1. Consumer Electronics Team – Session 5 Checkpoint B
Daniel Anderson – dananderson17@gmail.com
Raphael Brykman – raphaelbrykman2015@u.northwestern.edu
Eric Gero – gero.eric@gmail.com
Ketan Lakhani – ketan.lakhani@gmail.com
Aaron Matthews – aaronmatthews2018@u.northwestern.edu
Northwestern University
Author Note
Predict 480, Sec 55
2. File “DERAK Sprint – 1.xlsm” is an example of the project
plan that will be used during the project. The project plan will
allow the team to view and track the progress of tasks for each
sprint, and is based on an Agile methodology and integrates the
concepts of CRISP-DM.
To prepare for the project, the team has met with the
stakeholders and completed the Iteration 0 tasks of identifying and
estimating stories. For this project, each sprint will be 14 calendar
days, with weekends and holidays excluded from the available
hours. Therefore, the team of 5 will have 400 hours available for
each sprint.
The “Sprint” tab lists all tasks assigned to the sprint. On this
tab, tasks may be assigned to individuals and their progress
tracked. The “Story Backlog” tab includes all stories that have
been defined to-date. Currently, that includes Iteration 0 tasks,
Iteration 1 tasks, and a portion of Iteration 2 tasks. This tab serves
as the master log of all tasks. The “Analysis” tab contains
burndown charts for the sprint. It also provides a breakdown of
3. hours worked versus hours remaining for each task. The
“Capacity” and “Team Roster” tabs are used to list team members
and define their capacity for the iteration.
While the current spreadsheet works well for a sprint, it does
not provide a complete view for the project from start to finish. To
address this issue, several changes are being made. On the “Sprint”
tab, a sprint column will be added. This will allow all tasks to be
listed and tracked on the “Sprint” tab. A particular sprint may be
viewed by applying a filter on that column.
Currently, the project plan only allows one developer to work
on a task at a time. To assign more than one developer to a task,
the task must be listed multiple times, which inflates the hours
required for the sprint and makes tracking the hours for that task
difficult. A viable solution for this issue is being discussed.
Since the “Analysis” tab only tracks progress for the current
sprint, a new tab will be added to track progress for the entire
project. The project level tab will be similar to the “Analysis” tab.