©2006ENSPMFormationIndustrie-IFPTraining
CHAPTER 6
BIT SELECTION
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Bit selection
• This Chapter aims at selecting the bit that will lead to
the lowest cost per foot, taking into account angle
corrections and reamed sections.. Both Technical
and Economical parameters will be involved in this
selection.
• Due to the great variety of formations to drill and due
also to the relative misunderstanding of the
characteristics of these formations, of the bits
currently available and of the various drilling
environments (material and costs..), it is impossible
to point out a few bits that would do a great job
everywhere.
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Bit selection
• In exploratory wells, geological data regarding the
formations to drill come from seismic surveys,
regional geology maps and some samples collected
here and there, where the corresponding rocks reach
the surface.
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Bit selection
• In development wells, lithology, formation thickness
and rock characteristics are usually well known.
• Cuttings samples, cores, plugs taken on cores, direct
measurements on cuttings, gives indications about
the nature of the rocks, their compressive strengths,
porosity & permeability.
• Electric logs, recording of drilling parameters and
MWD logs sometimes merged in one single document
called Master Log or Composite Log, allows direct
correspondence between the parameters, the bit
behavior and the rocks being drilled.
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Bit selection
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Bit selection
• Another set of information available concerns the bits used
in the surrounding wells (called offset wells) under the
form of morning reports or bit records.
• To optimize the choice of the bit, it is necessary to take into
account:
– Data concerning the formation to be drilled.
– Parameters applied to the bits used in the pevious wells, the
performances carried out by these bits and their wear.
– Basic equipment and surface installations used (hydraulic
power available, capacity of the equipment of mechanical
treatment of the solids, composition of the drill stem, etc)
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Bit selection
• Availabilities and of the delivery times of the various
types of bits, the surrounded costs of the apparatus
and the tools used.
• Characteristics of mud used (type, density, content of
solids, etc).
• Specificities of the well to be drilled (trajectory, slope,
etc).
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Parameters linked to the formation
• Drilling performance will be influenced by various
parameters linked to the formations to drill, they can be
divided in two sets:
– The intrinsic properties of the rocks (mineralogy, grain
size and fabric of the deposits, matrix strength, porosity
..)
– The environment at the time of drilling (confinement
pressure, pore pressure, reactions with the drilling fluids,
stresses on the rocks..)
• The two sets of parameters will interact to modify the
rock strength in compression and shearing, abrasivity
and behavior at the moment it is destroyed by the bit.
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Parameters linked to the formation
• To have an idea of the formation drillability, it is
therefore important to know:
– The Rock Composition, by direct observations (cuttings
and cores) or by in-situ measurement through electric
logs. Both studies are complementary.
– The in-situ compaction that is related to the pore
pressure and the local stresses (vertical and
horizontal).
– The value of the stresses that prevail in the area around
the well (overburden pressure, rock tensile strength..)
These values can be determined by leak off tests, sonic
and caliper logs, seismic interpretations (under
compacted zones).
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Information from bits used on previous wells
• Information supplied by the dull grading.
– Dull grading is a direct and fast way for selecting both
the bit and the appropriate parameters for the man on
the rig, only if it is properly made.
• Cost per Foot.
– That is in fact the most important one, as bits are rarely
reused (except the diamond bits), looking for the lowest
cost per foot, even at the detriment of the bit life is what
matters. The longest distance drilled within the shortest
time, according to rig power available.
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Other selection criteria
• The capacities of the rig must be taken into account.
The power of pumping and rotation must be sufficient
to make it possible to use the bit with the parameters
envisaged.
©2006ENSPMFormationIndustrie-IFPTraining
SEC
Conclusion
• It is very difficult to choose the best adapted bit to
drill a formation for many reasons.
• First of all, the technology and the possibilities
offered by certain types of bits evolve/move very
quickly. Such type of bit which today is not adapted
for such type of rock can be it tomorrow.
• It also should be remembered that rocks having the
same name can have very different characteristics.
• The best way to select the best adapted bit to a
formation or a phase of drilling is still to establish
correlations between the tools used, the parameters
applied, the wear of the tools and the characteristics
of the rocks to be drilled.

More Related Content

What's hot

My pd cdrillbitpresentation - copy
My pd cdrillbitpresentation - copyMy pd cdrillbitpresentation - copy
My pd cdrillbitpresentation - copyAbhijeet Chodankar
 
Drill bit types advantages and disadvantages
Drill bit types advantages and disadvantagesDrill bit types advantages and disadvantages
Drill bit types advantages and disadvantagesJyoti Khatiwada
 
Presentation 3 drilling bits
Presentation 3 drilling bitsPresentation 3 drilling bits
Presentation 3 drilling bitsAli Trichelli
 
8 bit selection
8   bit selection8   bit selection
8 bit selectionamrhaggag
 
SPIROL Slotted Spring Pin Design Guide
SPIROL Slotted Spring Pin Design GuideSPIROL Slotted Spring Pin Design Guide
SPIROL Slotted Spring Pin Design GuideSPIROL
 
Ch 6 reaming, boring, broaching
Ch 6 reaming, boring, broachingCh 6 reaming, boring, broaching
Ch 6 reaming, boring, broachingNandan Choudhary
 
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid PinsSPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid PinsSPIROL
 
Ch 8.2 screw thread manufacturing
Ch 8.2 screw thread manufacturingCh 8.2 screw thread manufacturing
Ch 8.2 screw thread manufacturingNandan Choudhary
 
Flexovit Abrasives Training
Flexovit Abrasives TrainingFlexovit Abrasives Training
Flexovit Abrasives Trainingflexovitsocia
 
Comparative Analysis and Design of Flat and Grid Slab System with Conventiona...
Comparative Analysis and Design of Flat and Grid Slab System with Conventiona...Comparative Analysis and Design of Flat and Grid Slab System with Conventiona...
Comparative Analysis and Design of Flat and Grid Slab System with Conventiona...IRJET Journal
 
Soil Investigation And Drilling ( Types,Drill Bits )
Soil Investigation And Drilling ( Types,Drill Bits )Soil Investigation And Drilling ( Types,Drill Bits )
Soil Investigation And Drilling ( Types,Drill Bits )Aon Ali Jaffery
 

What's hot (20)

My pd cdrillbitpresentation - copy
My pd cdrillbitpresentation - copyMy pd cdrillbitpresentation - copy
My pd cdrillbitpresentation - copy
 
Drill bit types advantages and disadvantages
Drill bit types advantages and disadvantagesDrill bit types advantages and disadvantages
Drill bit types advantages and disadvantages
 
Presentation 3 drilling bits
Presentation 3 drilling bitsPresentation 3 drilling bits
Presentation 3 drilling bits
 
Iadc tricone bits
Iadc tricone bitsIadc tricone bits
Iadc tricone bits
 
Drill bits
Drill bitsDrill bits
Drill bits
 
Drill bits
Drill bitsDrill bits
Drill bits
 
Drilling bits
Drilling bitsDrilling bits
Drilling bits
 
8 bit selection
8   bit selection8   bit selection
8 bit selection
 
Ch 5 drilling
Ch 5 drillingCh 5 drilling
Ch 5 drilling
 
Gears Manufacturing
Gears ManufacturingGears Manufacturing
Gears Manufacturing
 
SPIROL Slotted Spring Pin Design Guide
SPIROL Slotted Spring Pin Design GuideSPIROL Slotted Spring Pin Design Guide
SPIROL Slotted Spring Pin Design Guide
 
Ch 6 reaming, boring, broaching
Ch 6 reaming, boring, broachingCh 6 reaming, boring, broaching
Ch 6 reaming, boring, broaching
 
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid PinsSPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
 
Ch 8.2 screw thread manufacturing
Ch 8.2 screw thread manufacturingCh 8.2 screw thread manufacturing
Ch 8.2 screw thread manufacturing
 
Flexovit Abrasives Training
Flexovit Abrasives TrainingFlexovit Abrasives Training
Flexovit Abrasives Training
 
Comparative Analysis and Design of Flat and Grid Slab System with Conventiona...
Comparative Analysis and Design of Flat and Grid Slab System with Conventiona...Comparative Analysis and Design of Flat and Grid Slab System with Conventiona...
Comparative Analysis and Design of Flat and Grid Slab System with Conventiona...
 
Ch 8.1 gear manufacturing
Ch 8.1 gear manufacturingCh 8.1 gear manufacturing
Ch 8.1 gear manufacturing
 
Soil Investigation And Drilling ( Types,Drill Bits )
Soil Investigation And Drilling ( Types,Drill Bits )Soil Investigation And Drilling ( Types,Drill Bits )
Soil Investigation And Drilling ( Types,Drill Bits )
 
Dodge USAF Bearings Brochure
Dodge USAF Bearings BrochureDodge USAF Bearings Brochure
Dodge USAF Bearings Brochure
 
Ch33 mechanical assembly-tseng
Ch33 mechanical assembly-tsengCh33 mechanical assembly-tseng
Ch33 mechanical assembly-tseng
 

Similar to Drilling bit 6

Application oriented wear testing equipment
Application oriented wear testing equipmentApplication oriented wear testing equipment
Application oriented wear testing equipmentKati Valtonen
 
Raise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,liningRaise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,liningSafdar Ali
 
Rock engineering and ground control
Rock engineering and ground controlRock engineering and ground control
Rock engineering and ground controlBhaskar Naidu
 
Shaft sinking operation
Shaft sinking operationShaft sinking operation
Shaft sinking operationSafdar Ali
 
Concepcion bartolo kling alberth segundo trabajo
Concepcion bartolo kling alberth segundo trabajoConcepcion bartolo kling alberth segundo trabajo
Concepcion bartolo kling alberth segundo trabajoJharriEHuerto
 
F.E.M ANALYSIS OF ANNULAR MAT FOUNDATION WITH & WITHOUT ANNULAR BEAM
F.E.M ANALYSIS OF ANNULAR MAT FOUNDATION WITH & WITHOUT ANNULAR BEAMF.E.M ANALYSIS OF ANNULAR MAT FOUNDATION WITH & WITHOUT ANNULAR BEAM
F.E.M ANALYSIS OF ANNULAR MAT FOUNDATION WITH & WITHOUT ANNULAR BEAMIRJET Journal
 
Fatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker PennimentFatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker PennimentNSW Environment and Planning
 
Workshop_on_Mine_Planning_and_Valuation_.pptx
Workshop_on_Mine_Planning_and_Valuation_.pptxWorkshop_on_Mine_Planning_and_Valuation_.pptx
Workshop_on_Mine_Planning_and_Valuation_.pptxssuserf9eaaf
 
Non-Traditional Machining Process (UCMP)
Non-Traditional Machining Process (UCMP)Non-Traditional Machining Process (UCMP)
Non-Traditional Machining Process (UCMP)S. Sathishkumar
 
Final project ppt
Final project pptFinal project ppt
Final project pptAkhil Vas
 
Performance review of TBM
Performance review of TBMPerformance review of TBM
Performance review of TBMindranjanGhosh
 
final presentation 1 goa
final presentation 1 goafinal presentation 1 goa
final presentation 1 goaAnkit Anand
 
Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)sou_suk_sou
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testingcfpbolivia
 
Road
RoadRoad
Roadjuwes
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...IRJET Journal
 
UNCONVENTIONAL MACHINING PROCESS
UNCONVENTIONAL MACHINING PROCESSUNCONVENTIONAL MACHINING PROCESS
UNCONVENTIONAL MACHINING PROCESSS. Sathishkumar
 

Similar to Drilling bit 6 (20)

Application oriented wear testing equipment
Application oriented wear testing equipmentApplication oriented wear testing equipment
Application oriented wear testing equipment
 
Raise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,liningRaise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,lining
 
Rock engineering and ground control
Rock engineering and ground controlRock engineering and ground control
Rock engineering and ground control
 
Core plugging test
Core plugging test   Core plugging test
Core plugging test
 
Shaft sinking operation
Shaft sinking operationShaft sinking operation
Shaft sinking operation
 
Concepcion bartolo kling alberth segundo trabajo
Concepcion bartolo kling alberth segundo trabajoConcepcion bartolo kling alberth segundo trabajo
Concepcion bartolo kling alberth segundo trabajo
 
F.E.M ANALYSIS OF ANNULAR MAT FOUNDATION WITH & WITHOUT ANNULAR BEAM
F.E.M ANALYSIS OF ANNULAR MAT FOUNDATION WITH & WITHOUT ANNULAR BEAMF.E.M ANALYSIS OF ANNULAR MAT FOUNDATION WITH & WITHOUT ANNULAR BEAM
F.E.M ANALYSIS OF ANNULAR MAT FOUNDATION WITH & WITHOUT ANNULAR BEAM
 
Fatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker PennimentFatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker Penniment
 
Workshop_on_Mine_Planning_and_Valuation_.pptx
Workshop_on_Mine_Planning_and_Valuation_.pptxWorkshop_on_Mine_Planning_and_Valuation_.pptx
Workshop_on_Mine_Planning_and_Valuation_.pptx
 
Non-Traditional Machining Process (UCMP)
Non-Traditional Machining Process (UCMP)Non-Traditional Machining Process (UCMP)
Non-Traditional Machining Process (UCMP)
 
Core Goniometry PanTerra Presentation
Core Goniometry PanTerra Presentation Core Goniometry PanTerra Presentation
Core Goniometry PanTerra Presentation
 
Final project ppt
Final project pptFinal project ppt
Final project ppt
 
Performance review of TBM
Performance review of TBMPerformance review of TBM
Performance review of TBM
 
Mark gee npl
Mark gee   nplMark gee   npl
Mark gee npl
 
final presentation 1 goa
final presentation 1 goafinal presentation 1 goa
final presentation 1 goa
 
Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
 
Road
RoadRoad
Road
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
 
UNCONVENTIONAL MACHINING PROCESS
UNCONVENTIONAL MACHINING PROCESSUNCONVENTIONAL MACHINING PROCESS
UNCONVENTIONAL MACHINING PROCESS
 

Recently uploaded

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 

Recently uploaded (20)

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 

Drilling bit 6

  • 2. ©2006ENSPMFormationIndustrie-IFPTraining SEC Bit selection • This Chapter aims at selecting the bit that will lead to the lowest cost per foot, taking into account angle corrections and reamed sections.. Both Technical and Economical parameters will be involved in this selection. • Due to the great variety of formations to drill and due also to the relative misunderstanding of the characteristics of these formations, of the bits currently available and of the various drilling environments (material and costs..), it is impossible to point out a few bits that would do a great job everywhere.
  • 3. ©2006ENSPMFormationIndustrie-IFPTraining SEC Bit selection • In exploratory wells, geological data regarding the formations to drill come from seismic surveys, regional geology maps and some samples collected here and there, where the corresponding rocks reach the surface.
  • 4. ©2006ENSPMFormationIndustrie-IFPTraining SEC Bit selection • In development wells, lithology, formation thickness and rock characteristics are usually well known. • Cuttings samples, cores, plugs taken on cores, direct measurements on cuttings, gives indications about the nature of the rocks, their compressive strengths, porosity & permeability. • Electric logs, recording of drilling parameters and MWD logs sometimes merged in one single document called Master Log or Composite Log, allows direct correspondence between the parameters, the bit behavior and the rocks being drilled.
  • 6. ©2006ENSPMFormationIndustrie-IFPTraining SEC Bit selection • Another set of information available concerns the bits used in the surrounding wells (called offset wells) under the form of morning reports or bit records. • To optimize the choice of the bit, it is necessary to take into account: – Data concerning the formation to be drilled. – Parameters applied to the bits used in the pevious wells, the performances carried out by these bits and their wear. – Basic equipment and surface installations used (hydraulic power available, capacity of the equipment of mechanical treatment of the solids, composition of the drill stem, etc)
  • 7. ©2006ENSPMFormationIndustrie-IFPTraining SEC Bit selection • Availabilities and of the delivery times of the various types of bits, the surrounded costs of the apparatus and the tools used. • Characteristics of mud used (type, density, content of solids, etc). • Specificities of the well to be drilled (trajectory, slope, etc).
  • 8. ©2006ENSPMFormationIndustrie-IFPTraining SEC Parameters linked to the formation • Drilling performance will be influenced by various parameters linked to the formations to drill, they can be divided in two sets: – The intrinsic properties of the rocks (mineralogy, grain size and fabric of the deposits, matrix strength, porosity ..) – The environment at the time of drilling (confinement pressure, pore pressure, reactions with the drilling fluids, stresses on the rocks..) • The two sets of parameters will interact to modify the rock strength in compression and shearing, abrasivity and behavior at the moment it is destroyed by the bit.
  • 9. ©2006ENSPMFormationIndustrie-IFPTraining SEC Parameters linked to the formation • To have an idea of the formation drillability, it is therefore important to know: – The Rock Composition, by direct observations (cuttings and cores) or by in-situ measurement through electric logs. Both studies are complementary. – The in-situ compaction that is related to the pore pressure and the local stresses (vertical and horizontal). – The value of the stresses that prevail in the area around the well (overburden pressure, rock tensile strength..) These values can be determined by leak off tests, sonic and caliper logs, seismic interpretations (under compacted zones).
  • 10. ©2006ENSPMFormationIndustrie-IFPTraining SEC Information from bits used on previous wells • Information supplied by the dull grading. – Dull grading is a direct and fast way for selecting both the bit and the appropriate parameters for the man on the rig, only if it is properly made. • Cost per Foot. – That is in fact the most important one, as bits are rarely reused (except the diamond bits), looking for the lowest cost per foot, even at the detriment of the bit life is what matters. The longest distance drilled within the shortest time, according to rig power available.
  • 11. ©2006ENSPMFormationIndustrie-IFPTraining SEC Other selection criteria • The capacities of the rig must be taken into account. The power of pumping and rotation must be sufficient to make it possible to use the bit with the parameters envisaged.
  • 12. ©2006ENSPMFormationIndustrie-IFPTraining SEC Conclusion • It is very difficult to choose the best adapted bit to drill a formation for many reasons. • First of all, the technology and the possibilities offered by certain types of bits evolve/move very quickly. Such type of bit which today is not adapted for such type of rock can be it tomorrow. • It also should be remembered that rocks having the same name can have very different characteristics. • The best way to select the best adapted bit to a formation or a phase of drilling is still to establish correlations between the tools used, the parameters applied, the wear of the tools and the characteristics of the rocks to be drilled.