11. Tier IV resilience Power Cooling Mains Generator Mains Generator Change Over Change Over UPS UPS Equipment Heat Rejection Heat Rejection (N+N) (N+N) Room Units Room Units (N+N)
35. Oxy-reduct Not approved by UK building insurers or Building Regulations so other protection also required. H&S limits exposure to 6 hours per day, otherwise completely safe. Oxygen level equivalent to 2700m above sea level.
38. CS2 4.5 kVA/rack N+N Power Cooling Transformer Generator UPS MER Racks MER Room Units Changeover Heat Rejection Heat Rejection MER Room Units UPS (N+N) SER S SER N 50% traders 50% traders (N+N) Changeover Transformer Mains (N+N)
39. CS2 8kVA/rack N+1 Power Cooling Transformer Generator N+1 UPS MER Racks N+1 MER Room Units Changeover N+1 Heat Rejection SER S SER N 50% traders 50% traders Changeover Transformer Mains
40.
Editor's Notes
ENERGY COST IS LARGE PROPORTION BUILD COST – GET IT RIGHT!
Future Proofing - Optimizing Tier-IV Data Centers You are most vulnerable to what you don’t see or didn’t anticipate. FUTURE PROOFING collaboration and cross-pollination Where will it fail vs will it work? Investing in strategic planning
Future Proofing - Optimizing Tier-IV Data Centers Fault tolerance = Mean Time Between Failures MTBF MTTR = Mean time to restore Critical Infrastructure must be intuitively operable Simplicity = Reliability
Allows additional supplies and enhanced capacity N+1 INSERT PICTURES