2. PREVIOUS MEETING PENDING POINTS STATUS
Sr.
No.
DEPART
MENT
DESCRIPTION STATUS Remarks
1
SAWH-2
(Mech. Maint.)
Crane No. 8 Operator cabin & staircase extension
to be done
Service PR (PR No. 1320023137) has been releases and waiting
for PO confirmation.
New Target Date -
OCT-2021
2
SAWH-1
(Elect. Maint.)
Flux recovery system HMI, PLC program to be
in-house developed with Siemens make.
Complete Material has been received.
50 % of work has been completed for up gradation of PLC
program and rest is under progress.
New Target Date
October-2021
3
New X,Y & Z slide installation with Auto Laser
tracking at tack welding system for Mill up to
speed 10 meters/min.
Under Process.
Material received, installed & cold trial taken successful. Since
mill is in ideal condition, final trial will be taken during mill runs.
New Target Date –
December-2021
4
Flux Recovery System Modification With S7, 300
PLC.
PLC program up gradation work completed 20 percent & rest
work under progress from 200 To 300 series.
.
New Target NOV-
2021
5
Mill Trolley Welding Slide Motor And Drive To
Be Replaced With SBM Series.
Drives and motors are received. Gear box received. Motor &
gear box assembly work done.
New Target Sep-
2021
6
SAWH-2
(Elect. Maint.)
New DC 1500 Elmatech power source
installation & commissioning to be done as a
Master/ Slave combination with Existing system
for increase mill speed up to 10 meters/min.
Under Process.
M/s Elmatech Germany is not confirm plan for site visit due to
COVID-19
New Target Date -
December-2021
7
SAWH-1& 2
(Elect. Maint.)
New Bead grinding machine electrical installation
& commissioning to be done.
SAWH-2 - Work completed - December 2020
SAWH-1 - Under Process for spiral-1
New Target Date for
SAWH 1 - December-
2021
8
JCO-2
Electrical
Maintenance
3MVA & 5MVA transformer painting of JCO &
IBM work to be done.
M/S Laxmi electrical will execute the painting work.
New Target Aug-
2021
JINDAL SAW LIMITED (IPU) SAMAGHOGHA
2
JULY-2021 -DEC-2021
3. PRODUCTION SUMMARY
(July-2021 – December-2021)
Month
CRA Welded pipe
(Mtr.)
IBM (Nos.)
SAWH 1
(Mtr.)
SAWH 2
(Mtr.)
July-2021
August -2021
September-2021
October-2021
November-2021
December-2021
Total
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
3
JULY-2021 -DEC-2021
4. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 - December-2021)
Sr.
No.
Depar
tment
Objective
Key
Performance
Indicator
July-21
Aug-
21
Sep-21 Oct-21 Nov-21 Dec-21
JCO-II
QA/QC (JCO-II)
1
JCO
(QA/QC)
Controlling field non-
conformities.
“0” field non-
conformities
Customer complaints not
more than 3 (other than
product/field non
conformity)
≤3 Customer
complaints
2
3
Certification of ISO 9001
for Seamless CRA pipe
100%
PRODUCTION (JCO-II)
3
JCO
(Production)
Pipe Production
As
per
monthly
Production
Plan
Production
Planning (MT)
Achievement
(MT)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 4
JULY-2021 -DEC-2021
5. QMS OBJECTIVES ACHIEVEMENT REPORT
(JULY-2021 -DEC-2021)
Sr.
No
Depa
rtme
nt
Objective
Key Performance
Indicator
July-21
Aug-
21
Sep-21 Oct-21 Nov-21 Dec-21
5
JCO-2
(Produc
tion)
Control over consumption
of welding consumables
during TIG-Plasma
welding process and ID
TIG welding process (for
square butt weld groove)
As
per
updated
Norms
of
year
2021
Planning
(kg/m)
Achievement
(kg/m)
6
To minimize the total
weld repair length
(Straight welding, Plate
joining and
Circumferential welding)
≤ 0.4% of total weld
length
7
To minimize the rejection
of Bend
0% of Total Production
Bend
Mechanical Maintenance (JCO-II)
8A
JCO-2
(Mecha
nical
Mainte
nance)
JCO Press:
Breakdown time shall
not exceed 95 minutes
per month (30 days).
Base Line: 100
minutes (for 30
working days)-Year
2020 target
Maximum
breakdown
time 95
minutes per
Month (30
days)
Plant running
days in a month
Actual target vs.
plant running
days (Minutes)
Breakdown Time
(Minutes)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 5
JULY-2021 -DEC-2021
6. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
Sr.
No.
Depar
tment
Objective
Key Performance
Indicator
July-21
Aug-
21
Sep-21 Oct-21 Nov-21 Dec-21
8B
JCO
(Mechanica
l
Maintenanc
e)
Edge Miller: Breakdown
time shall not exceed 53
minutes per month (30
days).
Base Line: 55 minutes (for
30 working days)-Year
2020 target
Edge Miller:
Maximum
breakdown
time 53
minutes per
Month (30
days).
Plant running
days in a month
Actual target vs.
plant running days
Breakdown Time
(Minutes)
8C
Welding (TIG Plasma):
Breakdown time shall not
exceed 38 minutes per
month (30 days).
Base Line: 40 minutes (for
30 working days)-Year
2020 target
Maximum
breakdown
time 38
minutes per
Month (30
days).
Plant running
days in a month
Actual target vs.
plant running days
Breakdown Time
(Minutes)
8D
End Facer (1&2):
Breakdown time shall not
exceed 90 minutes per
month (30 days).
Base Line: 95 minutes (for
30 working days)-Year
2020 target
Maximum
breakdown
time 90
minutes per
Month (30
days).
Plant running
days in a month
Actual target vs.
plant running days
Breakdown Time
(Minutes)
Expander (1&2):
Breakdown time shall not
exceed 28 minutes per
month (30 days).
Base Line: 30 minutes (for
30 working days)-Year
2020 target.
Maximum
breakdown
time 28
minutes per
Month (30
days).
Plant running
days in a month
8E
Actual target vs.
plant running days
Breakdown Time
(Minutes)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 6
JULY-2021 -DEC-2021
7. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
Sr.
No.
Depar
tment
Objective
Key Performance
Indicator
July-
21
Aug-
21
Sep-
21
Oct-21
Nov-
21
Dec-
21
9
JCO
(Mecha
nical
Mainten
ance)
2% reduce monthly
consumption of Hydraulic Oil
-68 in JCO plant as compared
to previous year KPI.
Base line- Previous year
(Year 2019) 588
Liters/Month
monthly consumption of
Hydraulic Oil-68 in JCO plant
576 liters/month
10A
IBM 1&2: Breakdown time
shall not exceed 160 minutes
per month (30 days).
Base Line: 165 minutes (for
30 working days)-Year 2020
target.
Maximum
breakdown
time 160
minutes per
Month (30
days).
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown Time
(Minutes)
10B
IBM Hydro tester:
Breakdown time shall not
exceed 48 minutes per month
(30 days).
Base Line: 50 minutes (for 30
working days)-Year 2020
target
Maximum
breakdown
time 48
minutes per
Month (30
days).
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown Time
(Minutes)
Electrical Maintenance (JCO-II)
11A
JCO
(Electric
al
Mainten
ance)
JCO Press: Breakdown time
shall not exceed 238 minutes
per month (30 days).
Base Line: 250 minutes (for
30 working days)-Year 2020
target
.
Maximum
breakdown
time 238
minutes
per Month
(30 days).
Plant running days
in a month
Actual target vs.
plant running days
Breakdown Time
(Minutes)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA
7
JULY-2021 -DEC-2021
8. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
Sr.
No
.
Depart
ment
Objective
Key Performance
Indicator
July-21 Aug-21
Sep-
21
Oct-21
Nov-
21
Dec-
21
11B
JCO
(Electrical
Maintenan
ce)
Edge Miller: Breakdown
time shall not exceed 333
minutes per month (30 days).
Base Line: 350 minutes (for
30 working days)-Year 2020
target
.
Maximum
breakdown
time 333
minutes per
Month (30
days).
Plant running days
in a month
Actual target vs.
plant running days
Breakdown Time
(Minutes)
11C
Welding (TIG Plasma):
Breakdown time shall not
exceed 613 minutes per
month (30 days).
Base Line: 645 minutes (for
30 working days)-Year 2020
target
Maximum
breakdown
time 613
minutes per
Month (30
days).
Plant running days
in a month
Actual target vs.
plant running days
Breakdown Time
(Minutes)
11D
Expander (1&2): Breakdown
time shall not exceed 100
minutes per month (30 days).
Base Line: 105 minutes (for
30 working days)-Year 2020
target
Maximum
breakdown
time 100
minutes per
Month (30
days).
Plant running days
in a month
Actual target vs.
plant running days
Breakdown Time
(Minutes)
11E
Hydro tester: Breakdown
time shall not exceed 109
minutes per month (30 days).
Base Line: 115 minutes (for
30 working days)-Year 2020
target
Maximum
breakdown
time 109
minutes per
Month (30
days).
Plant running days
in a month
Actual target vs.
plant running days
Breakdown Time
(Minutes)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA
8
JULY-2021 -DEC-2021
9. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
Sr.
No
.
Depa
rtme
nt
Objective
Key Performance
Indicator
July-
21
Aug-
21
Sep-21
Oct-
21
Nov-
21
Dec-
21
12
JCO-2
(Electrica
l
Maintena
nce)
2% Reduction in
consumption of electrical
power in non production
area (Store, Admin, Plant
light and office light) as
compared to year 2020
Power consumption in
year 2020 = 171490 KWh
Maximum power
consumption in non
production area 168060 KWh
for the year 2021
13A
IBM 1&2 :Breakdown time
shall not exceed 100
minutes per month (30
days).
Base Line: 105 minutes (for
30 working days)-Year
2020 target
Maximum
breakdown
time 100
minutes per
Month (30
days).
Plant running
days in a
month
Actual target
vs. plant
running days
Breakdown
Time
(Minutes)
13B
IBM End Facer:
Breakdown time shall not
exceed 119 minutes per
month (30 days).
Base Line: 125 minutes
(for 30 working days)-Year
2020 target
Maximum
breakdown
time 119
minutes per
Month (30
days).
Plant running
days in a
month
Actual target
vs. plant
running days
Breakdown
Time
(Minutes)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 9
JULY-2021 -DEC-2021
10. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
Sr
.
N
o.
Depart
ment
Objective
Key Performance
Indicator
July-21
Aug-
21
Sep-21 Oct-21 Nov-21 Dec-21
SAWH-Unit (Spiral I & Spiral II)
QA/QC (SAWH)
14
SAWH
(QA/QC)
To ensure No
Customer Complaint
with regards to
Product Quality
Zero (0) customer
Complaints
SAWH-1
SAWH-2
15
No Non Conformity
in a month by Third
Party Inspection
Agency (TPIA)
during Final Visual
and Dimensional
Inspection stage.
No non conformity
by TPIA during
final visual and
dimensional
inspection stage.
SAWH-1
SAWH-2
16
X-Ray film
Consumption due to
RT and DRT shall
not exceed 1.38%
during API order
X-Ray film
consumption on
A/C of RT &
DRT= 1.38 %
maximum.
SAWH-1
SAWH-2
JINDAL SAW LIMITED (IPU) SAMAGHOGHA
10
JULY-2021 -DEC-2021
11. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
Sr.
No.
Depar
tment
Objective
Key Performance
Indicator
July-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21
PRODUCTION (SAWH)
17
SAWH
(Produc
tion)
Pipe Production
As per
monthly
Production
Plan
SAWH-1
SAWH-2
28
To reduce the
milling inserts
consumption
0.12
insert/MT
SAWH-1
SAWH-2
19
To reduce the weld
repair length
0.006 % of
total weld
length
produced
SAWH-1
SAWH-2
20
To reduce the
consumption of
beveling inserts
0.017
insert/MT
SAWH-1
SAWH-2
JINDAL SAW LIMITED (IPU) SAMAGHOGHA
11
JULY-2021 -DEC-2021
12. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
Sr.
No.
Depart
ment
Objective
Key Performance
Indicator
July-21
Aug-
21
Sep-21 Oct-21 Nov-21 Dec-21
MECH. MAINTENANCE (SAWH)
For SAWH-1 Plant (Monthly Breakdown Time)
21A
SAWH-
1
(Mech.
Mainten
ance)
Forming Mill: Breakdown
time shall not exceed 480
minutes per month (30
days).
Base Line: 490 minute (for
30 working days)-Year 2020
target
Maximum
breakdown
time 480
minutes per
Month (30
days).
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown
Time (Minutes)
21B
Welding (ID/OD 1 +
ID/OD 2 + ID/OD 3):
Breakdown time shall not
exceed 275 minutes per
month (30 days).
Base Line: 290 minute (for
30 working days)-Year 2020
target
Maximum
breakdown
time 275
minutes per
Month (30
days).
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown
Time (Minutes)
21C
Hydro tester: Breakdown
time shall not exceed 320
minutes per month (30
days).
Base Line: 335 minute (for
30 working days)-Year 2020
target
Maximum
breakdown
time 320
minutes per
Month (30
days)
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown
Time (Minutes)
JULY-2021 -DEC-2021
JINDAL SAW LIMITED (IPU) SAMAGHOGHA
12
13. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 13
Sr.
No.
Depart
ment
Objective
Key Performance
Indicator
July-
21
Aug-
21
Sep-
21
Oct-21
Nov-
21
Dec-
21
For SAWH-2 Plant (Monthly Breakdown Time)
21
A
SAWH-
2
(Mech.
Mainte
nance)
Forming Mill: Breakdown
time shall not exceed 960
minutes per month (30 days).
Base Line: 980 minute (for
30 working days)-Year 2020
target
Maximum
breakdown
time 960
minutes per
Month (30
days).
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown Time
(Minutes)
21
B
Welding (ID/OD 2 + ID/OD
3 + ID/OD 4): Breakdown
time shall not exceed 720
minutes per month (30 days).
Base Line: 760 minute (for
30 working days)-Year 2020
target
Maximum
breakdown
time 720
minutes per
Month (30
days).
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown Time
(Minutes)
21
C
Hydro tester: Breakdown
time shall not exceed 585
minutes per month (30 days).
Base Line: 600 minute (for
30 working days)-Year 2020
target.
Maximum
breakdown
time 585
minutes per
Month (30
days)
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown Time
(Minutes)
22
Hydraulic oil consumption is
reduced to 520 liters for year
2021 (Reduced by 30 liters)
Base line-550 liters (Year
2020 target)
Maximum
consumption
of Hydraulic
oil 520 liters
per month
SAWH-1
SAWH-2
JULY-2021 -DEC-2021
14. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
Sr.
No.
Depart
ment
Objective
Key Performance
Indicator
July-21
Aug-
21
Sep-21 Oct-21 Nov-21 Dec-21
ELECTRICAL MAINTENANCE
For SAWH-1 Plant (Monthly Breakdown Time)
23A
SAWH-1
(Elec.
Maintena
nce)
Forming Mill: Breakdown
time shall not exceed
1164minutes per month (30
days).
Base Line: 1225 minutes (for
30 working days)-Year 2020
target
Maximum
breakdown
time 1164
minutes per
Month (30
days)
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown Time
(Minutes)
23B
Welding (ID/OD 1 + ID/OD
2 + ID/OD 3): Breakdown
time shall not exceed
637minutes per month (30
days).
Base Line: 670 minutes (for
30 working days)-Year 2020
target
Maximum
breakdown
time 637
minutes per
Month (30
days)
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown Time
(Minutes)
For SAWH-2 Plant (Monthly Breakdown Time)
23A
SAWH-2
(Elec.
Maintena
nce)
Forming Mill: Breakdown
time shall not exceed 172
minutes per month (30 days).
Base Line: 175 minutes (for
30 working days)-Year 2020
target
Maximum
breakdown
time 172
minutes per
Month (30
days)
Plant running
days in a
month
Actual target
vs. plant
running days
Breakdown
Time (Minutes)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 14
JULY-2021 -DEC-2021
15. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
Sr.
No.
Depart
ment
Objective
Key Performance
Indicator
July-21
Aug-
21
Sep-21 Oct-21 Nov-21
Dec-
21
23B
SAWH -2
(Elec.
Maintenance)
Welding (ID/OD 2 + ID/OD 3
+ ID/OD 4): Breakdown time
shall not exceed 1188 minutes
per month (30 days).
Base Line: 1250 minutes (for 30
working days)-Year 2020 target
Maximum
breakdown time
1188 minutes
per Month (30
days)
Plant running
days in a month
Actual target vs.
plant running
days
Breakdown
Time (Minutes)
24
2% Reduction in Non
Production Area Power
Consumption (Store, Office
Building, High Mast Tower &
Street Light) from previous year
(year 2020) actual consumption
Spiral-1 Plant - Base Line =
42640 kWh
Spiral-2 Plant - Base Line=
153990 kWh
Maximum
power
consumption in
non production
area for the year
2021
Spiral-1 Plant
– 41787 kWh
Spiral-2 Plant
– 150910 kWh
SAWH-1
SAWH-2
DISPATCH
25
Dispatch
Damages in Pipe and Bend on
the account of product handling.
0
26
TPI/QC complaint on the
account of pipe handling.
0
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 15
JULY-2021 -DEC-2021
16. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 16
JULY-2021 -DEC-2021
Sr.
No
.
Depart
ment
Objective
Key
Performanc
e Indicator
July-21
Aug-
21
Sep-
21
Oct-21 Nov-21 Dec-21
HR (Human Recourse)
27
HR (Human
Recourse)
To impart minimum 8800 man hours
of Technical & System related
training in the current year
Minimum 8800
man hours in
year 2021
Stores
28
Stores
Conversion of material gate entry
into SAP Goods receipt
(MIGO) within 48 hours – 95 %
95 %
29
Availability of material require
planning (mini – max items) and
safety items
99.5%
Purchase (Non Raw Material)
30
Purchase
(NRM)
PROCUREMENT CYCLE
TIME: 94% of total approved line
items, having detailed information to
be converted into purchase
order/work order within 30 days.
94%
31
REJECTION LEVEL/QUALITY
OF ITEMS PROCURED - Quality
of items purchased must be in line
with user requirement which is to be
reflected via rejection. Rejections
level (cumulative average) should be
as low as 2% of total items received
(monthly).
<2.0%
17. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 17
Sr.
No.
Depart
ment
Objective
Key
Performance
Indicator
Achievement in Q1-Q4 of FY 2021-2022
Purchase Raw Material (For Financial Year 2021-2022)
32
Purchase
(Raw
Material)
Upgrade at least one Steel Supplier for a
higher Grade
100%
33
Add at least one Steel Mill for API Grade
(Non Sour/Sour) during the assessment
year
100%
Marketing (For Financial Year 2021-2022)
34
Marketing
(SAWH and
IBM)
Aiming to obtain orders from new
customer.
6
35
Aiming to achieve customer satisfaction
index FY 2021-22
9.25
36
Aiming a total revenue generation in FY
2021-22 in large diameter business..
Approx. 4000
Crores
JULY-2021 -DEC-2021
18. QMS OBJECTIVES ACHIEVEMENT REPORT
(July-2021 – December-2021)
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 18
Sr.
No.
Depart
ment
Objective
Key
Performance
Indicator
Achievement in Q1-Q4 of FY 2020-2021
Purchase Raw Material for CRA Pipe
37
Purchase
(Raw
Material-
CRA Pipes)
Add at least one foreign vendor of CRA
Steel (Coil/Plate) during this assessment
year ( April 21 to March 22)
100% on
Successful
evaluation as
per our
procedure
38
To Develop at least one Welding
Consumable supplier for CRA steel
during this assessment year (April 21 to
March 22)
100% on
Successful
evaluation as
per our
procedure
Marketing _ CRA Welded pipe (For Financial Year 2021-2022)
39
Marketing
(CRA
Welded pipe)
Aiming to achieve average Customer
Satisfaction index
4.5
40 Order booking
2000 Ton
Minimum
41 Developing New Customers 5 new customers
42 Grade and Size Enhancement with EIL 100%
JULY-2021 -DEC-2021
19. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
19
JULY-2021 -DEC-2021
Data analysis for Dimensional, Mechanical & Chemical requirement, refer
project histogram (attached as separate file).
28. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
28
JULY-2021 -DEC-2021
IBM 1 & 2: BREAKDOWN ANALYSIS (Mechanical Maintenance)
IBM Hydro tester
29. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
29
JULY-2021 -DEC-2021
JCO PRESS & EDGE MILLER : Breakdown Analysis (Electrical Maintenance)
JCO PRESS EDGE MILLER
WELDING TIG PLASMA
EXPANDER(1&2)
HYDROTESTER
30. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
30
JULY-2021 -DEC-2021
2% Reduction in consumption of electrical power in non production area
(Store, Admin, Plant light and office light)
31. DATA ANALYSIS
JINDAL SAW LIMITED (IPU) SAMAGHOGHA
31
JULY-2021 -DEC-2021
Breakdown Analysis (Electrical Maintenance) END FACER , IBM 1&2
IBM 1&2 END FACER
32. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
32
JULY-2021 -DEC-2021
SR
NO.
DATE
B/D
(MIN)
M/C PROBLM CAUSE OF PROBLEM ACTION TAKEN
1
Major Breakdown Summary and Action Taken
33. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
33
SAWH 1&2 (QA/QC) :
Data analysis for Dimensional, Mechanical & Chemical requirement - refer project histogram
attached as separate file.
JULY-2021 -DEC-2021
SAWH 1 SAWH 2
35. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
35
SAWH 1&2 (QA/QC) :
JULY-2021 -DEC-2021
No non conformity by TPIA in a month (JULY 2021 – DEC 2021)
36. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
36
SAWH 1&2 (QA/QC)
X-Ray Film Consumption due to RT & DRT shall not exceed 1.38% for API Orders
JULY-2021 -DEC-2021
37. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
37
SAWH 1&2 (QA/QC)
RAW MATERIAL YIELD (%) (JULY 2021 – DEC 2021)
JULY-2021 -DEC-2021
38. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
38
SAWH 1&2 (QA/QC) JULY 2021 – DEC 2021
JULY-2021 -DEC-2021
Reason of Achieved Low Yield (SAWH-1 & 2)
39. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
39
SAWH 1&2 (Production) JULYUARY 2021 – DEC 2021
JULY-2021 -DEC-2021
OBJECTIVE :- 100% Pipe Production as per monthly Production Plan
SAWH 2
SAWH 1
40. DATAANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
40
JULY-2021 -DEC-2021
SAWH 1&2 (Production – Forming)
OBJECTIVE :- Reduce the consumption of Milling inserts up to 0.12 Insert/MT
41. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
41
JULY-2021 -DEC-2021
SAWH 1&2 (Production – Finishing)
OBJECTIVE :- Reduce the consumption of Beveling inserts up to 0.017 Insert/MT
SAWH 2
SAWH 1
46. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
46
JULY-2021 -DEC-2021
DISPATCH
Damages in Pipe and Bend on the account of Product Handling
47. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
47
JULY-2021 -DEC-2021
DISPATCH (JULY-21 TO DEC-21)
TPI/QC Complaint on the account of pipe handling
48. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
48
JULY-2021 -DEC-2021
Human Resources (JULY-21 TO DEC-21)
Minimum 8800 man hours of Technical & System related training in current year
49. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
49
JULY-2021 -DEC-2021
HR Dept. (JULY-21 TO DEC-21)
Minimum 8800 man hours of technical & System related training in current year
Total Training (Technical & System) Performance Report
(JULY’2021– DEC’2021)
S. No. Month MCS Staff Worker
Total
Participants
Total
Man
hours
Cumulative
Man hours
1
2
3
4
5
6
Total
Note :
50. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
50
JULY-2021 -DEC-2021
STORE - (JULY 2021 TO DEC 2021)
Objective: Conversion of Material Gate Entry into SAP Goods Receipt
(MIGO) within 48 hours
51. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
51
JULY-2021 -DEC-2021
Note : Due to Corona Virus (Covid -19) all trainings cancelled from March’21
Objective: Availability of Materials requires planning (Min – Max items) and Safety items
STORE - (JULY 2021 TO DEC 2021)
52. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
52
JULY-2021 -DEC-2021
PURCHASE (NRM) (JULY 2021 TO DEC 2021)
Objective: Minimum 94% of total approved line items, having detailed
information to be converted into purchase order/work order within 30 days.
53. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
53
JULY-2021 -DEC-2021
MARKETING (IBM & SAWH Pipes)
Hit Rate Analysis (Q1 ~ Q4 of FY 2021-22)
54. DATA ANALYSIS
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
54
JULY-2021 -DEC-2021
MARKETING (IBM & SAWH Pipes)
Hit Rate Analysis (Q1 ~ Q4 of FY 2021-22)
55. DATA ANALYSIS
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 55
JULY-2021 -DEC-2021
MARKETING (IBM & SAWH Pipes)
LOSS INQUIRY ANALYSIS – EXPORTS (Q1 ~ Q4 of FY 2021-22)
56. DATA ANALYSIS
JINDAL SAW LIMITED (IPU) SAMAGHOGHA 56
JULY-2021 -DEC-2021
MARKETING (IBM & SAWH Pipes)
Statistical analysis for reasons of Loss of projects
(Q1 ~ Q4 of FY 2021-22)
59. CUSTOMER FEEDBACK, COMPLAINT & SATISFACTION
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
59
JULY-2021 -DEC-2021
No customer complaint received in CRA Welded pipe, SAWH & IBM
unit during JULY’ 2021 – DEC’2021.
60. PRODUCTION & REJECTION REPORT
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
60
JULY-2021 -DEC-2021
CRA Welded Pipe
Month Pipes Produced (Mtr.)
Rejection
(Full Pipe Rejection + End
Cut/Off) (Mtr.)
Remarks
July-2021
August -2021
September-2021
October-2021
November-2021
December-2021
Total
61. PRODUCTION & REJECTION REPORT
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
61
JULY-2021 -DEC-2021
SAWH -1 (JULY 2021 – DEC 2021)
Month Pipes Produced (Mtr.)
Rejection
(Full Pipe Rejection + End
Cut/Off) (Mtr.)
Remarks
July-2021
August -2021
September-2021
October-2021
November-2021
December-2021
Total
62. PRODUCTION & REJECTION REPORT
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
62
JULY-2021 -DEC-2021
SAWH-2 (JULY 2021 – DEC 2021)
Month Pipes Produced (Mtr.)
Rejection
(Full Pipe Rejection + End Cut/Off)
(Mtr.)
Remarks
July-2021
August -2021
September-2021
October-2021
November-2021
December-2021
Total
63. PRODUCTION & REJECTION REPORT
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
63
JULY-2021 -DEC-2021
HOT INDUCTION BEND (IBM)
Month
Bend Produced
(Nos.)
Bend Rejected (Nos.) Remarks
July-2021
August -2021
September-2021
October-2021
November-2021
December-2021
Total
64. JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
64
STATUS OF PREVENTIVE ACTION
JULY-2021 -DEC-2021
Ref .
Potential NC
Description of
Potential non
conformance
Root cause Preventive Actions Responsibility Status
-- -- -- -- -- --
65. JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
65
Status of Corrective & Preventive Action
JULY-2021 -DEC-2021
Ref . Non
Conformance
Department
Description of Detected /
Potential non conformance
Root cause Actions Taken Remarks
Objective was not
achieved in month
May- 2021
66. JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
66
Status of Corrective & Preventive Action (Product NC)
JULY-2021 -DEC-2021
Ref . Non
Conformance
Departmen
t
Description of
Detected/Potential non
conformance
Root cause Actions Taken Remarks
67. JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
67
Status of Corrective & Preventive Action (Internal
Audit NC Nov-2021)
JULY-2021 -DEC-2021
Ref . Non
Conformance
Departmen
t
Description of
Detected/Potential non
conformance
Root cause Actions Taken Remarks
68. Risk Assessment
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
68
Information for Risk Assessment & Contingency Planning has been reviewed
in month of December 2021.
JULY‘21 TO DEC'21
69. List of Revised/New Procedure for Quality Management System
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
69
Sr. no. Procedure Description Document No. Version Effective Date
JULY‘21 TO DEC‘21
71. Status of Improvements Planned in Previous MRM
Sr.
No.
Department Description Status New Target Remark
1
SAWH-2 (Electrical
Maintenance
ID/OD-1 (OLWS) new machine Installation
& commissioning.
Procurement 20% material received &
electrical panel will be received end of the
July month.
Aug-2021
2
JCO-II Electrical
maintenance
JCO Hydro tester High Pressure Pump 100
HP Driven By VFD Variable Frequency
Drive.
VFD (Variable Frequency Drive)
installation is postponed due to pressure
is control through control valve.
3
JCO-2 Electrical
Maintenance
JCO-2 11KV HT Breaker Replacement With
ABB VD4
Work Is Under Progress. July-21
4 JCO-2 Substation PCC Panel Painting Work. Work Is Under Progress. July-21
5 IBM Substation PCC Panel Painting Work.
Work Is Under Progress.
July-21
6
TR-3 FEED,MTB DC Drive To Be Replaced
With 6RA80
Work Is Under Progress.
September-21
7
40 NOS 150W LED Shed HIBAY Light To Be
Replaced With HPSV Light
Work Is Under Progress. August-21
8
SAWH 2 (Mech.
Maint)
EOT Crane Bay Platform Installation
Raw Materials Are Received. Service Po
Pending
Oct-2021
Depends On
Plant Idle
Time
9
EOT Crane No-8, Cable Carrier Side Platform
Installation
Raw Materials Are Received. Service Po
Pending
Oct-2021
Depends On
Plant Idle
Time
JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
71
JULY'21 TO DEC'21
73. JINDAL SAW LIMITED (IPU)
SAMAGHOGHA
73
JULY'21 TO DEC'21
Changes Applicable to Petroleum, Petrochemical and Natural Gas Industry
Standards
S. No Standard/
Specifications
Key Changes Remark