SlideShare a Scribd company logo
1 of 37
INNOVATIVE SOLUTIONS FOR
MARGINAL FACILITIES
Brady Parmenter
Facilities Engineering Intern
Midland Basin (Central)
Midland ClayDesta Office
Saturday, August 22, 2015
• Bio
– From Glennallen, Alaska
• Education
– University of Tulsa
– Mechanical Engineering
– Expected Graduation May 2017
• Prior Experience
– Geothermal drill-hand, Goldsby Oklahoma
– Maintenance Tech, Kuparuk Alaska
2
Introduction
• Project Scope
• Trial Site
• Possible options
• Economic Analysis
• Universal Applications
• Summary & Future Work
3
Outline
• Hundreds of low producing tank batteries in the Permian Basin
• $500,000 replacing pressure vessels in Midland Basin in two years
• Much of operating equipment has passed its designed life
• What options are available when the separator fails?
• Compare these options
– Technically
– Environmentally
– Economically
• Under what criteria should each option be used?
• Design a universal tool using the results of this study
4
Project Scope
• Cummins Lease
– Cummins M tank battery
• Two wells
• Facility Production Rates
– 4 BOPD
– 52 Mcf/D Gas
• Equipment
– (1) Vertical Separator
– (1) Vertical Heater Treater not in service
– (2) 500 bbl Steel Oil Tanks
– (1) 300 bbl Fiberglass Water Tank
5
Trial Site
• Vertical separator has exceeded its design life
– Identification has rusted away
– Operating pressure of 20 psig
6
Vertical Separator
• (2) 500 bbl Steel Oil tanks
• (1) 300 bbl Fiberglass Water tank
7
Tanks
Options bypassing separator
1. Produce to tanks and vent
2. Produce to tanks + VRU
3. Produce directly to compressor unit
Options Using Separators
4. Replace Separator
5. Compressor unit with a separator
8
What to Do When the Separator Fails
9
And This Happened An Hour Ago
• Reduction of wellhead surface pressure (Casing Pressure)
• Using differential pressures, can estimate % increase in production
Theoretical Site
• 15 BOPD, 30 mcf/D Gas
• Surface pressure of 50 psig
• Pump intake pressure of 500 psig
• Can drop surface pressure from 50 psig to 20 psig
• Potential increase of 6.7%
• About $20,000 more per year!
10
Potential Production Increase
𝑄 𝑖
𝑃−𝑃 𝑖
=
𝑄 𝑓
𝑃−𝑃 𝑓
• Pro’s
– Inexpensive to keep battery producing oil
• $13M total cost
– Easy to pipe up
– Zero added maintenance
– Potential production increase
• Con’s
– Lose gas sales
– Environmental/Safety concerns
• Site by site basis especially for this option
11
1. Produce to Tanks + Vent
• Pro’s
– Under current EPA (QuadO)
requirements
– Maintain gas sales
– Possibility of increased production
• Con’s
– High initial capital
• $40M for just the unit
– More OPEX
– May need to run electrical lines
– Need good tanks on site
12
2. Produce to Tanks + VRU
• Pro’s
– Very easy to pipe up
– Possible production increase
– Equipped with all valves needed
– Good for handling low fluid flow rates
• Con’s
– Only handle about 30 BFD
– Need electricity on pad
– If unit goes down, wells need shut in
– Can’t handle much H2S
– Rental or high initial capital
• Rental $1.7M per month
• Purchase $38M
13
3. Produce Directly to Compressor Unit
• Pro’s
– Keep gas sales
– Small separators are inexpensive
• $4M-$20M
• Con’s
– No increase in production
– Holding backpressure on wells
– Valve maintenance
14
4. Replace Separator
• Pro’s
– Potential production increase
– More protection from down time
– Can handle much greater than 30 BFD
– Universal application to wide range of sites
• Con’s
– Can’t handle much H2S
– May need to run electrical line
15
5. Replace Separator + Compressor Unit
Compare Options
• Initial capital
• Return on investment
– Income per year over the initial capital expressed as a percentage
• Payback period
– How fast the cost of the initial capital can be recovered
• Net Present Value (15%)
– The net value of the project after a period of time expressed with the present
value of money
*Use on Cummins M site, assuming zero production when separator fails
16
Economic Analysis
17
Production Rates
41%
59%
Yearly Revenue
Gas
Oil
Cummins M
Production Rates
for Facility
Maintenance Capital
Cost Estimate
8/22/2015
Quantity/ Year Price Units Total Yearly Sales
Gas 52 Mcf/d 18980 $3.00 $/Mcf $56,940
Oil 4 BOPD 1460 $55.00 $/bbl $80,300
Gas %sales = 41.49%
of total sales
SUM = $137,240
Oil %sales = 58.51%
Production Inrease
Due to Decreased
Surface Pressure =
Production Increase Sales Increase per Year
1.10% $1,510
18
Initial Total Capital
$14M
$115M
$49M
$22M
$66M
$0
$20
$40
$60
$80
$100
$120
$140
1.) Produce to
Tanks + Vent
2.) Produce to
Tanks + VRU
3.) Produce to
Compressor Unit
4.) Replacement 5.) Compressor
Unit + Separator
THOUSANDS(M)
Initial Capital
19
Return On Investment
600%
120%
260%
630%
190%
0%
100%
200%
300%
400%
500%
600%
700%
1.) Produce to
Tanks + Vent
2.) Produce to
Tanks + VRU
3.) Produce to
Compressor Unit
4.) Replacement 5.) Compressor
Unit + Separator
ROI Analysis
20
Payback Period
2
10
5
2
6
0
2
4
6
8
10
12
1.) Produce to
Tanks + Vent
2.) Produce to
Tanks + VRU
3.) Produce to
Compressor Unit
4.) Replacement 5.) Compressor
Unit + Separator
Months
PBP Analysis
21
Net Present Value (15%)
$170M
$190M
$240M
$290M
$210M
$260M
$330M
$370M
$430M
$350M
$390M
$550M
$580M
$660M
$550M
$0
$100
$200
$300
$400
$500
$600
$700
1.) Produce to
Tanks + Vent
2.) Produce to
Tanks + VRU
3.) Produce to
Compressor Unit
4.) Replacement 5.) Compressor
Unit + Separator
Thousands(M)
NPV15
3 Year 5 Year 10 Year
• Gas is equivalent to 42% of total sales
– Need to keep gas sales
• Minimal production increase at this site
– Very low surface pressure to begin with
– High PIP for these wells
• Most of initial capital is electrical
– If electricity is on pad, initial capital is drastically reduced
• VRU is not economic if site is already below QuadO emission limits
• Recommendation for this site: Replace Separator
22
Cummins M Conclusions
Environmental
•EPA (QuadO) VOC emissions
• 6 tons/year
Economic
•Yearly sales increase
•Initial costs
• Equipment
• Electrical
• Tank Replacements
Technical
•Gas Oil Ratio
•H2S content
•Barrels of Fluid
•Number of tanks
•Tank Condition
23
Universal Applications
• Develop universal criteria
• Create computer code to step through procedure
based on these criteria
• Flowchart gives visual step through of
procedure
• Validates computer program
• Allows double check of all options
• Determines best options based on specific inputs
24
Facility Inputs
• Find information in LOWIS
• Gives estimated sales increase
25
Well Inputs
26
Outputs
• Found options to deal with separator failures at marginal batteries
– Initial cost savings
– Potential increases in production
• Developed criteria to compare options
– Economic
– Environmental
– Technical
• Created templates to easily analyze specific sites
– Field Sheet/Inputs
– Outputs
27
Summary
• 5 sites next year that have separator/HT fail
• Previous cost of replacing averaged about $40,000
• $200,000 total spent on 5 sites
– Replacing exactly what is there now
• Using this study
– (2) need replacements
• Get small inexpensive separator instead of just replacing
• $30,000 a piece for those 2 sites
– (2) we can just produce to tanks and vent
• About $15,000 a piece and less maintenance costs
• Low pressures on site so no production increase
– (1) we can produce directly to compressor unit ($50,000 total)
• Get a 10% increase in production at this site
• Saved $60,000 and increased a site’s production by 10%
28
Example
• Apply this study to the hundreds of low producing tank
batteries in the Permian Basin
– Lead to major initial cost savings
– Increases in production
– Bring old sites under current environmental regulations
– Extend the economic feasibility of sites
29
Future Work
Mentor: Colyn Jurek
Manager: Del Oliver
Stephanie Arriola
Brandon Merrill
Walter Fults
Kyle Richter
Jennifer James
Brent Corwin
Eric Wooten
Joshua West
Corey Payne
Larry Sammons
30
Acknowledgements
Questions?
THANK YOU
• Arnold, Ken, and Maurice Stewart. "4/Two-Phase Oil and Gas
Separation, 5/Three-Phase Oil an Gas Separation." Surface Production
Operations. Amsterdam: Elsevier, 2008. 150-310. Print.
• El-Halwagi, Mahmoud M. "2/Overview of Process Economics."
Sustainable Design Through Process Integration. Amsterdam: Elsevier,
2012. 15-62. Print.
• Huvard, Gary S., Richard M. Felder, and Ronald W. Rousseau.
Elementary Principles of Chemical Processes. New York: Wiley, 2005.
Print.
• OXY Petroleum Inc., Oil and Gas Exploration and Production. A Guide
for Selecting Production Equipment. Tulsa: Crest Engineering, 1983.
Print.
33
References
• LOW PRODUCING BATTERY TOOL.xlsm
• Procedure Flowchart.xlsx
34
Tools
35
Production vs. Pump Intake Pressure
36
Production Increase Graph
14.50
15.00
15.50
16.00
16.50
17.00
17.50
18.00
18.50
0 200 400 600 800 1000 1200
BOPD
Pumping Pressure (psi)
New Oil Production vs. Pumping Pressure
New Oil Production
Original Oil Production
• Pro’s
– Under environmental regulations
• Con’s
– Lose gas sales
– More expensive than tiny separator
– Needs backpressure to operate
*Operationally will not work
37
Produce to Tanks + VCU

More Related Content

What's hot

Velocys ppt141028_Gasification_Technologies_Council
Velocys ppt141028_Gasification_Technologies_CouncilVelocys ppt141028_Gasification_Technologies_Council
Velocys ppt141028_Gasification_Technologies_CouncilJohn Glenning
 
Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014John Glenning
 
Velocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumVelocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumJohn Glenning
 
Fuel Flexibility - a techno-economic review
Fuel Flexibility - a techno-economic reviewFuel Flexibility - a techno-economic review
Fuel Flexibility - a techno-economic reviewShaun West
 
Ground-Up Re-Engineering of the New CleanCNG™ Compressor
Ground-Up Re-Engineering of the New CleanCNG™ CompressorGround-Up Re-Engineering of the New CleanCNG™ Compressor
Ground-Up Re-Engineering of the New CleanCNG™ CompressorPath Marketing Inc.
 
GAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
GAS-TO-POWER via Throttle Energy's Virtual Pipeline TechnologyGAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
GAS-TO-POWER via Throttle Energy's Virtual Pipeline TechnologyKolawole E. Akinmuyiwa
 
Natural Gas Roundtable - City of Janesville Presentation
Natural Gas Roundtable - City of Janesville PresentationNatural Gas Roundtable - City of Janesville Presentation
Natural Gas Roundtable - City of Janesville PresentationWisconsin Clean Cities
 
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Marcellus Drilling News
 
Cem 350 gilbane corp mep retrofit systems overview 4 2011
Cem 350 gilbane corp mep retrofit systems overview  4 2011Cem 350 gilbane corp mep retrofit systems overview  4 2011
Cem 350 gilbane corp mep retrofit systems overview 4 2011miresmaeil
 

What's hot (20)

Recommend pract cng_
Recommend pract cng_Recommend pract cng_
Recommend pract cng_
 
A Compelling Case for Natural Gas Vehicles
A Compelling Case for Natural Gas VehiclesA Compelling Case for Natural Gas Vehicles
A Compelling Case for Natural Gas Vehicles
 
Velocys ppt141028_Gasification_Technologies_Council
Velocys ppt141028_Gasification_Technologies_CouncilVelocys ppt141028_Gasification_Technologies_Council
Velocys ppt141028_Gasification_Technologies_Council
 
OffgridCNG Virtual Pipeline Equipment
OffgridCNG Virtual Pipeline EquipmentOffgridCNG Virtual Pipeline Equipment
OffgridCNG Virtual Pipeline Equipment
 
Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014
 
Velocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumVelocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology Forum
 
Virtual pipelines 201: Industrial CNG Applications Beyond the Pipeline
Virtual pipelines 201: Industrial CNG Applications Beyond the PipelineVirtual pipelines 201: Industrial CNG Applications Beyond the Pipeline
Virtual pipelines 201: Industrial CNG Applications Beyond the Pipeline
 
CompleteCNG - Clean Energy Compression’s CompleteCNG includes proven CleanCNG...
CompleteCNG - Clean Energy Compression’s CompleteCNG includes proven CleanCNG...CompleteCNG - Clean Energy Compression’s CompleteCNG includes proven CleanCNG...
CompleteCNG - Clean Energy Compression’s CompleteCNG includes proven CleanCNG...
 
Throttle Energy Business PPT
Throttle Energy Business PPTThrottle Energy Business PPT
Throttle Energy Business PPT
 
Clean Energy Compression Corporate overview
Clean Energy Compression Corporate overview Clean Energy Compression Corporate overview
Clean Energy Compression Corporate overview
 
Modern gas-fueled power generation
Modern gas-fueled power generationModern gas-fueled power generation
Modern gas-fueled power generation
 
Natural Gas Basics Webinar
Natural Gas Basics WebinarNatural Gas Basics Webinar
Natural Gas Basics Webinar
 
Fuel Flexibility - a techno-economic review
Fuel Flexibility - a techno-economic reviewFuel Flexibility - a techno-economic review
Fuel Flexibility - a techno-economic review
 
Ground-Up Re-Engineering of the New CleanCNG™ Compressor
Ground-Up Re-Engineering of the New CleanCNG™ CompressorGround-Up Re-Engineering of the New CleanCNG™ Compressor
Ground-Up Re-Engineering of the New CleanCNG™ Compressor
 
Use of lng
Use of lngUse of lng
Use of lng
 
GAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
GAS-TO-POWER via Throttle Energy's Virtual Pipeline TechnologyGAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
GAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
 
Natural Gas Roundtable - City of Janesville Presentation
Natural Gas Roundtable - City of Janesville PresentationNatural Gas Roundtable - City of Janesville Presentation
Natural Gas Roundtable - City of Janesville Presentation
 
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
 
Cem 350 gilbane corp mep retrofit systems overview 4 2011
Cem 350 gilbane corp mep retrofit systems overview  4 2011Cem 350 gilbane corp mep retrofit systems overview  4 2011
Cem 350 gilbane corp mep retrofit systems overview 4 2011
 
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
 

Viewers also liked

TIK BAB 4 KELAS IX
TIK BAB 4 KELAS IXTIK BAB 4 KELAS IX
TIK BAB 4 KELAS IXTamaMEN27
 
Resume_Troy Carpenter Aug 2015
Resume_Troy Carpenter Aug 2015Resume_Troy Carpenter Aug 2015
Resume_Troy Carpenter Aug 2015Troy Carpenter
 
Bab 2 TIK kelas IX smp 18 semarang
Bab 2 TIK kelas IX smp 18 semarang Bab 2 TIK kelas IX smp 18 semarang
Bab 2 TIK kelas IX smp 18 semarang TamaMEN27
 
TIK BAB 6 KELAS IX
TIK BAB 6 KELAS IXTIK BAB 6 KELAS IX
TIK BAB 6 KELAS IXTamaMEN27
 
Bab 1 TIK kelas IX smp 18 semarang
Bab 1 TIK kelas IX smp 18 semarang Bab 1 TIK kelas IX smp 18 semarang
Bab 1 TIK kelas IX smp 18 semarang TamaMEN27
 
Resume_Troy Carpenter Aug 2015
Resume_Troy Carpenter Aug 2015Resume_Troy Carpenter Aug 2015
Resume_Troy Carpenter Aug 2015Troy Carpenter
 
Will_4-13-15_GroupMtng_Final
Will_4-13-15_GroupMtng_FinalWill_4-13-15_GroupMtng_Final
Will_4-13-15_GroupMtng_FinalWilliam Daggett
 

Viewers also liked (12)

TIK BAB 4 KELAS IX
TIK BAB 4 KELAS IXTIK BAB 4 KELAS IX
TIK BAB 4 KELAS IX
 
TIK BAB 3
TIK BAB 3 TIK BAB 3
TIK BAB 3
 
La escuela no es una empresa. laval
La escuela no es una empresa. lavalLa escuela no es una empresa. laval
La escuela no es una empresa. laval
 
Resume_Troy Carpenter Aug 2015
Resume_Troy Carpenter Aug 2015Resume_Troy Carpenter Aug 2015
Resume_Troy Carpenter Aug 2015
 
Bab 2 TIK kelas IX smp 18 semarang
Bab 2 TIK kelas IX smp 18 semarang Bab 2 TIK kelas IX smp 18 semarang
Bab 2 TIK kelas IX smp 18 semarang
 
Source Nov 2014
Source Nov 2014Source Nov 2014
Source Nov 2014
 
CV Fikri
CV FikriCV Fikri
CV Fikri
 
TIK BAB 6 KELAS IX
TIK BAB 6 KELAS IXTIK BAB 6 KELAS IX
TIK BAB 6 KELAS IX
 
Bab 1 TIK kelas IX smp 18 semarang
Bab 1 TIK kelas IX smp 18 semarang Bab 1 TIK kelas IX smp 18 semarang
Bab 1 TIK kelas IX smp 18 semarang
 
Resume_Troy Carpenter Aug 2015
Resume_Troy Carpenter Aug 2015Resume_Troy Carpenter Aug 2015
Resume_Troy Carpenter Aug 2015
 
Will_4-13-15_GroupMtng_Final
Will_4-13-15_GroupMtng_FinalWill_4-13-15_GroupMtng_Final
Will_4-13-15_GroupMtng_Final
 
CV
CVCV
CV
 

Similar to Parmenter, Brady, Presentation

Parmenter, Brady, Poster
Parmenter, Brady, PosterParmenter, Brady, Poster
Parmenter, Brady, PosterBrady Parmenter
 
Power-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion PaperPower-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion PaperBowen
 
Costs of capturing CO2 from industrial sources - Morgan Summers, National Ene...
Costs of capturing CO2 from industrial sources - Morgan Summers, National Ene...Costs of capturing CO2 from industrial sources - Morgan Summers, National Ene...
Costs of capturing CO2 from industrial sources - Morgan Summers, National Ene...Global CCS Institute
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsGerard B. Hawkins
 
Artificial-Lift-System-N production engineering.pdf
Artificial-Lift-System-N production engineering.pdfArtificial-Lift-System-N production engineering.pdf
Artificial-Lift-System-N production engineering.pdfIsmailKatun1
 
Apec workshop 2 presentation 6 1 compression and transport apec
Apec workshop 2 presentation 6 1  compression and transport apecApec workshop 2 presentation 6 1  compression and transport apec
Apec workshop 2 presentation 6 1 compression and transport apecGlobal CCS Institute
 
2023 CalAPA Spring Conference presentation by Astec on the plant of the future
2023 CalAPA Spring Conference presentation by Astec on the plant of the future2023 CalAPA Spring Conference presentation by Astec on the plant of the future
2023 CalAPA Spring Conference presentation by Astec on the plant of the futureCalifornia Asphalt Pavement Association
 
Marcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten
 
Gte company presentation
Gte company presentationGte company presentation
Gte company presentation동훈 이
 
Overview of Current Directions in Carbon Capture R&D
Overview of Current Directions in Carbon Capture R&DOverview of Current Directions in Carbon Capture R&D
Overview of Current Directions in Carbon Capture R&DGlobal CCS Institute
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...Manohar Tatwawadi
 
Enhancing Refinery Profitability
Enhancing Refinery ProfitabilityEnhancing Refinery Profitability
Enhancing Refinery Profitabilitypipllp
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALSiFluids Engineering
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALSiFluids Engineering
 
Humidification Retrofits Deliver Residential Furnace Efficiency
Humidification Retrofits Deliver Residential Furnace EfficiencyHumidification Retrofits Deliver Residential Furnace Efficiency
Humidification Retrofits Deliver Residential Furnace EfficiencyCenter for Energy and Environment
 
Reducing your carbon footprint (Senior Project - Mexico)
Reducing your carbon footprint (Senior Project - Mexico)Reducing your carbon footprint (Senior Project - Mexico)
Reducing your carbon footprint (Senior Project - Mexico)asauter93
 
Highlights of the Kuwait HVAC&R Conference 2017
Highlights of the Kuwait HVAC&R Conference 2017Highlights of the Kuwait HVAC&R Conference 2017
Highlights of the Kuwait HVAC&R Conference 2017Swati Warang
 

Similar to Parmenter, Brady, Presentation (20)

Parmenter, Brady, Poster
Parmenter, Brady, PosterParmenter, Brady, Poster
Parmenter, Brady, Poster
 
Power-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion PaperPower-Gen 2016 Coal to Gas Conversion Paper
Power-Gen 2016 Coal to Gas Conversion Paper
 
Costs of capturing CO2 from industrial sources - Morgan Summers, National Ene...
Costs of capturing CO2 from industrial sources - Morgan Summers, National Ene...Costs of capturing CO2 from industrial sources - Morgan Summers, National Ene...
Costs of capturing CO2 from industrial sources - Morgan Summers, National Ene...
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen Plants
 
Optimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy EfficiencyOptimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy Efficiency
 
Artificial-Lift-System-N production engineering.pdf
Artificial-Lift-System-N production engineering.pdfArtificial-Lift-System-N production engineering.pdf
Artificial-Lift-System-N production engineering.pdf
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
Apec workshop 2 presentation 6 1 compression and transport apec
Apec workshop 2 presentation 6 1  compression and transport apecApec workshop 2 presentation 6 1  compression and transport apec
Apec workshop 2 presentation 6 1 compression and transport apec
 
2023 CalAPA Spring Conference presentation by Astec on the plant of the future
2023 CalAPA Spring Conference presentation by Astec on the plant of the future2023 CalAPA Spring Conference presentation by Astec on the plant of the future
2023 CalAPA Spring Conference presentation by Astec on the plant of the future
 
Marcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept Engineer
 
Gte company presentation
Gte company presentationGte company presentation
Gte company presentation
 
Overview of Current Directions in Carbon Capture R&D
Overview of Current Directions in Carbon Capture R&DOverview of Current Directions in Carbon Capture R&D
Overview of Current Directions in Carbon Capture R&D
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
 
Enhancing Refinery Profitability
Enhancing Refinery ProfitabilityEnhancing Refinery Profitability
Enhancing Refinery Profitability
 
Hy bgc presentation for 2017 swpsc
Hy bgc presentation for 2017 swpscHy bgc presentation for 2017 swpsc
Hy bgc presentation for 2017 swpsc
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALS
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALS
 
Humidification Retrofits Deliver Residential Furnace Efficiency
Humidification Retrofits Deliver Residential Furnace EfficiencyHumidification Retrofits Deliver Residential Furnace Efficiency
Humidification Retrofits Deliver Residential Furnace Efficiency
 
Reducing your carbon footprint (Senior Project - Mexico)
Reducing your carbon footprint (Senior Project - Mexico)Reducing your carbon footprint (Senior Project - Mexico)
Reducing your carbon footprint (Senior Project - Mexico)
 
Highlights of the Kuwait HVAC&R Conference 2017
Highlights of the Kuwait HVAC&R Conference 2017Highlights of the Kuwait HVAC&R Conference 2017
Highlights of the Kuwait HVAC&R Conference 2017
 

Parmenter, Brady, Presentation

  • 1. INNOVATIVE SOLUTIONS FOR MARGINAL FACILITIES Brady Parmenter Facilities Engineering Intern Midland Basin (Central) Midland ClayDesta Office Saturday, August 22, 2015
  • 2. • Bio – From Glennallen, Alaska • Education – University of Tulsa – Mechanical Engineering – Expected Graduation May 2017 • Prior Experience – Geothermal drill-hand, Goldsby Oklahoma – Maintenance Tech, Kuparuk Alaska 2 Introduction
  • 3. • Project Scope • Trial Site • Possible options • Economic Analysis • Universal Applications • Summary & Future Work 3 Outline
  • 4. • Hundreds of low producing tank batteries in the Permian Basin • $500,000 replacing pressure vessels in Midland Basin in two years • Much of operating equipment has passed its designed life • What options are available when the separator fails? • Compare these options – Technically – Environmentally – Economically • Under what criteria should each option be used? • Design a universal tool using the results of this study 4 Project Scope
  • 5. • Cummins Lease – Cummins M tank battery • Two wells • Facility Production Rates – 4 BOPD – 52 Mcf/D Gas • Equipment – (1) Vertical Separator – (1) Vertical Heater Treater not in service – (2) 500 bbl Steel Oil Tanks – (1) 300 bbl Fiberglass Water Tank 5 Trial Site
  • 6. • Vertical separator has exceeded its design life – Identification has rusted away – Operating pressure of 20 psig 6 Vertical Separator
  • 7. • (2) 500 bbl Steel Oil tanks • (1) 300 bbl Fiberglass Water tank 7 Tanks
  • 8. Options bypassing separator 1. Produce to tanks and vent 2. Produce to tanks + VRU 3. Produce directly to compressor unit Options Using Separators 4. Replace Separator 5. Compressor unit with a separator 8 What to Do When the Separator Fails
  • 9. 9 And This Happened An Hour Ago
  • 10. • Reduction of wellhead surface pressure (Casing Pressure) • Using differential pressures, can estimate % increase in production Theoretical Site • 15 BOPD, 30 mcf/D Gas • Surface pressure of 50 psig • Pump intake pressure of 500 psig • Can drop surface pressure from 50 psig to 20 psig • Potential increase of 6.7% • About $20,000 more per year! 10 Potential Production Increase 𝑄 𝑖 𝑃−𝑃 𝑖 = 𝑄 𝑓 𝑃−𝑃 𝑓
  • 11. • Pro’s – Inexpensive to keep battery producing oil • $13M total cost – Easy to pipe up – Zero added maintenance – Potential production increase • Con’s – Lose gas sales – Environmental/Safety concerns • Site by site basis especially for this option 11 1. Produce to Tanks + Vent
  • 12. • Pro’s – Under current EPA (QuadO) requirements – Maintain gas sales – Possibility of increased production • Con’s – High initial capital • $40M for just the unit – More OPEX – May need to run electrical lines – Need good tanks on site 12 2. Produce to Tanks + VRU
  • 13. • Pro’s – Very easy to pipe up – Possible production increase – Equipped with all valves needed – Good for handling low fluid flow rates • Con’s – Only handle about 30 BFD – Need electricity on pad – If unit goes down, wells need shut in – Can’t handle much H2S – Rental or high initial capital • Rental $1.7M per month • Purchase $38M 13 3. Produce Directly to Compressor Unit
  • 14. • Pro’s – Keep gas sales – Small separators are inexpensive • $4M-$20M • Con’s – No increase in production – Holding backpressure on wells – Valve maintenance 14 4. Replace Separator
  • 15. • Pro’s – Potential production increase – More protection from down time – Can handle much greater than 30 BFD – Universal application to wide range of sites • Con’s – Can’t handle much H2S – May need to run electrical line 15 5. Replace Separator + Compressor Unit
  • 16. Compare Options • Initial capital • Return on investment – Income per year over the initial capital expressed as a percentage • Payback period – How fast the cost of the initial capital can be recovered • Net Present Value (15%) – The net value of the project after a period of time expressed with the present value of money *Use on Cummins M site, assuming zero production when separator fails 16 Economic Analysis
  • 17. 17 Production Rates 41% 59% Yearly Revenue Gas Oil Cummins M Production Rates for Facility Maintenance Capital Cost Estimate 8/22/2015 Quantity/ Year Price Units Total Yearly Sales Gas 52 Mcf/d 18980 $3.00 $/Mcf $56,940 Oil 4 BOPD 1460 $55.00 $/bbl $80,300 Gas %sales = 41.49% of total sales SUM = $137,240 Oil %sales = 58.51% Production Inrease Due to Decreased Surface Pressure = Production Increase Sales Increase per Year 1.10% $1,510
  • 18. 18 Initial Total Capital $14M $115M $49M $22M $66M $0 $20 $40 $60 $80 $100 $120 $140 1.) Produce to Tanks + Vent 2.) Produce to Tanks + VRU 3.) Produce to Compressor Unit 4.) Replacement 5.) Compressor Unit + Separator THOUSANDS(M) Initial Capital
  • 19. 19 Return On Investment 600% 120% 260% 630% 190% 0% 100% 200% 300% 400% 500% 600% 700% 1.) Produce to Tanks + Vent 2.) Produce to Tanks + VRU 3.) Produce to Compressor Unit 4.) Replacement 5.) Compressor Unit + Separator ROI Analysis
  • 20. 20 Payback Period 2 10 5 2 6 0 2 4 6 8 10 12 1.) Produce to Tanks + Vent 2.) Produce to Tanks + VRU 3.) Produce to Compressor Unit 4.) Replacement 5.) Compressor Unit + Separator Months PBP Analysis
  • 21. 21 Net Present Value (15%) $170M $190M $240M $290M $210M $260M $330M $370M $430M $350M $390M $550M $580M $660M $550M $0 $100 $200 $300 $400 $500 $600 $700 1.) Produce to Tanks + Vent 2.) Produce to Tanks + VRU 3.) Produce to Compressor Unit 4.) Replacement 5.) Compressor Unit + Separator Thousands(M) NPV15 3 Year 5 Year 10 Year
  • 22. • Gas is equivalent to 42% of total sales – Need to keep gas sales • Minimal production increase at this site – Very low surface pressure to begin with – High PIP for these wells • Most of initial capital is electrical – If electricity is on pad, initial capital is drastically reduced • VRU is not economic if site is already below QuadO emission limits • Recommendation for this site: Replace Separator 22 Cummins M Conclusions
  • 23. Environmental •EPA (QuadO) VOC emissions • 6 tons/year Economic •Yearly sales increase •Initial costs • Equipment • Electrical • Tank Replacements Technical •Gas Oil Ratio •H2S content •Barrels of Fluid •Number of tanks •Tank Condition 23 Universal Applications • Develop universal criteria • Create computer code to step through procedure based on these criteria • Flowchart gives visual step through of procedure • Validates computer program • Allows double check of all options • Determines best options based on specific inputs
  • 25. • Find information in LOWIS • Gives estimated sales increase 25 Well Inputs
  • 27. • Found options to deal with separator failures at marginal batteries – Initial cost savings – Potential increases in production • Developed criteria to compare options – Economic – Environmental – Technical • Created templates to easily analyze specific sites – Field Sheet/Inputs – Outputs 27 Summary
  • 28. • 5 sites next year that have separator/HT fail • Previous cost of replacing averaged about $40,000 • $200,000 total spent on 5 sites – Replacing exactly what is there now • Using this study – (2) need replacements • Get small inexpensive separator instead of just replacing • $30,000 a piece for those 2 sites – (2) we can just produce to tanks and vent • About $15,000 a piece and less maintenance costs • Low pressures on site so no production increase – (1) we can produce directly to compressor unit ($50,000 total) • Get a 10% increase in production at this site • Saved $60,000 and increased a site’s production by 10% 28 Example
  • 29. • Apply this study to the hundreds of low producing tank batteries in the Permian Basin – Lead to major initial cost savings – Increases in production – Bring old sites under current environmental regulations – Extend the economic feasibility of sites 29 Future Work
  • 30. Mentor: Colyn Jurek Manager: Del Oliver Stephanie Arriola Brandon Merrill Walter Fults Kyle Richter Jennifer James Brent Corwin Eric Wooten Joshua West Corey Payne Larry Sammons 30 Acknowledgements
  • 33. • Arnold, Ken, and Maurice Stewart. "4/Two-Phase Oil and Gas Separation, 5/Three-Phase Oil an Gas Separation." Surface Production Operations. Amsterdam: Elsevier, 2008. 150-310. Print. • El-Halwagi, Mahmoud M. "2/Overview of Process Economics." Sustainable Design Through Process Integration. Amsterdam: Elsevier, 2012. 15-62. Print. • Huvard, Gary S., Richard M. Felder, and Ronald W. Rousseau. Elementary Principles of Chemical Processes. New York: Wiley, 2005. Print. • OXY Petroleum Inc., Oil and Gas Exploration and Production. A Guide for Selecting Production Equipment. Tulsa: Crest Engineering, 1983. Print. 33 References
  • 34. • LOW PRODUCING BATTERY TOOL.xlsm • Procedure Flowchart.xlsx 34 Tools
  • 35. 35 Production vs. Pump Intake Pressure
  • 36. 36 Production Increase Graph 14.50 15.00 15.50 16.00 16.50 17.00 17.50 18.00 18.50 0 200 400 600 800 1000 1200 BOPD Pumping Pressure (psi) New Oil Production vs. Pumping Pressure New Oil Production Original Oil Production
  • 37. • Pro’s – Under environmental regulations • Con’s – Lose gas sales – More expensive than tiny separator – Needs backpressure to operate *Operationally will not work 37 Produce to Tanks + VCU

Editor's Notes

  1. Introduce self briefly Explain prior experience in detail
  2. Quickly go over outline. Don’t explain anything yet
  3. Spend awhile on here explaining project. Mention cost savings a lot, production increases
  4. Briefly tell about Cummins Lease and why it is a good candidate for this study
  5. This is the reason looking at Cummins Lease. Lots of sites that look just like this
  6. Mention just how old site is
  7. Emphasize that the usual is to just replace the separator
  8. Really say that this is a super rough estimate and if deciding that the production increase may be significant, a production engineer should be contacted to get more accurate numbers
  9. Contact environmental for case by case basis if this looks like the best option for a specific site
  10. Emphasize the technical issues this causes as well as the costs involved to make this work
  11. Describe how they operate and how it is different from a VRU
  12. Emphasize the NO GAIN fact
  13. Spend detail describing how this option is more universal and that it also achieves the desired production increase
  14. Tell that all based off of assuming that without implementing the option, the battery would not be producing. Not incremental from a base model.
  15. Show that at this site gas is a major part of the sales. And point out 1% production increase
  16. Describe electricity costs and tank replacements
  17. All pretty good. Some just better than others
  18. All paid back pretty quickly
  19. Say that the outlook for some sites may be different. Low producers may only be around for another few years
  20. Explain that tank replacements and electricity costs make VRU option not as favorable.
  21. Describe that this can easily be taken to the field to get all the information needed. Need to obtain oil and gas analysis
  22. Can find all information on LOWIS
  23. Gives automated output based on criteria above. Gives best options because there may be certain criteria at sites that prevent options from working
  24. Emphasize the cost savings and potential increases in production
  25. Can potentially impact non low producing sites as well