SlideShare a Scribd company logo
1 of 25
Long Life Asphalt Pavement
and Mix Design
John Harvey
University of California Pavement Research Center
CalAPA
Sacramento
25 October, 2017
Current Long-Life Rehabilitation
Strategies
200-225
mm PCC
100-150 mm
CTB
150 mm
AS
CSOL
Crack and Seat PCC,
Place Thick AC Overlay
FDAC
Remove PCC or AC,
Replace with partial or
full-depth
AC structure
Remove PCC, Replace
with 200-300 mm
Concrete Slab
Retain or replace
existing base
Typical now
150-300
mm AC
150-200
mm CTB
or GB
Typical Structures Needing Long-Life Rehabilitation
• Rural
– Asphalt
– Fatigue cracking
– Reflection cracks
from CTB, PCC, old
asphalt
• Urban
– Cracked jointed
plain PCC
– No dowels
3
General Principles
• Site investigation (minimize surprises)
• Keep material types relatively simple
– Reduces the risk of construction quality issues
– Helps control costs
– Faster construction
• Materials properties = materials + compaction
• Performance related tests
• Drive distresses to occur at the surface
• Ensure bonding between layers during
construction
4
Crack, Seat and Overlay
Bottom layer - cracking
Middle layer – cracking, rutting
Top layer – rutting, cracking
Base layers
Sacrificial layer – safety, noise
Cracked and Seated PCC
0.08-0.15 ft (25-50 mm )
fabric
0.15-0.33 ft (50-100 mm)
Varying
thickness
0.10 ft (30 mm)
subgrade
Existing grade
Full-Depth Asphalt Concrete
Bottom layer - cracking
Middle layer – cracking, rutting
Top layer – rutting, cracking
subgrade
Sacrificial layer – safety, noise
granular base (recycled PCC,
CTB, granular)
0.08-0.15 ft (25-50 mm)
0.15-0.33 ft (50-100 mm)
Varying
thickness
0.15-0.25 ft (50-75 mm )
0-0.50 ft (0-150 mm )
Existing grade
California Design Criteria
• Structure
– 40 year design life
– 95% reliability (within project) using CalME
– Structure designed for rutting (total rut, all
layers considered), bottom-up fatigue
cracking
• Surface layers
– 15 year design life for sacrificial layer
– 40 years for rutting of top layer
7
Sacrificial Surface Layer
• Sacrificial layer (safety, noise)
– Rubberized hot mix open-graded
– Shorter design life than rest of pavement
– When removed,
also removes
top-down cracks
8
HMA
RHMA-G
OGFC
RHMA-O
OBSI noise with SRTT tire at 60 mph
Performance over 15 years
Increased noise
Permanent Top Layer
• Top layer (rutting, top-down cracking)
– Polymer-modified dense-graded asphalt
– Thickness (75-100 mm) depends on expected depth
of high temperatures
– Critical shear
stresses typical
at 50 mm depth
10
0
5
10
15
20
25
30
-
50,000 100,000 150,000 200,000
HVS Load Applications
RutDepth,mm
Conv. mix G*=82 MPa
Typical mix
Typical mix
76-mm polymer
modified mix G*=32 MPa
Polymer better than stiffer conventional
HVS Rut Test Results
Temperature = 50 C at 50 mm depth
Bottom-Up Fatigue Cracking
• Focus on compaction using conventional
materials
• Increased stiffness to reduce tensile
strains at bottom
– Ideas from Australia, UK, France (bitume dur,
Enrobés à Module Elevé [EME])
Middle Layer
• Primary structural layer
– Good rutting resistance (may carry traffic until surface
constructed)
– Good fatigue resistance
– Stiff
• Stiff conventional asphalt, not polymer
– Polymer modified asphalt usually softer than
conventional asphalt at moderate temperature,
reduces bending resistance
– Use higher RAP binder replacement to make stiffer
– No WMA to help ensure blending
• Thickness determined by CalME design
13
Reduction of Air-Voids 8% to 5 %
1.E+06
1.E+07
1.E+08
1.E+09
1.E+10
200 250 300 350 400 450 500
Total AC thickness(mm)
FatigueLife(ESAL)
AR4000c (8% av,5% ac),AR4000c (8% av,5%ac)
AR4000c(5% av,5% ac),AR4000c(5% av,5% ac)
Traffic Index 15
Traffic Index 17
PG58-28
5% air-voids
8% air-voids
Rich-Bottom Layer
• Definition
– Same gradation and RAP content as top layer
– 0 to 3 % air-voids
– Asphalt content increased (contractor choice) to
facilitate compaction
• 50 to 75 mm (0.15-0.25 ft) optimal thickness
• Benefit is from increased compaction, not
increased asphalt content
• Must be out of zone of rutting risk
– More than about 150 mm (0.5 ft) below surface
depending on climate, traffic
Effect of Rich Bottom
1.E+06
1.E+07
1.E+08
1.E+09
1.E+10
1.E+11
200 250 300 350 400 450 500
Total AC thickness (mm)
FatigueLife
AR4000c (8% av,5% ac),AR4000c (8% av,5%ac)
AR4000c(5% av,5% ac),AR4000c(5% av,5% ac)
AR4000c (5% av,5% ac), AR4000c (2%av ,5% ac)
AR4000c (5% av,5% ac), AR4000c(2% av,5.5% ac)
Traffic Index 15
Traffic Index 17
8% AV
5% AV
5% AV, 2% AV bottom same %binder
5% air-void, 2% AV bottom +0.5%binder
Must Have Good Bonding
• Tack coat required between all lifts
• Often use paving asphalt as tack on long-life
instead of emulsion
• Cracking life can be halved if lose bond
17
Mechanistic-Empirical Design
CalME
• Introduced in 2006
• Focus on rehabilitation and preservation
• Incremental – Recursive approach
– Simulation runs one increment of loads/temperatures at
a time
– Calculates damage and
permanent deformation
– Adjusted stiffnesses
are used as input for
the next increment
• Outputs damage,
surface cracking,
IRI, and rut depth
Projects to
Date
• Long Beach
projects under
Hveem, AR
binder
• Last three
projects included
25% RAP, PG
• Next project:
I-5 Sacramento,
Superpave
I-5 Weed 2012
I-5
Red Bluff
2011
I-80
Dixon
2013
I-710 Long Beach
2002, 2006
Main feedback from last three
projects
• Try to make the mix design time go faster
• Changes in specifications and testing:
– Simplified flexural fatigue testing approach
• Cut testing time by about 1/3
• No extrapolation
– Use of Repeated Load Triaxial with AMPT
instead of shear test
• No extrapolation
– Added Semi-circular beam
20
Performance Related Tests
Rolling wheel compaction; Contractors built molds at plant
Design Parameters
Test
Method
Sample
Air Voids
Requirement
HMA-LL-Top
HMA-LL-
Middle
HMA-LL-
Rich Bottom
Permanent deformation (percent): 2,3
Maximum PAS7 at 10,000 cycles
Maximum PAS7 at 20,000 cycles
AASHTO
TP 79
Modified1
Mix
Specific6
XXX
XXX
XXX
XXX
Not
Required
Beam stiffness (psi): 3,4
Minimum stiffness at the 50th
cycle at given testing strain level
AASHTO T
321
Modified1
Mix
specific6
YYY at
XXXĂ—10-6
in./in. strain
YYY at
YYYĂ—10-6
in./in. strain
Not
Required
Beam fatigue: 3,4
Minimum of 1,000,000 cycles to
failure at this strain
Minimum of 250,000 cycles to
failure at this strain
AASHTO T
321
Modified1
Mix
specific6
XXXĂ—10-6
in./in.
XXXĂ—10-6
in./in.
XXXĂ—10-6
in./in.
XXXĂ—10-6
in./in.
XXXĂ—10-6
in./in.
XXXĂ—10-6
in./in.
Semicircular beam fracture
potential:
Flexibility Index
AASHTO
TP 1241
Mix
specific6
YYY
YYY
YYY
Moisture Sensitivity: 5
Minimum repetitions
AASHTO T
324
Modified1
Per test
method
20,000 20,000
Not
Required
Laboratory Tests – Estimated testing
times for three mixes, one iteration
Rolling wheel compaction; Contractors built molds at plant
• Starting point: Superpave mix design (Top, Middle)
• Week 1: Repeated Load Triaxial Top mix
– Multiple binder contents
– Binder content meets RLT permanent strain requirement
• Week 2, 3: Fatigue (Top), Mix Design (Middle)
– Flexural fatigue
• Week 3, 4: Fatigue (Middle), Mix Design (Rich Bottom)
– Rich Bottom mix design using gyratory compaction to get
2% AV, same gradation as surface mix but with
conventional binder
• Week 5, 6: Fatigue (Rich Bottom)
• Repeat as needed for any mix if do not meet requirements
Current Performance Based
Laboratory Tests – Fatigue Testing
Rolling wheel compaction; Contractors built molds at plant
Mix Design Guidance – Alternative ideas
to improve rutting and/or fatigue
Rolling wheel compaction; Contractors built molds at plant
Questions?

More Related Content

What's hot

03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...Hossam Shafiq I
 
Evaluation of Rutting and Stripping Potential of WMA with Different Additives
Evaluation of Rutting and Stripping Potential of WMA with Different AdditivesEvaluation of Rutting and Stripping Potential of WMA with Different Additives
Evaluation of Rutting and Stripping Potential of WMA with Different AdditivesViswalalViswanathan1
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Malyar Talash
 
6-7 Binder ( Highway Engineering Dr. Sherif El-Badawy )
6-7 Binder ( Highway Engineering Dr. Sherif El-Badawy )6-7 Binder ( Highway Engineering Dr. Sherif El-Badawy )
6-7 Binder ( Highway Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
Oxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderOxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderCheng (Wayne) Zhu
 
Drilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteDrilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteAhmad Elsir
 
2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENABenoit Latapie
 
Turbo Abrasive Finishing
Turbo Abrasive FinishingTurbo Abrasive Finishing
Turbo Abrasive FinishingDave Davidson
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)John Latilla
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testingSravan Muguda
 
Airfield design methods
Airfield design methodsAirfield design methods
Airfield design methodsBhavya Jaiswal
 
High strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdHigh strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdIndependent Geoscience
 

What's hot (15)

WMA & Admixtures
WMA & AdmixturesWMA & Admixtures
WMA & Admixtures
 
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
 
Evaluation of Rutting and Stripping Potential of WMA with Different Additives
Evaluation of Rutting and Stripping Potential of WMA with Different AdditivesEvaluation of Rutting and Stripping Potential of WMA with Different Additives
Evaluation of Rutting and Stripping Potential of WMA with Different Additives
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
6-7 Binder ( Highway Engineering Dr. Sherif El-Badawy )
6-7 Binder ( Highway Engineering Dr. Sherif El-Badawy )6-7 Binder ( Highway Engineering Dr. Sherif El-Badawy )
6-7 Binder ( Highway Engineering Dr. Sherif El-Badawy )
 
Oxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderOxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binder
 
Drilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteDrilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai site
 
2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA
 
2014 Wind Turbine Blade Workshop- Bottasso
2014 Wind Turbine Blade Workshop- Bottasso2014 Wind Turbine Blade Workshop- Bottasso
2014 Wind Turbine Blade Workshop- Bottasso
 
Turbo Abrasive Finishing
Turbo Abrasive FinishingTurbo Abrasive Finishing
Turbo Abrasive Finishing
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testing
 
What is Pile Integrity Test ?
What is Pile Integrity Test ?What is Pile Integrity Test ?
What is Pile Integrity Test ?
 
Airfield design methods
Airfield design methodsAirfield design methods
Airfield design methods
 
High strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdHigh strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty Ltd
 

Similar to Long Life Asphalt Pavements in California

2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...California Asphalt Pavement Association
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfad_gordon
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptbala506586
 
Epoxy asphalt vs gussasphalt and sma
Epoxy asphalt vs gussasphalt and smaEpoxy asphalt vs gussasphalt and sma
Epoxy asphalt vs gussasphalt and smajbors
 
FDR Mix Design
FDR Mix DesignFDR Mix Design
FDR Mix Designciviloscar
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
 
Superpavemixdesign
Superpavemixdesign Superpavemixdesign
Superpavemixdesign pradip dangar
 
Mst bar technical data
Mst bar technical dataMst bar technical data
Mst bar technical dataHamed Moosaei
 
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...R C Patil Patil
 
Singapore Presentation 2015 new
Singapore Presentation 2015 newSingapore Presentation 2015 new
Singapore Presentation 2015 newTom Ray
 
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)Utsav Tripathy
 
Presentation
PresentationPresentation
Presentationexpertshagun
 
SPE Aug15
SPE Aug15SPE Aug15
SPE Aug15ttglink
 

Similar to Long Life Asphalt Pavements in California (20)

2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdf
 
Hans Ho: Pavement maintenance challenges and opportunities
Hans Ho: Pavement maintenance challenges and opportunitiesHans Ho: Pavement maintenance challenges and opportunities
Hans Ho: Pavement maintenance challenges and opportunities
 
Kellingray
KellingrayKellingray
Kellingray
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
 
Epoxy asphalt vs gussasphalt and sma
Epoxy asphalt vs gussasphalt and smaEpoxy asphalt vs gussasphalt and sma
Epoxy asphalt vs gussasphalt and sma
 
FDR Mix Design
FDR Mix DesignFDR Mix Design
FDR Mix Design
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Superpavemixdesign
Superpavemixdesign Superpavemixdesign
Superpavemixdesign
 
Mst bar technical data
Mst bar technical dataMst bar technical data
Mst bar technical data
 
asphalt.pdf
asphalt.pdfasphalt.pdf
asphalt.pdf
 
Superpave - Low Volume
Superpave - Low VolumeSuperpave - Low Volume
Superpave - Low Volume
 
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
 
Singapore Presentation 2015 new
Singapore Presentation 2015 newSingapore Presentation 2015 new
Singapore Presentation 2015 new
 
Specifications for Local Agencies
Specifications for Local AgenciesSpecifications for Local Agencies
Specifications for Local Agencies
 
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
 
Presentation
PresentationPresentation
Presentation
 
121802.Electra4
121802.Electra4121802.Electra4
121802.Electra4
 
SPE Aug15
SPE Aug15SPE Aug15
SPE Aug15
 
08 jay behnke
08 jay behnke08 jay behnke
08 jay behnke
 

More from California Asphalt Pavement Association

UCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologiesUCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologiesCalifornia Asphalt Pavement Association
 
National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...California Asphalt Pavement Association
 
Presentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiativePresentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiativeCalifornia Asphalt Pavement Association
 
Update on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industryUpdate on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industryCalifornia Asphalt Pavement Association
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...California Asphalt Pavement Association
 
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial IntelligenceCalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial IntelligenceCalifornia Asphalt Pavement Association
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024California Asphalt Pavement Association
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansCalifornia Asphalt Pavement Association
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolCalifornia Asphalt Pavement Association
 

More from California Asphalt Pavement Association (20)

Reducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industryReducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industry
 
Industry perspective on cold in-place recycling
Industry perspective on cold in-place recyclingIndustry perspective on cold in-place recycling
Industry perspective on cold in-place recycling
 
UCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologiesUCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologies
 
Caltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavementsCaltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavements
 
Update on the latest research with regard to RAP
Update on the latest research with regard to RAPUpdate on the latest research with regard to RAP
Update on the latest research with regard to RAP
 
Pavement quality focus for local agencies in California
Pavement quality focus for local agencies in CaliforniaPavement quality focus for local agencies in California
Pavement quality focus for local agencies in California
 
National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...
 
Utilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixesUtilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixes
 
Pavement Maintenance tools and technology update
Pavement Maintenance tools and technology updatePavement Maintenance tools and technology update
Pavement Maintenance tools and technology update
 
Presentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiativePresentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiative
 
Update on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industryUpdate on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industry
 
Asphalt industry EPD benchmarking update 2024
Asphalt industry EPD benchmarking update  2024Asphalt industry EPD benchmarking update  2024
Asphalt industry EPD benchmarking update 2024
 
Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
 
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial IntelligenceCalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials technicians
 
EPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt PlantEPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt Plant
 
EPD Benchmarks and lessons learned
EPD Benchmarks and lessons learnedEPD Benchmarks and lessons learned
EPD Benchmarks and lessons learned
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD tool
 

Recently uploaded

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 

Recently uploaded (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 

Long Life Asphalt Pavements in California

  • 1. Long Life Asphalt Pavement and Mix Design John Harvey University of California Pavement Research Center CalAPA Sacramento 25 October, 2017
  • 2. Current Long-Life Rehabilitation Strategies 200-225 mm PCC 100-150 mm CTB 150 mm AS CSOL Crack and Seat PCC, Place Thick AC Overlay FDAC Remove PCC or AC, Replace with partial or full-depth AC structure Remove PCC, Replace with 200-300 mm Concrete Slab Retain or replace existing base Typical now 150-300 mm AC 150-200 mm CTB or GB
  • 3. Typical Structures Needing Long-Life Rehabilitation • Rural – Asphalt – Fatigue cracking – Reflection cracks from CTB, PCC, old asphalt • Urban – Cracked jointed plain PCC – No dowels 3
  • 4. General Principles • Site investigation (minimize surprises) • Keep material types relatively simple – Reduces the risk of construction quality issues – Helps control costs – Faster construction • Materials properties = materials + compaction • Performance related tests • Drive distresses to occur at the surface • Ensure bonding between layers during construction 4
  • 5. Crack, Seat and Overlay Bottom layer - cracking Middle layer – cracking, rutting Top layer – rutting, cracking Base layers Sacrificial layer – safety, noise Cracked and Seated PCC 0.08-0.15 ft (25-50 mm ) fabric 0.15-0.33 ft (50-100 mm) Varying thickness 0.10 ft (30 mm) subgrade Existing grade
  • 6. Full-Depth Asphalt Concrete Bottom layer - cracking Middle layer – cracking, rutting Top layer – rutting, cracking subgrade Sacrificial layer – safety, noise granular base (recycled PCC, CTB, granular) 0.08-0.15 ft (25-50 mm) 0.15-0.33 ft (50-100 mm) Varying thickness 0.15-0.25 ft (50-75 mm ) 0-0.50 ft (0-150 mm ) Existing grade
  • 7. California Design Criteria • Structure – 40 year design life – 95% reliability (within project) using CalME – Structure designed for rutting (total rut, all layers considered), bottom-up fatigue cracking • Surface layers – 15 year design life for sacrificial layer – 40 years for rutting of top layer 7
  • 8. Sacrificial Surface Layer • Sacrificial layer (safety, noise) – Rubberized hot mix open-graded – Shorter design life than rest of pavement – When removed, also removes top-down cracks 8
  • 9. HMA RHMA-G OGFC RHMA-O OBSI noise with SRTT tire at 60 mph Performance over 15 years Increased noise
  • 10. Permanent Top Layer • Top layer (rutting, top-down cracking) – Polymer-modified dense-graded asphalt – Thickness (75-100 mm) depends on expected depth of high temperatures – Critical shear stresses typical at 50 mm depth 10
  • 11. 0 5 10 15 20 25 30 - 50,000 100,000 150,000 200,000 HVS Load Applications RutDepth,mm Conv. mix G*=82 MPa Typical mix Typical mix 76-mm polymer modified mix G*=32 MPa Polymer better than stiffer conventional HVS Rut Test Results Temperature = 50 C at 50 mm depth
  • 12. Bottom-Up Fatigue Cracking • Focus on compaction using conventional materials • Increased stiffness to reduce tensile strains at bottom – Ideas from Australia, UK, France (bitume dur, EnrobĂ©s Ă  Module ElevĂ© [EME])
  • 13. Middle Layer • Primary structural layer – Good rutting resistance (may carry traffic until surface constructed) – Good fatigue resistance – Stiff • Stiff conventional asphalt, not polymer – Polymer modified asphalt usually softer than conventional asphalt at moderate temperature, reduces bending resistance – Use higher RAP binder replacement to make stiffer – No WMA to help ensure blending • Thickness determined by CalME design 13
  • 14. Reduction of Air-Voids 8% to 5 % 1.E+06 1.E+07 1.E+08 1.E+09 1.E+10 200 250 300 350 400 450 500 Total AC thickness(mm) FatigueLife(ESAL) AR4000c (8% av,5% ac),AR4000c (8% av,5%ac) AR4000c(5% av,5% ac),AR4000c(5% av,5% ac) Traffic Index 15 Traffic Index 17 PG58-28 5% air-voids 8% air-voids
  • 15. Rich-Bottom Layer • Definition – Same gradation and RAP content as top layer – 0 to 3 % air-voids – Asphalt content increased (contractor choice) to facilitate compaction • 50 to 75 mm (0.15-0.25 ft) optimal thickness • Benefit is from increased compaction, not increased asphalt content • Must be out of zone of rutting risk – More than about 150 mm (0.5 ft) below surface depending on climate, traffic
  • 16. Effect of Rich Bottom 1.E+06 1.E+07 1.E+08 1.E+09 1.E+10 1.E+11 200 250 300 350 400 450 500 Total AC thickness (mm) FatigueLife AR4000c (8% av,5% ac),AR4000c (8% av,5%ac) AR4000c(5% av,5% ac),AR4000c(5% av,5% ac) AR4000c (5% av,5% ac), AR4000c (2%av ,5% ac) AR4000c (5% av,5% ac), AR4000c(2% av,5.5% ac) Traffic Index 15 Traffic Index 17 8% AV 5% AV 5% AV, 2% AV bottom same %binder 5% air-void, 2% AV bottom +0.5%binder
  • 17. Must Have Good Bonding • Tack coat required between all lifts • Often use paving asphalt as tack on long-life instead of emulsion • Cracking life can be halved if lose bond 17
  • 18. Mechanistic-Empirical Design CalME • Introduced in 2006 • Focus on rehabilitation and preservation • Incremental – Recursive approach – Simulation runs one increment of loads/temperatures at a time – Calculates damage and permanent deformation – Adjusted stiffnesses are used as input for the next increment • Outputs damage, surface cracking, IRI, and rut depth
  • 19. Projects to Date • Long Beach projects under Hveem, AR binder • Last three projects included 25% RAP, PG • Next project: I-5 Sacramento, Superpave I-5 Weed 2012 I-5 Red Bluff 2011 I-80 Dixon 2013 I-710 Long Beach 2002, 2006
  • 20. Main feedback from last three projects • Try to make the mix design time go faster • Changes in specifications and testing: – Simplified flexural fatigue testing approach • Cut testing time by about 1/3 • No extrapolation – Use of Repeated Load Triaxial with AMPT instead of shear test • No extrapolation – Added Semi-circular beam 20
  • 21. Performance Related Tests Rolling wheel compaction; Contractors built molds at plant Design Parameters Test Method Sample Air Voids Requirement HMA-LL-Top HMA-LL- Middle HMA-LL- Rich Bottom Permanent deformation (percent): 2,3 Maximum PAS7 at 10,000 cycles Maximum PAS7 at 20,000 cycles AASHTO TP 79 Modified1 Mix Specific6 XXX XXX XXX XXX Not Required Beam stiffness (psi): 3,4 Minimum stiffness at the 50th cycle at given testing strain level AASHTO T 321 Modified1 Mix specific6 YYY at XXXĂ—10-6 in./in. strain YYY at YYYĂ—10-6 in./in. strain Not Required Beam fatigue: 3,4 Minimum of 1,000,000 cycles to failure at this strain Minimum of 250,000 cycles to failure at this strain AASHTO T 321 Modified1 Mix specific6 XXXĂ—10-6 in./in. XXXĂ—10-6 in./in. XXXĂ—10-6 in./in. XXXĂ—10-6 in./in. XXXĂ—10-6 in./in. XXXĂ—10-6 in./in. Semicircular beam fracture potential: Flexibility Index AASHTO TP 1241 Mix specific6 YYY YYY YYY Moisture Sensitivity: 5 Minimum repetitions AASHTO T 324 Modified1 Per test method 20,000 20,000 Not Required
  • 22. Laboratory Tests – Estimated testing times for three mixes, one iteration Rolling wheel compaction; Contractors built molds at plant • Starting point: Superpave mix design (Top, Middle) • Week 1: Repeated Load Triaxial Top mix – Multiple binder contents – Binder content meets RLT permanent strain requirement • Week 2, 3: Fatigue (Top), Mix Design (Middle) – Flexural fatigue • Week 3, 4: Fatigue (Middle), Mix Design (Rich Bottom) – Rich Bottom mix design using gyratory compaction to get 2% AV, same gradation as surface mix but with conventional binder • Week 5, 6: Fatigue (Rich Bottom) • Repeat as needed for any mix if do not meet requirements
  • 23. Current Performance Based Laboratory Tests – Fatigue Testing Rolling wheel compaction; Contractors built molds at plant
  • 24. Mix Design Guidance – Alternative ideas to improve rutting and/or fatigue Rolling wheel compaction; Contractors built molds at plant