efore the new treatment works at Peacehaven, wastewater from Peacehaven, Telscombe Cliffs, Saltdean,
Rottingdean, Ovingdean and Brighton and Hove, passed through preliminary treatment before being released
out to sea at Portobello. As one of the last remaining conurbation in the UK failing to meet the European Urban
Waste Water Treatment Directive, Southern Water (SW) launched a major new environmental improvement scheme
to bring the south coast into line with the directive. Twelve years later, planning was approved and work began
on the Cleaner Seas for Sussex Project. In a dry valley to the north of Peacehaven, works began on the construction
of the Cleaner Seas for Sussex Project in July 2009. After four and a half years, more than 1 million cubic metres of
earth excavated, 39,000m3
of concrete poured and over 4.5 million man hours worked, this £300m project had to
be handed over to Southern Water. After successful completion of commissioning the previous year, work began on
achieving compliance and take over testing.
Introduction
Undertaken by 4Delivery Ltd (a joint venture between Costain,
Veolia and MWH) this flagship project involved the construction of
a new wastewater treatment works (WTW), and sludge recycling
centre (SRC) serving a population of 300,000, and capable of
treating up to 218ML/d.
Threedeepshaftpumpingstationspassforwardflowthrough11km
of new sewer tunnel which runs from Brighton Marina to the works
at Peacehaven, varying from eight to 40m below ground level. At
the works, flows pass through three stages of treatment before
being released 2.5km out to sea. Preliminary treatment consists
of 3 (No.) 6mm band screens followed by 3 (No.) aerated lanes to
remove fat, oil, grit and grease (FOGG). Primary settlement takes
the form of 4 (No.) chemically assisted Multiflo™ lamellas supplied
and commissioned by Veolia Water Solutions & Technology.
www.WaterProjectsOnline.com	 Wastewater Treatment & Sewerage
UK Water Projects 2014	 Page 1
Brighton & Hove WwT Scheme
Peacehaven WwTW - handover and completion
of the Cleaner Seas for Sussex project
by Anthony Thomas MEng, Mike Walker & Iain McGregor BEng
After 12 years of planning and four years of construction Peacehaven WwTW is fully operational - Courtesy of Southern Water
A Biostyr™ biologically aerated flooded filter (also fromVeolia) is the
final treatment stage; 10 (No.) cells filled with polystyrene beads
which promote the growth of bacteria, ensure that the quality
consents for the final effluent are achieved.
Sludge from the lamellas is screened before co-settlement and
thickening by gravity belt thickeners to 7% dry solids (DS). It is then
fed into anaerobic digesters at 35oC. The resulting biogas is used
by the combined heat and power (CHP) plant to produce 1MW
of electricity, for use on site, and heating for maintaining digester
temperature.The electricity generated from biogas allows Southern
Water to receive Renewable Obligation Certificates (ROCs).
After 14 days the digested sludge passes into post digestion tanks
before it is centrifuged to 25% DS and dried in a thermal dryer,
supplied by Andritz UK, to 92% DS.
Plasticon UK Limited engineers and manufacturers of GRP products, including Storage
Tanks, Process Vessels and Equipment, Ductwork and Piping Systems, Speciality
Products, Field Fabrication, Installation and Maintenance Services
Providing turnkey Odour Treatment Plants including, but not
restricted to, the following equipment:
 Biofilters
 Jet Venturi Scrubber – Solids Removal
 Ammonia Chemical Scrubber Stage – Sulphuric Acid
 Wet Chemical Scrubber Stage – Caustic/Hypochlorite
 Chemical Storage Tanks and Dosing Systems
 Tanker Delivery Filling Stations
 Carbon Adsorber Units – Polishing Filters
 OCU Slab & Field Extract Ductwork Systems
 Exhaust Stack
 Control Systems
 Proprietary Equipment (Fans, Pumps, Valves & Instrumentation)
 Pipework Systems
 Installation
 Testing and Commissioning
Clients include:
 Wessex Water
 Thames Water
 4Delivery/Southern Water
 Scottish Water
 Anglian Water
 Yorkshire Water
 United Utilities
 Trant Construction
 Black & Veatch
 KMI
 AECOM
 GCA
 MWH
 Interserve
 ETM
 Novartis
 Jacobs UK
 Fine Environmental
ISO9001:2008 Accredited
Members of: British Plastics Federation, Achilles & ECIA
Plasticon UK Limited
44C Stockholm Road,
Sutton Fields Industrial Estate
HULL, HU7 OXW
United Kingdom
Tel: + 44 (0)1482 862194
Fax: + 44 (0)1482 871398
sales@plasticon.co.uk
www.plasticoncomposites.com
For further information or to discuss your individual requirements please contact
Plasticon UK on +44 (0)1482 862194 or email sales@plasticon.co.uk
www.WaterProjectsOnline.com	 Wastewater Treatment & Sewerage
UK Water Projects 2014	 Page 3
The SRC has the facilities to accept deliveries of imported liquid
sludge, raw cake and digested cake. This facility allows the site to
help other SW assets in emergency situation.
All processes and building spaces have odour extraction (provided
and commissioned by Plasticon (UK) which treats 250,000m3
per
hour though three acid and three alkali scrubbers and three carbon
absorbers before releasing it to atmosphere.
Commissioning
Before commissioning started, a detailed Commissioning Plan was
producedexplainingthetestregimesandstrategyofbringtheplant
online, ensuring client buy-in and establishing communication
from the outset. By implementing a 100% testing regime the client
signed off areas of commissioning on a daily basis, allowing for
progress to continue without conflict.
As part of their strategy, 4Delivery broke down the project scope in
to 18 areas with sub groups of between one and six sections. This
allowed the site to be broken down into manageable process areas
and achieve sign off on individual areas.
A phased approach was taken for commissioning. This allowed
for construction completion of the later treatment stages whilst
accepting flows for preliminary treatment. The works was brought
into service in three defined Turn of Flows (TOF):
•	 TOF 1: Was the infrastructure pumping stations and
preliminary WTW
•	 TOF 2: Focused on the lamella primary treatment and
sludge treatment
•	 TOF 3: Looked at the secondary treatment BAFF plant and
dryer package.
At TOF 1 flows were initially restricted to 600l/s to ensure a
steady, continuous flow into the treatment works, with excess
flows continuing to pass to the existing works at Portobello. After
the FOGG process was optimised and working correctly, TOF 2
commissioning began. Over the course of a month the 4 (No.)
Multiflo™ cells were brought online with their respective chemical
dosing for flocculation and coagulation. The settled sludge was
then screened and forwarded on to the sludge treatment process.
The digesters were seeded with stable sludge from another SW site
promoting bacterial growth within the new indigenous sludge.
Sludge from the co-settlement tanks was fed into the gravity belt
thickeners before being pumped into the digester feed tanks. After
a period of carefully introducing indigenous sludge to the digesters,
they over spilled into the post digestion tanks, which enabled TOF
3 commissioning of the centrifuges and dryer, resulting in the
production of granules for agricultural use.
In TOF 3 the Biostyr™ plant was brought online. Full flows were
now being treated on site and all ten cells were brought online
together. As the biological processes established themselves, the
quality improved and once all phases of the plant had stabilised
compliance testing could begin.
Compliance testing
Compliance testing for the Cleaner Seas for Sussex Project involved
completing 13 tests to a strict set of criteria. The tests ensured that
SW could meet discharge consents for final effluent and odour
emissions. Biological oxygen demand (BOD), chemical oxygen
demand (COD), metals and suspended solids were tested to ensure
that the quality of the final effluent achieved the required consent.
Flow to site was also tested to ensure that the peak pass forward
rate, as defined in the consent, is also achieved. Odour stack
velocity and H2S concentration were also measured for compliance
with planning conditions.
The new treatment works is covered by one of the largest green roofs in
Europe, covering almost 18,000m2
- Courtesy of Southern Water
Located on the a traffic island between the carriageway of the A259,
Marine Drive Pumping Station is a landmark building to the east of
Brighton and Hove - Courtesy of Southern Water
Sludge collected during the treatment process is treated on site, the final
process of which dries this bi-product to produce a soil conditioner for
agriculture in a thermal dryer - Courtesy of Southern Water
Peacehaven Inlet Pumping Station
Courtesy of Southern Water
www.WaterProjectsOnline.com	 Wastewater Treatment & Sewerage
UK Water Projects 2014	 Page 4
The tests were conducted over a continuous period of 28 days for
successful testing to be achieved. Prior to the commencement of
testing, 4D entered into a phase of pre-testing. This ensured that
the tests would achieve their criteria within the 28 days without
having to restart the tests.
Compliance testing was completed on the March 10, 2013.
Following the receipt of all accredited sampling two weeks later the
compliance test report was handed to SW to review, signed off as
complete one week later, achieving the consent deadline.
By holding daily meetings between 4D and Southern Water, 4D
was able to react to any problems/risks we were faced with and
reviewed progress towards completing any actions raised. These
meetings allowed 4D to keep a running tally of completed days
and tests without having to review them at the end. By involving
SW prior to entering into compliance testing and conducting 100%
pre-testing, 4D was able to provide SW with confidence that the
tests would achieve the criteria within the period.
Take over testing
In a similar fashion to compliance testing, Take Over Testing (ToT)
comprised of 44 tests running over a 28 day period, testing every
part of the infrastructure and treatment works.
Some of these were repeats of the tests seen in compliance testing,
howeverToT looked into the operation and reliability of the plant as
well as the quality for water and sludge processes. A pre-test period
occurred before entering into test.
Incorporating lessons learnt from compliance testing; SW had a
major role during the test period. Methodologies were presented
to SW for approval before entering into the test. This ensured that
they understood how the tests were being conducted and how the
results would be presented. Daily meetings were held between
4D and SW during the test period where plant performance was
reviewed, sampling, alarms, events and other tests results were
discussed and approved at this meeting. Events of that day,
previous and the next day were reviewed as well to ensure that
all parties knew what was occurring and representatives could be
arranged for witnessing.
On October 10, 2013, ToT began and was achieved on the
December 19, 2013, except for a few areas where the plant still
had to be tested, because sludge and cess imports were not at that
stage being received on-site. This meant they couldn’t be done
within the original test period and were therefore tested when the
programme of works was completed.
SW and 4D worked collaboratively for a successful resolution of
these delayed areas and allowed the ToT to begin for the rest of the
site while this work was on-going.
Examples of the take over tests
Test T23 was a repeat from compliance testing; 4D worked with
Southern Water to define exactly how it would be carried out and
what it entailed. With agreement 4D hired specialists from RPS to
perform velocity measurements across the odour stack and report
back their findings. The velocity achieved the criteria. From the
results it was possible to determine a coefficient which can be
applied to the flow meter of the fans for the stack, SW agreed that
this method for ToT. This enabled 4D to save cost by not having to
hire the contractor again and time by not having to wait for the
results to be presented.
TestT30 tested the reliability of the plant.This test would fail should
any process stream be unavailable for more than 1% of the test
period. Since the whole works was included in this test, a permit
regime was strictly enforced to manage planned maintenance.
Daily alarms and events were used to measure the unavailability.
A biological aerated flooded filter (BAFF) provides the final stage of wastewater treatment at Peacehaven WwTW - Courtesy of Southern Water
www.WaterProjectsOnline.com	 Wastewater Treatment & Sewerage
UK Water Projects 2014	 Page 5
More than 100 people attending the project’s was formal opening on
14 October 2013 - Courtesy of Southern Water
Media were shown the site as part of the formal opening of the project
Courtesy of Southern Water
Test # Specific Test Performance criteria Type of sample Sampling point Frequency of sampling
# of allowable
failures
T23
Odour control
stack velocity
A velocity not less than
that assumed in the odour
dispersion modelling
(21m/s) and not less than
15m/s at average air flow
rates
Spot reading
Ventilation system
operating at average
discharge rate
Until reliable readings
obtained
0
T30 Plant reliability
Not more than 1%
unavailability of any process
stream or operation during
the 28 day test period.
Operational records Operational records Continuous 0
T35
WTW hydraulic
profile and
performance
verification
Water levels in process units,
chambers and channels
shall not exceed design
levels.
Level sensors/SCADA and
supplementary water level
measurement as necessary
to demonstrate compliance.
Throughout the water line
of the WTW
Up to 4 times (at least
once to coincide with
maximum flow or
simulated maximum
flow conditions).
0
The works has been designed with standby plant for nearly
every item on site; as a result the test was passed with only 31
minutes of downtime out of the possible 403 minutes allowed
within the 28 days’ test period. This is a good example of how
day to day management alongside the client and operation staff
accommodated an effective and efficient test period.
TestT35 was a guarantee to SW that what has been design and built
by 4D was hydraulically correct. The methodology for this test went
through a series of revisions before an agreement was made. SW
worked with 4D to define and perform the test which enable the
results to be agreed as measurements were taken. The contract
definitions of the take over tests noted above are in the table above.
Conclusion
Bringing into service and testing of a new £300m wastewater
treatment works and sludge treatment and recycling centre the
size of the Cleaner Seas for Sussex project would normally result in
considerable amount of time being spent in discussions with the
client following the conclusion of the test period; generally these
discussions taking longer than the tests themselves.
However, Southern Water provided a site team that was both
involved and engaged with all aspects of the project and as a result
gained a detailed working knowledge of the plant. More than
this, they were determined and worked with the same drive and
enthusiasm as 4D staff to have the tests professionally completed.
Furthermore, issues arising from the test were worked through
quickly to the satisfaction of both parties.
4Delivery implemented a regime of 100% pre-testing to prove to
themselves and the client that the test criteria would be achieved
before beginning the test. This ironed out any interference factors
and demonstrated that the plant would operate as expected giving
confidence to all parties.
Since achieving take over in December 2013, the final tests have
been successfully completed and a series of performance tests
commenced.
With client collaboration in every step of the commissioning phase
and by committing to a 100% testing strategy, 4Delivery was able
to achieve hand over of this flagship project, attaining the high
quality standards required while demonstrating the stability of
the process. The scale and engagement of this scheme makes it a
truly remarkable project that has been extensively recognised by
numerous national bodies.
The Editor & Publishers would like to thank Anthony Thomas,
Engineer, Mike Walker, Commissioning Manager, and Iain
McGregor , Project Installation and Commissioning Manager, all
with 4Delivery, for providing the above article for publication.
The wastewater arriving on site (left) has rag, a mixture of toilet roll, wet
wipes and anything else flushed down the toilet, removed (middle) before
it is treated to secondary treatment standard and released 2.5km off
shore (right) - Courtesy of Southern Water
www.paques.nl
Removal of Solids,
Nitrogen & Phosphorus
ASTRASAND®
Continuous sand filtration
ASTRASEPARATOR®
Compact lamella clarifier
• 25 years operational experience
• 3,600 units installed worldwide
• Tertiary (waste)water treatment

More Related Content

What's hot

O&GFaclities_Oct2013_SandManagementMethodologies
O&GFaclities_Oct2013_SandManagementMethodologiesO&GFaclities_Oct2013_SandManagementMethodologies
O&GFaclities_Oct2013_SandManagementMethodologiesHank Rawlins
 
PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsMarcellus Drilling News
 
2009-06-25 Luncheon - What a Utility Needs to Consider When Converting a Syst...
2009-06-25 Luncheon - What a Utility Needs to Consider When Converting a Syst...2009-06-25 Luncheon - What a Utility Needs to Consider When Converting a Syst...
2009-06-25 Luncheon - What a Utility Needs to Consider When Converting a Syst...Southeast Chapter of Texas AWWA
 
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.Mike Dupont
 
IRJET - Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
IRJET -  	  Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...IRJET -  	  Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
IRJET - Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...IRJET Journal
 
IRJET- A Review on Utilization of Sequence Batch Reactor Technology (SBR)...
IRJET-  	  A Review on Utilization of Sequence Batch Reactor Technology (SBR)...IRJET-  	  A Review on Utilization of Sequence Batch Reactor Technology (SBR)...
IRJET- A Review on Utilization of Sequence Batch Reactor Technology (SBR)...IRJET Journal
 
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Society of Petroleum Engineers
 
Shale Development – Does Cheap Energy Really Mean Flaming Tap Water?
Shale Development – Does Cheap Energy Really Mean Flaming Tap Water?Shale Development – Does Cheap Energy Really Mean Flaming Tap Water?
Shale Development – Does Cheap Energy Really Mean Flaming Tap Water?Society of Petroleum Engineers
 
Copper nap AWPA update 20150406
Copper nap AWPA update 20150406Copper nap AWPA update 20150406
Copper nap AWPA update 20150406Ken Laughlin
 
Fish Market Drainage At Abu Hamour
Fish Market Drainage At Abu HamourFish Market Drainage At Abu Hamour
Fish Market Drainage At Abu HamourMohamed ElSirsy
 
Marina and Village Surface Water Runoff and Waste Water Management plan
 Marina and Village Surface Water Runoff and Waste Water Management plan Marina and Village Surface Water Runoff and Waste Water Management plan
Marina and Village Surface Water Runoff and Waste Water Management planFrank Costanzo Connelly
 
Harnessing oxygen to boost performance in wastewater treatment plant upgrade
Harnessing oxygen to boost performance in wastewater treatment plant upgradeHarnessing oxygen to boost performance in wastewater treatment plant upgrade
Harnessing oxygen to boost performance in wastewater treatment plant upgradeLinde Gas Benelux
 
Improvement of uf membrane performance
Improvement of uf membrane performanceImprovement of uf membrane performance
Improvement of uf membrane performancemauriciocabral2018
 
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Society of Petroleum Engineers
 
BROCHURE+max+profits+email
BROCHURE+max+profits+emailBROCHURE+max+profits+email
BROCHURE+max+profits+emailRicky Diggs
 

What's hot (20)

O&GFaclities_Oct2013_SandManagementMethodologies
O&GFaclities_Oct2013_SandManagementMethodologiesO&GFaclities_Oct2013_SandManagementMethodologies
O&GFaclities_Oct2013_SandManagementMethodologies
 
Hank Rawlins
Hank RawlinsHank Rawlins
Hank Rawlins
 
PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas Operations
 
2009-06-25 Luncheon - What a Utility Needs to Consider When Converting a Syst...
2009-06-25 Luncheon - What a Utility Needs to Consider When Converting a Syst...2009-06-25 Luncheon - What a Utility Needs to Consider When Converting a Syst...
2009-06-25 Luncheon - What a Utility Needs to Consider When Converting a Syst...
 
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
SPE Workshop Water Quality and Hz Inj - MB Dupont P.Eng.
 
IRJET - Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
IRJET -  	  Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...IRJET -  	  Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
IRJET - Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
 
IRJET- A Review on Utilization of Sequence Batch Reactor Technology (SBR)...
IRJET-  	  A Review on Utilization of Sequence Batch Reactor Technology (SBR)...IRJET-  	  A Review on Utilization of Sequence Batch Reactor Technology (SBR)...
IRJET- A Review on Utilization of Sequence Batch Reactor Technology (SBR)...
 
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
 
Shale Development – Does Cheap Energy Really Mean Flaming Tap Water?
Shale Development – Does Cheap Energy Really Mean Flaming Tap Water?Shale Development – Does Cheap Energy Really Mean Flaming Tap Water?
Shale Development – Does Cheap Energy Really Mean Flaming Tap Water?
 
Copper nap AWPA update 20150406
Copper nap AWPA update 20150406Copper nap AWPA update 20150406
Copper nap AWPA update 20150406
 
Abstract32808 mecham
Abstract32808 mechamAbstract32808 mecham
Abstract32808 mecham
 
Fish Market Drainage At Abu Hamour
Fish Market Drainage At Abu HamourFish Market Drainage At Abu Hamour
Fish Market Drainage At Abu Hamour
 
Does Heavy Oil Recovery Need Steam?
Does Heavy Oil Recovery Need Steam?Does Heavy Oil Recovery Need Steam?
Does Heavy Oil Recovery Need Steam?
 
Marina and Village Surface Water Runoff and Waste Water Management plan
 Marina and Village Surface Water Runoff and Waste Water Management plan Marina and Village Surface Water Runoff and Waste Water Management plan
Marina and Village Surface Water Runoff and Waste Water Management plan
 
Harnessing oxygen to boost performance in wastewater treatment plant upgrade
Harnessing oxygen to boost performance in wastewater treatment plant upgradeHarnessing oxygen to boost performance in wastewater treatment plant upgrade
Harnessing oxygen to boost performance in wastewater treatment plant upgrade
 
Improvement of uf membrane performance
Improvement of uf membrane performanceImprovement of uf membrane performance
Improvement of uf membrane performance
 
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
 
BROCHURE+max+profits+email
BROCHURE+max+profits+emailBROCHURE+max+profits+email
BROCHURE+max+profits+email
 
Groundwater Rule Overview and Best Practices
Groundwater Rule Overview and Best PracticesGroundwater Rule Overview and Best Practices
Groundwater Rule Overview and Best Practices
 
Robert Hawkes
Robert HawkesRobert Hawkes
Robert Hawkes
 

Viewers also liked

Brandnew(s) magazine februari 2015
Brandnew(s) magazine   februari 2015Brandnew(s) magazine   februari 2015
Brandnew(s) magazine februari 2015Sam Aga
 
BRANDNEW(S) magazine - mei 2015
BRANDNEW(S) magazine - mei 2015BRANDNEW(S) magazine - mei 2015
BRANDNEW(S) magazine - mei 2015Sam Aga
 
BRANDNEW(S) april 2016
BRANDNEW(S) april 2016BRANDNEW(S) april 2016
BRANDNEW(S) april 2016Sam Aga
 
Spotlight Feature - Interview Martin Sciarrillo Global lead for Linux Services
Spotlight Feature - Interview Martin Sciarrillo Global lead for Linux ServicesSpotlight Feature - Interview Martin Sciarrillo Global lead for Linux Services
Spotlight Feature - Interview Martin Sciarrillo Global lead for Linux ServicesMartin Sciarrillo
 
Total Quality Management (TQM)
Total Quality Management (TQM)Total Quality Management (TQM)
Total Quality Management (TQM)Khan Hoque
 
Total Quality Management (TQM)
Total Quality Management (TQM)Total Quality Management (TQM)
Total Quality Management (TQM)Khan Hoque
 
BCS Recruitment Rules 1981
BCS  Recruitment Rules 1981BCS  Recruitment Rules 1981
BCS Recruitment Rules 1981Khan Hoque
 
lecture notes on Bearings
lecture notes on Bearingslecture notes on Bearings
lecture notes on BearingsSarath Bandara
 
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéSActualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéSCarmen Vera
 
Le Blog Dans L’Enseignement Des Langues éTrangèRes
Le Blog Dans L’Enseignement Des Langues éTrangèResLe Blog Dans L’Enseignement Des Langues éTrangèRes
Le Blog Dans L’Enseignement Des Langues éTrangèResCarmen Vera
 
Internet pour les DNL francophones
Internet pour les DNL francophonesInternet pour les DNL francophones
Internet pour les DNL francophonesCarmen Vera
 
Créer une chasse au trésor avec Web Worksheet Wizard
Créer une chasse au trésor avec Web Worksheet WizardCréer une chasse au trésor avec Web Worksheet Wizard
Créer une chasse au trésor avec Web Worksheet WizardCarmen Vera
 
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéSActualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéSCarmen Vera
 

Viewers also liked (17)

Brandnew(s) magazine februari 2015
Brandnew(s) magazine   februari 2015Brandnew(s) magazine   februari 2015
Brandnew(s) magazine februari 2015
 
BRubison-Unit 9-SRC
BRubison-Unit 9-SRCBRubison-Unit 9-SRC
BRubison-Unit 9-SRC
 
BRANDNEW(S) magazine - mei 2015
BRANDNEW(S) magazine - mei 2015BRANDNEW(S) magazine - mei 2015
BRANDNEW(S) magazine - mei 2015
 
BRANDNEW(S) april 2016
BRANDNEW(S) april 2016BRANDNEW(S) april 2016
BRANDNEW(S) april 2016
 
See addtachment
See addtachmentSee addtachment
See addtachment
 
Spotlight Feature - Interview Martin Sciarrillo Global lead for Linux Services
Spotlight Feature - Interview Martin Sciarrillo Global lead for Linux ServicesSpotlight Feature - Interview Martin Sciarrillo Global lead for Linux Services
Spotlight Feature - Interview Martin Sciarrillo Global lead for Linux Services
 
Total Quality Management (TQM)
Total Quality Management (TQM)Total Quality Management (TQM)
Total Quality Management (TQM)
 
Total Quality Management (TQM)
Total Quality Management (TQM)Total Quality Management (TQM)
Total Quality Management (TQM)
 
BRubison-Unit 9-SLDC
BRubison-Unit 9-SLDCBRubison-Unit 9-SLDC
BRubison-Unit 9-SLDC
 
BCS Recruitment Rules 1981
BCS  Recruitment Rules 1981BCS  Recruitment Rules 1981
BCS Recruitment Rules 1981
 
lecture notes on Bearings
lecture notes on Bearingslecture notes on Bearings
lecture notes on Bearings
 
Le Web 2
Le Web 2Le Web 2
Le Web 2
 
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéSActualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
 
Le Blog Dans L’Enseignement Des Langues éTrangèRes
Le Blog Dans L’Enseignement Des Langues éTrangèResLe Blog Dans L’Enseignement Des Langues éTrangèRes
Le Blog Dans L’Enseignement Des Langues éTrangèRes
 
Internet pour les DNL francophones
Internet pour les DNL francophonesInternet pour les DNL francophones
Internet pour les DNL francophones
 
Créer une chasse au trésor avec Web Worksheet Wizard
Créer une chasse au trésor avec Web Worksheet WizardCréer une chasse au trésor avec Web Worksheet Wizard
Créer une chasse au trésor avec Web Worksheet Wizard
 
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéSActualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
Actualizacion Didactica Para Profesores Dnl De Secciones BilingüEs De FrancéS
 

Similar to Southern_Peacehaven_2014

Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...LOWaterkeeper
 
PROSPECT WATER FILTRATION PLANT (NSW)
PROSPECT WATER FILTRATION PLANT (NSW)PROSPECT WATER FILTRATION PLANT (NSW)
PROSPECT WATER FILTRATION PLANT (NSW)Rick Nabett
 
Cronulla wastewater treatment plant
Cronulla wastewater treatment plantCronulla wastewater treatment plant
Cronulla wastewater treatment plantRick Nabett
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...DOE Office of River Protection
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
Island Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportIsland Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportToronto Public Consultation Unit
 
2010 2012-groundwater-plume
2010 2012-groundwater-plume2010 2012-groundwater-plume
2010 2012-groundwater-plumeEric Xanderson
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferenceJohn Grover
 
Newsletter EPA Landfill Leachate Project
Newsletter EPA Landfill Leachate ProjectNewsletter EPA Landfill Leachate Project
Newsletter EPA Landfill Leachate ProjectRaymond Brennan
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15ADAM DUKE
 
OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06John Grover
 
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...LOWaterkeeper
 
Ati pogam modified
Ati pogam modifiedAti pogam modified
Ati pogam modifiedVladimir
 
Ecw 579 week 6. latest
Ecw 579 week 6. latestEcw 579 week 6. latest
Ecw 579 week 6. latestAdilah Anuar
 
EPPMPresentationOMOct22 (1).pptx
EPPMPresentationOMOct22 (1).pptxEPPMPresentationOMOct22 (1).pptx
EPPMPresentationOMOct22 (1).pptxHedi Ben Mohamed
 
Innovations in wastewater treatment
Innovations in wastewater treatmentInnovations in wastewater treatment
Innovations in wastewater treatmentLinde Gas Benelux
 
C. Belfield Detailed Work History
C. Belfield Detailed Work HistoryC. Belfield Detailed Work History
C. Belfield Detailed Work HistoryCaroline Belfield
 

Similar to Southern_Peacehaven_2014 (20)

Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
 
PROSPECT WATER FILTRATION PLANT (NSW)
PROSPECT WATER FILTRATION PLANT (NSW)PROSPECT WATER FILTRATION PLANT (NSW)
PROSPECT WATER FILTRATION PLANT (NSW)
 
Leather complex
Leather complexLeather complex
Leather complex
 
Personal Resume of Darrell CordeiroV3
Personal Resume of Darrell CordeiroV3Personal Resume of Darrell CordeiroV3
Personal Resume of Darrell CordeiroV3
 
Cronulla wastewater treatment plant
Cronulla wastewater treatment plantCronulla wastewater treatment plant
Cronulla wastewater treatment plant
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
Island Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportIsland Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File Report
 
2010 2012-groundwater-plume
2010 2012-groundwater-plume2010 2012-groundwater-plume
2010 2012-groundwater-plume
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline Conference
 
Newsletter EPA Landfill Leachate Project
Newsletter EPA Landfill Leachate ProjectNewsletter EPA Landfill Leachate Project
Newsletter EPA Landfill Leachate Project
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06
 
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
 
Ati pogam modified
Ati pogam modifiedAti pogam modified
Ati pogam modified
 
Ecw 579 week 6. latest
Ecw 579 week 6. latestEcw 579 week 6. latest
Ecw 579 week 6. latest
 
EPPMPresentationOMOct22 (1).pptx
EPPMPresentationOMOct22 (1).pptxEPPMPresentationOMOct22 (1).pptx
EPPMPresentationOMOct22 (1).pptx
 
Innovations in wastewater treatment
Innovations in wastewater treatmentInnovations in wastewater treatment
Innovations in wastewater treatment
 
C. Belfield Detailed Work History
C. Belfield Detailed Work HistoryC. Belfield Detailed Work History
C. Belfield Detailed Work History
 

Southern_Peacehaven_2014

  • 1. B efore the new treatment works at Peacehaven, wastewater from Peacehaven, Telscombe Cliffs, Saltdean, Rottingdean, Ovingdean and Brighton and Hove, passed through preliminary treatment before being released out to sea at Portobello. As one of the last remaining conurbation in the UK failing to meet the European Urban Waste Water Treatment Directive, Southern Water (SW) launched a major new environmental improvement scheme to bring the south coast into line with the directive. Twelve years later, planning was approved and work began on the Cleaner Seas for Sussex Project. In a dry valley to the north of Peacehaven, works began on the construction of the Cleaner Seas for Sussex Project in July 2009. After four and a half years, more than 1 million cubic metres of earth excavated, 39,000m3 of concrete poured and over 4.5 million man hours worked, this £300m project had to be handed over to Southern Water. After successful completion of commissioning the previous year, work began on achieving compliance and take over testing. Introduction Undertaken by 4Delivery Ltd (a joint venture between Costain, Veolia and MWH) this flagship project involved the construction of a new wastewater treatment works (WTW), and sludge recycling centre (SRC) serving a population of 300,000, and capable of treating up to 218ML/d. Threedeepshaftpumpingstationspassforwardflowthrough11km of new sewer tunnel which runs from Brighton Marina to the works at Peacehaven, varying from eight to 40m below ground level. At the works, flows pass through three stages of treatment before being released 2.5km out to sea. Preliminary treatment consists of 3 (No.) 6mm band screens followed by 3 (No.) aerated lanes to remove fat, oil, grit and grease (FOGG). Primary settlement takes the form of 4 (No.) chemically assisted Multiflo™ lamellas supplied and commissioned by Veolia Water Solutions & Technology. www.WaterProjectsOnline.com Wastewater Treatment & Sewerage UK Water Projects 2014 Page 1 Brighton & Hove WwT Scheme Peacehaven WwTW - handover and completion of the Cleaner Seas for Sussex project by Anthony Thomas MEng, Mike Walker & Iain McGregor BEng After 12 years of planning and four years of construction Peacehaven WwTW is fully operational - Courtesy of Southern Water A Biostyr™ biologically aerated flooded filter (also fromVeolia) is the final treatment stage; 10 (No.) cells filled with polystyrene beads which promote the growth of bacteria, ensure that the quality consents for the final effluent are achieved. Sludge from the lamellas is screened before co-settlement and thickening by gravity belt thickeners to 7% dry solids (DS). It is then fed into anaerobic digesters at 35oC. The resulting biogas is used by the combined heat and power (CHP) plant to produce 1MW of electricity, for use on site, and heating for maintaining digester temperature.The electricity generated from biogas allows Southern Water to receive Renewable Obligation Certificates (ROCs). After 14 days the digested sludge passes into post digestion tanks before it is centrifuged to 25% DS and dried in a thermal dryer, supplied by Andritz UK, to 92% DS.
  • 2. Plasticon UK Limited engineers and manufacturers of GRP products, including Storage Tanks, Process Vessels and Equipment, Ductwork and Piping Systems, Speciality Products, Field Fabrication, Installation and Maintenance Services Providing turnkey Odour Treatment Plants including, but not restricted to, the following equipment:  Biofilters  Jet Venturi Scrubber – Solids Removal  Ammonia Chemical Scrubber Stage – Sulphuric Acid  Wet Chemical Scrubber Stage – Caustic/Hypochlorite  Chemical Storage Tanks and Dosing Systems  Tanker Delivery Filling Stations  Carbon Adsorber Units – Polishing Filters  OCU Slab & Field Extract Ductwork Systems  Exhaust Stack  Control Systems  Proprietary Equipment (Fans, Pumps, Valves & Instrumentation)  Pipework Systems  Installation  Testing and Commissioning Clients include:  Wessex Water  Thames Water  4Delivery/Southern Water  Scottish Water  Anglian Water  Yorkshire Water  United Utilities  Trant Construction  Black & Veatch  KMI  AECOM  GCA  MWH  Interserve  ETM  Novartis  Jacobs UK  Fine Environmental ISO9001:2008 Accredited Members of: British Plastics Federation, Achilles & ECIA Plasticon UK Limited 44C Stockholm Road, Sutton Fields Industrial Estate HULL, HU7 OXW United Kingdom Tel: + 44 (0)1482 862194 Fax: + 44 (0)1482 871398 sales@plasticon.co.uk www.plasticoncomposites.com For further information or to discuss your individual requirements please contact Plasticon UK on +44 (0)1482 862194 or email sales@plasticon.co.uk
  • 3. www.WaterProjectsOnline.com Wastewater Treatment & Sewerage UK Water Projects 2014 Page 3 The SRC has the facilities to accept deliveries of imported liquid sludge, raw cake and digested cake. This facility allows the site to help other SW assets in emergency situation. All processes and building spaces have odour extraction (provided and commissioned by Plasticon (UK) which treats 250,000m3 per hour though three acid and three alkali scrubbers and three carbon absorbers before releasing it to atmosphere. Commissioning Before commissioning started, a detailed Commissioning Plan was producedexplainingthetestregimesandstrategyofbringtheplant online, ensuring client buy-in and establishing communication from the outset. By implementing a 100% testing regime the client signed off areas of commissioning on a daily basis, allowing for progress to continue without conflict. As part of their strategy, 4Delivery broke down the project scope in to 18 areas with sub groups of between one and six sections. This allowed the site to be broken down into manageable process areas and achieve sign off on individual areas. A phased approach was taken for commissioning. This allowed for construction completion of the later treatment stages whilst accepting flows for preliminary treatment. The works was brought into service in three defined Turn of Flows (TOF): • TOF 1: Was the infrastructure pumping stations and preliminary WTW • TOF 2: Focused on the lamella primary treatment and sludge treatment • TOF 3: Looked at the secondary treatment BAFF plant and dryer package. At TOF 1 flows were initially restricted to 600l/s to ensure a steady, continuous flow into the treatment works, with excess flows continuing to pass to the existing works at Portobello. After the FOGG process was optimised and working correctly, TOF 2 commissioning began. Over the course of a month the 4 (No.) Multiflo™ cells were brought online with their respective chemical dosing for flocculation and coagulation. The settled sludge was then screened and forwarded on to the sludge treatment process. The digesters were seeded with stable sludge from another SW site promoting bacterial growth within the new indigenous sludge. Sludge from the co-settlement tanks was fed into the gravity belt thickeners before being pumped into the digester feed tanks. After a period of carefully introducing indigenous sludge to the digesters, they over spilled into the post digestion tanks, which enabled TOF 3 commissioning of the centrifuges and dryer, resulting in the production of granules for agricultural use. In TOF 3 the Biostyr™ plant was brought online. Full flows were now being treated on site and all ten cells were brought online together. As the biological processes established themselves, the quality improved and once all phases of the plant had stabilised compliance testing could begin. Compliance testing Compliance testing for the Cleaner Seas for Sussex Project involved completing 13 tests to a strict set of criteria. The tests ensured that SW could meet discharge consents for final effluent and odour emissions. Biological oxygen demand (BOD), chemical oxygen demand (COD), metals and suspended solids were tested to ensure that the quality of the final effluent achieved the required consent. Flow to site was also tested to ensure that the peak pass forward rate, as defined in the consent, is also achieved. Odour stack velocity and H2S concentration were also measured for compliance with planning conditions. The new treatment works is covered by one of the largest green roofs in Europe, covering almost 18,000m2 - Courtesy of Southern Water Located on the a traffic island between the carriageway of the A259, Marine Drive Pumping Station is a landmark building to the east of Brighton and Hove - Courtesy of Southern Water Sludge collected during the treatment process is treated on site, the final process of which dries this bi-product to produce a soil conditioner for agriculture in a thermal dryer - Courtesy of Southern Water Peacehaven Inlet Pumping Station Courtesy of Southern Water
  • 4. www.WaterProjectsOnline.com Wastewater Treatment & Sewerage UK Water Projects 2014 Page 4 The tests were conducted over a continuous period of 28 days for successful testing to be achieved. Prior to the commencement of testing, 4D entered into a phase of pre-testing. This ensured that the tests would achieve their criteria within the 28 days without having to restart the tests. Compliance testing was completed on the March 10, 2013. Following the receipt of all accredited sampling two weeks later the compliance test report was handed to SW to review, signed off as complete one week later, achieving the consent deadline. By holding daily meetings between 4D and Southern Water, 4D was able to react to any problems/risks we were faced with and reviewed progress towards completing any actions raised. These meetings allowed 4D to keep a running tally of completed days and tests without having to review them at the end. By involving SW prior to entering into compliance testing and conducting 100% pre-testing, 4D was able to provide SW with confidence that the tests would achieve the criteria within the period. Take over testing In a similar fashion to compliance testing, Take Over Testing (ToT) comprised of 44 tests running over a 28 day period, testing every part of the infrastructure and treatment works. Some of these were repeats of the tests seen in compliance testing, howeverToT looked into the operation and reliability of the plant as well as the quality for water and sludge processes. A pre-test period occurred before entering into test. Incorporating lessons learnt from compliance testing; SW had a major role during the test period. Methodologies were presented to SW for approval before entering into the test. This ensured that they understood how the tests were being conducted and how the results would be presented. Daily meetings were held between 4D and SW during the test period where plant performance was reviewed, sampling, alarms, events and other tests results were discussed and approved at this meeting. Events of that day, previous and the next day were reviewed as well to ensure that all parties knew what was occurring and representatives could be arranged for witnessing. On October 10, 2013, ToT began and was achieved on the December 19, 2013, except for a few areas where the plant still had to be tested, because sludge and cess imports were not at that stage being received on-site. This meant they couldn’t be done within the original test period and were therefore tested when the programme of works was completed. SW and 4D worked collaboratively for a successful resolution of these delayed areas and allowed the ToT to begin for the rest of the site while this work was on-going. Examples of the take over tests Test T23 was a repeat from compliance testing; 4D worked with Southern Water to define exactly how it would be carried out and what it entailed. With agreement 4D hired specialists from RPS to perform velocity measurements across the odour stack and report back their findings. The velocity achieved the criteria. From the results it was possible to determine a coefficient which can be applied to the flow meter of the fans for the stack, SW agreed that this method for ToT. This enabled 4D to save cost by not having to hire the contractor again and time by not having to wait for the results to be presented. TestT30 tested the reliability of the plant.This test would fail should any process stream be unavailable for more than 1% of the test period. Since the whole works was included in this test, a permit regime was strictly enforced to manage planned maintenance. Daily alarms and events were used to measure the unavailability. A biological aerated flooded filter (BAFF) provides the final stage of wastewater treatment at Peacehaven WwTW - Courtesy of Southern Water
  • 5. www.WaterProjectsOnline.com Wastewater Treatment & Sewerage UK Water Projects 2014 Page 5 More than 100 people attending the project’s was formal opening on 14 October 2013 - Courtesy of Southern Water Media were shown the site as part of the formal opening of the project Courtesy of Southern Water Test # Specific Test Performance criteria Type of sample Sampling point Frequency of sampling # of allowable failures T23 Odour control stack velocity A velocity not less than that assumed in the odour dispersion modelling (21m/s) and not less than 15m/s at average air flow rates Spot reading Ventilation system operating at average discharge rate Until reliable readings obtained 0 T30 Plant reliability Not more than 1% unavailability of any process stream or operation during the 28 day test period. Operational records Operational records Continuous 0 T35 WTW hydraulic profile and performance verification Water levels in process units, chambers and channels shall not exceed design levels. Level sensors/SCADA and supplementary water level measurement as necessary to demonstrate compliance. Throughout the water line of the WTW Up to 4 times (at least once to coincide with maximum flow or simulated maximum flow conditions). 0 The works has been designed with standby plant for nearly every item on site; as a result the test was passed with only 31 minutes of downtime out of the possible 403 minutes allowed within the 28 days’ test period. This is a good example of how day to day management alongside the client and operation staff accommodated an effective and efficient test period. TestT35 was a guarantee to SW that what has been design and built by 4D was hydraulically correct. The methodology for this test went through a series of revisions before an agreement was made. SW worked with 4D to define and perform the test which enable the results to be agreed as measurements were taken. The contract definitions of the take over tests noted above are in the table above. Conclusion Bringing into service and testing of a new £300m wastewater treatment works and sludge treatment and recycling centre the size of the Cleaner Seas for Sussex project would normally result in considerable amount of time being spent in discussions with the client following the conclusion of the test period; generally these discussions taking longer than the tests themselves. However, Southern Water provided a site team that was both involved and engaged with all aspects of the project and as a result gained a detailed working knowledge of the plant. More than this, they were determined and worked with the same drive and enthusiasm as 4D staff to have the tests professionally completed. Furthermore, issues arising from the test were worked through quickly to the satisfaction of both parties. 4Delivery implemented a regime of 100% pre-testing to prove to themselves and the client that the test criteria would be achieved before beginning the test. This ironed out any interference factors and demonstrated that the plant would operate as expected giving confidence to all parties. Since achieving take over in December 2013, the final tests have been successfully completed and a series of performance tests commenced. With client collaboration in every step of the commissioning phase and by committing to a 100% testing strategy, 4Delivery was able to achieve hand over of this flagship project, attaining the high quality standards required while demonstrating the stability of the process. The scale and engagement of this scheme makes it a truly remarkable project that has been extensively recognised by numerous national bodies. The Editor & Publishers would like to thank Anthony Thomas, Engineer, Mike Walker, Commissioning Manager, and Iain McGregor , Project Installation and Commissioning Manager, all with 4Delivery, for providing the above article for publication. The wastewater arriving on site (left) has rag, a mixture of toilet roll, wet wipes and anything else flushed down the toilet, removed (middle) before it is treated to secondary treatment standard and released 2.5km off shore (right) - Courtesy of Southern Water
  • 6. www.paques.nl Removal of Solids, Nitrogen & Phosphorus ASTRASAND® Continuous sand filtration ASTRASEPARATOR® Compact lamella clarifier • 25 years operational experience • 3,600 units installed worldwide • Tertiary (waste)water treatment