SlideShare a Scribd company logo
1 of 25
Engineering Procurement & Project Management
Engineering Procurement & Project
Management
O&M ACTIVITIES
Engineering Procurement & Project Management
 EPC contractor with more than 30 years of
experience
 Certified for an Integrated QHSE Management
System
ISO 9001: 2015 – ISO 14001:2015- ISO
45001:2018
 Registered and active in several MEA
countries
EPPM PROFILE
 Created in Tunis, 1993
 Certified for Security Information
Management System ISO 27001
Engineering Procurement & Project Management
Gathering System,
Pipeline,
Oil & Gas processing
plant,
Storage Facilities,
Oily water Treatment,
Water Injection,
Refinery
Oil & Gas
Desalination
Purification,
Potabilization,
Oil removal,
Remineralization,
Waste Management,
Sludge Treatment
Water
& Environment
Energy
& Renewable Energy
FIELDS OF ACTIVITIES
Industry
Fertilising plants
Cement plants
Manufacturing
Agro and Pharmaceutical
Conventional /
Power plants
Photovoltaic
Bio-Gas
EPPM IN NUMBERS
Offices Worldwide
Years of Experience
Industry Sectors
30
12 04
Turnover Projects
Clients
150M
USD
+250
+50
Engineering Procurement & Project Management
Engineering Procurement & Project Management
PROJECT TYPES
EPPM is involved in several Types of Projects such as:
Engineering Design & Consultancy
PMC Projects : Project Management & Consultancy
EPCC Projects : Engineering, Procurement, Construction &
Commissioning
Commissioning, Operation & Maintenance Projects
Investment Projects :
- BOT “Build Own Transfer”
- BOO “Build Own Operate”
- Leasing projects
EPPM GROUP
Engineering Procurement & Project Management
Complementary
activities
Middle East
Africa Investment
Companies
EPPM SERVICES
COMMUNICATION
MANAGEMENT
HUMAN
RESOURCES
MANAGEMENT
SCHEDULE
MANAGEMENT
STAKEHOLDER
MANAGEMENT
RISK
MANAGEMENT
SCOPE
MANAGEMENT
PROCUREMENT
MANAGEMENT
QUALITY
MANAGEMENT
COST
MANAGEMENT
INTEGRATION
MANAGEMENT
PROJECT MANAGEMENT
Engineering Procurement & Project Management
ENGINEERING CAPABILITIES
Multidisciplinary Engineering Services,
Engineering Annual capacity 400 000 to 500 000 man-hours / year
Using the state of the art software,
Using “Electronic Documents Management System” to digitalize validation
process (internal & External) of all technical documents.
Engineering Procurement & Project Management
EPPM has created the R&D Department as extension to it’s design
capabilities, which aims to provide added value to ongoing projects, to
promote and support technological research, and to develop new fields of
activities for the group, mainly in :
Renewable Energies,
Water treatment,
Agriculture,
Food,
Bio Resources,
New building materials,…
With partnership involving local and foreign
research centers (public and private).
RESEARCH & DEVELOPMENT
Engineering Procurement & Project Management
Suppliers Prequalification and Assessment
Supply Chain Management (Negotiation, Expediting, Project deadlines, Packing &
Transport Survey, Transportation, Custom Clearance, inventory management and
warehousing, Etc.),
Negotiation and Contracts Finalisation,
Production Control,
Project QHSE Requirements,
Quality Control.
To manage procurement services, EPPM opts for updated solutions :
- E-Procurement Suppliers management, Inquiry cycle, Bids, Technical evaluation,
evaluation, Purchasing, PO history.
- 2IPS (Industrial Integrated Procurement System): inquiry process, purchasing process,
Receiving cycle.
PROCUREMENT
Engineering Procurement & Project Management
CONSTRUCTION
Construction Management :
Site Engineering
Elaboration of Method Statement
Coordination and Supervision
Reporting (daily, weekly and monthly)
Quality Assurance / Quality Control
HSE Supervision
Interface Management with local content.
Construction Works :
Mechanical : equipment installation & fitting
Piping Works : welding, erection, tests …
Electrical : equipment installation, cable laying & connections (LV, MV & HV)
Instrumentation Works : Instrument installation, Control System, Installation (SCADA,
PLC).
Engineering Procurement & Project Management
COMMISSIONING & START-UP
Pre-Commissioning procedures, Commissioning
Interface Management with Deign office
Commissioning resources assignment and mobilization
FAT & SAT
Coordination of commissioning tests
Development of the QA / QC of Commissioning
Mobilization of Construction Team and Technicians, Vendors
Preparation of the test and closing reports
Training plan preparation, provide field and classroom training sessions to Clients
After market and liability warranty services management.
Engineering Procurement & Project Management
OPERATION & MAINTENANCE
Elaboration of Operation and Maintenance manuals,
Production operation assistance
Maintenance activities of offshore and onshore plants,
Additional services :
Maintenance build: Asset register, maintenance task lists, maintenance plan,
Preparing maintenance plans in accordance with RCM and SCE analysis.
- Facilites management,
- Logistic , procurement and spare-parts management,
- Preparation, planning and management of major overhauls
Engineering Procurement & Project Management
O & M REFERENCES
Scope of Work
Engineering Procurement & Project Management
Project: Juaymah Terminal
Contenairized Waste Water
Treatment Plant
Objective: Reduce the impact of
waste water on the environment.
Location: Juaymah- Saudi
Arabia
Construct, Operate, and maintain for 3 years of a produced oily
water treatment system to treat the wastewater collected in Juaymah
Tank Farm evaporation pond, for disposal into the marine environment.
Supply of spare parts
Supply of chemicals
Scope of Work
Engineering Procurement & Project Management
Project: Upgrade of Biological
Treatment in IWTP 8
Objective: Improve treated water
quality of IWTP and absorb
excess water flowrate above the
existing plant design capacity.
Location: Jubail Industrial city -
Saudi Arabia
Construct, Operate, and maintain for 5 years period by installing Biological
process upgrading system to treat 50 000 m3/day of Industrial Waste water
Treatment Plant through HYBAC System:
Hybacs Area: Hybacs, Blower & Piping Installation & MCC & PLC
Installation & Connection, Handrails & Steel Stairs installation, control
room,…
Chemical Injection Skids
Scope of Work
The treated water is characterized as follows:
 Hydrocarbon Elimination (< 10 mg/l),
 Elimination of other materials (20 mg/l),
 Elimination of solid materials,
 Water filtration: 25 microns.
Phase 1: Revamping of all equipment & installations, during 2 years,
including engineering, procurement, installations and commissioning.
Phase 2: 3 years of Operation and Maintenance including :
 Existing equipment Revamping and Maintenance,
 Operation follow-up,
 Quality control of treated water,
 Procurement of the chemical and lubricant products,
 Procurement of the necessary equipment to the maintenance,
 Recommendation of the necessary spare parts,
Engineering Procurement & Project Management
Project : Revamping,
maintenance and operation of 02
Oily Water Treatment plants
(EPCO)
Capacity
• CINA Site : 6000 m3/day
• CIS Site : 8000 m3/day
Objective: Reduce the impact of
oily water on the environment.
Location: Hassi Messaoud -
Algeria
Scope of Work
Client : SONATRACH
Project : Revamping, maintenance
and operation of 03 Oily Water
Treatment plants (EPCO Project)
Capacity
Objective: Reduce the impact of oily
water on the environment
Location: Haoudh Barkaoui – Algeria
• Haoudh Berkaoui Site: 2400
m3/day
• Belkahla Site : 960 m3/day
• Guellala Site : 1440 m3/day
The treated water is characterized as follows :
 Mes < 20 ppm
 HC < 5 ppm
 Sulfato-reducing bacteria < 100 germs
Engineering Procurement & Project Management
Phase 1: Revamping of all equipment & installations, during 1 year,
including engineering, procurement, installations and commissioning.
Phase 2: 4 years of Operation and Maintenance including :
 Existing equipment Revamping and Maintenance,
 Operation follow-up,
 Quality control of treated water,
 Procurement of the chemical and lubricant products,
 Procurement of the necessary equipment to the maintenance,
 Recommendation of the necessary spare parts,
Scope of Work
Client : SOMOIL
Project : Maintenance Services of
FS/FST Associations
Objective: Guarantee continuity of
production platforms and the transfer of
production from offshore and onshore
production (FS / FST) to Block 3
Sonangol.
Location: Soyo - Angola
Preventive, and corrective maintenance, obsolescence equipment study and
replacement, new equipment and packages installation and integration, and
many improvements within the operation field under 4 years maintenance
service agreement (with extension period):
Rotating machines : Generators, gas compressors, electric pumps, air
compressors, …
Static Equipment: Treaters, separator, air and gas vessels, piping,
Repair leaks on piping: Welding, renewing, etc…
Control and measuring instruments : Flow metering, level control, Control
system, etc… (Foxborro, fisher, rosemount etc…) ,
Power Management & Electrical Equipment: all kinds of panels,
Field Safety Equipment
Engineering Procurement & Project Management
Scope of Work
Client : SOMOIL
Project : Offshore Maintenance
Services Bloc 2/05 platforms
Production Capacity : 12 500 BPD
Objective: Maintain all productive
equipment including ; rotating
machinery on all platforms and
satellites in block 2/05 to ensure
continuity of platform production.
Location: Soyo - Angola
Preventive, and corrective maintenance, obsolescence equipment study
and replacement, new equipment and packages installation and
integration, and many improvements within the operation field under 4
years maintenance service agreement (with extension period):
Engineering Procurement & Project Management
Rotative equipment: Pumps, Generators, air & gas compressor, etc.
Static equipment: Theaters, Separators, air & gas vessels, piping,
valves, etc.
Field Process Control Equipment : Valves i.e. SDV, ESDV, BDV,
Pressure and Relief Safety valves, etc.
Control and measuring instruments : Level, pressure, temperature
and flow measurement
Power Management & Electrical Equipment
Field Safety Equipment
Scope of Work :
BOT “Build Own Transfer”
30-years
Client: Ministry of Hydrocarbons
Project: Kivu Lake methane gas
exploitation for electricity production
Objective: Generate electricity from the
extraction of methane gas
Location: Democratic Republic of
Congo
30-years BOT project consists of:
Extract, process, transport and store methane gas from KIVU
Lake,
Build a power station with an installed capacity of 30 MW
operating on fuel oil and methane gas and ensure its operation
and maintenance for a period of 27 years and 03 months,
Build energy transmission lines (high, medium and low-voltage)
and associated stations to interconnect [possibly] with-existing
networks,
Sell all electricity generated at [SNEL]
Engineering Procurement & Project Management
MINISTERE DES HYDROCARBURES
Phase 1 : Realization of a photovoltaic power plant of 10 MW with
string inverters and tracker system, the project consists on :
• Engineering Services,
• Project Management,
• Procurement of all necessary equipment,
• Construction of photovoltaic plant,
• Commissioning & Start-up,
Phase 2 : 20 years of station operation.
Scope of Work
Client: STEG
Project: Production of electricity from
photovoltaic solar energy; Meknassy 10
MW.
Location: Meknassy - Tunisia
Objective: Production of electricity
from photovoltaic solar energy.
BOO “Build Own Operate”
20-years
Engineering Procurement & Project Management
WHO TRUST US
Engineering Procurement & Project Management
Silver Street - Fatma Building - Lake gardens -1053 -Tunis -TUNISIA
Tel. +216 71 16 81 00 Fax. +216 71 19 09 18
www.eppm.com.tn eppm@eppm.com.tn
Engineering Procurement & Project Management

More Related Content

Similar to EPPMPresentationOMOct22 (1).pptx

Interaction sharing my experience
Interaction   sharing my experienceInteraction   sharing my experience
Interaction sharing my experienceSamir Dave
 
Mohammad Rehan Akbar Khan 2- CV
Mohammad Rehan Akbar Khan 2- CVMohammad Rehan Akbar Khan 2- CV
Mohammad Rehan Akbar Khan 2- CVRehan Khan
 
Yahia Eisa- pipeline technical specialist
Yahia Eisa- pipeline technical specialistYahia Eisa- pipeline technical specialist
Yahia Eisa- pipeline technical specialistYahia Ibrahim
 
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...dun yang
 
Resume-Thomas Mathew
Resume-Thomas MathewResume-Thomas Mathew
Resume-Thomas MathewThomas Mathew
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentationRiaz Zalil
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARSAQIB MANIAR
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R S Rajaram
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R S Rajaram
 
My CV, Shahar Ali tuhin
My CV, Shahar Ali tuhinMy CV, Shahar Ali tuhin
My CV, Shahar Ali tuhinMohammed ali
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARSAQIB MANIAR
 
VFDFVFDV
VFDFVFDVVFDFVFDV
VFDFVFDVdfdfdf7
 

Similar to EPPMPresentationOMOct22 (1).pptx (20)

Rimon forclients 62016
Rimon forclients 62016Rimon forclients 62016
Rimon forclients 62016
 
Resume 2016 nadeem siddiqui
Resume   2016 nadeem siddiquiResume   2016 nadeem siddiqui
Resume 2016 nadeem siddiqui
 
Interaction sharing my experience
Interaction   sharing my experienceInteraction   sharing my experience
Interaction sharing my experience
 
Mohammad Rehan Akbar Khan 2- CV
Mohammad Rehan Akbar Khan 2- CVMohammad Rehan Akbar Khan 2- CV
Mohammad Rehan Akbar Khan 2- CV
 
RobertKulick_2016
RobertKulick_2016RobertKulick_2016
RobertKulick_2016
 
Yahia Eisa- pipeline technical specialist
Yahia Eisa- pipeline technical specialistYahia Eisa- pipeline technical specialist
Yahia Eisa- pipeline technical specialist
 
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
 
RobertKulick2016
RobertKulick2016RobertKulick2016
RobertKulick2016
 
Resume-Thomas Mathew
Resume-Thomas MathewResume-Thomas Mathew
Resume-Thomas Mathew
 
CV_2016_rev_4_RW
CV_2016_rev_4_RWCV_2016_rev_4_RW
CV_2016_rev_4_RW
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
JUNDEE MAR TEJEDO
JUNDEE MAR TEJEDOJUNDEE MAR TEJEDO
JUNDEE MAR TEJEDO
 
Moh.Ramadan-CV
Moh.Ramadan-CVMoh.Ramadan-CV
Moh.Ramadan-CV
 
My CV, Shahar Ali tuhin
My CV, Shahar Ali tuhinMy CV, Shahar Ali tuhin
My CV, Shahar Ali tuhin
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
VFDFVFDV
VFDFVFDVVFDFVFDV
VFDFVFDV
 

More from Hedi Ben Mohamed

SYSTEME DE SECURITE INCENDIE (NF-SSI).pdf
SYSTEME DE SECURITE INCENDIE (NF-SSI).pdfSYSTEME DE SECURITE INCENDIE (NF-SSI).pdf
SYSTEME DE SECURITE INCENDIE (NF-SSI).pdfHedi Ben Mohamed
 
Fire Gas System Specification (1).pdf
Fire  Gas System Specification (1).pdfFire  Gas System Specification (1).pdf
Fire Gas System Specification (1).pdfHedi Ben Mohamed
 
A_Basics_of_Explosion_Protection_HAZARDO.pdf
A_Basics_of_Explosion_Protection_HAZARDO.pdfA_Basics_of_Explosion_Protection_HAZARDO.pdf
A_Basics_of_Explosion_Protection_HAZARDO.pdfHedi Ben Mohamed
 
SI_SK. securite incendie.pdf
SI_SK. securite incendie.pdfSI_SK. securite incendie.pdf
SI_SK. securite incendie.pdfHedi Ben Mohamed
 
dokumen.tips_download-wastewater-mng-module-4-powerpoint-file.ppt
dokumen.tips_download-wastewater-mng-module-4-powerpoint-file.pptdokumen.tips_download-wastewater-mng-module-4-powerpoint-file.ppt
dokumen.tips_download-wastewater-mng-module-4-powerpoint-file.pptHedi Ben Mohamed
 
Ei 1540 design_construction_commissionin (2)
Ei 1540 design_construction_commissionin (2)Ei 1540 design_construction_commissionin (2)
Ei 1540 design_construction_commissionin (2)Hedi Ben Mohamed
 
Guide des-travaux-à-proximité-des-installations-de-gaz-naturel-2013
Guide des-travaux-à-proximité-des-installations-de-gaz-naturel-2013Guide des-travaux-à-proximité-des-installations-de-gaz-naturel-2013
Guide des-travaux-à-proximité-des-installations-de-gaz-naturel-2013Hedi Ben Mohamed
 
Arrete inter mininst_elect_14-07-2011
Arrete inter mininst_elect_14-07-2011Arrete inter mininst_elect_14-07-2011
Arrete inter mininst_elect_14-07-2011Hedi Ben Mohamed
 

More from Hedi Ben Mohamed (13)

SYSTEME DE SECURITE INCENDIE (NF-SSI).pdf
SYSTEME DE SECURITE INCENDIE (NF-SSI).pdfSYSTEME DE SECURITE INCENDIE (NF-SSI).pdf
SYSTEME DE SECURITE INCENDIE (NF-SSI).pdf
 
Fire Gas System Specification (1).pdf
Fire  Gas System Specification (1).pdfFire  Gas System Specification (1).pdf
Fire Gas System Specification (1).pdf
 
foam tank _df_pid01.pdf
foam tank _df_pid01.pdffoam tank _df_pid01.pdf
foam tank _df_pid01.pdf
 
A_Basics_of_Explosion_Protection_HAZARDO.pdf
A_Basics_of_Explosion_Protection_HAZARDO.pdfA_Basics_of_Explosion_Protection_HAZARDO.pdf
A_Basics_of_Explosion_Protection_HAZARDO.pdf
 
SI_SK. securite incendie.pdf
SI_SK. securite incendie.pdfSI_SK. securite incendie.pdf
SI_SK. securite incendie.pdf
 
dokumen.tips_download-wastewater-mng-module-4-powerpoint-file.ppt
dokumen.tips_download-wastewater-mng-module-4-powerpoint-file.pptdokumen.tips_download-wastewater-mng-module-4-powerpoint-file.ppt
dokumen.tips_download-wastewater-mng-module-4-powerpoint-file.ppt
 
METHANE REGENERATION.pptx
METHANE REGENERATION.pptxMETHANE REGENERATION.pptx
METHANE REGENERATION.pptx
 
Présentation OSCAR.pptx
Présentation OSCAR.pptxPrésentation OSCAR.pptx
Présentation OSCAR.pptx
 
topic5 (1).ppt
topic5 (1).ppttopic5 (1).ppt
topic5 (1).ppt
 
Ei 1540 design_construction_commissionin (2)
Ei 1540 design_construction_commissionin (2)Ei 1540 design_construction_commissionin (2)
Ei 1540 design_construction_commissionin (2)
 
Hac ei1540 (2)
Hac ei1540 (2)Hac ei1540 (2)
Hac ei1540 (2)
 
Guide des-travaux-à-proximité-des-installations-de-gaz-naturel-2013
Guide des-travaux-à-proximité-des-installations-de-gaz-naturel-2013Guide des-travaux-à-proximité-des-installations-de-gaz-naturel-2013
Guide des-travaux-à-proximité-des-installations-de-gaz-naturel-2013
 
Arrete inter mininst_elect_14-07-2011
Arrete inter mininst_elect_14-07-2011Arrete inter mininst_elect_14-07-2011
Arrete inter mininst_elect_14-07-2011
 

Recently uploaded

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

EPPMPresentationOMOct22 (1).pptx

  • 1. Engineering Procurement & Project Management Engineering Procurement & Project Management O&M ACTIVITIES
  • 2. Engineering Procurement & Project Management  EPC contractor with more than 30 years of experience  Certified for an Integrated QHSE Management System ISO 9001: 2015 – ISO 14001:2015- ISO 45001:2018  Registered and active in several MEA countries EPPM PROFILE  Created in Tunis, 1993  Certified for Security Information Management System ISO 27001
  • 3. Engineering Procurement & Project Management Gathering System, Pipeline, Oil & Gas processing plant, Storage Facilities, Oily water Treatment, Water Injection, Refinery Oil & Gas Desalination Purification, Potabilization, Oil removal, Remineralization, Waste Management, Sludge Treatment Water & Environment Energy & Renewable Energy FIELDS OF ACTIVITIES Industry Fertilising plants Cement plants Manufacturing Agro and Pharmaceutical Conventional / Power plants Photovoltaic Bio-Gas
  • 4. EPPM IN NUMBERS Offices Worldwide Years of Experience Industry Sectors 30 12 04 Turnover Projects Clients 150M USD +250 +50 Engineering Procurement & Project Management
  • 5. Engineering Procurement & Project Management PROJECT TYPES EPPM is involved in several Types of Projects such as: Engineering Design & Consultancy PMC Projects : Project Management & Consultancy EPCC Projects : Engineering, Procurement, Construction & Commissioning Commissioning, Operation & Maintenance Projects Investment Projects : - BOT “Build Own Transfer” - BOO “Build Own Operate” - Leasing projects
  • 6. EPPM GROUP Engineering Procurement & Project Management Complementary activities Middle East Africa Investment Companies
  • 9. ENGINEERING CAPABILITIES Multidisciplinary Engineering Services, Engineering Annual capacity 400 000 to 500 000 man-hours / year Using the state of the art software, Using “Electronic Documents Management System” to digitalize validation process (internal & External) of all technical documents. Engineering Procurement & Project Management
  • 10. EPPM has created the R&D Department as extension to it’s design capabilities, which aims to provide added value to ongoing projects, to promote and support technological research, and to develop new fields of activities for the group, mainly in : Renewable Energies, Water treatment, Agriculture, Food, Bio Resources, New building materials,… With partnership involving local and foreign research centers (public and private). RESEARCH & DEVELOPMENT Engineering Procurement & Project Management
  • 11. Suppliers Prequalification and Assessment Supply Chain Management (Negotiation, Expediting, Project deadlines, Packing & Transport Survey, Transportation, Custom Clearance, inventory management and warehousing, Etc.), Negotiation and Contracts Finalisation, Production Control, Project QHSE Requirements, Quality Control. To manage procurement services, EPPM opts for updated solutions : - E-Procurement Suppliers management, Inquiry cycle, Bids, Technical evaluation, evaluation, Purchasing, PO history. - 2IPS (Industrial Integrated Procurement System): inquiry process, purchasing process, Receiving cycle. PROCUREMENT Engineering Procurement & Project Management
  • 12. CONSTRUCTION Construction Management : Site Engineering Elaboration of Method Statement Coordination and Supervision Reporting (daily, weekly and monthly) Quality Assurance / Quality Control HSE Supervision Interface Management with local content. Construction Works : Mechanical : equipment installation & fitting Piping Works : welding, erection, tests … Electrical : equipment installation, cable laying & connections (LV, MV & HV) Instrumentation Works : Instrument installation, Control System, Installation (SCADA, PLC). Engineering Procurement & Project Management
  • 13. COMMISSIONING & START-UP Pre-Commissioning procedures, Commissioning Interface Management with Deign office Commissioning resources assignment and mobilization FAT & SAT Coordination of commissioning tests Development of the QA / QC of Commissioning Mobilization of Construction Team and Technicians, Vendors Preparation of the test and closing reports Training plan preparation, provide field and classroom training sessions to Clients After market and liability warranty services management. Engineering Procurement & Project Management
  • 14. OPERATION & MAINTENANCE Elaboration of Operation and Maintenance manuals, Production operation assistance Maintenance activities of offshore and onshore plants, Additional services : Maintenance build: Asset register, maintenance task lists, maintenance plan, Preparing maintenance plans in accordance with RCM and SCE analysis. - Facilites management, - Logistic , procurement and spare-parts management, - Preparation, planning and management of major overhauls Engineering Procurement & Project Management
  • 15. O & M REFERENCES
  • 16. Scope of Work Engineering Procurement & Project Management Project: Juaymah Terminal Contenairized Waste Water Treatment Plant Objective: Reduce the impact of waste water on the environment. Location: Juaymah- Saudi Arabia Construct, Operate, and maintain for 3 years of a produced oily water treatment system to treat the wastewater collected in Juaymah Tank Farm evaporation pond, for disposal into the marine environment. Supply of spare parts Supply of chemicals
  • 17. Scope of Work Engineering Procurement & Project Management Project: Upgrade of Biological Treatment in IWTP 8 Objective: Improve treated water quality of IWTP and absorb excess water flowrate above the existing plant design capacity. Location: Jubail Industrial city - Saudi Arabia Construct, Operate, and maintain for 5 years period by installing Biological process upgrading system to treat 50 000 m3/day of Industrial Waste water Treatment Plant through HYBAC System: Hybacs Area: Hybacs, Blower & Piping Installation & MCC & PLC Installation & Connection, Handrails & Steel Stairs installation, control room,… Chemical Injection Skids
  • 18. Scope of Work The treated water is characterized as follows:  Hydrocarbon Elimination (< 10 mg/l),  Elimination of other materials (20 mg/l),  Elimination of solid materials,  Water filtration: 25 microns. Phase 1: Revamping of all equipment & installations, during 2 years, including engineering, procurement, installations and commissioning. Phase 2: 3 years of Operation and Maintenance including :  Existing equipment Revamping and Maintenance,  Operation follow-up,  Quality control of treated water,  Procurement of the chemical and lubricant products,  Procurement of the necessary equipment to the maintenance,  Recommendation of the necessary spare parts, Engineering Procurement & Project Management Project : Revamping, maintenance and operation of 02 Oily Water Treatment plants (EPCO) Capacity • CINA Site : 6000 m3/day • CIS Site : 8000 m3/day Objective: Reduce the impact of oily water on the environment. Location: Hassi Messaoud - Algeria
  • 19. Scope of Work Client : SONATRACH Project : Revamping, maintenance and operation of 03 Oily Water Treatment plants (EPCO Project) Capacity Objective: Reduce the impact of oily water on the environment Location: Haoudh Barkaoui – Algeria • Haoudh Berkaoui Site: 2400 m3/day • Belkahla Site : 960 m3/day • Guellala Site : 1440 m3/day The treated water is characterized as follows :  Mes < 20 ppm  HC < 5 ppm  Sulfato-reducing bacteria < 100 germs Engineering Procurement & Project Management Phase 1: Revamping of all equipment & installations, during 1 year, including engineering, procurement, installations and commissioning. Phase 2: 4 years of Operation and Maintenance including :  Existing equipment Revamping and Maintenance,  Operation follow-up,  Quality control of treated water,  Procurement of the chemical and lubricant products,  Procurement of the necessary equipment to the maintenance,  Recommendation of the necessary spare parts,
  • 20. Scope of Work Client : SOMOIL Project : Maintenance Services of FS/FST Associations Objective: Guarantee continuity of production platforms and the transfer of production from offshore and onshore production (FS / FST) to Block 3 Sonangol. Location: Soyo - Angola Preventive, and corrective maintenance, obsolescence equipment study and replacement, new equipment and packages installation and integration, and many improvements within the operation field under 4 years maintenance service agreement (with extension period): Rotating machines : Generators, gas compressors, electric pumps, air compressors, … Static Equipment: Treaters, separator, air and gas vessels, piping, Repair leaks on piping: Welding, renewing, etc… Control and measuring instruments : Flow metering, level control, Control system, etc… (Foxborro, fisher, rosemount etc…) , Power Management & Electrical Equipment: all kinds of panels, Field Safety Equipment Engineering Procurement & Project Management
  • 21. Scope of Work Client : SOMOIL Project : Offshore Maintenance Services Bloc 2/05 platforms Production Capacity : 12 500 BPD Objective: Maintain all productive equipment including ; rotating machinery on all platforms and satellites in block 2/05 to ensure continuity of platform production. Location: Soyo - Angola Preventive, and corrective maintenance, obsolescence equipment study and replacement, new equipment and packages installation and integration, and many improvements within the operation field under 4 years maintenance service agreement (with extension period): Engineering Procurement & Project Management Rotative equipment: Pumps, Generators, air & gas compressor, etc. Static equipment: Theaters, Separators, air & gas vessels, piping, valves, etc. Field Process Control Equipment : Valves i.e. SDV, ESDV, BDV, Pressure and Relief Safety valves, etc. Control and measuring instruments : Level, pressure, temperature and flow measurement Power Management & Electrical Equipment Field Safety Equipment
  • 22. Scope of Work : BOT “Build Own Transfer” 30-years Client: Ministry of Hydrocarbons Project: Kivu Lake methane gas exploitation for electricity production Objective: Generate electricity from the extraction of methane gas Location: Democratic Republic of Congo 30-years BOT project consists of: Extract, process, transport and store methane gas from KIVU Lake, Build a power station with an installed capacity of 30 MW operating on fuel oil and methane gas and ensure its operation and maintenance for a period of 27 years and 03 months, Build energy transmission lines (high, medium and low-voltage) and associated stations to interconnect [possibly] with-existing networks, Sell all electricity generated at [SNEL] Engineering Procurement & Project Management MINISTERE DES HYDROCARBURES
  • 23. Phase 1 : Realization of a photovoltaic power plant of 10 MW with string inverters and tracker system, the project consists on : • Engineering Services, • Project Management, • Procurement of all necessary equipment, • Construction of photovoltaic plant, • Commissioning & Start-up, Phase 2 : 20 years of station operation. Scope of Work Client: STEG Project: Production of electricity from photovoltaic solar energy; Meknassy 10 MW. Location: Meknassy - Tunisia Objective: Production of electricity from photovoltaic solar energy. BOO “Build Own Operate” 20-years Engineering Procurement & Project Management
  • 24. WHO TRUST US Engineering Procurement & Project Management
  • 25. Silver Street - Fatma Building - Lake gardens -1053 -Tunis -TUNISIA Tel. +216 71 16 81 00 Fax. +216 71 19 09 18 www.eppm.com.tn eppm@eppm.com.tn Engineering Procurement & Project Management