐214 90 ‐215 90 ‐231 92 ‐248 95 ‐268 95 ‐284 95 ‐299 95 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF122650 Stone Work @ lift lobby 08/12/10 07/11/11 80 ‐213 80 ‐229 94 ‐245 95 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5 COMF124140 Screed work @ Corridore area 06/04/11 12/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF122060 Testing & clearance prior to false cei 04/05/11 09/01/12 0 ‐224 66 ‐221 66 ‐237 66 ‐254 80 ‐260 80 ‐276 80 ‐291 80 ‐307 80 ‐311 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF122530 Suspended Ceiling‐ Wet area 04/05/11 10/01/12 0 ‐222 16 ‐221 16 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 3 4 5 COMF123370 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 13/06/11 28/09/11 0 ‐255 0 ‐251 10 ‐264 20 ‐279 98 ‐299 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5 COMF124160 Stone Floor @ Corridore area 11/07/11 13/12/11 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5 COMF123090 Ceiling works to lift lobby & bulkhea 03/08/11 29/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐258 70 ‐260 70 ‐276 70 ‐292 70 ‐308 70 ‐311 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF124150 Ceiling Installation  @ Corridore area 30/08/11 10/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 15 ‐267 30 ‐274 60 ‐287 60 ‐302 60 ‐318 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 4 5 COMF124170 MEP final fixes to lift lobby/Corrid./W 13/09/11 04/06/12 0 ‐254 0 ‐250 0 ‐261 0 ‐275 0 ‐295 2 ‐317 2.44 ‐325 19 ‐330 19 ‐350 70 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 1 2 3 4 5 COMF123390 Final Ceiling Tiles install ‐ Tenant Are 24/09/11 29/01/12 0 ‐255 0 ‐254 0 ‐264 0 ‐279 0 ‐299 85 ‐314 85 ‐320 85 ‐331 85 ‐351 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5 COMF123380 Floor Trunking & Raised Floor Install 27/09/11 03/01/12 0 ‐255 0 ‐251 0 ‐264 0 ‐279 0 ‐299 10 ‐317 20 ‐326 80 ‐321 90 ‐336 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5 COMF124130 MEP final fixes to Tenant Area 16/10/11 04/06/12 0 ‐250 0 ‐250 0 ‐260 0 ‐275 0 ‐295 0 ‐317 10 ‐325 21 ‐330 21 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 1 2 3 4 5 COMF122540 Plumbing Fixture Install & Mirror‐ W 15/11/11 11/01/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 20 ‐327 60 ‐337 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5 COMF123100 Sliding Door @ Lift Lobby 27/12/11 04/01/12 0 ‐241 0 ‐241 0 ‐257 0 ‐255 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF123400 Door Installation ‐ Tenant area 29/12/11 17/01/12 0 ‐249 0 ‐246 0 ‐259 0 ‐274 0 ‐294 0 ‐316 0 ‐326 0 ‐321 0 ‐336 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF122550 Threshold & Door Install‐ Wet area 29/12/11 20/02/12 0 ‐222 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐327 0 ‐337 90 ‐347 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF123110 Door Installation @Corrid. & Plant R 10/01/12 01/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐309 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF123410 Final Painting works to Tenant Area 17/01/12 24/04/12 0 ‐255 0 ‐254 0 ‐264 0 ‐279 0 ‐299 0 ‐316 0 ‐326 0 ‐334 0 ‐354 40 ‐350 85 ‐351 90 ‐358 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5 COMF123420 Final Painting/Vinyl wall paper works 11/02/12 24/05/12 0 ‐253 0 ‐244 0 ‐259 0 ‐269 0 ‐288 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor 2 3 4 5 COMF122520 Installation of Cubicle ‐ Wet area 08/05/12 24/05/12 0 ‐218 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐328 0 ‐342 0 ‐347 0 ‐361 0 ‐377 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF129065 Snagging & Keys 05/06/12 21/06/12 0 ‐255 0 ‐254 0 ‐264 0 ‐279 0 ‐299 0 ‐316 0 ‐326 0 ‐335 0 ‐354 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.12 12th Floor M450 C1 O MF 12 12th Floor COMF131840 MEP 2nd fixes 23/03/10 07/12/11 80 ‐253 80 ‐255 80 ‐271 80 ‐288 80 ‐308 89 ‐324 89.9 ‐339 90.2 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5 COMF133270 Plaster to column & lift lobby 02/05/10 28/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF133240 Office Fitout (1st & 2nd Fix Trades) 12/06/10 13/04/12 34 ‐250 72 ‐235 73 ‐251 75 ‐268 75 ‐288 80 ‐304 80 ‐323 80 ‐336 80 ‐352 80 ‐352 90 ‐355 90 ‐371 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5 COMF132440 Ceramic tiles ‐ Wet area 28/10/10 28/11/11 90 ‐214 90 ‐215 90 ‐231 92 ‐248 95 ‐268 95 ‐284 95 ‐299 95 ‐314 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF132640 Stone Work @ lift lobby 14/03/11 09/11/11 34 ‐213 75 ‐229 94 ‐245 96 ‐265 98 ‐275 98 ‐290 98 ‐304 98 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5 COMF134080 Screed work @ Corridore area 07/04/11 13/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF132050 Testing & clearance prior to false cei 05/05/11 14/01/12 0 ‐221 60 ‐219 60 ‐235 60 ‐252 60 ‐262 60 ‐278 60 ‐291 70 ‐306 70 ‐308 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF132490 Suspended Ceiling‐ Wet area 02/07/11 21/01/12 0 ‐222 0 ‐221 0 ‐237 60 ‐255 80 ‐266 80 ‐282 80 ‐298 80 ‐314 80 ‐329 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 3 4 5 COMF134100 Stone Floor @ Corridore area 13/07/11 13/12/11 0 ‐258 0 ‐249 0 ‐264 50 ‐269 55 ‐286 55 ‐302 80 ‐314 95 ‐330 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5 COMF133060 Ceiling works to lift lobby & bulkhea 04/08/11 22/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 70 ‐275 70 ‐290 70 ‐304 70 ‐320 70 ‐308 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF133280 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 08/08/11 16/10/11 0 ‐255 0 ‐251 0 ‐267 0 ‐284 90 ‐299 95 ‐307 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF134090 Ceiling Installation  @ Corridore area 06/09/11 11/01/12 0 ‐257 0 ‐238 0 ‐254 0 ‐274 0 ‐267 30 ‐273 60 ‐285 60 ‐298 60 ‐315 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 4 5 COMF134110 MEP final fixes to lift lobby/Corrid./W 13/09/11 08/06/12 0 ‐255 0 ‐250 0 ‐262 0 ‐279 0 ‐295 2 ‐317 2.44 ‐325 11 ‐331 10 ‐350 70 ‐361 90 ‐375 97 ‐390 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 1 2 3 4 5 COMF133340 Final Ceiling Tiles install ‐ Tenant Are 01/10/11 18/02/12 0 ‐255 0 ‐254 0 ‐267 0 ‐284 0 ‐299 0 ‐309 80 ‐319 80 ‐330 80 ‐350 98 ‐352 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5 COMF133310 Floor Trunking & Raised Floor Install 02/10/11 14/01/12 0 ‐255 0 ‐251 0 ‐267 0 ‐284 0 ‐299 0 ‐307 20 ‐323 43 ‐332 65 ‐341 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5 COMF134120 MEP final fixes to Tenant Area 17/10/11 08/06/12 0 ‐250 0 ‐250 0 ‐262 0 ‐279 0 ‐295 0 ‐317 10 ‐325 10 ‐331 10 ‐350 90 ‐360 90 ‐375 90 ‐390 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 1 2 3 4 5 COMF132500 Plumbing Fixture Install & Mirror‐ W 21/11/11 11/01/12 0 ‐222 0 ‐224 0 ‐240 0 ‐260 0 ‐280 0 ‐296 0 ‐312 20 ‐326 60 ‐336 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5 COMF133350 Door Installation ‐ Tenant area 27/12/11 22/01/12 0 ‐249 0 ‐246 0 ‐261 0 ‐278 0 ‐294 0 ‐302 0 ‐323 0 ‐332 0 ‐341 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF133070 Sliding Door @ Lift Lobby 29/12/11 04/01/12 0 ‐242 0 ‐242 0 ‐258 0 ‐262 0 ‐275 0 ‐291 0 ‐306 0 ‐322 0 ‐334 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF132510 Threshold & Door Install‐ Wet area 29/12/11 20/02/12 0 ‐222 0 ‐224 0 ‐240 0 ‐260 0 ‐280 0 ‐296 0 ‐312 0 ‐326 0 ‐336 90 ‐346 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF133080 Door Installation @Corrid. & Plant R 11/01/12 02/02/12 0 ‐249 0 ‐249 0 ‐256 0 ‐273 0 ‐292 0 ‐309 0 ‐322 0 ‐338 0 ‐357 100 0 100 0 100 0 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF133360 Final Painting works to Tenant Area 17/01/12 27/04/12 0 ‐255 0 ‐254 0 ‐267 0 ‐284 0 ‐299 0 ‐316 0 ‐325 0 ‐334 0 ‐354 35 ‐350 85 ‐351 90 ‐358 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5 COMF133330 Final Painting/Vinyl wall paper works 12/02/12 30/05/12 0 ‐254 0 ‐245 0 ‐260 0 ‐272 0 ‐288 0 ‐298 0 ‐314 0 ‐330 0 ‐346 0 ‐361 80 ‐370 80 ‐384 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor 2 3 4 5 COMF132480 Installation of Cubicle ‐ Wet area 11/05/12 29/05/12 0 ‐218 0 ‐225 0 ‐241 0 ‐261 0 ‐281 0 ‐297 0 ‐313 0 ‐328 0 ‐342 0 ‐347 0 ‐361 0 ‐377 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF139055 Snagging & Keys 11/06/12 27/06/12 0 ‐255 0 ‐254 0 ‐267 0 ‐284 0 ‐299 0 ‐316 0 ‐326 0 ‐335 0 ‐355 0 ‐355 0 ‐367 0 ‐383 M450.C1.O.MF.13 13th Floor M450 C1 O MF 13 13th Floor COMF141830 MEP 2nd fixes 24/03/10 07/12/11 77 ‐253 79 ‐255 80 ‐271 80 ‐288 80 ‐308 83 ‐324 84.1 ‐339 84.1 ‐355 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 2 3 4 5 COMF143290 Plaster to column & lift lobby 02/05/10 01/12/10 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor COMF143230 Office Fitout (1st & 2nd Fix Trades) 14/06/10 13/04/12 47 ‐236 80 ‐234 80 ‐250 80 ‐267 80 ‐287 80 ‐303 80 ‐318 80 ‐338 80 ‐352 80 ‐348 90 ‐355 90 ‐371 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 1 2 3 4 5 COMF142430 Ceramic tiles ‐ Wet area 02/11/10 28/11/11 90 ‐212 90 ‐214 90 ‐230 92 ‐246 95 ‐266 95 ‐282 95 ‐298 95 ‐313 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor COMF142630 Stone Work @ lift lobby 20/03/11 12/11/11 34 ‐213 83 ‐229 90 ‐245 95 ‐265 95 ‐275 95 ‐290 95 ‐304 95 ‐320 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 2 3 4 5 COMF144050 Screed work @ Corridore area 09/04/11 14/04/11 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor COMF142040 Testing & clearance prior to false cei 03/05/11 15/01/12 0 ‐219 33 ‐218 40 ‐234 40 ‐251 40 ‐266 40 ‐281 40 ‐295 70 ‐308 70 ‐307 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor COMF144070 Stone Floor @ Corridore area 11/07/11 11/01/12 0 ‐258 0 ‐249 0 ‐264 80 ‐269 90 ‐286 90 ‐302 95 ‐314 95 ‐330 95 ‐314 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 2 3 4 5 COMF142450 Suspended Ceiling‐ Wet area 27/07/11 22/01/12 0 ‐222 0 ‐221 0 ‐237 41 ‐255 60 ‐266 70 ‐282 70 ‐298 70 ‐314 70 ‐329 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 3 4 5 COMF143030 Ceiling works to lift lobby & bulkhea 09/08/11 22/01/12 0 ‐244 0 ‐245 0 ‐261 0 ‐265 70 ‐267 70 ‐282 70 ‐296 70 ‐311 70 ‐307 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor COMF143240 Ceiling Grid & Gyp. Bulkhead ‐ Tenan 21/08/11 16/11/11 0 ‐255 0 ‐252 0 ‐268 0 ‐285 70 ‐299 95 ‐307 98 ‐318 100 0 100 0 100 0 100 0 100 0 M450.C1.O.MF.14 14th Floor M450 C1 O MF 14 14th Floor 1 2 3 4 5 5 of 7