SlideShare a Scribd company logo
1 of 48
Procurement (CONS6817) Lara Tookey & John Boon
PROCUREMENT – SESSION #8
Strategic Long Term Partnering
Framework agreements
Introduction to PPPs – Public Private Partnering
Procurement (CONS6817) Lara Tookey & John Boon
WHAT’S THE PROBLEM?
The behavioural aspects of projects
Procurement (CONS6817) Lara Tookey & John Boon
Typical organisation on DBB project
All parties selected on the
basis of lowest price
• Need to minimise
expenditure
• Need to increase price
wherever possible
Architect Engineers QS Construction
Contractor
Sub-contractors &
Suppliers
Project
Manager
Procurement (CONS6817) Lara Tookey & John Boon
Normal behaviour is…..
• Tendency is for parties to the project to
stand apart from one another;
• Demand the other party perform as required
by the contract; and
• Pursue claims against them when they fail to
perform.
Procurement (CONS6817) Lara Tookey & John Boon
Normal behaviour is…..
• Do not seek to assist other party(s) to perform;
• No attempt to help the other party overcome a
problem when they hit one;
• Never consider exceeding the requirements of
the contract; and
• Never consider mutually beneficial ways of
improving on the deliverables
Procurement (CONS6817) Lara Tookey & John Boon
End result tends to be….
• Projects delivered to marginally acceptable
quality standards;
• Contractors and consultants only achieve
marginally acceptable levels of profitability;
• Cost and time overruns; and
• Contract completion involves a process of
resolving significant numbers of claims either by
negotiation or litigation.
Procurement (CONS6817) Lara Tookey & John Boon
Plus the issues of lack of
constructor input into
the design process ……
Procurement (CONS6817) Lara Tookey & John Boon
WHEN THINGS GO RIGHT...
Strategic partnering – long(er) term relationships
Procurement (CONS6817) Lara Tookey & John Boon
IF YOU CAN MAKE SIGNIFICANT GAINS
BY COLLABORATING ON ONE OFF
PROJECTS YOU SHOULD BE ABLE TO
MAKE EVEN BIGGER GAINS IF YOU
WORKED TOGETHER
COLLABORATIVELY ON A SERIES OF
PROJECTS.
LONG TERM STRATEGIC
RELATIONSHIPS
Procurement (CONS6817) Lara Tookey & John Boon
UK EXPERIENCE
Procurement (CONS6817) Lara Tookey & John Boon
Egan report – Rethinking
Construction 1998
• Debilitating cycle of competitive tender,
conflict, low margins and dissatisfied clients
• The industry must replace competitive
tendering with long time relationships based
on clear measurement of performance and
sustained improvement in quality and
efficiency
Procurement (CONS6817) Lara Tookey & John Boon
CLIENT LED CHANGE
Procurement (CONS6817) Lara Tookey & John Boon
Procurement (CONS6817) Lara Tookey & John Boon
• Early 2000 Sinclair Knight Merz (SKM) was
appointed as part of a client-led team to
undertake a fundamental review of the design,
procurement and construction of retail assets
for Tesco Stores Limited.
• The brief (design & construction professionals):
• significantly reduce construction costs and build
programmes for new retail space, whilst improving
the shopping experience, through rationalisation,
standardisation and simplification.
Procurement (CONS6817) Lara Tookey & John Boon
• A trial store at Haverfordwest (£4.75m),
completed in March 2000, confirmed the
success of the design initiatives as the target
costs and programme were achieved.
• Retaining the same team, building on the
success of the original project & improving all
aspects of the store design and construction
• two new trial store projects at Downham Market
(£3.5m) and Cardiff, Pengam Green (£6.15m) were
commissioned
Procurement (CONS6817) Lara Tookey & John Boon
• A complete review of the building structure,
fabric and services, together with the retail
design, was undertaken and new initiatives
were included in particular to modularise plant,
specific retail elements and ancillary areas, such
as toilets.
• The new stores were completed in April 2001,
again within cost and programme targets,
despite significant site-specific challenges.
Procurement (CONS6817) Lara Tookey & John Boon
• Sovereign Construction has been working
with Tesco Stores Limited for over 30 years.
• Challenges on a project:
• A short program duration in order to complete and open pre-xmas
in order to benefit from the enhanced trading period.
• An extremely busy and congested central London location.
• Noise and delivery restrictions creating greater pressure on the
short program duration.
• Local Authority planning restrictions and The Kensington Society ( a
local residents association) conservation requirements.
Procurement (CONS6817) Lara Tookey & John Boon
• Solutions:
• Promote a "One Team" approach with the client, retail,
professionals and Local Authority.
• Detailed and complex programming in order to meet the required
opening date and adhere to the significant restrictions on working
times and deliveries.
• Working within pre-agreed times to ensure that residents were not
disturbed.
• Detailed planning with regards to deliveries to overcome the traffic
and congestion issues.
• Good, consistent and regular communication with both the local
authority, the Kensington Society and where appropriate local
residents and businesses.
Procurement (CONS6817) Lara Tookey & John Boon
Procurement (CONS6817) Lara Tookey & John Boon
Procurement (CONS6817) Lara Tookey & John Boon
“As a leading construction company we aim to be the UK's first choice
construction partner for delivery of services to the community.”
MANSELL
Procurement (CONS6817) Lara Tookey & John Boon
• “Our dedication to customer service and
nurturing long-term relationships brings us
high levels of repeat business and the ability
to invest and grow”.
• 85% repeat business – frameworks and
sustainable relationships
• Turnover up 24%
Procurement (CONS6817) Lara Tookey & John Boon
Procurement (CONS6817) Lara Tookey & John Boon
Procurement (CONS6817) Lara Tookey & John Boon
Procurement (CONS6817) Lara Tookey & John Boon
COMMERCIAL ARRANGEMENTS
Framework agreement
Procurement (CONS6817) Lara Tookey & John Boon
Framework Agreement
• An umbrella agreement under which the
parties enter into a number of project
specific contracts
• Typically 3 – 5 year agreements
• Can be non-binding or legally binding
Procurement (CONS6817) Lara Tookey & John Boon
Contents of framework
agreement include - 1
• Scope - the services to be provided
• Volume – the agreement may specify the
volume of work to be provided
• Pricing mechanisms – how the price for the
services on individual projects will be
determined
• Risk and reward – painshare/gainshare
provisions
Procurement (CONS6817) Lara Tookey & John Boon
Contents of framework
agreement include - 2
• Performance specification
• Performance measures (KPIs) (often raised during
the period of the framework)
• Performance incentives
• Direct payments on achieving targets
• Share of total work relative to other framework
contractors
• Learning from project to project
• Innovation provisions
• How the parties will work together to achieve
innovation
• Who will fund what R&D
Procurement (CONS6817) Lara Tookey & John Boon
Contents of framework
agreement include - 3
• Supply chain provisions
• Working with other framework contractors (eg
design consultants)
• How the contractor will manage their own
supply chain (will they have framework
agreements with sub-contractors)
Procurement (CONS6817) Lara Tookey & John Boon
Typical building project under
a framework agreement
• Contractor involved in cost planning
throughout early design stages to establish a
target cost (verified by independent QS)
• As the design phase progresses the target
cost is refined and then fixed
• A contract is entered into between the client
and the framework contractor (based on
terms and conditions specified in the
framework agreement)
Procurement (CONS6817) Lara Tookey & John Boon
Typical payment models
• Full cost reimbursement + margin
• P&G + margin
• Cost reimbursement of subcontractors and
suppliers
• In either case gainshare/painshare provisions
apply
Procurement (CONS6817) Lara Tookey & John Boon
Benefits to client
• Improved predictability
• Cost
• Time
• Improved risk management
• Reduced time and cost in tendering individual
projects
• Improved performance over time:
• Value for money (cost efficiency)
• Project duration
• Quality
Procurement (CONS6817) Lara Tookey & John Boon
Benefits to contractor
• Continuity of work
• Ability to contribute to the design phase and
achieve construction efficiency
• Benefits from gainshare provisions
• Reduction in tender costs
Procurement (CONS6817) Lara Tookey & John Boon
PPP’s
ARE THESE JUST THE NEXT STEP, OR
ARE THEY SOMETHING A BIT MORE
SERIOUS?
Procurement (CONS6817) Lara Tookey & John Boon
Public Procurement
Engineer / Architect
D
Contractor
B
Bank / Financier
F
Operator
O
Public Authority
Investors Users
Shareholders
Agreement
Consultancy
Agreement
Construction
Contract
Loan
Employment /
O&M Contract
Tax/Rates/Tolls/Le
ase
Procurement (CONS6817) Lara Tookey & John Boon
PPP Procurement
Engineer / Architect
D
Contractor
B
Bank / Financier
F
Operator
O
Special Purpose
Vehicle
Investors Users
Shareholders
Agreement
Consultancy
Agreement
Construction
Contract
Loan
Employment /
O&M Contract
Tax/Rates/Tolls/Le
ase
Public Authority
Concession
Agreement
Procurement (CONS6817) Lara Tookey & John Boon
What is a PPP / PFi?
• Public = public sector authority
• Private = private organisations
• Partnership = risk sharing relationship (not
merely regulatory or short term contract)
• PFI (Private Finance Initiative)
• A generic classifier for all types of PPP
construction.
Procurement (CONS6817) Lara Tookey & John Boon
What are Public Private
Partnerships?
• ‘A contractual arrangement between public
and private sectors with clear agreement on
shared objectives for the delivery of public
infrastructure and/or public services by the
private sector that would have otherwise
been provided through traditional public
sector procurement’
• Extracted from Russell Kenley notes quoting Akintoye 2003
Procurement (CONS6817) Lara Tookey & John Boon
Public-Private-Partnerships
• Narrow definition: “instead of the public
sector procuring a capital asset by paying for
it in full up front, the effect of a typical PPP
structure is usually to create a single stand
alone business, financed and operated by
the private sector. The purpose is to create
the asset and then deliver a service to the
public sector client, in return for payment
commensurate with the service levels
provided.”
• International Financial Services, June 2001
Procurement (CONS6817) Lara Tookey & John Boon
Underlying Philosophy
• The private sector executes projects and
delivers services more efficiently and
manages the risks better.
• If the private sector bears both the initial capital
and operating costs it will make better “whole of
life” cost judgements.
Procurement (CONS6817) Lara Tookey & John Boon
A few important things:
• It must relate to the provision of public
services or public infrastructure.
• It necessitates the transfer of risk between
partners.
• If the arrangement does not include these two
concepts, they are not technically “ppp’s”.
• No universal definition of P3.
• Covers a wide range of projects, depending
on asset ownership, risk sharing, financing &
operation.
Procurement (CONS6817) Lara Tookey & John Boon
• FOR PPP’s/PFI’s “government” can mean any
level of government
• national, regional or local.
Procurement (CONS6817) Lara Tookey & John Boon
WHAT DOES A PPP LOOK LIKE?
Procurement (CONS6817) Lara Tookey & John Boon
Procurement (CONS6817) Lara Tookey & John Boon
PPP Procurement
Engineer / Architect
D
Contractor
B
Bank / Financier
F
Operator
O
Special Purpose
Vehicle
Investors Users
Shareholders
Agreement
Consultancy
Agreement
Construction
Contract
Loan
Employment /
O&M Contract
Tax/Rates/Tolls/Le
ase
Public Authority
Concession
Agreement
Procurement (CONS6817) Lara Tookey & John Boon
Wi
Wiri Prison – Full Service PPP
DBFOM
Procurement (CONS6817) Lara Tookey & John Boon
Special Purpose Vehicle (SPV)
• A company incorporated solely for the
implementation / management of the
project.
• Enters into contracts with the Government
and sub-contractors.
• Finances, develops, builds, maintains and
operates the project (or any other
combination).
• Guarantee and secure cash flows.

More Related Content

What's hot

Partnering and partnering contracts presentation
Partnering and partnering contracts presentationPartnering and partnering contracts presentation
Partnering and partnering contracts presentation
Kim Newman
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
Yong Sy
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
Lee Pei Gie
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
Pang Khai Shuen
 
20050314 tips on contract management
20050314 tips on contract management20050314 tips on contract management
20050314 tips on contract management
raymond_wan2005
 

What's hot (19)

CONS6817_S06'16
CONS6817_S06'16CONS6817_S06'16
CONS6817_S06'16
 
CONS6817_S02'16
CONS6817_S02'16CONS6817_S02'16
CONS6817_S02'16
 
Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17 Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
Raffles International Institute_Procurement methods
Raffles International  Institute_Procurement methodsRaffles International  Institute_Procurement methods
Raffles International Institute_Procurement methods
 
Partnering and partnering contracts presentation
Partnering and partnering contracts presentationPartnering and partnering contracts presentation
Partnering and partnering contracts presentation
 
PetroSync - Drilling Contract Negotiation & Management
PetroSync - Drilling Contract Negotiation & ManagementPetroSync - Drilling Contract Negotiation & Management
PetroSync - Drilling Contract Negotiation & Management
 
Architecture led procurement
Architecture led procurementArchitecture led procurement
Architecture led procurement
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
DESIGN & BUILD
DESIGN & BUILDDESIGN & BUILD
DESIGN & BUILD
 
Effective Contract Management
Effective Contract ManagementEffective Contract Management
Effective Contract Management
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Procurement system in the Indian construction industry issues and remedies
Procurement system in the Indian construction industry issues and remediesProcurement system in the Indian construction industry issues and remedies
Procurement system in the Indian construction industry issues and remedies
 
20050314 tips on contract management
20050314 tips on contract management20050314 tips on contract management
20050314 tips on contract management
 

Viewers also liked (9)

CONS6817_S05'16
CONS6817_S05'16CONS6817_S05'16
CONS6817_S05'16
 
Strategic planning is srewed up
Strategic planning is srewed upStrategic planning is srewed up
Strategic planning is srewed up
 
#sitFRA - Improving the UX for your users - Where to start?
#sitFRA - Improving the UX for your users - Where to start?#sitFRA - Improving the UX for your users - Where to start?
#sitFRA - Improving the UX for your users - Where to start?
 
M Sc Pm Lecture No 4 Risk
M Sc Pm Lecture No 4    RiskM Sc Pm Lecture No 4    Risk
M Sc Pm Lecture No 4 Risk
 
HMP Mercantile Corporation - The Sourcing Agent
HMP Mercantile Corporation - The Sourcing AgentHMP Mercantile Corporation - The Sourcing Agent
HMP Mercantile Corporation - The Sourcing Agent
 
BE CoNTRARIAN
BE CoNTRARIANBE CoNTRARIAN
BE CoNTRARIAN
 
Ux forum lean coffee with kanban
Ux forum lean coffee with kanbanUx forum lean coffee with kanban
Ux forum lean coffee with kanban
 
Tel Aviv Turner
Tel Aviv TurnerTel Aviv Turner
Tel Aviv Turner
 
Procurement Presentation
Procurement PresentationProcurement Presentation
Procurement Presentation
 

Similar to CONS6817_S08'16

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 

Similar to CONS6817_S08'16 (20)

CONS6817_S02'16
CONS6817_S02'16CONS6817_S02'16
CONS6817_S02'16
 
CONS6817_S01'16
CONS6817_S01'16CONS6817_S01'16
CONS6817_S01'16
 
Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010
 
AGC Webinar
AGC WebinarAGC Webinar
AGC Webinar
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
CEFPI Journal job order contracting opens doors to new era
CEFPI Journal job order contracting opens doors to new eraCEFPI Journal job order contracting opens doors to new era
CEFPI Journal job order contracting opens doors to new era
 
Business Excellence and Enhancement of ROI by Dr Punit Sethi
Business Excellence and Enhancement of ROI by Dr Punit SethiBusiness Excellence and Enhancement of ROI by Dr Punit Sethi
Business Excellence and Enhancement of ROI by Dr Punit Sethi
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
TURNKEY PROJECT.pptx
TURNKEY PROJECT.pptxTURNKEY PROJECT.pptx
TURNKEY PROJECT.pptx
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptx
 
Agile on the beach 2014: Contracted to deliver outcomes
Agile on the beach 2014: Contracted to deliver outcomesAgile on the beach 2014: Contracted to deliver outcomes
Agile on the beach 2014: Contracted to deliver outcomes
 
Robert O'Hara current cv details
Robert O'Hara current cv detailsRobert O'Hara current cv details
Robert O'Hara current cv details
 
CIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of Talk
CIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of TalkCIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of Talk
CIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of Talk
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Project success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementProject success through excellence in procurement and contract management
Project success through excellence in procurement and contract management
 
Contract management iritm aug2016
Contract management iritm aug2016Contract management iritm aug2016
Contract management iritm aug2016
 

Recently uploaded

1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Recently uploaded (20)

Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 

CONS6817_S08'16

  • 1. Procurement (CONS6817) Lara Tookey & John Boon PROCUREMENT – SESSION #8 Strategic Long Term Partnering Framework agreements Introduction to PPPs – Public Private Partnering
  • 2. Procurement (CONS6817) Lara Tookey & John Boon WHAT’S THE PROBLEM? The behavioural aspects of projects
  • 3. Procurement (CONS6817) Lara Tookey & John Boon Typical organisation on DBB project All parties selected on the basis of lowest price • Need to minimise expenditure • Need to increase price wherever possible Architect Engineers QS Construction Contractor Sub-contractors & Suppliers Project Manager
  • 4. Procurement (CONS6817) Lara Tookey & John Boon Normal behaviour is….. • Tendency is for parties to the project to stand apart from one another; • Demand the other party perform as required by the contract; and • Pursue claims against them when they fail to perform.
  • 5. Procurement (CONS6817) Lara Tookey & John Boon Normal behaviour is….. • Do not seek to assist other party(s) to perform; • No attempt to help the other party overcome a problem when they hit one; • Never consider exceeding the requirements of the contract; and • Never consider mutually beneficial ways of improving on the deliverables
  • 6. Procurement (CONS6817) Lara Tookey & John Boon End result tends to be…. • Projects delivered to marginally acceptable quality standards; • Contractors and consultants only achieve marginally acceptable levels of profitability; • Cost and time overruns; and • Contract completion involves a process of resolving significant numbers of claims either by negotiation or litigation.
  • 7. Procurement (CONS6817) Lara Tookey & John Boon Plus the issues of lack of constructor input into the design process ……
  • 8. Procurement (CONS6817) Lara Tookey & John Boon WHEN THINGS GO RIGHT... Strategic partnering – long(er) term relationships
  • 9. Procurement (CONS6817) Lara Tookey & John Boon IF YOU CAN MAKE SIGNIFICANT GAINS BY COLLABORATING ON ONE OFF PROJECTS YOU SHOULD BE ABLE TO MAKE EVEN BIGGER GAINS IF YOU WORKED TOGETHER COLLABORATIVELY ON A SERIES OF PROJECTS. LONG TERM STRATEGIC RELATIONSHIPS
  • 10. Procurement (CONS6817) Lara Tookey & John Boon UK EXPERIENCE
  • 11. Procurement (CONS6817) Lara Tookey & John Boon Egan report – Rethinking Construction 1998 • Debilitating cycle of competitive tender, conflict, low margins and dissatisfied clients • The industry must replace competitive tendering with long time relationships based on clear measurement of performance and sustained improvement in quality and efficiency
  • 12. Procurement (CONS6817) Lara Tookey & John Boon CLIENT LED CHANGE
  • 13. Procurement (CONS6817) Lara Tookey & John Boon
  • 14. Procurement (CONS6817) Lara Tookey & John Boon • Early 2000 Sinclair Knight Merz (SKM) was appointed as part of a client-led team to undertake a fundamental review of the design, procurement and construction of retail assets for Tesco Stores Limited. • The brief (design & construction professionals): • significantly reduce construction costs and build programmes for new retail space, whilst improving the shopping experience, through rationalisation, standardisation and simplification.
  • 15. Procurement (CONS6817) Lara Tookey & John Boon • A trial store at Haverfordwest (£4.75m), completed in March 2000, confirmed the success of the design initiatives as the target costs and programme were achieved. • Retaining the same team, building on the success of the original project & improving all aspects of the store design and construction • two new trial store projects at Downham Market (£3.5m) and Cardiff, Pengam Green (£6.15m) were commissioned
  • 16. Procurement (CONS6817) Lara Tookey & John Boon • A complete review of the building structure, fabric and services, together with the retail design, was undertaken and new initiatives were included in particular to modularise plant, specific retail elements and ancillary areas, such as toilets. • The new stores were completed in April 2001, again within cost and programme targets, despite significant site-specific challenges.
  • 17. Procurement (CONS6817) Lara Tookey & John Boon • Sovereign Construction has been working with Tesco Stores Limited for over 30 years. • Challenges on a project: • A short program duration in order to complete and open pre-xmas in order to benefit from the enhanced trading period. • An extremely busy and congested central London location. • Noise and delivery restrictions creating greater pressure on the short program duration. • Local Authority planning restrictions and The Kensington Society ( a local residents association) conservation requirements.
  • 18. Procurement (CONS6817) Lara Tookey & John Boon • Solutions: • Promote a "One Team" approach with the client, retail, professionals and Local Authority. • Detailed and complex programming in order to meet the required opening date and adhere to the significant restrictions on working times and deliveries. • Working within pre-agreed times to ensure that residents were not disturbed. • Detailed planning with regards to deliveries to overcome the traffic and congestion issues. • Good, consistent and regular communication with both the local authority, the Kensington Society and where appropriate local residents and businesses.
  • 19. Procurement (CONS6817) Lara Tookey & John Boon
  • 20. Procurement (CONS6817) Lara Tookey & John Boon
  • 21. Procurement (CONS6817) Lara Tookey & John Boon “As a leading construction company we aim to be the UK's first choice construction partner for delivery of services to the community.” MANSELL
  • 22. Procurement (CONS6817) Lara Tookey & John Boon • “Our dedication to customer service and nurturing long-term relationships brings us high levels of repeat business and the ability to invest and grow”. • 85% repeat business – frameworks and sustainable relationships • Turnover up 24%
  • 23. Procurement (CONS6817) Lara Tookey & John Boon
  • 24. Procurement (CONS6817) Lara Tookey & John Boon
  • 25. Procurement (CONS6817) Lara Tookey & John Boon
  • 26. Procurement (CONS6817) Lara Tookey & John Boon COMMERCIAL ARRANGEMENTS Framework agreement
  • 27. Procurement (CONS6817) Lara Tookey & John Boon Framework Agreement • An umbrella agreement under which the parties enter into a number of project specific contracts • Typically 3 – 5 year agreements • Can be non-binding or legally binding
  • 28. Procurement (CONS6817) Lara Tookey & John Boon Contents of framework agreement include - 1 • Scope - the services to be provided • Volume – the agreement may specify the volume of work to be provided • Pricing mechanisms – how the price for the services on individual projects will be determined • Risk and reward – painshare/gainshare provisions
  • 29. Procurement (CONS6817) Lara Tookey & John Boon Contents of framework agreement include - 2 • Performance specification • Performance measures (KPIs) (often raised during the period of the framework) • Performance incentives • Direct payments on achieving targets • Share of total work relative to other framework contractors • Learning from project to project • Innovation provisions • How the parties will work together to achieve innovation • Who will fund what R&D
  • 30. Procurement (CONS6817) Lara Tookey & John Boon Contents of framework agreement include - 3 • Supply chain provisions • Working with other framework contractors (eg design consultants) • How the contractor will manage their own supply chain (will they have framework agreements with sub-contractors)
  • 31. Procurement (CONS6817) Lara Tookey & John Boon Typical building project under a framework agreement • Contractor involved in cost planning throughout early design stages to establish a target cost (verified by independent QS) • As the design phase progresses the target cost is refined and then fixed • A contract is entered into between the client and the framework contractor (based on terms and conditions specified in the framework agreement)
  • 32. Procurement (CONS6817) Lara Tookey & John Boon Typical payment models • Full cost reimbursement + margin • P&G + margin • Cost reimbursement of subcontractors and suppliers • In either case gainshare/painshare provisions apply
  • 33. Procurement (CONS6817) Lara Tookey & John Boon Benefits to client • Improved predictability • Cost • Time • Improved risk management • Reduced time and cost in tendering individual projects • Improved performance over time: • Value for money (cost efficiency) • Project duration • Quality
  • 34. Procurement (CONS6817) Lara Tookey & John Boon Benefits to contractor • Continuity of work • Ability to contribute to the design phase and achieve construction efficiency • Benefits from gainshare provisions • Reduction in tender costs
  • 35. Procurement (CONS6817) Lara Tookey & John Boon PPP’s ARE THESE JUST THE NEXT STEP, OR ARE THEY SOMETHING A BIT MORE SERIOUS?
  • 36. Procurement (CONS6817) Lara Tookey & John Boon Public Procurement Engineer / Architect D Contractor B Bank / Financier F Operator O Public Authority Investors Users Shareholders Agreement Consultancy Agreement Construction Contract Loan Employment / O&M Contract Tax/Rates/Tolls/Le ase
  • 37. Procurement (CONS6817) Lara Tookey & John Boon PPP Procurement Engineer / Architect D Contractor B Bank / Financier F Operator O Special Purpose Vehicle Investors Users Shareholders Agreement Consultancy Agreement Construction Contract Loan Employment / O&M Contract Tax/Rates/Tolls/Le ase Public Authority Concession Agreement
  • 38. Procurement (CONS6817) Lara Tookey & John Boon What is a PPP / PFi? • Public = public sector authority • Private = private organisations • Partnership = risk sharing relationship (not merely regulatory or short term contract) • PFI (Private Finance Initiative) • A generic classifier for all types of PPP construction.
  • 39. Procurement (CONS6817) Lara Tookey & John Boon What are Public Private Partnerships? • ‘A contractual arrangement between public and private sectors with clear agreement on shared objectives for the delivery of public infrastructure and/or public services by the private sector that would have otherwise been provided through traditional public sector procurement’ • Extracted from Russell Kenley notes quoting Akintoye 2003
  • 40. Procurement (CONS6817) Lara Tookey & John Boon Public-Private-Partnerships • Narrow definition: “instead of the public sector procuring a capital asset by paying for it in full up front, the effect of a typical PPP structure is usually to create a single stand alone business, financed and operated by the private sector. The purpose is to create the asset and then deliver a service to the public sector client, in return for payment commensurate with the service levels provided.” • International Financial Services, June 2001
  • 41. Procurement (CONS6817) Lara Tookey & John Boon Underlying Philosophy • The private sector executes projects and delivers services more efficiently and manages the risks better. • If the private sector bears both the initial capital and operating costs it will make better “whole of life” cost judgements.
  • 42. Procurement (CONS6817) Lara Tookey & John Boon A few important things: • It must relate to the provision of public services or public infrastructure. • It necessitates the transfer of risk between partners. • If the arrangement does not include these two concepts, they are not technically “ppp’s”. • No universal definition of P3. • Covers a wide range of projects, depending on asset ownership, risk sharing, financing & operation.
  • 43. Procurement (CONS6817) Lara Tookey & John Boon • FOR PPP’s/PFI’s “government” can mean any level of government • national, regional or local.
  • 44. Procurement (CONS6817) Lara Tookey & John Boon WHAT DOES A PPP LOOK LIKE?
  • 45. Procurement (CONS6817) Lara Tookey & John Boon
  • 46. Procurement (CONS6817) Lara Tookey & John Boon PPP Procurement Engineer / Architect D Contractor B Bank / Financier F Operator O Special Purpose Vehicle Investors Users Shareholders Agreement Consultancy Agreement Construction Contract Loan Employment / O&M Contract Tax/Rates/Tolls/Le ase Public Authority Concession Agreement
  • 47. Procurement (CONS6817) Lara Tookey & John Boon Wi Wiri Prison – Full Service PPP DBFOM
  • 48. Procurement (CONS6817) Lara Tookey & John Boon Special Purpose Vehicle (SPV) • A company incorporated solely for the implementation / management of the project. • Enters into contracts with the Government and sub-contractors. • Finances, develops, builds, maintains and operates the project (or any other combination). • Guarantee and secure cash flows.