Road and Water Reconstruction on Queen's Park and Wellesley
1. Road and Water Services Reconstruction on Queen’s Park and Wellesley
1.0 Project Description
This project is part of the City of Toronto’s 2014 Capital Construction Program. [1] The
overall project involves road work that covers areas from Bloor St. to College on Queen's Park
Cres. and from Queen's Park to Yonge St. on Wellesley St.. Figure 1 in Appendix A shows a
map of the construction area. The major components of this project are as follows:
Queen’s Park Crescent: July 21st September 22nd 2014
road resurfacing and sidewalk reconstruction [1]
reconfiguring the Hoskin Ave. and Queen’s Park Cres. intersection [1]
addition of a separated bike lane from Hoskin Ave. to Wellesley St. [1]
Wellesley Street: July 21st December 2014
road and sidewalk reconstruction and separated bike lane construction [1]
watermain service transfer, as well as traffic signal improvements [1]
Prior to any addenda and extra work added to the contract documents, the project was
scheduled to finish in the first week of December 2014 [1].
1.1 Safety On Site
There are numerous safety measures that were applied on site to ensure the overall
safety of both workers and the public. Firstly, all workers on site wore their respective PPE
(boots, helmets, vest). The use of warning signs and cones with reflective sheeting was useful
in terms of directing traffic and pedestrians away from the areas where work was being done
(refer to Figure 2 for a visual). For example, the traffic cones covered the perimeter around the
side of the road on Queen’s Park Cres., where the concrete for the new bike lane curbs was
being poured. This practice made sure that pedestrians wouldn’t step on drying concrete as
they were crossing the street. This also ensured that individual pedestrians, and those walking
their dogs, did not injure their feet on the hot asphalt.
Metal fencing was installed around the perimeter of the north side of Wellesley St. going
towards Yonge St.. As the working crew was there operating on the sidewalks, road bases and
the water services, the public had to be a safe distance away. It separated traffic and
pedestrians from the vicinity of heavy operating equipment such as bulldozers, excavators and
backhoes. Moreover, the fencing was purposed to limit public access to the expensive
construction equipment and materials used on site.
2.0 Detailed Summary of the Construction Process
The following section is a summary of the 3 major components of the project: electrical, water
services, and road work. A detailed weekly account of the project is provided in Appendix A.
4.
2.3.1 Considerations
220,000 people were expected to be on site for a book fair, on the weekend of
September 26th28th so work on Queen’s Park was to be completed by then
Onwards of October 15th, there is an additional cost on concrete and asphalt, as
temperatures below 5 degrees cause segregation in the mix and is too cold to pour
requires the mix to be heated with an additive prior to pouring
protected with thermal blankets to prevent freezing
Concrete cannot be poured during extensive rain; schedule is changed to avoid delays
For example: The crew would pour two days’ worth of concrete the day prior to
expected rain in order to stay on schedule
2.3.2 Weekly Expectations
Complete 250m of sidewalk from Queen’s Park Crescent to Bay Street
Pour 34 loads of sidewalk
Pour 1015 loads of concrete for the road
2.4 Cycling Improvements
A major component of the entire project was the addition of separated bike lanes, known
as cycle tracks, along Queen’s Park Cres. and Wellesley St. These upgraded bike lanes are
part of Toronto’s plan to improve the cycling network in the downtown core with the goal of
making cycling facilities in the city safer and less intimidating for cyclists. [2] The construction of
these cycles tracks began with building the formwork for the concrete which would act as the
boundary that separated the bike lanes from the vehicle lane. Once the formwork was
completed, the pouring of concrete took place. Once poured, the concrete was smoothed and
compacted using floats. The finished bike lane curb along Queen’s Park Cres. can be seen in
Figure 5. Although beneficial to cyclists, the cycle tracks have several adverse effects on
motorists due to the fact that the bike lanes reduce the number of vehicle lanes on the road as
well as reducing the amount of available space for roadside parking.
3.0 Impacts on Vehicular and Pedestrian Traffic
The road resurfacing and sidewalk work being conducted on Queen’s Park Cres.
definitely had major impacts on pedestrian and motorist traffic flow. The road reconstruction,
water services and cycling improvement on Wellesley St. West also will also have similar
implications on vehicular and pedestrian traffic as the whole infrastructure is being changed.
Particularly, there is a reduction of road lanes from two to one in each direction along Queen’s
Park Cres. as part of Toronto’s initiative to provide friendlier cyclist conditions and a more
extensive network of bike lanes. Although cyclist traffic conditions are being improved, it seems
to be at the expense of motorists’ convenience.
As the number of lanes is reduced a vehicular congestion problem around Queen’s Park
Cres. and Wellesley St. is created. In addition, the installation of a curb to separate the bike
10. ● waste managed: bins exist for garbage, a truck picks it up and goes to recycling facilities
● this week only doing road work, pouring the concrete, and tomorrow they will be going
towards Bay street on the north side only to continue building the new road
● Electrical crew working at the streetlight, putting the permanent lights up
● 5 guys on this electrical crew, another 8 for the road
● These jobs are very repetitive, very linear, as one thing happens after the next
● materials: 6 inches stone going into concrete, 10 inches concrete road base on top, 4
inches of asphalt,
● the crew pours 100m of road today, but it takes 2 or 3 days to do the whole length
● They have oil on the form, so the concrete will then be separated from the form.
● a worker uses hand roller to flatten the concrete surface.
● subdrainpipe under ground, on top of which stones cover subdrain,
● the bulldozer used to push and compact the granular
Week 5 Oct 2026
• north side complete from Queen's park to Bay, only remaining part to be done is line marking
on road pavement
• water services are to be complete this weekend, but most likely tuesday water services and
catch basins installed on entire road, so now they're working on the north sidewalk from Bay to
Yonge just about complete
• bike lane curb stops for a part of the road, driveways need to be open, along blue fence to
truck there will be parking against the curb, so the bike lane will be further out dangerous as
far as Michael (project manager) is concerned
• Crew is working on the road base, just started the sidewalk
• northside 75% complete boxes are open so electrical can put new bases for streetlight poles,
sidewalks complete in a box,
• electrical guys suck out/dig out pole base, build it, pour it with concrete and they just have to
match concrete left there
Week 6 Oct 27 Nov 2
• traffic lights at Yonge Street have been installed (temporaries), permanent stuff has been
installed as well, going to do new street light poles from Bay to Yonge on north and south side
• now the road base and sidewalk on the north side is complete and crew will move over to the
south side, and consequently, traffic will be switched over to the completed north side
• on south side starting Tuesday (Oct 28th) work going to be done on Yonge to Bay on the
sidewalk
• water services and catchbasins all done, electricals as well so the finish will be quick
• bike lane on south side as well, line markings have been done inside the bike lane there are
2 separate lanes
• and then at the intersection (Queen's Park Crescent) there will be a cross over so that bikers
have one way direction traffic on each side of the road