SlideShare a Scribd company logo
1 of 4
Download to read offline
VELOCITY—a powerful business approach combining speed with direction—consists of three pillars: Theory
of Constraints, the system architecture; Theory of Constraints Lean Six Sigma (TOCLSS), the focused improvement
process; and SDAIS (Strategy-Design-Activate-Improve-Sustain), the deployment framework. 
Background
Although  they  had  made  significant 
improvements,  Republic  still  had  a  dark  secret 
they  only  whispered  about—their  on‐time 
delivery percentage for make‐to‐order jobs. Prior 
to their experience with AGI – Goldratt Institute, 
they didnʹt even distinguish their work between 
make‐to‐order  and  make‐to‐stock.  On‐time 
performance  wasnʹt  measured,  since  they  only 
made  delivery  promises  when  absolutely 
required, and unfortunately, they had a mediocre 
record of keeping them. 
However,  following  their  strategic  analysis  and 
after activating a constraint‐based design of their 
new  operations  management  process,  Republic 
was more reliable and able to produce at a much 
faster  rate.  Overall,  they  were  turning  their 
products  22  days  (36%)  faster  with  little  capital 
investment.  Their  new  design  prioritized  work 
based  on  the  number  of  days  an  item  had  been 
waiting  at  a  workstation,  because  their  analysis 
had revealed that many items were in queue up 
to  30  days  to  become  the  next  job,  only  to  get 
pushed back by a ʺhigherʺ priority. Therefore, to 
reduce the queue time for work‐in‐process (WIP), 
and  consequently  reduce  the  total  volume  of 
WIP,  they  had  established  a  scheduling  priority 
rule based exclusively on the number of days in 
queue.  They  also  used  a  drum  buffer‐rope 
decision process to gate the release of new work 
to  avoid  adding  more  WIP  than  the  system 
constraints  could  handle.  Activating  this  design 
stabilized  the  system  sufficiently  to  achieve 
significant  improvement  (see  Republic  Industries 
International:  Part  II—Understanding  Throughput). 
Even so, to be honest, their delivery performance 
was still poor with only 69% of their jobs being 
completed on time or early. 
VELOCITY and Focused System
Improvement
Integral to the VELOCITY approach are cycles of 
Focused  System  Improvement  as  organizations 
continue  to  monitor  performance  and  seek 
ongoing positive impact on their strategic results. 
Because  their  system  design  was  sufficient  to 
stabilize  their  systemʹs  performance,  Republic 
recognized they had to focus even more on work 
scheduling. They still had problems determining 
realistic  delivery  times  for  their  clients.  When 
specific  delivery  dates  were  required  to  exploit 
new  opportunities,  production  scheduling  was 
nearly  impossible  to  manage  as  they  had  little 
control over when a job would be worked next. 
Republicʹs Director of Supply Chain Management  
Republic Industries International
Part III—Improving Delivery Performance
Established in 1911, Republic Industries International repairs and produces large metal compo‐
nents supporting customers in the industrial and mining sectors. They also provide engineering 
services to develop unique solutions to meet customers’ needs. Based in Louisville, Kentucky, 
Republic operates as a make‐to‐order and make‐to‐stock company with about 100 employees. 
www.goldratt.com
Page 2 of 4
was  spending  a  great  deal  of  time  manually 
updating queue lists as he attempted to manage 
scheduling priorities.  
Under  pressure  to  resolve  this  issue,  Republicʹs 
scheduling  committee  modified  their  design  to 
use  scheduled  due  dates  as  the  determining 
factor  to  manage  job  priorities.  That  approach 
seemed  reasonable—they  believed  all  they 
needed  to  do  was  advance  a  jobʹs  due  date  to 
move  it  up  in  priority  on  the  daily  work  lists. 
Activating  this  design  change  did  relieve  some 
stress in scheduling; however, while the sequence 
of completed jobsʹ may have changed, the overall 
on‐time results did not. The same number of jobs 
still  ran  late.  Why  didnʹt  they  achieve  the 
expected improvement? 
Understanding the problem
In retrospect, the problems with using scheduled 
due  dates  became  pretty  clear.  Within  their 
system, the make‐to‐order jobs had unique work 
flows. Some of them required lengthy external or 
internal processes. Therefore, the greater amount 
of work to be done resulted in longer lead times. 
To  simplify  their  scheduling,  they  had  assigned 
all  the  make‐to‐stock  jobs  a  standardized  lead 
time  sufficient  to  cover  the  expected  work 
required. So items with due dates further in the 
future  (based  on  longer  lead  times)  might 
initially  sit  for  weeks,  while  items  with  earlier 
due dates received priority. To work around the 
disparity  in  lead  times,  on  occasion,  the 
schedulers  would  use  fake  due  dates  to  re‐
prioritize  a  job,  resulting  in  tremendous 
confusion about whether a job was actually late 
or  just  ʺfakeʺ  late.  Essentially,  the  due  dates  in 
their information system became more and more 
fictional, and despite their scheduling emphasis, 
they lacked credibility and meaning. 
Moreover,  both  this  design  and  the  previous 
design  had  a  common  flaw—Republic  never 
seemed to know a job was in jeopardy of being 
overdue until it was too late. They were using the 
classic  buffer  management  approach—Green, 
Yellow,  Red—to  monitor  a  jobʹs  progress 
compared  to  its  associated  ʺtime‐to‐reliably 
replenishʺ  (TRR).  However,  as  jobs  neared 
completion, their reports frequently showed their 
status as  `yellowʹ  (needs  review)  or  `redʹ  (needs 
intervention).  With  so  many  jobs  needing 
attention,  the  buffers  failed  to  motivate  the 
proper  actions.  Supervisors  were  already  too 
busy responding to the daily crises of whichever 
jobs, for whatever reasons, were the urgent fires 
to  be  dealt  with  that  day.  By  that  point,  they 
could  do  little  to  achieve  an  on‐time  delivery. 
Instead,  they  focused  their  expediting  efforts  to 
make items ʺless late.ʺ
Frequently their sales staff called asking when a 
job  would  be  finished,  despite  the  job  having  a 
specified due date. Research often found some of 
those  jobs  stuck  in  queues  despite  their  specific 
efforts  to  reduce  queue  times!  These  failures  to 
deliver on time jeopardized all the gains of their 
earlier  improvements,  especially  if  Republic 
became known as an unreliable vendor. The need 
was clear. Their next system improvement had to 
focus  on  work  priorities  and  scheduling  to 
reliably deliver on time. 
Buffer Management and Scheduling
To  improve  performance  in  TOC‐based  system 
designs,  managers  use  buffer  management  to 
prioritize  work,  to  know  when  to  expedite,  to 
identify  where  capacity  is  insufficient,  and  to 
adjust buffer sizes. Until this point, Republic had 
only really used quantity buffers to protect some 
inventory levels. When they described their latest 
www.goldratt.com
Page 3 of 4
problems,  AGI  proposed  an  evaluation  of  their 
new  generation  (GEN2)  buffer  management 
approach  in  their  MANAGE  Capability  of  the 
SUPPLY CHAIN Suite®
.  Although  Republic 
found  the  advanced  concepts  behind  the  ap‐
proach  somewhat  difficult  to  understand,  they 
found  the  logic  of  the  approach  to  be  very 
compelling. 
Republic  translated  their  data  to  the  format 
required by AGIʹs software. Their Supply Chain 
Management Director logged in to the MANAGE 
Capability for the first time. For all its conceptual 
complexity, he was initially underwhelmed that, 
with  just  a  few  screens,  it  would  be  possible  to 
manage  all  of  their  operations.  ʺYeah  right,ʺ  he 
thought skeptically. He believed:
Republicʹs  work  is  difficult  to  manage 
because  our  constraint  changes  when  we 
have a significant change in our workload. 
One  large  job  can  shift  the  constraint, 
making  all  the  previous  scheduling  work 
obsolete. In addition, we work a variety of 
scheduling  shifts—eight  in  total.  To 
complicate  things  further,  we  typically  do 
not  run  out  of  machines,  but  rather 
employees  who  can  run  specific  machines. 
We  have  a  flexible  work  force  and  daily 
tactical  decisions  determine  where  each 
person  works  during  a  shift.  Some 
machines are ʺunmannedʺ for days waiting 
for  the  first  available  skilled  operator  to 
finish  previous  jobs.  These  factors, 
combined  with  the  variability  of  the  jobs 
themselves, contribute to our poor on‐time 
performance. 
Very shortly after activation, the new MANAGE 
Capability was put to the test. With the economic 
downturn,  reduced  demand  forced  Republic  to 
proactively  seek  more  work.  They  succeeded  in 
being  awarded  a  significant  new  job  that  was 
atypical  because  it  contained  70  more 
components  than  other  jobs  in  its  throughput 
range.  And  it  had  a  must‐hit  due  date.  The 
director  loaded  their  system  with  all  the 
necessary  data.  When  he  reviewed  the 
information  provided  by  the  MANAGE 
Capability, in a job of more than 80 sub‐jobs, he 
was amazed to see clearly that just two identical 
sub‐jobs  were  key  to  the  overall  success.  Previ‐
ously,  he  would  never  have  been  able  to 
determine the critical elements of a job this size. 
To  take  all  these  sub‐jobs  across  the  factors 
discussed  above  was  simply  impractical.  In  the 
past, Republic would have picked the most labor‐
intense  sub‐job  as  their  focus  for  monitoring.  In 
addition,  because  they  didnʹt  have  a  system 
perspective,  they  would  have  started  work  as 
early  as  they  could  on  as  many  sub‐jobs  as 
possible. Their thinking was the earlier each sub‐
job was completed, the earlier they could proceed 
to  final  assembly.  Had  they  continued  to  use 
their old logic, they would have had some parts 
in WIP for an additional month and reduced the 
current  throughput  of  their  constraint.  In 
addition,  the  new  MANAGE  Capability  helped 
him determine the best sequence for all these sub 
jobs by providing detailed resource information. 
By  managing  the  critical  sub‐jobs  and  the 
production  sequence,  they  completed  this  large 
job  on  time  using  their  resources  in  the  most 
effective  way  possible  with  little  stress  on  other 
operations. 
Meanwhile,  the  Supply  Chain  Management   
Director continued to upload all the other work 
in  their  plant  and  rescheduled  those  jobs  based 
on the new system. The changes were significant 
and  fast.  In  the  first  week,  they  saw  problems 
that  could  be  corrected  before  the  job  was  late, 
and they were able to successfully manage how 
long a job would take by adjusting its associated 
time  buffer.  For  the  first  time,  they  controlled 
442 Orange Street Penthouse Level, Suntec Tower Three
New Haven, CT 06511 USA 8 Temask Blvd, SINGAPORE 038988
Tel: +1-203-624-9026 www.goldratt.com Tel: +65-97468450
Copyright ©2012 Avraham Y. Goldratt Institute, LP. All rights reserved. This paper may be downloaded, reproduced and distributed. However, distribution to the public by sale, rental or
lease is strictly prohibited. This paper shall not be used as part of or incorporated into any other written work or publication except with the written permission of the Avraham Y. Goldratt
Institute, LP. No derivative works may be created based on this paper except with the written permission of the Avraham Y. Goldratt Institute, LP.
Page 4 of 4
overtime  decisions  by  what  the  system  actually 
needed  to  generate  throughput,  not  just 
assuming  more  was  always  better–this  savings 
alone  paid  for  the  investment  in  the  MANAGE 
Capability. 
Since the GEN2 buffer management process took 
a  fraction  of  the  time  previously  devoted  to 
scheduling,  the  Supply  Chain  Management 
Director was able to add even more value to their 
system. With each job having a clear scheduling 
path with buffers to account for variability, when 
any  product  was  consistently  late,  Republic 
focused  their  attention  to  determine  the  cause 
and take the right corrective action. For example, 
they  found  some  welding  work  frequently  took 
longer  than  planned.  Re‐examining  the  specific 
processes,  they  identified  and  executed  rapid 
improvements  that  removed  15  unnecessary 
queue days (20% of the jobʹs total TRR).
By combining the strategic direction and system 
design  perspective  with  the  iterative  process  of 
Focused  System  Improvement  in  the  SDAIS 
framework,  Republic  has  remained  competitive 
in  these  challenging  economic  times.  While  not 
yet content with their on‐time performance, they 
have  measured  significant  gains.  The  trend  for 
the  throughput  value  of  work  completed  later 
than scheduled showed a 66% decrease over the 
previous  year.  Moreover,  the  value  of  work 
completed  on  time  or  early  has  increased—
resulting in a much improved cash flow position. 
Republic Industries International has recognized 
the benefits and startegic advantages of using the 
VELOCITY approach—this is a journey they plan 
to continue for a long time.
 
 
Source: Jason Coslow, Republic Industries International 
is a registered trademark of Avraham Y. Goldratt Institute, a Limited Partnership.
is a registered service mark of Avraham Y. Goldratt Institute, a Limited Partnership.

More Related Content

What's hot

Agile Project Management for PMP's
Agile Project Management for PMP'sAgile Project Management for PMP's
Agile Project Management for PMP'sVersionOne
 
Product development kaizen (pdk)
Product  development kaizen (pdk)Product  development kaizen (pdk)
Product development kaizen (pdk)Glen Alleman
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingGlen Alleman
 
Polca White Paper
Polca White PaperPolca White Paper
Polca White PaperMark Dawson
 
Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Glen Alleman
 
Transforming into Agile IT organisation
Transforming into Agile IT organisationTransforming into Agile IT organisation
Transforming into Agile IT organisationHans Oosterling
 
AgileImplementation10122014V1
AgileImplementation10122014V1AgileImplementation10122014V1
AgileImplementation10122014V1Hans Oosterling
 
Presentation: "Agile methodologies for Project Management - SCRUM" by Varty K...
Presentation: "Agile methodologies for Project Management - SCRUM" by Varty K...Presentation: "Agile methodologies for Project Management - SCRUM" by Varty K...
Presentation: "Agile methodologies for Project Management - SCRUM" by Varty K...varty
 
Agile Business Rhythm
Agile Business RhythmAgile Business Rhythm
Agile Business RhythmGlen Alleman
 
Agile project management is systems management
Agile project management is systems managementAgile project management is systems management
Agile project management is systems managementGlen Alleman
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beeneNASAPMC
 
Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)Glen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
HPE Agile Manager and Project and Portfolio Management PPM overview
HPE Agile Manager and Project and Portfolio Management PPM overview HPE Agile Manager and Project and Portfolio Management PPM overview
HPE Agile Manager and Project and Portfolio Management PPM overview Jeffrey Nunn
 
Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2Glen Alleman
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bagGlen Alleman
 
Capabilities Based Planning
Capabilities Based PlanningCapabilities Based Planning
Capabilities Based PlanningGlen Alleman
 

What's hot (20)

Agile Project Management for PMP's
Agile Project Management for PMP'sAgile Project Management for PMP's
Agile Project Management for PMP's
 
Product development kaizen (pdk)
Product  development kaizen (pdk)Product  development kaizen (pdk)
Product development kaizen (pdk)
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
 
Polca White Paper
Polca White PaperPolca White Paper
Polca White Paper
 
Control systems
Control systemsControl systems
Control systems
 
Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)
 
Transforming into Agile IT organisation
Transforming into Agile IT organisationTransforming into Agile IT organisation
Transforming into Agile IT organisation
 
AgileImplementation10122014V1
AgileImplementation10122014V1AgileImplementation10122014V1
AgileImplementation10122014V1
 
Presentation: "Agile methodologies for Project Management - SCRUM" by Varty K...
Presentation: "Agile methodologies for Project Management - SCRUM" by Varty K...Presentation: "Agile methodologies for Project Management - SCRUM" by Varty K...
Presentation: "Agile methodologies for Project Management - SCRUM" by Varty K...
 
Agile Business Rhythm
Agile Business RhythmAgile Business Rhythm
Agile Business Rhythm
 
Dit yvol2iss36
Dit yvol2iss36Dit yvol2iss36
Dit yvol2iss36
 
Agile project management is systems management
Agile project management is systems managementAgile project management is systems management
Agile project management is systems management
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beene
 
Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
HPE Agile Manager and Project and Portfolio Management PPM overview
HPE Agile Manager and Project and Portfolio Management PPM overview HPE Agile Manager and Project and Portfolio Management PPM overview
HPE Agile Manager and Project and Portfolio Management PPM overview
 
Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bag
 
Capabilities Based Planning
Capabilities Based PlanningCapabilities Based Planning
Capabilities Based Planning
 
Planning And Scheduling Proactively
Planning And Scheduling ProactivelyPlanning And Scheduling Proactively
Planning And Scheduling Proactively
 

Viewers also liked (18)

Kiitee2015 prospectus
Kiitee2015 prospectusKiitee2015 prospectus
Kiitee2015 prospectus
 
Prijem prvaka 2015
Prijem prvaka 2015Prijem prvaka 2015
Prijem prvaka 2015
 
2.J
2.J2.J
2.J
 
Ariela Martin, Bibliography
Ariela Martin, BibliographyAriela Martin, Bibliography
Ariela Martin, Bibliography
 
Why we travel
Why we travelWhy we travel
Why we travel
 
MKT Final Report
MKT Final ReportMKT Final Report
MKT Final Report
 
Nutrición y Alimentación.pptx Paola Leal Completo
Nutrición y Alimentación.pptx Paola Leal CompletoNutrición y Alimentación.pptx Paola Leal Completo
Nutrición y Alimentación.pptx Paola Leal Completo
 
Filiz özyaprak
Filiz özyaprakFiliz özyaprak
Filiz özyaprak
 
Bad brews night 02.25.2010
Bad brews night 02.25.2010Bad brews night 02.25.2010
Bad brews night 02.25.2010
 
01 обложка (39)
01 обложка (39)01 обложка (39)
01 обложка (39)
 
Criterios de evaluación. Vascularización de las cavidades de las cavidades to...
Criterios de evaluación. Vascularización de las cavidades de las cavidades to...Criterios de evaluación. Vascularización de las cavidades de las cavidades to...
Criterios de evaluación. Vascularización de las cavidades de las cavidades to...
 
MúSica Maestro!!!
MúSica Maestro!!!MúSica Maestro!!!
MúSica Maestro!!!
 
Uso correcto de la computadora
Uso correcto de la computadoraUso correcto de la computadora
Uso correcto de la computadora
 
G-Force_CuttingWords-v3
G-Force_CuttingWords-v3G-Force_CuttingWords-v3
G-Force_CuttingWords-v3
 
Arduino Uno Board - Robomart
Arduino Uno Board - RobomartArduino Uno Board - Robomart
Arduino Uno Board - Robomart
 
Irrigacion y drenaje venoso miembro toracico
Irrigacion y drenaje venoso miembro toracicoIrrigacion y drenaje venoso miembro toracico
Irrigacion y drenaje venoso miembro toracico
 
theories of tooth movement
theories of tooth movementtheories of tooth movement
theories of tooth movement
 
Du SO ( Du u Ok ) 555 - ITA - ZG
Du SO ( Du u Ok ) 555 - ITA - ZGDu SO ( Du u Ok ) 555 - ITA - ZG
Du SO ( Du u Ok ) 555 - ITA - ZG
 

Similar to Improving On-Time Delivery Through Focused System Improvement

Lean Schedulng Case Study Providence Oct 09
Lean Schedulng Case Study   Providence Oct 09Lean Schedulng Case Study   Providence Oct 09
Lean Schedulng Case Study Providence Oct 09Graphicast
 
RepublicCaseStudyI
RepublicCaseStudyIRepublicCaseStudyI
RepublicCaseStudyIJason Coslow
 
Lean Scheduling and Theory of Constraints
Lean Scheduling and Theory of ConstraintsLean Scheduling and Theory of Constraints
Lean Scheduling and Theory of ConstraintsGraphicast
 
1HW#1 DW Case StudyCase Studies of Data Warehousing Failu.docx
1HW#1 DW Case StudyCase Studies of Data Warehousing Failu.docx1HW#1 DW Case StudyCase Studies of Data Warehousing Failu.docx
1HW#1 DW Case StudyCase Studies of Data Warehousing Failu.docxherminaprocter
 
How processes masquerading as projects are hurting your business v4
How processes masquerading as projects are hurting your business v4How processes masquerading as projects are hurting your business v4
How processes masquerading as projects are hurting your business v4Jonathan Sapir
 
Case Studies of Data Warehousing FailuresFour studies of data .docx
Case Studies of Data Warehousing FailuresFour studies of data .docxCase Studies of Data Warehousing FailuresFour studies of data .docx
Case Studies of Data Warehousing FailuresFour studies of data .docxdewhirstichabod
 
Maintworld NEXUS v2
Maintworld NEXUS v2Maintworld NEXUS v2
Maintworld NEXUS v2Rafael Tsai
 
Gaining altitude and cruising smoothly to hr cloud
Gaining altitude and cruising smoothly to hr cloudGaining altitude and cruising smoothly to hr cloud
Gaining altitude and cruising smoothly to hr cloudNGA Human Resources
 
Automatic real time scheduling
Automatic real time schedulingAutomatic real time scheduling
Automatic real time schedulingManish kumar
 
Production Planning and Scheduling
Production Planning and SchedulingProduction Planning and Scheduling
Production Planning and SchedulingManish kumar
 
Yapp methodology anjo-kolk
Yapp methodology anjo-kolkYapp methodology anjo-kolk
Yapp methodology anjo-kolkToon Koppelaars
 
Production planning and scheduling
Production planning and schedulingProduction planning and scheduling
Production planning and schedulingManish kumar
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET Journal
 
Implementation of a portfolio programme management (PPM) tool, APM PMC SIG co...
Implementation of a portfolio programme management (PPM) tool, APM PMC SIG co...Implementation of a portfolio programme management (PPM) tool, APM PMC SIG co...
Implementation of a portfolio programme management (PPM) tool, APM PMC SIG co...Association for Project Management
 
Wtewp employee central guide oct16
Wtewp   employee central guide oct16Wtewp   employee central guide oct16
Wtewp employee central guide oct16Sateesh Jabisetty
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and controlManish kumar
 
An Innovative Real Time Production Management System
An Innovative Real Time Production Management System An Innovative Real Time Production Management System
An Innovative Real Time Production Management System supportetalika
 
Abbatelli - BB Mini-Project
Abbatelli - BB Mini-ProjectAbbatelli - BB Mini-Project
Abbatelli - BB Mini-ProjectNick Abbatelli
 
Agile Development: Will It Work for You?
Agile Development: Will It Work for You?Agile Development: Will It Work for You?
Agile Development: Will It Work for You?Callidus Software
 

Similar to Improving On-Time Delivery Through Focused System Improvement (20)

Lean Schedulng Case Study Providence Oct 09
Lean Schedulng Case Study   Providence Oct 09Lean Schedulng Case Study   Providence Oct 09
Lean Schedulng Case Study Providence Oct 09
 
RepublicCaseStudyI
RepublicCaseStudyIRepublicCaseStudyI
RepublicCaseStudyI
 
Lean Scheduling and Theory of Constraints
Lean Scheduling and Theory of ConstraintsLean Scheduling and Theory of Constraints
Lean Scheduling and Theory of Constraints
 
1HW#1 DW Case StudyCase Studies of Data Warehousing Failu.docx
1HW#1 DW Case StudyCase Studies of Data Warehousing Failu.docx1HW#1 DW Case StudyCase Studies of Data Warehousing Failu.docx
1HW#1 DW Case StudyCase Studies of Data Warehousing Failu.docx
 
How processes masquerading as projects are hurting your business v4
How processes masquerading as projects are hurting your business v4How processes masquerading as projects are hurting your business v4
How processes masquerading as projects are hurting your business v4
 
Case Studies of Data Warehousing FailuresFour studies of data .docx
Case Studies of Data Warehousing FailuresFour studies of data .docxCase Studies of Data Warehousing FailuresFour studies of data .docx
Case Studies of Data Warehousing FailuresFour studies of data .docx
 
Maintworld NEXUS v2
Maintworld NEXUS v2Maintworld NEXUS v2
Maintworld NEXUS v2
 
Gaining altitude and cruising smoothly to hr cloud
Gaining altitude and cruising smoothly to hr cloudGaining altitude and cruising smoothly to hr cloud
Gaining altitude and cruising smoothly to hr cloud
 
Automatic real time scheduling
Automatic real time schedulingAutomatic real time scheduling
Automatic real time scheduling
 
Production Planning and Scheduling
Production Planning and SchedulingProduction Planning and Scheduling
Production Planning and Scheduling
 
Yapp methodology anjo-kolk
Yapp methodology anjo-kolkYapp methodology anjo-kolk
Yapp methodology anjo-kolk
 
Production planning and scheduling
Production planning and schedulingProduction planning and scheduling
Production planning and scheduling
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
Implementation of a portfolio programme management (PPM) tool, APM PMC SIG co...
Implementation of a portfolio programme management (PPM) tool, APM PMC SIG co...Implementation of a portfolio programme management (PPM) tool, APM PMC SIG co...
Implementation of a portfolio programme management (PPM) tool, APM PMC SIG co...
 
Wtewp employee central guide oct16
Wtewp   employee central guide oct16Wtewp   employee central guide oct16
Wtewp employee central guide oct16
 
vldb08a
vldb08avldb08a
vldb08a
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
An Innovative Real Time Production Management System
An Innovative Real Time Production Management System An Innovative Real Time Production Management System
An Innovative Real Time Production Management System
 
Abbatelli - BB Mini-Project
Abbatelli - BB Mini-ProjectAbbatelli - BB Mini-Project
Abbatelli - BB Mini-Project
 
Agile Development: Will It Work for You?
Agile Development: Will It Work for You?Agile Development: Will It Work for You?
Agile Development: Will It Work for You?
 

Improving On-Time Delivery Through Focused System Improvement

  • 1. VELOCITY—a powerful business approach combining speed with direction—consists of three pillars: Theory of Constraints, the system architecture; Theory of Constraints Lean Six Sigma (TOCLSS), the focused improvement process; and SDAIS (Strategy-Design-Activate-Improve-Sustain), the deployment framework.  Background Although  they  had  made  significant  improvements,  Republic  still  had  a  dark  secret  they  only  whispered  about—their  on‐time  delivery percentage for make‐to‐order jobs. Prior  to their experience with AGI – Goldratt Institute,  they didnʹt even distinguish their work between  make‐to‐order  and  make‐to‐stock.  On‐time  performance  wasnʹt  measured,  since  they  only  made  delivery  promises  when  absolutely  required, and unfortunately, they had a mediocre  record of keeping them.  However,  following  their  strategic  analysis  and  after activating a constraint‐based design of their  new  operations  management  process,  Republic  was more reliable and able to produce at a much  faster  rate.  Overall,  they  were  turning  their  products  22  days  (36%)  faster  with  little  capital  investment.  Their  new  design  prioritized  work  based  on  the  number  of  days  an  item  had  been  waiting  at  a  workstation,  because  their  analysis  had revealed that many items were in queue up  to  30  days  to  become  the  next  job,  only  to  get  pushed back by a ʺhigherʺ priority. Therefore, to  reduce the queue time for work‐in‐process (WIP),  and  consequently  reduce  the  total  volume  of  WIP,  they  had  established  a  scheduling  priority  rule based exclusively on the number of days in  queue.  They  also  used  a  drum  buffer‐rope  decision process to gate the release of new work  to  avoid  adding  more  WIP  than  the  system  constraints  could  handle.  Activating  this  design  stabilized  the  system  sufficiently  to  achieve  significant  improvement  (see  Republic  Industries  International:  Part  II—Understanding  Throughput).  Even so, to be honest, their delivery performance  was still poor with only 69% of their jobs being  completed on time or early.  VELOCITY and Focused System Improvement Integral to the VELOCITY approach are cycles of  Focused  System  Improvement  as  organizations  continue  to  monitor  performance  and  seek  ongoing positive impact on their strategic results.  Because  their  system  design  was  sufficient  to  stabilize  their  systemʹs  performance,  Republic  recognized they had to focus even more on work  scheduling. They still had problems determining  realistic  delivery  times  for  their  clients.  When  specific  delivery  dates  were  required  to  exploit  new  opportunities,  production  scheduling  was  nearly  impossible  to  manage  as  they  had  little  control over when a job would be worked next.  Republicʹs Director of Supply Chain Management   Republic Industries International Part III—Improving Delivery Performance Established in 1911, Republic Industries International repairs and produces large metal compo‐ nents supporting customers in the industrial and mining sectors. They also provide engineering  services to develop unique solutions to meet customers’ needs. Based in Louisville, Kentucky,  Republic operates as a make‐to‐order and make‐to‐stock company with about 100 employees. 
  • 2. www.goldratt.com Page 2 of 4 was  spending  a  great  deal  of  time  manually  updating queue lists as he attempted to manage  scheduling priorities.   Under  pressure  to  resolve  this  issue,  Republicʹs  scheduling  committee  modified  their  design  to  use  scheduled  due  dates  as  the  determining  factor  to  manage  job  priorities.  That  approach  seemed  reasonable—they  believed  all  they  needed  to  do  was  advance  a  jobʹs  due  date  to  move  it  up  in  priority  on  the  daily  work  lists.  Activating  this  design  change  did  relieve  some  stress in scheduling; however, while the sequence  of completed jobsʹ may have changed, the overall  on‐time results did not. The same number of jobs  still  ran  late.  Why  didnʹt  they  achieve  the  expected improvement?  Understanding the problem In retrospect, the problems with using scheduled  due  dates  became  pretty  clear.  Within  their  system, the make‐to‐order jobs had unique work  flows. Some of them required lengthy external or  internal processes. Therefore, the greater amount  of work to be done resulted in longer lead times.  To  simplify  their  scheduling,  they  had  assigned  all  the  make‐to‐stock  jobs  a  standardized  lead  time  sufficient  to  cover  the  expected  work  required. So items with due dates further in the  future  (based  on  longer  lead  times)  might  initially  sit  for  weeks,  while  items  with  earlier  due dates received priority. To work around the  disparity  in  lead  times,  on  occasion,  the  schedulers  would  use  fake  due  dates  to  re‐ prioritize  a  job,  resulting  in  tremendous  confusion about whether a job was actually late  or  just  ʺfakeʺ  late.  Essentially,  the  due  dates  in  their information system became more and more  fictional, and despite their scheduling emphasis,  they lacked credibility and meaning.  Moreover,  both  this  design  and  the  previous  design  had  a  common  flaw—Republic  never  seemed to know a job was in jeopardy of being  overdue until it was too late. They were using the  classic  buffer  management  approach—Green,  Yellow,  Red—to  monitor  a  jobʹs  progress  compared  to  its  associated  ʺtime‐to‐reliably  replenishʺ  (TRR).  However,  as  jobs  neared  completion, their reports frequently showed their  status as  `yellowʹ  (needs  review)  or  `redʹ  (needs  intervention).  With  so  many  jobs  needing  attention,  the  buffers  failed  to  motivate  the  proper  actions.  Supervisors  were  already  too  busy responding to the daily crises of whichever  jobs, for whatever reasons, were the urgent fires  to  be  dealt  with  that  day.  By  that  point,  they  could  do  little  to  achieve  an  on‐time  delivery.  Instead,  they  focused  their  expediting  efforts  to  make items ʺless late.ʺ Frequently their sales staff called asking when a  job  would  be  finished,  despite  the  job  having  a  specified due date. Research often found some of  those  jobs  stuck  in  queues  despite  their  specific  efforts  to  reduce  queue  times!  These  failures  to  deliver on time jeopardized all the gains of their  earlier  improvements,  especially  if  Republic  became known as an unreliable vendor. The need  was clear. Their next system improvement had to  focus  on  work  priorities  and  scheduling  to  reliably deliver on time.  Buffer Management and Scheduling To  improve  performance  in  TOC‐based  system  designs,  managers  use  buffer  management  to  prioritize  work,  to  know  when  to  expedite,  to  identify  where  capacity  is  insufficient,  and  to  adjust buffer sizes. Until this point, Republic had  only really used quantity buffers to protect some  inventory levels. When they described their latest 
  • 3. www.goldratt.com Page 3 of 4 problems,  AGI  proposed  an  evaluation  of  their  new  generation  (GEN2)  buffer  management  approach  in  their  MANAGE  Capability  of  the  SUPPLY CHAIN Suite® .  Although  Republic  found  the  advanced  concepts  behind  the  ap‐ proach  somewhat  difficult  to  understand,  they  found  the  logic  of  the  approach  to  be  very  compelling.  Republic  translated  their  data  to  the  format  required by AGIʹs software. Their Supply Chain  Management Director logged in to the MANAGE  Capability for the first time. For all its conceptual  complexity, he was initially underwhelmed that,  with  just  a  few  screens,  it  would  be  possible  to  manage  all  of  their  operations.  ʺYeah  right,ʺ  he  thought skeptically. He believed: Republicʹs  work  is  difficult  to  manage  because  our  constraint  changes  when  we  have a significant change in our workload.  One  large  job  can  shift  the  constraint,  making  all  the  previous  scheduling  work  obsolete. In addition, we work a variety of  scheduling  shifts—eight  in  total.  To  complicate  things  further,  we  typically  do  not  run  out  of  machines,  but  rather  employees  who  can  run  specific  machines.  We  have  a  flexible  work  force  and  daily  tactical  decisions  determine  where  each  person  works  during  a  shift.  Some  machines are ʺunmannedʺ for days waiting  for  the  first  available  skilled  operator  to  finish  previous  jobs.  These  factors,  combined  with  the  variability  of  the  jobs  themselves, contribute to our poor on‐time  performance.  Very shortly after activation, the new MANAGE  Capability was put to the test. With the economic  downturn,  reduced  demand  forced  Republic  to  proactively  seek  more  work.  They  succeeded  in  being  awarded  a  significant  new  job  that  was  atypical  because  it  contained  70  more  components  than  other  jobs  in  its  throughput  range.  And  it  had  a  must‐hit  due  date.  The  director  loaded  their  system  with  all  the  necessary  data.  When  he  reviewed  the  information  provided  by  the  MANAGE  Capability, in a job of more than 80 sub‐jobs, he  was amazed to see clearly that just two identical  sub‐jobs  were  key  to  the  overall  success.  Previ‐ ously,  he  would  never  have  been  able  to  determine the critical elements of a job this size.  To  take  all  these  sub‐jobs  across  the  factors  discussed  above  was  simply  impractical.  In  the  past, Republic would have picked the most labor‐ intense  sub‐job  as  their  focus  for  monitoring.  In  addition,  because  they  didnʹt  have  a  system  perspective,  they  would  have  started  work  as  early  as  they  could  on  as  many  sub‐jobs  as  possible. Their thinking was the earlier each sub‐ job was completed, the earlier they could proceed  to  final  assembly.  Had  they  continued  to  use  their old logic, they would have had some parts  in WIP for an additional month and reduced the  current  throughput  of  their  constraint.  In  addition,  the  new  MANAGE  Capability  helped  him determine the best sequence for all these sub  jobs by providing detailed resource information.  By  managing  the  critical  sub‐jobs  and  the  production  sequence,  they  completed  this  large  job  on  time  using  their  resources  in  the  most  effective  way  possible  with  little  stress  on  other  operations.  Meanwhile,  the  Supply  Chain  Management    Director continued to upload all the other work  in  their  plant  and  rescheduled  those  jobs  based  on the new system. The changes were significant  and  fast.  In  the  first  week,  they  saw  problems  that  could  be  corrected  before  the  job  was  late,  and they were able to successfully manage how  long a job would take by adjusting its associated  time  buffer.  For  the  first  time,  they  controlled 
  • 4. 442 Orange Street Penthouse Level, Suntec Tower Three New Haven, CT 06511 USA 8 Temask Blvd, SINGAPORE 038988 Tel: +1-203-624-9026 www.goldratt.com Tel: +65-97468450 Copyright ©2012 Avraham Y. Goldratt Institute, LP. All rights reserved. This paper may be downloaded, reproduced and distributed. However, distribution to the public by sale, rental or lease is strictly prohibited. This paper shall not be used as part of or incorporated into any other written work or publication except with the written permission of the Avraham Y. Goldratt Institute, LP. No derivative works may be created based on this paper except with the written permission of the Avraham Y. Goldratt Institute, LP. Page 4 of 4 overtime  decisions  by  what  the  system  actually  needed  to  generate  throughput,  not  just  assuming  more  was  always  better–this  savings  alone  paid  for  the  investment  in  the  MANAGE  Capability.  Since the GEN2 buffer management process took  a  fraction  of  the  time  previously  devoted  to  scheduling,  the  Supply  Chain  Management  Director was able to add even more value to their  system. With each job having a clear scheduling  path with buffers to account for variability, when  any  product  was  consistently  late,  Republic  focused  their  attention  to  determine  the  cause  and take the right corrective action. For example,  they  found  some  welding  work  frequently  took  longer  than  planned.  Re‐examining  the  specific  processes,  they  identified  and  executed  rapid  improvements  that  removed  15  unnecessary  queue days (20% of the jobʹs total TRR). By combining the strategic direction and system  design  perspective  with  the  iterative  process  of  Focused  System  Improvement  in  the  SDAIS  framework,  Republic  has  remained  competitive  in  these  challenging  economic  times.  While  not  yet content with their on‐time performance, they  have  measured  significant  gains.  The  trend  for  the  throughput  value  of  work  completed  later  than scheduled showed a 66% decrease over the  previous  year.  Moreover,  the  value  of  work  completed  on  time  or  early  has  increased— resulting in a much improved cash flow position.  Republic Industries International has recognized  the benefits and startegic advantages of using the  VELOCITY approach—this is a journey they plan  to continue for a long time.     Source: Jason Coslow, Republic Industries International  is a registered trademark of Avraham Y. Goldratt Institute, a Limited Partnership. is a registered service mark of Avraham Y. Goldratt Institute, a Limited Partnership.