SlideShare a Scribd company logo
1 of 85
Download to read offline
VEHICULAR BRIDGE DESIGN
“CASE STUDY COMMUNITY OF OBRAJES”
JAIME NAVÍA TÉLLEZ
To my parents
Jaime Navía Camacho
Tusnelda Téllez de Navía
I dedicate this project to my Parents, my source of inspiration and
wisdom.
For their endless love and support thank you.
Jaime Navía Téllez
3 J.N.T.
ABSTRACT
NAME OF THE PROJECT: Vehicular Bridge Design “Case Study
Community of Obrajes”
The community of Obrajes is located in the Municipality of Soracachi,
province Cercado of the department of Oruro. Is characterized by a frigid
and dry climate, which is increasing considerably by the altitude of the
area.
For a long time, the idea of building a vehicular bridge that allows the
population a free movement has prevailed. And since the demand for
vehicular flow has been growing in recent years in the Municipality of
Soracachi, the construction of a vehicular bridge has become a necessity.
One of the main activities carried out in the Municipality of Soracachi is
agriculture, the municipality has a high agricultural potential, the transfer
and marketing of its products is complicated due to the poor state of the
road and in rainy seasons with the river rising it is impassable, so the
inhabitants of the different Communities of the Municipality look for
alternate routes.
Given the above pretensions, we assume the task of carrying out this work
consisting of the design of the superstructure and infrastructure of a bridge
located on the road Obrajes- Iruma.
With the realization of the project, a free transit will be achieved and the
quality of life of the community members will be improved.
Jaime Navía Téllez
4 J.N.T.
The project consists of the design and calculation of a vehicular bridge
type “Beam – Slab” located in the community of Obrajes. It is a bridge
with 3 spans of 10 meters each one with beams simply supported; adding
up a total span of 30 meters. The design process of a bridge can be divided
into four basic stages: conceptual design, preliminary design and detailed
design. The purpose of the conceptual design is to come up with various
feasible bridge schemes and to decide on one or more final concepts for
further consideration. The purpose of the preliminary design is to select
the best scheme from these proposed concepts and then to ascertain the
feasibility of the selected concept and finally to refine its cost estimates.
Finally, the purpose of the detailed design is to finalize all the details of
the bridge structure so that the document is sufficient for tendering and
construction.
Jaime Navía Téllez
5 J.N.T.
Contenido
CHAPTER 1 INTRODUCTION...................................................... 9
1.1 BACKGROUND.................................................................. 10
1.1.1 GENERAL BACKGROUND ....................................... 10
1.1.2 SPECIFIC BACKGROUND......................................... 11
1.2. PROBLEM STATEMENT.................................................. 13
1.2.1 IDENTIFICATION OF THE PROBLEM .................... 13
1.2.2 FORMULATION OF THE PROBLEM ....................... 15
1.3 OBJECTIVES....................................................................... 15
1.3.1 GENERAL OBJECTIVE .............................................. 15
1.3.2 SPECIFIC OBJECTIVES ............................................. 15
1.4 JUSTIFICATION AND SCOPE.......................................... 16
1.4.1 JUSTIFICATION.......................................................... 16
1.4.2 SCOPE........................................................................... 17
1.5. RESEARCH METHODOLOGY ........................................ 18
1.5.1. KIND OF INVESTIGATION ...................................... 18
1.5.2. LOCATION.................................................................. 19
CHAPTER 2................................................................................... 21
THEORETICAL CONCEPTUAL FRAMEWORK ...................... 21
2.1 MUNICIPALITY OF SORACACHI................................... 22
2.1.1 POLITICAL AND ADMINISTRATIVE DIVISION... 22
2.1.2 POPULATION.............................................................. 23
2.1.3 LANGUAGE................................................................. 23
2.1.4 ECONOMIC PRODUCTIVE ASPECT........................ 24
2.2 VEHICULAR BRIDGE ....................................................... 24
2.2.1 HISTORY...................................................................... 24
2.2.2 BRIDGE ........................................................................ 25
2.2.3 TYPES OF BRIDGES................................................... 25
2.2.4 BRIDGE TYPES BY USE............................................ 26
2.2.5 BRIDGE TYPES BY MATERIAL............................... 26
Jaime Navía Téllez
6 J.N.T.
2.2.6 AESTHETICS ............................................................... 27
2.2.7 BRIDGE MAINTENANCE.......................................... 28
2.2.8 BRIDGE FAILURES .................................................... 28
2.2.9 BRIDGE MONITORING.............................................. 28
2.3 DEFINITIONS AND COMPONENTS ............................... 29
2.3.1 VEHICULAR BRIDGE ................................................ 30
2.3.2 ROAD INFRASTRUCTURE ....................................... 30
2.3.3 SUPERSTRUCTURE ................................................... 31
2.3.4 SUBSTRUCTURE........................................................ 31
2.3.5 AASHTO DESIGN STANDARD ................................ 31
2.3.6 LOADS OF DESIGN.................................................... 31
2.3.7 PERMANENT LOAD................................................... 31
2.3.8 LIVE LOAD.................................................................. 32
2.3.9 FOUNDATION............................................................. 32
2.3.10 BEAM / GIRDER........................................................ 33
2.3.11 BEARING ................................................................... 33
2.3.12 PIER OR COLUMN.................................................... 33
2.3.13 TRUCK TYPE LOAD AND EQUIVALENT LOAD 34
2.3.14 CONCRETE RESISTANCE....................................... 34
2.3.15 TRAFFIC DECK THICKNESS.................................. 34
2.3.16 REINFORCED CONCRETE BEAMS ....................... 35
2.3.17 CONCRETE SLAB..................................................... 35
2.3.18 COMPONENT ............................................................ 35
2.3.19 DEFORMATION........................................................ 36
2.3.20 DESIGN ...................................................................... 36
2.3.21 ELASTIC..................................................................... 36
2.3.22 ELEMENT .................................................................. 36
2.3.23 EQUILIBRIUM........................................................... 36
2.3.24 EQUIVALENT BEAM............................................... 36
2.3.25 EQUIVALENT STRIP................................................ 37
Jaime Navía Téllez
7 J.N.T.
2.3.26 FINITE DIFFERENCE METHOD ............................. 37
2.3.27 FORCE EFFECT......................................................... 37
2.3.28 FOUNDATION........................................................... 37
2.3.29 LARGE DEFLECTION THEORY............................. 37
2.3.30 MEMBER.................................................................... 38
2.3.31 METHOD OF ANALYSIS ......................................... 38
2.3.32 MODEL....................................................................... 38
2.3.33 STIFFNESS................................................................. 38
2.3.34 YIELD LINE METHOD............................................. 38
CHAPTER 3 CALCULATION AND DESIGN ............................ 39
3.1 BRIDGE CONSTRUCTION ............................................... 40
3.2 BRIDGE CONSTRUCTION PLANNING.......................... 40
3.3 BRIDGE FOUNDATION.................................................... 41
3.4 BRIDGE CONSTRUCTION EQUIPMENT ....................... 41
3.5 BRIDGE LOADS................................................................. 42
3.6 TESTING OF BRIDGES ..................................................... 42
3.7 CONSIDERATIONS IN BRIDGE DESIGN....................... 43
3.8 SUPERSTRUCTURE AND INFRASTRUCTURE ............ 44
3.9 TENSION AND COMPRESSION ...................................... 45
3.10 RESONANCE .................................................................... 45
3.11 DESIGN METHODS ......................................................... 46
3.12 DESIGN PHILOSOPHY.................................................... 47
3.13 STRUCTURAL ANALYSIS ............................................. 49
3.14 ACCEPTABLE METHODS OF STRUCTURAL
ANALYSIS ................................................................................ 50
3.15 MATHEMATICAL MODELING ..................................... 50
3.16 ELASTIC BEHAVIOR...................................................... 51
3.17 SMALL DEFLECTION THEORY.................................... 51
3.18 ANALYSIS AND STRUCTURAL DESIGN OF THE
BRIDGE ..................................................................................... 52
Jaime Navía Téllez
8 J.N.T.
3.18.1 CONSIDERATIONS OF SUPERSTRUCTURE AND
INFRASTRUCTURE DESIGN ............................................. 52
3.19 DESIGN OF SUPERSTRUCTURE................................... 54
3.19.1 HANDRAIL DESIGN................................................. 54
3.19.2 SLAB DESIGN ........................................................... 55
3.19.3 CALCULATION AND DESIGN OF OPTIMIZED
BEAMS .................................................................................. 58
3.20 INFRASTRUCTURE DESIGN ......................................... 59
3.20.1 DESIGN OF WALLS, COLUMNS AND
FOUNDATIONS.................................................................... 59
3.20.2 DESIGN OF WALLS.................................................. 60
3.21 DRAWINGS....................................................................... 61
3.22 ECONOMIC AND FINANCIAL EVALUATION............ 72
3.23. ENVIRONMENTAL FILE ............................................... 75
CHAPTER 4................................................................................... 81
CONLCUSIONS ............................................................................ 81
AND ............................................................................................... 81
RECOMMENDATIONS ............................................................... 81
4.1 CONCLUSIONS .................................................................. 82
4.2 RECOMMENDATIONS ..................................................... 83
CHAPTER 5 APPENDICES.......................................................... 85
Jaime Navía Téllez
9 J.N.T.
CHAPTER 1 INTRODUCTION
Jaime Navía Téllez
10 J.N.T.
1.1 BACKGROUND
1.1.1 GENERAL BACKGROUND
The bridges constitute an element of extreme importance in the
construction of a highway. A bridge is a construction that allows saving a
geographic accident like a river, a canyon, a valley, a road, a railroad, or
any other physical obstacle. The design of each bridge varies depending
on its function and the nature of the terrain on which it is built.
Its design and its calculation belong to structural engineering, with
numerous types of designs that have been applied throughout history,
influenced by available materials, techniques developed and economic
considerations, among other factors. At the moment of analyzing the
design of a bridge, the quality of the soil or rock where it will be
supported and the regime of the river above the one that crosses are of
paramount importance to guarantee the life of the same one.
The design and construction of vehicular bridges in Bolivia has been
developed in response to the urgent demand that the inhabitants of the
cities and communities are far from improving their quality of life, since
without them, their quality of life would be very bad especially of the
remote communities because they would have great difficulties in their
transfer and mobilization in the place, in most cases the lack of this type
of infrastructures negatively affects mainly remote communities, most of
the communities live from agricultural production and livestock, and
Jaime Navía Téllez
11 J.N.T.
without the infrastructure it would be impossible for them to move their
products for later sale.
That is why the importance of this type of structures that improves the
quality of life of residents both social and economic.
1.1.2 SPECIFIC BACKGROUND
The community of Obrajes is located in the Municipality of Soracachi,
province Cercado of the department of Oruro.
It is located 26 km northwest of the city, 30 to 40 minutes by public
transport.
The Municipality of Soracachi has an area of 1254.94 Km2, is divided
into four municipal districts, seven cantons and 113 communities.
According to the 2012 census the municipality has a total population of
12,788; 6,420 (50.2%) males and 6,368 (49.8%) females.
Soracachi is characterized by a frigid and dry climate, which is increasing
considerably by the altitude of the area.
Although the climate and characteristics of the Altiplano are factors that
conditioning the agricultural production, the municipality shows its
agricultural and livestock potential. The geographical distribution of the
municipality shows a high zone, several hills that make up micro basins,
all with agroecological characteristics, with a productive potential
oriented mainly to agriculture and livestock, in most of the municipality
mixed production systems are developed.
Jaime Navía Téllez
12 J.N.T.
The agricultural activity of the municipality is recognized for its
horticultural production, mainly carrot and onion.
Data from the Municipal Government (2011) show that the cultivation of
barley represents an area of 19.77%, carrot 17.38% and alfalfa 16.24%.
Another potential is the cattle activity, in this activity has preeminence the
ovine cattle, followed by the cattle camelido and bovine.
Jaime Navía Téllez
13 J.N.T.
1.2. PROBLEM STATEMENT
1.2.1 IDENTIFICATION OF THE PROBLEM
In this case we use one of the most known methods to identify problems:
Which name is “Problem tree” consist in identify causes and effects of the
problem.
Jaime Navía Téllez
14 J.N.T.
The problem is:
“LOW TRANSITABILITY OF VEHICLES IN RAINY SEASON
IN THE COMMUNITY OF OBRAJES”, to solve that problem we
need three steps:
1) Design Project
2) Financing by the municipality
3) With the project we construct the bridge
Steps 2 and 3 depend on the municipal authorities of Obrajes for
that reason we can’t solve all the problems, but step 1 “Design
Project” which means calculation and design we can solve it.
As a result the specific problem will be:
“Lack of a road project in the community of Obrajes”
Jaime Navía Téllez
15 J.N.T.
1.2.2 FORMULATION OF THE PROBLEM
How can we solve the Lack of a road project in the community of
Obrajes?
1.2.2.1 HYPOTHESIS
We will be able solve the Lack of a road project in the community of
Obrajes with the design and calculation of the superstructure and
infrastructure of a vehicular bridge.
1.3 OBJECTIVES
1.3.1 GENERAL OBJECTIVE
Design and calculation of the superstructure and infrastructure of the
vehicular bridge located in the community of Obrajes.
1.3.2 SPECIFIC OBJECTIVES
-Calculation and design of the elements that constitute the superstructure
of the vehicular bridge.
-Calculation and design of the elements that constitute the infrastructure
of the vehicular bridge.
-Draw up detailed drawings with their dimensions and steel cutting.
-Elaboration of costs and budgets taking into account all the necessary and
constructive aspects of the vehicular bridge for its respective feasibility
analysis.
Jaime Navía Téllez
16 J.N.T.
-Elaboration of the environmental impact study with the corresponding
mitigation measures.
1.4 JUSTIFICATION AND SCOPE
1.4.1 JUSTIFICATION
1.4.1.1. TECHNICAL JUSTIFICATION
A bridge is a road infrastructure that allows saving a geographic accident
to allow a constant vehicular flow in all the seasons of the year. So with
the design of the superstructure of the vehicle bridge Obrajes would be
guaranteeing to the affected population a free vehicular traffic.
For decades, the design of vehicle bridges has been made, so the design is
safe and reliable and there are design standards that facilitate design and
reliability.
There are several types of bridges and different materials, which give a
wide range of possibilities to solve problems of transitability, and also
give the possibility of choosing the best alternative either as complexity or
cost of the structure.
1.4.1.2. ECONOMIC JUSTIFICATION
Recall that the main economic activity of the community and the
municipality is agriculture and livestock. Also remember that in rainy
seasons it is difficult for the villagers to move these products for later sale,
Jaime Navía Téllez
17 J.N.T.
in some cases can occur delays in deliveries or also for the bad state of the
road losses can occur in their products, which affects in a economic way
to the municipality.
And with the design of this vehicular bridge would be guaranteeing a free
transitability in all the seasons of the year, reason why would be
benefiting in the economic activity of the municipality.
1.4.1.3. SOCIAL JUSTIFICATION
A vehicular bridge is a road structure that, besides saving geographical
obstacles, allows the joining of two or more sections, which means that
the vehicular bridge will not only benefit the affected population, it also
will allow the connection of the community of Obrajes with other
communities granting easy access to each of them.
Also in the tourist part, the community of Obrajes has “Pinturas
Rupestres” and with the existence of a vehicular bridge would facilitate
access to it and would become more common the visit of tourists.
1.4.2 SCOPE
1.4.2.1. THEMATIC SCOPE
In this project a proposal will be made to design a superstructure and
infrastructure of a vehicular bridge which will grant a free transitability
during rainy seasons in the community of Obrajes.
Jaime Navía Téllez
18 J.N.T.
1.4.2.2. SPACE SCOPE
The project will be carried out in the community of Obrajes. Focused on a
model that grants a free transitability in times of rain.
1.4.2.3. TEMPORARY SCOPE
The project will be developed in a time of 3 months.
1.5. RESEARCH METHODOLOGY
For this project we are going to use the scientific method, is a method of
research in which a problem is identified, relevant data are gathered, a
hypothesis is formulated from these data, and the hypothesis is
empirically tested.
1.5.1. KIND OF INVESTIGATION
The degree project is categorized as a proactive research since it
consists of a design proposal of a vehicular bridge located in the
community of Obrajes, thus giving solution to the problem posed
previously.
It is the Community of Obrajes who will decide in the future the
construction of this project.
Jaime Navía Téllez
19 J.N.T.
1.5.2. LOCATION
The project is located in the municipality of Soracachi, province of
Cercado, Oruro Department. It is bordered to the North by La Paz
department, to the South by the municipality of Machacamarca (Pantaleon
Dalence Province), to the east by the municipality of Huanuni (Pantaleon
Dalence Province) and to the West by the municipality of Caracollo
(Cercado province).
The municipality of Soracachi, is located 26 km northwest of the city of
Oruro, 30 to 40 minutes by public transport. It is located between the
parallels 17 ° 30 'and 18 ° 05' south latitude and meridians 66 ° 42 'and 67
° 20' west longitude, in the central high plateau of Bolivia. The average
altitude in the municipality of Soracachi is 3,706 meters above sea level,
one of the highest points is located in the community of Romerocota on
the hill Irupata with 4,304 meters above sea level.
Jaime Navía Téllez
20 J.N.T.
POLITICAL AND GEOGRAPHICAL LOCATION OF THE PROJECT
Department: Oruro
Province: Cercado
Province Section : Third Section Municipality of Soracachi
Cantón : Iruma
Community: Obrajes
Geographically the Obrajes community is located approximately between
the coordinates of Austral latitude of the Greenwich Meridian.
Latitude: 17 ° 49 '35.062 "South
Length: 66 ° 59'23.34 "West
The community of Obrajes limits with the following communities:
NORTH: Population of Cotochullpa
SOUTH: Population of Amachuma
EAST: Iruma Population
WEST: Paria Population
The average elevation in which the beneficiary population is located is
approximately 3740 meters above sea level.
Jaime Navía Téllez
21 J.N.T.
CHAPTER 2
THEORETICAL CONCEPTUAL
FRAMEWORK
Jaime Navía Téllez
22 J.N.T.
2.1 MUNICIPALITY OF SORACACHI
2.1.1 POLITICAL AND ADMINISTRATIVE DIVISION
The Municipality of Soracachi has an area of 1254.94 Km2, is divided
into four municipal districts, seven cantons and where 113 communities
are located.
The first District has 3 Cantons:
1. Soracachi Canton where 8 communities are located.
2. Lequepalca Canton where 12 communities are located.
3. Iruma Canton where 13 communities are located.
The second District has 2 Cantons:
1. 9 de Abril (Tholapalca) Canton where 30 communities are located.
2. Paria Canton where 30 communities are located.
The third District has 1 Canton:
1. Teniente Bullain Canton where 8 communities are located.
The fourth District has 1 Canton:
1. Huayña Pasto Grande Canton where 12 communities are located.
Jaime Navía Téllez
23 J.N.T.
2.1.2 POPULATION
MUNICIPALITY OF SORACACHI:
According to the 2012 census the Municipality has a total population of
12,788:
6,420 (50.2%) males and 6,368 (49.8%) females.
With an annual intercensal growth rate of 1.0% (2001 - 2012).
POPULATION “MUNICIPALITY OF SORACACHI”
BOTH GENDERS MALE FEMALE
Age groups Rural Rural Rural
0 to 5 years 2215 1118 1097
6 to18 years 4310 2230 2080
19 to 39 years 3338 1635 1703
40 to 64 years 2131 1057 1074
65 years or more 794 380 414
Total : 12788 6420 6368
SOURCE: INE
Its population is young 77.6% is under 40 years. The overall fertility rate
is approximately 5.2, i.e. every woman during her fertile life has an
average of 5 children. 90.77% of the population declares to be of Quechua
origin and 4.13% of Aymara origin, in this area 85.07% of the population
declares to speak Quechua.
2.1.3 LANGUAGE
Language that the population speaks in percentage. The next information
was obtained from “INE”
Castellano Language: Male (56.41%), Female (43.59%) ; Quechua
Language: Male (50%), Female (50%) ; Aymara Language: Male
(1.06%), Female (0%).
Jaime Navía Téllez
24 J.N.T.
2.1.4 ECONOMIC PRODUCTIVE ASPECT
The agricultural activity of the municipality is recognized for its
horticultural production, mainly carrot and onion, data from the Municipal
Government (2011) show that the cultivation of barley represents an area
of 19.77%, carrot 17.38% and that of alfalfa 16.24%. Another potential is
the livestock activity, in this activity the sheep is preeminent, followed by
the camelid and bovine cattle, most of the species are native. Within the
municipality there are communities that have livestock vocation par
excellence; livestock production is the second in importance in the region.
It is recognized in the city of Oruro the production of cow's milk and
cheese, in the case of bovine livestock, district 1 concentrates 47.67% of
heads, district 2 21.38% and the lowest concentration is District 4 with
11.48%..
2.2 VEHICULAR BRIDGE
2.2.1 HISTORY
The first bridges made by humans were probably spans of cut wooden
logs or planks and eventually stones, using a simple support and
crossbeam arrangement. A common form of lashing sticks, logs, and
deciduous branches together involved the use of long reeds or other
harvested fibers woven together to form a huge rope capable of binding
and holding together the materials used in early bridges.
Jaime Navía Téllez
25 J.N.T.
2.2.2 BRIDGE
A bridge is a structure built to span physical obstacles without closing the
way underneath such as a body of water, valley, or road, for the purpose
of providing passage over the obstacle. There are many different designs
that each serve a particular purpose and apply to different situations.
Designs of bridges vary depending on the function of the bridge, the
nature of the terrain where the bridge is constructed and anchored, the
material used to make it, and the funds available to build it.
2.2.3 TYPES OF BRIDGES
Bridges can be categorized in several different ways. Common categories
include the type of structural elements used, by what they carry, whether
they are fixed or movable, and by the materials used.
2.2.3.1 BEAM BRIDGES
Beam bridges are horizontal beams supported at each end by substructure
units and can be either simply supported when the beams only connect
across a single span, or continuous when the beams are connected across
two or more spans. When there are multiple spans, the intermediate
supports are known as piers.
2.2.3.2 ARCH BRIDGES
Arch bridges have abutments at each end. The weight of the bridge is
thrust into the abutments at either side.
Jaime Navía Téllez
26 J.N.T.
2.2.3.3 TIED ARCH BRIDGES
Tied arch bridges have an arch-shaped superstructure, but differ from
conventional arch bridges. Instead of transferring the weight of the bridge
and traffic loads into thrust forces into the abutments, the ends of the
arches are restrained by tension in the bottom chord of the structure.
2.2.3.4 CABLE-STAYED BRIDGES
Cable-stayed bridges, like suspension bridges, are held up by cables.
However, in a cable-stayed bridge, less cable is required and the towers
holding the cables are proportionately higher.
2.2.4 BRIDGE TYPES BY USE
A bridge can be categorized by what it is designed to carry, such as trains,
pedestrian or road traffic, a pipeline or waterway for water transport or
barge traffic. An aqueduct is a bridge that carries water, resembling a
viaduct, which is a bridge that connects points of equal height. A road-rail
bridge carries both road and rail traffic.
2.2.5 BRIDGE TYPES BY MATERIAL
The materials used to build the structure are also used to categorize
bridges. Until the end of the 18th Century, bridges were made out of
timber, stone and masonry. Modern bridges are currently built in concrete,
steel, fiber reinforced polymers (FRP), stainless steel or combinations of
those materials.
Jaime Navía Téllez
27 J.N.T.
Suspension Bridge Type:
Materials Used: The cables are usually made of steel cables galvanised
with zinc, along with most of the bridge, but some bridges are still made
with steel reinforced concrete
Arch Bridge Type:
Materials Used: Stone, brick and other such materials that are strong in
compression and somewhat so in shear.
Beam Bridge Type:
Materials Used: Beam bridges can use pre-stressed concrete, an
inexpensive building material, which is then embedded with rebar. The
resulting bridge can resist both compression and tension forces
2.2.6 AESTHETICS
Most bridges are utilitarian in appearance, but in some cases, the
appearance of the bridge can have great importance. Often, this is the case
with a large bridge that serves as an entrance to a city, or crosses over a
main harbor entrance. These are sometimes known as signature bridges.
Designers of bridges in parks and along parkways often place more
importance to aesthetics.
Jaime Navía Téllez
28 J.N.T.
2.2.7 BRIDGE MAINTENANCE
Bridge maintenance consisting of a combination of structural health
monitoring and testing. This is regulated in country-specific engineer
standards and includes e.g. an ongoing monitoring every three to six
months, a simple test or inspection every two to three years and a major
inspection every six to ten years.
2.2.8 BRIDGE FAILURES
The failure of bridges is of special concern for structural engineers in
trying to learn lessons vital to bridge design, construction and
maintenance. The failure of bridges first assumed national interest during
the Victorian era when many new designs were being built, often using
new materials.
2.2.9 BRIDGE MONITORING
An option for structural-integrity monitoring is "non-contact monitoring",
which uses the Doppler effect (Doppler shift). A laser beam from a Laser
Doppler Vibrometer is directed at the point of interest, and the vibration
amplitude and frequency are extracted from the Doppler shift of the laser
beam frequency due to the motion of the surface. The advantage of this
method is that the setup time for the equipment is faster and, unlike an
accelerometer, this makes measurements possible on multiple structures in
Jaime Navía Téllez
29 J.N.T.
as short a time as possible. Additionally, this method can measure specific
points on a bridge that might be difficult to access.
2.3 DEFINITIONS AND COMPONENTS
In this part we will describe and define each of the terms to be used in the
project.
Jaime Navía Téllez
30 J.N.T.
2.3.1 VEHICULAR BRIDGE
A vehicular bridge is a construction that allows surpassing a geographic
accident or any physical obstacle, also has the objective to accelerate the
road mobility and to improve the vehicular circulation in very busy
sectors. The design may vary depending on the function of each bridge
and the nature of the terrain.
A vehicular bridge consists of:
The infrastructure that is formed by the extreme walls, the pier column or
supports for central bridges and the foundations, that forms the base of
both
The superstructure is the part that directly supports the loads and the
reinforcements, constituted by beams, cables and arcs that transmit the
loads of the board to the piles and the stirrups.
2.3.2 ROAD INFRASTRUCTURE
The road infrastructure is the whole set of elements that allows the
movement of vehicles in a comfortable and safe way from one point to
another. It is the set of physical components that interrelated with each
other in a coherent way and under compliance with certain technical
specifications of design and construction, offer comfortable and safe
conditions for the circulation of users who make use.
Jaime Navía Téllez
31 J.N.T.
2.3.3 SUPERSTRUCTURE
Superstructure that part of the structure which supports traffic and
includes deck, slab and girders. All the parts of the bridge which is
mounted on a supporting system can be classified as a Super structure.
2.3.4 SUBSTRUCTURE
Substructure that part of the structure, ie piers and abutments, which
supports the superstructure and which transfers the structural load to the
foundations.
2.3.5 AASHTO DESIGN STANDARD
AASHTO is a standard for the calculation or road design; it is a code for
the Road Design.
2.3.6 LOADS OF DESIGN
They are the forces acting on the infrastructure, with which it will be
designed.
Note: Each of the loads are detailed in the standard AASHTO
STANDARD or LRFD.
2.3.7 PERMANENT LOAD
The own weight or dead load of the superstructure generally consists of
the beams, the concrete slab and the diaphragms that constitute what is
more properly called the permanent dead load. And complementary to
Jaime Navía Téllez
32 J.N.T.
these are: The sidewalks, the posts, the handrails, the layer of rolling,
pipes, cables and others.
2.3.8 LIVE LOAD
Live loads, or imposed loads, are temporary, of short duration, or a
moving load. These dynamic loads may involve considerations such as
impact, momentum, vibration, which correspond to trucks, buses,
automobiles, construction and agricultural equipment, cyclists,
pedestrians, livestock.
The supporting elements and bridge pieces will be designed with the load
of truck HS 20-44, taking as design load the one that produces the greatest
living moments, according to the light distribution.
A.A.S.H.T.O. distinguishes two types of live load: TYPE TRUCK that is
taken as single load for each traffic belt and its corresponding
EQUIVALENT LOAD that replaces the type truck after having exceeded
a certain length.
2.3.9 FOUNDATION
Foundation is the component which transfers loads from the substructure
to the bearing strata. Depending on the geotechnical properties of the
bearing strata, shallow or deep foundations are adopted. Usually, piles and
well foundations are adopted for bridge foundations.
Jaime Navía Téllez
33 J.N.T.
2.3.10 BEAM / GIRDER
Beam or girder is that part of superstructure structure which is under
bending along the span. it is the load bearing member which supports the
deck. Span is the distance between points of support (eg piers, abutment).
Deck is bridge floor directly carrying traffic loads. Deck transfers loads to
the Girders depending on the decking material.
2.3.11 BEARING
Bearing transfers loads from the girders to the pier caps. Bearing is a
component which supports part of the bridge and which transmits forces
from that part to another part of the structure whilst permitting angular
and/or linear movement between parts.
2.3.12 PIER OR COLUMN
Pier is that part of a part of the substructure which supports the
superstructure at the end of the span and which transfers loads on the
superstructure to the foundations. Depending up on aesthetics, site, space
and economic constraints various shapes of piers are adopted to suit to the
requirement. Mostly Reinforced Concrete or Prestressed concrete are
adopted for the construction of piers. Piers are compression members.
Depending on the loading and bearing articulations, piers may be
subjected to bending as well.
Jaime Navía Téllez
34 J.N.T.
2.3.13 TRUCK TYPE LOAD AND EQUIVALENT LOAD
The design truck is a type truck that proposes the AASHTO standard,
which produces a type of solicitation in the infrastructure, which must be
designed to support it.
The heaviest AASHTO truck is known as H20-S16 or HS20 and has a
total weight of 36 US tons, equivalent to 32.67 metric tons.
The weights and separations between the axles and wheels of the design
truck are defined by the AASHTO standard. An increase by dynamic load
shall be considered as specified in Article 3.6.2. Except as specified in
Articles 3.6.1.3.1 and 3.6.1.4.1, the spacing between the two axles of
145,000 N shall be varied between 4300 and 9000 mm to produce the
extreme stresses.
2.3.14 CONCRETE RESISTANCE
It is its characteristic resistance with which our infrastructure will be
designed, that is to say how much load to compression will support the
concrete.
2.3.15 TRAFFIC DECK THICKNESS
It is the last layer to be applied, where traffic must circulate, in many
cases there is an intermediate layer and in less cases (highways and
infrastructures for heavy traffic) the firm will consist of a base layer, an
intermediate layer and the final layer of rolling.
Jaime Navía Téllez
35 J.N.T.
The traffic deck thickness refers to the thickness of the layer, which by
AASHTO has a minimum thickness of e = 0.02 [m].
2.3.16 REINFORCED CONCRETE BEAMS
An element capable of withstanding the applied forces when working in
conjunction with longitudinal reinforcements and steel stirrups. They are
the large pieces that, together with the columns, support the structures and
loads, allowing flexibility.
For this reason, when preparing or arming them, they must be proven to
perfectly withstand traction and compression efforts simultaneously.
2.3.17 CONCRETE SLAB
Two-dimensional structural elements. Act by bending, since the loads
acting on them are fundamentally perpendicular to the main plane thereof.
These slabs are supported by larger beams or by beams of other
independent materials and integrated into the slab. Sustained slabs on
walls: they are supported by concrete walls, masonry walls or walls of
other material.
2.3.18 COMPONENT
A structural unit requiring separate design consideration; synonymous
with member.
Jaime Navía Téllez
36 J.N.T.
2.3.19 DEFORMATION
A change in structural geometry due to force effects, including axial
displacement, shear displacement, and rotations.
2.3.20 DESIGN
Proportioning and detailing the components and connections of a bridge to
satisfy the requirements of these Specifications.
2.3.21 ELASTIC
A structural material behavior in which the ratio of stress to strain is
constant, the material returns to its original unloaded state upon load
removal.
2.3.22 ELEMENT
A part of a component or member consisting of one material.
2.3.23 EQUILIBRIUM
A state where the sum of forces and moments about any point in space is
zero.
2.3.24 EQUIVALENT BEAM
A single straight or curved beam resisting both flexure and torsional
effects.
Jaime Navía Téllez
37 J.N.T.
2.3.25 EQUIVALENT STRIP
An artificial linear element, isolated from a deck for the purpose of
analysis, in which extreme force effects calculated for a line of wheel
loads, transverse or longitudinal, will approximate those actually taking
place in the deck.
2.3.26 FINITE DIFFERENCE METHOD
A method of analysis in which the governing differential equation is
satisfied at discrete points on the structure.
2.3.27 FORCE EFFECT
A deformation, stress, or stress resultant, i.e., axial force, shear force,
flexural, or torsional moment, caused by applied loads, imposed
deformations, or volumetric changes.
2.3.28 FOUNDATION
A supporting element that derives its resistance by transferring its load to
the soil or rock supporting the bridge.
2.3.29 LARGE DEFLECTION THEORY
Any method of analysis in which the effects of deformation upon forces
effects is taken into account.
Jaime Navía Téllez
38 J.N.T.
2.3.30 MEMBER
Same as components.
2.3.31 METHOD OF ANALYSIS
A mathematical process by which structural deformations, forces, and
stresses are determined.
2.3.32 MODEL
A mathematical or physical idealization of a structure or component used
for analysis.
2.3.33 STIFFNESS
Force effect resulting from a unit deformation.
2.3.34 YIELD LINE METHOD
A method of analysis in which a number of possible yield line patterns are
examined in order to determine load-carrying capacity.
Jaime Navía Téllez
39 J.N.T.
CHAPTER 3 CALCULATION
AND DESIGN
Jaime Navía Téllez
40 J.N.T.
Only design results are shown, the detailed design and full calculation is
detailed in annexes section.
3.1 BRIDGE CONSTRUCTION
Bridge construction has been improved tremendously with the
advancement in science and technology. Better and lighter materials are
now available that can endure greater loads. The construction is now
much faster due to the introduction of a variety of heavy construction
equipment.
3.2 BRIDGE CONSTRUCTION PLANNING
Bridge construction tends to involve huge projects that encompass the
utilization of skills related to several engineering disciplines including
geology, civil, electrical, mechanical, and computer sciences. Therefore,
integrating the efforts of all involved must be meticulous. The initial plans
are prepared regarding the project, including the characteristics of the
desired bridge, the site details, and the requirement of resources. The
bridge design will be determined by the type of bridge being constructed.
The main types of the bridges are beam, arch, truss, cantilever, and
suspension. The beam bridge is one of the popular types.
Jaime Navía Téllez
41 J.N.T.
3.3 BRIDGE FOUNDATION
Construction of the foundations is the first step toward building a bridge.
This process involves detailed geotechnical investigations of the bridge
site. The type of bridge foundation has to be selected, such as the well
foundation, pile foundation, and the opened foundation. Each foundation
is suitable for specific soil strata, and the desired bridge characteristics.
The soil characteristics will determine the load bearing capacity, and other
important parameters. The superstructure is basically designed in
accordance with the technical requirements, aesthetic reasons, and the
construction methodology. Excavation required for the foundations may
need to be executed to sizeable depths, involving hard ground, before the
solid rocks are reached. Engineering feats will be involved to avoid water,
and prevent collapse of the diggings. Tunnels specifically may be
subjected to sudden failures.
3.4 BRIDGE CONSTRUCTION EQUIPMENT
Heavy equipment will be used extensively during the bridge construction
including bulldozers, excavators, asphalt mixers, formworks, and
fabrication equipment. The construction and other equipment needs to be
identified thoroughly, according to their capability and other desired
functions. The foundation and the superstructure design will need to be
considered. This expensive equipment should not remain idle, and must be
used cautiously to obtain optimum advantage.
Jaime Navía Téllez
42 J.N.T.
3.5 BRIDGE LOADS
Several loads act on a bridge, and the bridge is designed accordingly.
Dynamic loads are particularly of prime significance. A bridge is designed
to endure the normal vehicle loads, and other forces created due to winds
and earthquakes. Several bridges have collapsed due to high speed winds.
Even if the wind speeds are reasonably low, the dynamic forces can
become excessive for the bridge to resist. Initially, the bridge may vibrate
violently, causing the bridge structure to fail at a few weak elements, or
even damage the major components. Investigations conducted after bridge
failures have revealed that the real forces on bridges that collapsed were
significantly less compared to the loads for which the bridge was
designed. However, the oscillations created due to the winds were enough
to cause the failure. Therefore, special reinforcement may be necessary for
prevention against high speed winds and earthquakes. Thus, lighter
materials are used that are arranged in suitable geometric structures, and it
is ensured that the configuration is aerodynamically stable.
3.6 TESTING OF BRIDGES
Since bridge construction is an expensive project, it is essential that all
necessary tests may be conducted prior to the actual construction. These
tests and investigations can reveal the bridge behavior under different
dynamic loads. Computer aided design and testing are powerful tools that
Jaime Navía Téllez
43 J.N.T.
must be used to assist in the bridge design. Bridge design has benefited
considerably due to the growth of computer programs. Such computer
programs reveal immense information concerning the effect of different
forces being applied on a bridge. The four main factors are used in
describing a bridge. By combining these terms one may give a general
description of most bridge types.
Span (simple, continuous, cantilever).
Material (stone, concrete, metal, etc.).
Placement of the travel surface in relation to the structure (deck, pony,
through).
Form (beam, arch, truss, etc.).
In this project we will use simple spans kind of bridge.
3.7 CONSIDERATIONS IN BRIDGE DESIGN
Engineers have been designing bridges for thousands of years. A lot of
thought goes into designing the perfect bridge, to ensure that the structure
is safe, reliable and able to withstand the test of time. Of course, engineers
today have access to more precise tools than the bridge designers of
yesterday, allowing them, among other things, to prototype their work far
earlier in the process. Though, in historical terms, CAD training is a
Jaime Navía Téllez
44 J.N.T.
relatively new discipline for architectural or engineering technicians,
bridge design isn’t. If you’re interested in using CAD software to design a
bridge, the science of bridge design contains a wealth of experience and
information that can be very useful for a Computer Aided Drafter to
take into consideration, particularly at the level of specification,
standardization, and reliability.
3.8 SUPERSTRUCTURE AND INFRASTRUCTURE
To understand bridge design, you’ll have to learn the difference between
the bridge’s superstructure and its substructure. By the bridge’s
superstructure, we mean anything above the bearings, including the hard
surface drivers used to travel from one side to the other. By the
substructure, we mean the bridge’s foundation, including the columns
supporting it. The superstructure and the substructure work together, but
have different goals. Choosing the shape of the structure of your bridge,
for example, will affect the substructure. A bridge can be shaped like an
arc, suspended by cables, built primarily using powerful beams and more.
These design considerations, of course, are more complex than simply
asking “What shape do you prefer?”, you should take the time to factor in
the environment around the bridge and various economic considerations,
such as costs of materials, among others.
Jaime Navía Téllez
45 J.N.T.
3.9 TENSION AND COMPRESSION
Regardless of the shape of your bridge, its key structural components will
be beams, arches, trusses and suspensions. How you use these elements
will determine the quality of your bridge. Two forces you should make
sure you understand are tension and compression. To understand tension,
imagine a rope being pulled on from both sides during a game of tug-of-
war. This is tension, and it’s a force that will act on your bridge to add
stress. To understand compression, just imagine what happens to a spring
when you apply pressure on it. That’s right – it collapses into itself, which
shortens its length. Compressional stress will also affect your bridge, and
it will act in direct opposition to tensional stress. The bridge’s design,
therefore, must be able to handle these forces without buckling or
snapping.
3.10 RESONANCE
Resonance is another force that can act on your bridge. Imagine a
snowball rolling down a hill and increasing in size and speed. This is
resonance. It starts with small vibrations, such as when wind attacks a
bridge, and those vibrations can continue increasing over time until they
take down the entire structure! There are several ways to deal with
resonance, but one of the most popular methods is to incorporate
Jaime Navía Téllez
46 J.N.T.
dampeners into the bridge design, which can interrupt the resonant waves
and prevent them from growing.
3.11 DESIGN METHODS
Two basic methods are used – Service Load Design and Strength Design.
The Service Load Design (Allowable Stress Design) shall be used for the
design of all steel members and reinforced concrete members except
columns, sound barrier walls and bridge railings. Columns and sound
barrier walls shall be designed by the Strength Design Method (Load
Factor Design). Bridge railing design for new bridges shall be based on
the AASHTO LRFD Bridge Design Specifications.
In Service Load Design, loads of the magnitude anticipated during the life
of the structure are distributing empirically and each member analyzed
assuming completely elastic performance. Calculated stresses are
compared to specified allowable stresses which have been scaled down
from the tested strength of the materials by a factor judged to provide a
suitable margin of safety.
In Strength Design, the same service loads are distributed empirically and
the external forces on each member are determined by elastic analysis.
These member forces are increased by factors judged to provide a suitable
margin of safety against overloading. These factored forces are compared
to the ultimate strength of the member scaled down by a factor reflecting
Jaime Navía Téllez
47 J.N.T.
the possible consequences from construction deficiencies. Serviceability
aspects, such as deflection, fatigue and crack control, must be determined
by Service Load Analysis.
The Strength Design Method produces a more uniform factor of safety
against overload between structures of different types and span lengths.
Strength Design also tends to produce more flexible structures.
3.12 DESIGN PHILOSOPHY
New structure types were developed to meet specific needs. Concrete
slab, T-Girder and Box Beam bridges were developed in the late 1940’s
because many short span stream crossings were being constructed
uneconomically with steel beams and trusses. These bridges are still used
very economically in considerable numbers today. Precast pretensioned
beams were developed in the 1950’s for medium span stream crossings
and grade separations because steel beams became expensive and
sometimes slow on delivery. Fewer plans are assembled from standard
prestressed girder drawings today because bridge geometry has become
more complicated and variable so that most details must be specially
prepared. The beams themselves are still the standard shapes developed
in the beginning and the accessories required to complete the span are
covered with standard details. Cast-In-Place Post-Tensioned Box Girder
Jaime Navía Téllez
48 J.N.T.
bridges were introduced the 1970’s and became one of the most common
types of bridges used.
Geometry is considered an important part of bridge design. Framing
dimensions and elevations must be accurate in order to avoid expensive
field correction. Design engineers are primarily responsible for geometry
accuracy.
Constructability is highly desirable. There have been designs which
looked good on paper but were virtually impossible to construct.
Designers need to consider how to build the component being designed.
Construction experience remains a valuable asset.
Details may be the most critical aspect of the design process. Failure to
provide for proper stress flow at discontinuities has often caused local
stress and sometimes mortal injury to a system. Engineers and technicians
should recognize and carefully evaluate untested details.
The bottom line on bridge design is maintenance. It is usually much more
expensive to repair a bridge than it was to build it. Unfortunately,
maintenance problems tend to occur many years after the structure is built.
During that time there may be many more bridges designed with the same
problem. Experience is a good teacher, but the lesson is sometimes slow
to be learned. It takes a good designer to anticipate maintenance problems
and spend just enough of the taxpayers’ money to prevent or delay them.
Jaime Navía Téllez
49 J.N.T.
Design calculations are the documentation for structural adequacy and
accuracy of pay quantities for each bridge. These will be kept on file for a
reasonable period after construction of the bridge. The condition of the
calculations reflects the attitude of the designer and checker. The design
calculations should consist of a concise, but complete, clear, and easily
followed record of all essential features of the final design of each
structure. It is often necessary to refer to these calculations because of
changes or questions which arise during the construction period. If
properly prepared and assembled, these calculations are of great value as a
guide and time saver for preparing a similar design of another structure.
3.13 STRUCTURAL ANALYSIS
In general, bridge structures are to be analyzed elastically which are based
on documented material characteristics and satisfy equilibrium and
compatibility. However, exceptions may apply to some continuous beam
superstructures by using inelastic analysis or redistribution of force
effects.
This section identifies and promotes the application methods of structural
analysis that are suitable for bridges. The selected method of analysis
may vary from the approximate to the very sophisticated, depending on
the size, complexity, and importance of the structure. The primary
objective in the use of more sophisticated methods of analysis is to obtain
Jaime Navía Téllez
50 J.N.T.
a better understanding of structural behavior. Such improved
understanding may often, but not always, lead to the potential for saving
material.
These methods of analysis, which are suitable for the determination of
deformations and force effects in bridge structures, have been successfully
demonstrated, and most have been used for years.
3.14 ACCEPTABLE METHODS OF STRUCTURAL ANALYSIS
Any method of analysis that satisfies the requirements of equilibrium and
compatibility and utilizes stress-strain relationships for the proposed
materials may be used, including but not limited to:
Classical force and displacement methods (Moment Distribution, and
Slope Deflection Methods, etc.), Finite difference method, Finite element
method, Folded plate method, Finite strip method, Grillage analogy
method, Serious or other harmonic methods, and Yield line method.
3.15 MATHEMATICAL MODELING
Mathematical models should include loads, geometry, and material
behavior of the structure, and, where appropriate, response characteristics
of the foundation. In most cases, the mathematical model of the structure
should be analyzed as fully elastic, linear behavior except in some cases,
the structure may be modeled with inelastic or nonlinear behavior.
Jaime Navía Téllez
51 J.N.T.
3.16 ELASTIC BEHAVIOR
Elastic material properties and characteristics of concrete, steel, aluminum
and wood shall be in accordance with the sections given by AASHTO
Specifications. Changes in these values due to maturity of concrete and
environmental effects should be included in the model, where appropriate.
3.17 SMALL DEFLECTION THEORY
If the deformation of the structure does not result in a significant change
in force effects due to an increase in the eccentricity of compressive or
tensile forces, such secondary effects may be ignored. Small deflection
theory is usually adequate for the analysis of beam-type bridges.
Columns, suspension bridges, and very flexible cable-stayed bridges and
some arches other than tie arches and frames in which the flexural
moments are increased or decreased by deflection tend to be sensitive to
deflection considerations. In many cases, the degree of sensitivity can be
assessed and evaluated by a single-step approximate method, such as the
Moment Magnification Factor Method. Due to advances in material
technology the bridge components become more flexible and the
boundary between small- and large-deflection theory becomes less
distinct.
Jaime Navía Téllez
52 J.N.T.
Only design results are shown, the detailed design and full calculation
is detailed in annexes section.
3.18 ANALYSIS AND STRUCTURAL DESIGN OF THE
BRIDGE
3.18.1 CONSIDERATIONS OF SUPERSTRUCTURE AND
INFRASTRUCTURE DESIGN
Design standards, we will use:
AASHTO STANDARD
ACI CODE - 318 – 05
TRUCK TYPE LOAD AND EQUIVALENT LOAD
DESIGN TRUCK
The weights and separations between the axles and the wheels of the
design truck shall be as specified in Figure 1. The spacing between the
two axles of 145,000 N shall be varied between 4300 and 9000
millimeters to produce the extreme stresses.
Jaime Navía Téllez
53 J.N.T.
Calculation length
This length refers to the calculation span of the bridge in the longitudinal
direction.
It is a bridge of 3 equal spans, with 3 beams of 10 meters simply
supported, adding a total span of 30 m.
Roadway width
The free width of road will be 7.3 meters.
Number of traffic lanes
This bridge will have 2 traffic lanes
Width of sidewalk
The width of sidewalk will be 0.5 meters and the width of the edge beam
will be 0.2 meters, then:
The total width will be 0.7 meters
Truck type
Jaime Navía Téllez
54 J.N.T.
The type of truck for the design will be HS 20-44; standard HS truck
according to AASHTO
Concrete resistance
The Concrete resistance "f 'c" will be: f' c = 210 [kg / cm2]
Steel creep resistance
The creep strength of the "Fy" steel will be:
Fy = 4200 [kg / cm2]
Specific weight of the concrete
The specific weight of the concrete "γHᵒ" will be:
γH = 2400 [kg / m 3]
Traffic deck thickness
The thickness of the traffic deck "e" will be: e = 0.02 [m]
3.19 DESIGN OF SUPERSTRUCTURE
3.19.1 HANDRAIL DESIGN
The design of Handrail (is a Type P3) was made according to the
AASHTO standard article 1.2.11
In this case we will use a standard handrail used in Oruro, is not necessary
the calculation and design.
Jaime Navía Téllez
55 J.N.T.
THIS IS THE FINAL SCHEME OF THE HANDRAIL DESIGN
3.19.2 SLAB DESIGN
INTERIOR SLAB DESIGN
CALCULATION OF AMOUNT OF STEEL:
We will design with a 12 millimeters diameter bar; ø= 12 [mm]
Number of bars =9
Separation between bars = 11, 2 centimeters
Distribution steel:
Main steel perpendicular to traffic
We will design with a 12 millimeters diameter bar; ø= 12 [mm]
Number of bars=7
Separation between bars = 15 centimeters
EXTERIOR SLAB DESIGN
CALCULATION OF AMOUNT OF STEEL:
We will design with a 16 millimeters diameter bar; ø= 16 [mm]
Jaime Navía Téllez
56 J.N.T.
Number of bars=10
Separation between bars = 10 centimeters
Steel of distribution:
Main steel perpendicular to traffic
We will design with a 12 millimeters diameter bar; ø= 12 [mm]
Number of bars=6
Separation between bars = 17 centimeters
Jaime Navía Téllez
57 J.N.T.
THIS IS THE FINAL SCHEME OF THE SLAB DESIGN
INTERIOR SLAB
EXTERIOR SLAB
Jaime Navía Téllez
58 J.N.T.
3.19.3 CALCULATION AND DESIGN OF OPTIMIZED
BEAMS
FLEXION DESIGN
CALCULATION OF AMOUNT OF STEEL:
We will design with a 25 millimeters diameter bar; ø= 25 [mm]
Number of bars=12
SHEAR DESIGN
CALCULATION OF AMOUNT OF STEEL:
We will design with a 10 millimeters diameter bar; ø= 10 [mm]
Separation between bars = 7,5 centimeters
THIS IS THE FINAL SCHEME OF THE BEAM DESIGN
Jaime Navía Téllez
59 J.N.T.
3.20 INFRASTRUCTURE DESIGN
3.20.1 DESIGN OF WALLS, COLUMNS AND FOUNDATIONS
THIS IS THE FINAL SCHEME OF THE DESIGN OF COLUMNS AND
FOUNDATIONS
PIER COLUMN AND FOUNDATION 1:
PIER COLUMN AND FOUNDATION 2:
Jaime Navía Téllez
60 J.N.T.
3.20.2 DESIGN OF WALLS
Wall 1 and wall 2 were designed with the same dimensions, due to the
characteristics of the terrain.
THIS IS THE FINAL SCHEME OF THE DESIGN OF WALLS
Note:
Only the final schemes were presented in this section, the calculation and
design is detailed in appendices and the results are in the drawings
section.
Jaime Navía Téllez
61 J.N.T.
3.21 DRAWINGS
Jaime Navía Téllez
62 J.N.T.
HANDRAIL DRAWINGS
Jaime Navía Téllez
63 J.N.T.
PIER COLUMNS AND FOUNDATIONS DRAWINGS
Jaime Navía Téllez
64 J.N.T.
Jaime Navía Téllez
65 J.N.T.
SLAB, BEAMS AND WALLS DRAWINGS
Jaime Navía Téllez
66 J.N.T.
TOPOGRAPHIC DRAWINGS
Jaime Navía Téllez
67 J.N.T.
REINFORCED CONCRETE HANDRAIL SHEET
Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg]
Pasamanos superior 10 200 40 120 288 178
Pasamanos inferior 14 200 40 120 288 348
Pasamanos superior 6 40 20 300 180 40
Pasamanos inferior 6 40 20 300 180 40
Estribos de corte 6 60 20 128 102,4 23
Cuerpo del poste 12 102 90 7 12,5 40 64 160,96 143
Acera y bordillo 10 65 40 15 40 40 64 128 79
Longitudinal acera 10 200 40 120 288 178
Longitudinal bordillo 12 200 40 120 288 256
Jaime Navía Téllez
68 J.N.T.
REINFORCED CONCRETE SLAB AND BEAMS SHEET
Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg]
VIGAS LONGITUDINAL 25 1000 40 108 1123,2 4328
VIGAS TRANSVERSAL 10 25 65 20 1200 1320 814
LOSA INTERIOR LONG. 12 1000 40 138 1435,2 1274
LOSA INTERIOR TRANSV. 12 550 50 200 1200 1065
LOSA INT. LONG. SUP. 12 1000 40 72 748,8 665
LOSA INT. TRANSV. SUP. 12 550 50 200 1200 1065
LOSA EXTERIOR LONG. 16 1000 40 54 561,6 886
LOSA EXTERIOR TRANSV. 16 125 20 40 353 653,05 1031
Jaime Navía Téllez
69 J.N.T.
REINFORCED CONCRETE PIER COLUMNS SHEET
Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg]
Columnas pila 1 25 370 40 88 360,8 1390
Estribos pila 1 10 45 714 20 11 85,69 53
Columnas pila 2 25 475 40 88 453,2 1746
Estribos pila 2 10 45 714 20 14 109,06 67
Jaime Navía Téllez
70 J.N.T.
REINFORCED CONCRETE WALLS SHEET
Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg]
PANTALLA ESTRIBO 10 300 40 90 306 189
CUERPO ESTRIBO 10 310 45 40 90 355,5 219
PARAPETO ESTRIBO 10 90 14 110 40 40 90 264,6 163
TRANSV. ESTRIBO 20 710 40 40 300 740
Jaime Navía Téllez
71 J.N.T.
REINFORCED CONCRETE FOUNDATIONS SHEET
Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg]
ZAPATA PILA 1 TRANSVERSAL 25 340 40 26 98,8 381
ZAPATA PILA 1 LONGITUDINAL 25 816 40 25 214 825
ZAPATA PILA 2 TRANSVERSAL 25 354 40 27 106,38 410
ZAPATA PILA 2 LONGITUDINAL 25 816 40 27 231,12 891
ZAPATA DEL ESTRIBO TRANSV. 10 260 40 90 270 166
ZAPATA DEL ESTRIBO LONG. 20 710 14 99,4 245
ZAPATA DEL ESTRIBO TRANSV. INF. 20 265 50 21 66,15 163
ZAPATA DEL ESTRIBO LONG. 20 710 40 14 105 259
Jaime Navía Téllez
72 J.N.T.
3.22 ECONOMIC AND FINANCIAL EVALUATION
Crops of the project Area
Crops AREA [Ha] %
Bean 20 32.26
Potato 12 19.35
Onion 10 16.13
Carrot 10 16.13
Alfalfa 7 11.29
Barley forage 3 4.84
Total 62 100
Volume of production [Tn]
Crops Área [Ha] Performance [t/Ha] Output
Bean 20 5 100
Potato 12 9.2 110.4
Onion 10 16.1 161
Carrot 10 14.49 144.9
Alfalfa 7 4 28
Barley forage 3 3 9
Total 62 553.3
Net value of production in the current situation
Crops Net value of production [Sus] Net worth
[SuS]
Without project
hectare Cost/Hectare Total cost Gross
income /
Hectare
Total
gross
income
Bean 20 246.52 4930.4 1650 33000 28069.6
Potato 12 849.5 10194 3542 42504 32310
Onion 10 868.26 8682.6 2254 22540 13857.4
Carrot 10 849.55 8495.5 1738.8 17388 8892.5
Alfalfa 7 645.94 4521.58 1280 8960 4438.42
Barley
forage
3 286.68 860.04 600 1800 939.96
Total 62 37684.12 126192 88507.88
Jaime Navía Téllez
73 J.N.T.
Net value of production with project
Crops Net value of production [Sus] Net worth
[SuS]
With project
hectare Cost/Hectare Total
cost
Gross
income /
Hectare
Total
gross
income
Bean 20 357.62 7152.4 1980 39600 32447.6
Potato 12 1112.6 13351.2 5775 69300 55948.8
Onion 10 875.16 8751.6 2800 28000 19248.4
Carrot 10 849.55 8495.5 2160 21600 13104.5
Alfalfa 7 685.89 4801.2 1856 12992 8190.8
Barley
forage
3 317 951 778 2334 1383
Total 62 43502.9 173826 130323.1
Socioeconomic evaluation
In any project, it is determined if it is or not feasible the construction,
through socioeconomic indicators, having as an evaluation tool the
parameterized schedules, which determines through its results the
feasibility of the project being the profitability indicators greater than
those established by the vice-minister of public investment and external
financing.
National Parameters
Ratio price account efficiency of the currency 1.24%
Ratio price account efficiency of non-qualified rural labor 0.47%
Ratio price account efficiency of urban unskilled labor 0.23%
Ratio price account efficiency of semi-skilled urban labor 0.43%
Ratio price account efficiency of the total skilled labor 0.44%
Ratio price account efficiency of skilled urban labor 1%
Price account efficiency of foreign labor 0.99%
Jaime Navía Téllez
74 J.N.T.
Social discount rate 12.67%
We also take into account the costs of operation and maintenance.
Detail Costs [SuS]
Tradable goods 1580
Local Materials 200
Skilled labor 2000
Rural unskilled labor 480
Total 4260
Financial indicators
Indicator Value
VACP 888894.46
VANP 1941280.36
CAEP 125095.01
TIRS / 12.67% 40.96
RBCP 3.18
Socioeconomic Indicators
Indicator Value
VACS 825610.61
VANS 2030116.22
CAES 115204.84
TIRS / 12.67% 43.78
RBC social 3.46
As we can see in the tables, the profitability indicators comply with what
is determined by the VIPFE and the preinvestment regulation, in the sense
that the NPV (VAN) is greater than 0 and the IRR (TIR) is higher than the
discount rate. So it is concluded that the project is totally profitable.
Jaime Navía Téllez
75 J.N.T.
3.23. ENVIRONMENTAL FILE
1. GENERAL INFORMATION
Date 10/17/13
Location: Municipality of Soracachi
Developer: Independent
Responsible for completing the form:
Name and surname: Jaime Navía Téllez
Profession: Civil Engineer
Department: Oruro
2. IDENTIFICATION AND LOCATION OF THE PROJECT
Name of the project: DESIGN OF THE SUPERESTRUCTURE VEHICULAR
BRIDGE “OBRAJES”
Physical location of the project, city and / or locality:
Canton: Iruma
Town or City: Soracachi
Province: Cercado
Department: Oruro
Latitude: 17 ° - 49 '-76 "ᵒS
Length: 66 ° - 59' - 16.36" ᵒO
Adjoining Buildings and Developing Activities:
North: Population of Cotochullpa
South: Population of Amachuma
East: Iruma population
West: Population of Paria
Use of soil. Current Usage: Agricultural, Livestock
Potential use: Agricultural
3. DESCRIPTION OF THE SITE OF THE PROJECT
OCCUPIED SURFACE: 1800 [m2]
Occupied by project: 220 [m2]
Description of the land
Topography and slopes: The municipality of Soracachi sits physiographically in
the Bolivian highlands, the influence of the Royal or Eastern mountain range
forms a complex of mountains, without the presence of eternal snow. These form
high terraces, heavily undulating plateaus that, when descending, form small
basins with temperate Sami microclimates
Water quality: Class C1 S1
Predominant vegetation:
COMMON NAME TECHNICAL NAME
Paja suave Esthipa ichu
Paja brava Festuca orthophyla
Suphu thola Parastrephia lepidophyla
Ñacka thola Parastrephia cuadrangulare
Chiji negro Mhulenbergia fastigiata
Jaime Navía Téllez
76 J.N.T.
Tara tara Faviana densa
Natural Drainage Network: Sewer
Human Environment: Rural Population
4. DESCRIPTION OF THE PROJECT
Sector activity: Roads and communication
Specific Activity: Transportation
Nature of the project: New (x) Ampliatory () Others ()
Project stage: Exploitation (x) Execution () Operation ()
Maintenance () Future Induced () Abandonment ()
Scope of the project: Urban () Rural (x)
Overall objective of the project:
The objective of this project is to contribute to improving the quality of life
through a safe and efficient road infrastructure, with the Design of the
superstructure of a vehicular bridge in the community of Obrajes.
Specific objectives of the project:
- Calculation and design of the elements that constitute the superstructure of the
vehicular bridge.
- Draw up detailed drawings with their dimensions and steel cutting.
- Elaboration of costs and budgets taking into account all the necessary and
constructive aspects of the vehicular bridge for its respective feasibility analysis.
- Elaboration of the environmental impact study with the corresponding
mitigation measures.
Relationship with other projects:
It is part of: A plan () Program () Isolated project (x)
Estimated project life: 25 years
5. TOTAL INVESTMENT
Project investment [bs.]
Total cost 851258.25
Jaime Navía Téllez
77 J.N.T.
6. ACTIVITIES
7. HUMAN RESOURCES (Labor)
Qualified Permanent Non permanent
10 7
Non Qualified Permanent Non permanent
4 7
8. NATURAL RESOURCES OF THE AREA, WHICH WILL BE ACHIEVED
RESOURCES QUANTITY [m3]
Material for embankment 47
ITEM DESCRIPTION UNITS WIDTH [m] HIGH [m] AREA [m2] LENGTH [m] TIMES PARTIAL TOTAL
1 PRELIMINARY WORKS M2 280
TOPOGRAPHIC REPLACEMENT M2 8 35 1 280
INFRASTRUCTURE
2 EXCAVATION M3 266,8
WALL 1 M3 3,5 2 8 1 56
WALL 2 M3 3,5 2 8 1 56
PIER COLUMN 1 M3 4,2 2 9 1 75,6
PIER COLUMN 2 M3 4,4 2 9 1 79,2
3 FILLED AND COMPACTED M3 126,84
WALL 1 M3 2,1 1,3 7,3 1 19,929
WALL 2 M3 2,1 1,3 7,3 1 19,929
PIER COLUMN 1 M3 2,9 1,45 8,3 1 34,9015
PIER COLUMN 2 M3 3,1 1,45 8,3 1 37,3085
ADDITIONAL WALL 1 M3 0,7 0,7 8 1 3,92
WALL 2 M3 0,7 0,7 8 1 3,92
PIER COLUMN 1 M3 0,7 0,55 9 1 3,465
PIER COLUMN 2 M3 0,7 0,55 9 1 3,465
4 REINFORCED CONCRETE FUNDATIONS M3 61,48
WALL 1 M3 2,8 0,7 7,3 1 14,308
WALL 2 M3 2,8 0,7 7,3 1 14,308
PIER COLUMN 1 M3 3,5 0,55 8,3 1 15,9775
PIER COLUMN 2 M3 3,7 0,55 8,3 1 16,8905
5 REINFORCED CONCRETE PIERS M3 35,04
PIER COLUMN 1 M3 0,6 3,5 7,3 1 15,33
PIER COLUMN 2 M3 0,6 4,5 7,3 1 19,71
6 WALLS M3 26,28
WALL 1 M3 1,8 7,3 1 13,14
WALL 2 M3 1,8 7,3 1 13,14
SUPERSTRUCTURE
7 REINFORCED CONCRETE BEAMS M3 22,94
PRINCIPAL BEAMS M3 0,3 0,55 10 9 14,85
TRANSVERSE BEAMS M3 2,4 0,4 0,2 14 2,69
EDGE BEAM M3 0,2 0,45 10 6 5,4
8 REINFORCED CONCRETE SLAB M3 43,92
PRINCIPAL SLAB M3 7,3 0,18 10 3 39,42
SIDEWALK M3 0,5 0,15 10 6 4,5
9 REINFORCED CONCRETE PROTECTION M3 3,11
POST M3 0,134 0,2 32 0,86
HANDRAIL M3 0,15 0,125 10 12 2,25
10 TRAFFIC DECK M3 4,38
TRAFFIC DECK M3 7,3 0,02 10 3 4,38
11 NEOPRENE SUPPORTS PZA 18
NEOPRENE SUPPORTS PZA 0,2 0,1 0,5 18
12 SIGNALING PZA 4
VERTICAL PZA
PREVENTIVE SP 34 PZA 1
HORIZONTAL PZA 3
13 GENERAL CLEANING M2 8 35 280
Jaime Navía Téllez
78 J.N.T.
9. NOISE PRODUCTION
SOURCE Construction Equipment
MINIMUM LEVEL: 60 [db] MAXIMUM LEVEL: 80 [db]
10. INDICATE HOW AND WHERE THE INPUTS ARE STORED
The inputs used during project execution such as cement, fuels, timber and others
will be stored under safe and controlled environments.
The water will be stored directly in tank tanks.
11. INDICATE PROCESSES OF TRANSPORTATION AND HANDLING OF
INPUTS
The sand, stone, gravel will be transported from the loan banks to the point of
execution in the corresponding machinery.
The materials considered as natural resources will be used from the same place.
The transport of lubricants and fuels will be carried out by tanker respectively.
12. POSSIBLE ACCIDENTS AND / OR CONTINGENCIES
Exploration:
During the transport of technical personnel who will carry out this stage of the
project, the company is recommended to have industrial safety measures.
During the installation of the camp, various alterations to the environment may
occur, related to the removal of the vegetation cover of the area, temporary
changes in land use, gas emissions, suspended particles, use of lubricants and
others.
Execution:
In the preventive matter of accidents or human contingencies that can be
presented, there is a risk of accidents that may be suffered by workers with
working tools, whether they are minor tools or machinery, these accidents can
Jaime Navía Téllez
79 J.N.T.
suffer from self-neglect or poor maintenance of equipment of work, that is why
the construction company must equip the workers with safety equipment and also
must perform a maintenance in the construction equipment.
13. ENVIRONMENTAL CONSIDERATIONS
(-) Air: particles suspended by earthworks:
Provide personnel with protective nasal spray and water the work area to avoid
particles.
(-) Air: Use of heavy machinery generates gases (Co and Co2) generating
temporary direct impacts, catalysts can be used as a mitigation measure
(-) Soil: Material lending sites are affected by erosion and compaction directly
and permanently, replenishing the vegetation layer as a mitigation measure.
(-) Soil: Machinery originates erosion in the new provisional roads, for the
transfer of loan material, temporary direct impacts are generated, to replenish the
affected earth layer by scarifying and revegetation as a mitigation measure.
(-) Noise: The generation of noise caused by the use of machinery in operation,
should be provided to the personnel hearing protection equipment as a mitigation
measure.
(-) Water: the watercourses will be affected by particles suspended directly and
temporarily. Control the slope compaction of the road as a mitigation measure.
(-) Ecology: The loan of material generates changes in the landscape of the place
in a direct and temporary; reestablish the affected area with plantation and local
species as a mitigation measure.
(+) Socioeconomic: Changes in living standards directly and permanently.
(+) Socioeconomic: Generation of employment directly and permanently.
Jaime Navía Téllez
80 J.N.T.
(+) Socioeconomic: Greater economic movement, for the benefit of the
inhabitants.
(+) Socioeconomic: Better lifestyle of the beneficiary population.
14. ENVIRONMENTAL IMPACT IDENTIFICATION MATRIX
WEIGHTING SCALE:
POSITIVES: 1 = LOW 2 = MODERATE 3 = HIGH
NEGATIVES: -1 = LOW -2 = MODERATE -3 = HIGH
Classification of projects for environmental assessment
Interpreting the results obtained in the matrix of environmental impacts, we observe that it
falls into category ii, which means that it requires specific analytical environmental impact
assessment.
Jaime Navía Téllez
81 J.N.T.
CHAPTER 4
CONLCUSIONS
AND
RECOMMENDATIONS
Jaime Navía Téllez
82 J.N.T.
4.1 CONCLUSIONS
With the project “Obrajes vehicular bridge” it was possible to grant to the
community of Obrajes a project of vehicular bridge, if it is constructed
could solve the problems of null transitability in rainy seasons.
Were designed and calculated all the elements belonging to the
superstructure of the vehicular bridge.
The interior slab and exterior slab of the vehicular bridge were designed
and calculated.
Each of the beams of the vehicular bridge were designed and calculated.
We calculated the steel reinforcement of the slab and beams of the
vehicular bridge.
The scale drawings of each of the elements belonging to the
superstructure as well as each of the transverse and longitudinal sections
of the vehicular bridge were designed.
We elaborated the costs and budgets taking into account all the necessary
and constructive aspects of the vehicular bridge for its respective
feasibility analysis.
We elaborated the environmental impact study with the corresponding
mitigation measures.
If the project is constructed, it could grant to the community of Obrajes an
infrastructure suitable to achieve a free and fluid transitability at all
seasons of the year.
Jaime Navía Téllez
83 J.N.T.
If the project is constructed it could solve the problems of transitability in
rainy seasons and improve the lifestyle of the beneficiary populations.
if the project is constructed it could be solved that the villagers will no
longer have the need to look for alternate routes when there is a flood of
the river.
If the project is built it could improve the economic aspect of the villagers,
because due to this vehicular bridge the villagers will no longer have
difficulties in the transfer of their agricultural and livestock products.
4.2 RECOMMENDATIONS
If the project will be constructed it is recommended to follow the design
drawings and each of the specifications placed in it, so as not to have
inconveniences of cracking or collapse of the structure. The biggest
danger in the construction of the vehicular bridge is the launching of the
beams, because when they are launched with a crane, they suffer the risk
of being destroyed or deformed in the lifting process, which would lead to
rework, producing an extra cost , so it is recommended firstly the
formwork of the beams can be disassembled after 3 days and need a
minimum of 14 days before they can be lifted, although the concrete
maintains its shape after only 3 days, needs at least 14 days to achieve a
strong resistance to be able.
Jaime Navía Téllez
84 J.N.T.
It is necessary to hire a crane strong enough to move the beams, the beams
have a certain weight, but since they tend to deform it would be good to
increase the already calculated weight by 30% as a safety factor, therefore
get a crane that can move the weight of the increased beam by 30%.
The beams must be lifting with the hooks at each end, lifting them in this
way means that the forces in the beams will be the same when placed on
piles and stirrups.
The beams can be deformed during the casting process, if this happens the
support of the formwork can be increased with more stakes joined with
wire.
It is important to keep the edges of the pressed wood lined up, if they
separate or move, they can create raw edges, and those points are high
pressure that can cause a collapse.
Recommendations for repairing a beam after casting
Large holes in a beam should be repaired with concrete of 1 cement, 2 of
sand, 3 gravel, and Sika.
Surface repairs, such as exposed gravel, can be used with Sika mortars.
If there is a hole in which the reinforcing steel can be seen, it is necessary
to make a new beam.
Jaime Navía Téllez
85 J.N.T.
CHAPTER 5 APPENDICES

More Related Content

Similar to VEHICULAR BRIDGE DESIGN 1/2 - JAIME NAVÍA TÉLLEZ

Alvarado cabrera inca martinez david polanco_vidal cardeña_graus medina
Alvarado cabrera inca martinez david polanco_vidal cardeña_graus medinaAlvarado cabrera inca martinez david polanco_vidal cardeña_graus medina
Alvarado cabrera inca martinez david polanco_vidal cardeña_graus medina
jose12002
 
water for rural communities
water for rural communitieswater for rural communities
water for rural communities
Stephen Musimba
 
Book2water for rural_communitiespdf
Book2water for rural_communitiespdfBook2water for rural_communitiespdf
Book2water for rural_communitiespdf
smohakhud44
 
Eugene PBMP Final small_201409161329153001
Eugene PBMP Final small_201409161329153001Eugene PBMP Final small_201409161329153001
Eugene PBMP Final small_201409161329153001
Briana Orr
 
Centerline Cons.(Final Print)
Centerline Cons.(Final Print)Centerline Cons.(Final Print)
Centerline Cons.(Final Print)
Mariel Rosario
 
My "Feasibility" Project
My "Feasibility" ProjectMy "Feasibility" Project
My "Feasibility" Project
saveli4
 

Similar to VEHICULAR BRIDGE DESIGN 1/2 - JAIME NAVÍA TÉLLEZ (20)

Civic Master Plan - Oct. 3, 2013 Draft
Civic Master Plan - Oct. 3, 2013 DraftCivic Master Plan - Oct. 3, 2013 Draft
Civic Master Plan - Oct. 3, 2013 Draft
 
Rethinking the Jonio Metro station as a Transport Hub
Rethinking the Jonio Metro station as a Transport HubRethinking the Jonio Metro station as a Transport Hub
Rethinking the Jonio Metro station as a Transport Hub
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA Winners
 
Last paper 1 edited1
Last paper 1 edited1Last paper 1 edited1
Last paper 1 edited1
 
Proposal rasjayanto sumuran
Proposal rasjayanto sumuranProposal rasjayanto sumuran
Proposal rasjayanto sumuran
 
Deniz Akman Portfolio 2017
Deniz Akman Portfolio 2017Deniz Akman Portfolio 2017
Deniz Akman Portfolio 2017
 
Alvarado cabrera inca martinez david polanco_vidal cardeña_graus medina
Alvarado cabrera inca martinez david polanco_vidal cardeña_graus medinaAlvarado cabrera inca martinez david polanco_vidal cardeña_graus medina
Alvarado cabrera inca martinez david polanco_vidal cardeña_graus medina
 
Civic Master Plan - October 18, 2013 Draft
Civic Master Plan - October 18, 2013 DraftCivic Master Plan - October 18, 2013 Draft
Civic Master Plan - October 18, 2013 Draft
 
water for rural communities
water for rural communitieswater for rural communities
water for rural communities
 
Kenya; Water for Rural Communities: How Kenyan Rural Communities Can Create...
Kenya;  Water for Rural Communities:  How Kenyan Rural Communities Can Create...Kenya;  Water for Rural Communities:  How Kenyan Rural Communities Can Create...
Kenya; Water for Rural Communities: How Kenyan Rural Communities Can Create...
 
Book2water for rural_communitiespdf
Book2water for rural_communitiespdfBook2water for rural_communitiespdf
Book2water for rural_communitiespdf
 
Civic Master Plan - Nov. 4, 2013 Version
Civic Master Plan - Nov. 4, 2013 VersionCivic Master Plan - Nov. 4, 2013 Version
Civic Master Plan - Nov. 4, 2013 Version
 
Eugene PBMP Final small_201409161329153001
Eugene PBMP Final small_201409161329153001Eugene PBMP Final small_201409161329153001
Eugene PBMP Final small_201409161329153001
 
City of Beaufort Civic Master Plan - Adopted
City of Beaufort Civic Master Plan - AdoptedCity of Beaufort Civic Master Plan - Adopted
City of Beaufort Civic Master Plan - Adopted
 
Centerline Cons.(Final Print)
Centerline Cons.(Final Print)Centerline Cons.(Final Print)
Centerline Cons.(Final Print)
 
City of Concord Complete Streets Study
City of Concord Complete Streets StudyCity of Concord Complete Streets Study
City of Concord Complete Streets Study
 
City of Concord Complete Streets Study
City of Concord Complete Streets StudyCity of Concord Complete Streets Study
City of Concord Complete Streets Study
 
My "Feasibility" Project
My "Feasibility" ProjectMy "Feasibility" Project
My "Feasibility" Project
 
Revised-EIA-Report-of-MRT-Line-1.pdf
Revised-EIA-Report-of-MRT-Line-1.pdfRevised-EIA-Report-of-MRT-Line-1.pdf
Revised-EIA-Report-of-MRT-Line-1.pdf
 
Project Report on House Construction under PMAY
Project Report on House Construction under PMAYProject Report on House Construction under PMAY
Project Report on House Construction under PMAY
 

More from Jaime Navía Téllez

PAPER: Determination of additional carbon dioxide emissions in light internal...
PAPER: Determination of additional carbon dioxide emissions in light internal...PAPER: Determination of additional carbon dioxide emissions in light internal...
PAPER: Determination of additional carbon dioxide emissions in light internal...
Jaime Navía Téllez
 
Determinación de las emisiones adicionales de dióxido de carbono en vehículos...
Determinación de las emisiones adicionales de dióxido de carbono en vehículos...Determinación de las emisiones adicionales de dióxido de carbono en vehículos...
Determinación de las emisiones adicionales de dióxido de carbono en vehículos...
Jaime Navía Téllez
 
PAPER: Determination of excess fuel consumption in light internal combustion ...
PAPER: Determination of excess fuel consumption in light internal combustion ...PAPER: Determination of excess fuel consumption in light internal combustion ...
PAPER: Determination of excess fuel consumption in light internal combustion ...
Jaime Navía Téllez
 
ARTÍCULO: Determinación del consumo excesivo de combustible en vehículos livi...
ARTÍCULO: Determinación del consumo excesivo de combustible en vehículos livi...ARTÍCULO: Determinación del consumo excesivo de combustible en vehículos livi...
ARTÍCULO: Determinación del consumo excesivo de combustible en vehículos livi...
Jaime Navía Téllez
 
PAPER: Comparison between λ, α, Meyerhof, Vesic, Coyle Castello, SPT, Briaud,...
PAPER: Comparison between λ, α, Meyerhof, Vesic, Coyle Castello, SPT, Briaud,...PAPER: Comparison between λ, α, Meyerhof, Vesic, Coyle Castello, SPT, Briaud,...
PAPER: Comparison between λ, α, Meyerhof, Vesic, Coyle Castello, SPT, Briaud,...
Jaime Navía Téllez
 
ARTÍCULO: Comparación entre los métodos λ, α, Meyerhof, Vesic, Coyle Castello...
ARTÍCULO: Comparación entre los métodos λ, α, Meyerhof, Vesic, Coyle Castello...ARTÍCULO: Comparación entre los métodos λ, α, Meyerhof, Vesic, Coyle Castello...
ARTÍCULO: Comparación entre los métodos λ, α, Meyerhof, Vesic, Coyle Castello...
Jaime Navía Téllez
 
PAPER: DETERMINATION OF THE EVAPOTRANSPIRATION OF THE HYDROGRAPHIC BASIN “HYD...
PAPER: DETERMINATION OF THE EVAPOTRANSPIRATION OF THE HYDROGRAPHIC BASIN “HYD...PAPER: DETERMINATION OF THE EVAPOTRANSPIRATION OF THE HYDROGRAPHIC BASIN “HYD...
PAPER: DETERMINATION OF THE EVAPOTRANSPIRATION OF THE HYDROGRAPHIC BASIN “HYD...
Jaime Navía Téllez
 
ARTICULO: DETERMINACIÓN DE LA EVAPOTRANSPIRACIÓN DE LA CUENCA HIDROGRÁFICA "U...
ARTICULO: DETERMINACIÓN DE LA EVAPOTRANSPIRACIÓN DE LA CUENCA HIDROGRÁFICA "U...ARTICULO: DETERMINACIÓN DE LA EVAPOTRANSPIRACIÓN DE LA CUENCA HIDROGRÁFICA "U...
ARTICULO: DETERMINACIÓN DE LA EVAPOTRANSPIRACIÓN DE LA CUENCA HIDROGRÁFICA "U...
Jaime Navía Téllez
 
PAPER: DETERMINATION OF SEDIMENT TRANSPORT IN THE BASIN "HYDROGRAPHIC UNIT 02...
PAPER: DETERMINATION OF SEDIMENT TRANSPORT IN THE BASIN "HYDROGRAPHIC UNIT 02...PAPER: DETERMINATION OF SEDIMENT TRANSPORT IN THE BASIN "HYDROGRAPHIC UNIT 02...
PAPER: DETERMINATION OF SEDIMENT TRANSPORT IN THE BASIN "HYDROGRAPHIC UNIT 02...
Jaime Navía Téllez
 
ARTICULO DETERMINACIÓN DEL TRANSPORTE DE SEDIMENTOS EN LA CUENCA UNIDAD HIDRO...
ARTICULO DETERMINACIÓN DEL TRANSPORTE DE SEDIMENTOS EN LA CUENCA UNIDAD HIDRO...ARTICULO DETERMINACIÓN DEL TRANSPORTE DE SEDIMENTOS EN LA CUENCA UNIDAD HIDRO...
ARTICULO DETERMINACIÓN DEL TRANSPORTE DE SEDIMENTOS EN LA CUENCA UNIDAD HIDRO...
Jaime Navía Téllez
 
ESTUDIO A DISEÑO FINAL PUENTE VEHICULAR TIPO VIGA LOSA – JAIME NAVÍA TÉLLEZ
ESTUDIO A DISEÑO FINAL PUENTE VEHICULAR TIPO VIGA LOSA – JAIME NAVÍA TÉLLEZESTUDIO A DISEÑO FINAL PUENTE VEHICULAR TIPO VIGA LOSA – JAIME NAVÍA TÉLLEZ
ESTUDIO A DISEÑO FINAL PUENTE VEHICULAR TIPO VIGA LOSA – JAIME NAVÍA TÉLLEZ
Jaime Navía Téllez
 
ARTICULO: SIG APLICADO A LA EVALUACIÓN DE IMPACTOS AMBIENTALES EN CARRETERAS ...
ARTICULO: SIG APLICADO A LA EVALUACIÓN DE IMPACTOS AMBIENTALES EN CARRETERAS ...ARTICULO: SIG APLICADO A LA EVALUACIÓN DE IMPACTOS AMBIENTALES EN CARRETERAS ...
ARTICULO: SIG APLICADO A LA EVALUACIÓN DE IMPACTOS AMBIENTALES EN CARRETERAS ...
Jaime Navía Téllez
 
ELABORACIÓN DE UN MAPA DE DESLIZAMIENTOS TRASLACIONALES MEDIANTE EL PROGRAMA ...
ELABORACIÓN DE UN MAPA DE DESLIZAMIENTOS TRASLACIONALES MEDIANTE EL PROGRAMA ...ELABORACIÓN DE UN MAPA DE DESLIZAMIENTOS TRASLACIONALES MEDIANTE EL PROGRAMA ...
ELABORACIÓN DE UN MAPA DE DESLIZAMIENTOS TRASLACIONALES MEDIANTE EL PROGRAMA ...
Jaime Navía Téllez
 
CALCULO DE LA CAPACIDAD DE CARGA ÚLTIMA EN ARCILLAS - JAIME NAVÍA TÉLLEZ
CALCULO DE LA CAPACIDAD DE CARGA ÚLTIMA EN ARCILLAS - JAIME NAVÍA TÉLLEZCALCULO DE LA CAPACIDAD DE CARGA ÚLTIMA EN ARCILLAS - JAIME NAVÍA TÉLLEZ
CALCULO DE LA CAPACIDAD DE CARGA ÚLTIMA EN ARCILLAS - JAIME NAVÍA TÉLLEZ
Jaime Navía Téllez
 
PLAN DE CONTROL Y ASEGURAMIENTO DE LA CALIDAD PUENTE OBRAJES - JAIME NAVÍA TÉ...
PLAN DE CONTROL Y ASEGURAMIENTO DE LA CALIDAD PUENTE OBRAJES - JAIME NAVÍA TÉ...PLAN DE CONTROL Y ASEGURAMIENTO DE LA CALIDAD PUENTE OBRAJES - JAIME NAVÍA TÉ...
PLAN DE CONTROL Y ASEGURAMIENTO DE LA CALIDAD PUENTE OBRAJES - JAIME NAVÍA TÉ...
Jaime Navía Téllez
 
APRENDIZAJE OPERANTE DE SKINNER Y THORNDIKE APLICADO A LA INGENIERÍA CIVIL - ...
APRENDIZAJE OPERANTE DE SKINNER Y THORNDIKE APLICADO A LA INGENIERÍA CIVIL - ...APRENDIZAJE OPERANTE DE SKINNER Y THORNDIKE APLICADO A LA INGENIERÍA CIVIL - ...
APRENDIZAJE OPERANTE DE SKINNER Y THORNDIKE APLICADO A LA INGENIERÍA CIVIL - ...
Jaime Navía Téllez
 
TEORÍA DISEÑO Y EVALUACIÓN CURRICULAR - Jaime Navía Téllez
TEORÍA DISEÑO Y EVALUACIÓN CURRICULAR - Jaime Navía TéllezTEORÍA DISEÑO Y EVALUACIÓN CURRICULAR - Jaime Navía Téllez
TEORÍA DISEÑO Y EVALUACIÓN CURRICULAR - Jaime Navía Téllez
Jaime Navía Téllez
 
GUÍA BOLIVIANA PARA LA SUPERVISIÓN DE OBRAS - Jaime Navía Téllez
GUÍA BOLIVIANA PARA LA SUPERVISIÓN DE OBRAS - Jaime Navía TéllezGUÍA BOLIVIANA PARA LA SUPERVISIÓN DE OBRAS - Jaime Navía Téllez
GUÍA BOLIVIANA PARA LA SUPERVISIÓN DE OBRAS - Jaime Navía Téllez
Jaime Navía Téllez
 

More from Jaime Navía Téllez (18)

PAPER: Determination of additional carbon dioxide emissions in light internal...
PAPER: Determination of additional carbon dioxide emissions in light internal...PAPER: Determination of additional carbon dioxide emissions in light internal...
PAPER: Determination of additional carbon dioxide emissions in light internal...
 
Determinación de las emisiones adicionales de dióxido de carbono en vehículos...
Determinación de las emisiones adicionales de dióxido de carbono en vehículos...Determinación de las emisiones adicionales de dióxido de carbono en vehículos...
Determinación de las emisiones adicionales de dióxido de carbono en vehículos...
 
PAPER: Determination of excess fuel consumption in light internal combustion ...
PAPER: Determination of excess fuel consumption in light internal combustion ...PAPER: Determination of excess fuel consumption in light internal combustion ...
PAPER: Determination of excess fuel consumption in light internal combustion ...
 
ARTÍCULO: Determinación del consumo excesivo de combustible en vehículos livi...
ARTÍCULO: Determinación del consumo excesivo de combustible en vehículos livi...ARTÍCULO: Determinación del consumo excesivo de combustible en vehículos livi...
ARTÍCULO: Determinación del consumo excesivo de combustible en vehículos livi...
 
PAPER: Comparison between λ, α, Meyerhof, Vesic, Coyle Castello, SPT, Briaud,...
PAPER: Comparison between λ, α, Meyerhof, Vesic, Coyle Castello, SPT, Briaud,...PAPER: Comparison between λ, α, Meyerhof, Vesic, Coyle Castello, SPT, Briaud,...
PAPER: Comparison between λ, α, Meyerhof, Vesic, Coyle Castello, SPT, Briaud,...
 
ARTÍCULO: Comparación entre los métodos λ, α, Meyerhof, Vesic, Coyle Castello...
ARTÍCULO: Comparación entre los métodos λ, α, Meyerhof, Vesic, Coyle Castello...ARTÍCULO: Comparación entre los métodos λ, α, Meyerhof, Vesic, Coyle Castello...
ARTÍCULO: Comparación entre los métodos λ, α, Meyerhof, Vesic, Coyle Castello...
 
PAPER: DETERMINATION OF THE EVAPOTRANSPIRATION OF THE HYDROGRAPHIC BASIN “HYD...
PAPER: DETERMINATION OF THE EVAPOTRANSPIRATION OF THE HYDROGRAPHIC BASIN “HYD...PAPER: DETERMINATION OF THE EVAPOTRANSPIRATION OF THE HYDROGRAPHIC BASIN “HYD...
PAPER: DETERMINATION OF THE EVAPOTRANSPIRATION OF THE HYDROGRAPHIC BASIN “HYD...
 
ARTICULO: DETERMINACIÓN DE LA EVAPOTRANSPIRACIÓN DE LA CUENCA HIDROGRÁFICA "U...
ARTICULO: DETERMINACIÓN DE LA EVAPOTRANSPIRACIÓN DE LA CUENCA HIDROGRÁFICA "U...ARTICULO: DETERMINACIÓN DE LA EVAPOTRANSPIRACIÓN DE LA CUENCA HIDROGRÁFICA "U...
ARTICULO: DETERMINACIÓN DE LA EVAPOTRANSPIRACIÓN DE LA CUENCA HIDROGRÁFICA "U...
 
PAPER: DETERMINATION OF SEDIMENT TRANSPORT IN THE BASIN "HYDROGRAPHIC UNIT 02...
PAPER: DETERMINATION OF SEDIMENT TRANSPORT IN THE BASIN "HYDROGRAPHIC UNIT 02...PAPER: DETERMINATION OF SEDIMENT TRANSPORT IN THE BASIN "HYDROGRAPHIC UNIT 02...
PAPER: DETERMINATION OF SEDIMENT TRANSPORT IN THE BASIN "HYDROGRAPHIC UNIT 02...
 
ARTICULO DETERMINACIÓN DEL TRANSPORTE DE SEDIMENTOS EN LA CUENCA UNIDAD HIDRO...
ARTICULO DETERMINACIÓN DEL TRANSPORTE DE SEDIMENTOS EN LA CUENCA UNIDAD HIDRO...ARTICULO DETERMINACIÓN DEL TRANSPORTE DE SEDIMENTOS EN LA CUENCA UNIDAD HIDRO...
ARTICULO DETERMINACIÓN DEL TRANSPORTE DE SEDIMENTOS EN LA CUENCA UNIDAD HIDRO...
 
ESTUDIO A DISEÑO FINAL PUENTE VEHICULAR TIPO VIGA LOSA – JAIME NAVÍA TÉLLEZ
ESTUDIO A DISEÑO FINAL PUENTE VEHICULAR TIPO VIGA LOSA – JAIME NAVÍA TÉLLEZESTUDIO A DISEÑO FINAL PUENTE VEHICULAR TIPO VIGA LOSA – JAIME NAVÍA TÉLLEZ
ESTUDIO A DISEÑO FINAL PUENTE VEHICULAR TIPO VIGA LOSA – JAIME NAVÍA TÉLLEZ
 
ARTICULO: SIG APLICADO A LA EVALUACIÓN DE IMPACTOS AMBIENTALES EN CARRETERAS ...
ARTICULO: SIG APLICADO A LA EVALUACIÓN DE IMPACTOS AMBIENTALES EN CARRETERAS ...ARTICULO: SIG APLICADO A LA EVALUACIÓN DE IMPACTOS AMBIENTALES EN CARRETERAS ...
ARTICULO: SIG APLICADO A LA EVALUACIÓN DE IMPACTOS AMBIENTALES EN CARRETERAS ...
 
ELABORACIÓN DE UN MAPA DE DESLIZAMIENTOS TRASLACIONALES MEDIANTE EL PROGRAMA ...
ELABORACIÓN DE UN MAPA DE DESLIZAMIENTOS TRASLACIONALES MEDIANTE EL PROGRAMA ...ELABORACIÓN DE UN MAPA DE DESLIZAMIENTOS TRASLACIONALES MEDIANTE EL PROGRAMA ...
ELABORACIÓN DE UN MAPA DE DESLIZAMIENTOS TRASLACIONALES MEDIANTE EL PROGRAMA ...
 
CALCULO DE LA CAPACIDAD DE CARGA ÚLTIMA EN ARCILLAS - JAIME NAVÍA TÉLLEZ
CALCULO DE LA CAPACIDAD DE CARGA ÚLTIMA EN ARCILLAS - JAIME NAVÍA TÉLLEZCALCULO DE LA CAPACIDAD DE CARGA ÚLTIMA EN ARCILLAS - JAIME NAVÍA TÉLLEZ
CALCULO DE LA CAPACIDAD DE CARGA ÚLTIMA EN ARCILLAS - JAIME NAVÍA TÉLLEZ
 
PLAN DE CONTROL Y ASEGURAMIENTO DE LA CALIDAD PUENTE OBRAJES - JAIME NAVÍA TÉ...
PLAN DE CONTROL Y ASEGURAMIENTO DE LA CALIDAD PUENTE OBRAJES - JAIME NAVÍA TÉ...PLAN DE CONTROL Y ASEGURAMIENTO DE LA CALIDAD PUENTE OBRAJES - JAIME NAVÍA TÉ...
PLAN DE CONTROL Y ASEGURAMIENTO DE LA CALIDAD PUENTE OBRAJES - JAIME NAVÍA TÉ...
 
APRENDIZAJE OPERANTE DE SKINNER Y THORNDIKE APLICADO A LA INGENIERÍA CIVIL - ...
APRENDIZAJE OPERANTE DE SKINNER Y THORNDIKE APLICADO A LA INGENIERÍA CIVIL - ...APRENDIZAJE OPERANTE DE SKINNER Y THORNDIKE APLICADO A LA INGENIERÍA CIVIL - ...
APRENDIZAJE OPERANTE DE SKINNER Y THORNDIKE APLICADO A LA INGENIERÍA CIVIL - ...
 
TEORÍA DISEÑO Y EVALUACIÓN CURRICULAR - Jaime Navía Téllez
TEORÍA DISEÑO Y EVALUACIÓN CURRICULAR - Jaime Navía TéllezTEORÍA DISEÑO Y EVALUACIÓN CURRICULAR - Jaime Navía Téllez
TEORÍA DISEÑO Y EVALUACIÓN CURRICULAR - Jaime Navía Téllez
 
GUÍA BOLIVIANA PARA LA SUPERVISIÓN DE OBRAS - Jaime Navía Téllez
GUÍA BOLIVIANA PARA LA SUPERVISIÓN DE OBRAS - Jaime Navía TéllezGUÍA BOLIVIANA PARA LA SUPERVISIÓN DE OBRAS - Jaime Navía Téllez
GUÍA BOLIVIANA PARA LA SUPERVISIÓN DE OBRAS - Jaime Navía Téllez
 

Recently uploaded

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 

Recently uploaded (20)

Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 

VEHICULAR BRIDGE DESIGN 1/2 - JAIME NAVÍA TÉLLEZ

  • 1. VEHICULAR BRIDGE DESIGN “CASE STUDY COMMUNITY OF OBRAJES” JAIME NAVÍA TÉLLEZ
  • 2. To my parents Jaime Navía Camacho Tusnelda Téllez de Navía I dedicate this project to my Parents, my source of inspiration and wisdom. For their endless love and support thank you.
  • 3. Jaime Navía Téllez 3 J.N.T. ABSTRACT NAME OF THE PROJECT: Vehicular Bridge Design “Case Study Community of Obrajes” The community of Obrajes is located in the Municipality of Soracachi, province Cercado of the department of Oruro. Is characterized by a frigid and dry climate, which is increasing considerably by the altitude of the area. For a long time, the idea of building a vehicular bridge that allows the population a free movement has prevailed. And since the demand for vehicular flow has been growing in recent years in the Municipality of Soracachi, the construction of a vehicular bridge has become a necessity. One of the main activities carried out in the Municipality of Soracachi is agriculture, the municipality has a high agricultural potential, the transfer and marketing of its products is complicated due to the poor state of the road and in rainy seasons with the river rising it is impassable, so the inhabitants of the different Communities of the Municipality look for alternate routes. Given the above pretensions, we assume the task of carrying out this work consisting of the design of the superstructure and infrastructure of a bridge located on the road Obrajes- Iruma. With the realization of the project, a free transit will be achieved and the quality of life of the community members will be improved.
  • 4. Jaime Navía Téllez 4 J.N.T. The project consists of the design and calculation of a vehicular bridge type “Beam – Slab” located in the community of Obrajes. It is a bridge with 3 spans of 10 meters each one with beams simply supported; adding up a total span of 30 meters. The design process of a bridge can be divided into four basic stages: conceptual design, preliminary design and detailed design. The purpose of the conceptual design is to come up with various feasible bridge schemes and to decide on one or more final concepts for further consideration. The purpose of the preliminary design is to select the best scheme from these proposed concepts and then to ascertain the feasibility of the selected concept and finally to refine its cost estimates. Finally, the purpose of the detailed design is to finalize all the details of the bridge structure so that the document is sufficient for tendering and construction.
  • 5. Jaime Navía Téllez 5 J.N.T. Contenido CHAPTER 1 INTRODUCTION...................................................... 9 1.1 BACKGROUND.................................................................. 10 1.1.1 GENERAL BACKGROUND ....................................... 10 1.1.2 SPECIFIC BACKGROUND......................................... 11 1.2. PROBLEM STATEMENT.................................................. 13 1.2.1 IDENTIFICATION OF THE PROBLEM .................... 13 1.2.2 FORMULATION OF THE PROBLEM ....................... 15 1.3 OBJECTIVES....................................................................... 15 1.3.1 GENERAL OBJECTIVE .............................................. 15 1.3.2 SPECIFIC OBJECTIVES ............................................. 15 1.4 JUSTIFICATION AND SCOPE.......................................... 16 1.4.1 JUSTIFICATION.......................................................... 16 1.4.2 SCOPE........................................................................... 17 1.5. RESEARCH METHODOLOGY ........................................ 18 1.5.1. KIND OF INVESTIGATION ...................................... 18 1.5.2. LOCATION.................................................................. 19 CHAPTER 2................................................................................... 21 THEORETICAL CONCEPTUAL FRAMEWORK ...................... 21 2.1 MUNICIPALITY OF SORACACHI................................... 22 2.1.1 POLITICAL AND ADMINISTRATIVE DIVISION... 22 2.1.2 POPULATION.............................................................. 23 2.1.3 LANGUAGE................................................................. 23 2.1.4 ECONOMIC PRODUCTIVE ASPECT........................ 24 2.2 VEHICULAR BRIDGE ....................................................... 24 2.2.1 HISTORY...................................................................... 24 2.2.2 BRIDGE ........................................................................ 25 2.2.3 TYPES OF BRIDGES................................................... 25 2.2.4 BRIDGE TYPES BY USE............................................ 26 2.2.5 BRIDGE TYPES BY MATERIAL............................... 26
  • 6. Jaime Navía Téllez 6 J.N.T. 2.2.6 AESTHETICS ............................................................... 27 2.2.7 BRIDGE MAINTENANCE.......................................... 28 2.2.8 BRIDGE FAILURES .................................................... 28 2.2.9 BRIDGE MONITORING.............................................. 28 2.3 DEFINITIONS AND COMPONENTS ............................... 29 2.3.1 VEHICULAR BRIDGE ................................................ 30 2.3.2 ROAD INFRASTRUCTURE ....................................... 30 2.3.3 SUPERSTRUCTURE ................................................... 31 2.3.4 SUBSTRUCTURE........................................................ 31 2.3.5 AASHTO DESIGN STANDARD ................................ 31 2.3.6 LOADS OF DESIGN.................................................... 31 2.3.7 PERMANENT LOAD................................................... 31 2.3.8 LIVE LOAD.................................................................. 32 2.3.9 FOUNDATION............................................................. 32 2.3.10 BEAM / GIRDER........................................................ 33 2.3.11 BEARING ................................................................... 33 2.3.12 PIER OR COLUMN.................................................... 33 2.3.13 TRUCK TYPE LOAD AND EQUIVALENT LOAD 34 2.3.14 CONCRETE RESISTANCE....................................... 34 2.3.15 TRAFFIC DECK THICKNESS.................................. 34 2.3.16 REINFORCED CONCRETE BEAMS ....................... 35 2.3.17 CONCRETE SLAB..................................................... 35 2.3.18 COMPONENT ............................................................ 35 2.3.19 DEFORMATION........................................................ 36 2.3.20 DESIGN ...................................................................... 36 2.3.21 ELASTIC..................................................................... 36 2.3.22 ELEMENT .................................................................. 36 2.3.23 EQUILIBRIUM........................................................... 36 2.3.24 EQUIVALENT BEAM............................................... 36 2.3.25 EQUIVALENT STRIP................................................ 37
  • 7. Jaime Navía Téllez 7 J.N.T. 2.3.26 FINITE DIFFERENCE METHOD ............................. 37 2.3.27 FORCE EFFECT......................................................... 37 2.3.28 FOUNDATION........................................................... 37 2.3.29 LARGE DEFLECTION THEORY............................. 37 2.3.30 MEMBER.................................................................... 38 2.3.31 METHOD OF ANALYSIS ......................................... 38 2.3.32 MODEL....................................................................... 38 2.3.33 STIFFNESS................................................................. 38 2.3.34 YIELD LINE METHOD............................................. 38 CHAPTER 3 CALCULATION AND DESIGN ............................ 39 3.1 BRIDGE CONSTRUCTION ............................................... 40 3.2 BRIDGE CONSTRUCTION PLANNING.......................... 40 3.3 BRIDGE FOUNDATION.................................................... 41 3.4 BRIDGE CONSTRUCTION EQUIPMENT ....................... 41 3.5 BRIDGE LOADS................................................................. 42 3.6 TESTING OF BRIDGES ..................................................... 42 3.7 CONSIDERATIONS IN BRIDGE DESIGN....................... 43 3.8 SUPERSTRUCTURE AND INFRASTRUCTURE ............ 44 3.9 TENSION AND COMPRESSION ...................................... 45 3.10 RESONANCE .................................................................... 45 3.11 DESIGN METHODS ......................................................... 46 3.12 DESIGN PHILOSOPHY.................................................... 47 3.13 STRUCTURAL ANALYSIS ............................................. 49 3.14 ACCEPTABLE METHODS OF STRUCTURAL ANALYSIS ................................................................................ 50 3.15 MATHEMATICAL MODELING ..................................... 50 3.16 ELASTIC BEHAVIOR...................................................... 51 3.17 SMALL DEFLECTION THEORY.................................... 51 3.18 ANALYSIS AND STRUCTURAL DESIGN OF THE BRIDGE ..................................................................................... 52
  • 8. Jaime Navía Téllez 8 J.N.T. 3.18.1 CONSIDERATIONS OF SUPERSTRUCTURE AND INFRASTRUCTURE DESIGN ............................................. 52 3.19 DESIGN OF SUPERSTRUCTURE................................... 54 3.19.1 HANDRAIL DESIGN................................................. 54 3.19.2 SLAB DESIGN ........................................................... 55 3.19.3 CALCULATION AND DESIGN OF OPTIMIZED BEAMS .................................................................................. 58 3.20 INFRASTRUCTURE DESIGN ......................................... 59 3.20.1 DESIGN OF WALLS, COLUMNS AND FOUNDATIONS.................................................................... 59 3.20.2 DESIGN OF WALLS.................................................. 60 3.21 DRAWINGS....................................................................... 61 3.22 ECONOMIC AND FINANCIAL EVALUATION............ 72 3.23. ENVIRONMENTAL FILE ............................................... 75 CHAPTER 4................................................................................... 81 CONLCUSIONS ............................................................................ 81 AND ............................................................................................... 81 RECOMMENDATIONS ............................................................... 81 4.1 CONCLUSIONS .................................................................. 82 4.2 RECOMMENDATIONS ..................................................... 83 CHAPTER 5 APPENDICES.......................................................... 85
  • 9. Jaime Navía Téllez 9 J.N.T. CHAPTER 1 INTRODUCTION
  • 10. Jaime Navía Téllez 10 J.N.T. 1.1 BACKGROUND 1.1.1 GENERAL BACKGROUND The bridges constitute an element of extreme importance in the construction of a highway. A bridge is a construction that allows saving a geographic accident like a river, a canyon, a valley, a road, a railroad, or any other physical obstacle. The design of each bridge varies depending on its function and the nature of the terrain on which it is built. Its design and its calculation belong to structural engineering, with numerous types of designs that have been applied throughout history, influenced by available materials, techniques developed and economic considerations, among other factors. At the moment of analyzing the design of a bridge, the quality of the soil or rock where it will be supported and the regime of the river above the one that crosses are of paramount importance to guarantee the life of the same one. The design and construction of vehicular bridges in Bolivia has been developed in response to the urgent demand that the inhabitants of the cities and communities are far from improving their quality of life, since without them, their quality of life would be very bad especially of the remote communities because they would have great difficulties in their transfer and mobilization in the place, in most cases the lack of this type of infrastructures negatively affects mainly remote communities, most of the communities live from agricultural production and livestock, and
  • 11. Jaime Navía Téllez 11 J.N.T. without the infrastructure it would be impossible for them to move their products for later sale. That is why the importance of this type of structures that improves the quality of life of residents both social and economic. 1.1.2 SPECIFIC BACKGROUND The community of Obrajes is located in the Municipality of Soracachi, province Cercado of the department of Oruro. It is located 26 km northwest of the city, 30 to 40 minutes by public transport. The Municipality of Soracachi has an area of 1254.94 Km2, is divided into four municipal districts, seven cantons and 113 communities. According to the 2012 census the municipality has a total population of 12,788; 6,420 (50.2%) males and 6,368 (49.8%) females. Soracachi is characterized by a frigid and dry climate, which is increasing considerably by the altitude of the area. Although the climate and characteristics of the Altiplano are factors that conditioning the agricultural production, the municipality shows its agricultural and livestock potential. The geographical distribution of the municipality shows a high zone, several hills that make up micro basins, all with agroecological characteristics, with a productive potential oriented mainly to agriculture and livestock, in most of the municipality mixed production systems are developed.
  • 12. Jaime Navía Téllez 12 J.N.T. The agricultural activity of the municipality is recognized for its horticultural production, mainly carrot and onion. Data from the Municipal Government (2011) show that the cultivation of barley represents an area of 19.77%, carrot 17.38% and alfalfa 16.24%. Another potential is the cattle activity, in this activity has preeminence the ovine cattle, followed by the cattle camelido and bovine.
  • 13. Jaime Navía Téllez 13 J.N.T. 1.2. PROBLEM STATEMENT 1.2.1 IDENTIFICATION OF THE PROBLEM In this case we use one of the most known methods to identify problems: Which name is “Problem tree” consist in identify causes and effects of the problem.
  • 14. Jaime Navía Téllez 14 J.N.T. The problem is: “LOW TRANSITABILITY OF VEHICLES IN RAINY SEASON IN THE COMMUNITY OF OBRAJES”, to solve that problem we need three steps: 1) Design Project 2) Financing by the municipality 3) With the project we construct the bridge Steps 2 and 3 depend on the municipal authorities of Obrajes for that reason we can’t solve all the problems, but step 1 “Design Project” which means calculation and design we can solve it. As a result the specific problem will be: “Lack of a road project in the community of Obrajes”
  • 15. Jaime Navía Téllez 15 J.N.T. 1.2.2 FORMULATION OF THE PROBLEM How can we solve the Lack of a road project in the community of Obrajes? 1.2.2.1 HYPOTHESIS We will be able solve the Lack of a road project in the community of Obrajes with the design and calculation of the superstructure and infrastructure of a vehicular bridge. 1.3 OBJECTIVES 1.3.1 GENERAL OBJECTIVE Design and calculation of the superstructure and infrastructure of the vehicular bridge located in the community of Obrajes. 1.3.2 SPECIFIC OBJECTIVES -Calculation and design of the elements that constitute the superstructure of the vehicular bridge. -Calculation and design of the elements that constitute the infrastructure of the vehicular bridge. -Draw up detailed drawings with their dimensions and steel cutting. -Elaboration of costs and budgets taking into account all the necessary and constructive aspects of the vehicular bridge for its respective feasibility analysis.
  • 16. Jaime Navía Téllez 16 J.N.T. -Elaboration of the environmental impact study with the corresponding mitigation measures. 1.4 JUSTIFICATION AND SCOPE 1.4.1 JUSTIFICATION 1.4.1.1. TECHNICAL JUSTIFICATION A bridge is a road infrastructure that allows saving a geographic accident to allow a constant vehicular flow in all the seasons of the year. So with the design of the superstructure of the vehicle bridge Obrajes would be guaranteeing to the affected population a free vehicular traffic. For decades, the design of vehicle bridges has been made, so the design is safe and reliable and there are design standards that facilitate design and reliability. There are several types of bridges and different materials, which give a wide range of possibilities to solve problems of transitability, and also give the possibility of choosing the best alternative either as complexity or cost of the structure. 1.4.1.2. ECONOMIC JUSTIFICATION Recall that the main economic activity of the community and the municipality is agriculture and livestock. Also remember that in rainy seasons it is difficult for the villagers to move these products for later sale,
  • 17. Jaime Navía Téllez 17 J.N.T. in some cases can occur delays in deliveries or also for the bad state of the road losses can occur in their products, which affects in a economic way to the municipality. And with the design of this vehicular bridge would be guaranteeing a free transitability in all the seasons of the year, reason why would be benefiting in the economic activity of the municipality. 1.4.1.3. SOCIAL JUSTIFICATION A vehicular bridge is a road structure that, besides saving geographical obstacles, allows the joining of two or more sections, which means that the vehicular bridge will not only benefit the affected population, it also will allow the connection of the community of Obrajes with other communities granting easy access to each of them. Also in the tourist part, the community of Obrajes has “Pinturas Rupestres” and with the existence of a vehicular bridge would facilitate access to it and would become more common the visit of tourists. 1.4.2 SCOPE 1.4.2.1. THEMATIC SCOPE In this project a proposal will be made to design a superstructure and infrastructure of a vehicular bridge which will grant a free transitability during rainy seasons in the community of Obrajes.
  • 18. Jaime Navía Téllez 18 J.N.T. 1.4.2.2. SPACE SCOPE The project will be carried out in the community of Obrajes. Focused on a model that grants a free transitability in times of rain. 1.4.2.3. TEMPORARY SCOPE The project will be developed in a time of 3 months. 1.5. RESEARCH METHODOLOGY For this project we are going to use the scientific method, is a method of research in which a problem is identified, relevant data are gathered, a hypothesis is formulated from these data, and the hypothesis is empirically tested. 1.5.1. KIND OF INVESTIGATION The degree project is categorized as a proactive research since it consists of a design proposal of a vehicular bridge located in the community of Obrajes, thus giving solution to the problem posed previously. It is the Community of Obrajes who will decide in the future the construction of this project.
  • 19. Jaime Navía Téllez 19 J.N.T. 1.5.2. LOCATION The project is located in the municipality of Soracachi, province of Cercado, Oruro Department. It is bordered to the North by La Paz department, to the South by the municipality of Machacamarca (Pantaleon Dalence Province), to the east by the municipality of Huanuni (Pantaleon Dalence Province) and to the West by the municipality of Caracollo (Cercado province). The municipality of Soracachi, is located 26 km northwest of the city of Oruro, 30 to 40 minutes by public transport. It is located between the parallels 17 ° 30 'and 18 ° 05' south latitude and meridians 66 ° 42 'and 67 ° 20' west longitude, in the central high plateau of Bolivia. The average altitude in the municipality of Soracachi is 3,706 meters above sea level, one of the highest points is located in the community of Romerocota on the hill Irupata with 4,304 meters above sea level.
  • 20. Jaime Navía Téllez 20 J.N.T. POLITICAL AND GEOGRAPHICAL LOCATION OF THE PROJECT Department: Oruro Province: Cercado Province Section : Third Section Municipality of Soracachi Cantón : Iruma Community: Obrajes Geographically the Obrajes community is located approximately between the coordinates of Austral latitude of the Greenwich Meridian. Latitude: 17 ° 49 '35.062 "South Length: 66 ° 59'23.34 "West The community of Obrajes limits with the following communities: NORTH: Population of Cotochullpa SOUTH: Population of Amachuma EAST: Iruma Population WEST: Paria Population The average elevation in which the beneficiary population is located is approximately 3740 meters above sea level.
  • 21. Jaime Navía Téllez 21 J.N.T. CHAPTER 2 THEORETICAL CONCEPTUAL FRAMEWORK
  • 22. Jaime Navía Téllez 22 J.N.T. 2.1 MUNICIPALITY OF SORACACHI 2.1.1 POLITICAL AND ADMINISTRATIVE DIVISION The Municipality of Soracachi has an area of 1254.94 Km2, is divided into four municipal districts, seven cantons and where 113 communities are located. The first District has 3 Cantons: 1. Soracachi Canton where 8 communities are located. 2. Lequepalca Canton where 12 communities are located. 3. Iruma Canton where 13 communities are located. The second District has 2 Cantons: 1. 9 de Abril (Tholapalca) Canton where 30 communities are located. 2. Paria Canton where 30 communities are located. The third District has 1 Canton: 1. Teniente Bullain Canton where 8 communities are located. The fourth District has 1 Canton: 1. Huayña Pasto Grande Canton where 12 communities are located.
  • 23. Jaime Navía Téllez 23 J.N.T. 2.1.2 POPULATION MUNICIPALITY OF SORACACHI: According to the 2012 census the Municipality has a total population of 12,788: 6,420 (50.2%) males and 6,368 (49.8%) females. With an annual intercensal growth rate of 1.0% (2001 - 2012). POPULATION “MUNICIPALITY OF SORACACHI” BOTH GENDERS MALE FEMALE Age groups Rural Rural Rural 0 to 5 years 2215 1118 1097 6 to18 years 4310 2230 2080 19 to 39 years 3338 1635 1703 40 to 64 years 2131 1057 1074 65 years or more 794 380 414 Total : 12788 6420 6368 SOURCE: INE Its population is young 77.6% is under 40 years. The overall fertility rate is approximately 5.2, i.e. every woman during her fertile life has an average of 5 children. 90.77% of the population declares to be of Quechua origin and 4.13% of Aymara origin, in this area 85.07% of the population declares to speak Quechua. 2.1.3 LANGUAGE Language that the population speaks in percentage. The next information was obtained from “INE” Castellano Language: Male (56.41%), Female (43.59%) ; Quechua Language: Male (50%), Female (50%) ; Aymara Language: Male (1.06%), Female (0%).
  • 24. Jaime Navía Téllez 24 J.N.T. 2.1.4 ECONOMIC PRODUCTIVE ASPECT The agricultural activity of the municipality is recognized for its horticultural production, mainly carrot and onion, data from the Municipal Government (2011) show that the cultivation of barley represents an area of 19.77%, carrot 17.38% and that of alfalfa 16.24%. Another potential is the livestock activity, in this activity the sheep is preeminent, followed by the camelid and bovine cattle, most of the species are native. Within the municipality there are communities that have livestock vocation par excellence; livestock production is the second in importance in the region. It is recognized in the city of Oruro the production of cow's milk and cheese, in the case of bovine livestock, district 1 concentrates 47.67% of heads, district 2 21.38% and the lowest concentration is District 4 with 11.48%.. 2.2 VEHICULAR BRIDGE 2.2.1 HISTORY The first bridges made by humans were probably spans of cut wooden logs or planks and eventually stones, using a simple support and crossbeam arrangement. A common form of lashing sticks, logs, and deciduous branches together involved the use of long reeds or other harvested fibers woven together to form a huge rope capable of binding and holding together the materials used in early bridges.
  • 25. Jaime Navía Téllez 25 J.N.T. 2.2.2 BRIDGE A bridge is a structure built to span physical obstacles without closing the way underneath such as a body of water, valley, or road, for the purpose of providing passage over the obstacle. There are many different designs that each serve a particular purpose and apply to different situations. Designs of bridges vary depending on the function of the bridge, the nature of the terrain where the bridge is constructed and anchored, the material used to make it, and the funds available to build it. 2.2.3 TYPES OF BRIDGES Bridges can be categorized in several different ways. Common categories include the type of structural elements used, by what they carry, whether they are fixed or movable, and by the materials used. 2.2.3.1 BEAM BRIDGES Beam bridges are horizontal beams supported at each end by substructure units and can be either simply supported when the beams only connect across a single span, or continuous when the beams are connected across two or more spans. When there are multiple spans, the intermediate supports are known as piers. 2.2.3.2 ARCH BRIDGES Arch bridges have abutments at each end. The weight of the bridge is thrust into the abutments at either side.
  • 26. Jaime Navía Téllez 26 J.N.T. 2.2.3.3 TIED ARCH BRIDGES Tied arch bridges have an arch-shaped superstructure, but differ from conventional arch bridges. Instead of transferring the weight of the bridge and traffic loads into thrust forces into the abutments, the ends of the arches are restrained by tension in the bottom chord of the structure. 2.2.3.4 CABLE-STAYED BRIDGES Cable-stayed bridges, like suspension bridges, are held up by cables. However, in a cable-stayed bridge, less cable is required and the towers holding the cables are proportionately higher. 2.2.4 BRIDGE TYPES BY USE A bridge can be categorized by what it is designed to carry, such as trains, pedestrian or road traffic, a pipeline or waterway for water transport or barge traffic. An aqueduct is a bridge that carries water, resembling a viaduct, which is a bridge that connects points of equal height. A road-rail bridge carries both road and rail traffic. 2.2.5 BRIDGE TYPES BY MATERIAL The materials used to build the structure are also used to categorize bridges. Until the end of the 18th Century, bridges were made out of timber, stone and masonry. Modern bridges are currently built in concrete, steel, fiber reinforced polymers (FRP), stainless steel or combinations of those materials.
  • 27. Jaime Navía Téllez 27 J.N.T. Suspension Bridge Type: Materials Used: The cables are usually made of steel cables galvanised with zinc, along with most of the bridge, but some bridges are still made with steel reinforced concrete Arch Bridge Type: Materials Used: Stone, brick and other such materials that are strong in compression and somewhat so in shear. Beam Bridge Type: Materials Used: Beam bridges can use pre-stressed concrete, an inexpensive building material, which is then embedded with rebar. The resulting bridge can resist both compression and tension forces 2.2.6 AESTHETICS Most bridges are utilitarian in appearance, but in some cases, the appearance of the bridge can have great importance. Often, this is the case with a large bridge that serves as an entrance to a city, or crosses over a main harbor entrance. These are sometimes known as signature bridges. Designers of bridges in parks and along parkways often place more importance to aesthetics.
  • 28. Jaime Navía Téllez 28 J.N.T. 2.2.7 BRIDGE MAINTENANCE Bridge maintenance consisting of a combination of structural health monitoring and testing. This is regulated in country-specific engineer standards and includes e.g. an ongoing monitoring every three to six months, a simple test or inspection every two to three years and a major inspection every six to ten years. 2.2.8 BRIDGE FAILURES The failure of bridges is of special concern for structural engineers in trying to learn lessons vital to bridge design, construction and maintenance. The failure of bridges first assumed national interest during the Victorian era when many new designs were being built, often using new materials. 2.2.9 BRIDGE MONITORING An option for structural-integrity monitoring is "non-contact monitoring", which uses the Doppler effect (Doppler shift). A laser beam from a Laser Doppler Vibrometer is directed at the point of interest, and the vibration amplitude and frequency are extracted from the Doppler shift of the laser beam frequency due to the motion of the surface. The advantage of this method is that the setup time for the equipment is faster and, unlike an accelerometer, this makes measurements possible on multiple structures in
  • 29. Jaime Navía Téllez 29 J.N.T. as short a time as possible. Additionally, this method can measure specific points on a bridge that might be difficult to access. 2.3 DEFINITIONS AND COMPONENTS In this part we will describe and define each of the terms to be used in the project.
  • 30. Jaime Navía Téllez 30 J.N.T. 2.3.1 VEHICULAR BRIDGE A vehicular bridge is a construction that allows surpassing a geographic accident or any physical obstacle, also has the objective to accelerate the road mobility and to improve the vehicular circulation in very busy sectors. The design may vary depending on the function of each bridge and the nature of the terrain. A vehicular bridge consists of: The infrastructure that is formed by the extreme walls, the pier column or supports for central bridges and the foundations, that forms the base of both The superstructure is the part that directly supports the loads and the reinforcements, constituted by beams, cables and arcs that transmit the loads of the board to the piles and the stirrups. 2.3.2 ROAD INFRASTRUCTURE The road infrastructure is the whole set of elements that allows the movement of vehicles in a comfortable and safe way from one point to another. It is the set of physical components that interrelated with each other in a coherent way and under compliance with certain technical specifications of design and construction, offer comfortable and safe conditions for the circulation of users who make use.
  • 31. Jaime Navía Téllez 31 J.N.T. 2.3.3 SUPERSTRUCTURE Superstructure that part of the structure which supports traffic and includes deck, slab and girders. All the parts of the bridge which is mounted on a supporting system can be classified as a Super structure. 2.3.4 SUBSTRUCTURE Substructure that part of the structure, ie piers and abutments, which supports the superstructure and which transfers the structural load to the foundations. 2.3.5 AASHTO DESIGN STANDARD AASHTO is a standard for the calculation or road design; it is a code for the Road Design. 2.3.6 LOADS OF DESIGN They are the forces acting on the infrastructure, with which it will be designed. Note: Each of the loads are detailed in the standard AASHTO STANDARD or LRFD. 2.3.7 PERMANENT LOAD The own weight or dead load of the superstructure generally consists of the beams, the concrete slab and the diaphragms that constitute what is more properly called the permanent dead load. And complementary to
  • 32. Jaime Navía Téllez 32 J.N.T. these are: The sidewalks, the posts, the handrails, the layer of rolling, pipes, cables and others. 2.3.8 LIVE LOAD Live loads, or imposed loads, are temporary, of short duration, or a moving load. These dynamic loads may involve considerations such as impact, momentum, vibration, which correspond to trucks, buses, automobiles, construction and agricultural equipment, cyclists, pedestrians, livestock. The supporting elements and bridge pieces will be designed with the load of truck HS 20-44, taking as design load the one that produces the greatest living moments, according to the light distribution. A.A.S.H.T.O. distinguishes two types of live load: TYPE TRUCK that is taken as single load for each traffic belt and its corresponding EQUIVALENT LOAD that replaces the type truck after having exceeded a certain length. 2.3.9 FOUNDATION Foundation is the component which transfers loads from the substructure to the bearing strata. Depending on the geotechnical properties of the bearing strata, shallow or deep foundations are adopted. Usually, piles and well foundations are adopted for bridge foundations.
  • 33. Jaime Navía Téllez 33 J.N.T. 2.3.10 BEAM / GIRDER Beam or girder is that part of superstructure structure which is under bending along the span. it is the load bearing member which supports the deck. Span is the distance between points of support (eg piers, abutment). Deck is bridge floor directly carrying traffic loads. Deck transfers loads to the Girders depending on the decking material. 2.3.11 BEARING Bearing transfers loads from the girders to the pier caps. Bearing is a component which supports part of the bridge and which transmits forces from that part to another part of the structure whilst permitting angular and/or linear movement between parts. 2.3.12 PIER OR COLUMN Pier is that part of a part of the substructure which supports the superstructure at the end of the span and which transfers loads on the superstructure to the foundations. Depending up on aesthetics, site, space and economic constraints various shapes of piers are adopted to suit to the requirement. Mostly Reinforced Concrete or Prestressed concrete are adopted for the construction of piers. Piers are compression members. Depending on the loading and bearing articulations, piers may be subjected to bending as well.
  • 34. Jaime Navía Téllez 34 J.N.T. 2.3.13 TRUCK TYPE LOAD AND EQUIVALENT LOAD The design truck is a type truck that proposes the AASHTO standard, which produces a type of solicitation in the infrastructure, which must be designed to support it. The heaviest AASHTO truck is known as H20-S16 or HS20 and has a total weight of 36 US tons, equivalent to 32.67 metric tons. The weights and separations between the axles and wheels of the design truck are defined by the AASHTO standard. An increase by dynamic load shall be considered as specified in Article 3.6.2. Except as specified in Articles 3.6.1.3.1 and 3.6.1.4.1, the spacing between the two axles of 145,000 N shall be varied between 4300 and 9000 mm to produce the extreme stresses. 2.3.14 CONCRETE RESISTANCE It is its characteristic resistance with which our infrastructure will be designed, that is to say how much load to compression will support the concrete. 2.3.15 TRAFFIC DECK THICKNESS It is the last layer to be applied, where traffic must circulate, in many cases there is an intermediate layer and in less cases (highways and infrastructures for heavy traffic) the firm will consist of a base layer, an intermediate layer and the final layer of rolling.
  • 35. Jaime Navía Téllez 35 J.N.T. The traffic deck thickness refers to the thickness of the layer, which by AASHTO has a minimum thickness of e = 0.02 [m]. 2.3.16 REINFORCED CONCRETE BEAMS An element capable of withstanding the applied forces when working in conjunction with longitudinal reinforcements and steel stirrups. They are the large pieces that, together with the columns, support the structures and loads, allowing flexibility. For this reason, when preparing or arming them, they must be proven to perfectly withstand traction and compression efforts simultaneously. 2.3.17 CONCRETE SLAB Two-dimensional structural elements. Act by bending, since the loads acting on them are fundamentally perpendicular to the main plane thereof. These slabs are supported by larger beams or by beams of other independent materials and integrated into the slab. Sustained slabs on walls: they are supported by concrete walls, masonry walls or walls of other material. 2.3.18 COMPONENT A structural unit requiring separate design consideration; synonymous with member.
  • 36. Jaime Navía Téllez 36 J.N.T. 2.3.19 DEFORMATION A change in structural geometry due to force effects, including axial displacement, shear displacement, and rotations. 2.3.20 DESIGN Proportioning and detailing the components and connections of a bridge to satisfy the requirements of these Specifications. 2.3.21 ELASTIC A structural material behavior in which the ratio of stress to strain is constant, the material returns to its original unloaded state upon load removal. 2.3.22 ELEMENT A part of a component or member consisting of one material. 2.3.23 EQUILIBRIUM A state where the sum of forces and moments about any point in space is zero. 2.3.24 EQUIVALENT BEAM A single straight or curved beam resisting both flexure and torsional effects.
  • 37. Jaime Navía Téllez 37 J.N.T. 2.3.25 EQUIVALENT STRIP An artificial linear element, isolated from a deck for the purpose of analysis, in which extreme force effects calculated for a line of wheel loads, transverse or longitudinal, will approximate those actually taking place in the deck. 2.3.26 FINITE DIFFERENCE METHOD A method of analysis in which the governing differential equation is satisfied at discrete points on the structure. 2.3.27 FORCE EFFECT A deformation, stress, or stress resultant, i.e., axial force, shear force, flexural, or torsional moment, caused by applied loads, imposed deformations, or volumetric changes. 2.3.28 FOUNDATION A supporting element that derives its resistance by transferring its load to the soil or rock supporting the bridge. 2.3.29 LARGE DEFLECTION THEORY Any method of analysis in which the effects of deformation upon forces effects is taken into account.
  • 38. Jaime Navía Téllez 38 J.N.T. 2.3.30 MEMBER Same as components. 2.3.31 METHOD OF ANALYSIS A mathematical process by which structural deformations, forces, and stresses are determined. 2.3.32 MODEL A mathematical or physical idealization of a structure or component used for analysis. 2.3.33 STIFFNESS Force effect resulting from a unit deformation. 2.3.34 YIELD LINE METHOD A method of analysis in which a number of possible yield line patterns are examined in order to determine load-carrying capacity.
  • 39. Jaime Navía Téllez 39 J.N.T. CHAPTER 3 CALCULATION AND DESIGN
  • 40. Jaime Navía Téllez 40 J.N.T. Only design results are shown, the detailed design and full calculation is detailed in annexes section. 3.1 BRIDGE CONSTRUCTION Bridge construction has been improved tremendously with the advancement in science and technology. Better and lighter materials are now available that can endure greater loads. The construction is now much faster due to the introduction of a variety of heavy construction equipment. 3.2 BRIDGE CONSTRUCTION PLANNING Bridge construction tends to involve huge projects that encompass the utilization of skills related to several engineering disciplines including geology, civil, electrical, mechanical, and computer sciences. Therefore, integrating the efforts of all involved must be meticulous. The initial plans are prepared regarding the project, including the characteristics of the desired bridge, the site details, and the requirement of resources. The bridge design will be determined by the type of bridge being constructed. The main types of the bridges are beam, arch, truss, cantilever, and suspension. The beam bridge is one of the popular types.
  • 41. Jaime Navía Téllez 41 J.N.T. 3.3 BRIDGE FOUNDATION Construction of the foundations is the first step toward building a bridge. This process involves detailed geotechnical investigations of the bridge site. The type of bridge foundation has to be selected, such as the well foundation, pile foundation, and the opened foundation. Each foundation is suitable for specific soil strata, and the desired bridge characteristics. The soil characteristics will determine the load bearing capacity, and other important parameters. The superstructure is basically designed in accordance with the technical requirements, aesthetic reasons, and the construction methodology. Excavation required for the foundations may need to be executed to sizeable depths, involving hard ground, before the solid rocks are reached. Engineering feats will be involved to avoid water, and prevent collapse of the diggings. Tunnels specifically may be subjected to sudden failures. 3.4 BRIDGE CONSTRUCTION EQUIPMENT Heavy equipment will be used extensively during the bridge construction including bulldozers, excavators, asphalt mixers, formworks, and fabrication equipment. The construction and other equipment needs to be identified thoroughly, according to their capability and other desired functions. The foundation and the superstructure design will need to be considered. This expensive equipment should not remain idle, and must be used cautiously to obtain optimum advantage.
  • 42. Jaime Navía Téllez 42 J.N.T. 3.5 BRIDGE LOADS Several loads act on a bridge, and the bridge is designed accordingly. Dynamic loads are particularly of prime significance. A bridge is designed to endure the normal vehicle loads, and other forces created due to winds and earthquakes. Several bridges have collapsed due to high speed winds. Even if the wind speeds are reasonably low, the dynamic forces can become excessive for the bridge to resist. Initially, the bridge may vibrate violently, causing the bridge structure to fail at a few weak elements, or even damage the major components. Investigations conducted after bridge failures have revealed that the real forces on bridges that collapsed were significantly less compared to the loads for which the bridge was designed. However, the oscillations created due to the winds were enough to cause the failure. Therefore, special reinforcement may be necessary for prevention against high speed winds and earthquakes. Thus, lighter materials are used that are arranged in suitable geometric structures, and it is ensured that the configuration is aerodynamically stable. 3.6 TESTING OF BRIDGES Since bridge construction is an expensive project, it is essential that all necessary tests may be conducted prior to the actual construction. These tests and investigations can reveal the bridge behavior under different dynamic loads. Computer aided design and testing are powerful tools that
  • 43. Jaime Navía Téllez 43 J.N.T. must be used to assist in the bridge design. Bridge design has benefited considerably due to the growth of computer programs. Such computer programs reveal immense information concerning the effect of different forces being applied on a bridge. The four main factors are used in describing a bridge. By combining these terms one may give a general description of most bridge types. Span (simple, continuous, cantilever). Material (stone, concrete, metal, etc.). Placement of the travel surface in relation to the structure (deck, pony, through). Form (beam, arch, truss, etc.). In this project we will use simple spans kind of bridge. 3.7 CONSIDERATIONS IN BRIDGE DESIGN Engineers have been designing bridges for thousands of years. A lot of thought goes into designing the perfect bridge, to ensure that the structure is safe, reliable and able to withstand the test of time. Of course, engineers today have access to more precise tools than the bridge designers of yesterday, allowing them, among other things, to prototype their work far earlier in the process. Though, in historical terms, CAD training is a
  • 44. Jaime Navía Téllez 44 J.N.T. relatively new discipline for architectural or engineering technicians, bridge design isn’t. If you’re interested in using CAD software to design a bridge, the science of bridge design contains a wealth of experience and information that can be very useful for a Computer Aided Drafter to take into consideration, particularly at the level of specification, standardization, and reliability. 3.8 SUPERSTRUCTURE AND INFRASTRUCTURE To understand bridge design, you’ll have to learn the difference between the bridge’s superstructure and its substructure. By the bridge’s superstructure, we mean anything above the bearings, including the hard surface drivers used to travel from one side to the other. By the substructure, we mean the bridge’s foundation, including the columns supporting it. The superstructure and the substructure work together, but have different goals. Choosing the shape of the structure of your bridge, for example, will affect the substructure. A bridge can be shaped like an arc, suspended by cables, built primarily using powerful beams and more. These design considerations, of course, are more complex than simply asking “What shape do you prefer?”, you should take the time to factor in the environment around the bridge and various economic considerations, such as costs of materials, among others.
  • 45. Jaime Navía Téllez 45 J.N.T. 3.9 TENSION AND COMPRESSION Regardless of the shape of your bridge, its key structural components will be beams, arches, trusses and suspensions. How you use these elements will determine the quality of your bridge. Two forces you should make sure you understand are tension and compression. To understand tension, imagine a rope being pulled on from both sides during a game of tug-of- war. This is tension, and it’s a force that will act on your bridge to add stress. To understand compression, just imagine what happens to a spring when you apply pressure on it. That’s right – it collapses into itself, which shortens its length. Compressional stress will also affect your bridge, and it will act in direct opposition to tensional stress. The bridge’s design, therefore, must be able to handle these forces without buckling or snapping. 3.10 RESONANCE Resonance is another force that can act on your bridge. Imagine a snowball rolling down a hill and increasing in size and speed. This is resonance. It starts with small vibrations, such as when wind attacks a bridge, and those vibrations can continue increasing over time until they take down the entire structure! There are several ways to deal with resonance, but one of the most popular methods is to incorporate
  • 46. Jaime Navía Téllez 46 J.N.T. dampeners into the bridge design, which can interrupt the resonant waves and prevent them from growing. 3.11 DESIGN METHODS Two basic methods are used – Service Load Design and Strength Design. The Service Load Design (Allowable Stress Design) shall be used for the design of all steel members and reinforced concrete members except columns, sound barrier walls and bridge railings. Columns and sound barrier walls shall be designed by the Strength Design Method (Load Factor Design). Bridge railing design for new bridges shall be based on the AASHTO LRFD Bridge Design Specifications. In Service Load Design, loads of the magnitude anticipated during the life of the structure are distributing empirically and each member analyzed assuming completely elastic performance. Calculated stresses are compared to specified allowable stresses which have been scaled down from the tested strength of the materials by a factor judged to provide a suitable margin of safety. In Strength Design, the same service loads are distributed empirically and the external forces on each member are determined by elastic analysis. These member forces are increased by factors judged to provide a suitable margin of safety against overloading. These factored forces are compared to the ultimate strength of the member scaled down by a factor reflecting
  • 47. Jaime Navía Téllez 47 J.N.T. the possible consequences from construction deficiencies. Serviceability aspects, such as deflection, fatigue and crack control, must be determined by Service Load Analysis. The Strength Design Method produces a more uniform factor of safety against overload between structures of different types and span lengths. Strength Design also tends to produce more flexible structures. 3.12 DESIGN PHILOSOPHY New structure types were developed to meet specific needs. Concrete slab, T-Girder and Box Beam bridges were developed in the late 1940’s because many short span stream crossings were being constructed uneconomically with steel beams and trusses. These bridges are still used very economically in considerable numbers today. Precast pretensioned beams were developed in the 1950’s for medium span stream crossings and grade separations because steel beams became expensive and sometimes slow on delivery. Fewer plans are assembled from standard prestressed girder drawings today because bridge geometry has become more complicated and variable so that most details must be specially prepared. The beams themselves are still the standard shapes developed in the beginning and the accessories required to complete the span are covered with standard details. Cast-In-Place Post-Tensioned Box Girder
  • 48. Jaime Navía Téllez 48 J.N.T. bridges were introduced the 1970’s and became one of the most common types of bridges used. Geometry is considered an important part of bridge design. Framing dimensions and elevations must be accurate in order to avoid expensive field correction. Design engineers are primarily responsible for geometry accuracy. Constructability is highly desirable. There have been designs which looked good on paper but were virtually impossible to construct. Designers need to consider how to build the component being designed. Construction experience remains a valuable asset. Details may be the most critical aspect of the design process. Failure to provide for proper stress flow at discontinuities has often caused local stress and sometimes mortal injury to a system. Engineers and technicians should recognize and carefully evaluate untested details. The bottom line on bridge design is maintenance. It is usually much more expensive to repair a bridge than it was to build it. Unfortunately, maintenance problems tend to occur many years after the structure is built. During that time there may be many more bridges designed with the same problem. Experience is a good teacher, but the lesson is sometimes slow to be learned. It takes a good designer to anticipate maintenance problems and spend just enough of the taxpayers’ money to prevent or delay them.
  • 49. Jaime Navía Téllez 49 J.N.T. Design calculations are the documentation for structural adequacy and accuracy of pay quantities for each bridge. These will be kept on file for a reasonable period after construction of the bridge. The condition of the calculations reflects the attitude of the designer and checker. The design calculations should consist of a concise, but complete, clear, and easily followed record of all essential features of the final design of each structure. It is often necessary to refer to these calculations because of changes or questions which arise during the construction period. If properly prepared and assembled, these calculations are of great value as a guide and time saver for preparing a similar design of another structure. 3.13 STRUCTURAL ANALYSIS In general, bridge structures are to be analyzed elastically which are based on documented material characteristics and satisfy equilibrium and compatibility. However, exceptions may apply to some continuous beam superstructures by using inelastic analysis or redistribution of force effects. This section identifies and promotes the application methods of structural analysis that are suitable for bridges. The selected method of analysis may vary from the approximate to the very sophisticated, depending on the size, complexity, and importance of the structure. The primary objective in the use of more sophisticated methods of analysis is to obtain
  • 50. Jaime Navía Téllez 50 J.N.T. a better understanding of structural behavior. Such improved understanding may often, but not always, lead to the potential for saving material. These methods of analysis, which are suitable for the determination of deformations and force effects in bridge structures, have been successfully demonstrated, and most have been used for years. 3.14 ACCEPTABLE METHODS OF STRUCTURAL ANALYSIS Any method of analysis that satisfies the requirements of equilibrium and compatibility and utilizes stress-strain relationships for the proposed materials may be used, including but not limited to: Classical force and displacement methods (Moment Distribution, and Slope Deflection Methods, etc.), Finite difference method, Finite element method, Folded plate method, Finite strip method, Grillage analogy method, Serious or other harmonic methods, and Yield line method. 3.15 MATHEMATICAL MODELING Mathematical models should include loads, geometry, and material behavior of the structure, and, where appropriate, response characteristics of the foundation. In most cases, the mathematical model of the structure should be analyzed as fully elastic, linear behavior except in some cases, the structure may be modeled with inelastic or nonlinear behavior.
  • 51. Jaime Navía Téllez 51 J.N.T. 3.16 ELASTIC BEHAVIOR Elastic material properties and characteristics of concrete, steel, aluminum and wood shall be in accordance with the sections given by AASHTO Specifications. Changes in these values due to maturity of concrete and environmental effects should be included in the model, where appropriate. 3.17 SMALL DEFLECTION THEORY If the deformation of the structure does not result in a significant change in force effects due to an increase in the eccentricity of compressive or tensile forces, such secondary effects may be ignored. Small deflection theory is usually adequate for the analysis of beam-type bridges. Columns, suspension bridges, and very flexible cable-stayed bridges and some arches other than tie arches and frames in which the flexural moments are increased or decreased by deflection tend to be sensitive to deflection considerations. In many cases, the degree of sensitivity can be assessed and evaluated by a single-step approximate method, such as the Moment Magnification Factor Method. Due to advances in material technology the bridge components become more flexible and the boundary between small- and large-deflection theory becomes less distinct.
  • 52. Jaime Navía Téllez 52 J.N.T. Only design results are shown, the detailed design and full calculation is detailed in annexes section. 3.18 ANALYSIS AND STRUCTURAL DESIGN OF THE BRIDGE 3.18.1 CONSIDERATIONS OF SUPERSTRUCTURE AND INFRASTRUCTURE DESIGN Design standards, we will use: AASHTO STANDARD ACI CODE - 318 – 05 TRUCK TYPE LOAD AND EQUIVALENT LOAD DESIGN TRUCK The weights and separations between the axles and the wheels of the design truck shall be as specified in Figure 1. The spacing between the two axles of 145,000 N shall be varied between 4300 and 9000 millimeters to produce the extreme stresses.
  • 53. Jaime Navía Téllez 53 J.N.T. Calculation length This length refers to the calculation span of the bridge in the longitudinal direction. It is a bridge of 3 equal spans, with 3 beams of 10 meters simply supported, adding a total span of 30 m. Roadway width The free width of road will be 7.3 meters. Number of traffic lanes This bridge will have 2 traffic lanes Width of sidewalk The width of sidewalk will be 0.5 meters and the width of the edge beam will be 0.2 meters, then: The total width will be 0.7 meters Truck type
  • 54. Jaime Navía Téllez 54 J.N.T. The type of truck for the design will be HS 20-44; standard HS truck according to AASHTO Concrete resistance The Concrete resistance "f 'c" will be: f' c = 210 [kg / cm2] Steel creep resistance The creep strength of the "Fy" steel will be: Fy = 4200 [kg / cm2] Specific weight of the concrete The specific weight of the concrete "γHᵒ" will be: γH = 2400 [kg / m 3] Traffic deck thickness The thickness of the traffic deck "e" will be: e = 0.02 [m] 3.19 DESIGN OF SUPERSTRUCTURE 3.19.1 HANDRAIL DESIGN The design of Handrail (is a Type P3) was made according to the AASHTO standard article 1.2.11 In this case we will use a standard handrail used in Oruro, is not necessary the calculation and design.
  • 55. Jaime Navía Téllez 55 J.N.T. THIS IS THE FINAL SCHEME OF THE HANDRAIL DESIGN 3.19.2 SLAB DESIGN INTERIOR SLAB DESIGN CALCULATION OF AMOUNT OF STEEL: We will design with a 12 millimeters diameter bar; ø= 12 [mm] Number of bars =9 Separation between bars = 11, 2 centimeters Distribution steel: Main steel perpendicular to traffic We will design with a 12 millimeters diameter bar; ø= 12 [mm] Number of bars=7 Separation between bars = 15 centimeters EXTERIOR SLAB DESIGN CALCULATION OF AMOUNT OF STEEL: We will design with a 16 millimeters diameter bar; ø= 16 [mm]
  • 56. Jaime Navía Téllez 56 J.N.T. Number of bars=10 Separation between bars = 10 centimeters Steel of distribution: Main steel perpendicular to traffic We will design with a 12 millimeters diameter bar; ø= 12 [mm] Number of bars=6 Separation between bars = 17 centimeters
  • 57. Jaime Navía Téllez 57 J.N.T. THIS IS THE FINAL SCHEME OF THE SLAB DESIGN INTERIOR SLAB EXTERIOR SLAB
  • 58. Jaime Navía Téllez 58 J.N.T. 3.19.3 CALCULATION AND DESIGN OF OPTIMIZED BEAMS FLEXION DESIGN CALCULATION OF AMOUNT OF STEEL: We will design with a 25 millimeters diameter bar; ø= 25 [mm] Number of bars=12 SHEAR DESIGN CALCULATION OF AMOUNT OF STEEL: We will design with a 10 millimeters diameter bar; ø= 10 [mm] Separation between bars = 7,5 centimeters THIS IS THE FINAL SCHEME OF THE BEAM DESIGN
  • 59. Jaime Navía Téllez 59 J.N.T. 3.20 INFRASTRUCTURE DESIGN 3.20.1 DESIGN OF WALLS, COLUMNS AND FOUNDATIONS THIS IS THE FINAL SCHEME OF THE DESIGN OF COLUMNS AND FOUNDATIONS PIER COLUMN AND FOUNDATION 1: PIER COLUMN AND FOUNDATION 2:
  • 60. Jaime Navía Téllez 60 J.N.T. 3.20.2 DESIGN OF WALLS Wall 1 and wall 2 were designed with the same dimensions, due to the characteristics of the terrain. THIS IS THE FINAL SCHEME OF THE DESIGN OF WALLS Note: Only the final schemes were presented in this section, the calculation and design is detailed in appendices and the results are in the drawings section.
  • 61. Jaime Navía Téllez 61 J.N.T. 3.21 DRAWINGS
  • 62. Jaime Navía Téllez 62 J.N.T. HANDRAIL DRAWINGS
  • 63. Jaime Navía Téllez 63 J.N.T. PIER COLUMNS AND FOUNDATIONS DRAWINGS
  • 65. Jaime Navía Téllez 65 J.N.T. SLAB, BEAMS AND WALLS DRAWINGS
  • 66. Jaime Navía Téllez 66 J.N.T. TOPOGRAPHIC DRAWINGS
  • 67. Jaime Navía Téllez 67 J.N.T. REINFORCED CONCRETE HANDRAIL SHEET Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg] Pasamanos superior 10 200 40 120 288 178 Pasamanos inferior 14 200 40 120 288 348 Pasamanos superior 6 40 20 300 180 40 Pasamanos inferior 6 40 20 300 180 40 Estribos de corte 6 60 20 128 102,4 23 Cuerpo del poste 12 102 90 7 12,5 40 64 160,96 143 Acera y bordillo 10 65 40 15 40 40 64 128 79 Longitudinal acera 10 200 40 120 288 178 Longitudinal bordillo 12 200 40 120 288 256
  • 68. Jaime Navía Téllez 68 J.N.T. REINFORCED CONCRETE SLAB AND BEAMS SHEET Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg] VIGAS LONGITUDINAL 25 1000 40 108 1123,2 4328 VIGAS TRANSVERSAL 10 25 65 20 1200 1320 814 LOSA INTERIOR LONG. 12 1000 40 138 1435,2 1274 LOSA INTERIOR TRANSV. 12 550 50 200 1200 1065 LOSA INT. LONG. SUP. 12 1000 40 72 748,8 665 LOSA INT. TRANSV. SUP. 12 550 50 200 1200 1065 LOSA EXTERIOR LONG. 16 1000 40 54 561,6 886 LOSA EXTERIOR TRANSV. 16 125 20 40 353 653,05 1031
  • 69. Jaime Navía Téllez 69 J.N.T. REINFORCED CONCRETE PIER COLUMNS SHEET Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg] Columnas pila 1 25 370 40 88 360,8 1390 Estribos pila 1 10 45 714 20 11 85,69 53 Columnas pila 2 25 475 40 88 453,2 1746 Estribos pila 2 10 45 714 20 14 109,06 67
  • 70. Jaime Navía Téllez 70 J.N.T. REINFORCED CONCRETE WALLS SHEET Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg] PANTALLA ESTRIBO 10 300 40 90 306 189 CUERPO ESTRIBO 10 310 45 40 90 355,5 219 PARAPETO ESTRIBO 10 90 14 110 40 40 90 264,6 163 TRANSV. ESTRIBO 20 710 40 40 300 740
  • 71. Jaime Navía Téllez 71 J.N.T. REINFORCED CONCRETE FOUNDATIONS SHEET Posicion ø [mm] Esquema a [cm] b [cm] c [cm] d [cm] e [cm] f [cm] No de barras L total [m] Peso [kg] ZAPATA PILA 1 TRANSVERSAL 25 340 40 26 98,8 381 ZAPATA PILA 1 LONGITUDINAL 25 816 40 25 214 825 ZAPATA PILA 2 TRANSVERSAL 25 354 40 27 106,38 410 ZAPATA PILA 2 LONGITUDINAL 25 816 40 27 231,12 891 ZAPATA DEL ESTRIBO TRANSV. 10 260 40 90 270 166 ZAPATA DEL ESTRIBO LONG. 20 710 14 99,4 245 ZAPATA DEL ESTRIBO TRANSV. INF. 20 265 50 21 66,15 163 ZAPATA DEL ESTRIBO LONG. 20 710 40 14 105 259
  • 72. Jaime Navía Téllez 72 J.N.T. 3.22 ECONOMIC AND FINANCIAL EVALUATION Crops of the project Area Crops AREA [Ha] % Bean 20 32.26 Potato 12 19.35 Onion 10 16.13 Carrot 10 16.13 Alfalfa 7 11.29 Barley forage 3 4.84 Total 62 100 Volume of production [Tn] Crops Área [Ha] Performance [t/Ha] Output Bean 20 5 100 Potato 12 9.2 110.4 Onion 10 16.1 161 Carrot 10 14.49 144.9 Alfalfa 7 4 28 Barley forage 3 3 9 Total 62 553.3 Net value of production in the current situation Crops Net value of production [Sus] Net worth [SuS] Without project hectare Cost/Hectare Total cost Gross income / Hectare Total gross income Bean 20 246.52 4930.4 1650 33000 28069.6 Potato 12 849.5 10194 3542 42504 32310 Onion 10 868.26 8682.6 2254 22540 13857.4 Carrot 10 849.55 8495.5 1738.8 17388 8892.5 Alfalfa 7 645.94 4521.58 1280 8960 4438.42 Barley forage 3 286.68 860.04 600 1800 939.96 Total 62 37684.12 126192 88507.88
  • 73. Jaime Navía Téllez 73 J.N.T. Net value of production with project Crops Net value of production [Sus] Net worth [SuS] With project hectare Cost/Hectare Total cost Gross income / Hectare Total gross income Bean 20 357.62 7152.4 1980 39600 32447.6 Potato 12 1112.6 13351.2 5775 69300 55948.8 Onion 10 875.16 8751.6 2800 28000 19248.4 Carrot 10 849.55 8495.5 2160 21600 13104.5 Alfalfa 7 685.89 4801.2 1856 12992 8190.8 Barley forage 3 317 951 778 2334 1383 Total 62 43502.9 173826 130323.1 Socioeconomic evaluation In any project, it is determined if it is or not feasible the construction, through socioeconomic indicators, having as an evaluation tool the parameterized schedules, which determines through its results the feasibility of the project being the profitability indicators greater than those established by the vice-minister of public investment and external financing. National Parameters Ratio price account efficiency of the currency 1.24% Ratio price account efficiency of non-qualified rural labor 0.47% Ratio price account efficiency of urban unskilled labor 0.23% Ratio price account efficiency of semi-skilled urban labor 0.43% Ratio price account efficiency of the total skilled labor 0.44% Ratio price account efficiency of skilled urban labor 1% Price account efficiency of foreign labor 0.99%
  • 74. Jaime Navía Téllez 74 J.N.T. Social discount rate 12.67% We also take into account the costs of operation and maintenance. Detail Costs [SuS] Tradable goods 1580 Local Materials 200 Skilled labor 2000 Rural unskilled labor 480 Total 4260 Financial indicators Indicator Value VACP 888894.46 VANP 1941280.36 CAEP 125095.01 TIRS / 12.67% 40.96 RBCP 3.18 Socioeconomic Indicators Indicator Value VACS 825610.61 VANS 2030116.22 CAES 115204.84 TIRS / 12.67% 43.78 RBC social 3.46 As we can see in the tables, the profitability indicators comply with what is determined by the VIPFE and the preinvestment regulation, in the sense that the NPV (VAN) is greater than 0 and the IRR (TIR) is higher than the discount rate. So it is concluded that the project is totally profitable.
  • 75. Jaime Navía Téllez 75 J.N.T. 3.23. ENVIRONMENTAL FILE 1. GENERAL INFORMATION Date 10/17/13 Location: Municipality of Soracachi Developer: Independent Responsible for completing the form: Name and surname: Jaime Navía Téllez Profession: Civil Engineer Department: Oruro 2. IDENTIFICATION AND LOCATION OF THE PROJECT Name of the project: DESIGN OF THE SUPERESTRUCTURE VEHICULAR BRIDGE “OBRAJES” Physical location of the project, city and / or locality: Canton: Iruma Town or City: Soracachi Province: Cercado Department: Oruro Latitude: 17 ° - 49 '-76 "ᵒS Length: 66 ° - 59' - 16.36" ᵒO Adjoining Buildings and Developing Activities: North: Population of Cotochullpa South: Population of Amachuma East: Iruma population West: Population of Paria Use of soil. Current Usage: Agricultural, Livestock Potential use: Agricultural 3. DESCRIPTION OF THE SITE OF THE PROJECT OCCUPIED SURFACE: 1800 [m2] Occupied by project: 220 [m2] Description of the land Topography and slopes: The municipality of Soracachi sits physiographically in the Bolivian highlands, the influence of the Royal or Eastern mountain range forms a complex of mountains, without the presence of eternal snow. These form high terraces, heavily undulating plateaus that, when descending, form small basins with temperate Sami microclimates Water quality: Class C1 S1 Predominant vegetation: COMMON NAME TECHNICAL NAME Paja suave Esthipa ichu Paja brava Festuca orthophyla Suphu thola Parastrephia lepidophyla Ñacka thola Parastrephia cuadrangulare Chiji negro Mhulenbergia fastigiata
  • 76. Jaime Navía Téllez 76 J.N.T. Tara tara Faviana densa Natural Drainage Network: Sewer Human Environment: Rural Population 4. DESCRIPTION OF THE PROJECT Sector activity: Roads and communication Specific Activity: Transportation Nature of the project: New (x) Ampliatory () Others () Project stage: Exploitation (x) Execution () Operation () Maintenance () Future Induced () Abandonment () Scope of the project: Urban () Rural (x) Overall objective of the project: The objective of this project is to contribute to improving the quality of life through a safe and efficient road infrastructure, with the Design of the superstructure of a vehicular bridge in the community of Obrajes. Specific objectives of the project: - Calculation and design of the elements that constitute the superstructure of the vehicular bridge. - Draw up detailed drawings with their dimensions and steel cutting. - Elaboration of costs and budgets taking into account all the necessary and constructive aspects of the vehicular bridge for its respective feasibility analysis. - Elaboration of the environmental impact study with the corresponding mitigation measures. Relationship with other projects: It is part of: A plan () Program () Isolated project (x) Estimated project life: 25 years 5. TOTAL INVESTMENT Project investment [bs.] Total cost 851258.25
  • 77. Jaime Navía Téllez 77 J.N.T. 6. ACTIVITIES 7. HUMAN RESOURCES (Labor) Qualified Permanent Non permanent 10 7 Non Qualified Permanent Non permanent 4 7 8. NATURAL RESOURCES OF THE AREA, WHICH WILL BE ACHIEVED RESOURCES QUANTITY [m3] Material for embankment 47 ITEM DESCRIPTION UNITS WIDTH [m] HIGH [m] AREA [m2] LENGTH [m] TIMES PARTIAL TOTAL 1 PRELIMINARY WORKS M2 280 TOPOGRAPHIC REPLACEMENT M2 8 35 1 280 INFRASTRUCTURE 2 EXCAVATION M3 266,8 WALL 1 M3 3,5 2 8 1 56 WALL 2 M3 3,5 2 8 1 56 PIER COLUMN 1 M3 4,2 2 9 1 75,6 PIER COLUMN 2 M3 4,4 2 9 1 79,2 3 FILLED AND COMPACTED M3 126,84 WALL 1 M3 2,1 1,3 7,3 1 19,929 WALL 2 M3 2,1 1,3 7,3 1 19,929 PIER COLUMN 1 M3 2,9 1,45 8,3 1 34,9015 PIER COLUMN 2 M3 3,1 1,45 8,3 1 37,3085 ADDITIONAL WALL 1 M3 0,7 0,7 8 1 3,92 WALL 2 M3 0,7 0,7 8 1 3,92 PIER COLUMN 1 M3 0,7 0,55 9 1 3,465 PIER COLUMN 2 M3 0,7 0,55 9 1 3,465 4 REINFORCED CONCRETE FUNDATIONS M3 61,48 WALL 1 M3 2,8 0,7 7,3 1 14,308 WALL 2 M3 2,8 0,7 7,3 1 14,308 PIER COLUMN 1 M3 3,5 0,55 8,3 1 15,9775 PIER COLUMN 2 M3 3,7 0,55 8,3 1 16,8905 5 REINFORCED CONCRETE PIERS M3 35,04 PIER COLUMN 1 M3 0,6 3,5 7,3 1 15,33 PIER COLUMN 2 M3 0,6 4,5 7,3 1 19,71 6 WALLS M3 26,28 WALL 1 M3 1,8 7,3 1 13,14 WALL 2 M3 1,8 7,3 1 13,14 SUPERSTRUCTURE 7 REINFORCED CONCRETE BEAMS M3 22,94 PRINCIPAL BEAMS M3 0,3 0,55 10 9 14,85 TRANSVERSE BEAMS M3 2,4 0,4 0,2 14 2,69 EDGE BEAM M3 0,2 0,45 10 6 5,4 8 REINFORCED CONCRETE SLAB M3 43,92 PRINCIPAL SLAB M3 7,3 0,18 10 3 39,42 SIDEWALK M3 0,5 0,15 10 6 4,5 9 REINFORCED CONCRETE PROTECTION M3 3,11 POST M3 0,134 0,2 32 0,86 HANDRAIL M3 0,15 0,125 10 12 2,25 10 TRAFFIC DECK M3 4,38 TRAFFIC DECK M3 7,3 0,02 10 3 4,38 11 NEOPRENE SUPPORTS PZA 18 NEOPRENE SUPPORTS PZA 0,2 0,1 0,5 18 12 SIGNALING PZA 4 VERTICAL PZA PREVENTIVE SP 34 PZA 1 HORIZONTAL PZA 3 13 GENERAL CLEANING M2 8 35 280
  • 78. Jaime Navía Téllez 78 J.N.T. 9. NOISE PRODUCTION SOURCE Construction Equipment MINIMUM LEVEL: 60 [db] MAXIMUM LEVEL: 80 [db] 10. INDICATE HOW AND WHERE THE INPUTS ARE STORED The inputs used during project execution such as cement, fuels, timber and others will be stored under safe and controlled environments. The water will be stored directly in tank tanks. 11. INDICATE PROCESSES OF TRANSPORTATION AND HANDLING OF INPUTS The sand, stone, gravel will be transported from the loan banks to the point of execution in the corresponding machinery. The materials considered as natural resources will be used from the same place. The transport of lubricants and fuels will be carried out by tanker respectively. 12. POSSIBLE ACCIDENTS AND / OR CONTINGENCIES Exploration: During the transport of technical personnel who will carry out this stage of the project, the company is recommended to have industrial safety measures. During the installation of the camp, various alterations to the environment may occur, related to the removal of the vegetation cover of the area, temporary changes in land use, gas emissions, suspended particles, use of lubricants and others. Execution: In the preventive matter of accidents or human contingencies that can be presented, there is a risk of accidents that may be suffered by workers with working tools, whether they are minor tools or machinery, these accidents can
  • 79. Jaime Navía Téllez 79 J.N.T. suffer from self-neglect or poor maintenance of equipment of work, that is why the construction company must equip the workers with safety equipment and also must perform a maintenance in the construction equipment. 13. ENVIRONMENTAL CONSIDERATIONS (-) Air: particles suspended by earthworks: Provide personnel with protective nasal spray and water the work area to avoid particles. (-) Air: Use of heavy machinery generates gases (Co and Co2) generating temporary direct impacts, catalysts can be used as a mitigation measure (-) Soil: Material lending sites are affected by erosion and compaction directly and permanently, replenishing the vegetation layer as a mitigation measure. (-) Soil: Machinery originates erosion in the new provisional roads, for the transfer of loan material, temporary direct impacts are generated, to replenish the affected earth layer by scarifying and revegetation as a mitigation measure. (-) Noise: The generation of noise caused by the use of machinery in operation, should be provided to the personnel hearing protection equipment as a mitigation measure. (-) Water: the watercourses will be affected by particles suspended directly and temporarily. Control the slope compaction of the road as a mitigation measure. (-) Ecology: The loan of material generates changes in the landscape of the place in a direct and temporary; reestablish the affected area with plantation and local species as a mitigation measure. (+) Socioeconomic: Changes in living standards directly and permanently. (+) Socioeconomic: Generation of employment directly and permanently.
  • 80. Jaime Navía Téllez 80 J.N.T. (+) Socioeconomic: Greater economic movement, for the benefit of the inhabitants. (+) Socioeconomic: Better lifestyle of the beneficiary population. 14. ENVIRONMENTAL IMPACT IDENTIFICATION MATRIX WEIGHTING SCALE: POSITIVES: 1 = LOW 2 = MODERATE 3 = HIGH NEGATIVES: -1 = LOW -2 = MODERATE -3 = HIGH Classification of projects for environmental assessment Interpreting the results obtained in the matrix of environmental impacts, we observe that it falls into category ii, which means that it requires specific analytical environmental impact assessment.
  • 81. Jaime Navía Téllez 81 J.N.T. CHAPTER 4 CONLCUSIONS AND RECOMMENDATIONS
  • 82. Jaime Navía Téllez 82 J.N.T. 4.1 CONCLUSIONS With the project “Obrajes vehicular bridge” it was possible to grant to the community of Obrajes a project of vehicular bridge, if it is constructed could solve the problems of null transitability in rainy seasons. Were designed and calculated all the elements belonging to the superstructure of the vehicular bridge. The interior slab and exterior slab of the vehicular bridge were designed and calculated. Each of the beams of the vehicular bridge were designed and calculated. We calculated the steel reinforcement of the slab and beams of the vehicular bridge. The scale drawings of each of the elements belonging to the superstructure as well as each of the transverse and longitudinal sections of the vehicular bridge were designed. We elaborated the costs and budgets taking into account all the necessary and constructive aspects of the vehicular bridge for its respective feasibility analysis. We elaborated the environmental impact study with the corresponding mitigation measures. If the project is constructed, it could grant to the community of Obrajes an infrastructure suitable to achieve a free and fluid transitability at all seasons of the year.
  • 83. Jaime Navía Téllez 83 J.N.T. If the project is constructed it could solve the problems of transitability in rainy seasons and improve the lifestyle of the beneficiary populations. if the project is constructed it could be solved that the villagers will no longer have the need to look for alternate routes when there is a flood of the river. If the project is built it could improve the economic aspect of the villagers, because due to this vehicular bridge the villagers will no longer have difficulties in the transfer of their agricultural and livestock products. 4.2 RECOMMENDATIONS If the project will be constructed it is recommended to follow the design drawings and each of the specifications placed in it, so as not to have inconveniences of cracking or collapse of the structure. The biggest danger in the construction of the vehicular bridge is the launching of the beams, because when they are launched with a crane, they suffer the risk of being destroyed or deformed in the lifting process, which would lead to rework, producing an extra cost , so it is recommended firstly the formwork of the beams can be disassembled after 3 days and need a minimum of 14 days before they can be lifted, although the concrete maintains its shape after only 3 days, needs at least 14 days to achieve a strong resistance to be able.
  • 84. Jaime Navía Téllez 84 J.N.T. It is necessary to hire a crane strong enough to move the beams, the beams have a certain weight, but since they tend to deform it would be good to increase the already calculated weight by 30% as a safety factor, therefore get a crane that can move the weight of the increased beam by 30%. The beams must be lifting with the hooks at each end, lifting them in this way means that the forces in the beams will be the same when placed on piles and stirrups. The beams can be deformed during the casting process, if this happens the support of the formwork can be increased with more stakes joined with wire. It is important to keep the edges of the pressed wood lined up, if they separate or move, they can create raw edges, and those points are high pressure that can cause a collapse. Recommendations for repairing a beam after casting Large holes in a beam should be repaired with concrete of 1 cement, 2 of sand, 3 gravel, and Sika. Surface repairs, such as exposed gravel, can be used with Sika mortars. If there is a hole in which the reinforcing steel can be seen, it is necessary to make a new beam.
  • 85. Jaime Navía Téllez 85 J.N.T. CHAPTER 5 APPENDICES