SlideShare a Scribd company logo
1 of 6
Download to read offline
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 4 Ver. III (Jul. - Aug. 2015), PP 01-06
www.iosrjournals.org
DOI: 10.9790/1684-12430106 www.iosrjournals.org 1 | Page
Productivity Improvement in Assembly Line of an Automobile
Industry
Nikhil Verma 1
Pulkit Trivedi 2
Vivek Agnihotri 3
1, 2,
Student (Department Of Mechanical Engineering,, S.R.M.G.P.C College,Lucknow/U.P.Technical
University, India)
3
Astt.Professor (Department Of Mechanical Engineering,, S.R.M.G.P.C College,Lucknow/U.P.Technical
University, India)
Abstract : Many factors are responsible in the successful operation and efficient working of a unit. To govern
these factors work techniques are discovered. This gives an exposure to two of the technique employed in the
production unit for calculation of time & motion involved and optimization Along with this it helps in a better
understanding of an assembly line at the grass root level, realizing the complexity of the system & how difficult
it is to just manage a production process let alone improvise it. The analysis of the listed techniques is
implemented on two units –ADHITYA AUTOMOTIVES APPPLICATION PVT LTD, Lko and TATA MOTORS,
Lko. Production of parts and an assembly in the units have been studied in the project with regard to the
guidelines of the techniques. The aim of the project is to compare the result of both time &motion study and to
bring out which of the study is utmost beneficial in calculation of time involved in assembling of the vehicles.
Also on the improvement techniques of production which are responsible for worker fatigue and time loss. Thus
enhancing productivity and heading towards optimization. In this Project we have tried to improve the
productivity with minimizing time and distance of worker. The graph is plotted between the Motion v/s Distance
& Motion v/s Time. A Relation is established between the two and then a minimized time and distance is
calculated. The result which comes out after the calculation is a large difference in reduction of distance and
time of worker.
Keywords: time &motion study, productivity, time and distance study, assembly line.
I. I Introduction
1.1 Productivity :
The rate at which a company produces goods or services in relation to the amount of materials and
number of employees needed. This is usually expressed in ratios of inputs to outputs. That is (input) cost per
(output) good/service. For calculation purpose, expression of productivity is -:
Productivity = Output/ Input
1.1.1 :Input may be Classified as:
 Material, Machine, Man Hours, Methods, Land.
1.1.2: Output may be classified as:
 Parts & product, Services, Wastage of any type, Pollutants of any type, etc
It is quantitative relationship between what we produce and what we have spent to produce.
Productivity is nothing but reduction in wastage of resources like men, material, machine, time, space, capital
etc. It can be expressed as human efforts to produce more and more with less and less inputs of resources so that
there will be maximum distribution of benefits among maximum number of people.
1.3: Roles and Responsibilities in the project:-
 Measures and monitoring of productivity.
 Work system design, assessment and resource requirement.
 Measures and monitor productivity of plant, cascading of targets and facilitate achievements of targets.
 Based on strategy and organization structure define organizational process, systems, work flow for attaining
of plant’s objectives.
 Based on the above, defined work content and role of each position.
 Study area wise resource requirement in line with productivity targets and work assessment.
 Recommendation of manpower nos. Along with the skill and competency requirement for management
approval.
Productivity Improvement in assembly line of an Automobile industry
DOI: 10.9790/1684-12430106 www.iosrjournals.org 2 | Page
1.2 Objectives
1.2.1 Time Study
Time Study is a work Measurement technique which is involved to calculate the time of the operation
in an assembly line with the help of an instrument (stopwatch).
 Initially calculating the time of the fitments in units (Adithya Automotive Applications Pvt Ltd / TATA
MOTORS, Lucknow ).
 Preparation of summary sheet.
1.2.2 Work Study
A generic term for all those techniques which are used in the examination of human working all its
context and which lead systematically to the investigation of all the factors which effect the efficiency and
economy of the situation being reviewed in order to effect the improvement. Basically it’s a productivity raising
technique by finding out the actual work content of a process and reduces it by proposing suitable
improvements. It has two basic components viz:
a. Method Study b. Work Measurement
1.2.3 Motion Study
Motion study is a technique of analyzing the body motions employed in doing a task in order to
eliminate or reduce ineffective movements and facilitates effective movements.
• By using motion study and the principles of motion economy the task is redesigned to be more effective and
less time consuming.
• Objective of motion study is job simplification so that it is less fatiguing and less time consuming.
1.3. Productivity Improvement Techniques
Productivity improvement techniques can be applied effectively in enterprises of any size, from one-
person companies to corporations with thousands of staff.
 JIDOKA , HEIJUNKA, KAIZEN, JIT, KANBAN, POM
II. Studies At Tata Motors
2.1 Movement Description Chart
Sl.No. TASK MOVEMENT DISTANCE(m) TIME(SEC)
1 acceleratorpedal ispickedfromthe rackandplacedonthe worktable 0-1,1-0 21.6 25
2 stopperispickedfromthe rackandplacedonthe worktable 0-2,2-0 18 16
3 stoppercapispickedfromthe rackandplacedonthe worktable 0-3,3-0 12 12
4 stoppercapismounteduponthe stopper operation 0 3
5 stoppercapisassembledonthe frontendof the acceleratorpedal operation 0 10
6 stoppercapistightenedbyaspanner operation 0 3
7 stoppercapisassembledonthe backendof the acceleratorpedal operation 0 10
8 stoppercapistightenedbyaspanner operation 0 3
9 ball andball endare pickedfromthe rackandplacedonthe worktable 0-4,4-0 19.2 20
10 pinisremovedfromthe ball endandball isputintoit operation 0 5
11 pinisputbackintothe ball end operation 0 2
12 ball endsubassemblyisputintothe acceleratorpedal end operation 0 3
13 ball endishandtightenedintothe acceleratorpedal operation 0 2
14 acceleratorpedal subassemblyispickedfromthe worktable andplacedonthe subassemlyrack 0-5,5-0 2.4 10
73.2 124
Total Movement During Accelerator Pedal Sub Assembly = 73.2m
Productivity Improvement in assembly line of an Automobile industry
DOI: 10.9790/1684-12430106 www.iosrjournals.org 3 | Page
2.2 Time Description Sheet
Sl.No. TASK MOVEMENT DISTANCE(m) TIME(SEC) VA/NVA
1 acceleratorpedalispickedfromtherackandplacedontheworktable 0-1,1-0 21.6 25 NVA
2 stopperispickedfromtherackandplacedontheworktable 0-2,2-0 18 16 NVA
3 stoppercapispickedfromtherackandplacedontheworktable 0-3,3-0 12 12 NVA
4 stoppercapismounteduponthestopper operation 0 3 VA
5 stoppercapisassembledonthefrontendoftheacceleratorpedal operation 0 10 VA
6 stoppercapistightenedbyaspanner operation 0 3 VA
7 stoppercapisassembledonthebackendoftheacceleratorpedal operation 0 10 VA
8 stoppercapistightenedbyaspanner operation 0 3 VA
9 ballandballendarepickedfromtherackandplacedontheworktable 0-4,4-0 19.2 20 NVA
10 pinisremovedfromtheballendandballisputintoit operation 0 5 VA
11 pinisputbackintotheballend operation 0 2 VA
12 ballendsubassemblyisputintotheacceleratorpedalend operation 0 3 VA
13 ballendishandtightenedintotheacceleratorpedal operation 0 2 VA
14 acceleratorpedalsubassemblyispickedfromtheworktableandplacedonthesubassemlyrack 0-5,5-0 2.4 10 NVA
73.2 124
Total Time Taken=124 Sec Value Added Time=41sec Non Value Added=83sec
Final Analysis
sl.No.TASK MOVEMENT DISTANCE(m) TIME(sec) VA/NVA
1 trolley istakenfromthe standtoacceleratorpedal rack 0-1 2.4 3 NVA
2 acceleratorpedal are takenfromthe rack andkeptontothe trolley operation 0 35 NVA
3 trolley istakentothe ball andball endrack 1-4 1.8 2 NVA
4 ball andball endare are takenfromthe rack andkeptuponthe Spare hold operation 0 20 NVA
5 trolley istakentothe stopperrack 4-2 0.6 1 NVA
6 stoppersare are takenfromthe rack andkeptuponthe Spare hold operation 0 25 NVA
7 trolley istakentothe stoppercaprack 2-3 7.2 6 NVA
8 stoppercapsare are takenfromthe rack andkeptuponthe Spare hold operation 0 20 NVA
9 trolley istakenback tothe stand 3-0 20 15 NVA
10 acceleratorpedal iskeptuponthe work areaof the trolley operation 0 20 VA
11 stoppercapsare pickedfromspare holdandkeptuponthe work areaof the trolley operation 0 20 VA
12 stoppersare pickedfromspare holdandkeptuponthe work areaof the trolley operation 0 20 VA
13 stoppercapsare putuponthe stoppersandnutsare put operation 0 20 VA
14 stoppersare assembledonthe acceleratorpedal andtightenedby spanner operation 0 20 VA
15 ball andball endare are pickedfromthe Spare holdandkeptonthe work areaof the trolley operation 0 30 VA
16 pinisremovedfromthe ball endandball isinsertedintoit operation 0 100 VA
17 pinisputback onthe ball end operation 0 30 VA
18 ball andball endare assembledontothe acceleratorpedal andishandtightened operation 0 100 VA
19 the complete acceleratorpedal assembly iskeptback uponthe spare hold operation 0 20 VA
32 507
TOTAL TIME= 507sec Non Value Added= 127sec Value Added= 380sec
Before Sub Assembly (Table Was Used) (Trolley In Use)
Productivity Improvement in assembly line of an Automobile industry
DOI: 10.9790/1684-12430106 www.iosrjournals.org 4 | Page
Before After
III. Result Analysis And Discussion
The percentage decrease in time by the above study is
= (124 - 51)/124 x 100
= 58.3%
The percentage decrease in the motion of the worker is
= (73.2 – 32)/73.2 x100
=56.3%
(Here graph distance variation graph is ploteed with the help of collected data).
(On differiating the equation mentioned above and equalisisng that equation to zero,we get):
X=1.0026 X=-0.519
Where negative sign shows the reduction in time.
This shows that Time and Motion Study is the best Study for the calculation of Work and time and the content
optimizes the enhancement in the productivity.
Hence we saved a total time of 73secs and reduced the motion up to 38 m.
(This finally leading to new method to improve our production.)
Productivity Improvement in assembly line of an Automobile industry
DOI: 10.9790/1684-12430106 www.iosrjournals.org 5 | Page
Iii Studies At Adithya Automotive Applications Pvt. Ltd.
Before:
Fixture used for the Tack Welding (BEFORE)
After studying the time for the tack welding of side board sub assembly frame we found that time calculated was
111 mins.
After:
Fixture used for tack welding of 12, 14, 16 and HD model Tipper Vehicles
When the improvements were made in the fixture the calculated time was found to be 45 mins.
BEFORE AFTER
IV. Result Analysis And Discussion
Hence percentage reduction in time is given as
= (111-45)/111 x100
= 59.45%
IT, show that up to 60% time is reduced with the advancement in fixture which increased the production of
Tippers from 30 to 75 Tippers in the month.
Time Reduction 111 mins 45 45 mins
Productivity Improvement in assembly line of an Automobile industry
DOI: 10.9790/1684-12430106 www.iosrjournals.org 6 | Page
V. Problems And Suggestions
1.5 Tata Motors
Problem 1: When the accelerator pedal assembly was done the worker has to travel more distance to collect the
accelerator pedal parts and 5S was not maintained on the sub-assembly table.
Suggestion: An accelerator pedal sub assembly trolley was made to reduce the motion of worker and 5S was
maintained on the table hence productivity improved.
Problem 2: Time required for the assembly of the accelerator pedal was more and there were more Non
Varying Activities.
Suggestion: Using a trolley reduced the motion of worker as well as improved ergonomics and fatigue was also
reduced.
1.6 Aaditya Automotives Applications Pvt Ltd
Problem 1: The table was used for side board tack welding; it was only for 12 cubic meter tipper model.
Workers were having a difficulty in placing the side board on the table too.
Suggestion: A new fixture was designed to do tack welding for 12, 10, 14, and heavy duty vehicles with
different.
Problem 2: It consumes more time for side board tack welding table as there were no holding devices.
Suggestion: According to the design of new fixture the time required for the side board tack welding was
reduced with a huge difference.
VI. Conclusion
The purpose of this project was to give the idea of basic functioning of real industry. This PROJECT
has not only given an exposure to various techniques employed in production units but also has added the new
dimension to vision of knowledge. It has given the basic idea of the working of an industry and core of every
industry lie in its fundamentals MAN, MACHINE AND MATERIAL and how the cohesion between them is
needed for the smooth running of nay industrial organization. TIME has acted as the main factor to be studied.
It is therefore concluded from the study that TIME STUDY AND WORK STUDY are the techniques which can
be used to increase the productivity.
Also, the result shows a big fraction of time is being saved, hence saving time is saving money.
References
[1]. J. Fowler and J. Robinson, ―Measurement and Improvement of Manufacturing Capacity,‖ SEMATECH, Inc, 1995.
[2]. D. Sumanth, ―Productivity Engineering and Management,‖ McGraw-Hill, New York, 1994.
[3]. M. Oxenburgh, and P. Marlow, ―The Productivity Assessment Tool: Computer-Based Cost Benefit Analysis Model for the
Economic Assessment of Occupational Health and Safety Interventions in the Workplace,‖ Journal of Safety Research, ECON
Proceedings Paper, 2005, pp. 209-214.
[4]. N. Van Hop, N. Sumate and N. Sitawatch, ―Modifying Integrated Model for Manufacturing Process Improvement,‖ Proceedings of
the International Conference on Simulation and Modeling, 2005, pp. 38-47.
[5]. W. Yung, ―An Integrated Model for Manufacturing Process Improvement,‖ European Journal of Operational Research, No. 61,
1996, pp. 39-43.
[6]. R. Radharamanan, L. P. Godoy and K. I. Watanabe, ―Quality and Productivity Improvement in a Custom- Made Furniture Industry
Using Kaizen,‖ Computers & Industrial Engineering, Vol. 31, No. 1-2, 1996, pp. 471- 474. doi:10.1016/0360-8352(96)00177-5
[7]. S. Huang, J. Dismukes, J. Shi, Q. Su, M. Razzak, R. Bodhale and D. Robinson, ―Manufacturing Productivity Improvement Using
Effectiveness Metric and Simulation Analysis,‖ International Journal of Production Research, Vol. 41, No. 3, 2003, pp. 513-527.
doi:10.1080/0020754021000042391
[8]. F. Andris and N. Benjamin, ―Method Standard and Work Design,‖ 11th Edition, McGraw-Hill, New York & London, 2004, pp.
335-348.
[9]. R. N. Mefford, ―Increasing Productivity in Global Firms: The CEO Challenge,‖ Journal of International Management, Vol. 15, No.
3, 2009, pp. 262-272. doi:10.1016/j.intman.2008.12.004
[10]. P. Kuhlang, T. Edtmayr and W. Sihn, ―Methodical Approach to Increase Productivity and Reduce Lead Time in Assembly and
Production-Logistic Processes,‖ CIRP Journal of Manufacturing Science and Technology, in Press, 2011, Available Online.
doi:10.1016/j.cirpj.2011.02.001
[11]. R. H. A. Seidel and G. Arndt, ―Productivity Improvement in Job Shop Production,‖ CIRP Annals—Manufacturing Technology,
Vol. 37, No. 1, 1988, pp. 421-424.
[12]. Gunasekaran, A. R. Korukonda, I. Virtanen and P. Yli-Olli, ―Improving Productivity and Quality in Manufacturing Organizations,‖
International Journal of Production Economics, Vol. 36, No. 2, 1994, pp. 69-183. doi:10.1016/0925-5273(94)90022-1
[13]. R. Maruta, ―Transforming Knowledge Workers into Innovation Workers to Improve Corporate Productivity,‖ Knowledge-Based
Systems, in Press, 2011, Available Online. doi:10.1016/j.knosys.2011.06.017
[14]. R. Mayer, ―Production of Operations Management,‖ 3rd Edition, McGraw-Hill, New York & London, 1975, pp 516-517.

More Related Content

What's hot

Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...eSAT Journals
 
Case 621 g zbar eh, new cab tier2 wheel loader service repair manual [fnh06...
Case 621 g zbar   eh, new cab tier2 wheel loader service repair manual [fnh06...Case 621 g zbar   eh, new cab tier2 wheel loader service repair manual [fnh06...
Case 621 g zbar eh, new cab tier2 wheel loader service repair manual [fnh06...ujdjkkskmme
 
Workstation redesign
Workstation redesignWorkstation redesign
Workstation redesignParth Shukla
 
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET Journal
 
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...Journal For Research
 
Ie microsoft office power point presentation
Ie  microsoft office power point presentationIe  microsoft office power point presentation
Ie microsoft office power point presentationShamim Hasan
 
Vibration Analysis of a Centrifugal Pump
Vibration Analysis of a Centrifugal PumpVibration Analysis of a Centrifugal Pump
Vibration Analysis of a Centrifugal PumpIRJET Journal
 

What's hot (7)

Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...
 
Case 621 g zbar eh, new cab tier2 wheel loader service repair manual [fnh06...
Case 621 g zbar   eh, new cab tier2 wheel loader service repair manual [fnh06...Case 621 g zbar   eh, new cab tier2 wheel loader service repair manual [fnh06...
Case 621 g zbar eh, new cab tier2 wheel loader service repair manual [fnh06...
 
Workstation redesign
Workstation redesignWorkstation redesign
Workstation redesign
 
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
 
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
 
Ie microsoft office power point presentation
Ie  microsoft office power point presentationIe  microsoft office power point presentation
Ie microsoft office power point presentation
 
Vibration Analysis of a Centrifugal Pump
Vibration Analysis of a Centrifugal PumpVibration Analysis of a Centrifugal Pump
Vibration Analysis of a Centrifugal Pump
 

Viewers also liked

9555569222 Supertech Basera Affordable Housing Sector 79 Gurgaon, Haryana Aff...
9555569222 Supertech Basera Affordable Housing Sector 79 Gurgaon, Haryana Aff...9555569222 Supertech Basera Affordable Housing Sector 79 Gurgaon, Haryana Aff...
9555569222 Supertech Basera Affordable Housing Sector 79 Gurgaon, Haryana Aff...affordablehousinggurgaon
 
Affordable & cheap bridesmaids dresses online page 5 gudeer.com
Affordable & cheap bridesmaids dresses online page 5   gudeer.comAffordable & cheap bridesmaids dresses online page 5   gudeer.com
Affordable & cheap bridesmaids dresses online page 5 gudeer.comGudeer Kitty
 
Evaluation of the Biochemical Composition of Four Marine Algae and Its Nutrit...
Evaluation of the Biochemical Composition of Four Marine Algae and Its Nutrit...Evaluation of the Biochemical Composition of Four Marine Algae and Its Nutrit...
Evaluation of the Biochemical Composition of Four Marine Algae and Its Nutrit...IOSR Journals
 
Cordial Labelling Of K-Regular Bipartite Graphs for K = 1, 2, N, N-1 Where K ...
Cordial Labelling Of K-Regular Bipartite Graphs for K = 1, 2, N, N-1 Where K ...Cordial Labelling Of K-Regular Bipartite Graphs for K = 1, 2, N, N-1 Where K ...
Cordial Labelling Of K-Regular Bipartite Graphs for K = 1, 2, N, N-1 Where K ...IOSR Journals
 
Izin Pembuatan NPIK, Tanda Pengenal Importir.
Izin Pembuatan NPIK, Tanda Pengenal Importir.Izin Pembuatan NPIK, Tanda Pengenal Importir.
Izin Pembuatan NPIK, Tanda Pengenal Importir.legalservice
 
Strategi yang tepat untuk merevolusi mental petani
Strategi yang tepat untuk merevolusi mental petaniStrategi yang tepat untuk merevolusi mental petani
Strategi yang tepat untuk merevolusi mental petaniAmanda Elfast Relian Dio
 
One shoulder bridesmaid dresses under 200 gudeer.com
One shoulder bridesmaid dresses  under 200 gudeer.comOne shoulder bridesmaid dresses  under 200 gudeer.com
One shoulder bridesmaid dresses under 200 gudeer.comGudeer Kitty
 

Viewers also liked (20)

9555569222 Supertech Basera Affordable Housing Sector 79 Gurgaon, Haryana Aff...
9555569222 Supertech Basera Affordable Housing Sector 79 Gurgaon, Haryana Aff...9555569222 Supertech Basera Affordable Housing Sector 79 Gurgaon, Haryana Aff...
9555569222 Supertech Basera Affordable Housing Sector 79 Gurgaon, Haryana Aff...
 
Affordable & cheap bridesmaids dresses online page 5 gudeer.com
Affordable & cheap bridesmaids dresses online page 5   gudeer.comAffordable & cheap bridesmaids dresses online page 5   gudeer.com
Affordable & cheap bridesmaids dresses online page 5 gudeer.com
 
Evaluation of the Biochemical Composition of Four Marine Algae and Its Nutrit...
Evaluation of the Biochemical Composition of Four Marine Algae and Its Nutrit...Evaluation of the Biochemical Composition of Four Marine Algae and Its Nutrit...
Evaluation of the Biochemical Composition of Four Marine Algae and Its Nutrit...
 
Cordial Labelling Of K-Regular Bipartite Graphs for K = 1, 2, N, N-1 Where K ...
Cordial Labelling Of K-Regular Bipartite Graphs for K = 1, 2, N, N-1 Where K ...Cordial Labelling Of K-Regular Bipartite Graphs for K = 1, 2, N, N-1 Where K ...
Cordial Labelling Of K-Regular Bipartite Graphs for K = 1, 2, N, N-1 Where K ...
 
N012147579
N012147579N012147579
N012147579
 
Photos (backstage)
Photos (backstage)Photos (backstage)
Photos (backstage)
 
E1304012630
E1304012630E1304012630
E1304012630
 
J010217780
J010217780J010217780
J010217780
 
O010227375
O010227375O010227375
O010227375
 
F010513135
F010513135F010513135
F010513135
 
H010234144
H010234144H010234144
H010234144
 
Izin Pembuatan NPIK, Tanda Pengenal Importir.
Izin Pembuatan NPIK, Tanda Pengenal Importir.Izin Pembuatan NPIK, Tanda Pengenal Importir.
Izin Pembuatan NPIK, Tanda Pengenal Importir.
 
J012626269
J012626269J012626269
J012626269
 
Strategi yang tepat untuk merevolusi mental petani
Strategi yang tepat untuk merevolusi mental petaniStrategi yang tepat untuk merevolusi mental petani
Strategi yang tepat untuk merevolusi mental petani
 
E010243540
E010243540E010243540
E010243540
 
One shoulder bridesmaid dresses under 200 gudeer.com
One shoulder bridesmaid dresses  under 200 gudeer.comOne shoulder bridesmaid dresses  under 200 gudeer.com
One shoulder bridesmaid dresses under 200 gudeer.com
 
U01821129153
U01821129153U01821129153
U01821129153
 
anplppfinal
anplppfinalanplppfinal
anplppfinal
 
SIUJK
SIUJKSIUJK
SIUJK
 
B017250715
B017250715B017250715
B017250715
 

Similar to A012430106

STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEWSTUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEWIAEME Publication
 
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTTIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTIRJET Journal
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET Journal
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudybejayrocks
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET Journal
 
Utilization of plc programming for gravity die casting automation
Utilization of plc programming for gravity die casting automationUtilization of plc programming for gravity die casting automation
Utilization of plc programming for gravity die casting automationeSAT Journals
 
Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...IRJET Journal
 
Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...IAEME Publication
 
Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...IAEME Publication
 
CIM report - final
CIM report - finalCIM report - final
CIM report - finalPraveen S R
 
Study and Analysis of Tire Changing Machine Components
Study and Analysis of Tire Changing Machine ComponentsStudy and Analysis of Tire Changing Machine Components
Study and Analysis of Tire Changing Machine ComponentsIRJET Journal
 
Project Report on Maynard Operation Sequence Technique
Project Report on Maynard Operation Sequence TechniqueProject Report on Maynard Operation Sequence Technique
Project Report on Maynard Operation Sequence Techniqueijtsrd
 
IRJET- Six Axis Pneumatic Materials Handling Robotic Arm
IRJET-  	  Six Axis Pneumatic Materials Handling Robotic ArmIRJET-  	  Six Axis Pneumatic Materials Handling Robotic Arm
IRJET- Six Axis Pneumatic Materials Handling Robotic ArmIRJET Journal
 
Study on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingStudy on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingAlwin Thomas
 

Similar to A012430106 (20)

STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEWSTUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
STUDIES ON AVAILABILITY AND UTILISATION OF MINING EQUIPMENT- AN OVERVIEW
 
K012556370
K012556370K012556370
K012556370
 
K012556370
K012556370K012556370
K012556370
 
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTTIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
 
Utilization of plc programming for gravity die casting automation
Utilization of plc programming for gravity die casting automationUtilization of plc programming for gravity die casting automation
Utilization of plc programming for gravity die casting automation
 
30320140501002
3032014050100230320140501002
30320140501002
 
Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...Improvement of supply chain process using Maynard Operation Sequence Techniqu...
Improvement of supply chain process using Maynard Operation Sequence Techniqu...
 
Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...
 
Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...Improving productivity for engine crank shaft machining line using tps techni...
Improving productivity for engine crank shaft machining line using tps techni...
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM Report
CIM ReportCIM Report
CIM Report
 
Study and Analysis of Tire Changing Machine Components
Study and Analysis of Tire Changing Machine ComponentsStudy and Analysis of Tire Changing Machine Components
Study and Analysis of Tire Changing Machine Components
 
Project Report on Maynard Operation Sequence Technique
Project Report on Maynard Operation Sequence TechniqueProject Report on Maynard Operation Sequence Technique
Project Report on Maynard Operation Sequence Technique
 
IRJET- Six Axis Pneumatic Materials Handling Robotic Arm
IRJET-  	  Six Axis Pneumatic Materials Handling Robotic ArmIRJET-  	  Six Axis Pneumatic Materials Handling Robotic Arm
IRJET- Six Axis Pneumatic Materials Handling Robotic Arm
 
B012530710
B012530710B012530710
B012530710
 
Study on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingStudy on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream Mapping
 

More from IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Recently uploaded

Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 

Recently uploaded (20)

Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort ServiceHot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 

A012430106

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 4 Ver. III (Jul. - Aug. 2015), PP 01-06 www.iosrjournals.org DOI: 10.9790/1684-12430106 www.iosrjournals.org 1 | Page Productivity Improvement in Assembly Line of an Automobile Industry Nikhil Verma 1 Pulkit Trivedi 2 Vivek Agnihotri 3 1, 2, Student (Department Of Mechanical Engineering,, S.R.M.G.P.C College,Lucknow/U.P.Technical University, India) 3 Astt.Professor (Department Of Mechanical Engineering,, S.R.M.G.P.C College,Lucknow/U.P.Technical University, India) Abstract : Many factors are responsible in the successful operation and efficient working of a unit. To govern these factors work techniques are discovered. This gives an exposure to two of the technique employed in the production unit for calculation of time & motion involved and optimization Along with this it helps in a better understanding of an assembly line at the grass root level, realizing the complexity of the system & how difficult it is to just manage a production process let alone improvise it. The analysis of the listed techniques is implemented on two units –ADHITYA AUTOMOTIVES APPPLICATION PVT LTD, Lko and TATA MOTORS, Lko. Production of parts and an assembly in the units have been studied in the project with regard to the guidelines of the techniques. The aim of the project is to compare the result of both time &motion study and to bring out which of the study is utmost beneficial in calculation of time involved in assembling of the vehicles. Also on the improvement techniques of production which are responsible for worker fatigue and time loss. Thus enhancing productivity and heading towards optimization. In this Project we have tried to improve the productivity with minimizing time and distance of worker. The graph is plotted between the Motion v/s Distance & Motion v/s Time. A Relation is established between the two and then a minimized time and distance is calculated. The result which comes out after the calculation is a large difference in reduction of distance and time of worker. Keywords: time &motion study, productivity, time and distance study, assembly line. I. I Introduction 1.1 Productivity : The rate at which a company produces goods or services in relation to the amount of materials and number of employees needed. This is usually expressed in ratios of inputs to outputs. That is (input) cost per (output) good/service. For calculation purpose, expression of productivity is -: Productivity = Output/ Input 1.1.1 :Input may be Classified as:  Material, Machine, Man Hours, Methods, Land. 1.1.2: Output may be classified as:  Parts & product, Services, Wastage of any type, Pollutants of any type, etc It is quantitative relationship between what we produce and what we have spent to produce. Productivity is nothing but reduction in wastage of resources like men, material, machine, time, space, capital etc. It can be expressed as human efforts to produce more and more with less and less inputs of resources so that there will be maximum distribution of benefits among maximum number of people. 1.3: Roles and Responsibilities in the project:-  Measures and monitoring of productivity.  Work system design, assessment and resource requirement.  Measures and monitor productivity of plant, cascading of targets and facilitate achievements of targets.  Based on strategy and organization structure define organizational process, systems, work flow for attaining of plant’s objectives.  Based on the above, defined work content and role of each position.  Study area wise resource requirement in line with productivity targets and work assessment.  Recommendation of manpower nos. Along with the skill and competency requirement for management approval.
  • 2. Productivity Improvement in assembly line of an Automobile industry DOI: 10.9790/1684-12430106 www.iosrjournals.org 2 | Page 1.2 Objectives 1.2.1 Time Study Time Study is a work Measurement technique which is involved to calculate the time of the operation in an assembly line with the help of an instrument (stopwatch).  Initially calculating the time of the fitments in units (Adithya Automotive Applications Pvt Ltd / TATA MOTORS, Lucknow ).  Preparation of summary sheet. 1.2.2 Work Study A generic term for all those techniques which are used in the examination of human working all its context and which lead systematically to the investigation of all the factors which effect the efficiency and economy of the situation being reviewed in order to effect the improvement. Basically it’s a productivity raising technique by finding out the actual work content of a process and reduces it by proposing suitable improvements. It has two basic components viz: a. Method Study b. Work Measurement 1.2.3 Motion Study Motion study is a technique of analyzing the body motions employed in doing a task in order to eliminate or reduce ineffective movements and facilitates effective movements. • By using motion study and the principles of motion economy the task is redesigned to be more effective and less time consuming. • Objective of motion study is job simplification so that it is less fatiguing and less time consuming. 1.3. Productivity Improvement Techniques Productivity improvement techniques can be applied effectively in enterprises of any size, from one- person companies to corporations with thousands of staff.  JIDOKA , HEIJUNKA, KAIZEN, JIT, KANBAN, POM II. Studies At Tata Motors 2.1 Movement Description Chart Sl.No. TASK MOVEMENT DISTANCE(m) TIME(SEC) 1 acceleratorpedal ispickedfromthe rackandplacedonthe worktable 0-1,1-0 21.6 25 2 stopperispickedfromthe rackandplacedonthe worktable 0-2,2-0 18 16 3 stoppercapispickedfromthe rackandplacedonthe worktable 0-3,3-0 12 12 4 stoppercapismounteduponthe stopper operation 0 3 5 stoppercapisassembledonthe frontendof the acceleratorpedal operation 0 10 6 stoppercapistightenedbyaspanner operation 0 3 7 stoppercapisassembledonthe backendof the acceleratorpedal operation 0 10 8 stoppercapistightenedbyaspanner operation 0 3 9 ball andball endare pickedfromthe rackandplacedonthe worktable 0-4,4-0 19.2 20 10 pinisremovedfromthe ball endandball isputintoit operation 0 5 11 pinisputbackintothe ball end operation 0 2 12 ball endsubassemblyisputintothe acceleratorpedal end operation 0 3 13 ball endishandtightenedintothe acceleratorpedal operation 0 2 14 acceleratorpedal subassemblyispickedfromthe worktable andplacedonthe subassemlyrack 0-5,5-0 2.4 10 73.2 124 Total Movement During Accelerator Pedal Sub Assembly = 73.2m
  • 3. Productivity Improvement in assembly line of an Automobile industry DOI: 10.9790/1684-12430106 www.iosrjournals.org 3 | Page 2.2 Time Description Sheet Sl.No. TASK MOVEMENT DISTANCE(m) TIME(SEC) VA/NVA 1 acceleratorpedalispickedfromtherackandplacedontheworktable 0-1,1-0 21.6 25 NVA 2 stopperispickedfromtherackandplacedontheworktable 0-2,2-0 18 16 NVA 3 stoppercapispickedfromtherackandplacedontheworktable 0-3,3-0 12 12 NVA 4 stoppercapismounteduponthestopper operation 0 3 VA 5 stoppercapisassembledonthefrontendoftheacceleratorpedal operation 0 10 VA 6 stoppercapistightenedbyaspanner operation 0 3 VA 7 stoppercapisassembledonthebackendoftheacceleratorpedal operation 0 10 VA 8 stoppercapistightenedbyaspanner operation 0 3 VA 9 ballandballendarepickedfromtherackandplacedontheworktable 0-4,4-0 19.2 20 NVA 10 pinisremovedfromtheballendandballisputintoit operation 0 5 VA 11 pinisputbackintotheballend operation 0 2 VA 12 ballendsubassemblyisputintotheacceleratorpedalend operation 0 3 VA 13 ballendishandtightenedintotheacceleratorpedal operation 0 2 VA 14 acceleratorpedalsubassemblyispickedfromtheworktableandplacedonthesubassemlyrack 0-5,5-0 2.4 10 NVA 73.2 124 Total Time Taken=124 Sec Value Added Time=41sec Non Value Added=83sec Final Analysis sl.No.TASK MOVEMENT DISTANCE(m) TIME(sec) VA/NVA 1 trolley istakenfromthe standtoacceleratorpedal rack 0-1 2.4 3 NVA 2 acceleratorpedal are takenfromthe rack andkeptontothe trolley operation 0 35 NVA 3 trolley istakentothe ball andball endrack 1-4 1.8 2 NVA 4 ball andball endare are takenfromthe rack andkeptuponthe Spare hold operation 0 20 NVA 5 trolley istakentothe stopperrack 4-2 0.6 1 NVA 6 stoppersare are takenfromthe rack andkeptuponthe Spare hold operation 0 25 NVA 7 trolley istakentothe stoppercaprack 2-3 7.2 6 NVA 8 stoppercapsare are takenfromthe rack andkeptuponthe Spare hold operation 0 20 NVA 9 trolley istakenback tothe stand 3-0 20 15 NVA 10 acceleratorpedal iskeptuponthe work areaof the trolley operation 0 20 VA 11 stoppercapsare pickedfromspare holdandkeptuponthe work areaof the trolley operation 0 20 VA 12 stoppersare pickedfromspare holdandkeptuponthe work areaof the trolley operation 0 20 VA 13 stoppercapsare putuponthe stoppersandnutsare put operation 0 20 VA 14 stoppersare assembledonthe acceleratorpedal andtightenedby spanner operation 0 20 VA 15 ball andball endare are pickedfromthe Spare holdandkeptonthe work areaof the trolley operation 0 30 VA 16 pinisremovedfromthe ball endandball isinsertedintoit operation 0 100 VA 17 pinisputback onthe ball end operation 0 30 VA 18 ball andball endare assembledontothe acceleratorpedal andishandtightened operation 0 100 VA 19 the complete acceleratorpedal assembly iskeptback uponthe spare hold operation 0 20 VA 32 507 TOTAL TIME= 507sec Non Value Added= 127sec Value Added= 380sec Before Sub Assembly (Table Was Used) (Trolley In Use)
  • 4. Productivity Improvement in assembly line of an Automobile industry DOI: 10.9790/1684-12430106 www.iosrjournals.org 4 | Page Before After III. Result Analysis And Discussion The percentage decrease in time by the above study is = (124 - 51)/124 x 100 = 58.3% The percentage decrease in the motion of the worker is = (73.2 – 32)/73.2 x100 =56.3% (Here graph distance variation graph is ploteed with the help of collected data). (On differiating the equation mentioned above and equalisisng that equation to zero,we get): X=1.0026 X=-0.519 Where negative sign shows the reduction in time. This shows that Time and Motion Study is the best Study for the calculation of Work and time and the content optimizes the enhancement in the productivity. Hence we saved a total time of 73secs and reduced the motion up to 38 m. (This finally leading to new method to improve our production.)
  • 5. Productivity Improvement in assembly line of an Automobile industry DOI: 10.9790/1684-12430106 www.iosrjournals.org 5 | Page Iii Studies At Adithya Automotive Applications Pvt. Ltd. Before: Fixture used for the Tack Welding (BEFORE) After studying the time for the tack welding of side board sub assembly frame we found that time calculated was 111 mins. After: Fixture used for tack welding of 12, 14, 16 and HD model Tipper Vehicles When the improvements were made in the fixture the calculated time was found to be 45 mins. BEFORE AFTER IV. Result Analysis And Discussion Hence percentage reduction in time is given as = (111-45)/111 x100 = 59.45% IT, show that up to 60% time is reduced with the advancement in fixture which increased the production of Tippers from 30 to 75 Tippers in the month. Time Reduction 111 mins 45 45 mins
  • 6. Productivity Improvement in assembly line of an Automobile industry DOI: 10.9790/1684-12430106 www.iosrjournals.org 6 | Page V. Problems And Suggestions 1.5 Tata Motors Problem 1: When the accelerator pedal assembly was done the worker has to travel more distance to collect the accelerator pedal parts and 5S was not maintained on the sub-assembly table. Suggestion: An accelerator pedal sub assembly trolley was made to reduce the motion of worker and 5S was maintained on the table hence productivity improved. Problem 2: Time required for the assembly of the accelerator pedal was more and there were more Non Varying Activities. Suggestion: Using a trolley reduced the motion of worker as well as improved ergonomics and fatigue was also reduced. 1.6 Aaditya Automotives Applications Pvt Ltd Problem 1: The table was used for side board tack welding; it was only for 12 cubic meter tipper model. Workers were having a difficulty in placing the side board on the table too. Suggestion: A new fixture was designed to do tack welding for 12, 10, 14, and heavy duty vehicles with different. Problem 2: It consumes more time for side board tack welding table as there were no holding devices. Suggestion: According to the design of new fixture the time required for the side board tack welding was reduced with a huge difference. VI. Conclusion The purpose of this project was to give the idea of basic functioning of real industry. This PROJECT has not only given an exposure to various techniques employed in production units but also has added the new dimension to vision of knowledge. It has given the basic idea of the working of an industry and core of every industry lie in its fundamentals MAN, MACHINE AND MATERIAL and how the cohesion between them is needed for the smooth running of nay industrial organization. TIME has acted as the main factor to be studied. It is therefore concluded from the study that TIME STUDY AND WORK STUDY are the techniques which can be used to increase the productivity. Also, the result shows a big fraction of time is being saved, hence saving time is saving money. References [1]. J. Fowler and J. Robinson, ―Measurement and Improvement of Manufacturing Capacity,‖ SEMATECH, Inc, 1995. [2]. D. Sumanth, ―Productivity Engineering and Management,‖ McGraw-Hill, New York, 1994. [3]. M. Oxenburgh, and P. Marlow, ―The Productivity Assessment Tool: Computer-Based Cost Benefit Analysis Model for the Economic Assessment of Occupational Health and Safety Interventions in the Workplace,‖ Journal of Safety Research, ECON Proceedings Paper, 2005, pp. 209-214. [4]. N. Van Hop, N. Sumate and N. Sitawatch, ―Modifying Integrated Model for Manufacturing Process Improvement,‖ Proceedings of the International Conference on Simulation and Modeling, 2005, pp. 38-47. [5]. W. Yung, ―An Integrated Model for Manufacturing Process Improvement,‖ European Journal of Operational Research, No. 61, 1996, pp. 39-43. [6]. R. Radharamanan, L. P. Godoy and K. I. Watanabe, ―Quality and Productivity Improvement in a Custom- Made Furniture Industry Using Kaizen,‖ Computers & Industrial Engineering, Vol. 31, No. 1-2, 1996, pp. 471- 474. doi:10.1016/0360-8352(96)00177-5 [7]. S. Huang, J. Dismukes, J. Shi, Q. Su, M. Razzak, R. Bodhale and D. Robinson, ―Manufacturing Productivity Improvement Using Effectiveness Metric and Simulation Analysis,‖ International Journal of Production Research, Vol. 41, No. 3, 2003, pp. 513-527. doi:10.1080/0020754021000042391 [8]. F. Andris and N. Benjamin, ―Method Standard and Work Design,‖ 11th Edition, McGraw-Hill, New York & London, 2004, pp. 335-348. [9]. R. N. Mefford, ―Increasing Productivity in Global Firms: The CEO Challenge,‖ Journal of International Management, Vol. 15, No. 3, 2009, pp. 262-272. doi:10.1016/j.intman.2008.12.004 [10]. P. Kuhlang, T. Edtmayr and W. Sihn, ―Methodical Approach to Increase Productivity and Reduce Lead Time in Assembly and Production-Logistic Processes,‖ CIRP Journal of Manufacturing Science and Technology, in Press, 2011, Available Online. doi:10.1016/j.cirpj.2011.02.001 [11]. R. H. A. Seidel and G. Arndt, ―Productivity Improvement in Job Shop Production,‖ CIRP Annals—Manufacturing Technology, Vol. 37, No. 1, 1988, pp. 421-424. [12]. Gunasekaran, A. R. Korukonda, I. Virtanen and P. Yli-Olli, ―Improving Productivity and Quality in Manufacturing Organizations,‖ International Journal of Production Economics, Vol. 36, No. 2, 1994, pp. 69-183. doi:10.1016/0925-5273(94)90022-1 [13]. R. Maruta, ―Transforming Knowledge Workers into Innovation Workers to Improve Corporate Productivity,‖ Knowledge-Based Systems, in Press, 2011, Available Online. doi:10.1016/j.knosys.2011.06.017 [14]. R. Mayer, ―Production of Operations Management,‖ 3rd Edition, McGraw-Hill, New York & London, 1975, pp 516-517.