SlideShare a Scribd company logo
1 of 20
Download to read offline
TABLE OF CONTENTS
 01           EXECUTIVE SUMMARY
 02           ERP Project Journey
 03           Engagement Model
 04           Milestones
 05           ERP Assessment Overview Summary
 06           GAP Analysis and Recommendations
 07           MAXIMO
 08           ORACLE FINANCIALS
 09           ORACLE HCM
 12           ERP Achievements
 13           ERP PIR Department Head Workshop
 15           Lessons Learned
 17           Memories




This report has been prepared by GASCO for general information only. Information contained herein has been
obtained from sources deemed reliable and no representation is made as to the accuracy thereof. This includes
government agencies, universities, third party suppliers, etc. GASCO does not guarantee, warrant or represent
that the information contained in this document is correct. Any interested party should undertake their own
inquiries as to the accuracy of the information. GASCOl excludes unequivocally all inferred or implied terms,
conditions and warranties arising out of this document and excludes all liability for loss and damages arising
there from.
EXECUTIVE SUMMARY

As a result of the management discussion in Sir Bani Yas Management
Retreat last January 2011, the CEO initiated the ERP Post Implementation
Review to assess the ERP project’s success level, to identify the gaps and
lessons learnt and to make recommendations for future projects.

The ERP Post Implementation Review (PIR) was conducted over a period of
six months with members from HC, FM, CD, TS, IT and with the assistance
of external subject matter experts. These experts were brought in to assess
the business and IT maturity based on best practices and to come up with
recommendations to bridge the gaps.

The review was undertaken through online surveys, face-to-face interviews
and workshops with key Management and end-users. The overall assess-
ment of the project was relatively positive, as exhibited in the following pages.




                                                                     ERP PIR 01
                                            ERP Post Implementation Review 03
ERP Project Journey
                                                                                                                 [The ERP Project] is a vital enabler
                                                                                                                 of our business, as it constitutes
                                                                                                                 the backbone of so many of internal
                                                                                                                 cross-functional activities. This
                                                                                                                 implementation will be a significant
                                                                                                                 improvement, a major change that will
                                                                                                                 touch every GASCO staff, or
                                                                                                                 contractor engaged in any working
                                                                                                                 relationship with GASCO.

                                                                                                                 – Dr. Yves Pouradier




       ERP Project Initiation                                                                               Review Process
       	     Analyze Project Performance
                                                                                         Review planeed vs Actual objectives
       		                   Award External SME
       		                     Face-to-Face Workshops / Surveys                           Conduct Interviews & Syrveys
       				                              Document Achievements and Lessons Learnt        Achievements & Lessons Learnt
       				                                        Analyze / Verify Findings
                                                                                         Identify Gaps
       				                           		             Design Improvement program
         							 and Engagement Model					                                               Recognize benefits realized
         			                    				                           Present PIR to Management
                                                                                         Formulate Recommendations
       									 PIR PROJECT CLOSURE
                                                                                                             Develop Project Plan

     Jan 2011 Mar 2011   Apr 2011       May 2011    Jun 2011       Jul 2011                                  Build Business Cases




        344                                        3                                               32
                         Online ERP                         Online ERP Project                               Gap Analysis Workshop
                         Applications                       Vendors Satisfaction                             with Maintenance,
                         end-users Satisfaction                                                              Commercial, Human
                                                            Surveys.
                         Surveys.                                                                            Capability, and Finance staff.


                                                                     35
                                                                                   Face-to-Face interviews

                          29         Online ERP Project
                                     Members Satisfaction
                                     Surveys
                                                                                   with SVP, VP and department
                                                                                   heads from TS, CD, FM, HC
                                                                                   and Plants.
02    gasco.com
ERP System Engagement Model
                                                                                          +




An Engagement Model was introduced to monitor the ERP PIR recommendations                     As seen above, the Model provides a restricted process for introducing new initiatives or

implementation and to review and control the new ERP initiatives. The Model consists of       enhancements into the ERP production environment with minimal disruption to the ongoing
three groups: the ERP Steering Committee to set future direction for ERP Solutions,           operations and also to monitor the ongoing issues. As with all projects, user engagement

IT/Business Department Heads (Custodians) to monitor and control the initiatives,             is a key factor to success, which was why GASCO tried to include the end users in as many

and the systems’ custodian focal points to formulate enhancement initiatives and to           phases of the ERP project as possible.

provide feedback on the success of enhancements.
                                                                                                                                                                            ERP PIR   03
Milestones
                                                                                                                                     PIR Project has all the right
                                                                                                                                     ingredients for success…
                                                                                                                                     Management support, End
                                                                                                                                     Users interest and support,
                                                                                                                                     and committed and
                                                                                                                                     competent Team Members.
            Pre - Implementation Phase
            Implementation Phase                                                                                                      – Khalid al Katheeri
            GO Live - Drop 1 “ORACLE HCM”
            GO Live - Drop 2 “MAXIMO & ORACLE Financials”
                                                                           Actual
            Post - Implementation Phase
            Post - Implementation Review                                   Planned




     2007        2008                             2009                                     2010                                   2011


     Sept                    Apr May                         Mar Apr May Jun                               May Jun                  Jan                         Jun


                                                         It was a golden opportunity for us to review the ERP Project    The ERP Project is a successful achievement by
                                                         Implementation to highlight the areas of improvement, lessons   having and adopting a well-proposed plan and
                                                         learnt and make sure that the ERP Project had solved the        good team involvement from sites and HQ.
                                                         problem that it was designed to address. Thank you for the      Well done!
                                                         management who is always supporting us towards
                                                         excellence.                                                     - Ismail al Hosani

                                                            – Jamal Omar Daqruq

04   gasco.com
ERP PIR Assessment Overview Summary
The ERP PIR assessment was divided into two main categories: the              first   was an

assessment of planned versus actual objectives, deliverables, scope, schedule, expenses
                                                                                                                                           The second part of the review was to assess the
and resources.
                                                                                                                                           effectiveness of existing ERP solutions and business
The below chart illustrates the assessment results of planned versus actual achieved project
                                                                                                                                           process gaps against leading best practices for
objectives for Maximo, ORACLE HCM, ORACLE Financials and the Infrastructure
                                                                                                                                           Maintenance, Commercial, Human Resource and
subprojects. The major deviations were related to delays in implementing the Budget
                                                                                                                                           Finance.
management module [ORACLE Hyperion] and Journals workflow approval; both are

expected to be deployed by Q3 2011.
                                                                                               23

              g rade                                                                           18
     im  o Up
 Max                                                                  l
                                     HC  M                  Fin ancia                          14
                                                                                               13
                                 CLE                    CLE
    10
                              ORA                   ORA
                                                                            Infra
                                                                                 struc
                                                                                      ture
                                                                                                8

     5                                                                                          7

     4
                                                                                                4




     1                                                                                                  es usiness                     s         s      s
                                                                                                    issu                   ons      ue        es
                                                                                                                                                    ion          s ss
                                                                                                                                                               ue usine ases ions
                                                                                                                                                                                         s       ss       s
                                                                                                           b      es   acti      iss       sin es
                                                                                                                                         bu cas act         iss
                                                                                                                                                                                       ue busineases tion
         No / Minor / Major    No / Minor / Major    No / Minor / Major   No / Minor / Major                   cas                                               b     c
                                                                                                                                                                           ac
                                                                                                                                                                              t     iss        c
                                                                                                                                                                                                    ac


         Deviations
                                                                                               Maximo & Maintenance              Maximo & CD            ORACLE HCM                  ORACLE
                                                          TOTAL : 28 No Deviations             business processes                business               &HC business                FINANCIAL & FM
                                                                  12 Minor Deviations                                            processes              processes                   processes
                                                                   2 Major Deviations

                                                                                                                                            73 issues were found, with the issues falling into
                                                                                                                                            technical, process and/or human categories.
                                                                                                                A TOTAL OF
                                                                                                                                            26 business cases and 33 quick win
                                                                                                                                            actions were generated as recommendations to
                                                                                                                                            bridge the gaps.



 During the meeting

                                                                                                                                                                                                        ERP PIR   05
Comparison

                                                     This section consolidates
                                                        all gaps identified
                                                      during the workshops,
                                                       project performance
              The effectiveness                              deviations
          of existing ERP solutions                 and ORACLE Financial/HCM                                 A strategy
         and business process gaps                           snag lists.                                  and project plan
           were assessed against                                                                       have been developed
           leading best practices                                                                     for the implementation
       for Maintenance, Commercial,                                                                 of these recommendations.
       Human Resource and Finance.




                                                 Application Satisfaction Survey:
                                Overall how would you rank your satisfaction with the following systems?



                   Maximo                           Oracle Financials                                Oracle HCM


                             6% Fair                              12% Fair                                           5% Fair



             68%                26%               44%                         44%                68%                    27%
             Excellent       Average                                                                                 Average
                                                     Excellent          Average                  Excellent

 gasco.com
Thank you, IT,
            for all your support.                                                                                                     GAP Analysis
            - Ahmed Bawazir


                                                                                                 Maximo
                                                           Gaps                        Recommendations
                                          Maximo is slow from Plant Sites      • Better Coordination among IT Teams
                                                                               • Analysis of Maximo Performance Issue by the Joint IT Team (team should be comprised of: 	
                                                                                 Maximo Support team, IT Systems & Database team, IT Security Team, IT Network team)
                                             Accuracy of data in Maximo        • Analyze the Data Quality Errors in Maximo (especially in description of Assets, Locations 		
                                                                                 and assignment of Asset to Locations)
                                                                               • Data Cleansing Exercise (ensure that Accuracy, Completeness and Uniqueness of data is 		
                                                                                 achieved)
                                                                               • Review of Quality Check Process before entering the data in Maximo
                                                                               • Standardization of Data Entry in Maximo by agreeing on Nomenclature and centralizing the 	
                                                                                 data entry of new asset
                        Maximo is not being used for HSE requirements          • Use Safety sub module to get directions from Safety department
                                                                               • Use Hazardous Material functionality
                                                                               • Automate and Integrate the Permit to Work Process
                  Commercial Directory is not utilized Comprehensively         • Reports should be generated and reviewed by Commercial Management to identify the lack 	
                                                                                 of utilization of Commercial Directory
                                                                               • Category Supplier History should be shared with Bid Opening Committee
                                                                               • Implementation of Comprehensive Suppliers Performance Evaluation System
                                    Lengthy Supplier Pre-qualification cycle   • Introduce comprehensive KPI to monitor supplier prequalification time
                                                                               • Simplification of Prequalification Process for Non Critical Categories
                                                                               • Unification of Supplier Prequalification Process and Directory across all Groups
Budget Check for Non Term contracts is done at the Release Order level
                                                                               • Budget check before raising a Non Term Contract

     Documentation is not updated once Change Requests are entered             • Update and Preparation of all System Specifications
                                                                               • Introduction of Design Authority and Change Control Procedure

                                               Lack of System Enviroments      • Introduction of Design Authority and Change Control Procedure

                                                                               • Report Committee should formulate GASCO’S Reporting Strategy
                                       Lack of Strategy for Reporting Tools



                                                                                                                                                                      ERP PIR   07
ERP Project is one way


 GAP Analysis
                                                                                                                             towards continuous
                                                                                                                             improvement and
                                                                                                                             enhancing our business
                                                                                                                             processes. Good luck!


                                                                                                                             - Hassan Al Hammadi




         ORACLE Financials
                                                          Gaps                    Recommendations
                                          Delay in resolving technical issues   • Conduct Regular Meetings with Finance Team
                                                                                • Introduction of Design Authority and Change Control Procedure
                                         Delay in Month-End Period Closing      • Establish Payables Task Force Committee to investigate Payables process and 	
                                                                                 eliminate manual controls and other non-value added activities in paying invoices
                                                                                • Review and agree holistic integrated Period-End Closure procedure to meet the 	
                                                                                 GASCO target (and strive to achieve industry benchmark)
                                       Cash Management Process is manual        • Configure Oracle to enable these available functionalities

                    Major Projects Commitments are not captured in System       • Capture Major Projects commitments in system

                                    Budgeting Process is not fully automated    • Ensure end-to-end Budgeting Process before Hyperion implementation
                                                                                • Increase the approval limits of the Accountant and Senior Accountant to reduce 	
            A lot of Manual work (manual verification) for Payments processes    the work of Head of AP
                                                                                • Establish Payables Task Force Committee to investigate Payables process and 	
                                                                                 eliminate manual controls and other non-value added activities in paying invoices
                                                                                • Review and agree holistic integrated Period-End Closure procedure to meet the 	
                                                                                 GASCO target (and strive to achieve industry benchmark)
                                                                                • Implement Oracle BI Applications and OBIEE
                                                     Lack of Financials KPIs
                                                                                • Introduce financial KPIs according to IBM Best practices




08   gasco.com
March 09th marks the beginning of the ERP


                                                                                                                             GAP Analysis
Project Deliverables reaching the end users.


   Memories
A massive amount of energy and time has
gone in ensuring that your requirements and
quality standards are reflected in the final
product - Oracle HCM.


- Yves Pouradier




                                                                                  ORACLE HCM
                                                          Gaps                    Recommendations
                                        Data Management & Quality Issues      • Conduct an Effective Awareness Program Targeting Oracle End-Users
                                                                              • Data Validation / Check Points
                                                                              • Conduct an Effective Awareness Program Targeting Oracle End-Users
                                                Lack of Reliable Reporting
                                                                              • Implement and Deploy Business Intelligence Reporting Tool
                                                                              • Conduct an Effective Awareness Program Targeting Oracle End-Users
                                               Limited Analytical Reporting
                                                                              • Data Validation / Check Points
                                                                              • Implement and Deploy Business Intelligence Reporting Tool

                        Oracle Competency Management not being used           • Integrated Talent Management Framework:
                                                                              	        Deploy Oracle Self-Service
                                                                              	        Build a “Smart” Skills Matrix
                                                                              	        Implement Oracle Talent Management Solution
                                      Learning Management not leveraged
                                                                              • Integrated Talent Management Framework
                          Performance Appraisal Management not utilized

                                           Urgent Payments outside Payroll    • Adhere to the ad hoc payroll run and quick pay such that employee payments outside 	
                                                                                the payroll can be liminated
                                Contractual Staff Salary Payment Process      • Contractual Staff Payroll to be streamlined via Oracle.
                                                                              • Carry out Business Process Realignment exercise escorted by effectual Change 		
                                                                                Managment
                                    Paper-based Expense Reimbursement         • Automate Expense Reimbursement
                                                                              • Carry out Business Process Realignment exercise escorted by effectual Change		
                                                                                Management
                                                                                                                                                           ERP PIR 09
We are proud that GASCO


                                                                                              ERP Achievements
is implemented state of the
art professional tools, world
class system, including new IT
insfrastructure technology, all of                                            +
which contributes to our corporate
journey toward ecxellence.


- Adel Salem Alkaff

                                                                                  • The ERP Project experience introduced more skilled internal
                                                                                  support resources in both business and IT leading to major
                              ICT Achievement Award
                                                                                  improvements in support quality and response
                              GASCO ERP Maximo Project won the ICT                time.
                        Achievement Awards of Best Energy Deployment
                                 of the year 2010 over the Middle East.
                                                                                  • Infrastructure was upgraded to the latest technology
                                                                                  ensuring better security, performance and availability.
                          The ICT Achievement Awards honours the high
                          achievers and trend-setters of the IT industry of
                                                                                  • Automated number of Financial & Human Capability processes
                                                                the region.
                                                                                  resulted in improving the processing time and elimination of
                                                                                  manual intervention.

                                                                                  • Automated the Maximo Maintenance and Commercial processes.
                                                                                  As a result, the processing time and procedure compliance was im-
              2010 IBM Maximo Supply Chain                                        proved and more than 1,156,000 workflows were initiated and
                                                                                  completed since the go live date.
                        Best Practice Award
                                                                                  • More than 200 visits to Plants.
                                                            Innovation
                                                 Return on Investment
                                       Empowering the User Community              • More than 1,000 workshops conducted during the ERP
                                                        Best Practices            Project.

                                                                                                                         +
                                                                                  • Fulltime members spent 10,000 additional working hours.




                                                                                                                                            ERP PIR   11
Last year ERP project planned 09th March 2009 for its de-
                       liverables, and I am pleased to announce that the First ERP
                       deliverable Oracle HCM is live and operational as of Today,
                       09th March 2009 as promised.

                       From today the single source of HR data is Oracle HCM.
                       It is now up to all of us to utilize this new application to its
                       full potential and ensure that the expected benefits to the
                       organisation are realized rapidly.

I would like to thank the Project Team for their continious dedication and the
very long working hours they spent on the project over the past months.
I would like also to recognize all other employees who contributed to the
ERP Project in a genuine spirit of openess, trust and teamwork, thus
ensuring this succes.

Best Regards,

Mohamed A. Sahoo Al - Suwaidi
General Manager , GASCO
PIR Dept Head Workshop
+




                                        IR
                                   ERP P 011
                                      NE 2
                                 23 JU hop
                                   works




The ERP Post-Implementation Review was held at Al Rimal Club on 23 June to
present the ERP Maximo and Oracle findings and to discuss the feedback from
the three-year long project.

Peter Verhulst (SVP, CS) welcomed the guests and was soon followed by Ben
Stanberry from the International Institute of Research (IIR), who was brought in to
discuss Change Management and how GASCO can benefit from this inevitable
organizational process.

Mr. Stanberry created a ‘crime scene’ to demonstrate how the 12 most common
corporate characteristics can ‘kill’ change and how GASCO can better assimilate
to and prepare for changes in the future. In the afternoon, IBM external
consultants held workshops for Maximo and Oracle users.

Also, a yoga instructor was brought in to show the team how stretching and
breathing can help to relieve stress.




                                                                           ERP PIR    13
Improvement
ERP Implementation, we are introducing
                   a very powerful set of systems, but
                   we need to remember that we will be
                   working with data migrated from different
                                                                                                                                         Lessons Learnt
                   legacy systems running on different
                   platforms. It is critical that activeties like
                   data clean up and data migration are                                                                                       Overall did you think the ERP was a succes?
                   approached in a comprehensive manner,
                   and all aspects are considered, tested                                                                                                            no          yes
                   and quality reviewd.


                   - Abdulla S. Al Minhali
                                                                                                                               31                    32                     32


                                                                                                                  4                     3
       ACHIEVED                                                                                                                                                3
USER PARTICIPATION
	         Encourage the participation of low level users who use the system more                            Were the project
                                                                                                            objectives achieved?      Did the implmentation
frequently in all project phases, especially requirements. They should be identified early on
                                                                                                                                      process go according
and involved in decision making to get their buy-in and manage their expectations.
                                                                                                                                      to plan?                       Was the project
(Source: Senior Mgmt Survey)
                                                                                                                                                              successful in your view?
VENDOR SUPPORT
	         Ensure vendor is certified and qualified and has the required competencies and
capabilities. Moreover, vendor support continuity after the implementation is completed is            MISSED
essential to increase awareness about the system. An agreement should be signed at the
project start to ensure their commitment. (Source: Senior Mgmt Survey)                          ERP EXPERIENCE	
                                                                                                	          No comprehensive business case was developed for the ERP Project. The
TEAMWORK                                                                                        business case should clearly state the expected business benefits and define measurable
	         The dedicated ERP interface team to test the process from end-to-end point of         objectives, goals and deliverables.
view contributed in minimizing the integration issues. (Source: PIR Presentation) 	             	          Data cleansing exercise was carried out during the ERP Project, but it was not
	         Grouping and Allocating Project members from business, IT, and external vendor        sufficient. More attention should be given to the ERP data quality.
in one location increased team’s productivity. (Source: PIR Presentation)
                                                                                                COMMUNICATION
MANAGEMENT	                                                                                     	        Change Management was not carried out properly and some ERP applications
	         Planning and simulating the ERP cut-off date more than 4 times minimized the Go       faced user resistance.
Live risks and improved the team readiness. (Source: PIR Presentation)
	         The ERP Systems deployment was smooth through the Soft & Safe Drops                   MANAGEMENT	
approach, which increased the stability probability and minimized the culture shock.            	         More sites visits need to be conducted to ensure the implementer capabilities,
(Source: PIR Presentation)                                                                      collect lessons learnt and to overcome the ERP challenges.

COMMUNICATION                                                                                   CORE-TEAM CONTINUITY
	         The ERP Project was successful in managing the communication process so that          	        Core team continuity is the driver of the project: Part-time involvement of some of
all stakeholders were informed of the project status on-time. Many methods were used,           the project team members and ending of the steering committee meetings caused a gap
including web portals, emails, and newsletters. (Source: PIR Presentation)                      towards the end.
                                                                                                                                                                                   ERP PIR     15
-
    GASCO’s business enviroment is one of significant growth. ERP is a
    necessity to accomodate this growth. Successful implementation of ERP
    requires a preparedness of our employees to accept change!


    I would urge every one to actively acquire the knowledge of how to work
    with the new system and take full advantages of the training program
    provided by the project.
    As extra, E-Learning tools will be provided, for all those who wish tp practise
    on their time, at their pace, and focus on a specific subject. This is an
    opportunity to enhance individual skills as well as GASCO’s business.


    - Cyrilles Huijsmans
    Assistant General Manager (Operations)

                                                              System integration, utilizing standard interfaces and
                                                              taking advantage of best practices, will help all of us
                                                              to access quality information immediately, in order
                                                              to take decisions in time. More robust interfaces
                                                              between Maximo and the Oracle are amongst the
                                                              major benefits we will experience from the new ERP
                                                              slution.


                                                              - Rashed Abdulla Al Shamsi,
                                                              AGM(A)
Memories




      ERP PIR   17
Bookgasco 06draft2

More Related Content

What's hot

IT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service StrategyIT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service StrategyNUS-ISS
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Rhodes.donna
Rhodes.donnaRhodes.donna
Rhodes.donnaNASAPMC
 
Healy edward
Healy edwardHealy edward
Healy edwardNASAPMC
 
How to set up initiatives portfolio management
How to set up initiatives portfolio managementHow to set up initiatives portfolio management
How to set up initiatives portfolio managementJuha-Matti Saario
 
Starting the ERP Discsussion
Starting the ERP DiscsussionStarting the ERP Discsussion
Starting the ERP DiscsussionBarry Cole
 
Romeo.mitchell
Romeo.mitchellRomeo.mitchell
Romeo.mitchellNASAPMC
 
RajeshKanchi_Resume_Latest_2016
RajeshKanchi_Resume_Latest_2016RajeshKanchi_Resume_Latest_2016
RajeshKanchi_Resume_Latest_2016Rajesh Kanchi
 
Day 1 p3 - project and portfolio management
Day 1   p3 - project and portfolio managementDay 1   p3 - project and portfolio management
Day 1 p3 - project and portfolio managementLilian Schaffer
 
Archibald di filippo_comprehensive_plc_model_final
Archibald di filippo_comprehensive_plc_model_finalArchibald di filippo_comprehensive_plc_model_final
Archibald di filippo_comprehensive_plc_model_finalsansharmajs
 
Portfolio Management Pipeline
Portfolio Management PipelinePortfolio Management Pipeline
Portfolio Management Pipelinerichardbellatcity
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingGlen Alleman
 
Mega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas IndustryMega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas IndustryStephen_Forster
 
RepublicCaseStudyIII
RepublicCaseStudyIIIRepublicCaseStudyIII
RepublicCaseStudyIIIJason Coslow
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 

What's hot (20)

IT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service StrategyIT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
 
Ranking portfolio initiatives, Bernard Marshall, june 2012
Ranking portfolio initiatives, Bernard Marshall, june 2012Ranking portfolio initiatives, Bernard Marshall, june 2012
Ranking portfolio initiatives, Bernard Marshall, june 2012
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Rhodes.donna
Rhodes.donnaRhodes.donna
Rhodes.donna
 
Healy edward
Healy edwardHealy edward
Healy edward
 
How to set up initiatives portfolio management
How to set up initiatives portfolio managementHow to set up initiatives portfolio management
How to set up initiatives portfolio management
 
Starting the ERP Discsussion
Starting the ERP DiscsussionStarting the ERP Discsussion
Starting the ERP Discsussion
 
Romeo.mitchell
Romeo.mitchellRomeo.mitchell
Romeo.mitchell
 
RajeshKanchi_Resume_Latest_2016
RajeshKanchi_Resume_Latest_2016RajeshKanchi_Resume_Latest_2016
RajeshKanchi_Resume_Latest_2016
 
Day 1 p3 - project and portfolio management
Day 1   p3 - project and portfolio managementDay 1   p3 - project and portfolio management
Day 1 p3 - project and portfolio management
 
ASAP 8.0 Methodology
ASAP 8.0 MethodologyASAP 8.0 Methodology
ASAP 8.0 Methodology
 
Archibald di filippo_comprehensive_plc_model_final
Archibald di filippo_comprehensive_plc_model_finalArchibald di filippo_comprehensive_plc_model_final
Archibald di filippo_comprehensive_plc_model_final
 
Portfolio Management Pipeline
Portfolio Management PipelinePortfolio Management Pipeline
Portfolio Management Pipeline
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Understand SAP ASAP 8.0
Understand SAP ASAP 8.0Understand SAP ASAP 8.0
Understand SAP ASAP 8.0
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
 
PMO 101
PMO 101PMO 101
PMO 101
 
Mega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas IndustryMega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas Industry
 
RepublicCaseStudyIII
RepublicCaseStudyIIIRepublicCaseStudyIII
RepublicCaseStudyIII
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 

Viewers also liked

Gasco Presentation Final
Gasco Presentation FinalGasco Presentation Final
Gasco Presentation FinalMahin Rahman
 
Case Study- Gasco
Case Study- Gasco Case Study- Gasco
Case Study- Gasco Addvantum
 
06 09 Retaining Talent (34 Slides)
06 09 Retaining Talent (34 Slides)06 09 Retaining Talent (34 Slides)
06 09 Retaining Talent (34 Slides)tsbartridge
 
PETROJET Training Certificate
PETROJET Training CertificatePETROJET Training Certificate
PETROJET Training CertificateIslam Ahmed
 
PetroJet Presentation
PetroJet PresentationPetroJet Presentation
PetroJet PresentationUSherwood
 
Bel mechanical engineering interview questions
Bel mechanical engineering interview questionsBel mechanical engineering interview questions
Bel mechanical engineering interview questionsPrashant Kumar
 
Khalda Petroleum company
Khalda Petroleum companyKhalda Petroleum company
Khalda Petroleum companyMahmoud Hamdy
 
Belzona Oil Presentation
Belzona Oil PresentationBelzona Oil Presentation
Belzona Oil Presentationguest6e90fd7
 
NPCIL Mechanical Engineering Interview Experience
NPCIL Mechanical Engineering Interview ExperienceNPCIL Mechanical Engineering Interview Experience
NPCIL Mechanical Engineering Interview ExperienceParesh Gujarati
 
Mechanical interview questions
Mechanical interview questionsMechanical interview questions
Mechanical interview questionsPrashant Kumar
 
Interview Questions for Mechanical Engineering Students
Interview Questions for Mechanical Engineering StudentsInterview Questions for Mechanical Engineering Students
Interview Questions for Mechanical Engineering StudentsMoredhvaj giri
 
Top 7 mechanical engineer interview questions answers
Top 7 mechanical engineer interview questions answersTop 7 mechanical engineer interview questions answers
Top 7 mechanical engineer interview questions answersjob-interview-questions
 
19 comptency questions and answers
19 comptency questions and answers19 comptency questions and answers
19 comptency questions and answersNikhil367
 
200 top most steam boilers, engines, nozzles and turbines mechanical engine...
200 top most steam boilers, engines, nozzles and turbines   mechanical engine...200 top most steam boilers, engines, nozzles and turbines   mechanical engine...
200 top most steam boilers, engines, nozzles and turbines mechanical engine...Dr. Qaisar Nadeem
 

Viewers also liked (19)

2761abdulla
2761abdulla2761abdulla
2761abdulla
 
Gasco Presentation Final
Gasco Presentation FinalGasco Presentation Final
Gasco Presentation Final
 
Case Study- Gasco
Case Study- Gasco Case Study- Gasco
Case Study- Gasco
 
06 09 Retaining Talent (34 Slides)
06 09 Retaining Talent (34 Slides)06 09 Retaining Talent (34 Slides)
06 09 Retaining Talent (34 Slides)
 
PETROJET Training Certificate
PETROJET Training CertificatePETROJET Training Certificate
PETROJET Training Certificate
 
PetroJet Presentation
PetroJet PresentationPetroJet Presentation
PetroJet Presentation
 
Bel mechanical engineering interview questions
Bel mechanical engineering interview questionsBel mechanical engineering interview questions
Bel mechanical engineering interview questions
 
Khalda - HPS June-2004 - SOE
Khalda - HPS June-2004 - SOEKhalda - HPS June-2004 - SOE
Khalda - HPS June-2004 - SOE
 
Khalda Petroleum company
Khalda Petroleum companyKhalda Petroleum company
Khalda Petroleum company
 
New PetroSavers Presentation
New PetroSavers PresentationNew PetroSavers Presentation
New PetroSavers Presentation
 
November 20
November  20November  20
November 20
 
Belzona Oil Presentation
Belzona Oil PresentationBelzona Oil Presentation
Belzona Oil Presentation
 
NPCIL Mechanical Engineering Interview Experience
NPCIL Mechanical Engineering Interview ExperienceNPCIL Mechanical Engineering Interview Experience
NPCIL Mechanical Engineering Interview Experience
 
Mechanical interview questions
Mechanical interview questionsMechanical interview questions
Mechanical interview questions
 
Interview Questions for Mechanical Engineering Students
Interview Questions for Mechanical Engineering StudentsInterview Questions for Mechanical Engineering Students
Interview Questions for Mechanical Engineering Students
 
Top 7 mechanical engineer interview questions answers
Top 7 mechanical engineer interview questions answersTop 7 mechanical engineer interview questions answers
Top 7 mechanical engineer interview questions answers
 
19 comptency questions and answers
19 comptency questions and answers19 comptency questions and answers
19 comptency questions and answers
 
Smart Answers in Interview
Smart Answers in InterviewSmart Answers in Interview
Smart Answers in Interview
 
200 top most steam boilers, engines, nozzles and turbines mechanical engine...
200 top most steam boilers, engines, nozzles and turbines   mechanical engine...200 top most steam boilers, engines, nozzles and turbines   mechanical engine...
200 top most steam boilers, engines, nozzles and turbines mechanical engine...
 

Similar to Bookgasco 06draft2

Considerations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentConsiderations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentHelene Heller, PMP
 
Project management best practices
Project management best practicesProject management best practices
Project management best practiceswalkerswu
 
Ds Erp Practice Overview 0403081
Ds Erp Practice Overview 0403081Ds Erp Practice Overview 0403081
Ds Erp Practice Overview 0403081kcompton
 
Sap implementation by priya pangam
Sap implementation by priya pangamSap implementation by priya pangam
Sap implementation by priya pangamamol1212
 
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdfPrimavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdfInSync2011
 
Erp Logic Corporate Brochure
Erp Logic Corporate BrochureErp Logic Corporate Brochure
Erp Logic Corporate Brochurecaldnambi
 
Alta Bering Retail and Consumer Industry Solutions
Alta Bering Retail and Consumer Industry SolutionsAlta Bering Retail and Consumer Industry Solutions
Alta Bering Retail and Consumer Industry SolutionsLevend Beriker
 
What Is ERP And How To Go About It
What Is ERP And How To Go About ItWhat Is ERP And How To Go About It
What Is ERP And How To Go About ItNauman Majeed
 
Erp post implementation audit
Erp post implementation auditErp post implementation audit
Erp post implementation auditvelcomerp
 
A Critical Success Factors Model For Enterprise Resource Planning Implementation
A Critical Success Factors Model For Enterprise Resource Planning ImplementationA Critical Success Factors Model For Enterprise Resource Planning Implementation
A Critical Success Factors Model For Enterprise Resource Planning ImplementationJoko Sriyanto
 
Enterprise Resource Planning(ERP)
Enterprise Resource Planning(ERP)Enterprise Resource Planning(ERP)
Enterprise Resource Planning(ERP)Tej Kiran
 
ERP: Start The Discussion
ERP: Start The DiscussionERP: Start The Discussion
ERP: Start The DiscussionBarry Cole
 
Project Portfolio Management
Project Portfolio ManagementProject Portfolio Management
Project Portfolio ManagementAnand Subramaniam
 
Worker microcosm hr online
Worker microcosm hr onlineWorker microcosm hr online
Worker microcosm hr onlinetjabali
 

Similar to Bookgasco 06draft2 (20)

Considerations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentConsiderations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT Investment
 
10.1.1.87.8236
10.1.1.87.823610.1.1.87.8236
10.1.1.87.8236
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
Ds Erp Practice Overview 0403081
Ds Erp Practice Overview 0403081Ds Erp Practice Overview 0403081
Ds Erp Practice Overview 0403081
 
Sap implementation by priya pangam
Sap implementation by priya pangamSap implementation by priya pangam
Sap implementation by priya pangam
 
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdfPrimavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
 
ERP For Univ
ERP For UnivERP For Univ
ERP For Univ
 
Erp Logic Corporate Brochure
Erp Logic Corporate BrochureErp Logic Corporate Brochure
Erp Logic Corporate Brochure
 
US DOT BPR Example Model
US DOT BPR Example ModelUS DOT BPR Example Model
US DOT BPR Example Model
 
Alta Bering Retail and Consumer Industry Solutions
Alta Bering Retail and Consumer Industry SolutionsAlta Bering Retail and Consumer Industry Solutions
Alta Bering Retail and Consumer Industry Solutions
 
What Is ERP And How To Go About It
What Is ERP And How To Go About ItWhat Is ERP And How To Go About It
What Is ERP And How To Go About It
 
Erp post implementation audit
Erp post implementation auditErp post implementation audit
Erp post implementation audit
 
A Critical Success Factors Model For Enterprise Resource Planning Implementation
A Critical Success Factors Model For Enterprise Resource Planning ImplementationA Critical Success Factors Model For Enterprise Resource Planning Implementation
A Critical Success Factors Model For Enterprise Resource Planning Implementation
 
Enterprise Resource Planning(ERP)
Enterprise Resource Planning(ERP)Enterprise Resource Planning(ERP)
Enterprise Resource Planning(ERP)
 
ERP: Start The Discussion
ERP: Start The DiscussionERP: Start The Discussion
ERP: Start The Discussion
 
Project Portfolio Management
Project Portfolio ManagementProject Portfolio Management
Project Portfolio Management
 
Worker microcosm hr online
Worker microcosm hr onlineWorker microcosm hr online
Worker microcosm hr online
 
Erp
ErpErp
Erp
 
OpenERP for Hologram Industry
OpenERP for Hologram IndustryOpenERP for Hologram Industry
OpenERP for Hologram Industry
 
Strategic management ppt
Strategic management pptStrategic management ppt
Strategic management ppt
 

Bookgasco 06draft2

  • 1.
  • 2. TABLE OF CONTENTS 01 EXECUTIVE SUMMARY 02 ERP Project Journey 03 Engagement Model 04 Milestones 05 ERP Assessment Overview Summary 06 GAP Analysis and Recommendations 07 MAXIMO 08 ORACLE FINANCIALS 09 ORACLE HCM 12 ERP Achievements 13 ERP PIR Department Head Workshop 15 Lessons Learned 17 Memories This report has been prepared by GASCO for general information only. Information contained herein has been obtained from sources deemed reliable and no representation is made as to the accuracy thereof. This includes government agencies, universities, third party suppliers, etc. GASCO does not guarantee, warrant or represent that the information contained in this document is correct. Any interested party should undertake their own inquiries as to the accuracy of the information. GASCOl excludes unequivocally all inferred or implied terms, conditions and warranties arising out of this document and excludes all liability for loss and damages arising there from.
  • 3. EXECUTIVE SUMMARY As a result of the management discussion in Sir Bani Yas Management Retreat last January 2011, the CEO initiated the ERP Post Implementation Review to assess the ERP project’s success level, to identify the gaps and lessons learnt and to make recommendations for future projects. The ERP Post Implementation Review (PIR) was conducted over a period of six months with members from HC, FM, CD, TS, IT and with the assistance of external subject matter experts. These experts were brought in to assess the business and IT maturity based on best practices and to come up with recommendations to bridge the gaps. The review was undertaken through online surveys, face-to-face interviews and workshops with key Management and end-users. The overall assess- ment of the project was relatively positive, as exhibited in the following pages. ERP PIR 01 ERP Post Implementation Review 03
  • 4. ERP Project Journey [The ERP Project] is a vital enabler of our business, as it constitutes the backbone of so many of internal cross-functional activities. This implementation will be a significant improvement, a major change that will touch every GASCO staff, or contractor engaged in any working relationship with GASCO. – Dr. Yves Pouradier ERP Project Initiation Review Process Analyze Project Performance Review planeed vs Actual objectives Award External SME Face-to-Face Workshops / Surveys Conduct Interviews & Syrveys Document Achievements and Lessons Learnt Achievements & Lessons Learnt Analyze / Verify Findings Identify Gaps Design Improvement program and Engagement Model Recognize benefits realized Present PIR to Management Formulate Recommendations PIR PROJECT CLOSURE Develop Project Plan Jan 2011 Mar 2011 Apr 2011 May 2011 Jun 2011 Jul 2011 Build Business Cases 344 3 32 Online ERP Online ERP Project Gap Analysis Workshop Applications Vendors Satisfaction with Maintenance, end-users Satisfaction Commercial, Human Surveys. Surveys. Capability, and Finance staff. 35 Face-to-Face interviews 29 Online ERP Project Members Satisfaction Surveys with SVP, VP and department heads from TS, CD, FM, HC and Plants. 02 gasco.com
  • 5. ERP System Engagement Model + An Engagement Model was introduced to monitor the ERP PIR recommendations As seen above, the Model provides a restricted process for introducing new initiatives or implementation and to review and control the new ERP initiatives. The Model consists of enhancements into the ERP production environment with minimal disruption to the ongoing three groups: the ERP Steering Committee to set future direction for ERP Solutions, operations and also to monitor the ongoing issues. As with all projects, user engagement IT/Business Department Heads (Custodians) to monitor and control the initiatives, is a key factor to success, which was why GASCO tried to include the end users in as many and the systems’ custodian focal points to formulate enhancement initiatives and to phases of the ERP project as possible. provide feedback on the success of enhancements. ERP PIR 03
  • 6. Milestones PIR Project has all the right ingredients for success… Management support, End Users interest and support, and committed and competent Team Members. Pre - Implementation Phase Implementation Phase – Khalid al Katheeri GO Live - Drop 1 “ORACLE HCM” GO Live - Drop 2 “MAXIMO & ORACLE Financials” Actual Post - Implementation Phase Post - Implementation Review Planned 2007 2008 2009 2010 2011 Sept Apr May Mar Apr May Jun May Jun Jan Jun It was a golden opportunity for us to review the ERP Project The ERP Project is a successful achievement by Implementation to highlight the areas of improvement, lessons having and adopting a well-proposed plan and learnt and make sure that the ERP Project had solved the good team involvement from sites and HQ. problem that it was designed to address. Thank you for the Well done! management who is always supporting us towards excellence. - Ismail al Hosani – Jamal Omar Daqruq 04 gasco.com
  • 7. ERP PIR Assessment Overview Summary The ERP PIR assessment was divided into two main categories: the first was an assessment of planned versus actual objectives, deliverables, scope, schedule, expenses The second part of the review was to assess the and resources. effectiveness of existing ERP solutions and business The below chart illustrates the assessment results of planned versus actual achieved project process gaps against leading best practices for objectives for Maximo, ORACLE HCM, ORACLE Financials and the Infrastructure Maintenance, Commercial, Human Resource and subprojects. The major deviations were related to delays in implementing the Budget Finance. management module [ORACLE Hyperion] and Journals workflow approval; both are expected to be deployed by Q3 2011. 23 g rade 18 im o Up Max l HC M Fin ancia 14 13 CLE CLE 10 ORA ORA Infra struc ture 8 5 7 4 4 1 es usiness s s s issu ons ue es ion s ss ue usine ases ions s ss s b es acti iss sin es bu cas act iss ue busineases tion No / Minor / Major No / Minor / Major No / Minor / Major No / Minor / Major cas b c ac t iss c ac Deviations Maximo & Maintenance Maximo & CD ORACLE HCM ORACLE TOTAL : 28 No Deviations business processes business &HC business FINANCIAL & FM 12 Minor Deviations processes processes processes 2 Major Deviations 73 issues were found, with the issues falling into technical, process and/or human categories. A TOTAL OF 26 business cases and 33 quick win actions were generated as recommendations to bridge the gaps. During the meeting ERP PIR 05
  • 8. Comparison This section consolidates all gaps identified during the workshops, project performance The effectiveness deviations of existing ERP solutions and ORACLE Financial/HCM A strategy and business process gaps snag lists. and project plan were assessed against have been developed leading best practices for the implementation for Maintenance, Commercial, of these recommendations. Human Resource and Finance. Application Satisfaction Survey: Overall how would you rank your satisfaction with the following systems? Maximo Oracle Financials Oracle HCM 6% Fair 12% Fair 5% Fair 68% 26% 44% 44% 68% 27% Excellent Average Average Excellent Average Excellent gasco.com
  • 9. Thank you, IT, for all your support. GAP Analysis - Ahmed Bawazir Maximo Gaps Recommendations Maximo is slow from Plant Sites • Better Coordination among IT Teams • Analysis of Maximo Performance Issue by the Joint IT Team (team should be comprised of: Maximo Support team, IT Systems & Database team, IT Security Team, IT Network team) Accuracy of data in Maximo • Analyze the Data Quality Errors in Maximo (especially in description of Assets, Locations and assignment of Asset to Locations) • Data Cleansing Exercise (ensure that Accuracy, Completeness and Uniqueness of data is achieved) • Review of Quality Check Process before entering the data in Maximo • Standardization of Data Entry in Maximo by agreeing on Nomenclature and centralizing the data entry of new asset Maximo is not being used for HSE requirements • Use Safety sub module to get directions from Safety department • Use Hazardous Material functionality • Automate and Integrate the Permit to Work Process Commercial Directory is not utilized Comprehensively • Reports should be generated and reviewed by Commercial Management to identify the lack of utilization of Commercial Directory • Category Supplier History should be shared with Bid Opening Committee • Implementation of Comprehensive Suppliers Performance Evaluation System Lengthy Supplier Pre-qualification cycle • Introduce comprehensive KPI to monitor supplier prequalification time • Simplification of Prequalification Process for Non Critical Categories • Unification of Supplier Prequalification Process and Directory across all Groups Budget Check for Non Term contracts is done at the Release Order level • Budget check before raising a Non Term Contract Documentation is not updated once Change Requests are entered • Update and Preparation of all System Specifications • Introduction of Design Authority and Change Control Procedure Lack of System Enviroments • Introduction of Design Authority and Change Control Procedure • Report Committee should formulate GASCO’S Reporting Strategy Lack of Strategy for Reporting Tools ERP PIR 07
  • 10. ERP Project is one way GAP Analysis towards continuous improvement and enhancing our business processes. Good luck! - Hassan Al Hammadi ORACLE Financials Gaps Recommendations Delay in resolving technical issues • Conduct Regular Meetings with Finance Team • Introduction of Design Authority and Change Control Procedure Delay in Month-End Period Closing • Establish Payables Task Force Committee to investigate Payables process and eliminate manual controls and other non-value added activities in paying invoices • Review and agree holistic integrated Period-End Closure procedure to meet the GASCO target (and strive to achieve industry benchmark) Cash Management Process is manual • Configure Oracle to enable these available functionalities Major Projects Commitments are not captured in System • Capture Major Projects commitments in system Budgeting Process is not fully automated • Ensure end-to-end Budgeting Process before Hyperion implementation • Increase the approval limits of the Accountant and Senior Accountant to reduce A lot of Manual work (manual verification) for Payments processes the work of Head of AP • Establish Payables Task Force Committee to investigate Payables process and eliminate manual controls and other non-value added activities in paying invoices • Review and agree holistic integrated Period-End Closure procedure to meet the GASCO target (and strive to achieve industry benchmark) • Implement Oracle BI Applications and OBIEE Lack of Financials KPIs • Introduce financial KPIs according to IBM Best practices 08 gasco.com
  • 11. March 09th marks the beginning of the ERP GAP Analysis Project Deliverables reaching the end users. Memories A massive amount of energy and time has gone in ensuring that your requirements and quality standards are reflected in the final product - Oracle HCM. - Yves Pouradier ORACLE HCM Gaps Recommendations Data Management & Quality Issues • Conduct an Effective Awareness Program Targeting Oracle End-Users • Data Validation / Check Points • Conduct an Effective Awareness Program Targeting Oracle End-Users Lack of Reliable Reporting • Implement and Deploy Business Intelligence Reporting Tool • Conduct an Effective Awareness Program Targeting Oracle End-Users Limited Analytical Reporting • Data Validation / Check Points • Implement and Deploy Business Intelligence Reporting Tool Oracle Competency Management not being used • Integrated Talent Management Framework: Deploy Oracle Self-Service Build a “Smart” Skills Matrix Implement Oracle Talent Management Solution Learning Management not leveraged • Integrated Talent Management Framework Performance Appraisal Management not utilized Urgent Payments outside Payroll • Adhere to the ad hoc payroll run and quick pay such that employee payments outside the payroll can be liminated Contractual Staff Salary Payment Process • Contractual Staff Payroll to be streamlined via Oracle. • Carry out Business Process Realignment exercise escorted by effectual Change Managment Paper-based Expense Reimbursement • Automate Expense Reimbursement • Carry out Business Process Realignment exercise escorted by effectual Change Management ERP PIR 09
  • 12.
  • 13. We are proud that GASCO ERP Achievements is implemented state of the art professional tools, world class system, including new IT insfrastructure technology, all of + which contributes to our corporate journey toward ecxellence. - Adel Salem Alkaff • The ERP Project experience introduced more skilled internal support resources in both business and IT leading to major ICT Achievement Award improvements in support quality and response GASCO ERP Maximo Project won the ICT time. Achievement Awards of Best Energy Deployment of the year 2010 over the Middle East. • Infrastructure was upgraded to the latest technology ensuring better security, performance and availability. The ICT Achievement Awards honours the high achievers and trend-setters of the IT industry of • Automated number of Financial & Human Capability processes the region. resulted in improving the processing time and elimination of manual intervention. • Automated the Maximo Maintenance and Commercial processes. As a result, the processing time and procedure compliance was im- 2010 IBM Maximo Supply Chain proved and more than 1,156,000 workflows were initiated and completed since the go live date. Best Practice Award • More than 200 visits to Plants. Innovation Return on Investment Empowering the User Community • More than 1,000 workshops conducted during the ERP Best Practices Project. + • Fulltime members spent 10,000 additional working hours. ERP PIR 11
  • 14. Last year ERP project planned 09th March 2009 for its de- liverables, and I am pleased to announce that the First ERP deliverable Oracle HCM is live and operational as of Today, 09th March 2009 as promised. From today the single source of HR data is Oracle HCM. It is now up to all of us to utilize this new application to its full potential and ensure that the expected benefits to the organisation are realized rapidly. I would like to thank the Project Team for their continious dedication and the very long working hours they spent on the project over the past months. I would like also to recognize all other employees who contributed to the ERP Project in a genuine spirit of openess, trust and teamwork, thus ensuring this succes. Best Regards, Mohamed A. Sahoo Al - Suwaidi General Manager , GASCO
  • 15. PIR Dept Head Workshop + IR ERP P 011 NE 2 23 JU hop works The ERP Post-Implementation Review was held at Al Rimal Club on 23 June to present the ERP Maximo and Oracle findings and to discuss the feedback from the three-year long project. Peter Verhulst (SVP, CS) welcomed the guests and was soon followed by Ben Stanberry from the International Institute of Research (IIR), who was brought in to discuss Change Management and how GASCO can benefit from this inevitable organizational process. Mr. Stanberry created a ‘crime scene’ to demonstrate how the 12 most common corporate characteristics can ‘kill’ change and how GASCO can better assimilate to and prepare for changes in the future. In the afternoon, IBM external consultants held workshops for Maximo and Oracle users. Also, a yoga instructor was brought in to show the team how stretching and breathing can help to relieve stress. ERP PIR 13
  • 17. ERP Implementation, we are introducing a very powerful set of systems, but we need to remember that we will be working with data migrated from different Lessons Learnt legacy systems running on different platforms. It is critical that activeties like data clean up and data migration are Overall did you think the ERP was a succes? approached in a comprehensive manner, and all aspects are considered, tested no yes and quality reviewd. - Abdulla S. Al Minhali 31 32 32 4 3 ACHIEVED 3 USER PARTICIPATION Encourage the participation of low level users who use the system more Were the project objectives achieved? Did the implmentation frequently in all project phases, especially requirements. They should be identified early on process go according and involved in decision making to get their buy-in and manage their expectations. to plan? Was the project (Source: Senior Mgmt Survey) successful in your view? VENDOR SUPPORT Ensure vendor is certified and qualified and has the required competencies and capabilities. Moreover, vendor support continuity after the implementation is completed is MISSED essential to increase awareness about the system. An agreement should be signed at the project start to ensure their commitment. (Source: Senior Mgmt Survey) ERP EXPERIENCE No comprehensive business case was developed for the ERP Project. The TEAMWORK business case should clearly state the expected business benefits and define measurable The dedicated ERP interface team to test the process from end-to-end point of objectives, goals and deliverables. view contributed in minimizing the integration issues. (Source: PIR Presentation) Data cleansing exercise was carried out during the ERP Project, but it was not Grouping and Allocating Project members from business, IT, and external vendor sufficient. More attention should be given to the ERP data quality. in one location increased team’s productivity. (Source: PIR Presentation) COMMUNICATION MANAGEMENT Change Management was not carried out properly and some ERP applications Planning and simulating the ERP cut-off date more than 4 times minimized the Go faced user resistance. Live risks and improved the team readiness. (Source: PIR Presentation) The ERP Systems deployment was smooth through the Soft & Safe Drops MANAGEMENT approach, which increased the stability probability and minimized the culture shock. More sites visits need to be conducted to ensure the implementer capabilities, (Source: PIR Presentation) collect lessons learnt and to overcome the ERP challenges. COMMUNICATION CORE-TEAM CONTINUITY The ERP Project was successful in managing the communication process so that Core team continuity is the driver of the project: Part-time involvement of some of all stakeholders were informed of the project status on-time. Many methods were used, the project team members and ending of the steering committee meetings caused a gap including web portals, emails, and newsletters. (Source: PIR Presentation) towards the end. ERP PIR 15
  • 18. - GASCO’s business enviroment is one of significant growth. ERP is a necessity to accomodate this growth. Successful implementation of ERP requires a preparedness of our employees to accept change! I would urge every one to actively acquire the knowledge of how to work with the new system and take full advantages of the training program provided by the project. As extra, E-Learning tools will be provided, for all those who wish tp practise on their time, at their pace, and focus on a specific subject. This is an opportunity to enhance individual skills as well as GASCO’s business. - Cyrilles Huijsmans Assistant General Manager (Operations) System integration, utilizing standard interfaces and taking advantage of best practices, will help all of us to access quality information immediately, in order to take decisions in time. More robust interfaces between Maximo and the Oracle are amongst the major benefits we will experience from the new ERP slution. - Rashed Abdulla Al Shamsi, AGM(A)
  • 19. Memories ERP PIR 17