25 years of overall experience in the field of EPC-Proposals, Plant Maintenance, Field
Engineering and Operations for Mechanical, Chemical, Oil & Gas Industry in Pakistan,
Saudi Arabia and UAE.
PROFESSIONAL SUMMARY
More than 10 years of handsome experience in Project Management of EPC Proposals
/ Projects comprising Management activities, Contract review, Procurement,
Construction, Risk Management, etc. for various Oil & Gas, Chemical and other
industrial plants.
Preparation & Review of EPC Technical & Commercial Proposals, Vendors’ Technical
proposals evaluation and preparation of reports for equipment and other associated
items of project; Cost/Budget estimates, Contractual Documents review and Contract
Negotiations, Claims, etc.
More than 10 years of experience in Mechanical/Manufacturing in Defense Industry;
responsibility includes the Operational / Manufacturing activities, Planning,
Purchasing and Negotiation with vendors etc.
More than 05 years of experience in Plant Maintenance including the installation of
various types of equipment and arranging the necessary spare parts from various
sources within country or from abroad.
PRESENT DUTIES
I joined ‘KHALED JUFFALI INDUSTRIAL COMPANY (KJIC) (www.kjgroup.com), Al-Khobar, Saudi
Arabia, around one year ago in the capacity of “EPC-Proposals Manager” and worked around six
months in that capacity.
Recently, I have completed the Shut Down of one of the SABICs Petro Chemical Plant in Jubail,
Saudia, in the capacity of “I/C Night Shift”. Scope included the maintenance of various Columns,
Reactors and Heat Exchangers etc. in the limited period of 35 days.
Earlier worked at one of KJIC’s project site in the Capacity of “SITE MANAGER” at ‘LUBEREF YANBU
REFINERY EXPANSION PROJECT’, Saudi Arabia.
Main scope of work comprises of “Steam Tracing Of Lube Oil Lines” comprises of two types of steam
tracers (Solution Annealed Tubes & Pre-Insulated Tubes) having total length of more than 182 kM of
lines.
2. MUHAMMAD AZHAR SAEED QAZI
CELL # (+92)345-5099668
(+92)335-5099668
azhar.qazi@asia.com & masqazi@hotmail.com
CV - MECHANICAL ENGINEERING PROFESSIONAL
Page 2 of 7
Main responsibilities and duties are to look after the project requirements in close co-ordination with
Client and KJIC Construction team and timely managing / arranging all the project related
requirements for smooth running of all construction related activities.
Earlier worked for more than 09 years, in the leading EPC company of Pakistan,
DESCON Engineering Ltd ( www.descon.com ) on different challenging positions
in the field of EPC-Proposals, Construction, Engineering / Field Engineering &
Procurement Management.
Before joining DESCON, I have worked in the field of Mechanical Maintenance, as Maintenance
Manager / Engineer in 02 different process plants within Pakistan as well as abroad, where I acquired
extensive knowledge of maintenance of different rotary and stationary equipment as well as learnt
latest maintenance practices and techniques.
In my early career, I have also worked in the field of manufacturing, where I have worked on
different positions in the areas of manufacturing and planning.
Education & Training
University of Engineering & Technology, Lahore, Pakistan.
- B.Sc. Mechanical Engineering 1989
DESCON Engineering Limited, Lahore, Pakistan
- Management Development Program, Level – 1
- Developing Leadership Skills
- Project Leadership Management
Computer Proficiency
▪ IBM – Lotus Notes ▪ MS Office (Word, Excel, Power Point)
▪ MS Outlook ▪ MS Visio ▪ Primavera Project Planner
▪ Win Bid (DESCON’s patent Bidding software)
3. MUHAMMAD AZHAR SAEED QAZI
CELL # (+92)345-5099668
(+92)335-5099668
azhar.qazi@asia.com & masqazi@hotmail.com
CV - MECHANICAL ENGINEERING PROFESSIONAL
Page 3 of 7
Employment History
KHALED JUFFALI INDUSTRIAL COMPANY 2015 – TILL PRESENT
Earlier
DESCON ENGINEERING LTD., PAKISTAN. 2005 – 2014
EPC - PROPOSALS MANAGER / PROPOSALS ENGINEER / CONSTRUCTION MANAGER
In DESCON, I played active role in ‘EPC Proposals’ pertaining, mainly, in Oil & Gas sector, not only in
Pakistan but also for Middle East region, in the capacity of ‘Proposals Manager / Engineer’.
After winning the Proposals, I have been deputed on Construction Sites in various capacities, whose
detail is as under:
Urea Debottlenecking Project @Fertil-1, UAE
As a Proposal Engineer, handled ‘Mechanical’ part of the CO2 area of the Urea Plant Debottlenecking
project. Responsibilities included study of ITB documents and preparation of RFQs for Equipment,
Piping and Piping Bulks along with the review of quotes and handled vendors’ queries for specific
area.
Won the proposal, worth US $ 170 Million.
- PROJECT ENGINEER @ FERTIL – 1 ( Jan. 2007 – Feb. 2008 )
After winning the Project, I was assigned on the project site in the capacity of Project
Engineer. Main role was to assist the Construction Manager in CO2 recovery area construction
activities.
After one year, I was assigned back to Proposals in the Head Office.
CO2 Recovery Plant @ Engro Fertilizer, Pakistan
As a Proposal Manager, prepared complete EPC proposal for ‘CO2 recovery plant’ for Engro Urea
Fertilizer plant.
Won the job worth US $ 20 Million.
4. MUHAMMAD AZHAR SAEED QAZI
CELL # (+92)345-5099668
(+92)335-5099668
azhar.qazi@asia.com & masqazi@hotmail.com
CV - MECHANICAL ENGINEERING PROFESSIONAL
Page 4 of 7
- Dy. Construction Manager @ ENGRO CO2 Recovery Plant @ Engro
( Nov.2008 – March 2010 )
Deputed on Project site in the capacity of Deputy Construction Manager and responsibilities
included to look after the day to day construction related activities on the Brown Field plant,
managing MP on site, Procuring the required material and equipment for smooth operations
of construction activities.
ADCO’s JETTY SUB-STATION PROJECT @ JEBEL DHANNA, Abu-Dhabi.
As a Proposals Manager prepared “Techno-Commercial” proposal for a Jetty Sub-station.
Won the job worth US $ 10 Millions
- Construction Manager @ JETTY S.S Project ( Sept. 2010 – July 2011 )
After winning the above said project, assigned as Construction Manager and completed the
project in 32 days earlier than the target time of 12months.
- ENGINEERING MANAGER / FIELD ENGINEERING MANAGER ( Jan. 2012 - May 2013 )
PROJECT: ADCO-THAMAMA ‘B’ GAS LIFT PROJECT FOR WELLS Bb-097 & Bb-603
Scope of Project
One of the Most Challenging job for me is to work as Engineering Manager for the mentioned project.
Scope of work comprises of residual engineering, procurement, construction, installation & erection of
equipment in two wellhead areas in the Bab region. Scope also comprises of installation of 10kM , 04
inch diameter underground pipe line for the supply of gas in well head areas.
Duties & Responsibilities
Plan, manages and oversees the daily functions of engineering,
Manage and coordination of the work plans with the assign division, meeting with staff to identify
and resolve problems,
Coordination with discipline engineers on technical issues and engineering matters related to the
project,
Monitor work flow as per plan, review and evaluate the work, method and procedures,
Prepared technical specifications, data sheets for quotes (RFQ) and requisition (RFP) for equipment
and associated bulks,
Coordinate with procurement team for resolving vendors’ technical queries in line with project
5. MUHAMMAD AZHAR SAEED QAZI
CELL # (+92)345-5099668
(+92)335-5099668
azhar.qazi@asia.com & masqazi@hotmail.com
CV - MECHANICAL ENGINEERING PROFESSIONAL
Page 5 of 7
requirements,
Develop technical bid evaluations and make recommendations, leading to the selection of vendors,
Proactively managed activities supporting the procurement of assigned equipment and materials in
order to maintain the project schedule and budget,
Review and approved supplier drawings, design calculations and data documentation to ensure
compliance with project specification requirements,
Review and approved vendor data books,
Coordinated answers to queries during fabrication and construction and make shop and site visits,
as necessary to ensure technical integrity of the equipment and design,
Updated equipment list,
Ensured proper implementation of the approved Design Change Note (DCN) in the designs through
checking the 3D Model and P&ID drawings.
Previous - Employment History
IN CHARGE MECHANICAL ENGINEERING DIVISION 2002 - 2005
BIAFO Industries Ltd. Hattar, Pakistan
Duties and Responsibilities:
Developed standards, specifications, engineering practices and procedures for maintenance, repair
and turnaround of plant equipment, to ensure smooth operation of the plant all the time,
Implementation of Computerized Maintenance Management System (CMMS) for scheduling and
execution of preventative and predictive maintenance to improve equipment reliability,
Conducted failure analysis of mechanical equipment as well as unexpected maintenance problems
and operational problems related to equipment,
Liaised with equipment vendors, consultant and contractor on engineering drawings, calculations
and quotations for procurement of new equipment, equipment spare parts, troubleshooting and
repair as well as for the installation and improvement of plant efficiency,
Ensured proper execution and closure of work orders for repair with regard to manpower
availability, skills, health & safety,
Recorded and interpreted essential workshop data such as equipment utilization, stock (spare parts)
records, repair frequencies and information necessary for budgetary and cost control,
Provided training to the technical staff and operators on the equipment maintenance and safe
operation,
Scheduled, supervised and inspected maintenance, turnaround, installation and repair of a
maintenance team consisting of over 20 technical specialists and 2 maintenance specialists,
Carried out I.S.O 9001: 2000 related activities for mechanical maintenance department.
6. MUHAMMAD AZHAR SAEED QAZI
CELL # (+92)345-5099668
(+92)335-5099668
azhar.qazi@asia.com & masqazi@hotmail.com
CV - MECHANICAL ENGINEERING PROFESSIONAL
Page 6 of 7
MAINTENANCE ENGINEER 2000 -2002
Southern Province Cement Company (SPCC), Saudi Arabia
Duties and Responsibilities:
GAS TURBINE AREA
Maintained ABB-Gas Turbine Power Plant auxiliary area where number of centrifugal pumps, was
installed. Keeping them in running condition was sole responsibility,
Staff handling and keep them educated about the plant and Safety is among the duties to perform,
Planning and ordering of essential spares for power plant,
Dealing with different vendors / sub-contractors for plant smooth running operation.
CEMENT PLANT AREA
Performed duties in the capacity of Maintenance engineer in the areas of ‘RAW MILL’ and ‘FINISH
MILL’ areas,
Keeping all the equipment of these areas which mainly includes number of conveyor belts, gear
reducers etc. was part of responsibilities,
Maintained the inventories for plant consumables at required levels at all the times,
Communicated with vendors for the procurement of plant spares in liaisons with the head office,
Prepared weekly and monthly reports of maintenance department for onward dispatch to head
office.
ASSISTANT MANAGER 1990 – 2000
Pakistan Ordnance Factory, Wah Cantt, Pakistan
My career life history started at Pakistan’s most prestigious defense organization and where I served
more than 10 years. During my service, I worked in different areas which included production
department, planning department, vendors’ relation department.
Following is the brief summary of the main duties performed:
Duties and Responsibilities:
In the Production shop floor, supervised more than 300 shop-floor workers and staff members
involved in the manufacturing of different assault rifles,
7. MUHAMMAD AZHAR SAEED QAZI
CELL # (+92)345-5099668
(+92)335-5099668
azhar.qazi@asia.com & masqazi@hotmail.com
CV - MECHANICAL ENGINEERING PROFESSIONAL
Page 7 of 7
Manufacturing involved thousands of big and small precision components of different assault rifles
which were manufactured on very strict quality control methods and techniques,
Managing and solving the day to day problems arising during production process,
Training of junior staff and skilled workers for increasing the productivity of the finished products,
Meeting annual production targets by employing effective planning techniques,
Liaisons with different vendors around the world for the supply of raw materials used in the
production of finished products,
Advance Planning, involved in the purchase of different raw materials for coming year’s production.