RENEWABLE ENERGY JORDANIE 2013
Presentation Of The Company
The Company of the Engineering of Electricity and Gas CEEG spa is a subsidiary company of SONELGAZ
HOLDING, it has in charge of the control of work (studies, control, work, reception and brought into service) of
the projects of realization of energy infrastructures (means of electricity production and gas, networks gas
transport and high voltage),all of that in the best technical conditions, of cost, quality and schedule of realization.
CEEG spa has the roles of :
1 To contribute to the development of general policies of the holding in the fields :
• Investments
• Technical
• Mode of realization of work
• Planning
2 To work out the programs of studies and work and to ensure their realization pursuant to the decisions of
committee of investment of the holding.
3 To promote and develop national integration in the various phases of construction of the works.
4 To take care of the quality of the design and the studies carried out.
5 To take care of the strict application of the rules of management of the investments, the orders and the
markets and contracts.
6 To ensure the permanent control of the building sites the various phases of realization (inspection vehicle,
quantity, cost, tests and control before reception and startup of the equipment).
Power Plants
Electric stations
Powerlines
Telecommunications
Renewables Energies
Gas
 Activities Activities
Président Directeur Général
Mr Arkab Mohamed
Direction Engineering
Réseau Haute Tension
Direction Engineering Gaz
Direction Engineering
Télécommunications
Direction Engineering Energies
Renouvelables
Direction Engineering Postes
Direction Engineering Lignes
Attachées Communication Assistante de La Direction Générale
Direction Engineering
Des Moyens de Production Direction Ressources Humaines
Direction Finances et Comptabilité
Direction Juridique et
Réglementation des Marchés
Division Commerciale
Service Développement Informatique
Service Affaires Générales
Directeur SIE
Our Organisation
Map of transmission of electric-energy
Fiber optic network
gas transport network
Renewable energy projects under construction
photovoltaic
panels plants of
1100 KWc in
Ghardaia
wind farm of 10,2 MW in
KABERTENE - ADRAR
Electrification by
Photovoltaic power
References
Acquisition of ten (10)
weather stations
measure
Realization of the factory of
manufacture of photovoltaic
modules in Rouïba of a capacity
of production of 200 MWc/an.
5
1
Electrification by Photovoltaic power2
4
3 Photovoltaic plants of 1100 KWc in Ghardaia
Wind farm of 10,2 MW in KABERTENE - ADRAR
II. Project Under construction
5
.
factory of manufacture of photovoltaic modules in Rouïba of 200 MWc/an
Acquisition of ten (10) weather stations measure
 Technology selected Silicium multi cristallin
 Client: ROUIBA ECLAIRAGE. Spa
 Contractors : CEEG / Primo contractor, SIDEM / civil plans, CTC / supervision of
works , INERGA /civil Works, ETTERKIB / for Installation of équipements ,
 Réalization deadline : 38 mois
 The land area: 4,2 Hectares
 Client: Sociétés de Distribution de l’Est SDE, l’Ouest SDO et Centre SDC.
 Contractor :Le groupement Algérien Inter entreprise/ Aquatec
 The land area for one solar Kit : 05 MW
 Réalization deadline : 12 months
Photovoltaic plants of 1100 KWc in Ghardaia
Eolienne + kiosque
……….Suite
 Maître d’Ouvrage: SPE Société Algérienne de Production de l’Electricité _ filiale sonelgaz,
 Délai de réalisation du projet: 08 mois
 Contrat attribué provisoirement à ATLAS AGRO (Suisse) pour l’Acquisition des équipements
des stations avec supervision du montage et mise en service d’une station pilote.
 Elaboration d’un cahier des charges pour l’étude, fourniture et installation de neufs mâts de
mesure météorologiques avec la réalisation des travaux de génie civil en cours.
Acquisition of ten (10) weather stations measure
IV. Project Before Construction
Projet centrale géothermique
de 5 MWe à GUELMA
Projet de réalisation d’une ferme éolienne
de 20MW à KHENCHELA
Projets centrales en panneaux photovoltaïques de 3 MW à DJANET,9 MW à TINDOUF
et 13 MW à TAMANRASSET
RCREEE-enerMENA_présentation  algeria

RCREEE-enerMENA_présentation algeria

  • 1.
  • 2.
    Presentation Of TheCompany The Company of the Engineering of Electricity and Gas CEEG spa is a subsidiary company of SONELGAZ HOLDING, it has in charge of the control of work (studies, control, work, reception and brought into service) of the projects of realization of energy infrastructures (means of electricity production and gas, networks gas transport and high voltage),all of that in the best technical conditions, of cost, quality and schedule of realization. CEEG spa has the roles of : 1 To contribute to the development of general policies of the holding in the fields : • Investments • Technical • Mode of realization of work • Planning 2 To work out the programs of studies and work and to ensure their realization pursuant to the decisions of committee of investment of the holding. 3 To promote and develop national integration in the various phases of construction of the works. 4 To take care of the quality of the design and the studies carried out. 5 To take care of the strict application of the rules of management of the investments, the orders and the markets and contracts. 6 To ensure the permanent control of the building sites the various phases of realization (inspection vehicle, quantity, cost, tests and control before reception and startup of the equipment).
  • 3.
  • 4.
    Président Directeur Général MrArkab Mohamed Direction Engineering Réseau Haute Tension Direction Engineering Gaz Direction Engineering Télécommunications Direction Engineering Energies Renouvelables Direction Engineering Postes Direction Engineering Lignes Attachées Communication Assistante de La Direction Générale Direction Engineering Des Moyens de Production Direction Ressources Humaines Direction Finances et Comptabilité Direction Juridique et Réglementation des Marchés Division Commerciale Service Développement Informatique Service Affaires Générales Directeur SIE Our Organisation
  • 5.
    Map of transmissionof electric-energy
  • 6.
  • 7.
  • 8.
    Renewable energy projectsunder construction photovoltaic panels plants of 1100 KWc in Ghardaia wind farm of 10,2 MW in KABERTENE - ADRAR Electrification by Photovoltaic power References Acquisition of ten (10) weather stations measure Realization of the factory of manufacture of photovoltaic modules in Rouïba of a capacity of production of 200 MWc/an.
  • 9.
    5 1 Electrification by Photovoltaicpower2 4 3 Photovoltaic plants of 1100 KWc in Ghardaia Wind farm of 10,2 MW in KABERTENE - ADRAR II. Project Under construction 5 . factory of manufacture of photovoltaic modules in Rouïba of 200 MWc/an Acquisition of ten (10) weather stations measure
  • 10.
     Technology selectedSilicium multi cristallin  Client: ROUIBA ECLAIRAGE. Spa  Contractors : CEEG / Primo contractor, SIDEM / civil plans, CTC / supervision of works , INERGA /civil Works, ETTERKIB / for Installation of équipements ,  Réalization deadline : 38 mois  The land area: 4,2 Hectares
  • 11.
     Client: Sociétésde Distribution de l’Est SDE, l’Ouest SDO et Centre SDC.  Contractor :Le groupement Algérien Inter entreprise/ Aquatec  The land area for one solar Kit : 05 MW  Réalization deadline : 12 months
  • 12.
    Photovoltaic plants of1100 KWc in Ghardaia
  • 13.
  • 14.
    ……….Suite  Maître d’Ouvrage:SPE Société Algérienne de Production de l’Electricité _ filiale sonelgaz,  Délai de réalisation du projet: 08 mois  Contrat attribué provisoirement à ATLAS AGRO (Suisse) pour l’Acquisition des équipements des stations avec supervision du montage et mise en service d’une station pilote.  Elaboration d’un cahier des charges pour l’étude, fourniture et installation de neufs mâts de mesure météorologiques avec la réalisation des travaux de génie civil en cours. Acquisition of ten (10) weather stations measure
  • 15.
    IV. Project BeforeConstruction Projet centrale géothermique de 5 MWe à GUELMA Projet de réalisation d’une ferme éolienne de 20MW à KHENCHELA Projets centrales en panneaux photovoltaïques de 3 MW à DJANET,9 MW à TINDOUF et 13 MW à TAMANRASSET