2. Manufactured Metal
Building
We build Control Rooms for Center-
Point for the electrical Sub Stations
Entire External Envelope of the
building is load bearing
It takes only about 5-7 day to erect an
entire building if the foundation is
already poured.
We also build classroom trailers called
T-Buildings or Transportable buildings
Those take about 14 to 20 days to go
up with ac and plumbing
4. Interior of Metal Building
Wide beam and column for the longer
buildings in the center of the building
This is a special case for the longer
buildings, the heavy steel is in there to
combat the twisting forces the wind
produces on the bulding
Ceiling panels
Wall Panels
6. Control Room For a
Center-Point Substation
Near the Coast
Building is on 9 concrete columns
About 15’ high off the ground
Galvanized metal structure for the
base of the building
Everything else is the same
7. Wheel Mounted Crane
I saw them use this to lift the rebar
cages
You can see the red fuel truck here
also