SlideShare a Scribd company logo
1 of 30
Scaffolding
Safety
D E PA R T M E N T O R D E R N O . 1 2 8
S e r i e s o f 2 0 1 3
A M E N D I N G R U L E 1 4 1 4 O N
S C A F F O L D I N G S O F T H E 1 9 8 9
O C C U PAT I O N A L H E A LT H A N D
S A F E T Y S TA N D A R D S
What is a scaffolding?
INTRODUCTION
It refers to a temporary or
movable platform supported on
the ground or suspended, used
for access and/or working at
considerable heights above
ground.
Working platform
Platform and walking passage
FUNCTIONS
OF A SCAFFOLDING
Classification of Scaffolds
⚬Supported Scaffolds
⚬Suspended Scaffolds
⚬Mobile
⚬Ladder
⚬Tube and coupler
⚬Frame
⚬Timber
Supported Scaffolds
⚬Bamboo
⚬Trestle
⚬Form and Carpenter’s
Bracket
⚬Roof Bracket
⚬Window Jack
Supported Scaffolds
⚬ Two-point adjustable
suspension
⚬ Single-point adjustable
suspension
Suspended Scaffolds
⚬ Design instruction shall be prepared by the end user.
⚬ Design shall be in accordance with recognized engineering principles.
⚬ Shall be designed with regard to ease and safety of erection and dismantling.
⚬ Supported scaffolds shall be capable of supporting without failure at least four (4)
times the maximum intended load, while suspended scaffolds shall have six (6)
times factor of safety.
⚬ All scaffolds designed by a structural engineer shall be approved by appropriate
authority.
DESIGN AND STABILITY
DESIGN
•Shall have vertical members(posts) diagonally and horizontally braced.
•No splices between the points of support of load carrying horizontal members and
secured to prevent lateral movement.
•The footing, sills or anchorage – sound, rigid, and capable of carrying twice the
maximum intended load.
•Posts shall rest on a foundation of sufficient size and strength to spread the load
from the posts.
•Any damaged or weakened scaffold members shall be immediately repaired,
replaced or discarded.
STRENGTH & STABILITY
DESIGN AND STABILITY
•Not be overloaded for which they are intended.
•Anchored or secured to permanent or rigid structures.
•Components produced by different manufacturers shall not be intermixed unless
the components fit together without force and the scaffold’s structural integrity is
maintained by the user.
•Front-end loaders and similar types of equipment shall not be used to support
scaffold platforms unless they have been specifically designed by the manufacturer
or such use.
STRENGTH & STABILITY
DESIGN AND STABILITY
•Must be inspected either upon delivery or before it is erected/installed.
•Any defective material shall be repaired, replaced or discarded.
•Lumber with two (2) nail holes aligned crosswise or four (4) nail holes
along its length shall not be used as horizontal load bearing member of
scaffold
INSPECTION OF SCAFFOLDS
•Check ground conditions, overhead wires, obstructions, changes in surface
elevation, and structural support.
• Ensure the following in site preparation:
• Soil are level and firm.
• Mud and soft soil are replaced with compacted gravel or crushed stone.
• On sloping grounds, the area where mudsills rest shall be leveled by
excavating rather than backfilling
SITE INSPECTION & PREPARATION
•Direct supervision of a competent/qualified person as the case may be.
•Maintained plumb regardless of connection.
•Conform to the designer’s specification.
•Runners shall be perpendicular to the posts. Spacing shall conform to the
designed scaffold.
•Diagonal braces shall extend from one connection to another.
•Diagonal braces shall not exceed an angle of 60deg from horizontal.
•Diagonal braces shall be installed immediately.
SCAFFOLD ERECTION
•All posts shall be joined or connected by means of joint pin, spigot or any
appropriate means of connections.
•Always maintain the base width to height ratio of 1:4 during installation for stability.
•No scaffold activity shall be undertaken if the wind velocity exceeds 48 kph.
•No work shall be allowed to commence below the scaffold.
•Working platform shall be provided per level during erection.
SCAFFOLD ERECTION
•Scaffolds of more than 6 meters in height shall be designed by a structural
engineer and shall be erected, installed and dismantled by TESDA certified
erectors.
•Scaffold shall be erected, added, altered or dismantled only under the supervision
of the competent/qualified person in the construction.
SCAFFOLD ERECTION
⚬ Performed by a qualified and competent person.
⚬ All manufactured scaffolds shall follow the manufacturers’ recommendations.
• Direct connections shall be evaluated by a qualified or competent person who
shall confirm.
• Inspections should be carried out daily and every shift.
INSPECTION & TAGGING
•Identification tags – solid green, yellow, or red color with black lettering.
•Tags shall be hanged in every scaffold access points.
■ Green tags – scaffolds access that have been inspected and are safe for use.
■ Yellow tags – special requirements for safe use are required and shall be closely
supervised.
■ Red “DANGER – UNSAFE FOR USE” tags – used when all green or yellow tags
has been removed.
All the records of the inspections shall be available on site and made available to
proper authority upon request.
INSPECTION & TAGGING
•Properly maintained, fixed and secured in position to prevent displacement.
•Not to be used unless it is rendered stable, strong and safe for the purpose.
•Left standing for four (4) months shall not be used until damaged members are
replaced.
MAINTENANCE DURING USE
⚬ Must be done by trained personnel.
⚬ Proceed in reverse order to its erection.
⚬ Workers should wear a safety harness and lanyard tied off to a secured anchor
before attempting to loosen stuck or jammed parts.
⚬ Do not hammer or pry apart the scaffold components.
⚬ Do not throw scaffold components.
SCAFFOLD DISMANTLING
•All scaffolds shall be properly maintained, kept, clean, and free of
damage.
• Accessories requiring lubrication shall be oiled prior to storage in a
covered or closed container, or as per manufacturer’s recommendation.
MAINTENANCE & STORAGE
BASIC CONSIDERATION
⚬The weight of workers, tools, materials and equipment to be carried by
the scaffold system.
⚬Site conditions
⚬Height to which the scaffold may be erected.
⚬Type of work that will be done from the scaffold.
SCAFFOLD AND TYPE SELECTIONS
SCAFFOLD AND TYPE SELECTIONS
BASIC CONSIDERATION
⚬Duration of work
⚬Weather conditions, including wind
⚬Requirements for pedestrian traffic through and under the scaffold area
⚬Means of access to the scaffold
⚬Configuration of the building or structure being worked on.
⚬Wind speed limit is 48kph (DO 128) and 40kph (International Practice)
SCAFFOLD AND TYPE SELECTIONS
SCAFFOLD CAPACITY
⚬Scaffolds must be capable of supporting its own weight and at least 4x the
expected load. Expected load includes Live Load + Dead Load.
SCAFFOLD LOAD RATINGS
⚬ The allowable working load of scaffolding is 3,450kg per leg [TESDA]
⚬ The allowable working load of scaffolding is 150 kg per sq. m [DO 128]
OVERLOADING
⚬ Most frequent violations in scaffold practice.
HOUSEKEEPING
⚬ Scaffold decks are usually small, narrow and confined. Debris and waste
materials should not be allowed to collect on the platform.
SAFETY
SAFE SCAFFOLD USE
⚬Do not use damaged parts that affect the strength of the scaffold.
⚬Do not allow employees to work on scaffolds when they are feeling weak, sick,
or dizzy.
⚬Do not work from any part of the scaffold other than the platform.
⚬Do not alter the scaffold.
⚬Do not move a scaffold horizontally while workers are on it, unless it is a mobile
scaffold and the proper procedures are followed.
⚬Do not put more weight on a scaffold than it is designed to hold.
SAFETY
SAFE SCAFFOLD USE
⚬Do not allow employees to work on scaffolds covered slippery materials.
⚬Do not erect, use, alter, or move scaffolds within 10 feet of overhead power
lines.
⚬Do not use shore or lean-to scaffolds.
⚬Do not swing loads near or on scaffolds unless you use a tag line.
⚬Do not work on scaffolds in bad weather or high winds unless the competent
person decides that doing so is safe.
⚬Do not let extra material build up on the platforms.
⚬Do not use ladders, boxes, barrels, or other makeshift contraptions to raise your
work height.
SAFETY
TRAINING & COMPETENCY
Competent Person - responsible for determining the feasibility and safety of providing
fall protection for personnel erecting, installing or dismantling scaffolds.
■ Must undergo the standard scaffold training and assessment prescribed by
DOLE and TESDA.
■ Training Certificate from DOLE or its accredited safety training organization.
■ Holder of TESDA prescribed Scaffold Erection Certificate.
■ At least 2 years experience in scaffold erection.
TRAINING & COMPETENCY
Scaffold Erector
■ Must undergo the standard scaffold training and assessment prescribed by
DOLE and TESDA.
■ One Day Workers Safety Orientation from DOLE or its accredited safety
training organization.
■ Must be a holder of TESDA prescribed Scaffold Erection NC II
END OF PRESENTATION

More Related Content

What's hot

Signalman training
Signalman trainingSignalman training
Signalman trainingRob Cowden
 
SCAFFOLDING SAFETY.ppt
SCAFFOLDING SAFETY.pptSCAFFOLDING SAFETY.ppt
SCAFFOLDING SAFETY.ppthamoudahedi
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingWilliam York
 
Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.pptIrfanAwan25
 
scaffolding safety.pdf
scaffolding safety.pdfscaffolding safety.pdf
scaffolding safety.pdfShahzadaGull1
 
Light bulb jsa
Light bulb jsaLight bulb jsa
Light bulb jsavtsiri
 
Seminar Cakna KKP - CONFINED SPACE Every Entry Shouldn't Be A One Way Trip
Seminar Cakna KKP - CONFINED SPACE Every Entry Shouldn't Be A One Way TripSeminar Cakna KKP - CONFINED SPACE Every Entry Shouldn't Be A One Way Trip
Seminar Cakna KKP - CONFINED SPACE Every Entry Shouldn't Be A One Way TripMoon Girl
 
04 trabajos en altura
04 trabajos en altura 04 trabajos en altura
04 trabajos en altura Fredy Ceras
 
Trenching Safety Training by State of Georgia
Trenching Safety Training by State of GeorgiaTrenching Safety Training by State of Georgia
Trenching Safety Training by State of GeorgiaAtlantic Training, LLC.
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxssuser926916
 
SG4:10 presentation
SG4:10 presentationSG4:10 presentation
SG4:10 presentationAlan Bate
 

What's hot (20)

Eta Scaffold Training
Eta Scaffold TrainingEta Scaffold Training
Eta Scaffold Training
 
Scaffolds ppt construction
Scaffolds ppt constructionScaffolds ppt construction
Scaffolds ppt construction
 
Signalman training
Signalman trainingSignalman training
Signalman training
 
SCAFFOLDING SAFETY.ppt
SCAFFOLDING SAFETY.pptSCAFFOLDING SAFETY.ppt
SCAFFOLDING SAFETY.ppt
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety Training
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.ppt
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
scaffolding safety.pdf
scaffolding safety.pdfscaffolding safety.pdf
scaffolding safety.pdf
 
Light bulb jsa
Light bulb jsaLight bulb jsa
Light bulb jsa
 
Seminar Cakna KKP - CONFINED SPACE Every Entry Shouldn't Be A One Way Trip
Seminar Cakna KKP - CONFINED SPACE Every Entry Shouldn't Be A One Way TripSeminar Cakna KKP - CONFINED SPACE Every Entry Shouldn't Be A One Way Trip
Seminar Cakna KKP - CONFINED SPACE Every Entry Shouldn't Be A One Way Trip
 
Confined Space Entry
Confined Space EntryConfined Space Entry
Confined Space Entry
 
Excavation & Trench Safety by NUCA
Excavation & Trench Safety by NUCAExcavation & Trench Safety by NUCA
Excavation & Trench Safety by NUCA
 
04 trabajos en altura
04 trabajos en altura 04 trabajos en altura
04 trabajos en altura
 
Trenching Safety Training by State of Georgia
Trenching Safety Training by State of GeorgiaTrenching Safety Training by State of Georgia
Trenching Safety Training by State of Georgia
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptx
 
Scaffolds by Safety Resources
Scaffolds by Safety ResourcesScaffolds by Safety Resources
Scaffolds by Safety Resources
 
Working at height slides
Working at height slidesWorking at height slides
Working at height slides
 
SG4:10 presentation
SG4:10 presentationSG4:10 presentation
SG4:10 presentation
 
Overhead Crane Operators by
Overhead  Crane Operators byOverhead  Crane Operators by
Overhead Crane Operators by
 

Similar to DO 128 - 13 SCAFFOLDING SAFETY.pptx

Scaffold And Aerial Lift Training by KTA
Scaffold And Aerial Lift Training by KTAScaffold And Aerial Lift Training by KTA
Scaffold And Aerial Lift Training by KTAAtlantic Training, LLC.
 
Safety Procedures while working in height
Safety Procedures while working in heightSafety Procedures while working in height
Safety Procedures while working in heightRoman Shrestha
 
Module 3.pptx
Module 3.pptxModule 3.pptx
Module 3.pptxShijo25
 
WORK AT HEIGHT.pptx
WORK AT HEIGHT.pptxWORK AT HEIGHT.pptx
WORK AT HEIGHT.pptxDavidNanda3
 
Scaffolding safety procedures and its types
Scaffolding safety procedures and its typesScaffolding safety procedures and its types
Scaffolding safety procedures and its typesabhisheksharma12001
 
DOC-20231115-WA0057..pdf
DOC-20231115-WA0057..pdfDOC-20231115-WA0057..pdf
DOC-20231115-WA0057..pdfrajaahmed49
 
Scaffolding by chakamba j
Scaffolding by chakamba jScaffolding by chakamba j
Scaffolding by chakamba jJohn Chakamba
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction siteNMRD Ltd
 
Safety while Working at Height
Safety while Working at HeightSafety while Working at Height
Safety while Working at HeightBimal Chandra Das
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction siteNMRD Ltd
 
WORKING AT HEIGHT pptx
WORKING AT HEIGHT pptxWORKING AT HEIGHT pptx
WORKING AT HEIGHT pptxDavidNanda3
 
Construction Fall Protection
Construction Fall Protection Construction Fall Protection
Construction Fall Protection John Newquist
 
Safe Material Handling
Safe Material Handling Safe Material Handling
Safe Material Handling Reliance
 

Similar to DO 128 - 13 SCAFFOLDING SAFETY.pptx (20)

Scaffolding safety at construction site
Scaffolding safety at construction siteScaffolding safety at construction site
Scaffolding safety at construction site
 
Scaffold and Aerial Lift Safety by KTA
Scaffold and Aerial Lift Safety by KTAScaffold and Aerial Lift Safety by KTA
Scaffold and Aerial Lift Safety by KTA
 
Scaffold And Aerial Lift Training by KTA
Scaffold And Aerial Lift Training by KTAScaffold And Aerial Lift Training by KTA
Scaffold And Aerial Lift Training by KTA
 
Safety Procedures while working in height
Safety Procedures while working in heightSafety Procedures while working in height
Safety Procedures while working in height
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Module 3.pptx
Module 3.pptxModule 3.pptx
Module 3.pptx
 
Scaffold Safety (2).ppt
Scaffold Safety (2).pptScaffold Safety (2).ppt
Scaffold Safety (2).ppt
 
Scaffolding by UTK
Scaffolding by UTKScaffolding by UTK
Scaffolding by UTK
 
WORK AT HEIGHT.pptx
WORK AT HEIGHT.pptxWORK AT HEIGHT.pptx
WORK AT HEIGHT.pptx
 
Scaffolding safety procedures and its types
Scaffolding safety procedures and its typesScaffolding safety procedures and its types
Scaffolding safety procedures and its types
 
DOC-20231115-WA0057..pdf
DOC-20231115-WA0057..pdfDOC-20231115-WA0057..pdf
DOC-20231115-WA0057..pdf
 
Scaffolding by chakamba j
Scaffolding by chakamba jScaffolding by chakamba j
Scaffolding by chakamba j
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction site
 
Safety while Working at Height
Safety while Working at HeightSafety while Working at Height
Safety while Working at Height
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction site
 
WORKING AT HEIGHT pptx
WORKING AT HEIGHT pptxWORKING AT HEIGHT pptx
WORKING AT HEIGHT pptx
 
Construction safety VI
Construction safety VIConstruction safety VI
Construction safety VI
 
Construction Fall Protection
Construction Fall Protection Construction Fall Protection
Construction Fall Protection
 
SCAFFOLDING
SCAFFOLDINGSCAFFOLDING
SCAFFOLDING
 
Safe Material Handling
Safe Material Handling Safe Material Handling
Safe Material Handling
 

Recently uploaded

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Recently uploaded (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

DO 128 - 13 SCAFFOLDING SAFETY.pptx

  • 2. D E PA R T M E N T O R D E R N O . 1 2 8 S e r i e s o f 2 0 1 3 A M E N D I N G R U L E 1 4 1 4 O N S C A F F O L D I N G S O F T H E 1 9 8 9 O C C U PAT I O N A L H E A LT H A N D S A F E T Y S TA N D A R D S
  • 3. What is a scaffolding? INTRODUCTION It refers to a temporary or movable platform supported on the ground or suspended, used for access and/or working at considerable heights above ground.
  • 4. Working platform Platform and walking passage FUNCTIONS OF A SCAFFOLDING
  • 5. Classification of Scaffolds ⚬Supported Scaffolds ⚬Suspended Scaffolds
  • 7. ⚬Bamboo ⚬Trestle ⚬Form and Carpenter’s Bracket ⚬Roof Bracket ⚬Window Jack Supported Scaffolds
  • 8. ⚬ Two-point adjustable suspension ⚬ Single-point adjustable suspension Suspended Scaffolds
  • 9. ⚬ Design instruction shall be prepared by the end user. ⚬ Design shall be in accordance with recognized engineering principles. ⚬ Shall be designed with regard to ease and safety of erection and dismantling. ⚬ Supported scaffolds shall be capable of supporting without failure at least four (4) times the maximum intended load, while suspended scaffolds shall have six (6) times factor of safety. ⚬ All scaffolds designed by a structural engineer shall be approved by appropriate authority. DESIGN AND STABILITY DESIGN
  • 10. •Shall have vertical members(posts) diagonally and horizontally braced. •No splices between the points of support of load carrying horizontal members and secured to prevent lateral movement. •The footing, sills or anchorage – sound, rigid, and capable of carrying twice the maximum intended load. •Posts shall rest on a foundation of sufficient size and strength to spread the load from the posts. •Any damaged or weakened scaffold members shall be immediately repaired, replaced or discarded. STRENGTH & STABILITY DESIGN AND STABILITY
  • 11. •Not be overloaded for which they are intended. •Anchored or secured to permanent or rigid structures. •Components produced by different manufacturers shall not be intermixed unless the components fit together without force and the scaffold’s structural integrity is maintained by the user. •Front-end loaders and similar types of equipment shall not be used to support scaffold platforms unless they have been specifically designed by the manufacturer or such use. STRENGTH & STABILITY DESIGN AND STABILITY
  • 12. •Must be inspected either upon delivery or before it is erected/installed. •Any defective material shall be repaired, replaced or discarded. •Lumber with two (2) nail holes aligned crosswise or four (4) nail holes along its length shall not be used as horizontal load bearing member of scaffold INSPECTION OF SCAFFOLDS
  • 13. •Check ground conditions, overhead wires, obstructions, changes in surface elevation, and structural support. • Ensure the following in site preparation: • Soil are level and firm. • Mud and soft soil are replaced with compacted gravel or crushed stone. • On sloping grounds, the area where mudsills rest shall be leveled by excavating rather than backfilling SITE INSPECTION & PREPARATION
  • 14. •Direct supervision of a competent/qualified person as the case may be. •Maintained plumb regardless of connection. •Conform to the designer’s specification. •Runners shall be perpendicular to the posts. Spacing shall conform to the designed scaffold. •Diagonal braces shall extend from one connection to another. •Diagonal braces shall not exceed an angle of 60deg from horizontal. •Diagonal braces shall be installed immediately. SCAFFOLD ERECTION
  • 15. •All posts shall be joined or connected by means of joint pin, spigot or any appropriate means of connections. •Always maintain the base width to height ratio of 1:4 during installation for stability. •No scaffold activity shall be undertaken if the wind velocity exceeds 48 kph. •No work shall be allowed to commence below the scaffold. •Working platform shall be provided per level during erection. SCAFFOLD ERECTION
  • 16. •Scaffolds of more than 6 meters in height shall be designed by a structural engineer and shall be erected, installed and dismantled by TESDA certified erectors. •Scaffold shall be erected, added, altered or dismantled only under the supervision of the competent/qualified person in the construction. SCAFFOLD ERECTION
  • 17. ⚬ Performed by a qualified and competent person. ⚬ All manufactured scaffolds shall follow the manufacturers’ recommendations. • Direct connections shall be evaluated by a qualified or competent person who shall confirm. • Inspections should be carried out daily and every shift. INSPECTION & TAGGING
  • 18. •Identification tags – solid green, yellow, or red color with black lettering. •Tags shall be hanged in every scaffold access points. ■ Green tags – scaffolds access that have been inspected and are safe for use. ■ Yellow tags – special requirements for safe use are required and shall be closely supervised. ■ Red “DANGER – UNSAFE FOR USE” tags – used when all green or yellow tags has been removed. All the records of the inspections shall be available on site and made available to proper authority upon request. INSPECTION & TAGGING
  • 19. •Properly maintained, fixed and secured in position to prevent displacement. •Not to be used unless it is rendered stable, strong and safe for the purpose. •Left standing for four (4) months shall not be used until damaged members are replaced. MAINTENANCE DURING USE
  • 20. ⚬ Must be done by trained personnel. ⚬ Proceed in reverse order to its erection. ⚬ Workers should wear a safety harness and lanyard tied off to a secured anchor before attempting to loosen stuck or jammed parts. ⚬ Do not hammer or pry apart the scaffold components. ⚬ Do not throw scaffold components. SCAFFOLD DISMANTLING
  • 21. •All scaffolds shall be properly maintained, kept, clean, and free of damage. • Accessories requiring lubrication shall be oiled prior to storage in a covered or closed container, or as per manufacturer’s recommendation. MAINTENANCE & STORAGE
  • 22. BASIC CONSIDERATION ⚬The weight of workers, tools, materials and equipment to be carried by the scaffold system. ⚬Site conditions ⚬Height to which the scaffold may be erected. ⚬Type of work that will be done from the scaffold. SCAFFOLD AND TYPE SELECTIONS
  • 23. SCAFFOLD AND TYPE SELECTIONS BASIC CONSIDERATION ⚬Duration of work ⚬Weather conditions, including wind ⚬Requirements for pedestrian traffic through and under the scaffold area ⚬Means of access to the scaffold ⚬Configuration of the building or structure being worked on. ⚬Wind speed limit is 48kph (DO 128) and 40kph (International Practice)
  • 24. SCAFFOLD AND TYPE SELECTIONS SCAFFOLD CAPACITY ⚬Scaffolds must be capable of supporting its own weight and at least 4x the expected load. Expected load includes Live Load + Dead Load. SCAFFOLD LOAD RATINGS ⚬ The allowable working load of scaffolding is 3,450kg per leg [TESDA] ⚬ The allowable working load of scaffolding is 150 kg per sq. m [DO 128]
  • 25. OVERLOADING ⚬ Most frequent violations in scaffold practice. HOUSEKEEPING ⚬ Scaffold decks are usually small, narrow and confined. Debris and waste materials should not be allowed to collect on the platform. SAFETY
  • 26. SAFE SCAFFOLD USE ⚬Do not use damaged parts that affect the strength of the scaffold. ⚬Do not allow employees to work on scaffolds when they are feeling weak, sick, or dizzy. ⚬Do not work from any part of the scaffold other than the platform. ⚬Do not alter the scaffold. ⚬Do not move a scaffold horizontally while workers are on it, unless it is a mobile scaffold and the proper procedures are followed. ⚬Do not put more weight on a scaffold than it is designed to hold. SAFETY
  • 27. SAFE SCAFFOLD USE ⚬Do not allow employees to work on scaffolds covered slippery materials. ⚬Do not erect, use, alter, or move scaffolds within 10 feet of overhead power lines. ⚬Do not use shore or lean-to scaffolds. ⚬Do not swing loads near or on scaffolds unless you use a tag line. ⚬Do not work on scaffolds in bad weather or high winds unless the competent person decides that doing so is safe. ⚬Do not let extra material build up on the platforms. ⚬Do not use ladders, boxes, barrels, or other makeshift contraptions to raise your work height. SAFETY
  • 28. TRAINING & COMPETENCY Competent Person - responsible for determining the feasibility and safety of providing fall protection for personnel erecting, installing or dismantling scaffolds. ■ Must undergo the standard scaffold training and assessment prescribed by DOLE and TESDA. ■ Training Certificate from DOLE or its accredited safety training organization. ■ Holder of TESDA prescribed Scaffold Erection Certificate. ■ At least 2 years experience in scaffold erection.
  • 29. TRAINING & COMPETENCY Scaffold Erector ■ Must undergo the standard scaffold training and assessment prescribed by DOLE and TESDA. ■ One Day Workers Safety Orientation from DOLE or its accredited safety training organization. ■ Must be a holder of TESDA prescribed Scaffold Erection NC II

Editor's Notes

  1. 1.7.2013
  2. 1.7.2013
  3. 1.7.2013
  4. 1.7.2013
  5. 1.7.2013
  6. 1.7.2013
  7. 1.7.2013
  8. 1.7.2013
  9. 1.7.2013
  10. 1.7.2013
  11. 1.7.2013
  12. 1.7.2013
  13. 1.7.2013
  14. 1.7.2013
  15. 1.7.2013
  16. 1.7.2013
  17. 1.7.2013
  18. 1.7.2013
  19. 1.7.2013
  20. 1.7.2013
  21. 1.7.2013
  22. 1.7.2013
  23. 1.7.2013