Imperial Journal of Interdisciplinary Research (IJIR)
Vol-3, Issue-2, 2017
ISSN: 2454-1362, http://www.onlinejournal.in
Imperial Journal of Interdisciplinary Research (IJIR) Page 1307
A review paper on To Identify the Various
Constraints for Delays in Construction Work and
Suggesting Remedial Measures for the Same
Mr. Harish R Rajmane1
, Dr. A. K. Gupta2
& Prof. D. B. Desai3
1
PG Student, Civil Engineering Department, Dr.J.J.Magdum College of Engineering, Jaysingpur,
Maharashtra, India.
2
Principal & Prof., Dr.J.J.Magdum College of Engineering, Jaysingpur, Maharashtra, India.
3
Asso. Professor, Dr.J.J.Magdum College of Engineering, Jaysingpur, Maharashtra, India.
Abstract: A constraint is defined as anything that
limits an organization or entity from moving toward
or achieving its goal. Needs and constraints in a
multi-party working situation bring complications in
project management. Needs are diversified when the
client is a large organization such as a public client
or a corporate client. However, constraints in
construction projects limit their achievement of high
performance. The aim and scope of this project is to
identify the constraints in construction project
working environment. If constraints are better
understood at the outset, it is believed that better
performance can be assured. Identifying and
removing constraints from bottleneck activities help
to reduce uncertainties in construction processes and
increases the transparency of project management.
This study was carried out based on literature review
and a questionnaire survey. The data for this study
will be gathering through a detailed questionnaire
survey. The questionnaire form is forwarded to
various construction industries through email and in
personal. The objectives of the study is to
successfully reduce the constraints which will help to
decrease the unnecessary wastage and loss of both
money and time because of inadequate planning.
1. Introduction
Nowadays, companies struggle to survive in a
global competition. Every company tries to find the
best philosophy which is suitable with their strategy
to gain any and every advantage among their rivals.
Companies should be more focused on understanding
their own structure in terms of processes whether
they are in the production or service sector. In this
situation, Theory of Constraints (TOC) becomes an
important theory which focuses on the weakest rings
in the chain. Constraints are defined as anything that
limits a system from attaining higher performance
towards its goal. Identifying and removing
constraints from bottleneck activities help to reduce
uncertainties in construction processes and increases
the transparency of project management. Needs and
constraints in a multi-party working situation bring
complications in project management. Needs are
diversified when the client is a large organization
such as a public client or a corporate client.
However, constraints in construction projects limit
their achievement of high performance that we are
unaware of the existence of the constraints, or, we
tend to put more emphasis on the project goals. The
construction working environment involves multi-
party participation. Needs and constraints in a
multiparty working situation bring complications in
project management. These can further develop into
conflicts and disputes, which bring cost
consequences, direct and indirect, to clients and
contractors. The project team members have to meet
client’s needs on one hand and to overcome
constraints on the other hand. With the limited
literature for the constraints in the construction
working environment, it is important to identify the
potential constraints in the construction project,
which will help to decrease the unnecessary wastage
and loss of both money and time because of
inadequate planning. Controlling the constraints is
thus a pre-condition for high performance of the
project. TOC is based on the idea that every system
has at least one bottleneck which can be defined as
any kind of situation that impedes the system to
reach high performance level in terms of its
purposes.. A constraint is defined as anything that
limits an organization or entity from moving toward
or achieving its goal. TOC logic forms major
portions of the organization's philosophy of
continuous improvement. It is applied to identify
what factors limit an organization from achieving its
goals, developing a solution to the problem, and
getting the individuals in the process to invent the
requisite changes for themselves.
2. Literature Review
Title - Key Constraints Analysis with
Integrated Production Scheduler.
Imperial Journal of Interdisciplinary Research (IJIR)
Vol-3, Issue-2, 2017
ISSN: 2454-1362, http://www.onlinejournal.in
Imperial Journal of Interdisciplinary Research (IJIR) Page 1308
Author – Chua D. K. H.
Identifying and removing constraints from
bottleneck activities help to reduce uncertainties in
construction processes and increases the
transparency of project management. The present
means of look-ahead planning do poorly in resolving
hidden constraints in the supply chain and
information flow. Accordingly, work plans are
vulnerable to the uncertainties that result in flow
variation. It has been realized that reducing and
eliminating critical constraints through better means
of look-ahead planning are the keys to achieving
reliable workflow and, consequently, increased
productivity. Constraint modeling is an indispensable
step in construction planning. Reliable planning
depends on effective identification, formulation, and
satisfaction of key constraints in production
processes. Constraint management helps to optimize
production plans, resolve resource conflicts, and
increase the availability of resource and information
prerequisites. Most existing project planning tools
are usually based on the critical path method CPM,
which, typically, only one type of constraints i.e., the
PROCESS constraints concerning precedence
relationships of activities, is modeled. The CPM does
not provide the means to deal with many hidden
constraints regarding resource supply and
information acquisition. Without identifying these
hidden constraints explicitly, it is hard to control and
reduce the workflow uncertainties that result in
process variability. Making reliable work plans is
important in achieving high productivity and
continuous workflow. Existing CPM-based planning
tools lack the ability to manage the hidden
constraints in the supply chain and information flow
with respect to resource and information
availabilities. As a result, the quality of production is
vulnerable to many uncertainties that are difficult to
eliminate or reduce. A new tool, Integrated
Production Scheduler, is introduced to ameliorate the
reliability of construction look-ahead plans by
modeling the resource and information constraints in
addition to the process constraints for construction
processes.
Title - Quantification of Delay Factors
Using the Relative Importance Index
Method for Construction Projects in
Turkey.
Author – Gunduz M.
To identify delay factors on construction
projects and analyse these factors with the relative
importance index method. The relative importances
of these delay factors were quantified by the relative
importance index method. The ranking of the factors
and groups were demonstrated according to their
importance level on delay. To identify the delay
factors in construction projects because delays are
considered to be a serious problem in the
construction industry. The common results of delays
are late completion of the project, increased cost,
disruption of work, loss of productivity, third-party
claims, disputes, and abandonment or termination of
contracts. Therefore, delays in construction projects
give rise to dissatisfaction to all parties involved.
Research aimed to (1)identify the delay factors in
construction projects, (2)categorize the delay factors
in construction projects, (3)quantify the relative
importance of delay factors and to demonstrate the
ranking of the factors and groups according to their
importance with respect to delays, (4)address the
factors and groups contributing most to delays, and
(5)make recommendations in order to minimize or
control delays in construction projects.
Title - Identification Of Constraints In
Construction Projects To Improve
Performance.
Author – Lau E.
Needs and constraints in a multi-party
working situation bring complications in project
management. Needs are diversified when the client is
a large organization such as a public client or a
corporate client. However, constraints in
construction projects limit their achievement of high
performance. To identify the constraints in
construction project working environment and apply
the theory of constraints (TOC), which provides
practical steps for making organizational decisions in
situations in which constraints exist. If constraints
are better understood at the outset, it is believed that
better performance can be assured. Presently clients’
needs in construction are well discussed, but
constraints have yet to be understood in context. The
constraints in five categories, they are: (1) economic
constraints, (2) legal constraints, (3) environmental
constraints, (4) technical constraints, and (5) social
constraints. The impacts of these constraints to the
construction project were studied. Developing
awareness to managing and controlling the
constraints in construction working environment for
achieving high performance in the construction
working environment.
Title - An Assessment of the Factors
Causing Delays on Building Construction
Projects in Uganda.
Author – Muhwezi L.
To assess the factors causing delays and
their effects on building construction projects in
Uganda. Eighty one project delay attributes were
identified through detailed literature review.
Structured interviews and questionnaire survey were
Imperial Journal of Interdisciplinary Research (IJIR)
Vol-3, Issue-2, 2017
ISSN: 2454-1362, http://www.onlinejournal.in
Imperial Journal of Interdisciplinary Research (IJIR) Page 1309
conducted across stakeholders that included among
others; consultants, contractors and clients on four
selected building projects to gather their views on
causes of delay in delivery of projects. The causes of
delay under four main groups of consultant related,
contractor related, client related and external related
and then assessed their impacts on delay using
relative importance index (RII) as a basis for
analysis. The RII for all delay factors and group of
categories was computed so as to rank the factors.
Title – Financial related causes
contributing to project delays.
Author – Rahman H..
Delay in construction projects is a common
phenomenon and a costly problem. The issues of
financial related delays in construction projects. It
identifies the root causes and scrutinises the suitable
mitigation actions of financial-related project delays.
Four main factors were identified in the literature,
namely late payment, poor cash flow management,
insufficient financial resources and financial market
instability. The result revealed that poor cash flow
management is the most significant factor that leads
to a project’s delay followed by late payment,
insufficient financial resources and financial market
instability. Contractors instable financial
background, client’s poor financial and business
management, difficulties in obtaining loan from
financiers and inflation were identified as the most
significant underlying causes. The clients play the
most important role in reducing the impact of
financial problems towards the extent of project’s
delay. Several suitable mitigation actions were
suggested by the respondents. The importance of
having more intensive research that give emphasis on
clients achieving a well managed cash flow in order
to obtain a prompt payment practice in the
construction industry. The greater the delay in
payment due to a contractor, the greater the cash
flow problems, the greater the extent of delays. The
poorer the cash flow management, the greater the
cash flow problems, the greater the extent of delays.
The greater the shortage of financial resources, the
greater the cash flow problems, the greater the extent
of delays. The greater the instability of financial
market, the greater the cash flow problems, the
greater the extent of delays.
3. Scope, Methodology and Purpose.
3.1 Scope:-
Following are the objectives of the proposed
dissertation work.
a) To study and identify the constraints in
construction industry for Residential Building
Scheme.
b) To identify the major root causes of financial
related problems that would lead to delays in
project.
c) To investigate the opinions of the parties upon
the actions that they undertake to manage the
financial problems.
d) To analyse the causes by using quantitative
techniques.
e) To give suggestive recommendations in order
to reduce the delay problems by considering
case study.
3.2 Methodology:-
For carrying out the proposed work, following
methodology will be adopted for data collecting and
analysis.
a) Collection of preliminary information through
literature review.
b) Collection of data by surveying amongst the
practitioners of building construction.
(Engineers, Contractors, Architects, Builders)
c) Identifying constraints in delay of construction
work.
d) Feaslibility study of constraints by using
Relative Importance Index Method.
e) To give results and conclusion from the data
analysed.
3.3 Purpose of Dissertation:-
The proposed work will help to identify the
constraints which leads to delays in construction
work. Suggesting and recommendations made
through this project work will be also useful for the
industrial people to use the remedial measures so as
to improve performance, reduce cost and delays in
construction project work.
References
[1] Chua D. K. H. and Shen L. J., “Key Constraints
Analysis with Integrated Production Scheduler” Journal Of
Construction Engineering And Management, 7, 2003, pp.
753-764.
[2] Gunduz M. , Nielsen Y, and Ozdemir M.,
“Quantification of Delay Factors Using the Relative
Importance Index Method for Construction Projects in
Turkey” Journal Of Management In Engineering, 29, 2,
2013, pp. 133-139.
[3] Lau E. and Kong J. J., “Identification Of Constraints In
Construction Projects To Improve Performance” The Joint
International Conference On Construction, Culture,
Innovation And Management, 2006, pp - 655-663.
[4] Muhwezi L. , Acai J. and Otim G., “An Assessment of
the Factors Causing Delays on Building Construction
Imperial Journal of Interdisciplinary Research (IJIR)
Vol-3, Issue-2, 2017
ISSN: 2454-1362, http://www.onlinejournal.in
Imperial Journal of Interdisciplinary Research (IJIR) Page 1310
Projects in Uganda” International Journal of Construction
Engineering and Management, 3, 1, 2014, pp. 13-23.
[5] Rahman H. A, Takim R and Min W. S., “Financial-
related causes contributing to project delays” Journal of
Retail & Leisure Property, 8, 3, 2009, pp. 225–238.

More Related Content

What's hot

Project Organizational Responsibility Model - ORM
Project Organizational Responsibility Model -  ORMProject Organizational Responsibility Model -  ORM
Project Organizational Responsibility Model - ORMGuttenberg Ferreira Passos
 
Selection criterion and implementation of case tools in gap analysis towa
Selection criterion and implementation of case tools in gap analysis towaSelection criterion and implementation of case tools in gap analysis towa
Selection criterion and implementation of case tools in gap analysis towaIAEME Publication
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projectsijtsrd
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface ManagementBob Prieto
 
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...
IRJET- Decision Making in Construction Management using AHP and Expert Ch...IRJET Journal
 
A critical success factors for software project manager in GVTs within covid-...
A critical success factors for software project manager in GVTs within covid-...A critical success factors for software project manager in GVTs within covid-...
A critical success factors for software project manager in GVTs within covid-...journalBEEI
 
Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Bob Prieto
 
IRJET- A Study on Supply Chain Management in Construction Projects
IRJET- A Study on Supply Chain Management in Construction ProjectsIRJET- A Study on Supply Chain Management in Construction Projects
IRJET- A Study on Supply Chain Management in Construction ProjectsIRJET Journal
 
Gus Caporusso6 12 Resume
Gus Caporusso6 12 ResumeGus Caporusso6 12 Resume
Gus Caporusso6 12 Resumeguscaporusso
 
Distributed Software Development Process, Initiatives and Key Factors: A Syst...
Distributed Software Development Process, Initiatives and Key Factors: A Syst...Distributed Software Development Process, Initiatives and Key Factors: A Syst...
Distributed Software Development Process, Initiatives and Key Factors: A Syst...zillesubhan
 
COMPRESSED NEW PRODUCT DEVELOPMENT CYCLE & ITS IMPACT ON OUTSOURCING DECISION...
COMPRESSED NEW PRODUCT DEVELOPMENT CYCLE & ITS IMPACT ON OUTSOURCING DECISION...COMPRESSED NEW PRODUCT DEVELOPMENT CYCLE & ITS IMPACT ON OUTSOURCING DECISION...
COMPRESSED NEW PRODUCT DEVELOPMENT CYCLE & ITS IMPACT ON OUTSOURCING DECISION...ijmvsc
 
The third way running effective projects
The third way   running effective projectsThe third way   running effective projects
The third way running effective projectsRune Aresvik
 
Product based design of business processes. Applied within Financial Services
Product based design of business processes. Applied within  Financial ServicesProduct based design of business processes. Applied within  Financial Services
Product based design of business processes. Applied within Financial Services112Motion
 
Employee Engagement within the IT Industry
Employee Engagement within the IT Industry Employee Engagement within the IT Industry
Employee Engagement within the IT Industry Momo Scott
 
Toward Customer Satisfaction SEC ERP Implementation Project
Toward Customer Satisfaction SEC ERP Implementation ProjectToward Customer Satisfaction SEC ERP Implementation Project
Toward Customer Satisfaction SEC ERP Implementation ProjectBaker Khader Abdallah, PMP
 
Six sigma black belts
Six sigma black beltsSix sigma black belts
Six sigma black beltsNEHA KAPOOR
 
IRJET- Most Efficient Critical Success Factor for Construction
IRJET-  	  Most Efficient Critical Success Factor for ConstructionIRJET-  	  Most Efficient Critical Success Factor for Construction
IRJET- Most Efficient Critical Success Factor for ConstructionIRJET Journal
 
Jibril muhammad bashir2
Jibril muhammad bashir2Jibril muhammad bashir2
Jibril muhammad bashir2Jibril Bashir
 

What's hot (20)

Project Organizational Responsibility Model - ORM
Project Organizational Responsibility Model -  ORMProject Organizational Responsibility Model -  ORM
Project Organizational Responsibility Model - ORM
 
Imbr
ImbrImbr
Imbr
 
Selection criterion and implementation of case tools in gap analysis towa
Selection criterion and implementation of case tools in gap analysis towaSelection criterion and implementation of case tools in gap analysis towa
Selection criterion and implementation of case tools in gap analysis towa
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
 
A critical success factors for software project manager in GVTs within covid-...
A critical success factors for software project manager in GVTs within covid-...A critical success factors for software project manager in GVTs within covid-...
A critical success factors for software project manager in GVTs within covid-...
 
Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...
 
IRJET- A Study on Supply Chain Management in Construction Projects
IRJET- A Study on Supply Chain Management in Construction ProjectsIRJET- A Study on Supply Chain Management in Construction Projects
IRJET- A Study on Supply Chain Management in Construction Projects
 
Gus Caporusso6 12 Resume
Gus Caporusso6 12 ResumeGus Caporusso6 12 Resume
Gus Caporusso6 12 Resume
 
Distributed Software Development Process, Initiatives and Key Factors: A Syst...
Distributed Software Development Process, Initiatives and Key Factors: A Syst...Distributed Software Development Process, Initiatives and Key Factors: A Syst...
Distributed Software Development Process, Initiatives and Key Factors: A Syst...
 
COMPRESSED NEW PRODUCT DEVELOPMENT CYCLE & ITS IMPACT ON OUTSOURCING DECISION...
COMPRESSED NEW PRODUCT DEVELOPMENT CYCLE & ITS IMPACT ON OUTSOURCING DECISION...COMPRESSED NEW PRODUCT DEVELOPMENT CYCLE & ITS IMPACT ON OUTSOURCING DECISION...
COMPRESSED NEW PRODUCT DEVELOPMENT CYCLE & ITS IMPACT ON OUTSOURCING DECISION...
 
The third way running effective projects
The third way   running effective projectsThe third way   running effective projects
The third way running effective projects
 
Product based design of business processes. Applied within Financial Services
Product based design of business processes. Applied within  Financial ServicesProduct based design of business processes. Applied within  Financial Services
Product based design of business processes. Applied within Financial Services
 
Fd0 f2d01
Fd0 f2d01Fd0 f2d01
Fd0 f2d01
 
Employee Engagement within the IT Industry
Employee Engagement within the IT Industry Employee Engagement within the IT Industry
Employee Engagement within the IT Industry
 
Toward Customer Satisfaction SEC ERP Implementation Project
Toward Customer Satisfaction SEC ERP Implementation ProjectToward Customer Satisfaction SEC ERP Implementation Project
Toward Customer Satisfaction SEC ERP Implementation Project
 
Six sigma black belts
Six sigma black beltsSix sigma black belts
Six sigma black belts
 
IRJET- Most Efficient Critical Success Factor for Construction
IRJET-  	  Most Efficient Critical Success Factor for ConstructionIRJET-  	  Most Efficient Critical Success Factor for Construction
IRJET- Most Efficient Critical Success Factor for Construction
 
Jibril muhammad bashir2
Jibril muhammad bashir2Jibril muhammad bashir2
Jibril muhammad bashir2
 

Similar to A review paper

IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...IRJET Journal
 
Agile methodologies in_project_management
Agile methodologies in_project_managementAgile methodologies in_project_management
Agile methodologies in_project_managementPravin Asar
 
An Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology ProjectsAn Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology ProjectsIOSR Journals
 
Project and Change Management Success Factors from Malaysian Government Depar...
Project and Change Management Success Factors from Malaysian Government Depar...Project and Change Management Success Factors from Malaysian Government Depar...
Project and Change Management Success Factors from Malaysian Government Depar...IOSR Journals
 
Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...IRJET Journal
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewIRJET Journal
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxcpatriciarpatricia
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxdeanmtaylor1545
 
Managing Interdependencies in Complex Organizations
Managing Interdependencies in Complex OrganizationsManaging Interdependencies in Complex Organizations
Managing Interdependencies in Complex OrganizationsNicolay Worren
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
Analysing attrition in outsourced
Analysing attrition in outsourcedAnalysing attrition in outsourced
Analysing attrition in outsourcedcsandit
 
Analysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software ProjectAnalysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software Projectcsandit
 
TQM in Construction Management A Review
TQM in Construction Management A ReviewTQM in Construction Management A Review
TQM in Construction Management A Reviewijtsrd
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
IRJET- Interface Management and its Effect on Project Complexity in Constr...
IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...
IRJET- Interface Management and its Effect on Project Complexity in Constr...IRJET Journal
 
IRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction IndustryIRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction IndustryIRJET Journal
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSIAEME Publication
 

Similar to A review paper (20)

IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
 
Agile methodologies in_project_management
Agile methodologies in_project_managementAgile methodologies in_project_management
Agile methodologies in_project_management
 
An Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology ProjectsAn Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology Projects
 
Project and Change Management Success Factors from Malaysian Government Depar...
Project and Change Management Success Factors from Malaysian Government Depar...Project and Change Management Success Factors from Malaysian Government Depar...
Project and Change Management Success Factors from Malaysian Government Depar...
 
Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...
 
Proposal .pdf
Proposal .pdfProposal .pdf
Proposal .pdf
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docx
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docx
 
Managing Interdependencies in Complex Organizations
Managing Interdependencies in Complex OrganizationsManaging Interdependencies in Complex Organizations
Managing Interdependencies in Complex Organizations
 
D012251726
D012251726D012251726
D012251726
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Analysing attrition in outsourced
Analysing attrition in outsourcedAnalysing attrition in outsourced
Analysing attrition in outsourced
 
Analysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software ProjectAnalysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software Project
 
TQM in Construction Management A Review
TQM in Construction Management A ReviewTQM in Construction Management A Review
TQM in Construction Management A Review
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IRJET- Interface Management and its Effect on Project Complexity in Constr...
IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...
IRJET- Interface Management and its Effect on Project Complexity in Constr...
 
IRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction IndustryIRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction Industry
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
 

Recently uploaded

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 

Recently uploaded (20)

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 

A review paper

  • 1. Imperial Journal of Interdisciplinary Research (IJIR) Vol-3, Issue-2, 2017 ISSN: 2454-1362, http://www.onlinejournal.in Imperial Journal of Interdisciplinary Research (IJIR) Page 1307 A review paper on To Identify the Various Constraints for Delays in Construction Work and Suggesting Remedial Measures for the Same Mr. Harish R Rajmane1 , Dr. A. K. Gupta2 & Prof. D. B. Desai3 1 PG Student, Civil Engineering Department, Dr.J.J.Magdum College of Engineering, Jaysingpur, Maharashtra, India. 2 Principal & Prof., Dr.J.J.Magdum College of Engineering, Jaysingpur, Maharashtra, India. 3 Asso. Professor, Dr.J.J.Magdum College of Engineering, Jaysingpur, Maharashtra, India. Abstract: A constraint is defined as anything that limits an organization or entity from moving toward or achieving its goal. Needs and constraints in a multi-party working situation bring complications in project management. Needs are diversified when the client is a large organization such as a public client or a corporate client. However, constraints in construction projects limit their achievement of high performance. The aim and scope of this project is to identify the constraints in construction project working environment. If constraints are better understood at the outset, it is believed that better performance can be assured. Identifying and removing constraints from bottleneck activities help to reduce uncertainties in construction processes and increases the transparency of project management. This study was carried out based on literature review and a questionnaire survey. The data for this study will be gathering through a detailed questionnaire survey. The questionnaire form is forwarded to various construction industries through email and in personal. The objectives of the study is to successfully reduce the constraints which will help to decrease the unnecessary wastage and loss of both money and time because of inadequate planning. 1. Introduction Nowadays, companies struggle to survive in a global competition. Every company tries to find the best philosophy which is suitable with their strategy to gain any and every advantage among their rivals. Companies should be more focused on understanding their own structure in terms of processes whether they are in the production or service sector. In this situation, Theory of Constraints (TOC) becomes an important theory which focuses on the weakest rings in the chain. Constraints are defined as anything that limits a system from attaining higher performance towards its goal. Identifying and removing constraints from bottleneck activities help to reduce uncertainties in construction processes and increases the transparency of project management. Needs and constraints in a multi-party working situation bring complications in project management. Needs are diversified when the client is a large organization such as a public client or a corporate client. However, constraints in construction projects limit their achievement of high performance that we are unaware of the existence of the constraints, or, we tend to put more emphasis on the project goals. The construction working environment involves multi- party participation. Needs and constraints in a multiparty working situation bring complications in project management. These can further develop into conflicts and disputes, which bring cost consequences, direct and indirect, to clients and contractors. The project team members have to meet client’s needs on one hand and to overcome constraints on the other hand. With the limited literature for the constraints in the construction working environment, it is important to identify the potential constraints in the construction project, which will help to decrease the unnecessary wastage and loss of both money and time because of inadequate planning. Controlling the constraints is thus a pre-condition for high performance of the project. TOC is based on the idea that every system has at least one bottleneck which can be defined as any kind of situation that impedes the system to reach high performance level in terms of its purposes.. A constraint is defined as anything that limits an organization or entity from moving toward or achieving its goal. TOC logic forms major portions of the organization's philosophy of continuous improvement. It is applied to identify what factors limit an organization from achieving its goals, developing a solution to the problem, and getting the individuals in the process to invent the requisite changes for themselves. 2. Literature Review Title - Key Constraints Analysis with Integrated Production Scheduler.
  • 2. Imperial Journal of Interdisciplinary Research (IJIR) Vol-3, Issue-2, 2017 ISSN: 2454-1362, http://www.onlinejournal.in Imperial Journal of Interdisciplinary Research (IJIR) Page 1308 Author – Chua D. K. H. Identifying and removing constraints from bottleneck activities help to reduce uncertainties in construction processes and increases the transparency of project management. The present means of look-ahead planning do poorly in resolving hidden constraints in the supply chain and information flow. Accordingly, work plans are vulnerable to the uncertainties that result in flow variation. It has been realized that reducing and eliminating critical constraints through better means of look-ahead planning are the keys to achieving reliable workflow and, consequently, increased productivity. Constraint modeling is an indispensable step in construction planning. Reliable planning depends on effective identification, formulation, and satisfaction of key constraints in production processes. Constraint management helps to optimize production plans, resolve resource conflicts, and increase the availability of resource and information prerequisites. Most existing project planning tools are usually based on the critical path method CPM, which, typically, only one type of constraints i.e., the PROCESS constraints concerning precedence relationships of activities, is modeled. The CPM does not provide the means to deal with many hidden constraints regarding resource supply and information acquisition. Without identifying these hidden constraints explicitly, it is hard to control and reduce the workflow uncertainties that result in process variability. Making reliable work plans is important in achieving high productivity and continuous workflow. Existing CPM-based planning tools lack the ability to manage the hidden constraints in the supply chain and information flow with respect to resource and information availabilities. As a result, the quality of production is vulnerable to many uncertainties that are difficult to eliminate or reduce. A new tool, Integrated Production Scheduler, is introduced to ameliorate the reliability of construction look-ahead plans by modeling the resource and information constraints in addition to the process constraints for construction processes. Title - Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey. Author – Gunduz M. To identify delay factors on construction projects and analyse these factors with the relative importance index method. The relative importances of these delay factors were quantified by the relative importance index method. The ranking of the factors and groups were demonstrated according to their importance level on delay. To identify the delay factors in construction projects because delays are considered to be a serious problem in the construction industry. The common results of delays are late completion of the project, increased cost, disruption of work, loss of productivity, third-party claims, disputes, and abandonment or termination of contracts. Therefore, delays in construction projects give rise to dissatisfaction to all parties involved. Research aimed to (1)identify the delay factors in construction projects, (2)categorize the delay factors in construction projects, (3)quantify the relative importance of delay factors and to demonstrate the ranking of the factors and groups according to their importance with respect to delays, (4)address the factors and groups contributing most to delays, and (5)make recommendations in order to minimize or control delays in construction projects. Title - Identification Of Constraints In Construction Projects To Improve Performance. Author – Lau E. Needs and constraints in a multi-party working situation bring complications in project management. Needs are diversified when the client is a large organization such as a public client or a corporate client. However, constraints in construction projects limit their achievement of high performance. To identify the constraints in construction project working environment and apply the theory of constraints (TOC), which provides practical steps for making organizational decisions in situations in which constraints exist. If constraints are better understood at the outset, it is believed that better performance can be assured. Presently clients’ needs in construction are well discussed, but constraints have yet to be understood in context. The constraints in five categories, they are: (1) economic constraints, (2) legal constraints, (3) environmental constraints, (4) technical constraints, and (5) social constraints. The impacts of these constraints to the construction project were studied. Developing awareness to managing and controlling the constraints in construction working environment for achieving high performance in the construction working environment. Title - An Assessment of the Factors Causing Delays on Building Construction Projects in Uganda. Author – Muhwezi L. To assess the factors causing delays and their effects on building construction projects in Uganda. Eighty one project delay attributes were identified through detailed literature review. Structured interviews and questionnaire survey were
  • 3. Imperial Journal of Interdisciplinary Research (IJIR) Vol-3, Issue-2, 2017 ISSN: 2454-1362, http://www.onlinejournal.in Imperial Journal of Interdisciplinary Research (IJIR) Page 1309 conducted across stakeholders that included among others; consultants, contractors and clients on four selected building projects to gather their views on causes of delay in delivery of projects. The causes of delay under four main groups of consultant related, contractor related, client related and external related and then assessed their impacts on delay using relative importance index (RII) as a basis for analysis. The RII for all delay factors and group of categories was computed so as to rank the factors. Title – Financial related causes contributing to project delays. Author – Rahman H.. Delay in construction projects is a common phenomenon and a costly problem. The issues of financial related delays in construction projects. It identifies the root causes and scrutinises the suitable mitigation actions of financial-related project delays. Four main factors were identified in the literature, namely late payment, poor cash flow management, insufficient financial resources and financial market instability. The result revealed that poor cash flow management is the most significant factor that leads to a project’s delay followed by late payment, insufficient financial resources and financial market instability. Contractors instable financial background, client’s poor financial and business management, difficulties in obtaining loan from financiers and inflation were identified as the most significant underlying causes. The clients play the most important role in reducing the impact of financial problems towards the extent of project’s delay. Several suitable mitigation actions were suggested by the respondents. The importance of having more intensive research that give emphasis on clients achieving a well managed cash flow in order to obtain a prompt payment practice in the construction industry. The greater the delay in payment due to a contractor, the greater the cash flow problems, the greater the extent of delays. The poorer the cash flow management, the greater the cash flow problems, the greater the extent of delays. The greater the shortage of financial resources, the greater the cash flow problems, the greater the extent of delays. The greater the instability of financial market, the greater the cash flow problems, the greater the extent of delays. 3. Scope, Methodology and Purpose. 3.1 Scope:- Following are the objectives of the proposed dissertation work. a) To study and identify the constraints in construction industry for Residential Building Scheme. b) To identify the major root causes of financial related problems that would lead to delays in project. c) To investigate the opinions of the parties upon the actions that they undertake to manage the financial problems. d) To analyse the causes by using quantitative techniques. e) To give suggestive recommendations in order to reduce the delay problems by considering case study. 3.2 Methodology:- For carrying out the proposed work, following methodology will be adopted for data collecting and analysis. a) Collection of preliminary information through literature review. b) Collection of data by surveying amongst the practitioners of building construction. (Engineers, Contractors, Architects, Builders) c) Identifying constraints in delay of construction work. d) Feaslibility study of constraints by using Relative Importance Index Method. e) To give results and conclusion from the data analysed. 3.3 Purpose of Dissertation:- The proposed work will help to identify the constraints which leads to delays in construction work. Suggesting and recommendations made through this project work will be also useful for the industrial people to use the remedial measures so as to improve performance, reduce cost and delays in construction project work. References [1] Chua D. K. H. and Shen L. J., “Key Constraints Analysis with Integrated Production Scheduler” Journal Of Construction Engineering And Management, 7, 2003, pp. 753-764. [2] Gunduz M. , Nielsen Y, and Ozdemir M., “Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey” Journal Of Management In Engineering, 29, 2, 2013, pp. 133-139. [3] Lau E. and Kong J. J., “Identification Of Constraints In Construction Projects To Improve Performance” The Joint International Conference On Construction, Culture, Innovation And Management, 2006, pp - 655-663. [4] Muhwezi L. , Acai J. and Otim G., “An Assessment of the Factors Causing Delays on Building Construction
  • 4. Imperial Journal of Interdisciplinary Research (IJIR) Vol-3, Issue-2, 2017 ISSN: 2454-1362, http://www.onlinejournal.in Imperial Journal of Interdisciplinary Research (IJIR) Page 1310 Projects in Uganda” International Journal of Construction Engineering and Management, 3, 1, 2014, pp. 13-23. [5] Rahman H. A, Takim R and Min W. S., “Financial- related causes contributing to project delays” Journal of Retail & Leisure Property, 8, 3, 2009, pp. 225–238.