SlideShare a Scribd company logo
1 of 2
Download to read offline
Large-panel ARES wall system
provides stability and aesthetics
for key Calgary roadway.
Southeast Stoney Trail was Alberta’s largest P3
highway project at the time of construction.
It forms a key part of Calgary’s ring road, and
required many Mechanically Stabilized Earth
(MSE) walls with a custom architectural finish.
Challenge
High traffic demand, winter construction
conditions and the chemical impacts from
de-icing salts are all challenges common to ring
road projects in Alberta; Stoney Trail was no
exception to that generalization. The need for 27
bridge structures, nine interchanges and three
flyovers within the 25 kilometers of its six-lane
southeast section made it especially challenging
to deliver on time and on budget.
Due to the corrosive nature of de-icing salts,
most MSE walls require geomembrane protection
trenches along the steel-reinforcements for each
wall. The design life for MSE wall components is
100 years, and they must work with a reinforced
mass that meets load and resistance standards.
Solution
Nilex recommended an innovative large-scale
3m x 3m ARES Modular Panel Retaining
Wall System because of its affordability,
simplicity, speed of construction and ability
to accommodate a wide range of finishes. The
systems’s HDPE geogrid eliminates salt concerns.
LOCATION:
Calgary, Alberta
PRODUCT:
ARES® and SierraScape®
PROJECT PARTNERS:
Owner
Alberta Transportation
Consultant
Golder Associates, LVM/DESSAU, McIntosh
Lalani Engineering, and MMM Geomatics
Contractor
Chinook Infrastructure and Chinook Roads
Partnership
Completion Date
September 2012
Southeast
Stoney Trail
PROJECT PROFILE
MSE WALLS
& SLOPES
Twenty-two pre-cast concrete ARES walls (with
architectural finish) were used in 12 structures,
for a project total of over 12,000 m2
. These large
panels are a unique benefit of Nilex’s partnership
with Lockwood Brothers Concrete Products and
Tensar International.
One small section of SierraScape Wire-Formed
Retaining Wall System was used for the structure
that redirected traffic along 52nd
Street, which
intersects Stoney Trail north-to-south.
Installation
The Nilex MSE team provided local engineering
and on-site support, including quick turnarounds
when required, due to local office access.
Crews easily installed the lightweight geogrid
soil reinforcement elements by hand, a distinct
advantage of Ares walls over systems that require
cranes for this step. Nilex’s design expertise
helped tackle coverage ratio issues where the
geogrid interacted with bridge piles, ensuring
there was full-width panel anchoring. The
HDPE tie-back anchors of the ARES system can
accomodate a much wider range of aggressive
soil pH (2-12) compared to steel systems.
Results
Nilex provided design, panel fabrication and site
support to deliver a superior MSE wall solution
that was responsive to all structural criteria and
more economical than a steel-reinforced system.
Local expertise and inventory of geosynthetics
provided key advantages that helped ensure
the project was completed on schedule. It made
ReNew Canada’s Top 100 Infrastructure Projects
list in 2011.
The Nilex Advantage
Nilex is committed to unearthing better results.
Whether it’s for a civil, resource or environmental
project, we offer the latest engineered and
technically-superior materials and techniques to
save our customers time and money, minimize the
need to move or remove earth, and reduce the
need for granular materials.
With over 35 years of experience, a long-standing
commitment to the environment and highly
qualified staff, Nilex delivers the products and
technologies that give clients an economic
advantage with environmental benefit.
Southeast Stoney Trail
Rev. 04/2016
nilex.com

More Related Content

What's hot

2010 Marina Bay Sands
2010 Marina Bay Sands2010 Marina Bay Sands
2010 Marina Bay SandsNatare Corp
 
Emin sg-sistema-mesa-por-tensar-international-(ingles)
Emin sg-sistema-mesa-por-tensar-international-(ingles)Emin sg-sistema-mesa-por-tensar-international-(ingles)
Emin sg-sistema-mesa-por-tensar-international-(ingles)EMIN Sistemas Geotecnicos
 
Raleigh Durham International Airport – PG-1 Structural Modifications
Raleigh Durham International Airport – PG-1 Structural ModificationsRaleigh Durham International Airport – PG-1 Structural Modifications
Raleigh Durham International Airport – PG-1 Structural ModificationsPostTensioningInstitute
 
GE Presentation 6th October 2010
GE Presentation 6th October 2010GE Presentation 6th October 2010
GE Presentation 6th October 2010Tonyamis
 
Terrett Court Storm Drainage Improvements
Terrett Court Storm Drainage ImprovementsTerrett Court Storm Drainage Improvements
Terrett Court Storm Drainage ImprovementsFairfax County
 
GDI 10-11 JanFeb 2017-Gedrill full ad
GDI 10-11 JanFeb 2017-Gedrill full adGDI 10-11 JanFeb 2017-Gedrill full ad
GDI 10-11 JanFeb 2017-Gedrill full adJennifer Hormell
 
GI Energy - Rehau PowerPoint June 2015
GI Energy - Rehau PowerPoint June 2015GI Energy - Rehau PowerPoint June 2015
GI Energy - Rehau PowerPoint June 2015GI Energy
 
Salus Passive House PresentationNV
Salus Passive House PresentationNVSalus Passive House PresentationNV
Salus Passive House PresentationNVKen Williams
 
Post tensioned concrete walls & frames for seismic resistance
Post tensioned concrete walls & frames for seismic resistancePost tensioned concrete walls & frames for seismic resistance
Post tensioned concrete walls & frames for seismic resistanceĐỗ Hữu Linh
 
Jackson-GM0415 Personal
Jackson-GM0415 PersonalJackson-GM0415 Personal
Jackson-GM0415 PersonalGary Jackson
 

What's hot (20)

Wacker Drive Viaduct Reconstruction
Wacker Drive Viaduct ReconstructionWacker Drive Viaduct Reconstruction
Wacker Drive Viaduct Reconstruction
 
2010 Marina Bay Sands
2010 Marina Bay Sands2010 Marina Bay Sands
2010 Marina Bay Sands
 
Edward Rice House
Edward Rice HouseEdward Rice House
Edward Rice House
 
Emin sg-sistema-mesa-(ingles)
Emin sg-sistema-mesa-(ingles)Emin sg-sistema-mesa-(ingles)
Emin sg-sistema-mesa-(ingles)
 
Veterans' Glass City Skyway Bridge
Veterans' Glass City Skyway BridgeVeterans' Glass City Skyway Bridge
Veterans' Glass City Skyway Bridge
 
I-64 Kanawha River Bridge
I-64 Kanawha River BridgeI-64 Kanawha River Bridge
I-64 Kanawha River Bridge
 
Emin sg-sistema-mesa-por-tensar-international-(ingles)
Emin sg-sistema-mesa-por-tensar-international-(ingles)Emin sg-sistema-mesa-por-tensar-international-(ingles)
Emin sg-sistema-mesa-por-tensar-international-(ingles)
 
The Trump International Hotel & Tower
The Trump International Hotel & TowerThe Trump International Hotel & Tower
The Trump International Hotel & Tower
 
Raleigh Durham International Airport – PG-1 Structural Modifications
Raleigh Durham International Airport – PG-1 Structural ModificationsRaleigh Durham International Airport – PG-1 Structural Modifications
Raleigh Durham International Airport – PG-1 Structural Modifications
 
Vidalta Bridge
Vidalta BridgeVidalta Bridge
Vidalta Bridge
 
Fallingwater Residence
Fallingwater ResidenceFallingwater Residence
Fallingwater Residence
 
McKinney Place Garage
McKinney Place GarageMcKinney Place Garage
McKinney Place Garage
 
GE Presentation 6th October 2010
GE Presentation 6th October 2010GE Presentation 6th October 2010
GE Presentation 6th October 2010
 
Green Screen Parking Structure
Green Screen Parking StructureGreen Screen Parking Structure
Green Screen Parking Structure
 
Terrett Court Storm Drainage Improvements
Terrett Court Storm Drainage ImprovementsTerrett Court Storm Drainage Improvements
Terrett Court Storm Drainage Improvements
 
GDI 10-11 JanFeb 2017-Gedrill full ad
GDI 10-11 JanFeb 2017-Gedrill full adGDI 10-11 JanFeb 2017-Gedrill full ad
GDI 10-11 JanFeb 2017-Gedrill full ad
 
GI Energy - Rehau PowerPoint June 2015
GI Energy - Rehau PowerPoint June 2015GI Energy - Rehau PowerPoint June 2015
GI Energy - Rehau PowerPoint June 2015
 
Salus Passive House PresentationNV
Salus Passive House PresentationNVSalus Passive House PresentationNV
Salus Passive House PresentationNV
 
Post tensioned concrete walls & frames for seismic resistance
Post tensioned concrete walls & frames for seismic resistancePost tensioned concrete walls & frames for seismic resistance
Post tensioned concrete walls & frames for seismic resistance
 
Jackson-GM0415 Personal
Jackson-GM0415 PersonalJackson-GM0415 Personal
Jackson-GM0415 Personal
 

Similar to Southeast Stoney Trail Project Profile

Ares cs delaware_12.12
Ares cs delaware_12.12Ares cs delaware_12.12
Ares cs delaware_12.12Tensar
 
Mesa cs brk_10.05
Mesa cs brk_10.05Mesa cs brk_10.05
Mesa cs brk_10.05Tensar
 
What is Mesa Segmental Retaining Wall System?
What is Mesa Segmental Retaining Wall System?What is Mesa Segmental Retaining Wall System?
What is Mesa Segmental Retaining Wall System?Nilex Inc
 
Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Tensar
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183Miklos Peller, Sr.
 
SIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERINGSIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERINGWilliam Wieners
 
fastrack technologies in bridges ppt
fastrack technologies in bridges pptfastrack technologies in bridges ppt
fastrack technologies in bridges pptSrinivasulu Srinu
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining WallJim McMullan
 
Sierra cs clagett_12.08
Sierra cs clagett_12.08Sierra cs clagett_12.08
Sierra cs clagett_12.08Tensar
 
Building technology report
Building technology reportBuilding technology report
Building technology reportChong Yi Hui
 
Design of R.C.C. Retaining Wall and Reinforced Earth Wall for 6 Meter Height
Design of R.C.C. Retaining Wall and Reinforced Earth Wall for 6 Meter HeightDesign of R.C.C. Retaining Wall and Reinforced Earth Wall for 6 Meter Height
Design of R.C.C. Retaining Wall and Reinforced Earth Wall for 6 Meter Heightijtsrd
 
Triton cs collins_11.07
Triton cs collins_11.07Triton cs collins_11.07
Triton cs collins_11.07Tensar
 
Rehab of an existing mse(1)
Rehab of an existing mse(1)Rehab of an existing mse(1)
Rehab of an existing mse(1)Dr. Ganesh Kame
 
Whitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyWhitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyAndrew White
 
Project Management - Marina bay Sands
Project Management - Marina bay SandsProject Management - Marina bay Sands
Project Management - Marina bay SandsBimenpreet Kaur
 

Similar to Southeast Stoney Trail Project Profile (20)

SFPR-Project-Profile_0
SFPR-Project-Profile_0SFPR-Project-Profile_0
SFPR-Project-Profile_0
 
Ares cs delaware_12.12
Ares cs delaware_12.12Ares cs delaware_12.12
Ares cs delaware_12.12
 
Mesa cs brk_10.05
Mesa cs brk_10.05Mesa cs brk_10.05
Mesa cs brk_10.05
 
What is Mesa Segmental Retaining Wall System?
What is Mesa Segmental Retaining Wall System?What is Mesa Segmental Retaining Wall System?
What is Mesa Segmental Retaining Wall System?
 
Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
 
ASHJACK
ASHJACKASHJACK
ASHJACK
 
SIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERINGSIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERING
 
Ashwall
AshwallAshwall
Ashwall
 
fastrack technologies in bridges ppt
fastrack technologies in bridges pptfastrack technologies in bridges ppt
fastrack technologies in bridges ppt
 
Advancement in retaining wall
Advancement  in retaining wallAdvancement  in retaining wall
Advancement in retaining wall
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining Wall
 
Sierra cs clagett_12.08
Sierra cs clagett_12.08Sierra cs clagett_12.08
Sierra cs clagett_12.08
 
Building technology report
Building technology reportBuilding technology report
Building technology report
 
Design of R.C.C. Retaining Wall and Reinforced Earth Wall for 6 Meter Height
Design of R.C.C. Retaining Wall and Reinforced Earth Wall for 6 Meter HeightDesign of R.C.C. Retaining Wall and Reinforced Earth Wall for 6 Meter Height
Design of R.C.C. Retaining Wall and Reinforced Earth Wall for 6 Meter Height
 
Triton cs collins_11.07
Triton cs collins_11.07Triton cs collins_11.07
Triton cs collins_11.07
 
Rehab of an existing mse(1)
Rehab of an existing mse(1)Rehab of an existing mse(1)
Rehab of an existing mse(1)
 
Whitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyWhitescape Civil Engineering Case Study
Whitescape Civil Engineering Case Study
 
Project Management - Marina bay Sands
Project Management - Marina bay SandsProject Management - Marina bay Sands
Project Management - Marina bay Sands
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 

Southeast Stoney Trail Project Profile

  • 1. Large-panel ARES wall system provides stability and aesthetics for key Calgary roadway. Southeast Stoney Trail was Alberta’s largest P3 highway project at the time of construction. It forms a key part of Calgary’s ring road, and required many Mechanically Stabilized Earth (MSE) walls with a custom architectural finish. Challenge High traffic demand, winter construction conditions and the chemical impacts from de-icing salts are all challenges common to ring road projects in Alberta; Stoney Trail was no exception to that generalization. The need for 27 bridge structures, nine interchanges and three flyovers within the 25 kilometers of its six-lane southeast section made it especially challenging to deliver on time and on budget. Due to the corrosive nature of de-icing salts, most MSE walls require geomembrane protection trenches along the steel-reinforcements for each wall. The design life for MSE wall components is 100 years, and they must work with a reinforced mass that meets load and resistance standards. Solution Nilex recommended an innovative large-scale 3m x 3m ARES Modular Panel Retaining Wall System because of its affordability, simplicity, speed of construction and ability to accommodate a wide range of finishes. The systems’s HDPE geogrid eliminates salt concerns. LOCATION: Calgary, Alberta PRODUCT: ARES® and SierraScape® PROJECT PARTNERS: Owner Alberta Transportation Consultant Golder Associates, LVM/DESSAU, McIntosh Lalani Engineering, and MMM Geomatics Contractor Chinook Infrastructure and Chinook Roads Partnership Completion Date September 2012 Southeast Stoney Trail PROJECT PROFILE MSE WALLS & SLOPES
  • 2. Twenty-two pre-cast concrete ARES walls (with architectural finish) were used in 12 structures, for a project total of over 12,000 m2 . These large panels are a unique benefit of Nilex’s partnership with Lockwood Brothers Concrete Products and Tensar International. One small section of SierraScape Wire-Formed Retaining Wall System was used for the structure that redirected traffic along 52nd Street, which intersects Stoney Trail north-to-south. Installation The Nilex MSE team provided local engineering and on-site support, including quick turnarounds when required, due to local office access. Crews easily installed the lightweight geogrid soil reinforcement elements by hand, a distinct advantage of Ares walls over systems that require cranes for this step. Nilex’s design expertise helped tackle coverage ratio issues where the geogrid interacted with bridge piles, ensuring there was full-width panel anchoring. The HDPE tie-back anchors of the ARES system can accomodate a much wider range of aggressive soil pH (2-12) compared to steel systems. Results Nilex provided design, panel fabrication and site support to deliver a superior MSE wall solution that was responsive to all structural criteria and more economical than a steel-reinforced system. Local expertise and inventory of geosynthetics provided key advantages that helped ensure the project was completed on schedule. It made ReNew Canada’s Top 100 Infrastructure Projects list in 2011. The Nilex Advantage Nilex is committed to unearthing better results. Whether it’s for a civil, resource or environmental project, we offer the latest engineered and technically-superior materials and techniques to save our customers time and money, minimize the need to move or remove earth, and reduce the need for granular materials. With over 35 years of experience, a long-standing commitment to the environment and highly qualified staff, Nilex delivers the products and technologies that give clients an economic advantage with environmental benefit. Southeast Stoney Trail Rev. 04/2016 nilex.com