This document outlines the work packages, activities, and schedule for a construction project. It includes:
1. A list of 25 activities with their durations for earthwork, civil works, brickwork, electrical wiring, and plaster work.
2. A network diagram linking the activities and showing dependencies and durations.
3. Tables showing the critical path, total floats, and free floats.
4. A milestone chart listing information requirements and the ordering of major items with start and end dates.
5. A resource sheet listing the resource needs for each activity.
6. A table showing how crashing some activities by 2-10 days could reduce the project duration by at least 10 days.
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
ย
Project Planning And Control Club house design with MSP
1. RICS SCHOOL OF BUILT ENVIRONMENT, Amity University
Submitted By : AYUSH KHANDELWAL
: KARAN SONI
: UTKARSH MITTAL
: RAJAT BHARDAWAJ
SECTION : โBโ
Group : 2
Sub Group : 5
Taught By:
Mrs. Susan George
Adjunct Associate Professor
2. INDEX
1. List of activities for the work packages
2. Network linking the activities and incorporating activity durations
3. Critical path calculation and duration of project
4. Calculation of total and free floats
5. Milestone chart showing information requirement and ordering of major items
6. Resource sheet with list of resource needs
7. Crashing of activity to reduce project time by at least 10 days (2 Marks)