SlideShare a Scribd company logo
1 of 13
What Is Cable Testing, And How
It's Done?
• The purpose of power cable testing is to guarantee that the cable’s insulation is
intact and that they operate correctly. Durability, high-voltage resistance, and
partial discharge detection are tested. Poor installation causes 99 percent of cable
issues during new electrical equipment commissioning.
• Power cable suppliers in UAE do rigorous testing to ensures that any potential
flaws are addressed before they cause more harm. They provide cable protection
from minor lacerations to punctures that result in current discharge.
Why Test Cables?
– Cable conformity
– Cabling quality
– Cable functionality
• A cable fault may often be identified before it becomes a problem.
• A visual inspection of your facility's wiring might uncover issues before they cause
downtime. We look for copper corrosion, insulation cracks, dampness on wires,
and other indicators of cable degradation.
• It is critical to ensure that cables and couplings are in great operating order and
that cable problem are detected immediately.
• Cable testing should be a priority for Power cable suppliers in UAE to prevent and
solve issues. Even with a range of test techniques and equipment, cable testing
may be a challenging operation.
• As a result, choosing and operating the best test equipment is as important as the
test equipment itself.
What Happens When Cables Are
Tested?
• The tests and inspections required before energizing 600V or less low voltage
cable are given below.
– Compare the cable data to the drawings and specs.
– Think about the number of sets and their insulation ratings.
– Examine exposed cable portions for material degradation. Inspect the cable
jacket and exposed insulation for damage.
– Verify that the single-line diagram's connecting points match.
– Check for excessive resistance using a calibrated torque wrench, low-
resistance ohmmeter, or thermographic survey.
– ANSI/NETA Table 100.12 US Standard Fasteners, Bolt Torque Values for
Electrical Connections
– Using a low resistance ohmmeter, compare the values of equivalent bolted
connections to find which one moves more than 50% of the lowest value.
– Examine the exposed cable jacket and insulation on low voltage wire and
cable.
– Before checking compression-applied connections, ensure the connector is
rated for the cable size and has the appropriate indentations.
• Each conductor should be tested for insulation resistance and ground resistance.
The test must last one minute and utilize the manufacturer's recommended
voltage.
• If no manufacturer information is provided, use 500/1000 volts dc for 300/600-volt
cable. To calculate insulating resistance, use the manufacturer's data. Otherwise,
the values should be at least 100 megohms—test for continuity to ensure
appropriate cable connection and phasing.
• Examine the resistance of parallel wires with a low-resistance ohmmeter. Identify
resistance variations between parallel wires by measuring each cable
independently.
How Is Cable Testing Done?
• Power cable suppliers test the following things to avoid leakage:
• Continuity Check
– The continuity test measures the low resistance of cables from 1 to 250
meters in length.
– The continuity test can be done with two or four wires, depending on the
resistance to be measured.
– It includes injecting a preset current and measuring the resistance's terminals
for voltage and current. Ohm’s law will decide that.
– Divide the switching matrix into two internal buses using the Kelvin technique.
– Directing the test current
– transmitting voltage between the element's terminals
– Opposing points are allocated to the measurement's SENSE and current
injection. This setup is suitable with two-wire continuity tests and may be
used throughout the switching matrix.
Insulation Testing
– A high resistance test (insulation) is usually done in DC.
– This test is combined with a short circuit and high voltage test in DC.
– The insulation test has several uses.
• The insulation test can reveal:
• calculating high voltage insulating resistances from 50-kilo ohm to 2000 megaohm
• Detection of short circuits and dielectric
• So, here's how it works:
– A low-voltage test (continuity measurement) detects short circuits (1). If a
short circuit is found, the insulation test fails (the message SHORT CIRCUIT
appears in the error list).
– If there is no short, the high voltage is applied. Breakdown happens within the
increasing time and the test is stopped (the breakdown voltage is given in the
error list).
– If there is no breakdown and the voltage does not reach the required level,
the message UUprog displays (ten percent).
– The voltage is then supplied for the set time
– If a failure occurs within this period, the test is terminated, and the error time
is displayed.
– To conclude the application time, the insulation test is done, and the
insulation resistance is measured
– (4). An extra measurement time is added depending on the intended range.
The measurement time varies from 20ms - 240ms.
• To finish the test, the tester lowers the high voltage and discharges the object to
the ground (total time 20ms).
• Every insulation measurement ends with this step.
• The dielectric strength test detects any rapid shift in the current test increase
outside the specified limit.
• Short circuit and high voltage testing can be disabled.
Experiment With Phasing
– The proper phasing of all LV circuits must be verified at all locations where LV
cables are terminated into fuse bases and while moving LV cables.
– This test requires specifically designed equipment. A 240-volt mains voltage is
insufficient for this test.
– For this test, the neutral conductor must be grounded.
• Earth Resistance Test:
– The earth resistance of an LV feeder in an overhead or underground network
must be less than 10 ohms before connecting to the existing network.
– Any overhead or underground network must have a total resistance to earth
of less than 1 ohm before joining.
High Voltage Test
• A/C or DC high voltage testing (also known as dielectric strength testing or hipot
testing) In DC, the high voltage test is linked with insulation; in AC, the high voltage
test is more demanding for the sample and is done as indicated below.
• High voltage testing utilizes an alternating voltage (50Hz) adjustable from 50V to
1500V. In all cases, the high voltage test identifies any sudden increase in current
up to a threshold.
• The short circuit test is always active. The time between application and rise is at
least a period.
• The capacitance of the tested equipment penalizes the high voltage test.
Remember that the generator's output is limited to 5 mA.
The Advantages of Cable Testing
• Limited product warranties are available.
• Repair is more costly than testing.
• Testing regularly will ensure that the infrastructure is future-proof.
Conclusion
• Since cables are the most expensive equipment in an installation, they must be
thoroughly tested using the methods listed above.
• Power cable suppliers install the cable in the proper directions, particularly in
curvatures, to avoid bending and kinking and improve power transmission and
avoid losses during transmission, thereby increasing the cable's reliability and
suspension.
https://www.urgroupuae.com/
+971 6 5341245 /
+971 6 5348425
Support:
info@urgroupuae.com
admin@urgroupuae.com
Wadi Al Rafesa Street, Shed no 177/1,
Near Dyna Trade, PO Box 47260 Sharjah
- UAE

More Related Content

What's hot

Shunt Calibration For Dummies
Shunt Calibration For DummiesShunt Calibration For Dummies
Shunt Calibration For DummiesInterface
 
Design planning & layout of high voltage laboratory
Design planning & layout of high voltage laboratoryDesign planning & layout of high voltage laboratory
Design planning & layout of high voltage laboratoryvishalgohel12195
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100Ali Sepehri
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testingmichaeljmack
 
Motor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagarMotor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagarjavid iqbal sodagar
 
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...Ali Sepehri
 
Sona Electric Power Engineering and Testing Centre
Sona Electric Power Engineering and Testing CentreSona Electric Power Engineering and Testing Centre
Sona Electric Power Engineering and Testing CentreSona College of Technology
 
Understanding overcurrent protection
Understanding overcurrent protectionUnderstanding overcurrent protection
Understanding overcurrent protectionmichaeljmack
 
Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...HighVoltageDUT
 
Transformer Oil Testing services
Transformer Oil Testing servicesTransformer Oil Testing services
Transformer Oil Testing servicesPower Electronical
 
Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...
Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...
Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...Thorne & Derrick International
 
Megger (mega-ohm-meter)
Megger (mega-ohm-meter)Megger (mega-ohm-meter)
Megger (mega-ohm-meter)Kausik das
 
Technical information for high voltage disconnector & earthing switch in enqu...
Technical information for high voltage disconnector & earthing switch in enqu...Technical information for high voltage disconnector & earthing switch in enqu...
Technical information for high voltage disconnector & earthing switch in enqu...Ali Sepehri
 
Partial Discharge Detection Products by EA Technology
Partial Discharge Detection Products by EA TechnologyPartial Discharge Detection Products by EA Technology
Partial Discharge Detection Products by EA TechnologyRyan McFallo
 
Identifying Casing Shorts With or Without Test Leads - Jim Walton
Identifying Casing Shorts With or Without Test Leads - Jim WaltonIdentifying Casing Shorts With or Without Test Leads - Jim Walton
Identifying Casing Shorts With or Without Test Leads - Jim Waltonnacetwincities
 

What's hot (20)

Shunt Calibration For Dummies
Shunt Calibration For DummiesShunt Calibration For Dummies
Shunt Calibration For Dummies
 
Design planning & layout of high voltage laboratory
Design planning & layout of high voltage laboratoryDesign planning & layout of high voltage laboratory
Design planning & layout of high voltage laboratory
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
 
Interface
Interface Interface
Interface
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testing
 
Tan delta faq
Tan delta faqTan delta faq
Tan delta faq
 
Motor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagarMotor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagar
 
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
 
Sona Electric Power Engineering and Testing Centre
Sona Electric Power Engineering and Testing CentreSona Electric Power Engineering and Testing Centre
Sona Electric Power Engineering and Testing Centre
 
Testing
TestingTesting
Testing
 
Understanding overcurrent protection
Understanding overcurrent protectionUnderstanding overcurrent protection
Understanding overcurrent protection
 
Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...
 
Insulation Resistance Test
Insulation Resistance TestInsulation Resistance Test
Insulation Resistance Test
 
Transformer Oil Testing services
Transformer Oil Testing servicesTransformer Oil Testing services
Transformer Oil Testing services
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...
Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...
Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...
 
Megger (mega-ohm-meter)
Megger (mega-ohm-meter)Megger (mega-ohm-meter)
Megger (mega-ohm-meter)
 
Technical information for high voltage disconnector & earthing switch in enqu...
Technical information for high voltage disconnector & earthing switch in enqu...Technical information for high voltage disconnector & earthing switch in enqu...
Technical information for high voltage disconnector & earthing switch in enqu...
 
Partial Discharge Detection Products by EA Technology
Partial Discharge Detection Products by EA TechnologyPartial Discharge Detection Products by EA Technology
Partial Discharge Detection Products by EA Technology
 
Identifying Casing Shorts With or Without Test Leads - Jim Walton
Identifying Casing Shorts With or Without Test Leads - Jim WaltonIdentifying Casing Shorts With or Without Test Leads - Jim Walton
Identifying Casing Shorts With or Without Test Leads - Jim Walton
 

Similar to Which test is done on cable before covering?

Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Thorne & Derrick International
 
Relay testing.............................
Relay testing.............................Relay testing.............................
Relay testing.............................hiiarindam
 
'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.pptThien Phan Bản
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushingNovia Putri
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHShankar Singh
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersLiving Online
 
Electrical Measurement Safety and Best Practices Webinar Presented by Fluke
Electrical Measurement Safety and Best Practices Webinar Presented by FlukeElectrical Measurement Safety and Best Practices Webinar Presented by Fluke
Electrical Measurement Safety and Best Practices Webinar Presented by FlukeTranscat
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTranscat
 
Shorted Casing Study - Tim Sievert
Shorted Casing Study - Tim SievertShorted Casing Study - Tim Sievert
Shorted Casing Study - Tim Sievertnacetwincities
 
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptxHVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptxMuthuKumar158260
 
Overhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by AmprobeOverhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by AmprobeTranscat
 
Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...
Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...
Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...PT. Siwali Swantika
 

Similar to Which test is done on cable before covering? (20)

Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
 
Relay testing.............................
Relay testing.............................Relay testing.............................
Relay testing.............................
 
'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt
 
Module 6part1
Module 6part1Module 6part1
Module 6part1
 
ET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptxET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptx
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Electrical testing
Electrical testingElectrical testing
Electrical testing
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
16950
1695016950
16950
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
 
Electrical Measurement Safety and Best Practices Webinar Presented by Fluke
Electrical Measurement Safety and Best Practices Webinar Presented by FlukeElectrical Measurement Safety and Best Practices Webinar Presented by Fluke
Electrical Measurement Safety and Best Practices Webinar Presented by Fluke
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV Systems
 
BR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-BrochureBR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-Brochure
 
Shorted Casing Study - Tim Sievert
Shorted Casing Study - Tim SievertShorted Casing Study - Tim Sievert
Shorted Casing Study - Tim Sievert
 
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptxHVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
 
Overhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by AmprobeOverhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by Amprobe
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...
Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...
Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...
 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
 

More from DevanshVarma1

8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cable8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cableDevanshVarma1
 
Prominent uses of power cables
Prominent uses of power cablesProminent uses of power cables
Prominent uses of power cablesDevanshVarma1
 
10 different equipment used in Distribution Substation
10 different equipment used in Distribution Substation10 different equipment used in Distribution Substation
10 different equipment used in Distribution SubstationDevanshVarma1
 
3 fundamental kinds of air compressors
3 fundamental kinds of air compressors3 fundamental kinds of air compressors
3 fundamental kinds of air compressorsDevanshVarma1
 
Kinds of security for electric cables
Kinds of security for electric cablesKinds of security for electric cables
Kinds of security for electric cablesDevanshVarma1
 
Parts of an electrical cable
Parts of an electrical cableParts of an electrical cable
Parts of an electrical cableDevanshVarma1
 
Kinds of Diesel Generators: various sorts about know
Kinds of Diesel Generators: various sorts about knowKinds of Diesel Generators: various sorts about know
Kinds of Diesel Generators: various sorts about knowDevanshVarma1
 
Checklist for Preventive Maintenance on Your Compressor
Checklist for Preventive Maintenance on Your CompressorChecklist for Preventive Maintenance on Your Compressor
Checklist for Preventive Maintenance on Your CompressorDevanshVarma1
 
Explanation of how positive and dynamic displacement Air Compressor work
Explanation of how positive and dynamic displacement Air Compressor workExplanation of how positive and dynamic displacement Air Compressor work
Explanation of how positive and dynamic displacement Air Compressor workDevanshVarma1
 
Tips for maintenance of the air compressor
Tips for maintenance of the air compressorTips for maintenance of the air compressor
Tips for maintenance of the air compressorDevanshVarma1
 
Visitor(s) rent: Air compressor equipment for a variety of reasons
Visitor(s) rent: Air compressor equipment for a variety of reasonsVisitor(s) rent: Air compressor equipment for a variety of reasons
Visitor(s) rent: Air compressor equipment for a variety of reasonsDevanshVarma1
 

More from DevanshVarma1 (11)

8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cable8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cable
 
Prominent uses of power cables
Prominent uses of power cablesProminent uses of power cables
Prominent uses of power cables
 
10 different equipment used in Distribution Substation
10 different equipment used in Distribution Substation10 different equipment used in Distribution Substation
10 different equipment used in Distribution Substation
 
3 fundamental kinds of air compressors
3 fundamental kinds of air compressors3 fundamental kinds of air compressors
3 fundamental kinds of air compressors
 
Kinds of security for electric cables
Kinds of security for electric cablesKinds of security for electric cables
Kinds of security for electric cables
 
Parts of an electrical cable
Parts of an electrical cableParts of an electrical cable
Parts of an electrical cable
 
Kinds of Diesel Generators: various sorts about know
Kinds of Diesel Generators: various sorts about knowKinds of Diesel Generators: various sorts about know
Kinds of Diesel Generators: various sorts about know
 
Checklist for Preventive Maintenance on Your Compressor
Checklist for Preventive Maintenance on Your CompressorChecklist for Preventive Maintenance on Your Compressor
Checklist for Preventive Maintenance on Your Compressor
 
Explanation of how positive and dynamic displacement Air Compressor work
Explanation of how positive and dynamic displacement Air Compressor workExplanation of how positive and dynamic displacement Air Compressor work
Explanation of how positive and dynamic displacement Air Compressor work
 
Tips for maintenance of the air compressor
Tips for maintenance of the air compressorTips for maintenance of the air compressor
Tips for maintenance of the air compressor
 
Visitor(s) rent: Air compressor equipment for a variety of reasons
Visitor(s) rent: Air compressor equipment for a variety of reasonsVisitor(s) rent: Air compressor equipment for a variety of reasons
Visitor(s) rent: Air compressor equipment for a variety of reasons
 

Recently uploaded

Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 

Recently uploaded (20)

Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 

Which test is done on cable before covering?

  • 1. What Is Cable Testing, And How It's Done?
  • 2. • The purpose of power cable testing is to guarantee that the cable’s insulation is intact and that they operate correctly. Durability, high-voltage resistance, and partial discharge detection are tested. Poor installation causes 99 percent of cable issues during new electrical equipment commissioning. • Power cable suppliers in UAE do rigorous testing to ensures that any potential flaws are addressed before they cause more harm. They provide cable protection from minor lacerations to punctures that result in current discharge.
  • 3. Why Test Cables? – Cable conformity – Cabling quality – Cable functionality • A cable fault may often be identified before it becomes a problem. • A visual inspection of your facility's wiring might uncover issues before they cause downtime. We look for copper corrosion, insulation cracks, dampness on wires, and other indicators of cable degradation. • It is critical to ensure that cables and couplings are in great operating order and that cable problem are detected immediately. • Cable testing should be a priority for Power cable suppliers in UAE to prevent and solve issues. Even with a range of test techniques and equipment, cable testing may be a challenging operation. • As a result, choosing and operating the best test equipment is as important as the test equipment itself.
  • 4. What Happens When Cables Are Tested? • The tests and inspections required before energizing 600V or less low voltage cable are given below. – Compare the cable data to the drawings and specs. – Think about the number of sets and their insulation ratings. – Examine exposed cable portions for material degradation. Inspect the cable jacket and exposed insulation for damage. – Verify that the single-line diagram's connecting points match. – Check for excessive resistance using a calibrated torque wrench, low- resistance ohmmeter, or thermographic survey. – ANSI/NETA Table 100.12 US Standard Fasteners, Bolt Torque Values for Electrical Connections – Using a low resistance ohmmeter, compare the values of equivalent bolted connections to find which one moves more than 50% of the lowest value. – Examine the exposed cable jacket and insulation on low voltage wire and cable. – Before checking compression-applied connections, ensure the connector is rated for the cable size and has the appropriate indentations.
  • 5. • Each conductor should be tested for insulation resistance and ground resistance. The test must last one minute and utilize the manufacturer's recommended voltage. • If no manufacturer information is provided, use 500/1000 volts dc for 300/600-volt cable. To calculate insulating resistance, use the manufacturer's data. Otherwise, the values should be at least 100 megohms—test for continuity to ensure appropriate cable connection and phasing. • Examine the resistance of parallel wires with a low-resistance ohmmeter. Identify resistance variations between parallel wires by measuring each cable independently.
  • 6. How Is Cable Testing Done? • Power cable suppliers test the following things to avoid leakage: • Continuity Check – The continuity test measures the low resistance of cables from 1 to 250 meters in length. – The continuity test can be done with two or four wires, depending on the resistance to be measured. – It includes injecting a preset current and measuring the resistance's terminals for voltage and current. Ohm’s law will decide that. – Divide the switching matrix into two internal buses using the Kelvin technique. – Directing the test current – transmitting voltage between the element's terminals – Opposing points are allocated to the measurement's SENSE and current injection. This setup is suitable with two-wire continuity tests and may be used throughout the switching matrix.
  • 7. Insulation Testing – A high resistance test (insulation) is usually done in DC. – This test is combined with a short circuit and high voltage test in DC. – The insulation test has several uses. • The insulation test can reveal: • calculating high voltage insulating resistances from 50-kilo ohm to 2000 megaohm • Detection of short circuits and dielectric • So, here's how it works: – A low-voltage test (continuity measurement) detects short circuits (1). If a short circuit is found, the insulation test fails (the message SHORT CIRCUIT appears in the error list). – If there is no short, the high voltage is applied. Breakdown happens within the increasing time and the test is stopped (the breakdown voltage is given in the error list).
  • 8. – If there is no breakdown and the voltage does not reach the required level, the message UUprog displays (ten percent). – The voltage is then supplied for the set time – If a failure occurs within this period, the test is terminated, and the error time is displayed. – To conclude the application time, the insulation test is done, and the insulation resistance is measured – (4). An extra measurement time is added depending on the intended range. The measurement time varies from 20ms - 240ms. • To finish the test, the tester lowers the high voltage and discharges the object to the ground (total time 20ms). • Every insulation measurement ends with this step. • The dielectric strength test detects any rapid shift in the current test increase outside the specified limit. • Short circuit and high voltage testing can be disabled.
  • 9. Experiment With Phasing – The proper phasing of all LV circuits must be verified at all locations where LV cables are terminated into fuse bases and while moving LV cables. – This test requires specifically designed equipment. A 240-volt mains voltage is insufficient for this test. – For this test, the neutral conductor must be grounded. • Earth Resistance Test: – The earth resistance of an LV feeder in an overhead or underground network must be less than 10 ohms before connecting to the existing network. – Any overhead or underground network must have a total resistance to earth of less than 1 ohm before joining.
  • 10. High Voltage Test • A/C or DC high voltage testing (also known as dielectric strength testing or hipot testing) In DC, the high voltage test is linked with insulation; in AC, the high voltage test is more demanding for the sample and is done as indicated below. • High voltage testing utilizes an alternating voltage (50Hz) adjustable from 50V to 1500V. In all cases, the high voltage test identifies any sudden increase in current up to a threshold. • The short circuit test is always active. The time between application and rise is at least a period. • The capacitance of the tested equipment penalizes the high voltage test. Remember that the generator's output is limited to 5 mA.
  • 11. The Advantages of Cable Testing • Limited product warranties are available. • Repair is more costly than testing. • Testing regularly will ensure that the infrastructure is future-proof.
  • 12. Conclusion • Since cables are the most expensive equipment in an installation, they must be thoroughly tested using the methods listed above. • Power cable suppliers install the cable in the proper directions, particularly in curvatures, to avoid bending and kinking and improve power transmission and avoid losses during transmission, thereby increasing the cable's reliability and suspension.
  • 13. https://www.urgroupuae.com/ +971 6 5341245 / +971 6 5348425 Support: info@urgroupuae.com admin@urgroupuae.com Wadi Al Rafesa Street, Shed no 177/1, Near Dyna Trade, PO Box 47260 Sharjah - UAE