SlideShare a Scribd company logo
1 of 39
Download to read offline
Tim Smart
27th June 2016
Tunnel Presentation
P1509 (1) HOL/10014/0002
2
Tunnel Briefing Agenda
1. Operational aspects of tunnels
(1) Safety arrangements
(2) Noise and vibration
(3) Vent shafts and smoke control
(4) Energy use in tunnels
2. Construction
(1) Tunnelling techniques
(2) Shaft construction
(3) Settlement
(4) Construction aspects
3. Costs implications
(1) Costs of tunnelling
P1509 (2) HOL/10014/0003
Tunnel Locations
3
P1509 (3) HOL/10014/0004
Tunnels Phase One
4
Twin BoredTunnel
• 7.4km
• London Clay
Euston
• 14km
• London
Clay/Lambeth/Chalk
Northholt
• 15.8km
• Chalk
Chilterns
• 1.5km
• Penarth Group/Mercia
Mudstone
Long
Itchington
Wood
• 2.8km
• Penarth Group/Mercia
Mudstone
Bromford
Cut & Cover
•1.4km
•Chalk
Wendover
•2.1km
•Glacial Till/Oolite/Whitby
Mudstone
Greatworth
•2.5km
•Low Jurassic
Marlstone/Mudstone
Chipping
Warden
•0.4km
•Penarth Group/Mercia
Mudstone
Long
Itchington
Wood
•0.5km
•Lower Carboniferous
Mudstone
Burton Green
P1509 (4) HOL/10014/0005
1. Operational Aspects of Tunnelling
(1) Safety Arrangements
(2) Noise and Vibration
(3) Vent Shafts and Smoke Control
(4) Energy use in Tunnels
5
P1509 (5) HOL/10014/0006
1.(1) Minimum Safety Requirements (TSI)
Place of relative safety
 If to the surface every 1 km
 To adjacent independent tunnel tube every 500m
Fire Fighting Points - Applies to all tunnels over 1 km and rolling stock dependent
 Tunnel Length 1 to 5 km at portals with minimum standing area
550 sq m
 Tunnels over 5km at every 5km depending on rolling stock
characteristics
Fire Fighting Point defined as
 Location inside or outside tunnel where fire fighting equipment
can be used and passengers can evacuate
 Water Supply capacity is a minimum of 800 l/min for 2 hrs.
6
P1509 (6) HOL/10014/0007
1.(1) Tunnel Cross Passage
7
P1509 (7) HOL/10014/0008
1.(1) Emergency Train Evacuation
8
P1509 (8) HOL/10014/0009
1.(1) Evacuation Walkway & Tunnel Cross Passage Opening HS1
9
P1509 (9) HOL/10014/0010
1.(1) Intervention Gap
10
P1509 (10) HOL/10014/0011
1. (2) Noise and Vibration
11
P1509 (11) HOL/10014/0012
1. (2) Vibration mitigation via “booted sleeper” track
12
P1509 (12) HOL/10014/0013
1. (2) Vent Shafts and Operational Noise
HS2 vent shafts are designed, constructed operated and maintained along
with their associated stationary equipment so that noise in the worst
affected residential receptors conforms to British Standard guidance and
achieves the aims of the Noise Policy Statement for England.
Mechanical equipment within the vent shaft is only operated under the
following circumstances;
 During and emergency
 During maintenance when required to maintain an acceptable air
quality environment.
 During tunnel congestion when required to maintain an acceptable
air quality environment.
13
P1509 (13) HOL/10014/0014
1.(3) Vent Shafts and Smoke Control
Primary Purpose
 Smoke extract and control.
 Pressure relief
 Access for emergency services.
 Passenger comfort to keep air quality and temperature
within acceptable limits.
Secondary Uses
 Tunnel boring machine maintenance intervention.
 Access for railway maintenance.
14
P1509 (14) HOL/10014/0015
1.(3) Vent Shafts along Bored Tunnels
15
P1509 (15) HOL/10014/0016
1. (4) Energy use in Tunnels
Traction power
• Energy required for the traction power of the trains increases
in tunnels.
• In the open air 80% of the energy used by the train goes into
overcoming air resistance. This increases to 90% in a tunnel.
Increased power for Mechanical and Electrical plant and
equipment
• Increase in energy costs for the railway due to the plant
necessary for safety arrangements (e.g fans, lifts, fire mains,
emergency lighting plus tunnel integrity plant (e.g pumps,
cooling arrangements)
16
P1509 (16) HOL/10014/0017
2. Construction
(1) Tunnelling techniques
(2) Shaft construction
(3) Settlement
(4) Construction aspects
17
P1509 (17) HOL/10014/0018
2.(1) Construction
18
P1509 (18) HOL/10014/0019
2.(1) Bored Tunnels
Earth Pressure Balance Tunnel Boring Machine (EPBM)
19
P1509 (19) HOL/10014/0020
2.(1) Bored Tunnels
20
HS1 EPBM in factory showing back up arrangements
P1509 (20) HOL/10014/0021
2.(1) Bored Tunnels
Slurry or “Hydroshield” Tunnel Boring Machine
21
P1509 (21) HOL/10014/0022
2.(1) Segment Yard & Drive Site Locations
22
P1509 (22) HOL/10014/0023
2.(1) Precast Tunnel Lining Manufacture
23
P1509 (23) HOL/10014/0024
2.(1) Construction Plan - West Hyde
24
P1509 (24) HOL/10014/0025
2.(1) Construction Plan – South Heath
25
P1509 (25) HOL/10014/0026
2.(1) Types of Tunnel: Mined tunnel
26
P1509 (26) HOL/10014/0027
2.(1) Cut and Cover
Construction Methodology 1
27
P1509 (27) HOL/10014/0028
2. (1) HS1 Cut and Cover Tunnel
28
P1509 (28) HOL/10014/0029
2. (1) Cut and Cover
Construction Methodology 2
29
P1509 (29) HOL/10014/0030
2. (1) D-wall Construction
30
P1509 (30) HOL/10014/0031
2.(2) Shaft Construction
31
P1509 (31) HOL/10014/0032
2.(3) Settlement
32
INDICATIVE
P1509 (32) HOL/10014/0033
2.(3) Settlement & Rate of Tunnelling
The rate of tunnelling will be important in minimising settlement. This is
achieved by operating tunnel boring machines appropriately such as using
Earth Pressure Balance machines in “closed” mode.
In order to keep settlement to acceptable limits HS2 has specified
maximum of 1% volume loss for bored tunnels.
Continuous 24 hour tunnelling also minimises settlement as it doesn’t
allow time for the for the ground to fully relax.
Other methods of controlling settlement include grouting techniques,
particularly compensation grouting.
33
P1509 (33) HOL/10014/0034
2.(3) Settlement and Protective Measures
The primary form of settlement mitigation will be by good tunnelling practice, including continuous
working. Where required additional measures (e.g. grouting and structural solutions) will be carried
out based on a three stage assessment as set out in Information Paper C3 Ground Settlement.
Phase 1 Assessment: A preliminary assessment based on “green field” conditions will be
undertaken. Where the predicted settlement is less than 10 mm or less than 1/500 slope, no further
assessment required.
Phase 2 Assessment: In the case of predicted settlement of more than 10mm or 1/500 slope an
individual building assessment will be carried out. If the potential damage classification is category
2 (slight) or below no further assessment is required.
Phase 3 Assessment: Where predicted settlement indicates potential damage classification of 3
(moderate) or higher a detailed evaluation will be carried out with the aim to reduce the effects to
acceptable levels. Where this is not possible further protective measures will be implemented.
Settlement Deed. Properties within 30 metres of tunnels may apply for a Deed as set out in
information paper C3 to ensure that protective measures are implemented in accordance with the
assessment criteria.
34
P1509 (34) HOL/10014/0035
2.(4) Construction Aspects – Noise Tunnel Drive Sites
Tunnel drive sites generate similar noise levels to other large
construction sites.
Tunnelling activities and the associated local site material
handling will be operated 24 hours a day.
Noise mitigation is provided by the standard means such as
hoarding, muffling, baffles and noise suppression on plant and
equipment .
Tunnel sites will be subject to the same HS2 procedures set out
under the Code of Construction practice and will be subject to
Local Authority Approval under Section 61 of CoPA.
35
P1509 (35) HOL/10014/0036
2.(4) Construction Aspects – Noise Tunnel Boring
Sound and vibration from the tunnel boring machine will be
perceptible inside properties for a few days either side of the
TBM as it passes beneath them.
The effects of ground‐borne sound and vibration from the
TBM on building occupants will be short‐term and hence they
are not considered to be significant.
36
P1509 (36) HOL/10014/0037
3. Costs of Tunnelling
Fixed Costs
 TBM typically £15 to £25m
 Back up material handling similar costs order
 Power supply
Linear Costs
 Labour
 Lining materials
 Excavated material disposal
 Ground monitoring
 Ground treatment
 Tunnel logistics
Incremental Cost increases
 Surface arrangements for drive sites, reception sites, portal arrangements
 Increase in number of shafts
 Increase in number of cross passages;
 Shaft and tunnel M&E systems.
37
P1509 (37) HOL/10014/0038
Cost vs. Length
38
P1509 (38) HOL/10014/0039
Thank you
P1509 (39) HOL/10014/0040

More Related Content

Similar to Tunnel Construction and Operations Techniques

coal mining training report
coal mining training report coal mining training report
coal mining training report VIKRAMSINGH1231
 
Dust monitoring and control in metal Mines
Dust monitoring and control in metal MinesDust monitoring and control in metal Mines
Dust monitoring and control in metal MinesAdil Mathew
 
Road Tunnel Fire-Life Safety and CFD Modeling
Road Tunnel Fire-Life Safety and CFD ModelingRoad Tunnel Fire-Life Safety and CFD Modeling
Road Tunnel Fire-Life Safety and CFD ModelingWSP
 
Faster Cycle Times The Future Of D&B
Faster Cycle Times The Future Of D&BFaster Cycle Times The Future Of D&B
Faster Cycle Times The Future Of D&Bpatrickhudd
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Abner Silva
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologykumarrajagp
 
Tech Paper Dismantling WAGR PVandI 1999
Tech Paper Dismantling WAGR PVandI 1999Tech Paper Dismantling WAGR PVandI 1999
Tech Paper Dismantling WAGR PVandI 1999Jon Halladay
 
Thomas & Betts - Hazardous Area Electrical Equipment & Cable Accessories
Thomas & Betts - Hazardous Area Electrical Equipment & Cable AccessoriesThomas & Betts - Hazardous Area Electrical Equipment & Cable Accessories
Thomas & Betts - Hazardous Area Electrical Equipment & Cable AccessoriesThorne & Derrick International
 
Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...
Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...
Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...Thorne & Derrick International
 
Opito bosiet safety induction
Opito bosiet safety inductionOpito bosiet safety induction
Opito bosiet safety inductionTejpal Barnela
 
Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Pratap Bhunia
 
Torino Metro Experience
Torino Metro ExperienceTorino Metro Experience
Torino Metro Experiencegifanta
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual meansSafdar Ali
 
Coal handling-guidelines
Coal handling-guidelinesCoal handling-guidelines
Coal handling-guidelinesPRABIR DATTA
 
Change- out P119 Pulley-2
Change- out P119 Pulley-2Change- out P119 Pulley-2
Change- out P119 Pulley-2Scott Jarrold
 
Metro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsMetro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsgifanta
 

Similar to Tunnel Construction and Operations Techniques (20)

coal mining training report
coal mining training report coal mining training report
coal mining training report
 
Dust monitoring and control in metal Mines
Dust monitoring and control in metal MinesDust monitoring and control in metal Mines
Dust monitoring and control in metal Mines
 
Road Tunnel Fire-Life Safety and CFD Modeling
Road Tunnel Fire-Life Safety and CFD ModelingRoad Tunnel Fire-Life Safety and CFD Modeling
Road Tunnel Fire-Life Safety and CFD Modeling
 
Es3
Es3Es3
Es3
 
Satyajeet
SatyajeetSatyajeet
Satyajeet
 
Faster Cycle Times The Future Of D&B
Faster Cycle Times The Future Of D&BFaster Cycle Times The Future Of D&B
Faster Cycle Times The Future Of D&B
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Tech Paper Dismantling WAGR PVandI 1999
Tech Paper Dismantling WAGR PVandI 1999Tech Paper Dismantling WAGR PVandI 1999
Tech Paper Dismantling WAGR PVandI 1999
 
208_fullpaper_notes
208_fullpaper_notes208_fullpaper_notes
208_fullpaper_notes
 
Thomas & Betts - Hazardous Area Electrical Equipment & Cable Accessories
Thomas & Betts - Hazardous Area Electrical Equipment & Cable AccessoriesThomas & Betts - Hazardous Area Electrical Equipment & Cable Accessories
Thomas & Betts - Hazardous Area Electrical Equipment & Cable Accessories
 
Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...
Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...
Thomas & Betts Kopex - Understanding Hazardous Areas & Specifying Flexible Co...
 
Opito bosiet safety induction
Opito bosiet safety inductionOpito bosiet safety induction
Opito bosiet safety induction
 
Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...
 
Report1
Report1Report1
Report1
 
Torino Metro Experience
Torino Metro ExperienceTorino Metro Experience
Torino Metro Experience
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
 
Coal handling-guidelines
Coal handling-guidelinesCoal handling-guidelines
Coal handling-guidelines
 
Change- out P119 Pulley-2
Change- out P119 Pulley-2Change- out P119 Pulley-2
Change- out P119 Pulley-2
 
Metro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsMetro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problems
 

Recently uploaded

Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 

Recently uploaded (20)

Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 

Tunnel Construction and Operations Techniques

  • 1. Tim Smart 27th June 2016 Tunnel Presentation P1509 (1) HOL/10014/0002
  • 2. 2 Tunnel Briefing Agenda 1. Operational aspects of tunnels (1) Safety arrangements (2) Noise and vibration (3) Vent shafts and smoke control (4) Energy use in tunnels 2. Construction (1) Tunnelling techniques (2) Shaft construction (3) Settlement (4) Construction aspects 3. Costs implications (1) Costs of tunnelling P1509 (2) HOL/10014/0003
  • 4. Tunnels Phase One 4 Twin BoredTunnel • 7.4km • London Clay Euston • 14km • London Clay/Lambeth/Chalk Northholt • 15.8km • Chalk Chilterns • 1.5km • Penarth Group/Mercia Mudstone Long Itchington Wood • 2.8km • Penarth Group/Mercia Mudstone Bromford Cut & Cover •1.4km •Chalk Wendover •2.1km •Glacial Till/Oolite/Whitby Mudstone Greatworth •2.5km •Low Jurassic Marlstone/Mudstone Chipping Warden •0.4km •Penarth Group/Mercia Mudstone Long Itchington Wood •0.5km •Lower Carboniferous Mudstone Burton Green P1509 (4) HOL/10014/0005
  • 5. 1. Operational Aspects of Tunnelling (1) Safety Arrangements (2) Noise and Vibration (3) Vent Shafts and Smoke Control (4) Energy use in Tunnels 5 P1509 (5) HOL/10014/0006
  • 6. 1.(1) Minimum Safety Requirements (TSI) Place of relative safety  If to the surface every 1 km  To adjacent independent tunnel tube every 500m Fire Fighting Points - Applies to all tunnels over 1 km and rolling stock dependent  Tunnel Length 1 to 5 km at portals with minimum standing area 550 sq m  Tunnels over 5km at every 5km depending on rolling stock characteristics Fire Fighting Point defined as  Location inside or outside tunnel where fire fighting equipment can be used and passengers can evacuate  Water Supply capacity is a minimum of 800 l/min for 2 hrs. 6 P1509 (6) HOL/10014/0007
  • 7. 1.(1) Tunnel Cross Passage 7 P1509 (7) HOL/10014/0008
  • 8. 1.(1) Emergency Train Evacuation 8 P1509 (8) HOL/10014/0009
  • 9. 1.(1) Evacuation Walkway & Tunnel Cross Passage Opening HS1 9 P1509 (9) HOL/10014/0010
  • 10. 1.(1) Intervention Gap 10 P1509 (10) HOL/10014/0011
  • 11. 1. (2) Noise and Vibration 11 P1509 (11) HOL/10014/0012
  • 12. 1. (2) Vibration mitigation via “booted sleeper” track 12 P1509 (12) HOL/10014/0013
  • 13. 1. (2) Vent Shafts and Operational Noise HS2 vent shafts are designed, constructed operated and maintained along with their associated stationary equipment so that noise in the worst affected residential receptors conforms to British Standard guidance and achieves the aims of the Noise Policy Statement for England. Mechanical equipment within the vent shaft is only operated under the following circumstances;  During and emergency  During maintenance when required to maintain an acceptable air quality environment.  During tunnel congestion when required to maintain an acceptable air quality environment. 13 P1509 (13) HOL/10014/0014
  • 14. 1.(3) Vent Shafts and Smoke Control Primary Purpose  Smoke extract and control.  Pressure relief  Access for emergency services.  Passenger comfort to keep air quality and temperature within acceptable limits. Secondary Uses  Tunnel boring machine maintenance intervention.  Access for railway maintenance. 14 P1509 (14) HOL/10014/0015
  • 15. 1.(3) Vent Shafts along Bored Tunnels 15 P1509 (15) HOL/10014/0016
  • 16. 1. (4) Energy use in Tunnels Traction power • Energy required for the traction power of the trains increases in tunnels. • In the open air 80% of the energy used by the train goes into overcoming air resistance. This increases to 90% in a tunnel. Increased power for Mechanical and Electrical plant and equipment • Increase in energy costs for the railway due to the plant necessary for safety arrangements (e.g fans, lifts, fire mains, emergency lighting plus tunnel integrity plant (e.g pumps, cooling arrangements) 16 P1509 (16) HOL/10014/0017
  • 17. 2. Construction (1) Tunnelling techniques (2) Shaft construction (3) Settlement (4) Construction aspects 17 P1509 (17) HOL/10014/0018
  • 19. 2.(1) Bored Tunnels Earth Pressure Balance Tunnel Boring Machine (EPBM) 19 P1509 (19) HOL/10014/0020
  • 20. 2.(1) Bored Tunnels 20 HS1 EPBM in factory showing back up arrangements P1509 (20) HOL/10014/0021
  • 21. 2.(1) Bored Tunnels Slurry or “Hydroshield” Tunnel Boring Machine 21 P1509 (21) HOL/10014/0022
  • 22. 2.(1) Segment Yard & Drive Site Locations 22 P1509 (22) HOL/10014/0023
  • 23. 2.(1) Precast Tunnel Lining Manufacture 23 P1509 (23) HOL/10014/0024
  • 24. 2.(1) Construction Plan - West Hyde 24 P1509 (24) HOL/10014/0025
  • 25. 2.(1) Construction Plan – South Heath 25 P1509 (25) HOL/10014/0026
  • 26. 2.(1) Types of Tunnel: Mined tunnel 26 P1509 (26) HOL/10014/0027
  • 27. 2.(1) Cut and Cover Construction Methodology 1 27 P1509 (27) HOL/10014/0028
  • 28. 2. (1) HS1 Cut and Cover Tunnel 28 P1509 (28) HOL/10014/0029
  • 29. 2. (1) Cut and Cover Construction Methodology 2 29 P1509 (29) HOL/10014/0030
  • 30. 2. (1) D-wall Construction 30 P1509 (30) HOL/10014/0031
  • 31. 2.(2) Shaft Construction 31 P1509 (31) HOL/10014/0032
  • 33. 2.(3) Settlement & Rate of Tunnelling The rate of tunnelling will be important in minimising settlement. This is achieved by operating tunnel boring machines appropriately such as using Earth Pressure Balance machines in “closed” mode. In order to keep settlement to acceptable limits HS2 has specified maximum of 1% volume loss for bored tunnels. Continuous 24 hour tunnelling also minimises settlement as it doesn’t allow time for the for the ground to fully relax. Other methods of controlling settlement include grouting techniques, particularly compensation grouting. 33 P1509 (33) HOL/10014/0034
  • 34. 2.(3) Settlement and Protective Measures The primary form of settlement mitigation will be by good tunnelling practice, including continuous working. Where required additional measures (e.g. grouting and structural solutions) will be carried out based on a three stage assessment as set out in Information Paper C3 Ground Settlement. Phase 1 Assessment: A preliminary assessment based on “green field” conditions will be undertaken. Where the predicted settlement is less than 10 mm or less than 1/500 slope, no further assessment required. Phase 2 Assessment: In the case of predicted settlement of more than 10mm or 1/500 slope an individual building assessment will be carried out. If the potential damage classification is category 2 (slight) or below no further assessment is required. Phase 3 Assessment: Where predicted settlement indicates potential damage classification of 3 (moderate) or higher a detailed evaluation will be carried out with the aim to reduce the effects to acceptable levels. Where this is not possible further protective measures will be implemented. Settlement Deed. Properties within 30 metres of tunnels may apply for a Deed as set out in information paper C3 to ensure that protective measures are implemented in accordance with the assessment criteria. 34 P1509 (34) HOL/10014/0035
  • 35. 2.(4) Construction Aspects – Noise Tunnel Drive Sites Tunnel drive sites generate similar noise levels to other large construction sites. Tunnelling activities and the associated local site material handling will be operated 24 hours a day. Noise mitigation is provided by the standard means such as hoarding, muffling, baffles and noise suppression on plant and equipment . Tunnel sites will be subject to the same HS2 procedures set out under the Code of Construction practice and will be subject to Local Authority Approval under Section 61 of CoPA. 35 P1509 (35) HOL/10014/0036
  • 36. 2.(4) Construction Aspects – Noise Tunnel Boring Sound and vibration from the tunnel boring machine will be perceptible inside properties for a few days either side of the TBM as it passes beneath them. The effects of ground‐borne sound and vibration from the TBM on building occupants will be short‐term and hence they are not considered to be significant. 36 P1509 (36) HOL/10014/0037
  • 37. 3. Costs of Tunnelling Fixed Costs  TBM typically £15 to £25m  Back up material handling similar costs order  Power supply Linear Costs  Labour  Lining materials  Excavated material disposal  Ground monitoring  Ground treatment  Tunnel logistics Incremental Cost increases  Surface arrangements for drive sites, reception sites, portal arrangements  Increase in number of shafts  Increase in number of cross passages;  Shaft and tunnel M&E systems. 37 P1509 (37) HOL/10014/0038
  • 38. Cost vs. Length 38 P1509 (38) HOL/10014/0039
  • 39. Thank you P1509 (39) HOL/10014/0040