Construction Notice
June 28, 2012

Dufferin Street
Watermain, Road Work and TTC Track Reconstruction
Start Date: July 3, 2012
End Date: December 2012

Timelines subject to change due to unforeseen events
Content is accurate and current at time of printing

Beginning on July 3, the City of Toronto -Technical Services and the Toronto Transit Commission (TTC) will
undertake major construction work on Dufferin Street from Queen Street West to Springhurst Avenue. A
previous public notice was distributed in early April 2012. The work will involve; reconstruction of watermain,
streetcar tracks, road, curb and sidewalk areas, traffic signals, and streetscape (e.g. construction of sign wall,
seat wall and banner pole).
Construction Notification
The project is being scheduled and staged in a manner to minimize disruption to the general traffic and transit
service during the Canadian National Exhibition (CNE). Construction on this project will be suspended during
the CNE. Project updates will be provided as required.
General Timeline
Phase 1: Watermain work begins between King Street and Queen Street with some sidewalk work.
Phase 2: Track reconstruction including road work begins between Springhurst Avenue and Queen Street.
Remaining watermain work begins between King Street and Springhurst Avenue.

Construction Details
Phase 1: Watermain Work between King Street and Queen Street.
Work will start just south of King Street and progress north
towards Queen Street. There will be no major disruption to your
water services. This work will continue into the month of
August.

Work Area

Traffic and Parking Restrictions
One lane of traffic in each direction will be maintained on
Dufferin Street between King Street and Queen Street.
Parking restrictions will be imposed within the active work zone.
Some left-turn restrictions may be required as well.
The curb lanes at the King/Dufferin and Queen/Dufferin
intersections will be affected during the construction work.
TTC Transit Service
The 29/329 Dufferin bus service will be affected differently
during the different phases of the project. During Phase 1 of the
project Dufferin buses will operate on regular routing in both
directions through the work zone.

Phase 2: Track Reconstruction between Springhurst
Avenue and Queen Street.
The existing track area will be completely excavated, new rail
installed and concrete placed.
Traffic and Parking Restrictions
Traffic will be reduced to one lane northbound. Southbound
lanes will be closed.
Left-turn restrictions within the work zone will be imposed and
parking will not be permitted.
The curb lanes at the King/Dufferin and Queen/Dufferin
intersections will be affected during the construction work.
TTC Transit Service
During Phase 2 of the project, details relating to the bus
service/diversions will be provided in a future notice and posted
on transit stops along the route prior to changes taking effect.
(Continued on reverse…)

Dufferin Street from Queen Street West to
Springhurst Avenue.
Construction Notice
Driveway Access and Allowances
At times, the construction will require temporary closure of private driveways. Where the property has two
entrances, one entrance will be maintained at all times. Temporary parking permits will be distributed by City
construction staff in advance of access restrictions.
Road Closures
Road closures will be required for work at the intersections of Liberty Street and Melbourne Avenue. Work at
the intersections will be scheduled for weekends, dates to be determined.
As work progresses, some one-way side streets connected with Dufferin Street will be converted to temporary
two-way operation.
As with any roadway construction and associated lane closures, it should be expected that traffic on Dufferin
Street will be displaced during stages of this project and overflow onto local streets. The City appreciates your
understanding.
Pedestrian Access
Pedestrian access to businesses and walkways will be maintained on both sides of all roads at all times during
all phases of construction. The contractor will further notify you should any temporary disruptions be required.
Work Hours
Work will generally run from 7 a.m. to 7 p.m., Monday to Friday, and from 7 a.m. to 5 p.m. on Saturday.
However, the TTC track reconstruction phase of this project will involve periods of late evening and overnight
work and extended weekend hours. The overnight rail work by TTC may consist of moving rail into position, rail
installation and rail welding / grinding. After-hours work by TTC is required to support the daytime construction
and complete the project as quickly as possible. While every effort will be made to minimize construction noise
during the work periods, noise should be expected.
Recycling and Garbage Collection
Follow your normal routine. If required, the contractor will move the items to an appropriate location and return
the bins/containers. Please label your bins/containers with your address.
Deliveries
During construction, deliveries to the front of businesses within the work zone may need to be coordinated with
the on-site City inspector. Kindly contact City of Toronto Project Manager.

Project Contacts
For more information about this project:
City Contacts
Shahid Virk
City of Toronto Project Engineer; 416-338-5542, svirk@toronto.ca
24/7 General Inquiries: 311
TTY: 416-338-0889
TTC Contacts
Diego Sinagoga - TTC track related work
TTC Community Liaison Representative; 416-393-2197
TTC Customer Service: 416-393-3030 (Daily 7a.m. to 10p.m., closed holidays)
TTY (TTC): 416-481-2523 (Daily, 8a.m. to 5p.m., closed holidays)
TTC Route Information: 416-393-INFO (4636)
Councillor
Gord Perks - Ward 14 Parkdale-High Park; 416 392-791, councillor_perks@toronto.ca
Both the City and TTC web sites will be updated with additional information nearing the start of construction:
www.toronto.ca/improvements
www.ttc.ca

More Related Content

What's hot

1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
Candice Spiroski
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Crosstown TO
 
PIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase IPIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase I
Sven Maedler
 
Eastern market community meeting presentation 012202020
Eastern market community meeting presentation 012202020Eastern market community meeting presentation 012202020
Eastern market community meeting presentation 012202020
RamaChilamkurthy
 

What's hot (19)

ICI
ICIICI
ICI
 
Update for pending works
Update for pending worksUpdate for pending works
Update for pending works
 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
 
Difficult Run Tributary at Brittenford Drive Stream Restoration
Difficult Run Tributary at Brittenford Drive Stream RestorationDifficult Run Tributary at Brittenford Drive Stream Restoration
Difficult Run Tributary at Brittenford Drive Stream Restoration
 
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
 
Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
 
Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...
Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...
Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...
 
Planning and scheduling project (psp 275)
Planning and scheduling project (psp 275)Planning and scheduling project (psp 275)
Planning and scheduling project (psp 275)
 
Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020
 
Binder1(1)
Binder1(1)Binder1(1)
Binder1(1)
 
PIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase IPIS Uyo - Ikot Ekpene Road Phase I
PIS Uyo - Ikot Ekpene Road Phase I
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
 
Beaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentationBeaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentation
 
Eastern market community meeting presentation 012202020
Eastern market community meeting presentation 012202020Eastern market community meeting presentation 012202020
Eastern market community meeting presentation 012202020
 
Sectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing PresentationSectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing Presentation
 
Master plan edit
Master plan editMaster plan edit
Master plan edit
 
Nick Kennedy cv
Nick Kennedy cvNick Kennedy cv
Nick Kennedy cv
 
Jamie Resume
Jamie ResumeJamie Resume
Jamie Resume
 

Viewers also liked

Rue La La Office Tour
Rue La La Office TourRue La La Office Tour
Rue La La Office Tour
Rue La La
 
Exposicion web 2 redes sociales
Exposicion web 2 redes socialesExposicion web 2 redes sociales
Exposicion web 2 redes sociales
yolina2189
 
Edital pnld eja_2014_190712
Edital pnld eja_2014_190712Edital pnld eja_2014_190712
Edital pnld eja_2014_190712
dayejef
 
1. sop pengelolaan pemb tematik terpadu ks
1. sop pengelolaan pemb tematik terpadu ks1. sop pengelolaan pemb tematik terpadu ks
1. sop pengelolaan pemb tematik terpadu ks
Sanda Zyrechsmart
 
English IV Thursday, 03.23.15 Lesson with Reflection
English IV Thursday, 03.23.15 Lesson with ReflectionEnglish IV Thursday, 03.23.15 Lesson with Reflection
English IV Thursday, 03.23.15 Lesson with Reflection
Mary Beth Gries
 

Viewers also liked (17)

Peer lectures in the medical undergraduate curriculum: a valid tool for lear...
Peer lectures in the medical undergraduate curriculum: a valid tool for  lear...Peer lectures in the medical undergraduate curriculum: a valid tool for  lear...
Peer lectures in the medical undergraduate curriculum: a valid tool for lear...
 
Verdadeiro amigo
Verdadeiro amigoVerdadeiro amigo
Verdadeiro amigo
 
GIT-Lesson-1
GIT-Lesson-1GIT-Lesson-1
GIT-Lesson-1
 
Rue La La Office Tour
Rue La La Office TourRue La La Office Tour
Rue La La Office Tour
 
Exposicion web 2 redes sociales
Exposicion web 2 redes socialesExposicion web 2 redes sociales
Exposicion web 2 redes sociales
 
Best Logos
Best LogosBest Logos
Best Logos
 
Mohan_resume
Mohan_resumeMohan_resume
Mohan_resume
 
Edital pnld eja_2014_190712
Edital pnld eja_2014_190712Edital pnld eja_2014_190712
Edital pnld eja_2014_190712
 
Case Study Of GE LinkedIn
Case Study Of GE LinkedInCase Study Of GE LinkedIn
Case Study Of GE LinkedIn
 
Sketching Paris...
Sketching Paris...Sketching Paris...
Sketching Paris...
 
1. sop pengelolaan pemb tematik terpadu ks
1. sop pengelolaan pemb tematik terpadu ks1. sop pengelolaan pemb tematik terpadu ks
1. sop pengelolaan pemb tematik terpadu ks
 
English IV Thursday, 03.23.15 Lesson with Reflection
English IV Thursday, 03.23.15 Lesson with ReflectionEnglish IV Thursday, 03.23.15 Lesson with Reflection
English IV Thursday, 03.23.15 Lesson with Reflection
 
La evolución del hombre
La evolución del hombreLa evolución del hombre
La evolución del hombre
 
Celebrity brand endorsement
Celebrity brand endorsementCelebrity brand endorsement
Celebrity brand endorsement
 
Steeple
SteepleSteeple
Steeple
 
Javaのプログラムはどうやって動いているの? GC編
Javaのプログラムはどうやって動いているの? GC編Javaのプログラムはどうやって動いているの? GC編
Javaのプログラムはどうやって動いているの? GC編
 
Seminario i lapso_iii_2012 reprogramado (2)
Seminario  i lapso_iii_2012 reprogramado (2)Seminario  i lapso_iii_2012 reprogramado (2)
Seminario i lapso_iii_2012 reprogramado (2)
 

Similar to Dufferin second-public-notice-june-27

Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
Crosstown TO
 
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Crosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
Crosstown TO
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
Crosstown TO
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
Crosstown TO
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
Crosstown TO
 

Similar to Dufferin second-public-notice-june-27 (20)

Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
 
Eglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House PresentationEglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House Presentation
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Eglinton Crosstown LRT - Public Notice
Eglinton Crosstown LRT - Public NoticeEglinton Crosstown LRT - Public Notice
Eglinton Crosstown LRT - Public Notice
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
Capital Works Project Bulletin: Windsor Siding
Capital Works Project Bulletin: Windsor SidingCapital Works Project Bulletin: Windsor Siding
Capital Works Project Bulletin: Windsor Siding
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 

Dufferin second-public-notice-june-27

  • 1. Construction Notice June 28, 2012 Dufferin Street Watermain, Road Work and TTC Track Reconstruction Start Date: July 3, 2012 End Date: December 2012 Timelines subject to change due to unforeseen events Content is accurate and current at time of printing Beginning on July 3, the City of Toronto -Technical Services and the Toronto Transit Commission (TTC) will undertake major construction work on Dufferin Street from Queen Street West to Springhurst Avenue. A previous public notice was distributed in early April 2012. The work will involve; reconstruction of watermain, streetcar tracks, road, curb and sidewalk areas, traffic signals, and streetscape (e.g. construction of sign wall, seat wall and banner pole). Construction Notification The project is being scheduled and staged in a manner to minimize disruption to the general traffic and transit service during the Canadian National Exhibition (CNE). Construction on this project will be suspended during the CNE. Project updates will be provided as required. General Timeline Phase 1: Watermain work begins between King Street and Queen Street with some sidewalk work. Phase 2: Track reconstruction including road work begins between Springhurst Avenue and Queen Street. Remaining watermain work begins between King Street and Springhurst Avenue. Construction Details Phase 1: Watermain Work between King Street and Queen Street. Work will start just south of King Street and progress north towards Queen Street. There will be no major disruption to your water services. This work will continue into the month of August. Work Area Traffic and Parking Restrictions One lane of traffic in each direction will be maintained on Dufferin Street between King Street and Queen Street. Parking restrictions will be imposed within the active work zone. Some left-turn restrictions may be required as well. The curb lanes at the King/Dufferin and Queen/Dufferin intersections will be affected during the construction work. TTC Transit Service The 29/329 Dufferin bus service will be affected differently during the different phases of the project. During Phase 1 of the project Dufferin buses will operate on regular routing in both directions through the work zone. Phase 2: Track Reconstruction between Springhurst Avenue and Queen Street. The existing track area will be completely excavated, new rail installed and concrete placed. Traffic and Parking Restrictions Traffic will be reduced to one lane northbound. Southbound lanes will be closed. Left-turn restrictions within the work zone will be imposed and parking will not be permitted. The curb lanes at the King/Dufferin and Queen/Dufferin intersections will be affected during the construction work. TTC Transit Service During Phase 2 of the project, details relating to the bus service/diversions will be provided in a future notice and posted on transit stops along the route prior to changes taking effect. (Continued on reverse…) Dufferin Street from Queen Street West to Springhurst Avenue.
  • 2. Construction Notice Driveway Access and Allowances At times, the construction will require temporary closure of private driveways. Where the property has two entrances, one entrance will be maintained at all times. Temporary parking permits will be distributed by City construction staff in advance of access restrictions. Road Closures Road closures will be required for work at the intersections of Liberty Street and Melbourne Avenue. Work at the intersections will be scheduled for weekends, dates to be determined. As work progresses, some one-way side streets connected with Dufferin Street will be converted to temporary two-way operation. As with any roadway construction and associated lane closures, it should be expected that traffic on Dufferin Street will be displaced during stages of this project and overflow onto local streets. The City appreciates your understanding. Pedestrian Access Pedestrian access to businesses and walkways will be maintained on both sides of all roads at all times during all phases of construction. The contractor will further notify you should any temporary disruptions be required. Work Hours Work will generally run from 7 a.m. to 7 p.m., Monday to Friday, and from 7 a.m. to 5 p.m. on Saturday. However, the TTC track reconstruction phase of this project will involve periods of late evening and overnight work and extended weekend hours. The overnight rail work by TTC may consist of moving rail into position, rail installation and rail welding / grinding. After-hours work by TTC is required to support the daytime construction and complete the project as quickly as possible. While every effort will be made to minimize construction noise during the work periods, noise should be expected. Recycling and Garbage Collection Follow your normal routine. If required, the contractor will move the items to an appropriate location and return the bins/containers. Please label your bins/containers with your address. Deliveries During construction, deliveries to the front of businesses within the work zone may need to be coordinated with the on-site City inspector. Kindly contact City of Toronto Project Manager. Project Contacts For more information about this project: City Contacts Shahid Virk City of Toronto Project Engineer; 416-338-5542, svirk@toronto.ca 24/7 General Inquiries: 311 TTY: 416-338-0889 TTC Contacts Diego Sinagoga - TTC track related work TTC Community Liaison Representative; 416-393-2197 TTC Customer Service: 416-393-3030 (Daily 7a.m. to 10p.m., closed holidays) TTY (TTC): 416-481-2523 (Daily, 8a.m. to 5p.m., closed holidays) TTC Route Information: 416-393-INFO (4636) Councillor Gord Perks - Ward 14 Parkdale-High Park; 416 392-791, councillor_perks@toronto.ca Both the City and TTC web sites will be updated with additional information nearing the start of construction: www.toronto.ca/improvements www.ttc.ca