SlideShare a Scribd company logo
1 of 113
Download to read offline
The Design of
Earth-retaining Structures
ENB485
Chris Bridges
The Design of
Earth-retaining Structures
ENB485
Chris Bridges
The Design of
Earth-retaining Structures
ENB485
Chris Bridges
May 2016
Lecture 6
Design of Earth-retaining Structures
Soil Nailing
17
Soil Nailing
What is soil nailing?
Anchors
Soil Nails
Soil Dowels
12 March 2015
ENB 485
3
What is soil nailing?
Anchor analogy – threaded bolt
Generates tensile force in
member
Normal force creates shear
stresses along failure plane
Requires pre-stress to be
maintained over life of structure –
(active structure)
12 March 2015
ENB 485
4
What is soil nailing?
Nail analogy
Shear stress around nail
generates tensile force in
member
‘Reinforces’ the slope
No pre-stress to be maintained
over life of structure – (passive
structure)
12 March 2015
ENB 485
5
Reinforcing the soil
Soil Nail – Main Components
HDPE Sheath
(for corrosion
protection)
External
centraliser
Internal
centraliser
Outer grout
tube
Inner grout
tube
Soil nail head
plate
(galvanised
for corrosion
protection)
Domed soil nail nut
(galvanised for
corrosion protection)
32mm diameter deformed soil
nail bar (galvanised for corrosion
protection)
12 March 2015
ENB 485
7
Nail Components
Nail Components
Applications
construction of new slopes and retaining walls;
construction of temporary works;
upgrading existing slopes with inadequate stability; and
the renovation of old retaining structures.
12 March 2015
ENB 485
10
Soil Nailing – Is
it suitable?
12 March 2015
ENB 485
11
Advantages Disadvantages
• construction flexibility
• cost
• environmental/aesthetic
considerations
• temporary conditions (cut must
stand vertically)
• groundwater
• clay soils
• land issues
• corrosion
• ground movement
What is soil nailing?
18
Airport Link Project –
Kedron Park Hotel
Tunnels
Key
• Approx. A$5bn
• 15km of tunnelling including
5.7km of twin tunnels
• Connects CLEM 7 Tunnel to
Brisbane Airport
• Sections of new busway &
stations
• Upgrade of major airport
intersection (airport roundabout)
12 March 2015
ENB 485
14
Case Study - Kedron Park Hotel Tunnels
Contractors Requirements
Church and
Hall
Moreton Bay
Fig
Kedron Park
Hotel
Housing
Open Car
Park
Tunnel
through wall
Tunnel under
wall
• Cut-and-cover tunnel
• Cut required to in excess of
30m depth with final
structure built within the box
• Church hall within 5m of
wall, Church and Hotel
within 15m
• Access for construction
plant at the crest (large
mobile crane loads etc)
• Tunnels (roadheader, drill
and blast) required
underneath the excavation
and through one of the walls12 March 2015
ENB 485
15
Kedron Park Hotel Tunnels
Contractors Preferences - Alternatives / Concepts
Initial Design – Stacked tunnel, internal
propping constructed top down. Secant
piles.
Issues with constructability and cost
Enquiry from TJH regarding suitability of
soil nails
Preparation of design for 30m+ high soil
nail wall (24m) / rock cut (6m)
Revised to 18m soil nail wall and 10m
contiguous piles due to mined tunnel
concerns
12 March 2015
ENB 485
16
Kedron Park Hotel Tunnels
Contractors Preferences – Adopted
12 March 2015
ENB 485
17
Kedron Park Hotel Tunnels
Design – Key Issues
Tunnelling through walls - constructability
Settlement of existing structures
Timescales
Suitability to gain approval through TJH design review process (PBA,
IV, CNI)
Appropriate modelling techniques
Construction plant as crest of wall
Tower crane
Existing services
Protected Trees
12 March 2015
ENB 485
18
Kedron Park Hotel Tunnels
Design - Layout
Extent of soil
nailed wall
12 March 2015
ENB 485
19
East
West
RS – ST CLAY
RS – H CLAY
VL-L STRENGTH
SANDSTONE
MS SANDSTONE
5mRL
22mRL Mobile crane
Kedron Park Hotel Tunnels
Design – Ground Model - South Wall
12 March 2015
ENB 485
20
Mobile Crane
Loading – 152kPa
Kedron Park Hotel Tunnels
Design – Wall Geometry - South Wall
12 March 2015
ENB 485
21
Kedron Park Hotel Tunnels
Design – Preliminary Sizing Recommendations
MODEL 1
• No soil nails
• Planar failure
Ref.: Zhang et al, 2001
MODEL 6
 Short soil nails
 L/H = 0.32
 Block failure
MODEL 8
 Long, widely spaced soil nails
 L/H = 1
 Planar failure
Kedron Park Hotel Tunnels
Design – Preliminary Sizing Recommendations
Ref.: Vucetic et al, 1996
TESTS 5-7
 L/H = 0.67 & 1.0
 Widely spaced at 0 deg inclination
 Planar failure
TESTS 1-4
• L/H = 0.67 (incl. 0-30 deg)
• Closely spaced
• Two-part wedge: no difference in
failure with nail inclination 0-30 deg.
Nail Spacing
Closer spaced nails provide greater internal stability
Wide spacing of nails can effect internal stability
Soil nail spacing should not exceed 1 nail per 6m2 of hard facing or 1
nail per 2m2 to 4m2 of flexible facing otherwise the soil nailed structure
will not act as a reinforced mass (CIRIA C637)
Max. spacing – typically 1 - 2m
Kedron Park Hotel Tunnels
Design – Preliminary Sizing Recommendations
12 March 2015
ENB 485
24
Nail Length
Long nails at top and shorter at bottom provides less stability
Shorter nails at top, longer at bottom provides “excellent” stability but
Shorter nails at the top will increase deformations (Shui & Chang,
2005)
As L/H increases, deformations decrease
Short nail lengths can effect external stability
Length of Nails - 0.8 - 1.2H (Clouterre)
Soil nail lengths above 15m should be avoided due to drilling
difficulties and greater deformation required to mobilise tensile
capacity.
Kedron Park Hotel Tunnels
Design – Preliminary Sizing Recommendations
12 March 2015
ENB 485
25
Nail Inclination
Nail inclination between 0 and 20 deg does not appear to affect
stability
>20 deg then rapid increase in wall deformation
Facing
Flexible facing provides similar overall stability to rigid facing, but more
localised deformation
Facing type (based on case studies) - face angle ≥70°= hard
face angle ≤70°= flexible
Kedron Park Hotel Tunnels
Design – Preliminary Sizing Recommendations
12 March 2015
ENB 485
26
vertical nail spacing, Sv = 1.2m
horizontal nail spacing, Sh = 1.5m
soil nail length, L / wall height, H = 15m/18m = 0.8
Kedron Park Hotel Tunnels
Design – Adopted Sizing
12 March 2015
ENB 485
27
Kedron Park Hotel Tunnels
Design – Adopted Sizing
12 March 2015
ENB 485
28
AS4678-2002 - Earth Retaining Structures
BS8006:1995 - Strengthened/ reinforced soils and other fills
BS8006:2011-2 - Strengthened/ reinforced soils and other fills
FHWA Geotechnical Engineering Circular No. 7 – Soil nail walls
(2003)
CIRIA C637 Soil nailing – best practice guidance (2005)
Kedron Park Hotel Tunnels
Design – Codes & Standards
12 March 2015
ENB 485
29
CIRIA Partial Factors
Kedron Park
Hotel Tunnels
Design –
Codes & Standards
12 March 2015
ENB 485
30
Kedron Park Hotel Tunnels
Design – Basis of Design
Kedron Park Hotel Tunnels
Design – Design Approach
Soil nailed wall
Kedron Park Hotel Tunnels
Design – Design Approach
12 March 2015
ENB 485
33
Modes of Failure
External Stability
Internal Stability
Kedron Park Hotel Tunnels
Design – Design Approach
Kedron Park Hotel Tunnels
Design – Analysis
1.333
Surcharge (Unit Weight): 32 kN/m³
Name: Stiff Clay Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 25 °
Name: Hard Clay Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 28 °
Name: VLS - LS Siltstone Unit Weight: 22 kN/m³ Cohesion: 22.5 kPa Phi: 30 °
Name: MS Siltstone Unit Weight: 22 kN/m³ Cohesion: 200 kPa Phi: 40 °
Stiff Clay
Hard Clay
VLS - LS Siltstone
MS Siltstone
South Wall
Eastern Side
Distance
0 5 10 15 20 25 30 35 40 45 50 55 60 65
-5
0
5
10
15
20
25
30
35
0 5 10 15 20 25 30 35 40 45 50 55 60 65
Elevation(mRL)
-5
0
5
10
15
20
25
30
35
12 March 2015
ENB 485
35
SNAIL
12 March 2015
ENB 485
36
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
37
Design pull-out capacity (AS4678)
T* = n .b ..D.Lf .u
Where: .
n = Structure classification design factor (Table 5.2)
= 0.9-1.1;
b = Bond reduction factor (Table B2) = 0.7;
D = Diameter of grout hole (m);
Lf = Fixed length (m);
u = Ultimate grout/ground resistance (bond stress)
(kN/m2).
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
38
Design pull-out capacity (CIRIA C637)
T* = (1/gp)..D.Lf .u
Where: .
D = Diameter of grout hole (m);
Lf = Fixed length (m);
gp = Partial factor (1.25, temp; 1.5, perm; 2, perm,
highly plastic clays);
u = ultimate grout/ground resistance (bond stress)
(kN/m2).
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
39
Bond Stress
Pull out tests
Empirical values
Effective stress design methods
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
40
Design bond stress (effective stress design method)
u = (c* + σ‘v tanf*) (kN/m2)
where:
σ‘v = effective vertical stress at the mid-depth of nail behind
the failure surface;
f* = design angle of internal friction of soil (deg.);
c* = design value of cohesion of soil (kN/m2).
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
41
Empirical values
Material Ultimate Bond Stress (kPa) Material Ultimate Bond Stress (kPa)
Residual soil 50 – 75 Class V Sandstone 150
Class V Shale 75 – 100 Class IV Sandstone 250 – 800
Class IV Shale 150
Typical values of ultimate bond stress for various materials in the
Sydney region are given below:
See also:
FHWA Geotechnical Engineering Circular No. 7 – Soil nail walls (2003)
CIRIA C637 Soil nailing – best practice guidance (2005)
Values should be confirmed by pull-out testing.
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
42
Design pull-out capacity
Pull-out resistance is usually assumed to be uniform along
the length of the nail.
This is reasonable if nails are short and stiff (dia. of bar
>20mm, bond length <5m)
For more elastic nails (eg. fibre-composite nails) the ave.
bond stress reduces when bond length >3m
CIRIA Report C637
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
43
0
50
100
150
200
250
300
0 5 10 15 20 25 30
AverageBondStress(kPa)
Fixed Length (m)
GRP 22mm bar
GRP Strands
Steel 50mm bar
Steel 20mm bar
Kedron Park Hotel Tunnels
Design – Analysis
Effect of Fixed Length on Bond Stress
(Barley and Graham, 1997)
12 March 2015
ENB 485
44
Kedron Park Hotel Tunnels
Design – Analysis
Nail tensile capacity:
Bar strength (tension capacity) can be determined from equation B4(1) in
AS4678-2002
T = k n t fp Ap (kN)
where:
k = Importance category reduction factor (Table B1) =
0.8 (perm.) - 0.9 (temp);
n = structure classification design factor (Table 5.2, AS4678)
= 0.9 - 1.1
t = Material reduction factor (Table B2) = 0.9;
fp = Tensile strength of nail (kN/m2);
Ap = Cross sectional area of nail (m2).
12 March 2015
ENB 485
45
Deformation
Typical Movements of Soil Nailed Structures (Clouterre, 1991)
(after Murray, 1993)
Vertical or
horizontal
deformation
Coarse sand /
gravel
Sand Clay
dv = dh H/1000 2H/1000 4H/1000
do 4H/1000 to 5H/1000
F 0.8 1.25 1.5
l is the distance from the facing to the point where
deformations become negligible and is given by:
l = F H (1 – tan b)
Where
b = initial angle of the
face relative to the
vertical
H = perpendicular height
of structure
F = constant
Kedron Park Hotel Tunnels
Design – Analysis
US/UK now consider
3H/1000 for clays
(not high/v. high
plasticity)
12 March 2015
ENB 485
46
12 March 2015
ENB 485
47
Parameter Unit Effect on Deformation
Wall Geometry
Nail length/Wall height - L/H ratio has greater effect when
L/H<0.97 for ≥ f’=38° and
L/H<0.83 for ≤ f’=38°
Nail inclination ° Deformation increases when inclination
>15°
Nail density m2/nail Deformation increases linearly with
increased nail spacing
Wall face angle ° Steeper wall face angle results in a
significant increase in wall deformation
Soil Properties
Soil modulus MPa Increasing deformation with decreasing
E, with greater increase in d when
E<20MPa
Cohesion kPa Has a significant impact on deformation,
especially when c’ ≤ 4kPa
Angle of internal friction ° Has a less impact than cohesion, but has
a greater effect when the other properties
start to take effect
Factor of safety for different soil nail
inclinations (90° wall face angle)
Factor of safety for different L/H ratios
(90° wall face angle)
12 March 2015
ENB 485
48
0.000
0.010
0.020
0.030
0.040
0.050
0.060
0.070
0.80
1.20
1.60
2.00
2.40
-5 0 5 10 15 20 25 30
Deformation(m)
F.O.S
Nail Inclination (deg)
FOS Vertical Deformation
Horizontal Deformation
f'=36°, c’=6kPa
0.000
0.005
0.010
0.015
0.020
0.025
0.8
1.2
1.6
2
2.4
2.8
3.2
3.6
4
4.4
4.8
5.2
0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3
Deformation(m)
F.O.S
L/H Ratio
FOS Vertical Deformation
Horizontal Deformation
f'=36°, c’=6kPa
Effect of soil nail inclination on
settlement profile behind wall face
Effect of soil nail inclination on
nail force
(Nail 1 is top row of nails)
12 March 2015
ENB 485
49
-0.090
-0.080
-0.070
-0.060
-0.050
-0.040
-0.030
-0.020
-0.010
0.000
20 25 30 35 40
Settlement(m)
Distance from Wall Face (m)
10 deg
20 deg
25 deg
30 deg
Wall face
End of 5m
long nail
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
-10 -5 0 5 10 15 20 25 30 35 40
FactorofSafety
NailForce(kN)
Soil Nail Inclination below Horizontal (degrees)
Nail 1
Nail 2
Nail 3
Nail 4
Nail 5
Nail 6
FOS
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
50
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
51
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
52
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
53
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
54
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
55
FacingFHWA
Geotechnical Circular
No. 7
Kedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
56
FacingKedron Park Hotel Tunnels
Design – Analysis
12 March 2015
ENB 485
57
Kedron Park Hotel Tunnels
Design - Instrumentation
12 March 2015
ENB 485
58
MRTS03 Drainage, Retaining Structures and Protective Treatments
Project Specific
QA Specification R64 Soil nailing
CIRIA C637 Soil nailing – best practice guidance (2005)
Kedron Park Hotel Tunnels
Design – Specifications
12 March 2015
ENB 485
59
Kedron Park Hotel Tunnels
Design – Drawings
12 March 2015
ENB 485
60
Typical DTMR Permanent Nail
Kedron Park Hotel Tunnels
Design – Drawings
MIN. NOW 125mm
MIN TOTAL GROUT
COVER 30mm
12 March 2015
ENB 485
61
Kedron Park Hotel Tunnels
Design – Drawings
East Wall
12 March 2015
ENB 485
62
Kedron Park Hotel Tunnels
Design – Drawings
12 March 2015
ENB 485
63
Tree Roots
Kedron Park Hotel Tunnels
Design – Drawings
North Wall
12 March 2015
ENB 485
64
Mobile crane
Access ramp
Kedron Park Hotel Tunnels
Design – Drawings
South Wall
12 March 2015
ENB 485
65
Kedron Park Hotel Tunnels
Construction
12 March 2015
ENB 485
66
Kedron Park Hotel Tunnels
Construction
12 March 2015
ENB 485
67
Kedron Park Hotel Tunnels
Construction - Role
Full time
Record progress during
construction
Mapping of face to correlate
testing
Observe testing
Record groundwater
Site photography
ITP sign off
Site instructions
12 March 2015
ENB 485
68
Kedron Park Hotel Tunnels
Construction Sequence
12 March 2015
ENB 485
69
Kedron Park
Hotel Tunnels
Construction Sequence
Kedron Park Hotel Tunnels
Construction
12 March 2015
ENB 485
71
Kedron Park Hotel Tunnels
Construction
12 March 2015
ENB 485
72
Kedron Park Hotel Tunnels
Construction
East Wall
GRP Nails
12 March 2015
ENB 485
73
Kedron Park Hotel Tunnels
Construction
Western End
12 March 2015
ENB 485
74
Kedron Park Hotel Tunnels
Construction - Drainage
12 March 2015
ENB 485
75
Kedron Park Hotel Tunnels
Construction
East Wall – installing canopy tubes
GRP Nails
Piles at base of wall
12 March 2015
ENB 485
76
Spacers of inadequate strength
Damage to installed soil nail bars by
excavator
Lack of experience of contractors staff
Kedron Park Hotel Tunnels
Construction - Issues
12 March 2015
ENB 485
77
Kedron Park Hotel Tunnels
Construction - Testing
• Ultimate Load (Pullout) Test
• Acceptance Testing
• Exhumation of test nails
Kedron Park Hotel Tunnels
Construction – Tower Crane
12 March 2015
ENB 485
79
Kedron Park Hotel Tunnels
Construction – Tower Crane
12 March 2015
ENB 485
80
Kedron Park Hotel Tunnels
Construction
Kedron Park Hotel Tunnels
Construction
Kedron Park Hotel Tunnels
Construction - Monitoring
RS
VLS-LS
Siltstone
RS
VLS-LS
Siltstone
RS
VLS-LS
Siltstone
Mid-South Wall Corner North Wall Mid-North Wall
33mm 10mm 22mm
Prediction = 22mm Prediction = 55mm
Base of excavation12 March 2015
ENB 485
83
Kedron Park Hotel Tunnels
Construction - Monitoring
12 March 2015
ENB 485
84
Kedron Park Hotel Tunnels
Completion
• Two year design life, 4 month
construction (nail wall).
• 18m deep excavation with further 10m
deep piled wall below
• Over 1500 soil nails 10 to 15m long
(steel and GRP)
• Backfilled with flowable fill
Soil Nail Walls are not such a great idea in water charged sands and silts
(They also can’t be expected to have a 2 weeks stand up time)
Airport Link – Construction Issues
12 March 2015
ENB 485
86
19
Other Projects
S E Queensland – Construction Issues
1
2 3
4
5
6
7 8
9
10
11
12
13 14
15
1.51
Mudstone
Original Design
Sandstone
Claystone
Name: General Backfill
Model: Mohr-Coulomb
Unit Weight: 19 kN/m³
Cohesion: 5 kPa
Phi: 30 °
Name: Claystone
Model: Mohr-Coulomb
Unit Weight: 21 kN/m³
Cohesion: 10 kPa
Phi: 40 °
Name: Mudstone
Model: Mohr-Coulomb
Unit Weight: 21 kN/m³
Cohesion: 10 kPa
Phi: 42 °
Name: Sandstone
Model: Mohr-Coulomb
Unit Weight: 20 kN/m³
Cohesion: 2 kPa
Phi: 42 °
Sandstone
Directory: K:Q1215 - LMICoffeyDesignWallsRW08
Pressure (Unit Weight): 20 kN/m³
General Backfill
Offset (m)
0 5 10 15 20 25 30 35
Height(m)
0
5
10
15
20
25
12 March 2015
ENB 485
89
S E Queensland
S E Queensland
1
2 3
4
5
6
7 8
9
10
11
12
13 14
15
1.53
Mudstone
Revised Design
Sandstone
Claystone
Name: General Backfill
Model: Mohr-Coulomb
Unit Weight: 19 kN/m³
Cohesion: 5 kPa
Phi: 30 °
Name: Claystone
Model: Mohr-Coulomb
Unit Weight: 21 kN/m³
Cohesion: 10 kPa
Phi: 40 °
Name: Mudstone
Model: Mohr-Coulomb
Unit Weight: 21 kN/m³
Cohesion: 10 kPa
Phi: 42 °
Name: Uncemented Sandstone
Model: Mohr-Coulomb
Unit Weight: 20 kN/m³
Cohesion: 0 kPa
Phi: 35 °
Name: Sandstone
Model: Mohr-Coulomb
Unit Weight: 20 kN/m³
Cohesion: 2 kPa
Phi: 42 °
Uncemented Sandstone
Directory: K:Q1215 - LMICoffeyDesignWallsRW08
Pressure (Unit Weight): 20 kN/m³
General Backfill
Offset (m)
0 5 10 15 20 25 30 35
Height(m)
0
5
10
15
20
25
Re-analysed wall with revised ground
model and design amended to
incorporate same length nails for full
height of wall over affected section
12 March 2015
ENB 485
92
Remediation
But, after wall completed:
Wall still showed signs of movement
Extra nails 10m in length were recommended along 20m of the
unstable section
12 March 2015
ENB 485
93
1
2 3
4
5
6
7 8
9
10
11
12
13 14
15
1.59
Mudstone
Remediation Nail Design
Sandstone
Claystone
Name: General Backfill
Model: Mohr-Coulomb
Unit Weight: 19 kN/m³
Cohesion: 5 kPa
Phi: 30 °
Name: Claystone
Model: Mohr-Coulomb
Unit Weight: 21 kN/m³
Cohesion: 10 kPa
Phi: 40 °
Name: Mudstone
Model: Mohr-Coulomb
Unit Weight: 21 kN/m³
Cohesion: 10 kPa
Phi: 42 °
Name: Uncemented Sandstone
Model: Mohr-Coulomb
Unit Weight: 20 kN/m³
Cohesion: 0 kPa
Phi: 35 °
Name: Sandstone
Model: Mohr-Coulomb
Unit Weight: 20 kN/m³
Cohesion: 2 kPa
Phi: 42 °
Uncemented Sandstone
Directory: K:Q1215 - LMICoffeyDesignWallsRW08
Pressure (Unit Weight): 20 kN/m³
General Backfill
Offset (m)
0 5 10 15 20 25 30 35
Height(m)
0
5
10
15
20
25
12 March 2015
ENB 485
94
S E Queensland
Over-excavation
12 March 2015
ENB 485
96
S E Queensland
Over-enthusiasm
Road over Rail Bridge
Existing Bridge
Existing RE Wall Drawings
12 March 2015
ENB 485
105
12 March 2015
ENB 485
106
Failures
Soil nail failures are fairly uncommon but the following are typical:
• hole collapse during installation of the soil nail, often due to loose fill
materials related to poorly backfilled utility trenches, for example;
• over excavation resulting in large unsupported lengths or heights of cut
slope;
• seepage;
• erosion/washout of slope surface;
• inappropriate soil - running sands;
• problems during drilling due to drill bits getting stuck or getting off line;
• grout loss during installation;
• poor construction of soil nail heads with voids beneath the soil nail head.
12 March 2015
ENB 485
107
Soil Nail Failures
Ref.: Tan. & Chow, 2004
Soil nail facing failure
Grout cover cracked and
peeled off from nail
Void within
cement grout
~250mm
Probed depth = 320 mm
into cement grout
Probed depth = 1590 mm
into cement grout
Cross-section
Soil Nail Failures
12 March 2015
ENB 485
109
Nail with
no grout
Plastic sheet
Short
column of
cement
grout
12 March 2015
ENB 485
110
Soil Nail Failures
Ref.: Sun & Tsui, 2005
Slope failure prior to soil nail
heads being installed during
heavy rain
Cause of failure:
• Ingress of water
Assisted by -
• Upper row of nails too low
below crest
• Wide nail spacing
• Lack of surface protection
• Poor construction of nails
Soil Nail Failures
6m3 failure in Completely Decomposed Tuff
References
• FHWA (1994). “Soil nailing field inspectors manual.” FHWA-SA-93-068, US
Department of Transportation, Washington.
• FHWA (1998). “Manual for design & construction monitoring of soil nail
walls.” FHWA-SA-96-069R, US Department of Transportation, Washington.
• FHWA (2003). “Soil nail walls.” Geotechnical Engineering Circular No.7,
FHWA0-IF-03-017, US Department of Transportation, Washington.
• Clouterre (1991) “French National Research Project Clouterre –
Recommendations Clouterre 1991”. (English Translation), Federal Highway
Administration, FHWA-SA-93-026, US Department of Transportation,
Washington.
• BSI (1989). “Code of practice for ground anchorages”, BS 8081:1989,
British Standards Institution, London.
• Highways Agency (1994). Design manual for roads and bridges- Advice
Note HA68/94, Design methods for the reinforcement of highway slopes by
reinforced soil and soil nailing techniques. The Stationary Office, London.
• Hong Kong Government Webpage:
http://www.cedd.gov.hk/eng/publications/index.htm
(Geoguide 7, Technical Guidance Notes, GEO Reports)

More Related Content

What's hot

OFFSHORE GEOTECHNICAL INTRODUCTION
OFFSHORE GEOTECHNICAL INTRODUCTIONOFFSHORE GEOTECHNICAL INTRODUCTION
OFFSHORE GEOTECHNICAL INTRODUCTIONNardipta Pratama
 
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)Hamed Zarei
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration TestMuftah Aljoat
 
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]Muhammad Irfan
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSKHUSHBU SHAH
 
Lecture 7 stress distribution in soil
Lecture 7 stress distribution in soilLecture 7 stress distribution in soil
Lecture 7 stress distribution in soilDr.Abdulmannan Orabi
 
Geotechnical Engineering-I [Lec #1: Introduction]
Geotechnical Engineering-I [Lec #1: Introduction]Geotechnical Engineering-I [Lec #1: Introduction]
Geotechnical Engineering-I [Lec #1: Introduction]Muhammad Irfan
 
Geotechnical Engineering-I [Lec #11: USCS & AASHTO]
Geotechnical Engineering-I [Lec #11: USCS & AASHTO]Geotechnical Engineering-I [Lec #11: USCS & AASHTO]
Geotechnical Engineering-I [Lec #11: USCS & AASHTO]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]Muhammad Irfan
 
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]Muhammad Irfan
 
Static pile capacity formula (usefulsearch.org) (useful search)
Static pile capacity formula (usefulsearch.org)  (useful search)Static pile capacity formula (usefulsearch.org)  (useful search)
Static pile capacity formula (usefulsearch.org) (useful search)Make Mannan
 
METHOD OF SOIL STABILIZARION
METHOD OF SOIL STABILIZARIONMETHOD OF SOIL STABILIZARION
METHOD OF SOIL STABILIZARIONRajnesh Sethiya
 

What's hot (20)

OFFSHORE GEOTECHNICAL INTRODUCTION
OFFSHORE GEOTECHNICAL INTRODUCTIONOFFSHORE GEOTECHNICAL INTRODUCTION
OFFSHORE GEOTECHNICAL INTRODUCTION
 
Geotechnical Engineering
Geotechnical EngineeringGeotechnical Engineering
Geotechnical Engineering
 
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration Test
 
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
Geotechnical Engineering-II [Lec #2: Mohr-Coulomb Failure Criteria]
 
Geotechnical Engineering - Dams
Geotechnical Engineering - DamsGeotechnical Engineering - Dams
Geotechnical Engineering - Dams
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
COMPRESSION MEMBERS
COMPRESSION MEMBERS COMPRESSION MEMBERS
COMPRESSION MEMBERS
 
Lecture 7 stress distribution in soil
Lecture 7 stress distribution in soilLecture 7 stress distribution in soil
Lecture 7 stress distribution in soil
 
Geotechnical Engineering-I [Lec #1: Introduction]
Geotechnical Engineering-I [Lec #1: Introduction]Geotechnical Engineering-I [Lec #1: Introduction]
Geotechnical Engineering-I [Lec #1: Introduction]
 
Geotechnical Engineering-I [Lec #11: USCS & AASHTO]
Geotechnical Engineering-I [Lec #11: USCS & AASHTO]Geotechnical Engineering-I [Lec #11: USCS & AASHTO]
Geotechnical Engineering-I [Lec #11: USCS & AASHTO]
 
Types of slope failures
Types of slope failuresTypes of slope failures
Types of slope failures
 
New Soil Investigation
New Soil InvestigationNew Soil Investigation
New Soil Investigation
 
Geotechnical investigation
Geotechnical investigationGeotechnical investigation
Geotechnical investigation
 
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
Geotechnical Engineering-II [Lec #24: Coulomb EP Theory]
 
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
Geotechnical Engineering-II [Lec #14: Timoshenko & Goodier Method]
 
Static pile capacity formula (usefulsearch.org) (useful search)
Static pile capacity formula (usefulsearch.org)  (useful search)Static pile capacity formula (usefulsearch.org)  (useful search)
Static pile capacity formula (usefulsearch.org) (useful search)
 
Lec5
Lec5Lec5
Lec5
 
METHOD OF SOIL STABILIZARION
METHOD OF SOIL STABILIZARIONMETHOD OF SOIL STABILIZARION
METHOD OF SOIL STABILIZARION
 
Slope stability
Slope stabilitySlope stability
Slope stability
 

Similar to Design of earth-retaining structures - Lecture 6

Armtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsArmtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsCommunications Branding
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wallHarsh Bothra
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design PresentationKeith Kong
 
Steel Compliance from the Consulting Engineer's Perspective
Steel Compliance from the Consulting Engineer's PerspectiveSteel Compliance from the Consulting Engineer's Perspective
Steel Compliance from the Consulting Engineer's PerspectiveMark Sheldon
 
An analytical and experimental study of concrete encased column
An analytical and experimental study of concrete encased columnAn analytical and experimental study of concrete encased column
An analytical and experimental study of concrete encased columnIRJET Journal
 
IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...
IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...
IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...IRJET Journal
 
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET Journal
 
Comparative study on behaviour of RCC and steel – concrete composite multisto...
Comparative study on behaviour of RCC and steel – concrete composite multisto...Comparative study on behaviour of RCC and steel – concrete composite multisto...
Comparative study on behaviour of RCC and steel – concrete composite multisto...IRJET Journal
 
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...IRJET Journal
 
PRESENTATION ON THE INTERNSHIP
 PRESENTATION ON THE INTERNSHIP PRESENTATION ON THE INTERNSHIP
PRESENTATION ON THE INTERNSHIPSufiyanAhmedJeddy
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedureBhavik A Shah
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignDr Mazin Alhamrany
 
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck SlabIRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck SlabIRJET Journal
 
IRJET- Experimental Study on Strength Properties of Laterite Concrete
IRJET- Experimental Study on Strength Properties of Laterite ConcreteIRJET- Experimental Study on Strength Properties of Laterite Concrete
IRJET- Experimental Study on Strength Properties of Laterite ConcreteIRJET Journal
 
IRJET- Sleeper Design using Fibre Reinforcement
IRJET- Sleeper Design using Fibre ReinforcementIRJET- Sleeper Design using Fibre Reinforcement
IRJET- Sleeper Design using Fibre ReinforcementIRJET Journal
 

Similar to Design of earth-retaining structures - Lecture 6 (20)

Final Document
Final DocumentFinal Document
Final Document
 
Armtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsArmtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End Treatments
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
Steel Compliance from the Consulting Engineer's Perspective
Steel Compliance from the Consulting Engineer's PerspectiveSteel Compliance from the Consulting Engineer's Perspective
Steel Compliance from the Consulting Engineer's Perspective
 
An analytical and experimental study of concrete encased column
An analytical and experimental study of concrete encased columnAn analytical and experimental study of concrete encased column
An analytical and experimental study of concrete encased column
 
IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...
IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...
IRJET- Ultimate Load Bearing Capacity and Settlement of Triangular Screw Pile...
 
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
 
Comparative study on behaviour of RCC and steel – concrete composite multisto...
Comparative study on behaviour of RCC and steel – concrete composite multisto...Comparative study on behaviour of RCC and steel – concrete composite multisto...
Comparative study on behaviour of RCC and steel – concrete composite multisto...
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
 
PRESENTATION ON THE INTERNSHIP
 PRESENTATION ON THE INTERNSHIP PRESENTATION ON THE INTERNSHIP
PRESENTATION ON THE INTERNSHIP
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedure
 
Niand work profile
Niand work profileNiand work profile
Niand work profile
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
Company profile
Company profileCompany profile
Company profile
 
SOIL NAILING
SOIL NAILINGSOIL NAILING
SOIL NAILING
 
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck SlabIRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
 
IRJET- Experimental Study on Strength Properties of Laterite Concrete
IRJET- Experimental Study on Strength Properties of Laterite ConcreteIRJET- Experimental Study on Strength Properties of Laterite Concrete
IRJET- Experimental Study on Strength Properties of Laterite Concrete
 
IRJET- Sleeper Design using Fibre Reinforcement
IRJET- Sleeper Design using Fibre ReinforcementIRJET- Sleeper Design using Fibre Reinforcement
IRJET- Sleeper Design using Fibre Reinforcement
 

More from Chris Bridges

Long-term geotechnical impacts of climate change on project
 Long-term geotechnical impacts of climate change on project Long-term geotechnical impacts of climate change on project
Long-term geotechnical impacts of climate change on projectChris Bridges
 
Geotechnical risk on large scale infrastructure projects
Geotechnical risk on large scale infrastructure projectsGeotechnical risk on large scale infrastructure projects
Geotechnical risk on large scale infrastructure projectsChris Bridges
 
The identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionThe identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionChris Bridges
 
The management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projectsThe management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projectsChris Bridges
 
The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsChris Bridges
 
Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8Chris Bridges
 
Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Chris Bridges
 
The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4Chris Bridges
 
The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3Chris Bridges
 
The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2Chris Bridges
 
The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1Chris Bridges
 

More from Chris Bridges (11)

Long-term geotechnical impacts of climate change on project
 Long-term geotechnical impacts of climate change on project Long-term geotechnical impacts of climate change on project
Long-term geotechnical impacts of climate change on project
 
Geotechnical risk on large scale infrastructure projects
Geotechnical risk on large scale infrastructure projectsGeotechnical risk on large scale infrastructure projects
Geotechnical risk on large scale infrastructure projects
 
The identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionThe identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway construction
 
The management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projectsThe management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projects
 
The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankments
 
Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8
 
Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5
 
The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4
 
The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3
 
The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2
 
The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 

Design of earth-retaining structures - Lecture 6

  • 1. The Design of Earth-retaining Structures ENB485 Chris Bridges The Design of Earth-retaining Structures ENB485 Chris Bridges The Design of Earth-retaining Structures ENB485 Chris Bridges May 2016 Lecture 6 Design of Earth-retaining Structures Soil Nailing
  • 3. What is soil nailing? Anchors Soil Nails Soil Dowels 12 March 2015 ENB 485 3
  • 4. What is soil nailing? Anchor analogy – threaded bolt Generates tensile force in member Normal force creates shear stresses along failure plane Requires pre-stress to be maintained over life of structure – (active structure) 12 March 2015 ENB 485 4
  • 5. What is soil nailing? Nail analogy Shear stress around nail generates tensile force in member ‘Reinforces’ the slope No pre-stress to be maintained over life of structure – (passive structure) 12 March 2015 ENB 485 5
  • 7. Soil Nail – Main Components HDPE Sheath (for corrosion protection) External centraliser Internal centraliser Outer grout tube Inner grout tube Soil nail head plate (galvanised for corrosion protection) Domed soil nail nut (galvanised for corrosion protection) 32mm diameter deformed soil nail bar (galvanised for corrosion protection) 12 March 2015 ENB 485 7
  • 10. Applications construction of new slopes and retaining walls; construction of temporary works; upgrading existing slopes with inadequate stability; and the renovation of old retaining structures. 12 March 2015 ENB 485 10
  • 11. Soil Nailing – Is it suitable? 12 March 2015 ENB 485 11
  • 12. Advantages Disadvantages • construction flexibility • cost • environmental/aesthetic considerations • temporary conditions (cut must stand vertically) • groundwater • clay soils • land issues • corrosion • ground movement What is soil nailing?
  • 13. 18 Airport Link Project – Kedron Park Hotel Tunnels
  • 14. Key • Approx. A$5bn • 15km of tunnelling including 5.7km of twin tunnels • Connects CLEM 7 Tunnel to Brisbane Airport • Sections of new busway & stations • Upgrade of major airport intersection (airport roundabout) 12 March 2015 ENB 485 14
  • 15. Case Study - Kedron Park Hotel Tunnels Contractors Requirements Church and Hall Moreton Bay Fig Kedron Park Hotel Housing Open Car Park Tunnel through wall Tunnel under wall • Cut-and-cover tunnel • Cut required to in excess of 30m depth with final structure built within the box • Church hall within 5m of wall, Church and Hotel within 15m • Access for construction plant at the crest (large mobile crane loads etc) • Tunnels (roadheader, drill and blast) required underneath the excavation and through one of the walls12 March 2015 ENB 485 15
  • 16. Kedron Park Hotel Tunnels Contractors Preferences - Alternatives / Concepts Initial Design – Stacked tunnel, internal propping constructed top down. Secant piles. Issues with constructability and cost Enquiry from TJH regarding suitability of soil nails Preparation of design for 30m+ high soil nail wall (24m) / rock cut (6m) Revised to 18m soil nail wall and 10m contiguous piles due to mined tunnel concerns 12 March 2015 ENB 485 16
  • 17. Kedron Park Hotel Tunnels Contractors Preferences – Adopted 12 March 2015 ENB 485 17
  • 18. Kedron Park Hotel Tunnels Design – Key Issues Tunnelling through walls - constructability Settlement of existing structures Timescales Suitability to gain approval through TJH design review process (PBA, IV, CNI) Appropriate modelling techniques Construction plant as crest of wall Tower crane Existing services Protected Trees 12 March 2015 ENB 485 18
  • 19. Kedron Park Hotel Tunnels Design - Layout Extent of soil nailed wall 12 March 2015 ENB 485 19
  • 20. East West RS – ST CLAY RS – H CLAY VL-L STRENGTH SANDSTONE MS SANDSTONE 5mRL 22mRL Mobile crane Kedron Park Hotel Tunnels Design – Ground Model - South Wall 12 March 2015 ENB 485 20
  • 21. Mobile Crane Loading – 152kPa Kedron Park Hotel Tunnels Design – Wall Geometry - South Wall 12 March 2015 ENB 485 21
  • 22. Kedron Park Hotel Tunnels Design – Preliminary Sizing Recommendations MODEL 1 • No soil nails • Planar failure Ref.: Zhang et al, 2001 MODEL 6  Short soil nails  L/H = 0.32  Block failure MODEL 8  Long, widely spaced soil nails  L/H = 1  Planar failure
  • 23. Kedron Park Hotel Tunnels Design – Preliminary Sizing Recommendations Ref.: Vucetic et al, 1996 TESTS 5-7  L/H = 0.67 & 1.0  Widely spaced at 0 deg inclination  Planar failure TESTS 1-4 • L/H = 0.67 (incl. 0-30 deg) • Closely spaced • Two-part wedge: no difference in failure with nail inclination 0-30 deg.
  • 24. Nail Spacing Closer spaced nails provide greater internal stability Wide spacing of nails can effect internal stability Soil nail spacing should not exceed 1 nail per 6m2 of hard facing or 1 nail per 2m2 to 4m2 of flexible facing otherwise the soil nailed structure will not act as a reinforced mass (CIRIA C637) Max. spacing – typically 1 - 2m Kedron Park Hotel Tunnels Design – Preliminary Sizing Recommendations 12 March 2015 ENB 485 24
  • 25. Nail Length Long nails at top and shorter at bottom provides less stability Shorter nails at top, longer at bottom provides “excellent” stability but Shorter nails at the top will increase deformations (Shui & Chang, 2005) As L/H increases, deformations decrease Short nail lengths can effect external stability Length of Nails - 0.8 - 1.2H (Clouterre) Soil nail lengths above 15m should be avoided due to drilling difficulties and greater deformation required to mobilise tensile capacity. Kedron Park Hotel Tunnels Design – Preliminary Sizing Recommendations 12 March 2015 ENB 485 25
  • 26. Nail Inclination Nail inclination between 0 and 20 deg does not appear to affect stability >20 deg then rapid increase in wall deformation Facing Flexible facing provides similar overall stability to rigid facing, but more localised deformation Facing type (based on case studies) - face angle ≥70°= hard face angle ≤70°= flexible Kedron Park Hotel Tunnels Design – Preliminary Sizing Recommendations 12 March 2015 ENB 485 26
  • 27. vertical nail spacing, Sv = 1.2m horizontal nail spacing, Sh = 1.5m soil nail length, L / wall height, H = 15m/18m = 0.8 Kedron Park Hotel Tunnels Design – Adopted Sizing 12 March 2015 ENB 485 27
  • 28. Kedron Park Hotel Tunnels Design – Adopted Sizing 12 March 2015 ENB 485 28
  • 29. AS4678-2002 - Earth Retaining Structures BS8006:1995 - Strengthened/ reinforced soils and other fills BS8006:2011-2 - Strengthened/ reinforced soils and other fills FHWA Geotechnical Engineering Circular No. 7 – Soil nail walls (2003) CIRIA C637 Soil nailing – best practice guidance (2005) Kedron Park Hotel Tunnels Design – Codes & Standards 12 March 2015 ENB 485 29
  • 30. CIRIA Partial Factors Kedron Park Hotel Tunnels Design – Codes & Standards 12 March 2015 ENB 485 30
  • 31. Kedron Park Hotel Tunnels Design – Basis of Design
  • 32. Kedron Park Hotel Tunnels Design – Design Approach
  • 33. Soil nailed wall Kedron Park Hotel Tunnels Design – Design Approach 12 March 2015 ENB 485 33
  • 34. Modes of Failure External Stability Internal Stability Kedron Park Hotel Tunnels Design – Design Approach
  • 35. Kedron Park Hotel Tunnels Design – Analysis 1.333 Surcharge (Unit Weight): 32 kN/m³ Name: Stiff Clay Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 25 ° Name: Hard Clay Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 28 ° Name: VLS - LS Siltstone Unit Weight: 22 kN/m³ Cohesion: 22.5 kPa Phi: 30 ° Name: MS Siltstone Unit Weight: 22 kN/m³ Cohesion: 200 kPa Phi: 40 ° Stiff Clay Hard Clay VLS - LS Siltstone MS Siltstone South Wall Eastern Side Distance 0 5 10 15 20 25 30 35 40 45 50 55 60 65 -5 0 5 10 15 20 25 30 35 0 5 10 15 20 25 30 35 40 45 50 55 60 65 Elevation(mRL) -5 0 5 10 15 20 25 30 35 12 March 2015 ENB 485 35
  • 37. Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 37
  • 38. Design pull-out capacity (AS4678) T* = n .b ..D.Lf .u Where: . n = Structure classification design factor (Table 5.2) = 0.9-1.1; b = Bond reduction factor (Table B2) = 0.7; D = Diameter of grout hole (m); Lf = Fixed length (m); u = Ultimate grout/ground resistance (bond stress) (kN/m2). Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 38
  • 39. Design pull-out capacity (CIRIA C637) T* = (1/gp)..D.Lf .u Where: . D = Diameter of grout hole (m); Lf = Fixed length (m); gp = Partial factor (1.25, temp; 1.5, perm; 2, perm, highly plastic clays); u = ultimate grout/ground resistance (bond stress) (kN/m2). Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 39
  • 40. Bond Stress Pull out tests Empirical values Effective stress design methods Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 40
  • 41. Design bond stress (effective stress design method) u = (c* + σ‘v tanf*) (kN/m2) where: σ‘v = effective vertical stress at the mid-depth of nail behind the failure surface; f* = design angle of internal friction of soil (deg.); c* = design value of cohesion of soil (kN/m2). Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 41
  • 42. Empirical values Material Ultimate Bond Stress (kPa) Material Ultimate Bond Stress (kPa) Residual soil 50 – 75 Class V Sandstone 150 Class V Shale 75 – 100 Class IV Sandstone 250 – 800 Class IV Shale 150 Typical values of ultimate bond stress for various materials in the Sydney region are given below: See also: FHWA Geotechnical Engineering Circular No. 7 – Soil nail walls (2003) CIRIA C637 Soil nailing – best practice guidance (2005) Values should be confirmed by pull-out testing. Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 42
  • 43. Design pull-out capacity Pull-out resistance is usually assumed to be uniform along the length of the nail. This is reasonable if nails are short and stiff (dia. of bar >20mm, bond length <5m) For more elastic nails (eg. fibre-composite nails) the ave. bond stress reduces when bond length >3m CIRIA Report C637 Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 43
  • 44. 0 50 100 150 200 250 300 0 5 10 15 20 25 30 AverageBondStress(kPa) Fixed Length (m) GRP 22mm bar GRP Strands Steel 50mm bar Steel 20mm bar Kedron Park Hotel Tunnels Design – Analysis Effect of Fixed Length on Bond Stress (Barley and Graham, 1997) 12 March 2015 ENB 485 44
  • 45. Kedron Park Hotel Tunnels Design – Analysis Nail tensile capacity: Bar strength (tension capacity) can be determined from equation B4(1) in AS4678-2002 T = k n t fp Ap (kN) where: k = Importance category reduction factor (Table B1) = 0.8 (perm.) - 0.9 (temp); n = structure classification design factor (Table 5.2, AS4678) = 0.9 - 1.1 t = Material reduction factor (Table B2) = 0.9; fp = Tensile strength of nail (kN/m2); Ap = Cross sectional area of nail (m2). 12 March 2015 ENB 485 45
  • 46. Deformation Typical Movements of Soil Nailed Structures (Clouterre, 1991) (after Murray, 1993) Vertical or horizontal deformation Coarse sand / gravel Sand Clay dv = dh H/1000 2H/1000 4H/1000 do 4H/1000 to 5H/1000 F 0.8 1.25 1.5 l is the distance from the facing to the point where deformations become negligible and is given by: l = F H (1 – tan b) Where b = initial angle of the face relative to the vertical H = perpendicular height of structure F = constant Kedron Park Hotel Tunnels Design – Analysis US/UK now consider 3H/1000 for clays (not high/v. high plasticity) 12 March 2015 ENB 485 46
  • 47. 12 March 2015 ENB 485 47 Parameter Unit Effect on Deformation Wall Geometry Nail length/Wall height - L/H ratio has greater effect when L/H<0.97 for ≥ f’=38° and L/H<0.83 for ≤ f’=38° Nail inclination ° Deformation increases when inclination >15° Nail density m2/nail Deformation increases linearly with increased nail spacing Wall face angle ° Steeper wall face angle results in a significant increase in wall deformation Soil Properties Soil modulus MPa Increasing deformation with decreasing E, with greater increase in d when E<20MPa Cohesion kPa Has a significant impact on deformation, especially when c’ ≤ 4kPa Angle of internal friction ° Has a less impact than cohesion, but has a greater effect when the other properties start to take effect
  • 48. Factor of safety for different soil nail inclinations (90° wall face angle) Factor of safety for different L/H ratios (90° wall face angle) 12 March 2015 ENB 485 48 0.000 0.010 0.020 0.030 0.040 0.050 0.060 0.070 0.80 1.20 1.60 2.00 2.40 -5 0 5 10 15 20 25 30 Deformation(m) F.O.S Nail Inclination (deg) FOS Vertical Deformation Horizontal Deformation f'=36°, c’=6kPa 0.000 0.005 0.010 0.015 0.020 0.025 0.8 1.2 1.6 2 2.4 2.8 3.2 3.6 4 4.4 4.8 5.2 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 Deformation(m) F.O.S L/H Ratio FOS Vertical Deformation Horizontal Deformation f'=36°, c’=6kPa
  • 49. Effect of soil nail inclination on settlement profile behind wall face Effect of soil nail inclination on nail force (Nail 1 is top row of nails) 12 March 2015 ENB 485 49 -0.090 -0.080 -0.070 -0.060 -0.050 -0.040 -0.030 -0.020 -0.010 0.000 20 25 30 35 40 Settlement(m) Distance from Wall Face (m) 10 deg 20 deg 25 deg 30 deg Wall face End of 5m long nail 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 -10 -5 0 5 10 15 20 25 30 35 40 FactorofSafety NailForce(kN) Soil Nail Inclination below Horizontal (degrees) Nail 1 Nail 2 Nail 3 Nail 4 Nail 5 Nail 6 FOS
  • 50. Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 50
  • 51. Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 51
  • 52. Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 52
  • 53. Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 53
  • 54. Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 54
  • 55. Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 55
  • 56. FacingFHWA Geotechnical Circular No. 7 Kedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 56
  • 57. FacingKedron Park Hotel Tunnels Design – Analysis 12 March 2015 ENB 485 57
  • 58. Kedron Park Hotel Tunnels Design - Instrumentation 12 March 2015 ENB 485 58
  • 59. MRTS03 Drainage, Retaining Structures and Protective Treatments Project Specific QA Specification R64 Soil nailing CIRIA C637 Soil nailing – best practice guidance (2005) Kedron Park Hotel Tunnels Design – Specifications 12 March 2015 ENB 485 59
  • 60. Kedron Park Hotel Tunnels Design – Drawings 12 March 2015 ENB 485 60
  • 61. Typical DTMR Permanent Nail Kedron Park Hotel Tunnels Design – Drawings MIN. NOW 125mm MIN TOTAL GROUT COVER 30mm 12 March 2015 ENB 485 61
  • 62. Kedron Park Hotel Tunnels Design – Drawings East Wall 12 March 2015 ENB 485 62
  • 63. Kedron Park Hotel Tunnels Design – Drawings 12 March 2015 ENB 485 63
  • 64. Tree Roots Kedron Park Hotel Tunnels Design – Drawings North Wall 12 March 2015 ENB 485 64
  • 65. Mobile crane Access ramp Kedron Park Hotel Tunnels Design – Drawings South Wall 12 March 2015 ENB 485 65
  • 66. Kedron Park Hotel Tunnels Construction 12 March 2015 ENB 485 66
  • 67. Kedron Park Hotel Tunnels Construction 12 March 2015 ENB 485 67
  • 68. Kedron Park Hotel Tunnels Construction - Role Full time Record progress during construction Mapping of face to correlate testing Observe testing Record groundwater Site photography ITP sign off Site instructions 12 March 2015 ENB 485 68
  • 69. Kedron Park Hotel Tunnels Construction Sequence 12 March 2015 ENB 485 69
  • 71. Kedron Park Hotel Tunnels Construction 12 March 2015 ENB 485 71
  • 72. Kedron Park Hotel Tunnels Construction 12 March 2015 ENB 485 72
  • 73. Kedron Park Hotel Tunnels Construction East Wall GRP Nails 12 March 2015 ENB 485 73
  • 74. Kedron Park Hotel Tunnels Construction Western End 12 March 2015 ENB 485 74
  • 75. Kedron Park Hotel Tunnels Construction - Drainage 12 March 2015 ENB 485 75
  • 76. Kedron Park Hotel Tunnels Construction East Wall – installing canopy tubes GRP Nails Piles at base of wall 12 March 2015 ENB 485 76
  • 77. Spacers of inadequate strength Damage to installed soil nail bars by excavator Lack of experience of contractors staff Kedron Park Hotel Tunnels Construction - Issues 12 March 2015 ENB 485 77
  • 78. Kedron Park Hotel Tunnels Construction - Testing • Ultimate Load (Pullout) Test • Acceptance Testing • Exhumation of test nails
  • 79. Kedron Park Hotel Tunnels Construction – Tower Crane 12 March 2015 ENB 485 79
  • 80. Kedron Park Hotel Tunnels Construction – Tower Crane 12 March 2015 ENB 485 80
  • 81. Kedron Park Hotel Tunnels Construction
  • 82. Kedron Park Hotel Tunnels Construction
  • 83. Kedron Park Hotel Tunnels Construction - Monitoring RS VLS-LS Siltstone RS VLS-LS Siltstone RS VLS-LS Siltstone Mid-South Wall Corner North Wall Mid-North Wall 33mm 10mm 22mm Prediction = 22mm Prediction = 55mm Base of excavation12 March 2015 ENB 485 83
  • 84. Kedron Park Hotel Tunnels Construction - Monitoring 12 March 2015 ENB 485 84
  • 85. Kedron Park Hotel Tunnels Completion • Two year design life, 4 month construction (nail wall). • 18m deep excavation with further 10m deep piled wall below • Over 1500 soil nails 10 to 15m long (steel and GRP) • Backfilled with flowable fill
  • 86. Soil Nail Walls are not such a great idea in water charged sands and silts (They also can’t be expected to have a 2 weeks stand up time) Airport Link – Construction Issues 12 March 2015 ENB 485 86
  • 88. S E Queensland – Construction Issues
  • 89. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1.51 Mudstone Original Design Sandstone Claystone Name: General Backfill Model: Mohr-Coulomb Unit Weight: 19 kN/m³ Cohesion: 5 kPa Phi: 30 ° Name: Claystone Model: Mohr-Coulomb Unit Weight: 21 kN/m³ Cohesion: 10 kPa Phi: 40 ° Name: Mudstone Model: Mohr-Coulomb Unit Weight: 21 kN/m³ Cohesion: 10 kPa Phi: 42 ° Name: Sandstone Model: Mohr-Coulomb Unit Weight: 20 kN/m³ Cohesion: 2 kPa Phi: 42 ° Sandstone Directory: K:Q1215 - LMICoffeyDesignWallsRW08 Pressure (Unit Weight): 20 kN/m³ General Backfill Offset (m) 0 5 10 15 20 25 30 35 Height(m) 0 5 10 15 20 25 12 March 2015 ENB 485 89
  • 92. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1.53 Mudstone Revised Design Sandstone Claystone Name: General Backfill Model: Mohr-Coulomb Unit Weight: 19 kN/m³ Cohesion: 5 kPa Phi: 30 ° Name: Claystone Model: Mohr-Coulomb Unit Weight: 21 kN/m³ Cohesion: 10 kPa Phi: 40 ° Name: Mudstone Model: Mohr-Coulomb Unit Weight: 21 kN/m³ Cohesion: 10 kPa Phi: 42 ° Name: Uncemented Sandstone Model: Mohr-Coulomb Unit Weight: 20 kN/m³ Cohesion: 0 kPa Phi: 35 ° Name: Sandstone Model: Mohr-Coulomb Unit Weight: 20 kN/m³ Cohesion: 2 kPa Phi: 42 ° Uncemented Sandstone Directory: K:Q1215 - LMICoffeyDesignWallsRW08 Pressure (Unit Weight): 20 kN/m³ General Backfill Offset (m) 0 5 10 15 20 25 30 35 Height(m) 0 5 10 15 20 25 Re-analysed wall with revised ground model and design amended to incorporate same length nails for full height of wall over affected section 12 March 2015 ENB 485 92
  • 93. Remediation But, after wall completed: Wall still showed signs of movement Extra nails 10m in length were recommended along 20m of the unstable section 12 March 2015 ENB 485 93
  • 94. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1.59 Mudstone Remediation Nail Design Sandstone Claystone Name: General Backfill Model: Mohr-Coulomb Unit Weight: 19 kN/m³ Cohesion: 5 kPa Phi: 30 ° Name: Claystone Model: Mohr-Coulomb Unit Weight: 21 kN/m³ Cohesion: 10 kPa Phi: 40 ° Name: Mudstone Model: Mohr-Coulomb Unit Weight: 21 kN/m³ Cohesion: 10 kPa Phi: 42 ° Name: Uncemented Sandstone Model: Mohr-Coulomb Unit Weight: 20 kN/m³ Cohesion: 0 kPa Phi: 35 ° Name: Sandstone Model: Mohr-Coulomb Unit Weight: 20 kN/m³ Cohesion: 2 kPa Phi: 42 ° Uncemented Sandstone Directory: K:Q1215 - LMICoffeyDesignWallsRW08 Pressure (Unit Weight): 20 kN/m³ General Backfill Offset (m) 0 5 10 15 20 25 30 35 Height(m) 0 5 10 15 20 25 12 March 2015 ENB 485 94
  • 98. Road over Rail Bridge
  • 100. Existing RE Wall Drawings
  • 101.
  • 102.
  • 103.
  • 104.
  • 105. 12 March 2015 ENB 485 105
  • 106. 12 March 2015 ENB 485 106
  • 107. Failures Soil nail failures are fairly uncommon but the following are typical: • hole collapse during installation of the soil nail, often due to loose fill materials related to poorly backfilled utility trenches, for example; • over excavation resulting in large unsupported lengths or heights of cut slope; • seepage; • erosion/washout of slope surface; • inappropriate soil - running sands; • problems during drilling due to drill bits getting stuck or getting off line; • grout loss during installation; • poor construction of soil nail heads with voids beneath the soil nail head. 12 March 2015 ENB 485 107
  • 108. Soil Nail Failures Ref.: Tan. & Chow, 2004 Soil nail facing failure Grout cover cracked and peeled off from nail
  • 109. Void within cement grout ~250mm Probed depth = 320 mm into cement grout Probed depth = 1590 mm into cement grout Cross-section Soil Nail Failures 12 March 2015 ENB 485 109
  • 110. Nail with no grout Plastic sheet Short column of cement grout 12 March 2015 ENB 485 110
  • 111. Soil Nail Failures Ref.: Sun & Tsui, 2005 Slope failure prior to soil nail heads being installed during heavy rain Cause of failure: • Ingress of water Assisted by - • Upper row of nails too low below crest • Wide nail spacing • Lack of surface protection • Poor construction of nails
  • 112. Soil Nail Failures 6m3 failure in Completely Decomposed Tuff
  • 113. References • FHWA (1994). “Soil nailing field inspectors manual.” FHWA-SA-93-068, US Department of Transportation, Washington. • FHWA (1998). “Manual for design & construction monitoring of soil nail walls.” FHWA-SA-96-069R, US Department of Transportation, Washington. • FHWA (2003). “Soil nail walls.” Geotechnical Engineering Circular No.7, FHWA0-IF-03-017, US Department of Transportation, Washington. • Clouterre (1991) “French National Research Project Clouterre – Recommendations Clouterre 1991”. (English Translation), Federal Highway Administration, FHWA-SA-93-026, US Department of Transportation, Washington. • BSI (1989). “Code of practice for ground anchorages”, BS 8081:1989, British Standards Institution, London. • Highways Agency (1994). Design manual for roads and bridges- Advice Note HA68/94, Design methods for the reinforcement of highway slopes by reinforced soil and soil nailing techniques. The Stationary Office, London. • Hong Kong Government Webpage: http://www.cedd.gov.hk/eng/publications/index.htm (Geoguide 7, Technical Guidance Notes, GEO Reports)