SlideShare a Scribd company logo
1 of 2
Download to read offline
Rosmolenweg 20
P.O. Box 209, 3350 AE Papendrecht
The Netherlands
Tel: +31 (0)78 - 69 69 099
Fax: +31 (0)78 - 69 69 555
E-mail: general@hydronamic.nl
Internet: www.hydronamic.nl
Client: Öresundkonsortiet
Location: Øresund, Denmark / Sweden
Period: 1995 - 1998
Port and Waterway Engineering, Project Development
The Øresund Tunnel
Location map.
Artist’s impression of the Øresund Link.
Introduction
The Øresund Tunnel forms part of the
Øresund Link that will connect the
cities of Copenhagen in Denmark and
Malmö in Sweden across the Øresund.
The Link, which will comprise a
motorway and a railway, consists of
three different construction elements:
• A man-made peninsula adjacent to
Copenhagen airport (Kastrup) and a 4
km long man-made island (called
Peberholm) located roughly in the
middle of the Øresund;
• The world’s longest immersed tunnel
of 3,520 metres, positioned between
the peninsula and Peberholm;
• A bridge of 7.8 km length between
the artificial island and the Swedish
coast near Malmö.
The decision to construct the Link was
taken by the Danish and Swedish
governments after lengthy discussions,
mainly about the environmental aspects
of the works.
The Link is being built under design &
construct contracts, and will be
operated by Øresundkonsortiet who will
charge a toll. The opening of the Link is
scheduled for 2000.
The tunnel project
In mid-1995 Øresundkonsortiet signed
a contract with the Øresund Tunnel
Contractors for the design and
construction of the tunnel.
The partners in Øresund Tunnel
Contractors (ØTC) Joint Venture are:
• NCC AB from Sweden,
• E. Phil & Søn A.S. from Denmark,
• Dumez-GTM S.A. from France,
• John Laing Construction Ltd. from
Great Britain
• Boskalis Westminster Dredging BV
from Holland.
Special aspects of tunnel construction
In response to the limited available
construction time ØTC developed an
innovative way of construction which,
in particular, was designed to minimise
risks resulting from the Scandinavian
weather conditions.
0 5 km
Denmark
Sweden
Multi Purpose Pontoon MPP.
Tunnel element before immersion.
Typical design features:
• Simultaneous construction of two
tunnel segments on two covered
production lines, in a casting yard at
land level
• Casting of a 2,500 m3 segment in
one continuous 24 hour cast
• Sluicing the completed elements
down from land to sea level by use of
a lock
• Preparation of a gravel bed foundation
for tunnel elements in the dredged
trench, using the Boskalis scrading®
method
• Use of satellite navigation for
transport and for tunnel element
immersion
On behalf of ØTC, Hydronamic
executed various engineering tasks
during the design phase of the project:
• Design of the gravel bed foundation,
including construction method
• Design of the survey system to verify
acceptability of the gravel bed
• Design of the stone protection layer
on top of the tunnel, including
required filter construction
• Supervision of model tests in the local
hydraulic laboratories (DHI)
• Development of immersion equipment
• Development of the QA (work-)
procedures for the marine works
• Development of the Multi Purpose
Pontoon (MPP) for ØTC.
The design
The tunnel cross-section consists of
two dual-carriage motorway bores,
with a service annex escape gallery in
between, and two single-track railway
bores. The total width of the tunnel is
38.65 m, with a height of 8.55 m.
Twenty 176 m long elements will form
a straight tunnel of 3,520 m.
The maximum construction depth is
approx. 22 m below water, while the
future navigation depth over the tunnel
will be dredged to -10 m.
A complicating factor at this site is the
behaviour of the current.
There is hardly any tidal variation but a
very complex current system exists in
the Little Belt, Great Belt and the
Øresund.
The most accurate current prediction
system available can only predict up to
12 hrs. ahead.
This limits the flexibility of operations,
necessitating strict management based
on step-by-step, ‘go or no go’ decision-
making.
Multi Purpose Pontoon
The purpose designed and built Multi
Purpose Pontoon has the following
tasks:
• Cleaning the dredged trench
• Construction of the gravel bed
• Survey of the gravel bed for
acceptance
• Repair and maintenance of the gravel
bed, when required
• Backfill of trench with sand and
stone material
• Construction of filter and armour
layers
Basically all functions are performed
with a fall-pipe, moving sideways along
the pontoon, while material is supplied
on a conveyer belt system. Depending
on the task to be performed different
tools are fixed to the bottom of the
fall-pipe, namely a gravel scrading unit,
sand chute or vortex clean-up unit, all
purpose designed and built.
The survey
Boskalis, in co-operation with Geocon
Holland Inc. are responsible for the
immersion survey works.
Transport and immersion of elements
are fully controlled through DGPS
navigation. Coordinates of antennas
are, via the command tower and access
shaft, transferred down to the element,
providing very accurate placement
information. For leveling of the gravel
bed a horizontally rotating laser-plane is
established, to provide even greater
accuracy. Ground bed sounding is
made with two rows of five 1 Mhz.
transducers, placed on the sides of the
scrading unit. On line corrections are
implementated for
water salinity variations.
Transport route of the tunnel elements.
0 1 2 3 4 5 km

More Related Content

Similar to Oresund

Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnelShaikh Ismail
 
GM-casestudy-uninett
GM-casestudy-uninettGM-casestudy-uninett
GM-casestudy-uninettScott Miller
 
Melbourne Channel Deepening
Melbourne Channel DeepeningMelbourne Channel Deepening
Melbourne Channel DeepeningSikko Krol
 
Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnelsarravindsai
 
wagdy garas CV 1
wagdy garas CV 1wagdy garas CV 1
wagdy garas CV 1Wagdy Garas
 
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...BPA-GmbH, Waterproofing is our Passion!
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructionsVinay Vb
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationAmir Amdani
 
Underwater construction
Underwater constructionUnderwater construction
Underwater constructionHetviPatel58
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 
Immersed Tunnels Recent developments
Immersed Tunnels Recent developmentsImmersed Tunnels Recent developments
Immersed Tunnels Recent developmentsStatybos Akademija
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - FletcherJade Keswick
 
Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1robinking277
 

Similar to Oresund (20)

Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnel
 
Submerged tunnel ppt
Submerged tunnel pptSubmerged tunnel ppt
Submerged tunnel ppt
 
GM-casestudy-uninett
GM-casestudy-uninettGM-casestudy-uninett
GM-casestudy-uninett
 
Melbourne Channel Deepening
Melbourne Channel DeepeningMelbourne Channel Deepening
Melbourne Channel Deepening
 
Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnels
 
wagdy garas CV 1
wagdy garas CV 1wagdy garas CV 1
wagdy garas CV 1
 
Anese brochure
Anese brochure Anese brochure
Anese brochure
 
Pont oresund
Pont oresundPont oresund
Pont oresund
 
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
 
The øresund bridge
The øresund bridge  The øresund bridge
The øresund bridge
 
Dana Medway HR
Dana Medway HRDana Medway HR
Dana Medway HR
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
Immersed Tunnels Recent developments
Immersed Tunnels Recent developmentsImmersed Tunnels Recent developments
Immersed Tunnels Recent developments
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - Fletcher
 
Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1
 

Oresund

  • 1. Rosmolenweg 20 P.O. Box 209, 3350 AE Papendrecht The Netherlands Tel: +31 (0)78 - 69 69 099 Fax: +31 (0)78 - 69 69 555 E-mail: general@hydronamic.nl Internet: www.hydronamic.nl Client: Öresundkonsortiet Location: Øresund, Denmark / Sweden Period: 1995 - 1998 Port and Waterway Engineering, Project Development The Øresund Tunnel Location map. Artist’s impression of the Øresund Link. Introduction The Øresund Tunnel forms part of the Øresund Link that will connect the cities of Copenhagen in Denmark and Malmö in Sweden across the Øresund. The Link, which will comprise a motorway and a railway, consists of three different construction elements: • A man-made peninsula adjacent to Copenhagen airport (Kastrup) and a 4 km long man-made island (called Peberholm) located roughly in the middle of the Øresund; • The world’s longest immersed tunnel of 3,520 metres, positioned between the peninsula and Peberholm; • A bridge of 7.8 km length between the artificial island and the Swedish coast near Malmö. The decision to construct the Link was taken by the Danish and Swedish governments after lengthy discussions, mainly about the environmental aspects of the works. The Link is being built under design & construct contracts, and will be operated by Øresundkonsortiet who will charge a toll. The opening of the Link is scheduled for 2000. The tunnel project In mid-1995 Øresundkonsortiet signed a contract with the Øresund Tunnel Contractors for the design and construction of the tunnel. The partners in Øresund Tunnel Contractors (ØTC) Joint Venture are: • NCC AB from Sweden, • E. Phil & Søn A.S. from Denmark, • Dumez-GTM S.A. from France, • John Laing Construction Ltd. from Great Britain • Boskalis Westminster Dredging BV from Holland. Special aspects of tunnel construction In response to the limited available construction time ØTC developed an innovative way of construction which, in particular, was designed to minimise risks resulting from the Scandinavian weather conditions. 0 5 km Denmark Sweden
  • 2. Multi Purpose Pontoon MPP. Tunnel element before immersion. Typical design features: • Simultaneous construction of two tunnel segments on two covered production lines, in a casting yard at land level • Casting of a 2,500 m3 segment in one continuous 24 hour cast • Sluicing the completed elements down from land to sea level by use of a lock • Preparation of a gravel bed foundation for tunnel elements in the dredged trench, using the Boskalis scrading® method • Use of satellite navigation for transport and for tunnel element immersion On behalf of ØTC, Hydronamic executed various engineering tasks during the design phase of the project: • Design of the gravel bed foundation, including construction method • Design of the survey system to verify acceptability of the gravel bed • Design of the stone protection layer on top of the tunnel, including required filter construction • Supervision of model tests in the local hydraulic laboratories (DHI) • Development of immersion equipment • Development of the QA (work-) procedures for the marine works • Development of the Multi Purpose Pontoon (MPP) for ØTC. The design The tunnel cross-section consists of two dual-carriage motorway bores, with a service annex escape gallery in between, and two single-track railway bores. The total width of the tunnel is 38.65 m, with a height of 8.55 m. Twenty 176 m long elements will form a straight tunnel of 3,520 m. The maximum construction depth is approx. 22 m below water, while the future navigation depth over the tunnel will be dredged to -10 m. A complicating factor at this site is the behaviour of the current. There is hardly any tidal variation but a very complex current system exists in the Little Belt, Great Belt and the Øresund. The most accurate current prediction system available can only predict up to 12 hrs. ahead. This limits the flexibility of operations, necessitating strict management based on step-by-step, ‘go or no go’ decision- making. Multi Purpose Pontoon The purpose designed and built Multi Purpose Pontoon has the following tasks: • Cleaning the dredged trench • Construction of the gravel bed • Survey of the gravel bed for acceptance • Repair and maintenance of the gravel bed, when required • Backfill of trench with sand and stone material • Construction of filter and armour layers Basically all functions are performed with a fall-pipe, moving sideways along the pontoon, while material is supplied on a conveyer belt system. Depending on the task to be performed different tools are fixed to the bottom of the fall-pipe, namely a gravel scrading unit, sand chute or vortex clean-up unit, all purpose designed and built. The survey Boskalis, in co-operation with Geocon Holland Inc. are responsible for the immersion survey works. Transport and immersion of elements are fully controlled through DGPS navigation. Coordinates of antennas are, via the command tower and access shaft, transferred down to the element, providing very accurate placement information. For leveling of the gravel bed a horizontally rotating laser-plane is established, to provide even greater accuracy. Ground bed sounding is made with two rows of five 1 Mhz. transducers, placed on the sides of the scrading unit. On line corrections are implementated for water salinity variations. Transport route of the tunnel elements. 0 1 2 3 4 5 km