SlideShare a Scribd company logo
1 of 36
Download to read offline
Long Life Asphalt Pavement
John Harvey
University of California Pavement Research Center
Davis and Berkeley
23 March 2023
Ontario, CA
1998
• Long-Life Pavement Rehabilitation Strategies
(LLPRS)
• Long-Life requires poor condition
and >150,000 ADT or >15,000 ADTT
– 2,000 lane-km meet these criteria
• Funding limitations
• Design and Construction criteria:
– 30+ year design lives, minimum maintenance
– 55-hour weekends or 72-hour weekday
construction closures
– Minimize lane closures
•Google was founded
•Titanic dominated the
Oscars
•President Bill Clinton
was impeached
•Europeans agreed on
the common currency of
the Euro
•Harry Potter made US
debut
•First MP3 players
Problem: How to Optimize Long Life
Rehabilitation Strategies on Multiple Criteria
• Want Long Life and Fast Construction and
Minimum Traffic Delay
– Pavement design strategies:
• Longer life pavements take longer to
construct
• Construction time linearly proportional to
thickness
• Requires Integration
– Pavement Engineering + Construction
Engineering + Traffic Engineering
General Pavement Approach
• Drive distresses to the surface
– Where they are easy to maintain
• Keep the materials simple to
produce and the design simple to
construct
• Integrate
– Mix design
– Structural design
– Constructability
General Pavement Approach
• From:
– SHRP project (tests)
– France/UK experience (stiff binder in thick asphalt
pavements
– UCPRC/Caltrans research (compaction, ME design,
rich bottom)
– CalAPA desert mix experience
• Approach:
– Performance related tests
– Polymer modification for surface for rutting
– Stiff binders below surface
– Maximum practical compaction (6% air-voids)
– Rich Bottom
150 mm, 5 % air-voids,
AR-8000
75 mm, Rich Bottom
75 mm PBA-6a
I-710 Reduction of Full-Depth
Pavement Thickness Under Bridges
535 mm thick
asphalt concrete
8 % air-voids,
same mix design
throughout
Asphalt Institute ME
Method design
Pre-CalME
UCPRC Mechanistic design
44% reduction in thickness
Faster construction
History of AC Long Life Projects
• I-710 Long Beach (2002/4)
• I-5 Red Bluff (2011/2)
• I-5 Weed (2011/2)
• I-80 Solano (2012/3)
• I-5 Sacramento (2021/2
A quick vocabulary check
LLAP = long life asphalt
pavement, 20+ years, generally
40 years
Can be done without PRS (non-
PRS)
PRS = performance related
specification
AC Long Life is an LLAP using
the 3-layer system from
previous projects
Talking today about LLAP PRS
projects using AC Long Life
approach
• Pavement design goals:
– 40-year design life for all structural layers
– Periodic replacement of thin surface layer,
typically RHMA-O
• Take advantage of construction quality
and mechanics to get thinner pavement
meeting design life requirements
– Balance stiffness and fatigue resistance
• CalME design software
– Lower air-voids makes everything better!
Current Concepts of LLAP PRS, AC Long Life
Surface Layer
• PG 64-28 Polymer Modified (or RHMA-G)
• Up to 15% RAP
• 94-97% Air Voids in Place
Full Depth cross -section for Reconstruction
Requires AB when new pavement
10
AC Long Life Structural Design
Intermediate Layers
• PG 64-16
• Up to 25% RAP without Step Down
• 94-97% Air Voids in Place
Rich Bottom Layer
• PG 64-16 with +X% of Binder (+0.5% recommended)
• Up to 15% RAP
• 97-100% Air Voids in Place
0.1’
0.2’
Variable
0.45’ on Sac-5
0.2’
1.0’
Rut and Top-Down Crack
Resistant Surface Layer
Stiff and Fatigue Resistant
Intermediate Layer
Stiff, Fatigue Resistant
Rich Bottom
Rubberized Open Grade
Rubberized Open Grade
Standard Section 39
LLAP PRS may use
RHMA-G for
surface
May only use two
layers (no Rich
Bottom)
Aggregate Base
Surface Layer
• PG 64-28 Polymer Modified
• Up to 15% RAP
• 94-97% Air Voids in Place
Crack-seat and overlay cross-section
11
AC Long Life Structural Design
Intermediate Layers
• PG 64-16
• Up to 25% RAP without Step Down
• 94-97% Air Voids in Place
Leveling Course
• ½” Conventional Type A, PG64-16
• Up to 15% RAP
• Method Specification
Rubberized Open Grade
Standard Section 39
Fabric
Use of CalME on LLAP PRS, AC Long Life
• Caltrans
Office of
Asphalt
Pavement
• Raghu
Shrestha
• Use balanced mix design (BMD)
– Use performance related tests (PRT)
– Require materials to meet performance related
specifications (PRS)
– Relax volumetric and other old experience-based
requirements
• What performance related tests and
specifications?
– For rutting, stiffness, fatigue, moisture damage
– Moisture sensitivity important everywhere
– Top-down cracking: no tests or models, use basic
principles in designs
Current Concepts of LLAP PRS, AC Long Life
Performance Related Tests for JMF
• Fatigue/Stiffness
– T 321, - Beam Flexural Fatigue test
• Permanent Deformation
– T 378, “Flow number test” using AMPT (asphalt mixture performance tester)
– Using repetitions to permanent axial strain because Flow Number can be hard
to pinpoint for California mixes
• Fracture
– IDEAL-CT (current test)
• Moisture Sensitivity
– T 324 Hamburg wheel tracking test (HWTT)
– T 283 Tensile strength ratio (TSR)
Setting of Baseline Performance Requirements for JMF
Setting the performance related
requirements
• Previously:
– Took local mix designs and optimized
them
– Some problems
– Lab mix not plant mix
• Now:
– Look at state-wide distribution of plant
mixes
– Set values to eliminate low
performance mixes
Testing in JMF for performance related
requirements
• 95% confidence intervals determined
from baseline mix tests
• Contractor average result needs to
meet 5% confidence interval
• Intent: take most of testing risk off
contractor
Setting of Baseline Performance Requirements
– Flexural Fatigue Life Example
Baseline Performance Requirements JMF – 1/2
HMA-LL Performance Requirements
Design parameters
Test
method
Sample Air
Voids
Requirement
HMA-LL,
Surface
HMA- LL,
Intermediate
HMA-LL,
Rich Bottom
Permanent deformation: 1,2
Minimum number of cycles to
3% permanent axial strain
AASHTO T
3783
Mix
specific4 2,093 4,131
Not
Required
Beam stiffness (psi): 2,5
Minimum stiffness at the 50th
cycle at the given testing strain
level
AASHTO T
321
Modified3
Mix
specific4
214,000 at
952×10-6
in./in.
789,000 at
446×10-6
in./in.
756,000 at
441×10-6
in./in.
Beam fatigue: 2,5
Minimum of 1,000,000 cycles
to failure at this strain
Minimum of 250,000 cycles to
failure at this strain
AASHTO T
321
Modified3
Mix
specific4
617×10-6
in./in.
952×10-6
in./in.
299×10-6
in./in.
446×10-6
in./in.
306×10-6
in./in.
441×10-6
in./in.
Baseline Performance Requirements JMF – 2/2
HMA-LL Performance Requirements
Design parameters
Test
method
Sample Air
Voids
Requirement
HMA-LL,
Surface
HMA- LL,
Intermediate
HMA-LL,
Rich Bottom
Semicircular beam fracture
potential: 2
Minimum flexibility index
AASHTO
TP 1243
Mix
specific4 3.0 0.5 0.5
Moisture Sensitivity: 6
Minimum repetitions
AASHTO T
324
Modified3
Per test
method
20,000 20,000
Not
Required
NOTES:
1 Tested at a temperature of 122F (50C), unconfined, 4.4 psi contact stress, and 70 psi repeated axial
stress
2 Average value determined from tests on 3 specimens and calculated as the geometric (not arithmetic)
mean.
3 Included in the testing procedure, LLP-AC3, "Sample Preparation and Testing for Long-Life Asphalt
Concrete Pavements" available at: http://www.dot.ca.gov/hq/esc/Translab/ormt/fpmlab.htm]
4 6 ± 0.5% for HMA-LL, Surface and HMA-LL, Intermediate mixes, and 3 ± 0.5% for HMA-LL, Rich Bottom
mix all following AASHTO T 331
5 Perform tests at 10 Hz load frequency and 68F (20C) test temperature
6 Minimum number of repetitions for rut depth of 0.5 in. at 122F (50C)
Replaced with
IDEAL-CT
Report Published to Aid Contractors in Meeting JMF
Performance-Related Specs
• Mix Design Guidance for Use with Asphalt Concrete
Performance-Related Specifications
• http://www.ucprc.ucdavis.edu/PDF/UCPRC-RR-2017-
12.pdf
• Example mix and guidance on how to improve
rutting, stiffness and fatigue performance related
properties
– Gradation
– Aggregate texture
– Binder content
– Binder grade
– Binder supplier
Testing During Construction QC/QA
• First four projects:
– Rely on standard volumetric tests for control
• Sac-5
– Repeated load triaxial and SCB or IDEAL-CT every day of production
– Currently analyzing the results to see if extra information worth the
time and costs
– Pointing towards reduce or even eliminate performance related
testing in QC/QA
21
What do LLP PRS Specifications do to
Mix Designs?
Sac-5 examples
22
y = 5E+22x-6.078
y = 3E+18x-5.074
y = 2E+18x-4.863
y = 2E+29x-8.421
y = 8E+24x-7.468
y = 1E+13x-2.83
100
1,000
10,000
100,000
1,000,000
10,000,000
100 1000
Fatigue
Life
(Cycles)
Peak-to-peak strain (με)
SML – 4PB - Wohler Curves: All Standard Materials Mixes
Spec. Fatigue Cycle- High Strain
Spec. Fatigue Cycle- Low Strain
Plant-Mix 18-NB-Surf. (R15, PG64-28PM)
Plant-Mix 20-NB-Int. (R22, PG64-16)
Plant-Mix 17-NB-R.B. (R15, PG64-16)
Plant-Mix 19-SB-Surf. (R15, PG64-28PM)
Plant-Mix 21-SB-Int. (R25, PG64-16)
Plant-Mix 16-SB-R.B. (R15, PG64-16)
23
100
150
200
250
300
0
50
100
150
200
2020
Ideal
Strength
(psi)
CT
Index
(#)
IdealCT Crack Tolerance Index at 25C, Daily QA Results
CT Index
Ideal Strength
2021
24
2021 Volumetric Test Results (QC)
Lift Mix ID
AC%,
TMM
Std
Dev.
#200
Std
Dev.
Va @
Ndesign
Std Dev. VMA
Std
Dev.
DP
Std
Dev.
SPGR
Std
Dev.
(desc.) (desc.) (%) (%) (%) (%) (%) (%) (%) (%) (#) (#) (#) (#)
Surface 352-Mix18-TeB-Srf 5.32 0.13 5.6 0.8 0.7 0.3 11.7 0.3 1.01 0.09 2.532 0.009
Surface 352-Mix19-GrD-Srf 5.23 0.13 4.9 0.2 1.3 0.4 11.9 0.4 0.93 0.05 2.555 0.008
Intermediate 352-Mix14-TeB-Int 5.27 0.07 5.1 1.0 1.8 0.7 13.9 0.5 0.96 0.20 2.532 0.007
Intermediate 352-Mix20-TeD-Int 5.16 0.14 4.4 0.7 2.9 0.7 14.0 0.6 0.86 0.12 2.539 0.009
Intermediate 352-Mix21-GrD-Int 5.22 0.13 4.5 0.3 2.4 0.7 12.7 0.7 0.90 0.20 2.556 0.008
Rich Bottom 352-Mix16-Grd-RcB 5.50 0.08 6.1 0.3 0.7 0.3 12.2 0.6 1.11 0.06 2.549 0.006
Rich Bottom 352-Mix17-TeD-RcB 5.29 0.29 5.0 0.6 3.9 2.0 15.0 1.3 0.94 0.12 2.541 0.017
Average 5.28 0.14 5.1 0.6 1.9 0.7 13.0 0.6 0.96 0.12 2.544 0.009
Result: very compactable mixes (good pay factors);
improved durability (fatigue, moisture); good rutting resistance
25
• Use plant mix performance test results from state-wide material library to
set specification requirements
• Communicate aggregate property, asphalt binder, handling, and
volumetric differences to optimize the fatigue beam testing; update Mix
Design Guidance
• Pre-qualification of mixes to reduce contractor risk in bidding
• Develop a quick test for binder fatigue and stiffness properties so mix
producers can choose to maximum fatigue performance
Some Sac-5 Preliminary Takeaways and
Recommendations for Improvement of Specification
26
• Control aging from sampling through testing; new draft Caltrans protocol
under development (beyond AASHTO R-30)
• Make testing faster, simpler, less costly, better results:
• Fatigue beam compaction, updated rutting test
• Determine appropriate amount of performance testing for QC/QA
• Allow more pathways for producers to achieve PRS
Some Sac-5 Preliminary Takeaways and
Recommendations for Improvement of Specification
27
• Get more laboratories on-line and verified that able to do flexural beam
tests
• UCPRC currently working with CSU-Chico (have equipment)
• Others?
• Better accounting of performance related test variability
• Training and round robins to build trust in tests
• Communicate success! (Sac-5 contractors’ suggestion)
• Recycling, economics and sustainability
Some Sac-5 Preliminary Takeaways and
Recommendations for Improvement of Specification
How are they doing?
Project Name Year EA Description PM
LA710-Long
Beach
2001-2004 07-1384U CSOL, and reconstruction
under bridges
6.8-9.8
TEH5-Red Bluff 2012-2013 02-3E810 HMA lane replacement and
HMA thick overlay
31.8-35.1NB
and 37.1-41.6
SIS5-Weed 2011-2013 02-3E750 CSOL and HMA thick overlay R19.1-R25.2
SOL80-Dixon 2013-2014 04-4A010 CSOL and slab replacement 30.6-38.7
SAC5-
Sacramento
2021-2022 CSOL and new HMA lane various over 19
miles
LA-710, mostly
20 years old
• IRI pre-
construction:
– 150 to 200
in/mile
• At construction:
– 60 to 100
• 2022:
– 60 to 100
– Some increase
in Lane 1
LA-710, mostly
20 years old
• Cracking:
– No cracking
– Small increase
in 2015 survey
– May be a
problem with
APCS that year
LA-710, mostly 20
years old
• Rutting:
– Less than ¼
inch (6 mm)
• Replacement
of RHMA-O in
2015
Tehama-5
2 to 7 years old: Aging, Air-voids, Binder Content
Other projects
• No maintenance
treatments
• Little change in as-built
IRI
• No cracking
– Except up to 15% in one
lane on Sis-5 in last 5
years
• Rutting less than ¼ inch
February 2023 California Transportation Commission Meeting:
NAPA Awards to Caltrans District 3, Contractors, UCPRC
for AC Long Life projects
Thanks to all
Caltrans,
contractor and
UCPRC people
involved in these
projects
www.ucprc.ucdavis.edu
www.ucprc.ucdavis.edu/ccpic

More Related Content

Similar to Long-Life Asphalt Pavement Optimization

PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...Alex Matveev
 
WMA Presentation at Transportation Research Board Conference 2007
WMA Presentation at Transportation Research Board Conference 2007WMA Presentation at Transportation Research Board Conference 2007
WMA Presentation at Transportation Research Board Conference 2007Shu Wei Goh
 
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
New Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary KrichauNew Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary Krichaunacetwincities
 
IPTC 18916 presentation slides (technical session 11)
IPTC 18916 presentation slides (technical session 11)IPTC 18916 presentation slides (technical session 11)
IPTC 18916 presentation slides (technical session 11)Theerepat Suppachoknirun
 
Extending service life of existing bridges
Extending service life of existing bridgesExtending service life of existing bridges
Extending service life of existing bridgesEva Lantsoght
 
Vehicle Light Weighting - A Greener, Composite Solution (for Class A Body Pan...
Vehicle Light Weighting - A Greener, Composite Solution (for Class A Body Pan...Vehicle Light Weighting - A Greener, Composite Solution (for Class A Body Pan...
Vehicle Light Weighting - A Greener, Composite Solution (for Class A Body Pan...OC_Composites
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhiRajesh Prasad
 
TDAS 615 Tubing Design pitfalls 2005.ppt
TDAS 615 Tubing Design pitfalls 2005.pptTDAS 615 Tubing Design pitfalls 2005.ppt
TDAS 615 Tubing Design pitfalls 2005.pptaminpeyvand
 
Oxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderOxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderCheng (Wayne) Zhu
 
Innovation Spuzic
Innovation SpuzicInnovation Spuzic
Innovation SpuzicSead Spuzic
 

Similar to Long-Life Asphalt Pavement Optimization (20)

PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
PASS/START-PROF capabilities for oil & gas gathering, upstream and midstr...
 
WMA Presentation at Transportation Research Board Conference 2007
WMA Presentation at Transportation Research Board Conference 2007WMA Presentation at Transportation Research Board Conference 2007
WMA Presentation at Transportation Research Board Conference 2007
 
LinkedIn
LinkedInLinkedIn
LinkedIn
 
Jim Signore: Hamburg Wheel Track test
Jim Signore: Hamburg Wheel Track testJim Signore: Hamburg Wheel Track test
Jim Signore: Hamburg Wheel Track test
 
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
 
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
 
New Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary KrichauNew Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary Krichau
 
IPTC 18916 presentation slides (technical session 11)
IPTC 18916 presentation slides (technical session 11)IPTC 18916 presentation slides (technical session 11)
IPTC 18916 presentation slides (technical session 11)
 
Extending service life of existing bridges
Extending service life of existing bridgesExtending service life of existing bridges
Extending service life of existing bridges
 
Vehicle Light Weighting - A Greener, Composite Solution (for Class A Body Pan...
Vehicle Light Weighting - A Greener, Composite Solution (for Class A Body Pan...Vehicle Light Weighting - A Greener, Composite Solution (for Class A Body Pan...
Vehicle Light Weighting - A Greener, Composite Solution (for Class A Body Pan...
 
Srp 2018 00
Srp 2018 00Srp 2018 00
Srp 2018 00
 
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
 
Sandia 2014 Wind Turbine Blade Workshop- Van Dam
Sandia 2014 Wind Turbine Blade Workshop- Van DamSandia 2014 Wind Turbine Blade Workshop- Van Dam
Sandia 2014 Wind Turbine Blade Workshop- Van Dam
 
RAR 2015
RAR 2015RAR 2015
RAR 2015
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
TDAS 615 Tubing Design pitfalls 2005.ppt
TDAS 615 Tubing Design pitfalls 2005.pptTDAS 615 Tubing Design pitfalls 2005.ppt
TDAS 615 Tubing Design pitfalls 2005.ppt
 
Oxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderOxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binder
 
Pavement quality focus for local agencies in California
Pavement quality focus for local agencies in CaliforniaPavement quality focus for local agencies in California
Pavement quality focus for local agencies in California
 
Innovation Spuzic
Innovation SpuzicInnovation Spuzic
Innovation Spuzic
 
Corun_-_Polymers (1).ppt
Corun_-_Polymers (1).pptCorun_-_Polymers (1).ppt
Corun_-_Polymers (1).ppt
 

More from California Asphalt Pavement Association

National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...California Asphalt Pavement Association
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...California Asphalt Pavement Association
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024California Asphalt Pavement Association
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansCalifornia Asphalt Pavement Association
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolCalifornia Asphalt Pavement Association
 

More from California Asphalt Pavement Association (20)

Reducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industryReducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industry
 
Industry perspective on cold in-place recycling
Industry perspective on cold in-place recyclingIndustry perspective on cold in-place recycling
Industry perspective on cold in-place recycling
 
UCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologiesUCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologies
 
Caltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavementsCaltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavements
 
Update on the latest research with regard to RAP
Update on the latest research with regard to RAPUpdate on the latest research with regard to RAP
Update on the latest research with regard to RAP
 
National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...
 
Utilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixesUtilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixes
 
Pavement Maintenance tools and technology update
Pavement Maintenance tools and technology updatePavement Maintenance tools and technology update
Pavement Maintenance tools and technology update
 
Presentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiativePresentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiative
 
Update on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industryUpdate on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industry
 
Asphalt industry EPD benchmarking update 2024
Asphalt industry EPD benchmarking update  2024Asphalt industry EPD benchmarking update  2024
Asphalt industry EPD benchmarking update 2024
 
Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
 
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial IntelligenceCalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials technicians
 
EPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt PlantEPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt Plant
 
EPD Benchmarks and lessons learned
EPD Benchmarks and lessons learnedEPD Benchmarks and lessons learned
EPD Benchmarks and lessons learned
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD tool
 
Challenges for EPD implementation
Challenges for EPD implementationChallenges for EPD implementation
Challenges for EPD implementation
 

Recently uploaded

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 

Long-Life Asphalt Pavement Optimization

  • 1. Long Life Asphalt Pavement John Harvey University of California Pavement Research Center Davis and Berkeley 23 March 2023 Ontario, CA
  • 2. 1998 • Long-Life Pavement Rehabilitation Strategies (LLPRS) • Long-Life requires poor condition and >150,000 ADT or >15,000 ADTT – 2,000 lane-km meet these criteria • Funding limitations • Design and Construction criteria: – 30+ year design lives, minimum maintenance – 55-hour weekends or 72-hour weekday construction closures – Minimize lane closures •Google was founded •Titanic dominated the Oscars •President Bill Clinton was impeached •Europeans agreed on the common currency of the Euro •Harry Potter made US debut •First MP3 players
  • 3. Problem: How to Optimize Long Life Rehabilitation Strategies on Multiple Criteria • Want Long Life and Fast Construction and Minimum Traffic Delay – Pavement design strategies: • Longer life pavements take longer to construct • Construction time linearly proportional to thickness • Requires Integration – Pavement Engineering + Construction Engineering + Traffic Engineering
  • 4. General Pavement Approach • Drive distresses to the surface – Where they are easy to maintain • Keep the materials simple to produce and the design simple to construct • Integrate – Mix design – Structural design – Constructability
  • 5. General Pavement Approach • From: – SHRP project (tests) – France/UK experience (stiff binder in thick asphalt pavements – UCPRC/Caltrans research (compaction, ME design, rich bottom) – CalAPA desert mix experience • Approach: – Performance related tests – Polymer modification for surface for rutting – Stiff binders below surface – Maximum practical compaction (6% air-voids) – Rich Bottom
  • 6. 150 mm, 5 % air-voids, AR-8000 75 mm, Rich Bottom 75 mm PBA-6a I-710 Reduction of Full-Depth Pavement Thickness Under Bridges 535 mm thick asphalt concrete 8 % air-voids, same mix design throughout Asphalt Institute ME Method design Pre-CalME UCPRC Mechanistic design 44% reduction in thickness Faster construction
  • 7. History of AC Long Life Projects • I-710 Long Beach (2002/4) • I-5 Red Bluff (2011/2) • I-5 Weed (2011/2) • I-80 Solano (2012/3) • I-5 Sacramento (2021/2
  • 8. A quick vocabulary check LLAP = long life asphalt pavement, 20+ years, generally 40 years Can be done without PRS (non- PRS) PRS = performance related specification AC Long Life is an LLAP using the 3-layer system from previous projects Talking today about LLAP PRS projects using AC Long Life approach
  • 9. • Pavement design goals: – 40-year design life for all structural layers – Periodic replacement of thin surface layer, typically RHMA-O • Take advantage of construction quality and mechanics to get thinner pavement meeting design life requirements – Balance stiffness and fatigue resistance • CalME design software – Lower air-voids makes everything better! Current Concepts of LLAP PRS, AC Long Life
  • 10. Surface Layer • PG 64-28 Polymer Modified (or RHMA-G) • Up to 15% RAP • 94-97% Air Voids in Place Full Depth cross -section for Reconstruction Requires AB when new pavement 10 AC Long Life Structural Design Intermediate Layers • PG 64-16 • Up to 25% RAP without Step Down • 94-97% Air Voids in Place Rich Bottom Layer • PG 64-16 with +X% of Binder (+0.5% recommended) • Up to 15% RAP • 97-100% Air Voids in Place 0.1’ 0.2’ Variable 0.45’ on Sac-5 0.2’ 1.0’ Rut and Top-Down Crack Resistant Surface Layer Stiff and Fatigue Resistant Intermediate Layer Stiff, Fatigue Resistant Rich Bottom Rubberized Open Grade Rubberized Open Grade Standard Section 39 LLAP PRS may use RHMA-G for surface May only use two layers (no Rich Bottom) Aggregate Base
  • 11. Surface Layer • PG 64-28 Polymer Modified • Up to 15% RAP • 94-97% Air Voids in Place Crack-seat and overlay cross-section 11 AC Long Life Structural Design Intermediate Layers • PG 64-16 • Up to 25% RAP without Step Down • 94-97% Air Voids in Place Leveling Course • ½” Conventional Type A, PG64-16 • Up to 15% RAP • Method Specification Rubberized Open Grade Standard Section 39 Fabric
  • 12. Use of CalME on LLAP PRS, AC Long Life • Caltrans Office of Asphalt Pavement • Raghu Shrestha
  • 13. • Use balanced mix design (BMD) – Use performance related tests (PRT) – Require materials to meet performance related specifications (PRS) – Relax volumetric and other old experience-based requirements • What performance related tests and specifications? – For rutting, stiffness, fatigue, moisture damage – Moisture sensitivity important everywhere – Top-down cracking: no tests or models, use basic principles in designs Current Concepts of LLAP PRS, AC Long Life
  • 14. Performance Related Tests for JMF • Fatigue/Stiffness – T 321, - Beam Flexural Fatigue test • Permanent Deformation – T 378, “Flow number test” using AMPT (asphalt mixture performance tester) – Using repetitions to permanent axial strain because Flow Number can be hard to pinpoint for California mixes • Fracture – IDEAL-CT (current test) • Moisture Sensitivity – T 324 Hamburg wheel tracking test (HWTT) – T 283 Tensile strength ratio (TSR)
  • 15. Setting of Baseline Performance Requirements for JMF Setting the performance related requirements • Previously: – Took local mix designs and optimized them – Some problems – Lab mix not plant mix • Now: – Look at state-wide distribution of plant mixes – Set values to eliminate low performance mixes Testing in JMF for performance related requirements • 95% confidence intervals determined from baseline mix tests • Contractor average result needs to meet 5% confidence interval • Intent: take most of testing risk off contractor
  • 16. Setting of Baseline Performance Requirements – Flexural Fatigue Life Example
  • 17. Baseline Performance Requirements JMF – 1/2 HMA-LL Performance Requirements Design parameters Test method Sample Air Voids Requirement HMA-LL, Surface HMA- LL, Intermediate HMA-LL, Rich Bottom Permanent deformation: 1,2 Minimum number of cycles to 3% permanent axial strain AASHTO T 3783 Mix specific4 2,093 4,131 Not Required Beam stiffness (psi): 2,5 Minimum stiffness at the 50th cycle at the given testing strain level AASHTO T 321 Modified3 Mix specific4 214,000 at 952×10-6 in./in. 789,000 at 446×10-6 in./in. 756,000 at 441×10-6 in./in. Beam fatigue: 2,5 Minimum of 1,000,000 cycles to failure at this strain Minimum of 250,000 cycles to failure at this strain AASHTO T 321 Modified3 Mix specific4 617×10-6 in./in. 952×10-6 in./in. 299×10-6 in./in. 446×10-6 in./in. 306×10-6 in./in. 441×10-6 in./in.
  • 18. Baseline Performance Requirements JMF – 2/2 HMA-LL Performance Requirements Design parameters Test method Sample Air Voids Requirement HMA-LL, Surface HMA- LL, Intermediate HMA-LL, Rich Bottom Semicircular beam fracture potential: 2 Minimum flexibility index AASHTO TP 1243 Mix specific4 3.0 0.5 0.5 Moisture Sensitivity: 6 Minimum repetitions AASHTO T 324 Modified3 Per test method 20,000 20,000 Not Required NOTES: 1 Tested at a temperature of 122F (50C), unconfined, 4.4 psi contact stress, and 70 psi repeated axial stress 2 Average value determined from tests on 3 specimens and calculated as the geometric (not arithmetic) mean. 3 Included in the testing procedure, LLP-AC3, "Sample Preparation and Testing for Long-Life Asphalt Concrete Pavements" available at: http://www.dot.ca.gov/hq/esc/Translab/ormt/fpmlab.htm] 4 6 ± 0.5% for HMA-LL, Surface and HMA-LL, Intermediate mixes, and 3 ± 0.5% for HMA-LL, Rich Bottom mix all following AASHTO T 331 5 Perform tests at 10 Hz load frequency and 68F (20C) test temperature 6 Minimum number of repetitions for rut depth of 0.5 in. at 122F (50C) Replaced with IDEAL-CT
  • 19. Report Published to Aid Contractors in Meeting JMF Performance-Related Specs • Mix Design Guidance for Use with Asphalt Concrete Performance-Related Specifications • http://www.ucprc.ucdavis.edu/PDF/UCPRC-RR-2017- 12.pdf • Example mix and guidance on how to improve rutting, stiffness and fatigue performance related properties – Gradation – Aggregate texture – Binder content – Binder grade – Binder supplier
  • 20. Testing During Construction QC/QA • First four projects: – Rely on standard volumetric tests for control • Sac-5 – Repeated load triaxial and SCB or IDEAL-CT every day of production – Currently analyzing the results to see if extra information worth the time and costs – Pointing towards reduce or even eliminate performance related testing in QC/QA
  • 21. 21 What do LLP PRS Specifications do to Mix Designs? Sac-5 examples
  • 22. 22 y = 5E+22x-6.078 y = 3E+18x-5.074 y = 2E+18x-4.863 y = 2E+29x-8.421 y = 8E+24x-7.468 y = 1E+13x-2.83 100 1,000 10,000 100,000 1,000,000 10,000,000 100 1000 Fatigue Life (Cycles) Peak-to-peak strain (με) SML – 4PB - Wohler Curves: All Standard Materials Mixes Spec. Fatigue Cycle- High Strain Spec. Fatigue Cycle- Low Strain Plant-Mix 18-NB-Surf. (R15, PG64-28PM) Plant-Mix 20-NB-Int. (R22, PG64-16) Plant-Mix 17-NB-R.B. (R15, PG64-16) Plant-Mix 19-SB-Surf. (R15, PG64-28PM) Plant-Mix 21-SB-Int. (R25, PG64-16) Plant-Mix 16-SB-R.B. (R15, PG64-16)
  • 24. 24 2021 Volumetric Test Results (QC) Lift Mix ID AC%, TMM Std Dev. #200 Std Dev. Va @ Ndesign Std Dev. VMA Std Dev. DP Std Dev. SPGR Std Dev. (desc.) (desc.) (%) (%) (%) (%) (%) (%) (%) (%) (#) (#) (#) (#) Surface 352-Mix18-TeB-Srf 5.32 0.13 5.6 0.8 0.7 0.3 11.7 0.3 1.01 0.09 2.532 0.009 Surface 352-Mix19-GrD-Srf 5.23 0.13 4.9 0.2 1.3 0.4 11.9 0.4 0.93 0.05 2.555 0.008 Intermediate 352-Mix14-TeB-Int 5.27 0.07 5.1 1.0 1.8 0.7 13.9 0.5 0.96 0.20 2.532 0.007 Intermediate 352-Mix20-TeD-Int 5.16 0.14 4.4 0.7 2.9 0.7 14.0 0.6 0.86 0.12 2.539 0.009 Intermediate 352-Mix21-GrD-Int 5.22 0.13 4.5 0.3 2.4 0.7 12.7 0.7 0.90 0.20 2.556 0.008 Rich Bottom 352-Mix16-Grd-RcB 5.50 0.08 6.1 0.3 0.7 0.3 12.2 0.6 1.11 0.06 2.549 0.006 Rich Bottom 352-Mix17-TeD-RcB 5.29 0.29 5.0 0.6 3.9 2.0 15.0 1.3 0.94 0.12 2.541 0.017 Average 5.28 0.14 5.1 0.6 1.9 0.7 13.0 0.6 0.96 0.12 2.544 0.009 Result: very compactable mixes (good pay factors); improved durability (fatigue, moisture); good rutting resistance
  • 25. 25 • Use plant mix performance test results from state-wide material library to set specification requirements • Communicate aggregate property, asphalt binder, handling, and volumetric differences to optimize the fatigue beam testing; update Mix Design Guidance • Pre-qualification of mixes to reduce contractor risk in bidding • Develop a quick test for binder fatigue and stiffness properties so mix producers can choose to maximum fatigue performance Some Sac-5 Preliminary Takeaways and Recommendations for Improvement of Specification
  • 26. 26 • Control aging from sampling through testing; new draft Caltrans protocol under development (beyond AASHTO R-30) • Make testing faster, simpler, less costly, better results: • Fatigue beam compaction, updated rutting test • Determine appropriate amount of performance testing for QC/QA • Allow more pathways for producers to achieve PRS Some Sac-5 Preliminary Takeaways and Recommendations for Improvement of Specification
  • 27. 27 • Get more laboratories on-line and verified that able to do flexural beam tests • UCPRC currently working with CSU-Chico (have equipment) • Others? • Better accounting of performance related test variability • Training and round robins to build trust in tests • Communicate success! (Sac-5 contractors’ suggestion) • Recycling, economics and sustainability Some Sac-5 Preliminary Takeaways and Recommendations for Improvement of Specification
  • 28. How are they doing? Project Name Year EA Description PM LA710-Long Beach 2001-2004 07-1384U CSOL, and reconstruction under bridges 6.8-9.8 TEH5-Red Bluff 2012-2013 02-3E810 HMA lane replacement and HMA thick overlay 31.8-35.1NB and 37.1-41.6 SIS5-Weed 2011-2013 02-3E750 CSOL and HMA thick overlay R19.1-R25.2 SOL80-Dixon 2013-2014 04-4A010 CSOL and slab replacement 30.6-38.7 SAC5- Sacramento 2021-2022 CSOL and new HMA lane various over 19 miles
  • 29. LA-710, mostly 20 years old • IRI pre- construction: – 150 to 200 in/mile • At construction: – 60 to 100 • 2022: – 60 to 100 – Some increase in Lane 1
  • 30. LA-710, mostly 20 years old • Cracking: – No cracking – Small increase in 2015 survey – May be a problem with APCS that year
  • 31. LA-710, mostly 20 years old • Rutting: – Less than ¼ inch (6 mm) • Replacement of RHMA-O in 2015
  • 32.
  • 33.
  • 34. Tehama-5 2 to 7 years old: Aging, Air-voids, Binder Content
  • 35. Other projects • No maintenance treatments • Little change in as-built IRI • No cracking – Except up to 15% in one lane on Sis-5 in last 5 years • Rutting less than ¼ inch February 2023 California Transportation Commission Meeting: NAPA Awards to Caltrans District 3, Contractors, UCPRC for AC Long Life projects
  • 36. Thanks to all Caltrans, contractor and UCPRC people involved in these projects www.ucprc.ucdavis.edu www.ucprc.ucdavis.edu/ccpic