The document evaluates innovative solutions for low producing oil and gas facilities when separation equipment fails, analyzing options such as bypassing the separator, replacing it, or using a compressor unit; it develops universal criteria to analyze technical, economic and environmental factors to determine the best solution and estimates $60,000 in savings by avoiding full replacements at two sites and increasing production 10% at another site.
2. • Bio
– From Glennallen, Alaska
• Education
– University of Tulsa
– Mechanical Engineering
– Expected Graduation May 2017
• Prior Experience
– Geothermal drill-hand, Goldsby Oklahoma
– Maintenance Tech, Kuparuk Alaska
2
Introduction
3. • Project Scope
• Trial Site
• Possible options
• Economic Analysis
• Universal Applications
• Summary & Future Work
3
Outline
4. • Hundreds of low producing tank batteries in the Permian Basin
• $500,000 replacing pressure vessels in Midland Basin in two years
• Much of operating equipment has passed its designed life
• What options are available when the separator fails?
• Compare these options
– Technically
– Environmentally
– Economically
• Under what criteria should each option be used?
• Design a universal tool using the results of this study
4
Project Scope
5. • Cummins Lease
– Cummins M tank battery
• Two wells
• Facility Production Rates
– 4 BOPD
– 52 Mcf/D Gas
• Equipment
– (1) Vertical Separator
– (1) Vertical Heater Treater not in service
– (2) 500 bbl Steel Oil Tanks
– (1) 300 bbl Fiberglass Water Tank
5
Trial Site
6. • Vertical separator has exceeded its design life
– Identification has rusted away
– Operating pressure of 20 psig
6
Vertical Separator
7. • (2) 500 bbl Steel Oil tanks
• (1) 300 bbl Fiberglass Water tank
7
Tanks
8. Options bypassing separator
1. Produce to tanks and vent
2. Produce to tanks + VRU
3. Produce directly to compressor unit
Options Using Separators
4. Replace Separator
5. Compressor unit with a separator
8
What to Do When the Separator Fails
10. • Reduction of wellhead surface pressure (Casing Pressure)
• Using differential pressures, can estimate % increase in production
Theoretical Site
• 15 BOPD, 30 mcf/D Gas
• Surface pressure of 50 psig
• Pump intake pressure of 500 psig
• Can drop surface pressure from 50 psig to 20 psig
• Potential increase of 6.7%
• About $20,000 more per year!
10
Potential Production Increase
𝑄 𝑖
𝑃−𝑃 𝑖
=
𝑄 𝑓
𝑃−𝑃 𝑓
11. • Pro’s
– Inexpensive to keep battery producing oil
• $13M total cost
– Easy to pipe up
– Zero added maintenance
– Potential production increase
• Con’s
– Lose gas sales
– Environmental/Safety concerns
• Site by site basis especially for this option
11
1. Produce to Tanks + Vent
12. • Pro’s
– Under current EPA (QuadO)
requirements
– Maintain gas sales
– Possibility of increased production
• Con’s
– High initial capital
• $40M for just the unit
– More OPEX
– May need to run electrical lines
– Need good tanks on site
12
2. Produce to Tanks + VRU
13. • Pro’s
– Very easy to pipe up
– Possible production increase
– Equipped with all valves needed
– Good for handling low fluid flow rates
• Con’s
– Only handle about 30 BFD
– Need electricity on pad
– If unit goes down, wells need shut in
– Can’t handle much H2S
– Rental or high initial capital
• Rental $1.7M per month
• Purchase $38M
13
3. Produce Directly to Compressor Unit
14. • Pro’s
– Keep gas sales
– Small separators are inexpensive
• $4M-$20M
• Con’s
– No increase in production
– Holding backpressure on wells
– Valve maintenance
14
4. Replace Separator
15. • Pro’s
– Potential production increase
– More protection from down time
– Can handle much greater than 30 BFD
– Universal application to wide range of sites
• Con’s
– Can’t handle much H2S
– May need to run electrical line
15
5. Replace Separator + Compressor Unit
16. Compare Options
• Initial capital
• Return on investment
– Income per year over the initial capital expressed as a percentage
• Payback period
– How fast the cost of the initial capital can be recovered
• Net Present Value (15%)
– The net value of the project after a period of time expressed with the present
value of money
*Use on Cummins M site, assuming zero production when separator fails
16
Economic Analysis
17. 17
Production Rates
41%
59%
Yearly Revenue
Gas
Oil
Cummins M
Production Rates
for Facility
Maintenance Capital
Cost Estimate
8/22/2015
Quantity/ Year Price Units Total Yearly Sales
Gas 52 Mcf/d 18980 $3.00 $/Mcf $56,940
Oil 4 BOPD 1460 $55.00 $/bbl $80,300
Gas %sales = 41.49%
of total sales
SUM = $137,240
Oil %sales = 58.51%
Production Inrease
Due to Decreased
Surface Pressure =
Production Increase Sales Increase per Year
1.10% $1,510
21. 21
Net Present Value (15%)
$170M
$190M
$240M
$290M
$210M
$260M
$330M
$370M
$430M
$350M
$390M
$550M
$580M
$660M
$550M
$0
$100
$200
$300
$400
$500
$600
$700
1.) Produce to
Tanks + Vent
2.) Produce to
Tanks + VRU
3.) Produce to
Compressor Unit
4.) Replacement 5.) Compressor
Unit + Separator
Thousands(M)
NPV15
3 Year 5 Year 10 Year
22. • Gas is equivalent to 42% of total sales
– Need to keep gas sales
• Minimal production increase at this site
– Very low surface pressure to begin with
– High PIP for these wells
• Most of initial capital is electrical
– If electricity is on pad, initial capital is drastically reduced
• VRU is not economic if site is already below QuadO emission limits
• Recommendation for this site: Replace Separator
22
Cummins M Conclusions
23. Environmental
•EPA (QuadO) VOC emissions
• 6 tons/year
Economic
•Yearly sales increase
•Initial costs
• Equipment
• Electrical
• Tank Replacements
Technical
•Gas Oil Ratio
•H2S content
•Barrels of Fluid
•Number of tanks
•Tank Condition
23
Universal Applications
• Develop universal criteria
• Create computer code to step through procedure
based on these criteria
• Flowchart gives visual step through of
procedure
• Validates computer program
• Allows double check of all options
• Determines best options based on specific inputs
27. • Found options to deal with separator failures at marginal batteries
– Initial cost savings
– Potential increases in production
• Developed criteria to compare options
– Economic
– Environmental
– Technical
• Created templates to easily analyze specific sites
– Field Sheet/Inputs
– Outputs
27
Summary
28. • 5 sites next year that have separator/HT fail
• Previous cost of replacing averaged about $40,000
• $200,000 total spent on 5 sites
– Replacing exactly what is there now
• Using this study
– (2) need replacements
• Get small inexpensive separator instead of just replacing
• $30,000 a piece for those 2 sites
– (2) we can just produce to tanks and vent
• About $15,000 a piece and less maintenance costs
• Low pressures on site so no production increase
– (1) we can produce directly to compressor unit ($50,000 total)
• Get a 10% increase in production at this site
• Saved $60,000 and increased a site’s production by 10%
28
Example
29. • Apply this study to the hundreds of low producing tank
batteries in the Permian Basin
– Lead to major initial cost savings
– Increases in production
– Bring old sites under current environmental regulations
– Extend the economic feasibility of sites
29
Future Work
30. Mentor: Colyn Jurek
Manager: Del Oliver
Stephanie Arriola
Brandon Merrill
Walter Fults
Kyle Richter
Jennifer James
Brent Corwin
Eric Wooten
Joshua West
Corey Payne
Larry Sammons
30
Acknowledgements
33. • Arnold, Ken, and Maurice Stewart. "4/Two-Phase Oil and Gas
Separation, 5/Three-Phase Oil an Gas Separation." Surface Production
Operations. Amsterdam: Elsevier, 2008. 150-310. Print.
• El-Halwagi, Mahmoud M. "2/Overview of Process Economics."
Sustainable Design Through Process Integration. Amsterdam: Elsevier,
2012. 15-62. Print.
• Huvard, Gary S., Richard M. Felder, and Ronald W. Rousseau.
Elementary Principles of Chemical Processes. New York: Wiley, 2005.
Print.
• OXY Petroleum Inc., Oil and Gas Exploration and Production. A Guide
for Selecting Production Equipment. Tulsa: Crest Engineering, 1983.
Print.
33
References
37. • Pro’s
– Under environmental regulations
• Con’s
– Lose gas sales
– More expensive than tiny separator
– Needs backpressure to operate
*Operationally will not work
37
Produce to Tanks + VCU
Editor's Notes
Introduce self briefly
Explain prior experience in detail
Quickly go over outline. Don’t explain anything yet
Spend awhile on here explaining project. Mention cost savings a lot, production increases
Briefly tell about Cummins Lease and why it is a good candidate for this study
This is the reason looking at Cummins Lease. Lots of sites that look just like this
Mention just how old site is
Emphasize that the usual is to just replace the separator
Really say that this is a super rough estimate and if deciding that the production increase may be significant, a production engineer should be contacted to get more accurate numbers
Contact environmental for case by case basis if this looks like the best option for a specific site
Emphasize the technical issues this causes as well as the costs involved to make this work
Describe how they operate and how it is different from a VRU
Emphasize the NO GAIN fact
Spend detail describing how this option is more universal and that it also achieves the desired production increase
Tell that all based off of assuming that without implementing the option, the battery would not be producing. Not incremental from a base model.
Show that at this site gas is a major part of the sales. And point out 1% production increase
Describe electricity costs and tank replacements
All pretty good. Some just better than others
All paid back pretty quickly
Say that the outlook for some sites may be different. Low producers may only be around for another few years
Explain that tank replacements and electricity costs make VRU option not as favorable.
Describe that this can easily be taken to the field to get all the information needed. Need to obtain oil and gas analysis
Can find all information on LOWIS
Gives automated output based on criteria above. Gives best options because there may be certain criteria at sites that prevent options from working
Emphasize the cost savings and potential increases in production
Can potentially impact non low producing sites as well