SlideShare a Scribd company logo
1 of 2
RIJNMOND ENERGY CENTER
This project was the first independent power project in the Netherlands. In 2002, ENKA and
Bechtel Joint Venture was awarded the lump sum turnkey (LSTK) EPC contract to build the
Rijnmond Energy Center Project, a combined-cycle cogeneration power plant.
The Rijnmond Energy Center was a natural gas fueled facility with a nominal 790 MW net
output. It consisted of two combustion turbine generators (CTGs), two fired heat-recovery
steam generators (HRSGs), and one lateral exhaust steam turbine generator (STG) in a 2x2x1
configuration. Plant cooling was provided by a mechanical draft, plume-abated cooling tower,
with makeup water from the nearby Petroleum Haven, following processing through an acti-floc
clarifier.
The plant was designed to deliver 125 tons/hour of steam to the nearby Shell refinery and was
designed to a capacity of exporting up to 350 tons/hour.
The CTGs were delivered by Siemens (Germany), the heat recovery steam generators by SFL (the
Netherlands), the STG was by Alstom Power (Germany), the DCS control systems were by ABB-
Bailey (USA), the water treatment plant was by US Filter (USA), the main and auxiliary
transformers by Areva (Turkey), the switchyard by Siemens (Turkey) and the cooling towers by
Balcke-Dür (Germany).
Construction of the Rijnmond Energy Center commenced in August, 2002. Substantial
completion was achieved within 22 months in June, 2004, five months ahead of schedule.
Project Description
• Rijnmond Energy Center
• Engineering
• Procurement
• Construction
• Testing & Pre-Commissioning
• Commissioning
• Start-up
Project Features
• Contract Type : Lump Sum Turn Key
• Scope of Work : Engineering, Procurement, Construction, Testing
& Pre-Commissioning, Commissioning, Start-up
• Client : Rijnmond Energie CV
• Contractor : BECHTEL – ENKA HOLLAND VoF Joint Venture
(ENKA’s share 35 %)
• Project Duration :
1. Start Date 01.08.2002
2. Finish Date 01.06.2004
3. Duration 22 Months
• Location : Rijnmond, Rotterdam, Netherlands

More Related Content

What's hot

Simon Taylor Dissertation
Simon Taylor DissertationSimon Taylor Dissertation
Simon Taylor Dissertation
simontaylor1990
 
[GBC Finlandin jäsentilaisuus 2013] Ilari Aho, Uponor Oy: Upororin toimitilau...
[GBC Finlandin jäsentilaisuus 2013] Ilari Aho, Uponor Oy: Upororin toimitilau...[GBC Finlandin jäsentilaisuus 2013] Ilari Aho, Uponor Oy: Upororin toimitilau...
[GBC Finlandin jäsentilaisuus 2013] Ilari Aho, Uponor Oy: Upororin toimitilau...
GBC Finland
 
arijit summer training
arijit summer trainingarijit summer training
arijit summer training
Arijit Roy
 
A micro chp solution based on a micro gas turbine
A micro chp solution based on a micro gas turbineA micro chp solution based on a micro gas turbine
A micro chp solution based on a micro gas turbine
dkdk444
 
Innovative thermal energy storage technologies (Vincent O'Brien)
Innovative thermal energy storage technologies (Vincent O'Brien)Innovative thermal energy storage technologies (Vincent O'Brien)
Innovative thermal energy storage technologies (Vincent O'Brien)
campone
 
Buildings as Power Stations - Pathway to a Resilient Future for Dorset - Work...
Buildings as Power Stations - Pathway to a Resilient Future for Dorset - Work...Buildings as Power Stations - Pathway to a Resilient Future for Dorset - Work...
Buildings as Power Stations - Pathway to a Resilient Future for Dorset - Work...
Ecological Sequestration Trust
 
THERMAL POWER CYCLES AND THEIR APPs
THERMAL POWER CYCLES AND THEIR APPsTHERMAL POWER CYCLES AND THEIR APPs
THERMAL POWER CYCLES AND THEIR APPs
Prateek Sharma
 

What's hot (20)

Key factors for top availability of geothermal power plants – Exergy’s Experi...
Key factors for top availability of geothermal power plants – Exergy’s Experi...Key factors for top availability of geothermal power plants – Exergy’s Experi...
Key factors for top availability of geothermal power plants – Exergy’s Experi...
 
What it Takes to Harness the Sun
What it Takes to Harness the SunWhat it Takes to Harness the Sun
What it Takes to Harness the Sun
 
Sustained power generation from low-grade heat. sk 270513
Sustained power generation from low-grade heat. sk 270513Sustained power generation from low-grade heat. sk 270513
Sustained power generation from low-grade heat. sk 270513
 
Sagging the Elephant Reserves
Sagging the Elephant ReservesSagging the Elephant Reserves
Sagging the Elephant Reserves
 
Simon Taylor Dissertation
Simon Taylor DissertationSimon Taylor Dissertation
Simon Taylor Dissertation
 
[GBC Finlandin jäsentilaisuus 2013] Ilari Aho, Uponor Oy: Upororin toimitilau...
[GBC Finlandin jäsentilaisuus 2013] Ilari Aho, Uponor Oy: Upororin toimitilau...[GBC Finlandin jäsentilaisuus 2013] Ilari Aho, Uponor Oy: Upororin toimitilau...
[GBC Finlandin jäsentilaisuus 2013] Ilari Aho, Uponor Oy: Upororin toimitilau...
 
arijit summer training
arijit summer trainingarijit summer training
arijit summer training
 
NZEB Office Building by David Walshe
NZEB Office Building by  David WalsheNZEB Office Building by  David Walshe
NZEB Office Building by David Walshe
 
A micro chp solution based on a micro gas turbine
A micro chp solution based on a micro gas turbineA micro chp solution based on a micro gas turbine
A micro chp solution based on a micro gas turbine
 
NZEB Office Building including renewable energy ratio calculation orla coyle
NZEB Office Building including renewable energy ratio calculation  orla coyleNZEB Office Building including renewable energy ratio calculation  orla coyle
NZEB Office Building including renewable energy ratio calculation orla coyle
 
T ds brochure_didsolit
T ds brochure_didsolitT ds brochure_didsolit
T ds brochure_didsolit
 
Nzeb case study esb
Nzeb case study   esbNzeb case study   esb
Nzeb case study esb
 
Avro jv package
Avro jv packageAvro jv package
Avro jv package
 
Innovative thermal energy storage technologies (Vincent O'Brien)
Innovative thermal energy storage technologies (Vincent O'Brien)Innovative thermal energy storage technologies (Vincent O'Brien)
Innovative thermal energy storage technologies (Vincent O'Brien)
 
CHP Units from SAV Systems
CHP Units from SAV Systems CHP Units from SAV Systems
CHP Units from SAV Systems
 
iCool CO2 transcritical condensing units
iCool CO2 transcritical condensing unitsiCool CO2 transcritical condensing units
iCool CO2 transcritical condensing units
 
Introducing the Hualapai Valley Solar Project
Introducing the Hualapai Valley Solar ProjectIntroducing the Hualapai Valley Solar Project
Introducing the Hualapai Valley Solar Project
 
Buildings as Power Stations - Pathway to a Resilient Future for Dorset - Work...
Buildings as Power Stations - Pathway to a Resilient Future for Dorset - Work...Buildings as Power Stations - Pathway to a Resilient Future for Dorset - Work...
Buildings as Power Stations - Pathway to a Resilient Future for Dorset - Work...
 
Harnessing the WhirlWind by AVE Technology
Harnessing the WhirlWind by AVE TechnologyHarnessing the WhirlWind by AVE Technology
Harnessing the WhirlWind by AVE Technology
 
THERMAL POWER CYCLES AND THEIR APPs
THERMAL POWER CYCLES AND THEIR APPsTHERMAL POWER CYCLES AND THEIR APPs
THERMAL POWER CYCLES AND THEIR APPs
 

Similar to RIJNMOND ENERGY CENTER

E.Berkay_EPRO Inc_ Company Profile
E.Berkay_EPRO Inc_ Company ProfileE.Berkay_EPRO Inc_ Company Profile
E.Berkay_EPRO Inc_ Company Profile
Erdal Berkay
 
CIBSEoct10 pp57-60 Hydrogen
CIBSEoct10 pp57-60 HydrogenCIBSEoct10 pp57-60 Hydrogen
CIBSEoct10 pp57-60 Hydrogen
Kevin Stanley
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report
Paul Warrington
 

Similar to RIJNMOND ENERGY CENTER (20)

B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyB4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
 
Combustion technology for generating energy from waste
Combustion technology for generating energy from wasteCombustion technology for generating energy from waste
Combustion technology for generating energy from waste
 
E.Berkay_EPRO Inc_ Company Profile
E.Berkay_EPRO Inc_ Company ProfileE.Berkay_EPRO Inc_ Company Profile
E.Berkay_EPRO Inc_ Company Profile
 
Romelectro general presentation
Romelectro general presentation Romelectro general presentation
Romelectro general presentation
 
Automotive Thermoelectric Generator
Automotive Thermoelectric GeneratorAutomotive Thermoelectric Generator
Automotive Thermoelectric Generator
 
Special AKOTRACE® Electrical Heat Tracing Solution for Gemasolar Solar Power...
Special AKOTRACE®  Electrical Heat Tracing Solution for Gemasolar Solar Power...Special AKOTRACE®  Electrical Heat Tracing Solution for Gemasolar Solar Power...
Special AKOTRACE® Electrical Heat Tracing Solution for Gemasolar Solar Power...
 
CIBSEoct10 pp57-60 Hydrogen
CIBSEoct10 pp57-60 HydrogenCIBSEoct10 pp57-60 Hydrogen
CIBSEoct10 pp57-60 Hydrogen
 
Geothermal Power Plants
Geothermal Power PlantsGeothermal Power Plants
Geothermal Power Plants
 
Find out more about the M+W Energy Center in Dresden
Find out more about the M+W Energy Center in DresdenFind out more about the M+W Energy Center in Dresden
Find out more about the M+W Energy Center in Dresden
 
Sunamp
SunampSunamp
Sunamp
 
Az Zour EPP08
Az Zour EPP08Az Zour EPP08
Az Zour EPP08
 
Energy Storage - 3: Dr Jochen Seier, Federal Ministry of Economics
Energy Storage - 3: Dr Jochen Seier, Federal Ministry of EconomicsEnergy Storage - 3: Dr Jochen Seier, Federal Ministry of Economics
Energy Storage - 3: Dr Jochen Seier, Federal Ministry of Economics
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report
 
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
 
Norway_Johan sverdrup, report 2015
Norway_Johan sverdrup, report 2015Norway_Johan sverdrup, report 2015
Norway_Johan sverdrup, report 2015
 
RCREEE-enerMENA_présentation algeria
RCREEE-enerMENA_présentation  algeriaRCREEE-enerMENA_présentation  algeria
RCREEE-enerMENA_présentation algeria
 
Show and Tell - Heat.pdf
Show and Tell - Heat.pdfShow and Tell - Heat.pdf
Show and Tell - Heat.pdf
 
Thyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressureThyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressure
 
A Modular C2 Splitter - Hydrocarbon Engineering April 2017
A Modular C2 Splitter - Hydrocarbon Engineering April 2017A Modular C2 Splitter - Hydrocarbon Engineering April 2017
A Modular C2 Splitter - Hydrocarbon Engineering April 2017
 
Gama power plant -- An overview (2018)
Gama power plant -- An overview (2018)Gama power plant -- An overview (2018)
Gama power plant -- An overview (2018)
 

RIJNMOND ENERGY CENTER

  • 1. RIJNMOND ENERGY CENTER This project was the first independent power project in the Netherlands. In 2002, ENKA and Bechtel Joint Venture was awarded the lump sum turnkey (LSTK) EPC contract to build the Rijnmond Energy Center Project, a combined-cycle cogeneration power plant. The Rijnmond Energy Center was a natural gas fueled facility with a nominal 790 MW net output. It consisted of two combustion turbine generators (CTGs), two fired heat-recovery steam generators (HRSGs), and one lateral exhaust steam turbine generator (STG) in a 2x2x1 configuration. Plant cooling was provided by a mechanical draft, plume-abated cooling tower, with makeup water from the nearby Petroleum Haven, following processing through an acti-floc clarifier. The plant was designed to deliver 125 tons/hour of steam to the nearby Shell refinery and was designed to a capacity of exporting up to 350 tons/hour. The CTGs were delivered by Siemens (Germany), the heat recovery steam generators by SFL (the Netherlands), the STG was by Alstom Power (Germany), the DCS control systems were by ABB- Bailey (USA), the water treatment plant was by US Filter (USA), the main and auxiliary transformers by Areva (Turkey), the switchyard by Siemens (Turkey) and the cooling towers by Balcke-Dür (Germany). Construction of the Rijnmond Energy Center commenced in August, 2002. Substantial completion was achieved within 22 months in June, 2004, five months ahead of schedule. Project Description • Rijnmond Energy Center • Engineering • Procurement • Construction • Testing & Pre-Commissioning • Commissioning • Start-up Project Features • Contract Type : Lump Sum Turn Key • Scope of Work : Engineering, Procurement, Construction, Testing
  • 2. & Pre-Commissioning, Commissioning, Start-up • Client : Rijnmond Energie CV • Contractor : BECHTEL – ENKA HOLLAND VoF Joint Venture (ENKA’s share 35 %) • Project Duration : 1. Start Date 01.08.2002 2. Finish Date 01.06.2004 3. Duration 22 Months • Location : Rijnmond, Rotterdam, Netherlands