SlideShare a Scribd company logo
1 of 11
Download to read offline
How Good is My Project Management Framework?
I believe that sponsor is absolutely positive stakeholder in any project. If sponsor educates himself on project management best practice and do not leave the project only to vendor’s project
management wisdom then project cannot fail miserable.
Presented by
Hari Prasad Thapliyal
Agilest & Project Management Trainer, Coach & Consultant
(MBA, MCA, PGDOM, PGDFM, CIC, PMP, PMI-ACP, CSM, SCPO, SDC
PRINCE2-Trainer, Scrum Certified Trainer, Microsoft Certified Trainer, ZED Master Trainer)
This Presentation is based on the GAPPS, 2007
http://globalpmstandards.org/wp-content/uploads/2014/12/GAPPS_Project_Manager_v1.1150411_A4.pdf
If projects in your organization are continuously challenged or failing
at unprecedented rate but you are not able to figure out what is
going wrong then simply compare domains and practices mentioned
in the following slide and know the cause of trouble. You need them
to manage a project successfully.
Is this Presentation for me?
1. Manage Stakeholder Relationships
2. Manage Development of the Plan for the Project
3. Manage Project Progress
4. Manage Product Acceptance
5. Manage Project Transitions
6. Evaluate and Improve Project Performance
Domains to Manage Projects
1.1 Ensure that stakeholder interests are identified and addressed.
1.1.1 Relevant stakeholders are determined.
1.1.2 Stakeholder interests are investigated and documented.
1.1.3 Stakeholder interests are considered when making project decisions.
1.1.4 Actions to address differing interests are implemented.
1.2 Promote effective individual and team performance.
1.2.1 Interpersonal skills are applied to encourage individuals and teams to perform effectively.
1.2.2 Individual project roles are defined, documented, communicated, assigned, and agreed to.
1.2.3 Individual and team behavioural expectations are established.
1.2.4 Individual and team performance is monitored and feedback provided.
1.2.5 Individual development needs and opportunities are recognised and addressed.
1.3 Manage stakeholder communications.
1.3.1 Communication needs of stakeholders are identified and documented.
1.3.2 Communication method, content, and timing is agreed to by relevant stakeholders.
1.3.3 Information is communicated as planned, and variances are identified and addressed.
1.4 Facilitate external stakeholder participation.
1.4.1 External stakeholder participation is planned, documented, and communicated.
1.4.2 External stakeholder participation is supported as planned, and variances are addressed.
1- Manage Stakeholder Relationships
2.1 Define the work of the project.
2.1.1 A shared understanding of desired project outcomes is agreed to with relevant stakeholders.
2.1.2 Processes and procedures to support the management of the project are identified, documented, and communicated to relevant stakeholders.
2.1.3 Work-items required to accomplish the product of the project are determined.
2.1.4 The work-items and completion criteria are agreed to by relevant stakeholders.
2.1.5 Assumptions, constraints, and exclusions are identified and documented.
2.1.6 Relevant knowledge gained from prior projects is incorporated into the plan for the project where feasible.
2.2 Ensure the plan for the project reflects relevant legal requirements.
2.2.1 Relevant legal requirements are identified, documented, and communicated to relevant stakeholders.
2.2.2 Potential for conflicts caused by legal requirements are identified and addressed in the plan for the project.
2.3 Document risks and risk responses for the project.
2.3.1 Risks are identified in consultation with relevant stakeholders.
2.3.2 Risk analysis techniques are used to evaluate risks and then prioritise them for further analysis and response planning.
2.3.3 Responses to risks are identified and agreed to by relevant stakeholders.
2.4 Confirm project success criteria.
2.4.1 Measurable project success criteria are identified and documented.
2.4.2 Project success criteria are agreed to by relevant stakeholders.
2.5 Develop and integrate project baselines.
2.5.1 Resource requirements are determined.
2.5.2 Schedule is developed based on resource requirements, resource availability, and required sequence of work-items.
2.5.3 Budget is developed based on resource requirements.
2.5.4 Conflicts and inconsistencies in the plan for the project are addressed.
2.5.5 The plan for the project is approved by authorised stakeholders and communicated to relevant stakeholders.
2- Manage Development of the Plan for the Project
3.1 Monitor, evaluate, and control project performance.
3.1.1 Performance of the project is measured, recorded, evaluated, and reported against the project baselines.
3.1.2 Processes and procedures are monitored and variances addressed.
3.1.3 Completed work-items are reviewed to ensure that agreed completion criteria were met.
3.1.4 Corrective action is taken as needed in support of meeting project success criteria.
3.2 Monitor risks to the project.
3.2.1 Identified risks are monitored.
3.2.2 Changes to the external environment are observed for impact to the project.
3.2.3 Applicable legal requirements are monitored for breaches and conflicts.
3.2.4 Actions are taken as needed.
3.3 Reflect on practice.
3.3.1 Feedback on personal performance is sought from relevant stakeholders and addressed.
3.3.2 Lessons learned are identified and documented.
3- Manage Project Progress
4.1 Ensure that the product of the project is defined.
4.1.1 Desired characteristics of the product of the project are identified in consultation with relevant stakeholders.
4.1.2 Characteristics of the product of the project are documented and agreed to by relevant stakeholders.
4.2 Ensure that changes to the product of the project are monitored and controlled.
4.2.1 Variances from agreed product characteristics are identified and addressed.
4.2.2 Requests for changes to the product of the project are documented, evaluated, and addressed in accordance with the change control
processes for the project.
4.2.3 Approved product changes are implemented.
4.3 Secure acceptance of the product of the project.
4.3.1 The product of the project is evaluated against the latest agreed characteristics and variances addressed where necessary.
4.3.2 The product of the project is transferred to identified stakeholders and accepted.
4- Manage Product Acceptance
5.1 Manage project start-up.
5.1.1 Authorisation to expend resources is obtained from the appropriate stakeholders.
5.1.2 Start-up activities are planned and conducted.
5.2 Manage transition between project phases.
5.2.1 Acceptance of the outputs of a prior phase is obtained from the relevant stakeholders.
5.2.2 Authorisation to begin work on a subsequent phase is obtained from the appropriate stakeholders.
5.2.3 Transition activities are planned and conducted.
5.3 Manage project closure.
5.3.1 Closure activities are planned and conducted.
5.3.2 Project records are finalised, signed off, and stored in compliance with processes and procedures.
5- Manage Project Transitions
6.1 Develop a plan for project evaluation.
6.1.1 Purpose, focus, and criteria of evaluation are determined.
6.1.2 Relevant evaluation techniques are determined.
6.2 Evaluate the project in accordance with plan.
6.2.1 Performance data is collected and analysed in accordance with the evaluation plan.
6.2.2 Evaluation process engages relevant stakeholders.
6.3 Capture and apply learning.
6.3.1 Knowledge sharing and skill transfer is encouraged among relevant stakeholders.
6.3.2 Results of evaluations are documented and made available for organisational learning.
6.3.3 Potential improvements are identified, documented and communicated to relevant stakeholders.
6.3.4 Improvements agreed for this project are applied.
6- Evaluate and Improve Project Performance
hari.prasad@vedavit-ps.com
+91 9535999336
https://in.linkedin.com/in/harithapliyal
http://twitter.com/pmlogy
http://pmlogy.com/
http://facebook.com/harithapliyalpage
https://in.pinterest.com/harithapliyal
https://www.instagram.com/thapliyal.h

More Related Content

What's hot

SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01Steven Leahy
 
Project integration management
Project  integration managementProject  integration management
Project integration managementdeep sharma
 
03 project management processes for a project
03  project management processes for a project03  project management processes for a project
03 project management processes for a projectAla Ibrahim
 
Pm processes, groups and k areas map and domains
Pm processes, groups and k areas map and domainsPm processes, groups and k areas map and domains
Pm processes, groups and k areas map and domainsMannay88
 
PMI knowledge areas and processes
PMI knowledge areas and processesPMI knowledge areas and processes
PMI knowledge areas and processesWiktor Kabatc
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
Pmbok flow 5_process
Pmbok flow 5_processPmbok flow 5_process
Pmbok flow 5_processPedro Arcas
 
PMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENTPMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENTHisham Ali,PMP
 
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...Shamil Habet
 
Pmbok 04 project integration management
Pmbok 04 project integration managementPmbok 04 project integration management
Pmbok 04 project integration managementWisam Shamroukh
 

What's hot (20)

Pmp in summary
Pmp in summaryPmp in summary
Pmp in summary
 
SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01
 
Project managment 2
Project managment 2Project managment 2
Project managment 2
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
PMBOK 5th Edition Schema
PMBOK 5th Edition SchemaPMBOK 5th Edition Schema
PMBOK 5th Edition Schema
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
Portfolio mostafa saad_jan_2020
Portfolio mostafa saad_jan_2020Portfolio mostafa saad_jan_2020
Portfolio mostafa saad_jan_2020
 
03 project management processes for a project
03  project management processes for a project03  project management processes for a project
03 project management processes for a project
 
Pm processes, groups and k areas map and domains
Pm processes, groups and k areas map and domainsPm processes, groups and k areas map and domains
Pm processes, groups and k areas map and domains
 
Itto pmbok guide 6th edition
Itto   pmbok guide 6th editionItto   pmbok guide 6th edition
Itto pmbok guide 6th edition
 
PMI knowledge areas and processes
PMI knowledge areas and processesPMI knowledge areas and processes
PMI knowledge areas and processes
 
Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Pmbok flow 5_process
Pmbok flow 5_processPmbok flow 5_process
Pmbok flow 5_process
 
The Project Management Plan in 20 steps
The Project Management Plan in 20 stepsThe Project Management Plan in 20 steps
The Project Management Plan in 20 steps
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
PMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENTPMP chapter(4) INTEGRATION MANAGEMENT
PMP chapter(4) INTEGRATION MANAGEMENT
 
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
 
Pmbok 04 project integration management
Pmbok 04 project integration managementPmbok 04 project integration management
Pmbok 04 project integration management
 

Viewers also liked

Портфель проектов: портфель без ручки или реактивный ранец
Портфель проектов: портфель без ручки или реактивный ранецПортфель проектов: портфель без ручки или реактивный ранец
Портфель проектов: портфель без ручки или реактивный ранецVadim Bogdanov PMP, PfMP, MVP, MCT, MCTS
 
Technology for Citizen Voices
Technology for Citizen VoicesTechnology for Citizen Voices
Technology for Citizen VoicesStuart Shulman
 
FDates Market Timing - Setups
FDates Market Timing - SetupsFDates Market Timing - Setups
FDates Market Timing - SetupsFDates
 
Joy canzoneri
Joy canzoneriJoy canzoneri
Joy canzonerix0joyx0
 
初心者のためのUser Centered Designの考え方(入門編)
初心者のためのUser Centered Designの考え方(入門編)初心者のためのUser Centered Designの考え方(入門編)
初心者のためのUser Centered Designの考え方(入門編)Katsumi Tazuke
 
Ccb1sandra mv
Ccb1sandra mvCcb1sandra mv
Ccb1sandra mvbegona10
 
CodersTrust Product Presentation
CodersTrust Product PresentationCodersTrust Product Presentation
CodersTrust Product PresentationFerdinand Kjærulff
 
Narciso.it
Narciso.itNarciso.it
Narciso.itciorci
 
Business plan presentation_format (1)
Business plan presentation_format (1)Business plan presentation_format (1)
Business plan presentation_format (1)BHARAT LIMAYE
 
Cronología de la Cohetería, el Vuelo y la Exploración Espacial: 1806 - 8 de O...
Cronología de la Cohetería, el Vuelo y la Exploración Espacial: 1806 - 8 de O...Cronología de la Cohetería, el Vuelo y la Exploración Espacial: 1806 - 8 de O...
Cronología de la Cohetería, el Vuelo y la Exploración Espacial: 1806 - 8 de O...Champs Elysee Roldan
 

Viewers also liked (19)

Портфель проектов: портфель без ручки или реактивный ранец
Портфель проектов: портфель без ручки или реактивный ранецПортфель проектов: портфель без ручки или реактивный ранец
Портфель проектов: портфель без ручки или реактивный ранец
 
Program Management
Program ManagementProgram Management
Program Management
 
Brown act
Brown actBrown act
Brown act
 
Zotero manual
Zotero manualZotero manual
Zotero manual
 
Technology for Citizen Voices
Technology for Citizen VoicesTechnology for Citizen Voices
Technology for Citizen Voices
 
FDates Market Timing - Setups
FDates Market Timing - SetupsFDates Market Timing - Setups
FDates Market Timing - Setups
 
Joy canzoneri
Joy canzoneriJoy canzoneri
Joy canzoneri
 
初心者のためのUser Centered Designの考え方(入門編)
初心者のためのUser Centered Designの考え方(入門編)初心者のためのUser Centered Designの考え方(入門編)
初心者のためのUser Centered Designの考え方(入門編)
 
How to treat_herpes
How to treat_herpesHow to treat_herpes
How to treat_herpes
 
Ccb1sandra mv
Ccb1sandra mvCcb1sandra mv
Ccb1sandra mv
 
CT Presentation 21.03.2015
CT Presentation 21.03.2015CT Presentation 21.03.2015
CT Presentation 21.03.2015
 
CodersTrust Product Presentation
CodersTrust Product PresentationCodersTrust Product Presentation
CodersTrust Product Presentation
 
Award Maker 4 Teachers
Award Maker 4 TeachersAward Maker 4 Teachers
Award Maker 4 Teachers
 
Narciso.it
Narciso.itNarciso.it
Narciso.it
 
Summit slide loop ny
Summit slide loop nySummit slide loop ny
Summit slide loop ny
 
Business plan presentation_format (1)
Business plan presentation_format (1)Business plan presentation_format (1)
Business plan presentation_format (1)
 
Cronología de la Cohetería, el Vuelo y la Exploración Espacial: 1806 - 8 de O...
Cronología de la Cohetería, el Vuelo y la Exploración Espacial: 1806 - 8 de O...Cronología de la Cohetería, el Vuelo y la Exploración Espacial: 1806 - 8 de O...
Cronología de la Cohetería, el Vuelo y la Exploración Espacial: 1806 - 8 de O...
 
Dagligvarer.nu
Dagligvarer.nuDagligvarer.nu
Dagligvarer.nu
 
Audience Research
Audience ResearchAudience Research
Audience Research
 

Similar to How good is my project management framework

13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management OverviewDavidMcLachlan1
 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration managementreddvise
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfHuyNguyen657394
 
Project management
Project managementProject management
Project managementBiswa Prusty
 
Units 2-11 Project management.ppt By Tol
Units 2-11 Project management.ppt By TolUnits 2-11 Project management.ppt By Tol
Units 2-11 Project management.ppt By TolTolessaSolomon
 
11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management OverviewDavidMcLachlan1
 
Organizational influences and project life cycle
Organizational influences and project life cycleOrganizational influences and project life cycle
Organizational influences and project life cycleAli Adil
 
Day 2-1 PMP.pptx
Day 2-1 PMP.pptxDay 2-1 PMP.pptx
Day 2-1 PMP.pptxAhmedKayed6
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder EngagementDavidMcLachlan1
 
Topic 9 - Project Stakeholder Management.pdf
Topic 9 - Project Stakeholder Management.pdfTopic 9 - Project Stakeholder Management.pdf
Topic 9 - Project Stakeholder Management.pdfHuyNguyen657394
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management FrameworkAarti Dahiya PMP
 
10.2 Manage Communication
10.2 Manage Communication10.2 Manage Communication
10.2 Manage CommunicationDavidMcLachlan1
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OneHossam Maghrabi
 

Similar to How good is my project management framework (20)

13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview
 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration management
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
 
Project management
Project managementProject management
Project management
 
Units 2-11 Project management.ppt By Tol
Units 2-11 Project management.ppt By TolUnits 2-11 Project management.ppt By Tol
Units 2-11 Project management.ppt By Tol
 
11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management Overview
 
Organizational influences and project life cycle
Organizational influences and project life cycleOrganizational influences and project life cycle
Organizational influences and project life cycle
 
PM FrameWork: Module 3
PM FrameWork: Module 3PM FrameWork: Module 3
PM FrameWork: Module 3
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
 
Project managment 3
Project managment 3Project managment 3
Project managment 3
 
Day 2-1 PMP.pptx
Day 2-1 PMP.pptxDay 2-1 PMP.pptx
Day 2-1 PMP.pptx
 
Day 2 PMP.pptx
Day 2 PMP.pptxDay 2 PMP.pptx
Day 2 PMP.pptx
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
 
02.pptx
02.pptx02.pptx
02.pptx
 
Topic 9 - Project Stakeholder Management.pdf
Topic 9 - Project Stakeholder Management.pdfTopic 9 - Project Stakeholder Management.pdf
Topic 9 - Project Stakeholder Management.pdf
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management Framework
 
10.2 Manage Communication
10.2 Manage Communication10.2 Manage Communication
10.2 Manage Communication
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part One
 

More from Hari Thapliyal

Project Professional 2016 - Reports
Project Professional 2016 - ReportsProject Professional 2016 - Reports
Project Professional 2016 - ReportsHari Thapliyal
 
Microsoft Project Online with PowerBI
Microsoft Project Online with PowerBIMicrosoft Project Online with PowerBI
Microsoft Project Online with PowerBIHari Thapliyal
 
Power BI Reporting & Project Online
Power BI Reporting & Project OnlinePower BI Reporting & Project Online
Power BI Reporting & Project OnlineHari Thapliyal
 
Project Professional 2016 - reports
Project Professional 2016 - reportsProject Professional 2016 - reports
Project Professional 2016 - reportsHari Thapliyal
 
Introduction to PMI and PMP
Introduction to PMI and PMPIntroduction to PMI and PMP
Introduction to PMI and PMPHari Thapliyal
 
Project Managment Good Practices
Project Managment Good PracticesProject Managment Good Practices
Project Managment Good PracticesHari Thapliyal
 
Microsoft Project Course with PMP Concepts
Microsoft Project Course with PMP ConceptsMicrosoft Project Course with PMP Concepts
Microsoft Project Course with PMP ConceptsHari Thapliyal
 
Relationship Business-Projects-Operations
Relationship Business-Projects-OperationsRelationship Business-Projects-Operations
Relationship Business-Projects-OperationsHari Thapliyal
 
Value of Project Management Trainings
Value of Project Management TrainingsValue of Project Management Trainings
Value of Project Management TrainingsHari Thapliyal
 

More from Hari Thapliyal (10)

Project Professional 2016 - Reports
Project Professional 2016 - ReportsProject Professional 2016 - Reports
Project Professional 2016 - Reports
 
Microsoft Project Online with PowerBI
Microsoft Project Online with PowerBIMicrosoft Project Online with PowerBI
Microsoft Project Online with PowerBI
 
Power BI Reporting & Project Online
Power BI Reporting & Project OnlinePower BI Reporting & Project Online
Power BI Reporting & Project Online
 
Project Professional 2016 - reports
Project Professional 2016 - reportsProject Professional 2016 - reports
Project Professional 2016 - reports
 
Introduction to PMI and PMP
Introduction to PMI and PMPIntroduction to PMI and PMP
Introduction to PMI and PMP
 
Project Managment Good Practices
Project Managment Good PracticesProject Managment Good Practices
Project Managment Good Practices
 
Microsoft Project Course with PMP Concepts
Microsoft Project Course with PMP ConceptsMicrosoft Project Course with PMP Concepts
Microsoft Project Course with PMP Concepts
 
Benefits of EPM
Benefits of EPMBenefits of EPM
Benefits of EPM
 
Relationship Business-Projects-Operations
Relationship Business-Projects-OperationsRelationship Business-Projects-Operations
Relationship Business-Projects-Operations
 
Value of Project Management Trainings
Value of Project Management TrainingsValue of Project Management Trainings
Value of Project Management Trainings
 

Recently uploaded

Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 

Recently uploaded (20)

Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 

How good is my project management framework

  • 1. How Good is My Project Management Framework? I believe that sponsor is absolutely positive stakeholder in any project. If sponsor educates himself on project management best practice and do not leave the project only to vendor’s project management wisdom then project cannot fail miserable. Presented by Hari Prasad Thapliyal Agilest & Project Management Trainer, Coach & Consultant (MBA, MCA, PGDOM, PGDFM, CIC, PMP, PMI-ACP, CSM, SCPO, SDC PRINCE2-Trainer, Scrum Certified Trainer, Microsoft Certified Trainer, ZED Master Trainer)
  • 2. This Presentation is based on the GAPPS, 2007 http://globalpmstandards.org/wp-content/uploads/2014/12/GAPPS_Project_Manager_v1.1150411_A4.pdf
  • 3. If projects in your organization are continuously challenged or failing at unprecedented rate but you are not able to figure out what is going wrong then simply compare domains and practices mentioned in the following slide and know the cause of trouble. You need them to manage a project successfully. Is this Presentation for me?
  • 4. 1. Manage Stakeholder Relationships 2. Manage Development of the Plan for the Project 3. Manage Project Progress 4. Manage Product Acceptance 5. Manage Project Transitions 6. Evaluate and Improve Project Performance Domains to Manage Projects
  • 5. 1.1 Ensure that stakeholder interests are identified and addressed. 1.1.1 Relevant stakeholders are determined. 1.1.2 Stakeholder interests are investigated and documented. 1.1.3 Stakeholder interests are considered when making project decisions. 1.1.4 Actions to address differing interests are implemented. 1.2 Promote effective individual and team performance. 1.2.1 Interpersonal skills are applied to encourage individuals and teams to perform effectively. 1.2.2 Individual project roles are defined, documented, communicated, assigned, and agreed to. 1.2.3 Individual and team behavioural expectations are established. 1.2.4 Individual and team performance is monitored and feedback provided. 1.2.5 Individual development needs and opportunities are recognised and addressed. 1.3 Manage stakeholder communications. 1.3.1 Communication needs of stakeholders are identified and documented. 1.3.2 Communication method, content, and timing is agreed to by relevant stakeholders. 1.3.3 Information is communicated as planned, and variances are identified and addressed. 1.4 Facilitate external stakeholder participation. 1.4.1 External stakeholder participation is planned, documented, and communicated. 1.4.2 External stakeholder participation is supported as planned, and variances are addressed. 1- Manage Stakeholder Relationships
  • 6. 2.1 Define the work of the project. 2.1.1 A shared understanding of desired project outcomes is agreed to with relevant stakeholders. 2.1.2 Processes and procedures to support the management of the project are identified, documented, and communicated to relevant stakeholders. 2.1.3 Work-items required to accomplish the product of the project are determined. 2.1.4 The work-items and completion criteria are agreed to by relevant stakeholders. 2.1.5 Assumptions, constraints, and exclusions are identified and documented. 2.1.6 Relevant knowledge gained from prior projects is incorporated into the plan for the project where feasible. 2.2 Ensure the plan for the project reflects relevant legal requirements. 2.2.1 Relevant legal requirements are identified, documented, and communicated to relevant stakeholders. 2.2.2 Potential for conflicts caused by legal requirements are identified and addressed in the plan for the project. 2.3 Document risks and risk responses for the project. 2.3.1 Risks are identified in consultation with relevant stakeholders. 2.3.2 Risk analysis techniques are used to evaluate risks and then prioritise them for further analysis and response planning. 2.3.3 Responses to risks are identified and agreed to by relevant stakeholders. 2.4 Confirm project success criteria. 2.4.1 Measurable project success criteria are identified and documented. 2.4.2 Project success criteria are agreed to by relevant stakeholders. 2.5 Develop and integrate project baselines. 2.5.1 Resource requirements are determined. 2.5.2 Schedule is developed based on resource requirements, resource availability, and required sequence of work-items. 2.5.3 Budget is developed based on resource requirements. 2.5.4 Conflicts and inconsistencies in the plan for the project are addressed. 2.5.5 The plan for the project is approved by authorised stakeholders and communicated to relevant stakeholders. 2- Manage Development of the Plan for the Project
  • 7. 3.1 Monitor, evaluate, and control project performance. 3.1.1 Performance of the project is measured, recorded, evaluated, and reported against the project baselines. 3.1.2 Processes and procedures are monitored and variances addressed. 3.1.3 Completed work-items are reviewed to ensure that agreed completion criteria were met. 3.1.4 Corrective action is taken as needed in support of meeting project success criteria. 3.2 Monitor risks to the project. 3.2.1 Identified risks are monitored. 3.2.2 Changes to the external environment are observed for impact to the project. 3.2.3 Applicable legal requirements are monitored for breaches and conflicts. 3.2.4 Actions are taken as needed. 3.3 Reflect on practice. 3.3.1 Feedback on personal performance is sought from relevant stakeholders and addressed. 3.3.2 Lessons learned are identified and documented. 3- Manage Project Progress
  • 8. 4.1 Ensure that the product of the project is defined. 4.1.1 Desired characteristics of the product of the project are identified in consultation with relevant stakeholders. 4.1.2 Characteristics of the product of the project are documented and agreed to by relevant stakeholders. 4.2 Ensure that changes to the product of the project are monitored and controlled. 4.2.1 Variances from agreed product characteristics are identified and addressed. 4.2.2 Requests for changes to the product of the project are documented, evaluated, and addressed in accordance with the change control processes for the project. 4.2.3 Approved product changes are implemented. 4.3 Secure acceptance of the product of the project. 4.3.1 The product of the project is evaluated against the latest agreed characteristics and variances addressed where necessary. 4.3.2 The product of the project is transferred to identified stakeholders and accepted. 4- Manage Product Acceptance
  • 9. 5.1 Manage project start-up. 5.1.1 Authorisation to expend resources is obtained from the appropriate stakeholders. 5.1.2 Start-up activities are planned and conducted. 5.2 Manage transition between project phases. 5.2.1 Acceptance of the outputs of a prior phase is obtained from the relevant stakeholders. 5.2.2 Authorisation to begin work on a subsequent phase is obtained from the appropriate stakeholders. 5.2.3 Transition activities are planned and conducted. 5.3 Manage project closure. 5.3.1 Closure activities are planned and conducted. 5.3.2 Project records are finalised, signed off, and stored in compliance with processes and procedures. 5- Manage Project Transitions
  • 10. 6.1 Develop a plan for project evaluation. 6.1.1 Purpose, focus, and criteria of evaluation are determined. 6.1.2 Relevant evaluation techniques are determined. 6.2 Evaluate the project in accordance with plan. 6.2.1 Performance data is collected and analysed in accordance with the evaluation plan. 6.2.2 Evaluation process engages relevant stakeholders. 6.3 Capture and apply learning. 6.3.1 Knowledge sharing and skill transfer is encouraged among relevant stakeholders. 6.3.2 Results of evaluations are documented and made available for organisational learning. 6.3.3 Potential improvements are identified, documented and communicated to relevant stakeholders. 6.3.4 Improvements agreed for this project are applied. 6- Evaluate and Improve Project Performance