SlideShare a Scribd company logo
1 of 45
Download to read offline
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 1 -
Overvoltage Protection
and
Insulation Coordination
in Power Systems
Prof. Dr.-Ing. Volker Hinrichsen
Dipl.-Ing. Simona Feier-Iova
Technische UniversitƤt Darmstadt
High Voltage Laboratories
Ā© Siemens
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 2 -
What is Insulation Coordination?
Definition in IEC 60071-1
Definition in IEC 60071-1
Definition in IEEE 1313.1
Definition in IEEE 1313.1
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 3 -
Fundamentals of Insulation Coordination
Time duration of (over-)voltage
Possible voltages without arresters
Voltages limited by arresters
Withstand voltage of equipment
Lightning overvoltages
(Microseconds)
Switching overvoltages
(Milliseconds)
Temporary overvoltages
(Seconds)
Highest voltage of equipment
(Continuously)
Magnitude
of
(over-)voltage
/
p.u.
1
2
3
4
0
5
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 4 -
What is Insulation Coordination?
Procedure of insulation coordination [THI-01]
Three elements are involved in the insulation coordination discipline, namely:
ā€¢ the study of the "stresses", both electrical and environmental, acting on the equipment
insulation. This is usually performed by calculations or field measurements;
ā€¢ the study of the "strength" (dielectric withstand characteristics) of the insulation (both
new and aged) when submitted to such stresses, taking into account, when applicable,
the effect of the environmental stresses (pollution, rain, snow, ice, atmospheric
conditions at large altidudes), including the study of the "test and measurement
techniques" which are employed to assess such strength. The strength is determined
by calculations, based on suitable discharge models, and/or by laboratory/factory tests,
on-site tests and in-service measurements (diagnostics);
ā€¢ the assessment of the insulation performance (usually expressed in terms of risk of
failure) in the considered situation of stresses and strength, including the selection and
application of "protective devices and techniques", to establish the final insulation
design fulfilling the specified requirements. This may be based on "deterministic" or
"statistical" approach.
Three elements are involved in the insulation coordination discipline, namely:
ā€¢ the study of the "stresses", both electrical and environmental, acting on the equipment
insulation. This is usually performed by calculations or field measurements;
ā€¢ the study of the "strength" (dielectric withstand characteristics) of the insulation (both
new and aged) when submitted to such stresses, taking into account, when applicable,
the effect of the environmental stresses (pollution, rain, snow, ice, atmospheric
conditions at large altidudes), including the study of the "test and measurement
techniques" which are employed to assess such strength. The strength is determined
by calculations, based on suitable discharge models, and/or by laboratory/factory tests,
on-site tests and in-service measurements (diagnostics);
ā€¢ the assessment of the insulation performance (usually expressed in terms of risk of
failure) in the considered situation of stresses and strength, including the selection and
application of "protective devices and techniques", to establish the final insulation
design fulfilling the specified requirements. This may be based on "deterministic" or
"statistical" approach.
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 5 -
Literature (1)
[BAL-04-1] G. Balzer
Power Systems, Part 2
Chapter 4: Insulation coordination
Script TU Darmstadt, 2004
[BAL-04-2] G. Balzer
Elektrische Energieversorgung, Teil 2
Kapitel 4: Isolationskoordination
Skript der TU Darmstadt, 2004
[CIG-73] CIGRE W.G. 13-02
Switching overvoltages in EHV and UHV systems with special reference
to closing and reclosing transmission lines
ELECTRA 30 (1973) pp. 70-122
[CIG-79-1] CIGRE WG 33.02
Phase-to-phase Insulation Co-ordination:
Part 1: Switching overvoltages in three-phase systems
ELECTRA 64 (1979) pp. 138-158
[CIG-79-2] CIGRE WG 33.03
Phase-to-phase Insulation Co-ordination
Part 2: Switching impulse strength of phase-to-phase external insulation
ELECTRA 64 1979, pp. 158-181
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 6 -
Literature (2)
[CIG-79-3] CIGRE WG 33.06
Phase-to-phase Insulation Co-ordination
Part 3: Design and testing of phase-to-phase insulation
ELECTRA 64 1979, pp. 182-210
[CIG-79-4] CIGRE TF 33-03.03
Phase-to-phase Insulation Co-ordination
Part 4: The influence of non-standard conditions on the switching impulse strength
of phase-to-phase insulation
ELECTRA 64 1979, pp. 211-230
[CIG-91] CIGRE WG 33.01
Guide to procedures for estimating the lightning performance of
transmission lines, CIGRE technical brochure No. 63, 1991
buch_020.pdf
[CIG-92] CIGRE WG 33-07
Guidelines for the evaluation of the dielectric strength of external
insulation, CIGRE technical brochure No. 72, 1992
buch_019.pdf
[DOR-81] H. Dorsch
Ɯberspannungen und Isolationsbemessung bei Drehstrom-Hochspannungsanlagen
Siemens AG, Erlangen, 1981 (ISBN 3-8009-1325-9)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 7 -
Literature (3)
[ERI-88] A.J. Eriksson, K.-H. Weck
Simplified procedures for determining representative substation impinging lightning
overvoltages, CIGRE report 33-16, 1988
[ETG-93] ETG-Fachbericht 49
ETG-Tage '93: Isolationskoordination in Hoch- und Mittelspannungsanlagen
vde-Verlag GmbH Berlin, Offenbach (ISBN 0341-3934)
[FGH-78] FGH Technischer Bericht 1-240
Isolationskoordination auf der Grundlage der neuen DIN/VDE-Bestimmung 0111
FGH, Mannheim, Juli 1978
[HIL-99] A. R. Hileman
Insulation Coordination for Power Systems
Marcel Dekker, Inc., New York, Basel, 1999
[HIN-00] V. Hinrichsen
Metalloxidableiter: Grundlagen
Siemens AG Berlin, 1. Auflage 2000
AbleiterBuch.pdf
[HIN-01] V. Hinrichsen
Metalloxidableiter: Grundlagen
Siemens AG Berlin, Edition 1, 2001
ArresterBook.pdf
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 8 -
[HIN-03] V. Hinrichsen
Latest Designs and Service Experience with Station-Class Polymer Housed Surge Arresters
World Conference on Insulators, Arresters & Bushings
Marbella (MƔlaga), Spain, November 16-19, 2003, Proceedings pp. 85-96
pub_048.pdf
[KIN-05] V. Hinrichsen
Latest Testing Requirements and Emerging Standards for Transmission Line Arresters
World Conference on Insulators, Arresters & Bushings
Hong Kong, November 27-30, 2005
inmr_2005_paper.pdf
[KIS-84] I. Kishizima, K. Matsumoto, Y. Watanabe, New facilities for phase switching impulse
tests and some test results, IEEE PAS TO3 No. 6, June 1984 pp. 1211-1216.
[KOE-93-1] D. Kƶnig, Y. N. Rao
Teilentladungen in Betriebsmitteln der Energietechnik
vde-Verlag, Berlin, Offenburg, 1993, ISBN 3-8007-1764-6
[KOE-93-2] D. Kƶnig, Y. N. Rao
Partial discharges in Power Apparatus
vde-Verlag, Berlin, Offenburg, 1993, ISBN 3-8007-1760-3
Literature (4)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 9 -
[PAR-68] L. Paris, R. Cortina
Switching and lightning impulse discharge characteristics of large air gaps and long insulation
strings, IEEE Trans on PAS, vol 87, No. 4, April 1968, p. 947-957
[RUD-99-1] R. Rudolph, B. Richter
Dimensioning, testing and application of metal oxide surge arresters in medium voltage networks
3rd Edition, 1999, ABB Switzerland, 26 pages (also available in German)
application_guide_medium_voltage_networks.pdf
[RUD-99-2] R. Rudolph, B. Richter
Bemessung, PrĆ¼fung und Einsatz von Metalloxid-Ableitern in Mittelspannungsnetzen
ABB Schweiz AG, Wettingen (CH), 3. Auflage 1999
Anwendungsrichtlinien_Mittelspannung.pdf
[THI-01] L. Thione
Insulation coordination in electrical power systems ā€“ theory and application
Tutorial, ALPI, Milan, 2001 (www.alpiass.com)
buch_018.pdf
Literature (5)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 10 -
[WEC-07] K.-H. Weck
Standardization of insulation withstand levels for UHV systems in
IEC TC 28 ā€žInsulation co-ordinationā€
IEC/CIGRE UHV Symposium Beijing 18-21 July 2007, report 5-4
5-4_KHWeck.pdf
Overview on CIGRE publications (very interesting!): CigrƩ Catalogue of Publications 01/07/2005
CATALOGUE_PUBLICATIONS_2005.pdf
Literature (6)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 11 -
IEC 60071-1, Edition 8.0 (2006-01)
Insulation co-ordination ā€“ Part 1: Definitions, principles and rules
IEC 60071-2, Third Edition (1996-12)
Insulation co-ordination ā€“ Part 2: Application guide
IEC/TR 60071-4, First Edition (2004-06)
Insulation co-ordination - Part 4: Computational guide to insulation co-ordination and modelling of
electrical networks
IEC 60099-4, Ed. 2.1, 2006-07
Surge arresters ā€“ Part 4: Metal-oxide surge arresters without gaps for a.c. systems
IEC 60099-5, Ed. 1.1, 2000-03
Surge arresters ā€“ Part 5: Selection and application recommendations
DIN EN 60071-1, 1996-07
Isolationskoordination - Teil 1: Begriffe, GrundsƤtze und Anforderungen (IEC 60071-1:1993); Deutsche Fassung EN
60071-1:1995
DIN EN 60071-2, 1997-09
Isolationskoordination - Teil 2: Anwendungsrichtlinie (IEC 60071-2:1996); Deutsche Fassung EN 60071-2:1997
IEEE 1313.1-1996
IEEE Standard for Insulation Coordinationā€”Definitions, Principles, and Rules
Standards (1)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 12 -
IEEE 1313.2-1999
IEEE Guide for the Application of Insulation Coordination
IEEE C62.11-2005
IEEE Standard for Metal-Oxide Surge Arresters for AC Power Circuits (> 1 kV)
IEEE C62.22-1997
IEEE Guide for the Application of Metal-Oxide Surge Arresters for Alternating-Current Systems
Standards (2)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 13 -
Organization
Lecture 13
31.01.2008
13
Test procedures; condition monitoring (life time aspects, partial
discharges, non-conventional approaches)
Lecture 12
24.01.2008
12
Calculation Examples
Lecture 11
17.01.2008
11
Insulation coordination
Lecture 10
10.01.2008
10
Christmas holidays
03.01.2008
Christmas holidays
27.12.2007
Insulation coordination
Lecture 9
20.12.2007
9
pollution, rain, parallel insulation, aging)
Lecture 8
13.12.2007
8
Dielectric strength (incl. gap factors,
Lecture 7
06.12.2007
7
Overvoltage protection incl. protective distance
Lecture 6
29.11.2007
6
Traveling waves
Lecture 5
22.11.2007
5
Lecture 4
15.11.2007
4
cancelled
08.11.2007
Lecture 3
01.11.2007
3 Voltage stresses
in power systems
Lecture 2
25.10.2007
2
Introduction
Lecture 1
18.10.2007
1
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 14 -
Organization
Examination
Examination
Exclusively oral
Exercises
Exercises
None; but calculation examples in the lecture
Script
Script
Slides will be available for download
www.hst.tu-darmstadt.de
User: studentiso
PW: isows0708
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 15 -
Insulation Coordination - Principles
Environment
System
System voltages
Dielectric
strength
Equipment
Overvoltage
protection devices
stress
versus
strength
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 16 -
Insulation Coordination - Principles
ā€¢ Voltages of the system
ā€“ Nominal voltage Un
Ā» rounded value for characterizing the system
Ā» 10 kV - 20 kV - 110 kV - 220 kV - 380 kV
ā€“ System voltage
Ā» voltage at which the system is being operated
Ā» around the nominal value, but not constant
ā€“ Highest system voltage Us
Ā» highest operating voltage between phases under normal conditions
Ā» 12 kV - 24 kV - 123 kV - 245 kV - 420 kV (IEC 60038)
ā€¢ Voltages of equipment
ā€“ Highest voltage for equipment Um
Ā» highest voltage between phases for which the insulation is designed
Ā» 12 kV - 24 kV - 123 kV - 245 kV - 420 kV (IEC 60071-1)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 17 -
Insulation Coordination - Principles
ā€¢ Overvoltages
ā€“ voltages exceeding the peak value of the highest system voltage
ā€“ various amplitudes and shapes depending on
Ā» system configuration (grid size, degree of meshing, etc.)
Ā» origin of overvoltage (failure, switching, lightning strike etc.)
ā€¢ Dielectric strength of insulation
ā€“ verified by type test in the laboratory with the help of
Ā» standardized test voltages (shape, amplitude)
Ā» specified test setups
Ā» specified environmental conditions
ā€¢ Insulation coordination
ā€“ Determination of interdependence between voltages and
overvoltages of the system and necessary test voltages for the
equipment in the laboratory
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 18 -
Insulation Coordination - Principles
Equipment in
the laboratory
Equipment in
the laboratory
Equipment in
the system
Equipment in
the system
Variety of amplitudes and
shapes of overvoltages
Variety of amplitudes and
shapes of overvoltages
Standardized amplitudes
and shapes of test voltages
Standardized amplitudes
and shapes of test voltages
Variety of operating
conditions and age
Variety of operating
conditions and age
Standardized setups
and conditions
Standardized setups
and conditions
Variety of
environmental conditions
Variety of
environmental conditions
Standardized
environmental conditions
Standardized
environmental conditions
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 19 -
Insulation Coordination - Principles
line
bb 1
bb 2
busbar disconnectors
Insulation phase - ground
stressed by voltages between one phase and ground
1
Insulation phase - phase
stressed by voltages between two phases
2
Longitudinal insulation
stressed by voltages between same phases of
two different systems
3
2
3
1
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 20 -
Insulation Coordination according to IEC 60071-1 (and 60071-2)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 21 -
Insulation Coordination according to IEC 60071-1 (and 60071-2)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 22 -
Insulation Coordination according to IEC 60071-1 (and 60071-2)
Procedure for
insulation
coordination
= 10 pages!
Procedure for
insulation
coordination
= 10 pages!
...39 pages in sum
...39 pages in sum
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 23 -
Insulation Coordination according to IEC 60071-1 (and 60071-2)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 24 -
Insulation Coordination according to IEC 60071-1 (and 60071-2)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 25 -
Insulation Coordination according to IEC 60071-1 (and 60071-2)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 26 -
Insulation Coordination according to IEC 60071-1 (and 60071-2)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 27 -
Insulation Coordination according to IEC 60071-1 (and 60071-2)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 28 -
Insulation Coordination according to IEC 60071-1 (and 60071-2)
...125 pages in sum
...125 pages in sum
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 29 -
Procedure for Insulation Coordination - General
The procedure for insulation coordination consists of the selection of a set of
standard withstand voltages which characterize the insulation of the
equipment.
Range I Range II
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 30 -
Procedure for Insulation Coordination - General
Basic difference between ranges I and II
withstand
voltage
time duration of stress
peak
gap spacing 3 m
gap spacing 0.5 m
[FGH-78]
Minimum of withstand
voltage for switching
overvoltage
Minimum of withstand
voltage for switching
overvoltage
Withstand voltage
continuously
decreasing with time
duration of stress
Withstand voltage
continuously
decreasing with time
duration of stress
Range I
Range I
Range II
Range II
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 31 -
Procedure for Insulation Coordination in Four Steps
Determination of the representative overvoltages Urp
ā€¢ The representative overvoltages are derived from real service conditions, but have
just standardized shapes.
ā€¢ They are determined in amplitude, shape and duration by system analysis, taking
into account overvoltage limiting devices.
[IEC 60071-1]
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 32 -
Determination of the coordination withstand voltages Ucw
ā€¢ The coordination withstand voltages are the lowest values of withstand voltages of
each overvoltage class, for which the expected low failure rate of the equipment is not
exceeded over its full lifetime.
ā€¢ Derived from the representative overvoltages Urp by the coordination factor Kc.
[IEC 60071-1]
Procedure for Insulation Coordination in Four Steps
Typical for
Germany:
0.1% per year
 1 failure in
1000 years
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 33 -
Procedure for Insulation Coordination in Four Steps
Deterministic approach
Deterministic approach Statistical approach
Statistical approach
Assumed maximum
of representative overvoltage
Assumed maximum
of representative overvoltage
Multiplication by coordination
factor based on
operating experience
Multiplication by coordination
factor based on
operating experience
Statistical distribution of
representative overvoltages
Statistical distribution of
representative overvoltages
Determination of
failure probability of insulation
Determination of
failure probability of insulation
Calculation of failure risk
depending on assumed
coordination withstand voltage
Calculation of failure risk
depending on assumed
coordination withstand voltage
Coordination withstand voltage
Assumed conventional Ucw (0% value) Statistical Ucw (10% value)
Coordination withstand voltage
Assumed conventional Ucw (0% value) Statistical Ucw (10% value)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 34 -
Determination of the required withstand voltages Urw
ā€¢ The required withstand voltages are determined by converting the coordination withstand
voltages to appropriate standard test conditions.
ā€¢ Usually different from the coordination withstand voltages.
ā€¢ Derived from the coordination withstand voltages Ucw by the safety factor Ks and the
atmospheric correction factor Kt or the altitude correction factor Ka.
[IEC 60071-1]
Procedure for Insulation Coordination in Four Steps
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 35 -
[IEC 60071-1]
Procedure for Insulation Coordination in Four Steps
Influences covered by the safety factor Ks
ā€¢ Differences in equipment assembly
ā€¢ Dispersion in product quality
ā€¢ Quality of installation
ā€¢ Aging of the installation during expected lifetime
ā€¢ Other unknown influences
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 36 -
Determination of the required withstand voltages Urw
ā€¢ The required withstand voltages are determined by converting the coordination withstand
voltages to appropriate standard test conditions.
ā€¢ Usually different from the coordination withstand voltages.
ā€¢ Derived from the coordination withstand voltages Ucw by the safety factor Ks and/or the
altitude correction factor Ka.
[IEC 60071-1]
Procedure for Insulation Coordination in Four Steps
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 37 -
Selection of the rated and of the standard insulation level
(set of standard rated withstand voltages Uw)
ā€¢ Most economical set of standard withstand voltages Uw of the insulation to prove that all
the required withstand voltages are met.
ā€¢ For each range (I or II) a combination of only two withstand voltages defined:
Range I: standard lightning impulse withstand voltage
standard short-duration power-frequency withstand voltage
Range II: standard switching impulse withstand voltage
standard lightning impulse withstand voltage
ā€¢ For range I, only phase-to-earth standard withstand voltages are defined, which have to
cover phase-to-earth, phase-to-phase and longitudinal insulation.
Procedure for Insulation Coordination in Four Steps
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 38 -
[IEC 60071-1]
Procedure for Insulation Coordination in Four Steps
Definitions
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 39 -
Procedure for Insulation Coordination in Four Steps
Examples forā€¦
... non-self-restoring insulation
(power transformers,
instrument transformers*))
*) mixed insulation
... self-restoring
insulation
(disconnectors,
insulators)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 40 -
[IEC 60071-1]
Procedure for Insulation Coordination in Four Steps
List of standard short-duration power-frequency withstand voltages (r.m.s. values in kV)
630
570
510
480
460
395
360
325
275
230
185
140
95
70
50
38
28
20
10
1800
750
95
1950
850
125
1675
650
75
2100
950
145
2400
2250
1550
1425
1300
1175
1050
550
450
325
250
170
60
40
20
List of standard impulse withstand voltages (peak values in kV)
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 41 -
The standard voltage values are
all the same for
ā€¢ phase-to-earth-,
ā€¢ phase-to-phase-,
ā€¢ longitudinal
insulation!
Range I:
Um = 1 kV up to and including Um = 245 kV
Procedure for Insulation Coordination in Four Steps
[IEC 60071-1]
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 42 -
Range II:
Um above 245 kV
Different standard voltage values for
ā€¢ phase-to-earth-,
ā€¢ phase-to-phase-,
ā€¢ longitudinal
insulation!
Procedure for Insulation Coordination in Four Steps
[IEC 60071-1]
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 43 -
Procedure for Insulation Coordination in Four Steps
Outcome of insulation coordination
ā€“ For three types of insulation
Ā» phase to ground
Ā» phase to phase
Ā» longitudinal
ā€“ and for 4 values each of required withstand voltages Urw
Ā» required continuous operating voltage
Ā» required short-duration power-frequency withstand voltage
Ā» required switching impulse withstand voltage
Ā» required lightning impulse withstand voltage



 Standardization of tests for equipment
ā€“ Reduction of these 12 values to a necessary minimum number of
withstand voltages Uw of the insulation
ā€“ Determination of necessary withstand voltages from tables for two
ranges of highest voltage for equipment
twelve
voltages
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 44 -
[IEC 60071-1]
Procedure for Insulation Coordination in Four Steps - Summary
Flow chart acc. to IEC 60071-1
(Figure 1)
continued next slide
Fachgebiet
Hochspannungstechnik
Overvoltage Protection and Insulation Coordination / Chapter 1 - 45 -
[IEC 60071-1]
Procedure for Insulation Coordination in Four Steps - Summary
Flow chart acc. to IEC 60071-1
(Figure 1) (continued)

More Related Content

What's hot

Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable SizingLeonardo ENERGY
Ā 
1.9 protection of power system
1.9 protection of power system1.9 protection of power system
1.9 protection of power systemW3Edify
Ā 
Coordinacion de aislamiento
Coordinacion de aislamientoCoordinacion de aislamiento
Coordinacion de aislamientoErika Aguilar
Ā 
Static var compensator
Static var compensatorStatic var compensator
Static var compensatorVinay Vishwakarma
Ā 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adamShaik Abdullah Adam
Ā 
Automatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino reportAutomatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino reportSelf-employed
Ā 
PARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERSPARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERSPower System Operation
Ā 
Overload capacity of power transformers
Overload capacity of power transformersOverload capacity of power transformers
Overload capacity of power transformersLeonardo ENERGY
Ā 
Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Kamran Gillani
Ā 
Relay coordination
Relay coordinationRelay coordination
Relay coordinationVB Engineering
Ā 
DigSILENT PF - 03 emt presentation
DigSILENT PF - 03 emt presentationDigSILENT PF - 03 emt presentation
DigSILENT PF - 03 emt presentationHimmelstern
Ā 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentalsmichaeljmack
Ā 
Differential Relay.pptx
Differential Relay.pptxDifferential Relay.pptx
Differential Relay.pptxMahmoudMustafa84
Ā 
Harmonic analysis procedure
Harmonic analysis procedureHarmonic analysis procedure
Harmonic analysis proceduresrini09
Ā 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection michaeljmack
Ā 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modelingHimmelstern
Ā 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
Ā 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION moiz89
Ā 

What's hot (20)

Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
Ā 
1.9 protection of power system
1.9 protection of power system1.9 protection of power system
1.9 protection of power system
Ā 
Coordinacion de aislamiento
Coordinacion de aislamientoCoordinacion de aislamiento
Coordinacion de aislamiento
Ā 
Static var compensator
Static var compensatorStatic var compensator
Static var compensator
Ā 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adam
Ā 
Automatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino reportAutomatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino report
Ā 
PARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERSPARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERS
Ā 
Overload capacity of power transformers
Overload capacity of power transformersOverload capacity of power transformers
Overload capacity of power transformers
Ā 
Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)
Ā 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
Ā 
DigSILENT PF - 03 emt presentation
DigSILENT PF - 03 emt presentationDigSILENT PF - 03 emt presentation
DigSILENT PF - 03 emt presentation
Ā 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
Ā 
Differential Relay.pptx
Differential Relay.pptxDifferential Relay.pptx
Differential Relay.pptx
Ā 
Harmonic analysis procedure
Harmonic analysis procedureHarmonic analysis procedure
Harmonic analysis procedure
Ā 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection
Ā 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modeling
Ā 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
Ā 
Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protection
Ā 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
Ā 
Overcurrent coordination
Overcurrent coordinationOvercurrent coordination
Overcurrent coordination
Ā 

Similar to Overvoltage Protection and Insulation Coordination in Power System.pdf

Metal oxide surge arresters
Metal oxide surge arrestersMetal oxide surge arresters
Metal oxide surge arrestersazzaabo
Ā 
Defense In Depth Of Electrical Systems Preliminary Findings And Recommendat...
Defense In Depth Of Electrical Systems   Preliminary Findings And Recommendat...Defense In Depth Of Electrical Systems   Preliminary Findings And Recommendat...
Defense In Depth Of Electrical Systems Preliminary Findings And Recommendat...John Bickel
Ā 
17thEdition.ppt
17thEdition.ppt17thEdition.ppt
17thEdition.pptChadWood16
Ā 
6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_web6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_webLaurence Michael, PE
Ā 
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDINGA LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDINGIJEEE
Ā 
IEC61482 Box Method For Testing Clothing PPE Against Thermal Hazards Of An E...
IEC61482 Box Method For Testing Clothing PPE Against Thermal Hazards Of  An E...IEC61482 Box Method For Testing Clothing PPE Against Thermal Hazards Of  An E...
IEC61482 Box Method For Testing Clothing PPE Against Thermal Hazards Of An E...Thorne & Derrick International
Ā 
Microcontroller based transformer protectio
Microcontroller based transformer protectioMicrocontroller based transformer protectio
Microcontroller based transformer protectioAminu Bugaje
Ā 
HAKEL_-_Surge_Protection_Device (1) (1)
HAKEL_-_Surge_Protection_Device (1) (1)HAKEL_-_Surge_Protection_Device (1) (1)
HAKEL_-_Surge_Protection_Device (1) (1)Allied Power APS
Ā 
The_insulation_of_HVDC_extruded_cable_sy.pdf
The_insulation_of_HVDC_extruded_cable_sy.pdfThe_insulation_of_HVDC_extruded_cable_sy.pdf
The_insulation_of_HVDC_extruded_cable_sy.pdfAhmed Refai ,M. Sc.,Ph. D
Ā 
Switchgear and Protection ...........................
Switchgear and Protection ...........................Switchgear and Protection ...........................
Switchgear and Protection ...........................MANOJ KHARADE
Ā 
Switchgear and Protection.................
Switchgear and Protection.................Switchgear and Protection.................
Switchgear and Protection.................MANOJ KHARADE
Ā 
S4 oman wind energy the technology 2016
S4 oman wind energy the technology 2016S4 oman wind energy the technology 2016
S4 oman wind energy the technology 2016CETN
Ā 
Study on Influence of Inverted V and W-Frame Column Support on Dynamic Behavi...
Study on Influence of Inverted V and W-Frame Column Support on Dynamic Behavi...Study on Influence of Inverted V and W-Frame Column Support on Dynamic Behavi...
Study on Influence of Inverted V and W-Frame Column Support on Dynamic Behavi...IRJET Journal
Ā 
HJC X2 Durable film capacitor thb heavy duty http://www.hjceurope.com
HJC X2 Durable film capacitor thb heavy duty  http://www.hjceurope.comHJC X2 Durable film capacitor thb heavy duty  http://www.hjceurope.com
HJC X2 Durable film capacitor thb heavy duty http://www.hjceurope.comaytacgulweb
Ā 
MO SURGE ARRESTERS - METAL OXIDE RESISTORS AND SURGE ARRESTERS FOR EMERGING S...
MO SURGE ARRESTERS - METAL OXIDE RESISTORS AND SURGE ARRESTERS FOR EMERGING S...MO SURGE ARRESTERS - METAL OXIDE RESISTORS AND SURGE ARRESTERS FOR EMERGING S...
MO SURGE ARRESTERS - METAL OXIDE RESISTORS AND SURGE ARRESTERS FOR EMERGING S...Power System Operation
Ā 
Hitachi_Energy_MV_Surge_Arrester_Application_Guidelines.pptx
Hitachi_Energy_MV_Surge_Arrester_Application_Guidelines.pptxHitachi_Energy_MV_Surge_Arrester_Application_Guidelines.pptx
Hitachi_Energy_MV_Surge_Arrester_Application_Guidelines.pptxAshokNarayanTripathi
Ā 
03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammerprasadkappala
Ā 
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsHybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsMahesh Chandra Manav
Ā 

Similar to Overvoltage Protection and Insulation Coordination in Power System.pdf (20)

Metal oxide surge arresters
Metal oxide surge arrestersMetal oxide surge arresters
Metal oxide surge arresters
Ā 
Defense In Depth Of Electrical Systems Preliminary Findings And Recommendat...
Defense In Depth Of Electrical Systems   Preliminary Findings And Recommendat...Defense In Depth Of Electrical Systems   Preliminary Findings And Recommendat...
Defense In Depth Of Electrical Systems Preliminary Findings And Recommendat...
Ā 
17thEdition.ppt
17thEdition.ppt17thEdition.ppt
17thEdition.ppt
Ā 
6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_web6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_web
Ā 
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDINGA LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
Ā 
IEC61482 Box Method For Testing Clothing PPE Against Thermal Hazards Of An E...
IEC61482 Box Method For Testing Clothing PPE Against Thermal Hazards Of  An E...IEC61482 Box Method For Testing Clothing PPE Against Thermal Hazards Of  An E...
IEC61482 Box Method For Testing Clothing PPE Against Thermal Hazards Of An E...
Ā 
Microcontroller based transformer protectio
Microcontroller based transformer protectioMicrocontroller based transformer protectio
Microcontroller based transformer protectio
Ā 
HAKEL_-_Surge_Protection_Device (1) (1)
HAKEL_-_Surge_Protection_Device (1) (1)HAKEL_-_Surge_Protection_Device (1) (1)
HAKEL_-_Surge_Protection_Device (1) (1)
Ā 
The_insulation_of_HVDC_extruded_cable_sy.pdf
The_insulation_of_HVDC_extruded_cable_sy.pdfThe_insulation_of_HVDC_extruded_cable_sy.pdf
The_insulation_of_HVDC_extruded_cable_sy.pdf
Ā 
Epcos 5
Epcos 5Epcos 5
Epcos 5
Ā 
Switchgear and Protection ...........................
Switchgear and Protection ...........................Switchgear and Protection ...........................
Switchgear and Protection ...........................
Ā 
Switchgear and Protection.................
Switchgear and Protection.................Switchgear and Protection.................
Switchgear and Protection.................
Ā 
S4 oman wind energy the technology 2016
S4 oman wind energy the technology 2016S4 oman wind energy the technology 2016
S4 oman wind energy the technology 2016
Ā 
Ex ic Intrinsic Safety New Protection Level
Ex ic  Intrinsic Safety New Protection LevelEx ic  Intrinsic Safety New Protection Level
Ex ic Intrinsic Safety New Protection Level
Ā 
Study on Influence of Inverted V and W-Frame Column Support on Dynamic Behavi...
Study on Influence of Inverted V and W-Frame Column Support on Dynamic Behavi...Study on Influence of Inverted V and W-Frame Column Support on Dynamic Behavi...
Study on Influence of Inverted V and W-Frame Column Support on Dynamic Behavi...
Ā 
HJC X2 Durable film capacitor thb heavy duty http://www.hjceurope.com
HJC X2 Durable film capacitor thb heavy duty  http://www.hjceurope.comHJC X2 Durable film capacitor thb heavy duty  http://www.hjceurope.com
HJC X2 Durable film capacitor thb heavy duty http://www.hjceurope.com
Ā 
MO SURGE ARRESTERS - METAL OXIDE RESISTORS AND SURGE ARRESTERS FOR EMERGING S...
MO SURGE ARRESTERS - METAL OXIDE RESISTORS AND SURGE ARRESTERS FOR EMERGING S...MO SURGE ARRESTERS - METAL OXIDE RESISTORS AND SURGE ARRESTERS FOR EMERGING S...
MO SURGE ARRESTERS - METAL OXIDE RESISTORS AND SURGE ARRESTERS FOR EMERGING S...
Ā 
Hitachi_Energy_MV_Surge_Arrester_Application_Guidelines.pptx
Hitachi_Energy_MV_Surge_Arrester_Application_Guidelines.pptxHitachi_Energy_MV_Surge_Arrester_Application_Guidelines.pptx
Hitachi_Energy_MV_Surge_Arrester_Application_Guidelines.pptx
Ā 
03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer
Ā 
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsHybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Ā 

Recently uploaded

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
Ā 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
Ā 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
Ā 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
Ā 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
Ā 
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”soniya singh
Ā 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
Ā 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
Ā 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
Ā 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
Ā 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
Ā 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
Ā 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
Ā 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
Ā 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
Ā 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
Ā 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
Ā 

Recently uploaded (20)

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
Ā 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Ā 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
Ā 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
Ā 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
Ā 
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Ā 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
Ā 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
Ā 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
Ā 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
Ā 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Ā 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Ā 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Ā 
ā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
ā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCRā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
ā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
Ā 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Ā 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
Ā 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Ā 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
Ā 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
Ā 

Overvoltage Protection and Insulation Coordination in Power System.pdf

  • 1. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 1 - Overvoltage Protection and Insulation Coordination in Power Systems Prof. Dr.-Ing. Volker Hinrichsen Dipl.-Ing. Simona Feier-Iova Technische UniversitƤt Darmstadt High Voltage Laboratories Ā© Siemens
  • 2. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 2 - What is Insulation Coordination? Definition in IEC 60071-1 Definition in IEC 60071-1 Definition in IEEE 1313.1 Definition in IEEE 1313.1
  • 3. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 3 - Fundamentals of Insulation Coordination Time duration of (over-)voltage Possible voltages without arresters Voltages limited by arresters Withstand voltage of equipment Lightning overvoltages (Microseconds) Switching overvoltages (Milliseconds) Temporary overvoltages (Seconds) Highest voltage of equipment (Continuously) Magnitude of (over-)voltage / p.u. 1 2 3 4 0 5
  • 4. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 4 - What is Insulation Coordination? Procedure of insulation coordination [THI-01] Three elements are involved in the insulation coordination discipline, namely: ā€¢ the study of the "stresses", both electrical and environmental, acting on the equipment insulation. This is usually performed by calculations or field measurements; ā€¢ the study of the "strength" (dielectric withstand characteristics) of the insulation (both new and aged) when submitted to such stresses, taking into account, when applicable, the effect of the environmental stresses (pollution, rain, snow, ice, atmospheric conditions at large altidudes), including the study of the "test and measurement techniques" which are employed to assess such strength. The strength is determined by calculations, based on suitable discharge models, and/or by laboratory/factory tests, on-site tests and in-service measurements (diagnostics); ā€¢ the assessment of the insulation performance (usually expressed in terms of risk of failure) in the considered situation of stresses and strength, including the selection and application of "protective devices and techniques", to establish the final insulation design fulfilling the specified requirements. This may be based on "deterministic" or "statistical" approach. Three elements are involved in the insulation coordination discipline, namely: ā€¢ the study of the "stresses", both electrical and environmental, acting on the equipment insulation. This is usually performed by calculations or field measurements; ā€¢ the study of the "strength" (dielectric withstand characteristics) of the insulation (both new and aged) when submitted to such stresses, taking into account, when applicable, the effect of the environmental stresses (pollution, rain, snow, ice, atmospheric conditions at large altidudes), including the study of the "test and measurement techniques" which are employed to assess such strength. The strength is determined by calculations, based on suitable discharge models, and/or by laboratory/factory tests, on-site tests and in-service measurements (diagnostics); ā€¢ the assessment of the insulation performance (usually expressed in terms of risk of failure) in the considered situation of stresses and strength, including the selection and application of "protective devices and techniques", to establish the final insulation design fulfilling the specified requirements. This may be based on "deterministic" or "statistical" approach.
  • 5. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 5 - Literature (1) [BAL-04-1] G. Balzer Power Systems, Part 2 Chapter 4: Insulation coordination Script TU Darmstadt, 2004 [BAL-04-2] G. Balzer Elektrische Energieversorgung, Teil 2 Kapitel 4: Isolationskoordination Skript der TU Darmstadt, 2004 [CIG-73] CIGRE W.G. 13-02 Switching overvoltages in EHV and UHV systems with special reference to closing and reclosing transmission lines ELECTRA 30 (1973) pp. 70-122 [CIG-79-1] CIGRE WG 33.02 Phase-to-phase Insulation Co-ordination: Part 1: Switching overvoltages in three-phase systems ELECTRA 64 (1979) pp. 138-158 [CIG-79-2] CIGRE WG 33.03 Phase-to-phase Insulation Co-ordination Part 2: Switching impulse strength of phase-to-phase external insulation ELECTRA 64 1979, pp. 158-181
  • 6. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 6 - Literature (2) [CIG-79-3] CIGRE WG 33.06 Phase-to-phase Insulation Co-ordination Part 3: Design and testing of phase-to-phase insulation ELECTRA 64 1979, pp. 182-210 [CIG-79-4] CIGRE TF 33-03.03 Phase-to-phase Insulation Co-ordination Part 4: The influence of non-standard conditions on the switching impulse strength of phase-to-phase insulation ELECTRA 64 1979, pp. 211-230 [CIG-91] CIGRE WG 33.01 Guide to procedures for estimating the lightning performance of transmission lines, CIGRE technical brochure No. 63, 1991 buch_020.pdf [CIG-92] CIGRE WG 33-07 Guidelines for the evaluation of the dielectric strength of external insulation, CIGRE technical brochure No. 72, 1992 buch_019.pdf [DOR-81] H. Dorsch Ɯberspannungen und Isolationsbemessung bei Drehstrom-Hochspannungsanlagen Siemens AG, Erlangen, 1981 (ISBN 3-8009-1325-9)
  • 7. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 7 - Literature (3) [ERI-88] A.J. Eriksson, K.-H. Weck Simplified procedures for determining representative substation impinging lightning overvoltages, CIGRE report 33-16, 1988 [ETG-93] ETG-Fachbericht 49 ETG-Tage '93: Isolationskoordination in Hoch- und Mittelspannungsanlagen vde-Verlag GmbH Berlin, Offenbach (ISBN 0341-3934) [FGH-78] FGH Technischer Bericht 1-240 Isolationskoordination auf der Grundlage der neuen DIN/VDE-Bestimmung 0111 FGH, Mannheim, Juli 1978 [HIL-99] A. R. Hileman Insulation Coordination for Power Systems Marcel Dekker, Inc., New York, Basel, 1999 [HIN-00] V. Hinrichsen Metalloxidableiter: Grundlagen Siemens AG Berlin, 1. Auflage 2000 AbleiterBuch.pdf [HIN-01] V. Hinrichsen Metalloxidableiter: Grundlagen Siemens AG Berlin, Edition 1, 2001 ArresterBook.pdf
  • 8. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 8 - [HIN-03] V. Hinrichsen Latest Designs and Service Experience with Station-Class Polymer Housed Surge Arresters World Conference on Insulators, Arresters & Bushings Marbella (MĆ”laga), Spain, November 16-19, 2003, Proceedings pp. 85-96 pub_048.pdf [KIN-05] V. Hinrichsen Latest Testing Requirements and Emerging Standards for Transmission Line Arresters World Conference on Insulators, Arresters & Bushings Hong Kong, November 27-30, 2005 inmr_2005_paper.pdf [KIS-84] I. Kishizima, K. Matsumoto, Y. Watanabe, New facilities for phase switching impulse tests and some test results, IEEE PAS TO3 No. 6, June 1984 pp. 1211-1216. [KOE-93-1] D. Kƶnig, Y. N. Rao Teilentladungen in Betriebsmitteln der Energietechnik vde-Verlag, Berlin, Offenburg, 1993, ISBN 3-8007-1764-6 [KOE-93-2] D. Kƶnig, Y. N. Rao Partial discharges in Power Apparatus vde-Verlag, Berlin, Offenburg, 1993, ISBN 3-8007-1760-3 Literature (4)
  • 9. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 9 - [PAR-68] L. Paris, R. Cortina Switching and lightning impulse discharge characteristics of large air gaps and long insulation strings, IEEE Trans on PAS, vol 87, No. 4, April 1968, p. 947-957 [RUD-99-1] R. Rudolph, B. Richter Dimensioning, testing and application of metal oxide surge arresters in medium voltage networks 3rd Edition, 1999, ABB Switzerland, 26 pages (also available in German) application_guide_medium_voltage_networks.pdf [RUD-99-2] R. Rudolph, B. Richter Bemessung, PrĆ¼fung und Einsatz von Metalloxid-Ableitern in Mittelspannungsnetzen ABB Schweiz AG, Wettingen (CH), 3. Auflage 1999 Anwendungsrichtlinien_Mittelspannung.pdf [THI-01] L. Thione Insulation coordination in electrical power systems ā€“ theory and application Tutorial, ALPI, Milan, 2001 (www.alpiass.com) buch_018.pdf Literature (5)
  • 10. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 10 - [WEC-07] K.-H. Weck Standardization of insulation withstand levels for UHV systems in IEC TC 28 ā€žInsulation co-ordinationā€ IEC/CIGRE UHV Symposium Beijing 18-21 July 2007, report 5-4 5-4_KHWeck.pdf Overview on CIGRE publications (very interesting!): CigrĆ© Catalogue of Publications 01/07/2005 CATALOGUE_PUBLICATIONS_2005.pdf Literature (6)
  • 11. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 11 - IEC 60071-1, Edition 8.0 (2006-01) Insulation co-ordination ā€“ Part 1: Definitions, principles and rules IEC 60071-2, Third Edition (1996-12) Insulation co-ordination ā€“ Part 2: Application guide IEC/TR 60071-4, First Edition (2004-06) Insulation co-ordination - Part 4: Computational guide to insulation co-ordination and modelling of electrical networks IEC 60099-4, Ed. 2.1, 2006-07 Surge arresters ā€“ Part 4: Metal-oxide surge arresters without gaps for a.c. systems IEC 60099-5, Ed. 1.1, 2000-03 Surge arresters ā€“ Part 5: Selection and application recommendations DIN EN 60071-1, 1996-07 Isolationskoordination - Teil 1: Begriffe, GrundsƤtze und Anforderungen (IEC 60071-1:1993); Deutsche Fassung EN 60071-1:1995 DIN EN 60071-2, 1997-09 Isolationskoordination - Teil 2: Anwendungsrichtlinie (IEC 60071-2:1996); Deutsche Fassung EN 60071-2:1997 IEEE 1313.1-1996 IEEE Standard for Insulation Coordinationā€”Definitions, Principles, and Rules Standards (1)
  • 12. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 12 - IEEE 1313.2-1999 IEEE Guide for the Application of Insulation Coordination IEEE C62.11-2005 IEEE Standard for Metal-Oxide Surge Arresters for AC Power Circuits (> 1 kV) IEEE C62.22-1997 IEEE Guide for the Application of Metal-Oxide Surge Arresters for Alternating-Current Systems Standards (2)
  • 13. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 13 - Organization Lecture 13 31.01.2008 13 Test procedures; condition monitoring (life time aspects, partial discharges, non-conventional approaches) Lecture 12 24.01.2008 12 Calculation Examples Lecture 11 17.01.2008 11 Insulation coordination Lecture 10 10.01.2008 10 Christmas holidays 03.01.2008 Christmas holidays 27.12.2007 Insulation coordination Lecture 9 20.12.2007 9 pollution, rain, parallel insulation, aging) Lecture 8 13.12.2007 8 Dielectric strength (incl. gap factors, Lecture 7 06.12.2007 7 Overvoltage protection incl. protective distance Lecture 6 29.11.2007 6 Traveling waves Lecture 5 22.11.2007 5 Lecture 4 15.11.2007 4 cancelled 08.11.2007 Lecture 3 01.11.2007 3 Voltage stresses in power systems Lecture 2 25.10.2007 2 Introduction Lecture 1 18.10.2007 1
  • 14. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 14 - Organization Examination Examination Exclusively oral Exercises Exercises None; but calculation examples in the lecture Script Script Slides will be available for download www.hst.tu-darmstadt.de User: studentiso PW: isows0708
  • 15. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 15 - Insulation Coordination - Principles Environment System System voltages Dielectric strength Equipment Overvoltage protection devices stress versus strength
  • 16. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 16 - Insulation Coordination - Principles ā€¢ Voltages of the system ā€“ Nominal voltage Un Ā» rounded value for characterizing the system Ā» 10 kV - 20 kV - 110 kV - 220 kV - 380 kV ā€“ System voltage Ā» voltage at which the system is being operated Ā» around the nominal value, but not constant ā€“ Highest system voltage Us Ā» highest operating voltage between phases under normal conditions Ā» 12 kV - 24 kV - 123 kV - 245 kV - 420 kV (IEC 60038) ā€¢ Voltages of equipment ā€“ Highest voltage for equipment Um Ā» highest voltage between phases for which the insulation is designed Ā» 12 kV - 24 kV - 123 kV - 245 kV - 420 kV (IEC 60071-1)
  • 17. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 17 - Insulation Coordination - Principles ā€¢ Overvoltages ā€“ voltages exceeding the peak value of the highest system voltage ā€“ various amplitudes and shapes depending on Ā» system configuration (grid size, degree of meshing, etc.) Ā» origin of overvoltage (failure, switching, lightning strike etc.) ā€¢ Dielectric strength of insulation ā€“ verified by type test in the laboratory with the help of Ā» standardized test voltages (shape, amplitude) Ā» specified test setups Ā» specified environmental conditions ā€¢ Insulation coordination ā€“ Determination of interdependence between voltages and overvoltages of the system and necessary test voltages for the equipment in the laboratory
  • 18. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 18 - Insulation Coordination - Principles Equipment in the laboratory Equipment in the laboratory Equipment in the system Equipment in the system Variety of amplitudes and shapes of overvoltages Variety of amplitudes and shapes of overvoltages Standardized amplitudes and shapes of test voltages Standardized amplitudes and shapes of test voltages Variety of operating conditions and age Variety of operating conditions and age Standardized setups and conditions Standardized setups and conditions Variety of environmental conditions Variety of environmental conditions Standardized environmental conditions Standardized environmental conditions
  • 19. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 19 - Insulation Coordination - Principles line bb 1 bb 2 busbar disconnectors Insulation phase - ground stressed by voltages between one phase and ground 1 Insulation phase - phase stressed by voltages between two phases 2 Longitudinal insulation stressed by voltages between same phases of two different systems 3 2 3 1
  • 20. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 20 - Insulation Coordination according to IEC 60071-1 (and 60071-2)
  • 21. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 21 - Insulation Coordination according to IEC 60071-1 (and 60071-2)
  • 22. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 22 - Insulation Coordination according to IEC 60071-1 (and 60071-2) Procedure for insulation coordination = 10 pages! Procedure for insulation coordination = 10 pages! ...39 pages in sum ...39 pages in sum
  • 23. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 23 - Insulation Coordination according to IEC 60071-1 (and 60071-2)
  • 24. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 24 - Insulation Coordination according to IEC 60071-1 (and 60071-2)
  • 25. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 25 - Insulation Coordination according to IEC 60071-1 (and 60071-2)
  • 26. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 26 - Insulation Coordination according to IEC 60071-1 (and 60071-2)
  • 27. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 27 - Insulation Coordination according to IEC 60071-1 (and 60071-2)
  • 28. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 28 - Insulation Coordination according to IEC 60071-1 (and 60071-2) ...125 pages in sum ...125 pages in sum
  • 29. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 29 - Procedure for Insulation Coordination - General The procedure for insulation coordination consists of the selection of a set of standard withstand voltages which characterize the insulation of the equipment. Range I Range II
  • 30. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 30 - Procedure for Insulation Coordination - General Basic difference between ranges I and II withstand voltage time duration of stress peak gap spacing 3 m gap spacing 0.5 m [FGH-78] Minimum of withstand voltage for switching overvoltage Minimum of withstand voltage for switching overvoltage Withstand voltage continuously decreasing with time duration of stress Withstand voltage continuously decreasing with time duration of stress Range I Range I Range II Range II
  • 31. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 31 - Procedure for Insulation Coordination in Four Steps Determination of the representative overvoltages Urp ā€¢ The representative overvoltages are derived from real service conditions, but have just standardized shapes. ā€¢ They are determined in amplitude, shape and duration by system analysis, taking into account overvoltage limiting devices. [IEC 60071-1]
  • 32. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 32 - Determination of the coordination withstand voltages Ucw ā€¢ The coordination withstand voltages are the lowest values of withstand voltages of each overvoltage class, for which the expected low failure rate of the equipment is not exceeded over its full lifetime. ā€¢ Derived from the representative overvoltages Urp by the coordination factor Kc. [IEC 60071-1] Procedure for Insulation Coordination in Four Steps Typical for Germany: 0.1% per year 1 failure in 1000 years
  • 33. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 33 - Procedure for Insulation Coordination in Four Steps Deterministic approach Deterministic approach Statistical approach Statistical approach Assumed maximum of representative overvoltage Assumed maximum of representative overvoltage Multiplication by coordination factor based on operating experience Multiplication by coordination factor based on operating experience Statistical distribution of representative overvoltages Statistical distribution of representative overvoltages Determination of failure probability of insulation Determination of failure probability of insulation Calculation of failure risk depending on assumed coordination withstand voltage Calculation of failure risk depending on assumed coordination withstand voltage Coordination withstand voltage Assumed conventional Ucw (0% value) Statistical Ucw (10% value) Coordination withstand voltage Assumed conventional Ucw (0% value) Statistical Ucw (10% value)
  • 34. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 34 - Determination of the required withstand voltages Urw ā€¢ The required withstand voltages are determined by converting the coordination withstand voltages to appropriate standard test conditions. ā€¢ Usually different from the coordination withstand voltages. ā€¢ Derived from the coordination withstand voltages Ucw by the safety factor Ks and the atmospheric correction factor Kt or the altitude correction factor Ka. [IEC 60071-1] Procedure for Insulation Coordination in Four Steps
  • 35. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 35 - [IEC 60071-1] Procedure for Insulation Coordination in Four Steps Influences covered by the safety factor Ks ā€¢ Differences in equipment assembly ā€¢ Dispersion in product quality ā€¢ Quality of installation ā€¢ Aging of the installation during expected lifetime ā€¢ Other unknown influences
  • 36. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 36 - Determination of the required withstand voltages Urw ā€¢ The required withstand voltages are determined by converting the coordination withstand voltages to appropriate standard test conditions. ā€¢ Usually different from the coordination withstand voltages. ā€¢ Derived from the coordination withstand voltages Ucw by the safety factor Ks and/or the altitude correction factor Ka. [IEC 60071-1] Procedure for Insulation Coordination in Four Steps
  • 37. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 37 - Selection of the rated and of the standard insulation level (set of standard rated withstand voltages Uw) ā€¢ Most economical set of standard withstand voltages Uw of the insulation to prove that all the required withstand voltages are met. ā€¢ For each range (I or II) a combination of only two withstand voltages defined: Range I: standard lightning impulse withstand voltage standard short-duration power-frequency withstand voltage Range II: standard switching impulse withstand voltage standard lightning impulse withstand voltage ā€¢ For range I, only phase-to-earth standard withstand voltages are defined, which have to cover phase-to-earth, phase-to-phase and longitudinal insulation. Procedure for Insulation Coordination in Four Steps
  • 38. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 38 - [IEC 60071-1] Procedure for Insulation Coordination in Four Steps Definitions
  • 39. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 39 - Procedure for Insulation Coordination in Four Steps Examples forā€¦ ... non-self-restoring insulation (power transformers, instrument transformers*)) *) mixed insulation ... self-restoring insulation (disconnectors, insulators)
  • 40. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 40 - [IEC 60071-1] Procedure for Insulation Coordination in Four Steps List of standard short-duration power-frequency withstand voltages (r.m.s. values in kV) 630 570 510 480 460 395 360 325 275 230 185 140 95 70 50 38 28 20 10 1800 750 95 1950 850 125 1675 650 75 2100 950 145 2400 2250 1550 1425 1300 1175 1050 550 450 325 250 170 60 40 20 List of standard impulse withstand voltages (peak values in kV)
  • 41. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 41 - The standard voltage values are all the same for ā€¢ phase-to-earth-, ā€¢ phase-to-phase-, ā€¢ longitudinal insulation! Range I: Um = 1 kV up to and including Um = 245 kV Procedure for Insulation Coordination in Four Steps [IEC 60071-1]
  • 42. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 42 - Range II: Um above 245 kV Different standard voltage values for ā€¢ phase-to-earth-, ā€¢ phase-to-phase-, ā€¢ longitudinal insulation! Procedure for Insulation Coordination in Four Steps [IEC 60071-1]
  • 43. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 43 - Procedure for Insulation Coordination in Four Steps Outcome of insulation coordination ā€“ For three types of insulation Ā» phase to ground Ā» phase to phase Ā» longitudinal ā€“ and for 4 values each of required withstand voltages Urw Ā» required continuous operating voltage Ā» required short-duration power-frequency withstand voltage Ā» required switching impulse withstand voltage Ā» required lightning impulse withstand voltage Standardization of tests for equipment ā€“ Reduction of these 12 values to a necessary minimum number of withstand voltages Uw of the insulation ā€“ Determination of necessary withstand voltages from tables for two ranges of highest voltage for equipment twelve voltages
  • 44. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 44 - [IEC 60071-1] Procedure for Insulation Coordination in Four Steps - Summary Flow chart acc. to IEC 60071-1 (Figure 1) continued next slide
  • 45. Fachgebiet Hochspannungstechnik Overvoltage Protection and Insulation Coordination / Chapter 1 - 45 - [IEC 60071-1] Procedure for Insulation Coordination in Four Steps - Summary Flow chart acc. to IEC 60071-1 (Figure 1) (continued)