SlideShare a Scribd company logo
1 of 70
Maryam Izadifar, Alireza Babaee,
Budiwan Adi Tirta, Ahmed Hassan El-Banna
Hydro-Geological Risks in
Mountain Area
Team Members:
Feb. 2015
Hydraulic Assessment
Professor:
Alessio Radice
Table of Contents
1- Introduction
2- River Modeling
2-1- Input Data
2-2- HEC-RAS model
2-3- BASEMENT model
3- City Modeling
3-1- Input Data
3-2- Previous Studies
3-3- Mesh Sensitivity
3-4- Steady Model
3-5- Transient Model
4- Results for Emergency Plan
1- Introduction
Area of interest
• The total area Mallero river basin is about
322 km2
• Length of the main river is 20 km
• Length of minor rivers is 36 km
• The hydraulic model starts from last 5 km
of the Sondrio’s reach
4
Flash Flood
• Flash flood event in mountains is related to the transportation of large
amounts of sediment.
• As a consequence, significant morphological changes may occur in rivers
during a single, short‐duration event, which has significant effect on the
water elevation.
1- Introduction
5
1- Introduction
Flood 1987
• A major flash flood occurred in the Mallero basin in July 1987
• The town of Sondrio was almost flooded
• Records of the event remark that a significant component of the flood
was represented by sediments which deposited along the in-town reach
due to relatively low slope
• The peak discharge of the event was estimated as almost 500 m3/s
• The sediment volume mobilized throughout the catchments was 3 × E6
m3, with 7 × E5 m3 supplied to the Mallero upstream of its last 5 km.
• Around 2 × E5 m3 of sediments were deposited in the in-town reach,
with aggradation depths of up to 5 m at the Garibaldi bridge and more
than 2 m at the Eiffel bridge.
1- Introduction
1- Introduction
Geological
Assessment
Hydrology
River
Modeling
(1D)
Erosion
(Event 1987)
Input Sediment graph
City
Modeling
(2D)
Outflow
hydrograph
Input
hydrograph
Emergency
Plan
Flood extension,
Depth, Velocity
(Time)
Methodology
Hydraulic Assessment Part
2- River Modeling
2-1- Input Data
• Input Data:
- Geometric Data (HEC-RAS and BASEMENT Input)
- Flood Hydrograph (HEC-RAS and BASEMENT Input)
- Sediment Graph (BASEMENT Input)
• Hydraulic modelling comprises two part:
1- define some critical sections along the town reach by
means of HEC-RAS
2- evaluate morphological evolution in the reach by means
of Basement
2- River Modeling
2-1- Input Data
• Flood Hydrograph (HEC-RAS and BASEMENT Input)
• Sediment Graph (BASEMENT Input)
Hydrograph Event 1987 Sediment graph (1987)
Area below sediment graph = 700,000 m3
First Section
(Basement: Sec 36,
HEC: Sec 56)
Critical Section
(Basement: Sec 70,
HEC: Sec 22)
(Basement: Sec 91,
HEC: Sec 1 )
2-River Modeling
2-1- Input Data
Pedestrian Bridge
Garibaldi Bridge
Eiffel Bridge
2-River Modeling
2-1- Input Data
2- River Modeling
2-2- HEC-RAS Model
• A preliminary analysis was carried out using HEC-RAS
considering steady analysis with peak flow of 495 m3/s.
• From the result it was observed that along the 5 km of
the reach, three different type of water conveyances
were defined based on their capacity.
HEC-RAS (Steady analysis with peak flow Qp=495 m^3/s)
First Section (Upstream)
High Conveyance Capacity
Last Section (Downstream)
Medium Conveyance Capacity
2- River Modeling
2-2- HEC-RAS Model
(Basement: Sec 91, HEC: Sec 1 )
(Basement: Sec 37, HEC: Sec 55 )
HEC-RAS (Steady analysis with
peak flow Qp = 495 m^3/s)
Critical Sections
Low Conveyance Capacity
2- River Modeling
2-2- HEC-RAS Model
(Basement: Sec 70, HEC: Sec 22 ) (Basement: Sec 74, HEC: Sec 18 )
Garibaldi Bridge
HEC-RAS (Steady analysis with
peak flow Qp=495 m^3/s)
2- River Modeling
2-2- HEC-RAS Model
Critical Sections
Low Conveyance Capacity
Critical Sections (Looking Upstream)
2- River Modeling
2-2- HEC-RAS Model
Critical Sections (Looking Downstream)
Basement Modeling
2- River Modeling
2-3- BASEMENT Model
• Basement is a software created with the purpose to evaluate morphological
evolution in a water stream, developed by the Hydraulic Department of the
Swiss Federal Institute of Technology ETH Zürich
• As an upstream boundary condition, a flow hydrograph is required. As a
downstream boundary condition, a normal depth with a slope value is
necessary for the model
18
• upstream boundary, a sediment discharge was selected in order to
simulate sediment feed upstream.
• The downstream boundary selected (IODown) guarantees that all
sediment entering the last computational cell will leave the cell over
the downstream boundary.
• Since this boundary condition requires that the elevation of the bed in
the downstream section remain unchanged, which is obviously not
realistic, an artificial reach is attached after the last section for 2 km in
order to minimize the adverse effect of the boundary condition
Basement Modeling
2- River Modeling
2-3- BASEMENT Model
19
In downstream (city) the bank elevations are considerably lower than upstream part . So, in
the case of bed aggradation in this part, bed elevation might be higher than bank elevation.
Avoiding crash in Basement calculation we have to use elevated banks in this part of river.
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Geometry
20
• Initial condition: Dry
• Upstream BC: constant hydrograph of 20 m3/s
• Strikler Coefficient * ,Ks = 25 m1/3/s (Ks=1/n=1/0.04)
• Upstream slope=0.032
• Downstream slope= 0.001
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- First Run Input data
NOTE: Ks strickler = 1/n manning. The coefficient Ks strickler varies from 20 (rough stone and
rough surface) to 80 m1/3/s (smooth concrete and cast iron).
Start with a fixed-bed model with initially dry bed, allowing enough time for a
steady condition to develop, to obtain the initial condition for the morphologic
model (second run)
21
• Initial condition is guaranteed by a constant hydrograph of 20 m3/s in the
whole length of the channel (first run)
• Upstream BC: 1987 event hydrograph
• Sediment Graph
• Strikler Coefficient * ,Ks = 25 m1/3/s (Ks=1/n=1/0.04)
• Upstream slope=0.032
• Downstream slope= 0.001
• Porosity: 0.35
• Particle Density: 2600 kg/m^3
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Second Run Input data
NOTE: Ks strickler = 1/n manning. The coefficient Ks strickler varies from 20 (rough stone and
rough surface) to 80 m1/3/s (smooth concrete and cast iron).
22
• Three different sediment size combination was used for sensitivity analysis:
Combination 1: 50mm for bed and feeding
Combination 2: 100mm for bed and feeding
Combination 3: mix 1 : 50mm (90%) and 150mm (10%) for the bed
mix 2 : 50mm (30%) and 150mm (70%) for the feeding
• Bed-load Transport Formula: mpmh (Meyer-Peter-Mueller and Hunziker)
for multiple grain classes
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Second Run Input data (continue)
Località Pendenza
S [%]
d50
[cm]
Cassandre 10 – 15 11-54
Sondrio 1 – 1.5 4-7
23
280
290
300
310
320
330
340
2000 2500 3000 3500 4000 4500
Elevation
Distance From Upstream (m)
Bed Morphology + Water Level (Peak time t=110000)
Bed Original
d=50&150
Observed Bed
Evolution
d=50mm
d=100mm
Bed aggradations in case of 50mm, 100mm and combination between (50&150mm)
at peak time of hydrograph. 50&150mm combination represents more similarity to
the observed bed evolution considering the critical sections.
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Sediment Size Sensitivity Analysis
24
As expected, the deposition of sediment is significant exactly from
section 68 to section 74 due to the decreasing slope.
295
297
299
301
303
305
307
309
311
313
315
317
319
321
323
325
327
329
2550 2650 2750 2850 2950
Elevation
Distance From Upstream (m)
Bed Morphology + Water Level (time t=130000) Sections 68 to 74
Bed Original
Left Bank
Corrected
New Bed
Water Level
Observed Bed
Evolution
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Bed Aggradation Analysis
25
295
297
299
301
303
305
307
309
311
313
315
317
319
321
323
325
327
329
2600 2620 2640 2660 2680 2700 2720 2740 2760 2780 2800
Elevation
Distance From Upstream (m)
Bed Morphology + Water Level (time t=130000) Outflow
Bed Original
Left Bank
Corrected
New Bed
Water Level
Observed Bed
Evolution
Bed aggradations and observed bed in critical section (70).
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Bed Aggradation Analysis
26
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Calculating Outflow
Q=C*A*sqrt(2*g*h)
C=0.3 (weir Coefficient)
Q=18.53 m3/s
27
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Calculating Outflow
Q=C*A*sqrt(2*g*h)
C=0.3 (weir Coefficient)
Q=52.41 m3/s
28
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Calculating Outflow
Q=C*A*sqrt(2*g*h)
C=0.3 (weir Coefficient)
Q=118 m3/s
29
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Calculating Outflow
Q=C*A*sqrt(2*g*h)
C=0.3 (weir Coefficient)
Q=63.85 m3/s
30
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Calculating Outflow
Q=C*A*sqrt(2*g*h)
C=0.3 (weir Coefficient)
Q=55.47 m3/s
31
312
313
314
315
316
317
2630 2640 2650 2660 2670 2680 2690 2700 2710 2720 2730
Elevation
Distance From Upstream (m)
Bed evolution & Water Level Out flow
CS70
Left Bank Corrected wes t=90000 wes t=110000
wes t=130000 wes t=150000 talweg t=130000
talweg t=150000
19
52
118
64
55
36
20
0
20
40
60
80
100
120
140
20 30 40 50 60
Discharge(m3/s)
Time (Hr)
Outflow Hydrograph (Section CS70)
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Outflow result
Q=C*A*sqrt(2*g*h)
C=0.3 (weir Coefficient)
32
• Peak = 118 m3/s
• Peak time = 36 hours (8 hours after the peak of inflow)
• Duration = about 40 hours
495
118
0
50
100
150
200
250
300
350
400
450
500
0 5 10 15 20 25 30 35 40 45 50 55 60
Discharge(m3/s)
Time (Hr)
Inflow and Outflow Hydrographs
Outflow in section 70
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Outflow result
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- Bed and Water level Analysis in CS 70
2- River Modeling
2-3- BASEMENT Model
Basement Modeling- outflow in east part of city from section 70 or to both
sides of the city in Garibaldi bridge (section 74)
3- City Modeling
3-1- Input Data
River2D input data:
• Bed geometry
• Inflow discharge:
Steady model: 118 m^3/s
Transient model: 4-hour hydrograph
• Inlet position:
Case 1: Pedestrian bridge (section 70)
Case 2: Garibaldi bridge (section 74)
• Inflow depth = average 1 m higher than levee
• Outflow depth = 50 m lower than earth surface in order to have dry initial condition
• Groundwater Transmissivity = 0.1 (by low values actual ground water discharge is
negligible)
• Groundwater Storativity = 0.1 (Storativity is a measure of volume of water the ground will
release. The default value is 1 but for accurate transient analysis this value should be
reduced)
3- City Modeling
3-2- Previous Studies
Scenario 1:
Q left = 50 m3/sec
Q right = 50 m3/sec
Our calculation:
Q max = 118 m3/sec
Q left = west side of the city
Q right = east side of the city
3- City Modeling
3-2- Previous Studies
Scenario 2:
Q left = 100 m3/sec
Q right = 195 m3/sec
Our calculation:
Q max = 118 m3/sec
Q left = west side of the city
Q right = east side of the city
3- City Modeling
3-2- Previous Studies
Scenario 3:
Q left = 125 m3/sec
Q right = 355 m3/sec
Our calculation:
Q max = 118 m3/sec
Q left = west side of the city
Q right = east side of the city
3- City Modeling
3-2- Previous Studies
Scenario 3:
Q left = 125 m3/sec
Q right = 355 m3/sec
Our calculation:
Q max = 118 m3/sec
Q left = west side of the city
Q right = east side of the city
3- City Modeling
3-3- Mesh Sensitivity
Model 1:
Mesh size: 20 m
Number of nodes: 4362
Number of elements: 7353
QI = 0.078
Model 2:
Mesh size: 40 m
Number of nodes: 1565
Number of elements: 2372
QI = 0.073
3- City Modeling
3-3- Mesh Sensitivity
Model 1: (run for 10 min flood)
Calculation time: 90 min
Lowest water depth
T = 10 min T = 10 min
Q steady = 118 m3/s
Model 2: (run for 10 min flood)
Calculation time: 6 min
3- City Modeling
3-3- Mesh Sensitivity
Model 1: (run for 10 min flood)
Calculation time: 90 min
T = 10 min T = 10 min
Q steady = 118 m3/s
Model 2: (run for 10 min flood)
Calculation time: 6 min
3- City Modeling
3-3- Mesh Sensitivity
Model 3:
Mesh size: 80 m
Number of nodes: 711
Number of elements: 959
QI = 0.048
Model 4:
Mesh size: 120 m
Number of nodes: 498
Number of elements: 640
QI = 0.003
3- City Modeling
3-3- Mesh Sensitivity
T = 10 min
Model 4: (run for 10 min flood)
Calculation time: 1 min
T = 10 min
Q steady = 118 m3/s
Model 3: (run for 10 min flood)
Calculation time: 2 min
3- City Modeling
3-3- Mesh Sensitivity
Model 3: (run for 10 min flood)
Calculation time: 2 min
T = 10 min T = 10 min
Q steady = 118 m3/s
Model 4: (run for 10 min flood)
Calculation time: 1 min
3- City Modeling
3-3- Mesh Sensitivity
T = 60 min
Model 4: (run for 60 min flood)
Mesh size: 120 m
T = 60 min
Q steady = 118 m3/s
Model 2: (run for 60 min flood)
Mesh size: 40 m
Almost the same extension of water
3- City Modeling
3-3- Mesh Sensitivity
Mesh Sensitivity results
• The finer the mesh, the higher the calculation time (mesh size 20 m is very time
consuming. But mesh size 40 m has reasonable time for simulation)
• The result in terms of water extension is similar (considering all four models for 10
min run and two models for 60 min run)
• The result for water depth is different. In coarse meshes, water depth is higher.
Therefore results in very coarse meshes are overestimation.
• The result for velocity also shows significant differences. Results in small meshes
are more accurate.
• To have a decent trade-off between calculation time and accuracy, the mesh
size 40 m is recommended. This mesh size is used for next part of the study.
3- City Modeling
3-4- Steady Model
Q = 118 m3/s
T = 10 min T = 20 min
Steady Model (Water depth evolution)
Inlet in the Pedestrian bridge (critical section 70)
3- City Modeling
3-4- Steady Model
Q = 118 m3/s
T = 30 min T = 60 min
Steady Model (Water depth evolution)
Inlet in the Pedestrian bridge (critical section 70)
3- City Modeling
3-4- Steady Model
Q = 118 m3/s
T = 2 hr T = 3 hr
Steady Model (Water depth evolution)
Inlet in the Pedestrian bridge (critical section 70)
3- City Modeling
3-4- Steady Model
Q = 118 m3/s
T = 4 hr T = 6 hr
Steady Model (Water depth evolution)
Inlet in the Pedestrian bridge (critical section 70)
3- City Modeling
3-4- Steady Model
Q = 118 m3/s
T = 8 hr
Steady Model (Water depth evolution)
Inlet in the Pedestrian bridge (critical section 70)
3- City Modeling
3-4- Steady Model
Q = 118 m3/s
T = 8 hr
Steady Model (Velocity)
Inlet in the Pedestrian bridge (critical section 70)
3- City Modeling
3-4- Steady Model
Steady Model (Water depth evolution)
Inlet in the Garibaldi bridge position (section 74)
Q = 118 m3/s
T = 5 min T = 10 min
3- City Modeling
3-4- Steady Model
Q = 118 m3/s
T = 20 min T = 30 min
Steady Model (Water depth evolution)
Inlet in the Garibaldi bridge position (section 74)
3- City Modeling
3-4- Steady Model
Q = 118 m3/s
T = 40 min T = 50 min
Steady Model (Water depth evolution)
Inlet in the Garibaldi bridge position (section 74)
3- City Modeling
3-4- Steady Model
Q = 118 m3/s
T = 60 min
Steady Model (Water depth evolution)
Inlet in the Garibaldi bridge position (section 74)
3- City Modeling
3-4- Steady Model
Steady Model (Velocity)
Inlet in the Garibaldi bridge position
Q = 118 m3/s
T = 60 min
3- City Modeling
3-4- Steady Model
Summary
In the case of inlet in section 70 (pedestrian bridge) half of the city will not be
inundated and results in terms of water extension is not compatible with previous
studies.
Considering the inlet position in Garibaldi bridge (Section 74), the extension of water
are more similar to previous studies.
Both cases are probable. In order to have a comparison between our study and old
versions, inlet position in Garibaldi bridge was simulated in the transient model.
3- City Modeling
3-5- Transient Model
Transient Model
Using 4 hours of river out-flow hydrograph
4 hours hydrograph
3- City Modeling
3-5- Transient Model
Transient Model (Water depth)
T = 0 min T = 5 min
3- City Modeling
3-5- Transient Model
Transient Model (Water depth)
T = 10 min T = 20 min
3- City Modeling
3-5- Transient Model
Transient Model (Water depth)
T = 30 min T = 40 min
3- City Modeling
3-5- Transient Model
Transient Model (Water depth)
T = 50 min T = 60 min (1 hour)
3- City Modeling
3-5- Transient Model
Transient Model (Water depth)
T = 120 min (2 hour)T = 90 min (1:30)
Peak discharge
3- City Modeling
3-5- Transient Model
Transient Model (Water depth)
T = 240 min (4 hour)T = 180 min (3 hours)
3- City Modeling
3-5- Transient Model
Transient Model (Velocity)
T = 240 min (4 hour)
4- Results for Emergency Plan
Two scenarios are considering for the Emergency Plan
1- scenario number 3 (extreme case) with Qr = 355 m^3/s from previous studies
2- transient simulation with inlet in Garibaldi bridge with Qpeak = 118 m^3/s
• Two scenarios have significant differences in terms of water extension and depth.
• Max water depth in first scenario is 2.5 m while in the second scenario is limited to 1.5 m.
• Max velocity in first scenario is 4 m/s while in the second scenario is 3.5 m.
• Since our model has only east part of the city, the result for the west part was concluded
from second scenario of the previous studies (Qleft = 100).
Combining water depth results from River2D on the city map
T = 240 min (4 hours)
Transient model
Qpeak = 118 m^3/s
4- Results for Emergency Plan
4- Results for Emergency Plan
Scenario 3 in previous studies (Qr=355) Our scenario (Qr=118)

More Related Content

What's hot

Water Resources Engineering - Question Bank (objective)
Water Resources Engineering - Question Bank (objective)Water Resources Engineering - Question Bank (objective)
Water Resources Engineering - Question Bank (objective)Malla Reddy University
 
Groundwater Modelling Application for Waterworks
Groundwater Modelling Application for WaterworksGroundwater Modelling Application for Waterworks
Groundwater Modelling Application for WaterworksTapesh Ajmera
 
River hydraulic modelling for river Serio (Northern Italy), 2014
River hydraulic modelling for river Serio (Northern Italy), 2014River hydraulic modelling for river Serio (Northern Italy), 2014
River hydraulic modelling for river Serio (Northern Italy), 2014Alireza Babaee
 
San Elijo Hills Drainage Diversion Hydrogeologist Report
San Elijo Hills Drainage Diversion Hydrogeologist ReportSan Elijo Hills Drainage Diversion Hydrogeologist Report
San Elijo Hills Drainage Diversion Hydrogeologist Reporttalerco
 
Estimation of morphometric parameters and
Estimation of morphometric parameters andEstimation of morphometric parameters and
Estimation of morphometric parameters andeSAT Publishing House
 
Analysis and design of an efficient drainage system in Chittagong city
Analysis and design of an efficient  drainage system in Chittagong cityAnalysis and design of an efficient  drainage system in Chittagong city
Analysis and design of an efficient drainage system in Chittagong citySabbir . Ahmmed
 
Day 2 akm saiful islam, institute of water and flood management, arrcc-cariss...
Day 2 akm saiful islam, institute of water and flood management, arrcc-cariss...Day 2 akm saiful islam, institute of water and flood management, arrcc-cariss...
Day 2 akm saiful islam, institute of water and flood management, arrcc-cariss...ICIMOD
 
C2VSim Workshop 5 - C2VSim Surface Water Representation
C2VSim Workshop 5 - C2VSim Surface Water RepresentationC2VSim Workshop 5 - C2VSim Surface Water Representation
C2VSim Workshop 5 - C2VSim Surface Water RepresentationCharlie Brush
 
Groundwater modeling
Groundwater modelingGroundwater modeling
Groundwater modelingAchmad Darul
 
Transient Modelling of Groundwater Flow, Application to Tunnel Dewatering
Transient Modelling of Groundwater Flow, Application to Tunnel DewateringTransient Modelling of Groundwater Flow, Application to Tunnel Dewatering
Transient Modelling of Groundwater Flow, Application to Tunnel DewateringDirk Kassenaar M.Sc. P.Eng.
 
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...Dirk Kassenaar M.Sc. P.Eng.
 
Flood estimation
Flood estimation Flood estimation
Flood estimation RAJ BAIRWA
 
Morphometric analysis of a vrishabhavathi sub watershed upstream side of gali...
Morphometric analysis of a vrishabhavathi sub watershed upstream side of gali...Morphometric analysis of a vrishabhavathi sub watershed upstream side of gali...
Morphometric analysis of a vrishabhavathi sub watershed upstream side of gali...eSAT Publishing House
 
Geotechnical Engineering-I [Lec #27: Flow Nets]
Geotechnical Engineering-I [Lec #27: Flow Nets]Geotechnical Engineering-I [Lec #27: Flow Nets]
Geotechnical Engineering-I [Lec #27: Flow Nets]Muhammad Irfan
 
Risk and standards based riprap design for grahamstown dam barker & hol...
Risk and standards based riprap design for grahamstown dam   barker & hol...Risk and standards based riprap design for grahamstown dam   barker & hol...
Risk and standards based riprap design for grahamstown dam barker & hol...Joseph Ng'ang'a Thuo
 

What's hot (18)

Water Resources Engineering - Question Bank (objective)
Water Resources Engineering - Question Bank (objective)Water Resources Engineering - Question Bank (objective)
Water Resources Engineering - Question Bank (objective)
 
Groundwater Modelling Application for Waterworks
Groundwater Modelling Application for WaterworksGroundwater Modelling Application for Waterworks
Groundwater Modelling Application for Waterworks
 
River hydraulic modelling for river Serio (Northern Italy), 2014
River hydraulic modelling for river Serio (Northern Italy), 2014River hydraulic modelling for river Serio (Northern Italy), 2014
River hydraulic modelling for river Serio (Northern Italy), 2014
 
San Elijo Hills Drainage Diversion Hydrogeologist Report
San Elijo Hills Drainage Diversion Hydrogeologist ReportSan Elijo Hills Drainage Diversion Hydrogeologist Report
San Elijo Hills Drainage Diversion Hydrogeologist Report
 
Surface runoff
Surface runoffSurface runoff
Surface runoff
 
Estimation of morphometric parameters and
Estimation of morphometric parameters andEstimation of morphometric parameters and
Estimation of morphometric parameters and
 
Analysis and design of an efficient drainage system in Chittagong city
Analysis and design of an efficient  drainage system in Chittagong cityAnalysis and design of an efficient  drainage system in Chittagong city
Analysis and design of an efficient drainage system in Chittagong city
 
Day 2 akm saiful islam, institute of water and flood management, arrcc-cariss...
Day 2 akm saiful islam, institute of water and flood management, arrcc-cariss...Day 2 akm saiful islam, institute of water and flood management, arrcc-cariss...
Day 2 akm saiful islam, institute of water and flood management, arrcc-cariss...
 
C2VSim Workshop 5 - C2VSim Surface Water Representation
C2VSim Workshop 5 - C2VSim Surface Water RepresentationC2VSim Workshop 5 - C2VSim Surface Water Representation
C2VSim Workshop 5 - C2VSim Surface Water Representation
 
Groundwater modeling
Groundwater modelingGroundwater modeling
Groundwater modeling
 
Transient Modelling of Groundwater Flow, Application to Tunnel Dewatering
Transient Modelling of Groundwater Flow, Application to Tunnel DewateringTransient Modelling of Groundwater Flow, Application to Tunnel Dewatering
Transient Modelling of Groundwater Flow, Application to Tunnel Dewatering
 
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
 
Dirk Kassenaar EarthFX Watertech 2016
Dirk Kassenaar EarthFX Watertech 2016 Dirk Kassenaar EarthFX Watertech 2016
Dirk Kassenaar EarthFX Watertech 2016
 
Flood estimation
Flood estimation Flood estimation
Flood estimation
 
Morphometric analysis of a vrishabhavathi sub watershed upstream side of gali...
Morphometric analysis of a vrishabhavathi sub watershed upstream side of gali...Morphometric analysis of a vrishabhavathi sub watershed upstream side of gali...
Morphometric analysis of a vrishabhavathi sub watershed upstream side of gali...
 
Flood Routing using Muskingum Method
Flood Routing using Muskingum MethodFlood Routing using Muskingum Method
Flood Routing using Muskingum Method
 
Geotechnical Engineering-I [Lec #27: Flow Nets]
Geotechnical Engineering-I [Lec #27: Flow Nets]Geotechnical Engineering-I [Lec #27: Flow Nets]
Geotechnical Engineering-I [Lec #27: Flow Nets]
 
Risk and standards based riprap design for grahamstown dam barker & hol...
Risk and standards based riprap design for grahamstown dam   barker & hol...Risk and standards based riprap design for grahamstown dam   barker & hol...
Risk and standards based riprap design for grahamstown dam barker & hol...
 

Similar to Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: hydraulic assessment

Flood risk evaluation for Serio river, Italy
Flood risk evaluation for Serio river, ItalyFlood risk evaluation for Serio river, Italy
Flood risk evaluation for Serio river, ItalyMaryam Izadifar
 
SImulating Past Flood Event using Nays 2D Flood
SImulating Past Flood Event using Nays 2D FloodSImulating Past Flood Event using Nays 2D Flood
SImulating Past Flood Event using Nays 2D FloodPutika Ashfar Khoiri
 
Simulating several flood events using Nays 2D Flood
Simulating several flood events using Nays 2D FloodSimulating several flood events using Nays 2D Flood
Simulating several flood events using Nays 2D FloodPutika Ashfar Khoiri
 
DSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
DSD-INT 2019 ShorelineS and future coastline modelling - RoelvinkDSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
DSD-INT 2019 ShorelineS and future coastline modelling - RoelvinkDeltares
 
Flooding areas of Ofanto river using advanced topographic and hydraulic appro...
Flooding areas of Ofanto river using advanced topographic and hydraulic appro...Flooding areas of Ofanto river using advanced topographic and hydraulic appro...
Flooding areas of Ofanto river using advanced topographic and hydraulic appro...Lia Romano
 
Implementation of a Finite Element Model to Generate Synthetic data for Open ...
Implementation of a Finite Element Model to Generate Synthetic data for Open ...Implementation of a Finite Element Model to Generate Synthetic data for Open ...
Implementation of a Finite Element Model to Generate Synthetic data for Open ...IRJET Journal
 
Control Seepage Thought Earth Dams
Control Seepage Thought Earth DamsControl Seepage Thought Earth Dams
Control Seepage Thought Earth DamsAhmed Mansor
 
Hydro-structural analysis of Northern Termination of Maiella
Hydro-structural analysis of Northern Termination of MaiellaHydro-structural analysis of Northern Termination of Maiella
Hydro-structural analysis of Northern Termination of Maiellakaisar ahmat
 
5-Runoff computation (2).ppt
5-Runoff computation (2).ppt5-Runoff computation (2).ppt
5-Runoff computation (2).pptJohnAyele
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnelijceronline
 
DSD-INT 2017 Use of RIBASIM in Lesotho - Passchier
DSD-INT 2017 Use of RIBASIM in Lesotho - PasschierDSD-INT 2017 Use of RIBASIM in Lesotho - Passchier
DSD-INT 2017 Use of RIBASIM in Lesotho - PasschierDeltares
 
Physical model for coastal inlet
Physical model for coastal inletPhysical model for coastal inlet
Physical model for coastal inletNguyen Thanh Luan
 
Integrated Modelling as a Tool for Assessing Groundwater Sustainability under...
Integrated Modelling as a Tool for Assessing Groundwater Sustainability under...Integrated Modelling as a Tool for Assessing Groundwater Sustainability under...
Integrated Modelling as a Tool for Assessing Groundwater Sustainability under...Dirk Kassenaar M.Sc. P.Eng.
 
Teaching Presentation.pptx
Teaching Presentation.pptxTeaching Presentation.pptx
Teaching Presentation.pptxSanchitMinocha1
 
Critical flow through an Open channel
Critical flow through an Open channelCritical flow through an Open channel
Critical flow through an Open channelAjoy Kumar Saha
 

Similar to Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: hydraulic assessment (20)

Flood risk evaluation for Serio river, Italy
Flood risk evaluation for Serio river, ItalyFlood risk evaluation for Serio river, Italy
Flood risk evaluation for Serio river, Italy
 
SImulating Past Flood Event using Nays 2D Flood
SImulating Past Flood Event using Nays 2D FloodSImulating Past Flood Event using Nays 2D Flood
SImulating Past Flood Event using Nays 2D Flood
 
Simulating several flood events using Nays 2D Flood
Simulating several flood events using Nays 2D FloodSimulating several flood events using Nays 2D Flood
Simulating several flood events using Nays 2D Flood
 
DSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
DSD-INT 2019 ShorelineS and future coastline modelling - RoelvinkDSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
DSD-INT 2019 ShorelineS and future coastline modelling - Roelvink
 
H0372040043
H0372040043H0372040043
H0372040043
 
Flooding areas of Ofanto river using advanced topographic and hydraulic appro...
Flooding areas of Ofanto river using advanced topographic and hydraulic appro...Flooding areas of Ofanto river using advanced topographic and hydraulic appro...
Flooding areas of Ofanto river using advanced topographic and hydraulic appro...
 
Ch2.ppt
Ch2.pptCh2.ppt
Ch2.ppt
 
GROUNDWATER MODELING SYSTEM
GROUNDWATER MODELING SYSTEMGROUNDWATER MODELING SYSTEM
GROUNDWATER MODELING SYSTEM
 
Implementation of a Finite Element Model to Generate Synthetic data for Open ...
Implementation of a Finite Element Model to Generate Synthetic data for Open ...Implementation of a Finite Element Model to Generate Synthetic data for Open ...
Implementation of a Finite Element Model to Generate Synthetic data for Open ...
 
16 Aug-2013 - Ary van der Lely - A stratigraphic model of the MIA
16 Aug-2013 - Ary van der Lely - A stratigraphic model of the MIA16 Aug-2013 - Ary van der Lely - A stratigraphic model of the MIA
16 Aug-2013 - Ary van der Lely - A stratigraphic model of the MIA
 
Control Seepage Thought Earth Dams
Control Seepage Thought Earth DamsControl Seepage Thought Earth Dams
Control Seepage Thought Earth Dams
 
Hydro-structural analysis of Northern Termination of Maiella
Hydro-structural analysis of Northern Termination of MaiellaHydro-structural analysis of Northern Termination of Maiella
Hydro-structural analysis of Northern Termination of Maiella
 
5-Runoff computation (2).ppt
5-Runoff computation (2).ppt5-Runoff computation (2).ppt
5-Runoff computation (2).ppt
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
 
DSD-INT 2017 Use of RIBASIM in Lesotho - Passchier
DSD-INT 2017 Use of RIBASIM in Lesotho - PasschierDSD-INT 2017 Use of RIBASIM in Lesotho - Passchier
DSD-INT 2017 Use of RIBASIM in Lesotho - Passchier
 
Physical model for coastal inlet
Physical model for coastal inletPhysical model for coastal inlet
Physical model for coastal inlet
 
Integrated Modelling as a Tool for Assessing Groundwater Sustainability under...
Integrated Modelling as a Tool for Assessing Groundwater Sustainability under...Integrated Modelling as a Tool for Assessing Groundwater Sustainability under...
Integrated Modelling as a Tool for Assessing Groundwater Sustainability under...
 
Teaching Presentation.pptx
Teaching Presentation.pptxTeaching Presentation.pptx
Teaching Presentation.pptx
 
Critical flow through an Open channel
Critical flow through an Open channelCritical flow through an Open channel
Critical flow through an Open channel
 
Final Ppt.pdf
Final Ppt.pdfFinal Ppt.pdf
Final Ppt.pdf
 

More from Alireza Babaee

Hazard Modelling and Risk Assessment for Urban Flood Scenario (Presentation)
Hazard Modelling and Risk Assessment for Urban Flood Scenario (Presentation)Hazard Modelling and Risk Assessment for Urban Flood Scenario (Presentation)
Hazard Modelling and Risk Assessment for Urban Flood Scenario (Presentation)Alireza Babaee
 
Hazard Modelling and Risk Assessment for Urban Flood Scenario
Hazard Modelling and Risk Assessment for Urban Flood ScenarioHazard Modelling and Risk Assessment for Urban Flood Scenario
Hazard Modelling and Risk Assessment for Urban Flood ScenarioAlireza Babaee
 
Final project for Geo-Engineering Techniques for Unstable Slopes
Final project for Geo-Engineering Techniques for Unstable SlopesFinal project for Geo-Engineering Techniques for Unstable Slopes
Final project for Geo-Engineering Techniques for Unstable SlopesAlireza Babaee
 
ICT Applied to Crisis Management and Seismic Risk Assessment for Post Event M...
ICT Applied to Crisis Management and Seismic Risk Assessment for Post Event M...ICT Applied to Crisis Management and Seismic Risk Assessment for Post Event M...
ICT Applied to Crisis Management and Seismic Risk Assessment for Post Event M...Alireza Babaee
 
Development of Emergency Plan of a flood scenario in Sondrio (Alpine Italy)
Development of Emergency Plan of a flood scenario in Sondrio (Alpine Italy)Development of Emergency Plan of a flood scenario in Sondrio (Alpine Italy)
Development of Emergency Plan of a flood scenario in Sondrio (Alpine Italy)Alireza Babaee
 
Development of avalanche hazard maps by ArcGIS for Trentino (Alpine Italy)
Development of avalanche hazard maps by ArcGIS for Trentino (Alpine Italy)Development of avalanche hazard maps by ArcGIS for Trentino (Alpine Italy)
Development of avalanche hazard maps by ArcGIS for Trentino (Alpine Italy)Alireza Babaee
 
Risk Assessment for an Earthquake Scenario in Istanbul City
Risk Assessment for an Earthquake Scenario in Istanbul CityRisk Assessment for an Earthquake Scenario in Istanbul City
Risk Assessment for an Earthquake Scenario in Istanbul CityAlireza Babaee
 

More from Alireza Babaee (8)

Hazard Modelling and Risk Assessment for Urban Flood Scenario (Presentation)
Hazard Modelling and Risk Assessment for Urban Flood Scenario (Presentation)Hazard Modelling and Risk Assessment for Urban Flood Scenario (Presentation)
Hazard Modelling and Risk Assessment for Urban Flood Scenario (Presentation)
 
Hazard Modelling and Risk Assessment for Urban Flood Scenario
Hazard Modelling and Risk Assessment for Urban Flood ScenarioHazard Modelling and Risk Assessment for Urban Flood Scenario
Hazard Modelling and Risk Assessment for Urban Flood Scenario
 
Final project for Geo-Engineering Techniques for Unstable Slopes
Final project for Geo-Engineering Techniques for Unstable SlopesFinal project for Geo-Engineering Techniques for Unstable Slopes
Final project for Geo-Engineering Techniques for Unstable Slopes
 
ICT Applied to Crisis Management and Seismic Risk Assessment for Post Event M...
ICT Applied to Crisis Management and Seismic Risk Assessment for Post Event M...ICT Applied to Crisis Management and Seismic Risk Assessment for Post Event M...
ICT Applied to Crisis Management and Seismic Risk Assessment for Post Event M...
 
Climate change
Climate changeClimate change
Climate change
 
Development of Emergency Plan of a flood scenario in Sondrio (Alpine Italy)
Development of Emergency Plan of a flood scenario in Sondrio (Alpine Italy)Development of Emergency Plan of a flood scenario in Sondrio (Alpine Italy)
Development of Emergency Plan of a flood scenario in Sondrio (Alpine Italy)
 
Development of avalanche hazard maps by ArcGIS for Trentino (Alpine Italy)
Development of avalanche hazard maps by ArcGIS for Trentino (Alpine Italy)Development of avalanche hazard maps by ArcGIS for Trentino (Alpine Italy)
Development of avalanche hazard maps by ArcGIS for Trentino (Alpine Italy)
 
Risk Assessment for an Earthquake Scenario in Istanbul City
Risk Assessment for an Earthquake Scenario in Istanbul CityRisk Assessment for an Earthquake Scenario in Istanbul City
Risk Assessment for an Earthquake Scenario in Istanbul City
 

Recently uploaded

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Recently uploaded (20)

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: hydraulic assessment

  • 1. Maryam Izadifar, Alireza Babaee, Budiwan Adi Tirta, Ahmed Hassan El-Banna Hydro-Geological Risks in Mountain Area Team Members: Feb. 2015 Hydraulic Assessment Professor: Alessio Radice
  • 2. Table of Contents 1- Introduction 2- River Modeling 2-1- Input Data 2-2- HEC-RAS model 2-3- BASEMENT model 3- City Modeling 3-1- Input Data 3-2- Previous Studies 3-3- Mesh Sensitivity 3-4- Steady Model 3-5- Transient Model 4- Results for Emergency Plan
  • 3. 1- Introduction Area of interest • The total area Mallero river basin is about 322 km2 • Length of the main river is 20 km • Length of minor rivers is 36 km • The hydraulic model starts from last 5 km of the Sondrio’s reach
  • 4. 4 Flash Flood • Flash flood event in mountains is related to the transportation of large amounts of sediment. • As a consequence, significant morphological changes may occur in rivers during a single, short‐duration event, which has significant effect on the water elevation. 1- Introduction
  • 5. 5 1- Introduction Flood 1987 • A major flash flood occurred in the Mallero basin in July 1987 • The town of Sondrio was almost flooded • Records of the event remark that a significant component of the flood was represented by sediments which deposited along the in-town reach due to relatively low slope • The peak discharge of the event was estimated as almost 500 m3/s • The sediment volume mobilized throughout the catchments was 3 × E6 m3, with 7 × E5 m3 supplied to the Mallero upstream of its last 5 km. • Around 2 × E5 m3 of sediments were deposited in the in-town reach, with aggradation depths of up to 5 m at the Garibaldi bridge and more than 2 m at the Eiffel bridge.
  • 7. 1- Introduction Geological Assessment Hydrology River Modeling (1D) Erosion (Event 1987) Input Sediment graph City Modeling (2D) Outflow hydrograph Input hydrograph Emergency Plan Flood extension, Depth, Velocity (Time) Methodology Hydraulic Assessment Part
  • 8. 2- River Modeling 2-1- Input Data • Input Data: - Geometric Data (HEC-RAS and BASEMENT Input) - Flood Hydrograph (HEC-RAS and BASEMENT Input) - Sediment Graph (BASEMENT Input) • Hydraulic modelling comprises two part: 1- define some critical sections along the town reach by means of HEC-RAS 2- evaluate morphological evolution in the reach by means of Basement
  • 9. 2- River Modeling 2-1- Input Data • Flood Hydrograph (HEC-RAS and BASEMENT Input) • Sediment Graph (BASEMENT Input) Hydrograph Event 1987 Sediment graph (1987) Area below sediment graph = 700,000 m3
  • 10. First Section (Basement: Sec 36, HEC: Sec 56) Critical Section (Basement: Sec 70, HEC: Sec 22) (Basement: Sec 91, HEC: Sec 1 ) 2-River Modeling 2-1- Input Data
  • 11. Pedestrian Bridge Garibaldi Bridge Eiffel Bridge 2-River Modeling 2-1- Input Data
  • 12. 2- River Modeling 2-2- HEC-RAS Model • A preliminary analysis was carried out using HEC-RAS considering steady analysis with peak flow of 495 m3/s. • From the result it was observed that along the 5 km of the reach, three different type of water conveyances were defined based on their capacity.
  • 13. HEC-RAS (Steady analysis with peak flow Qp=495 m^3/s) First Section (Upstream) High Conveyance Capacity Last Section (Downstream) Medium Conveyance Capacity 2- River Modeling 2-2- HEC-RAS Model (Basement: Sec 91, HEC: Sec 1 ) (Basement: Sec 37, HEC: Sec 55 )
  • 14. HEC-RAS (Steady analysis with peak flow Qp = 495 m^3/s) Critical Sections Low Conveyance Capacity 2- River Modeling 2-2- HEC-RAS Model (Basement: Sec 70, HEC: Sec 22 ) (Basement: Sec 74, HEC: Sec 18 ) Garibaldi Bridge
  • 15. HEC-RAS (Steady analysis with peak flow Qp=495 m^3/s) 2- River Modeling 2-2- HEC-RAS Model Critical Sections Low Conveyance Capacity
  • 16. Critical Sections (Looking Upstream) 2- River Modeling 2-2- HEC-RAS Model Critical Sections (Looking Downstream)
  • 17. Basement Modeling 2- River Modeling 2-3- BASEMENT Model • Basement is a software created with the purpose to evaluate morphological evolution in a water stream, developed by the Hydraulic Department of the Swiss Federal Institute of Technology ETH Zürich • As an upstream boundary condition, a flow hydrograph is required. As a downstream boundary condition, a normal depth with a slope value is necessary for the model
  • 18. 18 • upstream boundary, a sediment discharge was selected in order to simulate sediment feed upstream. • The downstream boundary selected (IODown) guarantees that all sediment entering the last computational cell will leave the cell over the downstream boundary. • Since this boundary condition requires that the elevation of the bed in the downstream section remain unchanged, which is obviously not realistic, an artificial reach is attached after the last section for 2 km in order to minimize the adverse effect of the boundary condition Basement Modeling 2- River Modeling 2-3- BASEMENT Model
  • 19. 19 In downstream (city) the bank elevations are considerably lower than upstream part . So, in the case of bed aggradation in this part, bed elevation might be higher than bank elevation. Avoiding crash in Basement calculation we have to use elevated banks in this part of river. 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Geometry
  • 20. 20 • Initial condition: Dry • Upstream BC: constant hydrograph of 20 m3/s • Strikler Coefficient * ,Ks = 25 m1/3/s (Ks=1/n=1/0.04) • Upstream slope=0.032 • Downstream slope= 0.001 2- River Modeling 2-3- BASEMENT Model Basement Modeling- First Run Input data NOTE: Ks strickler = 1/n manning. The coefficient Ks strickler varies from 20 (rough stone and rough surface) to 80 m1/3/s (smooth concrete and cast iron). Start with a fixed-bed model with initially dry bed, allowing enough time for a steady condition to develop, to obtain the initial condition for the morphologic model (second run)
  • 21. 21 • Initial condition is guaranteed by a constant hydrograph of 20 m3/s in the whole length of the channel (first run) • Upstream BC: 1987 event hydrograph • Sediment Graph • Strikler Coefficient * ,Ks = 25 m1/3/s (Ks=1/n=1/0.04) • Upstream slope=0.032 • Downstream slope= 0.001 • Porosity: 0.35 • Particle Density: 2600 kg/m^3 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Second Run Input data NOTE: Ks strickler = 1/n manning. The coefficient Ks strickler varies from 20 (rough stone and rough surface) to 80 m1/3/s (smooth concrete and cast iron).
  • 22. 22 • Three different sediment size combination was used for sensitivity analysis: Combination 1: 50mm for bed and feeding Combination 2: 100mm for bed and feeding Combination 3: mix 1 : 50mm (90%) and 150mm (10%) for the bed mix 2 : 50mm (30%) and 150mm (70%) for the feeding • Bed-load Transport Formula: mpmh (Meyer-Peter-Mueller and Hunziker) for multiple grain classes 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Second Run Input data (continue) Località Pendenza S [%] d50 [cm] Cassandre 10 – 15 11-54 Sondrio 1 – 1.5 4-7
  • 23. 23 280 290 300 310 320 330 340 2000 2500 3000 3500 4000 4500 Elevation Distance From Upstream (m) Bed Morphology + Water Level (Peak time t=110000) Bed Original d=50&150 Observed Bed Evolution d=50mm d=100mm Bed aggradations in case of 50mm, 100mm and combination between (50&150mm) at peak time of hydrograph. 50&150mm combination represents more similarity to the observed bed evolution considering the critical sections. 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Sediment Size Sensitivity Analysis
  • 24. 24 As expected, the deposition of sediment is significant exactly from section 68 to section 74 due to the decreasing slope. 295 297 299 301 303 305 307 309 311 313 315 317 319 321 323 325 327 329 2550 2650 2750 2850 2950 Elevation Distance From Upstream (m) Bed Morphology + Water Level (time t=130000) Sections 68 to 74 Bed Original Left Bank Corrected New Bed Water Level Observed Bed Evolution 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Bed Aggradation Analysis
  • 25. 25 295 297 299 301 303 305 307 309 311 313 315 317 319 321 323 325 327 329 2600 2620 2640 2660 2680 2700 2720 2740 2760 2780 2800 Elevation Distance From Upstream (m) Bed Morphology + Water Level (time t=130000) Outflow Bed Original Left Bank Corrected New Bed Water Level Observed Bed Evolution Bed aggradations and observed bed in critical section (70). 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Bed Aggradation Analysis
  • 26. 26 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Calculating Outflow Q=C*A*sqrt(2*g*h) C=0.3 (weir Coefficient) Q=18.53 m3/s
  • 27. 27 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Calculating Outflow Q=C*A*sqrt(2*g*h) C=0.3 (weir Coefficient) Q=52.41 m3/s
  • 28. 28 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Calculating Outflow Q=C*A*sqrt(2*g*h) C=0.3 (weir Coefficient) Q=118 m3/s
  • 29. 29 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Calculating Outflow Q=C*A*sqrt(2*g*h) C=0.3 (weir Coefficient) Q=63.85 m3/s
  • 30. 30 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Calculating Outflow Q=C*A*sqrt(2*g*h) C=0.3 (weir Coefficient) Q=55.47 m3/s
  • 31. 31 312 313 314 315 316 317 2630 2640 2650 2660 2670 2680 2690 2700 2710 2720 2730 Elevation Distance From Upstream (m) Bed evolution & Water Level Out flow CS70 Left Bank Corrected wes t=90000 wes t=110000 wes t=130000 wes t=150000 talweg t=130000 talweg t=150000 19 52 118 64 55 36 20 0 20 40 60 80 100 120 140 20 30 40 50 60 Discharge(m3/s) Time (Hr) Outflow Hydrograph (Section CS70) 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Outflow result Q=C*A*sqrt(2*g*h) C=0.3 (weir Coefficient)
  • 32. 32 • Peak = 118 m3/s • Peak time = 36 hours (8 hours after the peak of inflow) • Duration = about 40 hours 495 118 0 50 100 150 200 250 300 350 400 450 500 0 5 10 15 20 25 30 35 40 45 50 55 60 Discharge(m3/s) Time (Hr) Inflow and Outflow Hydrographs Outflow in section 70 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Outflow result
  • 33. 2- River Modeling 2-3- BASEMENT Model Basement Modeling- Bed and Water level Analysis in CS 70
  • 34. 2- River Modeling 2-3- BASEMENT Model Basement Modeling- outflow in east part of city from section 70 or to both sides of the city in Garibaldi bridge (section 74)
  • 35. 3- City Modeling 3-1- Input Data River2D input data: • Bed geometry • Inflow discharge: Steady model: 118 m^3/s Transient model: 4-hour hydrograph • Inlet position: Case 1: Pedestrian bridge (section 70) Case 2: Garibaldi bridge (section 74) • Inflow depth = average 1 m higher than levee • Outflow depth = 50 m lower than earth surface in order to have dry initial condition • Groundwater Transmissivity = 0.1 (by low values actual ground water discharge is negligible) • Groundwater Storativity = 0.1 (Storativity is a measure of volume of water the ground will release. The default value is 1 but for accurate transient analysis this value should be reduced)
  • 36. 3- City Modeling 3-2- Previous Studies Scenario 1: Q left = 50 m3/sec Q right = 50 m3/sec Our calculation: Q max = 118 m3/sec Q left = west side of the city Q right = east side of the city
  • 37. 3- City Modeling 3-2- Previous Studies Scenario 2: Q left = 100 m3/sec Q right = 195 m3/sec Our calculation: Q max = 118 m3/sec Q left = west side of the city Q right = east side of the city
  • 38. 3- City Modeling 3-2- Previous Studies Scenario 3: Q left = 125 m3/sec Q right = 355 m3/sec Our calculation: Q max = 118 m3/sec Q left = west side of the city Q right = east side of the city
  • 39. 3- City Modeling 3-2- Previous Studies Scenario 3: Q left = 125 m3/sec Q right = 355 m3/sec Our calculation: Q max = 118 m3/sec Q left = west side of the city Q right = east side of the city
  • 40. 3- City Modeling 3-3- Mesh Sensitivity Model 1: Mesh size: 20 m Number of nodes: 4362 Number of elements: 7353 QI = 0.078 Model 2: Mesh size: 40 m Number of nodes: 1565 Number of elements: 2372 QI = 0.073
  • 41. 3- City Modeling 3-3- Mesh Sensitivity Model 1: (run for 10 min flood) Calculation time: 90 min Lowest water depth T = 10 min T = 10 min Q steady = 118 m3/s Model 2: (run for 10 min flood) Calculation time: 6 min
  • 42. 3- City Modeling 3-3- Mesh Sensitivity Model 1: (run for 10 min flood) Calculation time: 90 min T = 10 min T = 10 min Q steady = 118 m3/s Model 2: (run for 10 min flood) Calculation time: 6 min
  • 43. 3- City Modeling 3-3- Mesh Sensitivity Model 3: Mesh size: 80 m Number of nodes: 711 Number of elements: 959 QI = 0.048 Model 4: Mesh size: 120 m Number of nodes: 498 Number of elements: 640 QI = 0.003
  • 44. 3- City Modeling 3-3- Mesh Sensitivity T = 10 min Model 4: (run for 10 min flood) Calculation time: 1 min T = 10 min Q steady = 118 m3/s Model 3: (run for 10 min flood) Calculation time: 2 min
  • 45. 3- City Modeling 3-3- Mesh Sensitivity Model 3: (run for 10 min flood) Calculation time: 2 min T = 10 min T = 10 min Q steady = 118 m3/s Model 4: (run for 10 min flood) Calculation time: 1 min
  • 46. 3- City Modeling 3-3- Mesh Sensitivity T = 60 min Model 4: (run for 60 min flood) Mesh size: 120 m T = 60 min Q steady = 118 m3/s Model 2: (run for 60 min flood) Mesh size: 40 m Almost the same extension of water
  • 47. 3- City Modeling 3-3- Mesh Sensitivity Mesh Sensitivity results • The finer the mesh, the higher the calculation time (mesh size 20 m is very time consuming. But mesh size 40 m has reasonable time for simulation) • The result in terms of water extension is similar (considering all four models for 10 min run and two models for 60 min run) • The result for water depth is different. In coarse meshes, water depth is higher. Therefore results in very coarse meshes are overestimation. • The result for velocity also shows significant differences. Results in small meshes are more accurate. • To have a decent trade-off between calculation time and accuracy, the mesh size 40 m is recommended. This mesh size is used for next part of the study.
  • 48. 3- City Modeling 3-4- Steady Model Q = 118 m3/s T = 10 min T = 20 min Steady Model (Water depth evolution) Inlet in the Pedestrian bridge (critical section 70)
  • 49. 3- City Modeling 3-4- Steady Model Q = 118 m3/s T = 30 min T = 60 min Steady Model (Water depth evolution) Inlet in the Pedestrian bridge (critical section 70)
  • 50. 3- City Modeling 3-4- Steady Model Q = 118 m3/s T = 2 hr T = 3 hr Steady Model (Water depth evolution) Inlet in the Pedestrian bridge (critical section 70)
  • 51. 3- City Modeling 3-4- Steady Model Q = 118 m3/s T = 4 hr T = 6 hr Steady Model (Water depth evolution) Inlet in the Pedestrian bridge (critical section 70)
  • 52. 3- City Modeling 3-4- Steady Model Q = 118 m3/s T = 8 hr Steady Model (Water depth evolution) Inlet in the Pedestrian bridge (critical section 70)
  • 53. 3- City Modeling 3-4- Steady Model Q = 118 m3/s T = 8 hr Steady Model (Velocity) Inlet in the Pedestrian bridge (critical section 70)
  • 54. 3- City Modeling 3-4- Steady Model Steady Model (Water depth evolution) Inlet in the Garibaldi bridge position (section 74) Q = 118 m3/s T = 5 min T = 10 min
  • 55. 3- City Modeling 3-4- Steady Model Q = 118 m3/s T = 20 min T = 30 min Steady Model (Water depth evolution) Inlet in the Garibaldi bridge position (section 74)
  • 56. 3- City Modeling 3-4- Steady Model Q = 118 m3/s T = 40 min T = 50 min Steady Model (Water depth evolution) Inlet in the Garibaldi bridge position (section 74)
  • 57. 3- City Modeling 3-4- Steady Model Q = 118 m3/s T = 60 min Steady Model (Water depth evolution) Inlet in the Garibaldi bridge position (section 74)
  • 58. 3- City Modeling 3-4- Steady Model Steady Model (Velocity) Inlet in the Garibaldi bridge position Q = 118 m3/s T = 60 min
  • 59. 3- City Modeling 3-4- Steady Model Summary In the case of inlet in section 70 (pedestrian bridge) half of the city will not be inundated and results in terms of water extension is not compatible with previous studies. Considering the inlet position in Garibaldi bridge (Section 74), the extension of water are more similar to previous studies. Both cases are probable. In order to have a comparison between our study and old versions, inlet position in Garibaldi bridge was simulated in the transient model.
  • 60. 3- City Modeling 3-5- Transient Model Transient Model Using 4 hours of river out-flow hydrograph 4 hours hydrograph
  • 61. 3- City Modeling 3-5- Transient Model Transient Model (Water depth) T = 0 min T = 5 min
  • 62. 3- City Modeling 3-5- Transient Model Transient Model (Water depth) T = 10 min T = 20 min
  • 63. 3- City Modeling 3-5- Transient Model Transient Model (Water depth) T = 30 min T = 40 min
  • 64. 3- City Modeling 3-5- Transient Model Transient Model (Water depth) T = 50 min T = 60 min (1 hour)
  • 65. 3- City Modeling 3-5- Transient Model Transient Model (Water depth) T = 120 min (2 hour)T = 90 min (1:30) Peak discharge
  • 66. 3- City Modeling 3-5- Transient Model Transient Model (Water depth) T = 240 min (4 hour)T = 180 min (3 hours)
  • 67. 3- City Modeling 3-5- Transient Model Transient Model (Velocity) T = 240 min (4 hour)
  • 68. 4- Results for Emergency Plan Two scenarios are considering for the Emergency Plan 1- scenario number 3 (extreme case) with Qr = 355 m^3/s from previous studies 2- transient simulation with inlet in Garibaldi bridge with Qpeak = 118 m^3/s • Two scenarios have significant differences in terms of water extension and depth. • Max water depth in first scenario is 2.5 m while in the second scenario is limited to 1.5 m. • Max velocity in first scenario is 4 m/s while in the second scenario is 3.5 m. • Since our model has only east part of the city, the result for the west part was concluded from second scenario of the previous studies (Qleft = 100).
  • 69. Combining water depth results from River2D on the city map T = 240 min (4 hours) Transient model Qpeak = 118 m^3/s 4- Results for Emergency Plan
  • 70. 4- Results for Emergency Plan Scenario 3 in previous studies (Qr=355) Our scenario (Qr=118)