SlideShare a Scribd company logo
1 of 13
Download to read offline
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli1
Lean Six Sigma Black Belt Mini-Project
Extended Education – NCR 9635
Project Title: Setup Time Reduction (Roll)
Prepared by Nick Abbatelli
nabbatel@calpoly.edu – (408) 838-2097
Company: GM Nameplate (San Jose, CA)
August 29th, 2014
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli2
EXECUTIVE SUMMARY
This Mini-Project was conducted at GM Nameplate in San Jose, CA. GM Nameplate
specializes in roll products. Some of the processes include: flexographic printing, digital printing,
screen printing, laminating and die cutting. The mission was to reduce setup time of certain
production areas in the facility, specifically the flexographic printing areas. Flexographic printing
involves unwinding and feeding material into the machine, a printing section, a drying section and
then feeding it to a re-winder as a finished roll product. The operational tools consist of rollers
(Foundation & Anilox), doctor blades and cylinders (Plate & Impression). Running product
through a machine from raw material to finish product account for 20% of the total process on
average. More than 70% of the time is spent setting up the machine. An order requires a specific
anilox roller, print cylinder and impression cylinder. The impression cylinder is unique to the job
because it has a plate that has a logo or cutout per requirements of the job. The plate is mounted
onto the impression cylinder before the cylinder is installed. GM Nameplate has an inventory of
5,000+ of these rollers and cylinders. One machine accounts for 72% of these tools. Since the
project was on a strict and short timeline, it focused its measurements and analysis on that
machine: Nilpeter Flexo Press. The team found the setup time was a little over 68 minutes on
average. Following the process of the operators we identified a procedure that could be improved
upon. Key tooling are being stored in a separate building on account of storage space in the
production area. Operators have to walk over to the separate building, identify and bring back the
specified tool to the production area before mounting the plate can even begin. The team
recommends improving the identification and planning process so GM Nameplate can reduce the
setup time of its Nilpeter machine, ultimately producing more jobs annually.
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli3
DEFINE Tool 1: Project Charter
Why Tool Selected: This document reveals the goals of the project. It can be revised and changed
but must always be referenced to. GM Nameplate created a charter to make sure tasks was laid out
correctly and in a timely matter.
Interpretation: The Project Charter was reviewed weekly by the project Champion. It gave the
team organization to stay on track and keep tasks in proper alignment of each other. Although not
every task was completed on time, the charter kept the team on track to the ultimate goal.
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli4
DEFINE Tool 2: Process Flow Chart
Why Tool Selected: A Process Flow Chart (or Process Map) is used to give a visual representation
of the steps in the process. The team wanted to find what processes happen once a job gets placed
in the work-in-progress bin of the Roll Department?
Interpretation: The process flow chart can improve any process improvement project by
increasing the understanding of people involved, flow of information and resources. This chart
shows three key processes that must be done before the job can even be ran: identification of
tooling, pulling of tooling and the setup, which involves mounting of the tooling pulled.
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli5
MEASURE Tool 1: Histogram
Why Tool Selected: Gathering data in a spreadsheet can be overwhelming. A Histogram provides a
visual representation of the data. The team took data from 1 production aspect of the Roll
Department to get a gauge upon: Nilpeter Room. What were common setup times of the Nilpeter
machine? [Twenty-five jobs within the month of August 2014 where used]
Interpretation: The graph shows a positively skewed set of data with the most common setup time
between 60 – 80 minutes. [Note: This data only represents 1 machine out of 5 within the Roll
Department. Due to time constraints, this machine was the most viable because it is the only
machine that runs constantly 8-hours/day. ]
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli6
MEASURE Tool 2: X and Moving Range Chart
Why Tool Selected: The team wanted to observe the setup times of the Nilpeter machine in the
recent calendar month completed: August 2014. By making an XmR chart, it will produce control
limits for the data. Visually viewing the control limits on the chart, the team can clearly identify
which job should be investigated and ask the question: Is the process stable?
Interpretation: Out of 16 jobs ordered in August 2014, there was an instance where the condition
was ‘out-of-control’ from jobs 6 to 7. These jobs need to be looked at closer in detail and
investigated for procedure fixes and flaws. Also, investigate job 16, where it was not normal and
fell out of the upper control limit.
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli7
ANALYZE Tool 1: 5 Why Analysis
Why Tool Selected: The team chose to use the 5-Why’s to find a more specific root cause of why
roll setup is taking a majority of the roll manufacturing process. The technique proclaims that if
you ask “Why?” five times, you can identify an understanding to the ultimate root causes. The team
chose to start the ‘Why’ process at, “Why does setup time take so long?”
 Nilpeter setup averages over 1 hour
o Why does the setup take so long?
 Dies and Tooling are bulky. It takes time to walk over to the next-door building and identify
the die and/or tooling for the specific job
o Why are dies and tooling stored in the next-door building?
 Jobs that require previously used dies are warehoused in the building next door because of
its large storage space. Often operators are over there multiple times a day
o Why multiple trips?
 Job tickets buildup throughout the day. Operators only see jobs that are progressing
throughout the manufacturing process
o Why don’t operators know of future jobs?
 There is no warning system in place to tell operators which dies to pull for future jobs
ahead.
o Why doesn’t Planning Department tell operators the current job schedule?
Interpretation: Root Cause – Planning Department should identify dies & tooling work-in-
progress better with the operators to lower the number of trips throughout the day next-door.
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli8
ANALYZE Tool 2: Hypothesis Testing
Why Tool Selected: Operators in the roll department believed setup time takes under an hour.
The Six Sigma team decided to use this common estimate as a Null Hypothesis.
Interpretation: Running the numbers in EngineRoom using the Hypothesis Testing tool, the results
to reject the Null Hypothesis. The mean of ‘Nilpeter Setup Time’ is greater than 60 minutes,
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli9
IMPROVE Tool 1: 5S
Why Tool Selected: Taking an outsiders perspective inside the Nilpeter Room, it looks dirty and
cluttered. There are many distractions inside the room and the 5S tool improves visibility of the
process, safety and worker performance.
Scan & Sort – Scan the area and sort through unneeded material, equipment, tooling and trash.
Old Material Supply Cabinet Behind Machine
Set in Order – Tooling and Instruments should be set in place, easy to find at all times.
Supplies Organized Tooling Organized
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli10
Shine – A clean workspace improves working conditions and the moral of operators.
Clean Aisles
Standardize – Create Shadow Boards for standard tooling and instruments within each working
station
Sustain – A 6S board was created within the department for department supervisors to sustain
the improvement process. The board also creates friendly departmental competition with audit
grades and scores.
Interpretation: Although the last 2 S’s could not have been completed due to internship length
restrictions, the 5S tool was highly effective within the manufacturing plant. Going through the
process with the operators, common remarks were: “I didn’t know when could throw this away,”
We can take this out?” and “I haven’t seen anyone use that in a decade.” It proved that taking a
simple step back and asking, “Why is this here?” solved many organizational issues.
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli11
IMPROVE Tool 2: Pull Scheduling
Why Tool Selected: Pull Scheduling consist of many aspects: balanced production, quick set-ups,
reducing lot size and standardized work to name a few. For this project, the team focused on quick
set-ups. How can the operators decrease setup time?
Interpretation: This photo is of the new WIP area for the Nilpeter room. All job orders are looked
at, at the beginning of the day and the operators collect plates and cylinders for each job. The red
bin is for plates and the bottom shelf is for the cylinders.
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli12
CONTROL Tool 1: CHECK Process
Why Tool Selected: How could GM Nameplate keep operators accountable for their workstations?
Interpretation: This form was created after the 5S activity was completed. It allows supervisors
and managers to sustain lean and clean workstations. It also promotes health competition
between the production areas amongst the operators.
Nick Abbatelli Cal Poly SLO – Business – Industrial Technology
10/14/14 Mini-Project – Abbatelli13
CONTROL Tool 2: Standardized Work
Why Tool Selected: How does the operator know which job takes priority?
Interpretation: This photo is of the new WIP area for the Nilpeter room. The metallic bins on the
top right of the table consists of 3 staggered bins. The farthest back bin represents job to be
completed within the given month. The middle bin represents the weekly job orders. The first bin
represents job to be done during the day (top priority).

More Related Content

What's hot

The Agile Revolution of IBM
The Agile Revolution of IBMThe Agile Revolution of IBM
The Agile Revolution of IBMAlan Kan
 
141015 Discovering Scrum at Scrum Roma
141015 Discovering Scrum at Scrum Roma141015 Discovering Scrum at Scrum Roma
141015 Discovering Scrum at Scrum RomaPeter Stevens
 
Awe k2 midterms
Awe k2 midtermsAwe k2 midterms
Awe k2 midtermsKaren Tay
 
Introduction to Scrum.ppt
Introduction to Scrum.pptIntroduction to Scrum.ppt
Introduction to Scrum.pptMohan Late
 
Innovative it project management practices
Innovative it project management practicesInnovative it project management practices
Innovative it project management practicesTathagat Varma
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bagGlen Alleman
 
Learning from the Trenches: Scrum for Hardware
Learning from the Trenches: Scrum for HardwareLearning from the Trenches: Scrum for Hardware
Learning from the Trenches: Scrum for HardwareJohn Carter
 
Improve SMT Labor Margin Per Unit
Improve SMT Labor Margin Per UnitImprove SMT Labor Margin Per Unit
Improve SMT Labor Margin Per UnitDamian Denis
 
Awe k2 midterms finals
Awe k2 midterms finalsAwe k2 midterms finals
Awe k2 midterms finalsKaren Tay
 
Project Management
Project ManagementProject Management
Project ManagementPrarthan P
 
Primer on Agile Project Management and SCRUM
Primer on Agile Project Management and SCRUMPrimer on Agile Project Management and SCRUM
Primer on Agile Project Management and SCRUMJoe Riego
 
R.Rodriguez_CurrentCoverLetter_Resume
R.Rodriguez_CurrentCoverLetter_ResumeR.Rodriguez_CurrentCoverLetter_Resume
R.Rodriguez_CurrentCoverLetter_ResumeRené Rodríguez, Jr.
 
Crossing the Chasm & Pull-based change interactive workshop handouts
Crossing the Chasm & Pull-based change interactive workshop handouts Crossing the Chasm & Pull-based change interactive workshop handouts
Crossing the Chasm & Pull-based change interactive workshop handouts Yuval Yeret
 
Lean applied in Project Management
Lean applied in Project ManagementLean applied in Project Management
Lean applied in Project ManagementAlvaro Plaza
 
Agile Web Development, Exove seminar August 15th, 2013
Agile Web Development, Exove seminar August 15th, 2013Agile Web Development, Exove seminar August 15th, 2013
Agile Web Development, Exove seminar August 15th, 2013Exove
 
Current Trends in Agile - opening keynote for Agile Israel 2014
Current Trends in Agile - opening keynote for Agile Israel 2014Current Trends in Agile - opening keynote for Agile Israel 2014
Current Trends in Agile - opening keynote for Agile Israel 2014Yuval Yeret
 

What's hot (20)

The Agile Revolution of IBM
The Agile Revolution of IBMThe Agile Revolution of IBM
The Agile Revolution of IBM
 
141015 Discovering Scrum at Scrum Roma
141015 Discovering Scrum at Scrum Roma141015 Discovering Scrum at Scrum Roma
141015 Discovering Scrum at Scrum Roma
 
Awe k2 midterms
Awe k2 midtermsAwe k2 midterms
Awe k2 midterms
 
AgileTesting_Ver1.0
AgileTesting_Ver1.0AgileTesting_Ver1.0
AgileTesting_Ver1.0
 
Introduction to Scrum.ppt
Introduction to Scrum.pptIntroduction to Scrum.ppt
Introduction to Scrum.ppt
 
Innovative it project management practices
Innovative it project management practicesInnovative it project management practices
Innovative it project management practices
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bag
 
Learning from the Trenches: Scrum for Hardware
Learning from the Trenches: Scrum for HardwareLearning from the Trenches: Scrum for Hardware
Learning from the Trenches: Scrum for Hardware
 
Tools of lean mfg
Tools of lean mfgTools of lean mfg
Tools of lean mfg
 
Ch5
Ch5Ch5
Ch5
 
Improve SMT Labor Margin Per Unit
Improve SMT Labor Margin Per UnitImprove SMT Labor Margin Per Unit
Improve SMT Labor Margin Per Unit
 
Awe k2 midterms finals
Awe k2 midterms finalsAwe k2 midterms finals
Awe k2 midterms finals
 
Project Management
Project ManagementProject Management
Project Management
 
Primer on Agile Project Management and SCRUM
Primer on Agile Project Management and SCRUMPrimer on Agile Project Management and SCRUM
Primer on Agile Project Management and SCRUM
 
R.Rodriguez_CurrentCoverLetter_Resume
R.Rodriguez_CurrentCoverLetter_ResumeR.Rodriguez_CurrentCoverLetter_Resume
R.Rodriguez_CurrentCoverLetter_Resume
 
Crossing the Chasm & Pull-based change interactive workshop handouts
Crossing the Chasm & Pull-based change interactive workshop handouts Crossing the Chasm & Pull-based change interactive workshop handouts
Crossing the Chasm & Pull-based change interactive workshop handouts
 
Agile Methodologies
Agile MethodologiesAgile Methodologies
Agile Methodologies
 
Lean applied in Project Management
Lean applied in Project ManagementLean applied in Project Management
Lean applied in Project Management
 
Agile Web Development, Exove seminar August 15th, 2013
Agile Web Development, Exove seminar August 15th, 2013Agile Web Development, Exove seminar August 15th, 2013
Agile Web Development, Exove seminar August 15th, 2013
 
Current Trends in Agile - opening keynote for Agile Israel 2014
Current Trends in Agile - opening keynote for Agile Israel 2014Current Trends in Agile - opening keynote for Agile Israel 2014
Current Trends in Agile - opening keynote for Agile Israel 2014
 

Viewers also liked (13)

mooc
moocmooc
mooc
 
MOOC, The chronicles
MOOC, The chroniclesMOOC, The chronicles
MOOC, The chronicles
 
tahun 2015-04
tahun 2015-04tahun 2015-04
tahun 2015-04
 
Nipun_Tanay
Nipun_TanayNipun_Tanay
Nipun_Tanay
 
WERA כלים וחידושים
WERA כלים וחידושיםWERA כלים וחידושים
WERA כלים וחידושים
 
Tst20 b3 moo cs
Tst20 b3 moo csTst20 b3 moo cs
Tst20 b3 moo cs
 
Alice and adventures in Wonderland
Alice and adventures in WonderlandAlice and adventures in Wonderland
Alice and adventures in Wonderland
 
Abdomen agudo perforado HTCA 2016
Abdomen agudo perforado HTCA 2016Abdomen agudo perforado HTCA 2016
Abdomen agudo perforado HTCA 2016
 
BIO-DATA
BIO-DATABIO-DATA
BIO-DATA
 
II hernia inguinal htca 2016 (1)
II hernia inguinal htca 2016 (1)II hernia inguinal htca 2016 (1)
II hernia inguinal htca 2016 (1)
 
Digital India Quiz
Digital India QuizDigital India Quiz
Digital India Quiz
 
Andew marvell's To his coy mistress
Andew marvell's To his coy mistressAndew marvell's To his coy mistress
Andew marvell's To his coy mistress
 
Chinmaya_Resume
Chinmaya_ResumeChinmaya_Resume
Chinmaya_Resume
 

Similar to Abbatelli - BB Mini-Project

M.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis PresentationM.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis PresentationSanchit Jain
 
Performance measurement of agile teams harold van heeringen
Performance measurement of agile teams   harold van heeringenPerformance measurement of agile teams   harold van heeringen
Performance measurement of agile teams harold van heeringenIWSM Mensura
 
Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)Harold van Heeringen
 
The Ultimate Agile Planning Handbook
The Ultimate Agile Planning HandbookThe Ultimate Agile Planning Handbook
The Ultimate Agile Planning HandbookKaren Ho
 
Summer 2013 Internship Reflection
Summer 2013 Internship ReflectionSummer 2013 Internship Reflection
Summer 2013 Internship ReflectionTrevor Huggins
 
Work Study- Methods Study
Work Study- Methods StudyWork Study- Methods Study
Work Study- Methods StudyJoseph Konnully
 
resume - Alexander Cruz
resume - Alexander Cruz resume - Alexander Cruz
resume - Alexander Cruz Alexander Cruz
 
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...John Carter
 
Introduction to Agile & scrum
Introduction to Agile & scrumIntroduction to Agile & scrum
Introduction to Agile & scrumElad Sofer
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTFASI93
 
Agile Hardware Product Development (NextGen NPD plus - MRO shop example) inc...
Agile Hardware Product Development  (NextGen NPD plus - MRO shop example) inc...Agile Hardware Product Development  (NextGen NPD plus - MRO shop example) inc...
Agile Hardware Product Development (NextGen NPD plus - MRO shop example) inc...Richard Platt
 
OPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.comOPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.comdonaldzs34
 
How to Reduce Changeover Time and Increase Throughput
How to Reduce Changeover Time and Increase ThroughputHow to Reduce Changeover Time and Increase Throughput
How to Reduce Changeover Time and Increase ThroughputOH!Manufacturing
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentIRJET Journal
 
IE431F15_CHR948TE_FinalPaper
IE431F15_CHR948TE_FinalPaperIE431F15_CHR948TE_FinalPaper
IE431F15_CHR948TE_FinalPaperArnaud Marquet
 
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIRJET Journal
 

Similar to Abbatelli - BB Mini-Project (20)

Agile survival kit
Agile survival kitAgile survival kit
Agile survival kit
 
M.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis PresentationM.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis Presentation
 
Performance measurement of agile teams harold van heeringen
Performance measurement of agile teams   harold van heeringenPerformance measurement of agile teams   harold van heeringen
Performance measurement of agile teams harold van heeringen
 
Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)
 
Joined document 24_5
Joined document 24_5Joined document 24_5
Joined document 24_5
 
The Ultimate Agile Planning Handbook
The Ultimate Agile Planning HandbookThe Ultimate Agile Planning Handbook
The Ultimate Agile Planning Handbook
 
Summer 2013 Internship Reflection
Summer 2013 Internship ReflectionSummer 2013 Internship Reflection
Summer 2013 Internship Reflection
 
Work Study- Methods Study
Work Study- Methods StudyWork Study- Methods Study
Work Study- Methods Study
 
resume - Alexander Cruz
resume - Alexander Cruz resume - Alexander Cruz
resume - Alexander Cruz
 
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
 
Introduction to Agile & scrum
Introduction to Agile & scrumIntroduction to Agile & scrum
Introduction to Agile & scrum
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPT
 
Agile Hardware Product Development (NextGen NPD plus - MRO shop example) inc...
Agile Hardware Product Development  (NextGen NPD plus - MRO shop example) inc...Agile Hardware Product Development  (NextGen NPD plus - MRO shop example) inc...
Agile Hardware Product Development (NextGen NPD plus - MRO shop example) inc...
 
sandeep sisodia rspl cv
sandeep sisodia rspl cvsandeep sisodia rspl cv
sandeep sisodia rspl cv
 
BAAgileQA
BAAgileQABAAgileQA
BAAgileQA
 
OPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.comOPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.com
 
How to Reduce Changeover Time and Increase Throughput
How to Reduce Changeover Time and Increase ThroughputHow to Reduce Changeover Time and Increase Throughput
How to Reduce Changeover Time and Increase Throughput
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding Department
 
IE431F15_CHR948TE_FinalPaper
IE431F15_CHR948TE_FinalPaperIE431F15_CHR948TE_FinalPaper
IE431F15_CHR948TE_FinalPaper
 
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
 

Abbatelli - BB Mini-Project

  • 1. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli1 Lean Six Sigma Black Belt Mini-Project Extended Education – NCR 9635 Project Title: Setup Time Reduction (Roll) Prepared by Nick Abbatelli nabbatel@calpoly.edu – (408) 838-2097 Company: GM Nameplate (San Jose, CA) August 29th, 2014
  • 2. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli2 EXECUTIVE SUMMARY This Mini-Project was conducted at GM Nameplate in San Jose, CA. GM Nameplate specializes in roll products. Some of the processes include: flexographic printing, digital printing, screen printing, laminating and die cutting. The mission was to reduce setup time of certain production areas in the facility, specifically the flexographic printing areas. Flexographic printing involves unwinding and feeding material into the machine, a printing section, a drying section and then feeding it to a re-winder as a finished roll product. The operational tools consist of rollers (Foundation & Anilox), doctor blades and cylinders (Plate & Impression). Running product through a machine from raw material to finish product account for 20% of the total process on average. More than 70% of the time is spent setting up the machine. An order requires a specific anilox roller, print cylinder and impression cylinder. The impression cylinder is unique to the job because it has a plate that has a logo or cutout per requirements of the job. The plate is mounted onto the impression cylinder before the cylinder is installed. GM Nameplate has an inventory of 5,000+ of these rollers and cylinders. One machine accounts for 72% of these tools. Since the project was on a strict and short timeline, it focused its measurements and analysis on that machine: Nilpeter Flexo Press. The team found the setup time was a little over 68 minutes on average. Following the process of the operators we identified a procedure that could be improved upon. Key tooling are being stored in a separate building on account of storage space in the production area. Operators have to walk over to the separate building, identify and bring back the specified tool to the production area before mounting the plate can even begin. The team recommends improving the identification and planning process so GM Nameplate can reduce the setup time of its Nilpeter machine, ultimately producing more jobs annually.
  • 3. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli3 DEFINE Tool 1: Project Charter Why Tool Selected: This document reveals the goals of the project. It can be revised and changed but must always be referenced to. GM Nameplate created a charter to make sure tasks was laid out correctly and in a timely matter. Interpretation: The Project Charter was reviewed weekly by the project Champion. It gave the team organization to stay on track and keep tasks in proper alignment of each other. Although not every task was completed on time, the charter kept the team on track to the ultimate goal.
  • 4. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli4 DEFINE Tool 2: Process Flow Chart Why Tool Selected: A Process Flow Chart (or Process Map) is used to give a visual representation of the steps in the process. The team wanted to find what processes happen once a job gets placed in the work-in-progress bin of the Roll Department? Interpretation: The process flow chart can improve any process improvement project by increasing the understanding of people involved, flow of information and resources. This chart shows three key processes that must be done before the job can even be ran: identification of tooling, pulling of tooling and the setup, which involves mounting of the tooling pulled.
  • 5. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli5 MEASURE Tool 1: Histogram Why Tool Selected: Gathering data in a spreadsheet can be overwhelming. A Histogram provides a visual representation of the data. The team took data from 1 production aspect of the Roll Department to get a gauge upon: Nilpeter Room. What were common setup times of the Nilpeter machine? [Twenty-five jobs within the month of August 2014 where used] Interpretation: The graph shows a positively skewed set of data with the most common setup time between 60 – 80 minutes. [Note: This data only represents 1 machine out of 5 within the Roll Department. Due to time constraints, this machine was the most viable because it is the only machine that runs constantly 8-hours/day. ]
  • 6. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli6 MEASURE Tool 2: X and Moving Range Chart Why Tool Selected: The team wanted to observe the setup times of the Nilpeter machine in the recent calendar month completed: August 2014. By making an XmR chart, it will produce control limits for the data. Visually viewing the control limits on the chart, the team can clearly identify which job should be investigated and ask the question: Is the process stable? Interpretation: Out of 16 jobs ordered in August 2014, there was an instance where the condition was ‘out-of-control’ from jobs 6 to 7. These jobs need to be looked at closer in detail and investigated for procedure fixes and flaws. Also, investigate job 16, where it was not normal and fell out of the upper control limit.
  • 7. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli7 ANALYZE Tool 1: 5 Why Analysis Why Tool Selected: The team chose to use the 5-Why’s to find a more specific root cause of why roll setup is taking a majority of the roll manufacturing process. The technique proclaims that if you ask “Why?” five times, you can identify an understanding to the ultimate root causes. The team chose to start the ‘Why’ process at, “Why does setup time take so long?”  Nilpeter setup averages over 1 hour o Why does the setup take so long?  Dies and Tooling are bulky. It takes time to walk over to the next-door building and identify the die and/or tooling for the specific job o Why are dies and tooling stored in the next-door building?  Jobs that require previously used dies are warehoused in the building next door because of its large storage space. Often operators are over there multiple times a day o Why multiple trips?  Job tickets buildup throughout the day. Operators only see jobs that are progressing throughout the manufacturing process o Why don’t operators know of future jobs?  There is no warning system in place to tell operators which dies to pull for future jobs ahead. o Why doesn’t Planning Department tell operators the current job schedule? Interpretation: Root Cause – Planning Department should identify dies & tooling work-in- progress better with the operators to lower the number of trips throughout the day next-door.
  • 8. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli8 ANALYZE Tool 2: Hypothesis Testing Why Tool Selected: Operators in the roll department believed setup time takes under an hour. The Six Sigma team decided to use this common estimate as a Null Hypothesis. Interpretation: Running the numbers in EngineRoom using the Hypothesis Testing tool, the results to reject the Null Hypothesis. The mean of ‘Nilpeter Setup Time’ is greater than 60 minutes,
  • 9. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli9 IMPROVE Tool 1: 5S Why Tool Selected: Taking an outsiders perspective inside the Nilpeter Room, it looks dirty and cluttered. There are many distractions inside the room and the 5S tool improves visibility of the process, safety and worker performance. Scan & Sort – Scan the area and sort through unneeded material, equipment, tooling and trash. Old Material Supply Cabinet Behind Machine Set in Order – Tooling and Instruments should be set in place, easy to find at all times. Supplies Organized Tooling Organized
  • 10. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli10 Shine – A clean workspace improves working conditions and the moral of operators. Clean Aisles Standardize – Create Shadow Boards for standard tooling and instruments within each working station Sustain – A 6S board was created within the department for department supervisors to sustain the improvement process. The board also creates friendly departmental competition with audit grades and scores. Interpretation: Although the last 2 S’s could not have been completed due to internship length restrictions, the 5S tool was highly effective within the manufacturing plant. Going through the process with the operators, common remarks were: “I didn’t know when could throw this away,” We can take this out?” and “I haven’t seen anyone use that in a decade.” It proved that taking a simple step back and asking, “Why is this here?” solved many organizational issues.
  • 11. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli11 IMPROVE Tool 2: Pull Scheduling Why Tool Selected: Pull Scheduling consist of many aspects: balanced production, quick set-ups, reducing lot size and standardized work to name a few. For this project, the team focused on quick set-ups. How can the operators decrease setup time? Interpretation: This photo is of the new WIP area for the Nilpeter room. All job orders are looked at, at the beginning of the day and the operators collect plates and cylinders for each job. The red bin is for plates and the bottom shelf is for the cylinders.
  • 12. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli12 CONTROL Tool 1: CHECK Process Why Tool Selected: How could GM Nameplate keep operators accountable for their workstations? Interpretation: This form was created after the 5S activity was completed. It allows supervisors and managers to sustain lean and clean workstations. It also promotes health competition between the production areas amongst the operators.
  • 13. Nick Abbatelli Cal Poly SLO – Business – Industrial Technology 10/14/14 Mini-Project – Abbatelli13 CONTROL Tool 2: Standardized Work Why Tool Selected: How does the operator know which job takes priority? Interpretation: This photo is of the new WIP area for the Nilpeter room. The metallic bins on the top right of the table consists of 3 staggered bins. The farthest back bin represents job to be completed within the given month. The middle bin represents the weekly job orders. The first bin represents job to be done during the day (top priority).