1 of 41
Contracted to 
deliver outcomes 
Agile on the Beach - September 2014
Introduction 
Kris Lander / @EnergizedKris 
www.energizedwork.com / @energizedwork 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Outcomes for this presentation 
● An understanding of how and why Energized Work’s approach to 
creating value for our clients has evolved over its history. 
● An understanding of how Energized Work is trying to create a contract 
model that aligns with its current outcomes-based approach. 
● An understanding of commercial contracts and typical contract models 
for software procurement 
● An understanding of the clash between an agile software delivery and 
traditional software contract models 
● An understanding of the most common agile contract model approaches 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
A teaser: What we do today 
We help companies design, manage and deliver programs of work which 
revolve around technology. 
We focus on aligning our engagements with the business strategy of our 
clients to achieve positive outcomes. 
Realising outcomes forms the basis of our contractual obligation to our clients 
and part of our payment is determined by measuring our impact on business 
outcomes. 
We are contracted to deliver outcomes. Let’s explore how we got there. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
A brief history 
of 
Energized Work 
2006 - 2009 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
History of EW: Agile Warriors 
Problem: Repeatable, predictable delivery 
Early 2000s 
● Professional software development wasn’t much fun. At least for me. 
● Began adoption of agile practices and methods. Learning and 
increasingly competent in applying process and technical practices. 
2006: In the right place, at the right time with the right people. 
● Step change in terms of speed, predictability and quality. 
● Success of team led Simon and Gus to found Energized Work. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
History of EW: Got ROI? 
Problem: Understanding the value delivered by teams 
2007: Project rescue 
● Macro measures of value/effectiveness became focused on £ invested 
vs user growth. 
● Adoption of Lean and ToC methods to focus on managing/measuring 
WIP, cycle time, queues, etc which made case for delivering more value 
over time. 
2008: Governance / PMO 
● Business and product strategy across portfolio lived outside of agile 
delivery and carried unvalidated assumptions about market and 
customer needs which was a far bigger risk to ROI. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
History of EW: Making hard 
choices 
Problem: Successful business strategy is more than just following the money. 
2009: Evaluation of IT strategy 
● Assessment of IT delivery capability and existing trading platform 
● Difficult to quantify return on investment in simple £ 
● Big gap in terms of expressing value to board led to realisation that there 
was a gap in our ability to express the value we were delivering 
(Irony: Financial industry has great tools for pricing information and risk management) 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Our Agile Journey 
Picking on a few of principles from the agile manifesto: 
“Our highest priority is to satisfy the customer through 
early and continuous delivery of valuable software.” 
“Working software is the primary measure of progress.” 
“Continuous attention to technical excellence and good design 
enhances agility.” 
(We had tended to do better with the terms on the left, as opposed to the 
terms on the right.) 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
We’d come along way… 
Technical excellence to achieve early and continuous delivery of working 
software. 
More responsive and predictable: 
● Just enough, just in time: small stories, short iterations and constraining 
work in process 
● Reduced cycle time/lead times, shipping regularly. 
Disciplined techniques produced working, maintainable software: 
● Test and deployment automation (CI/CD) 
● BDD/TDD 
Self organising teams have promoted collaboration, transparency and 
visibility. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
But we had some way to go… 
Measuring progress 
● Being judged/focused on output (Velocity, Features, etc) as a proxy for 
productivity. 
Good design 
● Agile methods have never explicitly addressed design, be it user 
experience design or technical design. 
Valuable work/software 
● Value needs to be based on more than subjective judgments and is 
more complicated than simple ROI (e.g. balancing multiple stakeholder 
needs) 
See Simon Baker’s paper No Bull. http://nobull.energizedwork.com/ 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Making a sale. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
A Request for Proposal 
Client makes a request for proposal: 
● Provides a brief: requirement spec (stories), wireframes, etc. 
● Client RFP covers wide area of ground. 
Client wants the supplier to demonstrate that they can deliver everything 
they want within their budget. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
“Requirements” 
“As a user, I am able to login to the application using the email/password 
credentials with which I registered with, so that I can access my account 
details.” 
We have 50 requirements like these. 
Performance requirements: 
The website must have an availability of 99.999% 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
How much and how long? 
The supplier knows that unless they have built something very similar before: 
● estimation of cost and time is very difficult with sparse information 
● performance requirements and dependencies are potential icebergs. 
● they don’t have a good understanding of what is more or less valuable to the 
client’s customers and other stakeholders 
So the supplier makes other promises as an alternative to committing to the 
unknown: 
● Early delivery of working software into production first week, every week. 
● Short statements of work (investment cycle), start and stop when it suits you. 
● Pay us for Time and Materials and take a leap of faith. 
But the client needs to know: How much and how long?! 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Time to get on with it… 
Client and supplier attempt to improve the existing requirements, clarify the 
unknowns and agree to cut down the scope in the hope that an agreement can 
be reached. 
Time is against both parties. The client has deadlines and the supplier’s cost of 
sales is spiraling out of control. 
Luckily, the client and supplier have developed a good relationship. The supplier 
has impressed with their expertise and insights and the client has been pragmatic 
and accommodating. 
It doesn't always work out that way. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Bounded by the contract 
The supplier wants to iterate in partnership with the client to discover and deliver 
what is valuable, but they know it’s very risky to deviate from the features 
specified in the contract. 
The client appreciates the focus on value the supplier brings, but they have to hit 
their deadlines and can’t go over budget. 
When things get tough will contract help or hinder? 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Contracts 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Contracts - Definition 
What is a contract? 
“a written or spoken agreement, especially one concerning employment, sales, or tenancy, 
that is intended to be enforceable by law.” 
“an agreement with specific terms between two or more persons or entities in which there is a 
promise to do something in return for a valuable benefit known as consideration.” 
The elements: 
● Offer and acceptance (meeting of minds) 
● Promise to perform (with commitments e.g. by date) 
● Consideration (payment) 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Contracts - The basic types 
Performance: But typical a definition of what is to be done. 
Pricing Models 
● Fixed Price variants 
● Cost Reimbursement variants 
● Time (Labour) and materials 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Contract model FAIL 
Why it doesn’t work: Traditional contracts, especially fixed price, fixed scope 
create many if the same problems as waterfall software development. 
● Specification of what is to be done, by when and makes the assumption 
that we know everything. 
● Risk for client isn’t just getting what they want done, but what they need 
(ROI) 
● Contract makes responding to change undesirable and expensive 
● Fixed scope, fixed cost, fixed time (we know what happens to quality) 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Fixed Price, Fixed Scope for Software 
We asked a 100 agile practitioners name reasons that fixed price, fixed scope 
contracts continue to be the most common form of contract for software 
procurement. 
● Easy to understand, I will get X for £Y by date 
● Prevailing belief that building software is like other construction industries. 
● Easiest to align with traditional business planning and budgeting 
● Constrained by policies of legal and procurement dept. 
● Client believes definition of what is to be done, is what they need, and this can 
be made transferrable & understandable in contract 
● Client feels that they are safely offloading responsibility and risk to supplier 
● Client gets to beat down supplier on price, supplier gets to claw back in 
changes 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
IT Programmes 
60% do not meet schedule, budget or quality goals. 
IBM 
50% fail to achieve what they set out to achieve. 
KPMG 
17% go so badly they can threaten the existence of the 
company. 
McKinsey & Company 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
The clash: Agile vs Contracts 
Evolutionary vs. Big Bang: One single contract for the expected lifetime of the project 
where delivery is only contractually enforceable at the end. 
Value vs. Scope: Contract typically specify a set of features without describing how 
they create value for the client. 
Initiative vs. Control: Business/product owner relationship is client/supplier and 
promote top-down management rather than collaboration. 
Satisfaction vs. Compliance: Supplier is incentivised to optimise for contractual 
compliance over customer satisfaction. 
Solutions vs. Retribution : Implicit design of solutions are legally bound into contract. 
Alternatives could be considered non-compliance and potentially punished. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Agile contracts 
Attempt to align better around agile methods: 
● Fixed price or time & materials as typical pricing model 
● Iterative/incremental statements of work define shorter chucks of scope 
● Provisions for scope of work to change or finish early 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Agile contracts: some examples 
Optional Scope Contracts 
(Short fixed price iterations, with fixed “quality”, time but variable scope) 
Money For Nothing, Change For Free 
(scope/priorty can change each iteration, client get to cut project short if there 
is no further ROI) 
Fixed Price per Story Point 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Agile contracts... 
Focus on what we’ve been good at doing: 
● Iterative, incremental delivery of working software 
● Responding to change 
Still a leap (albeit smaller) of faith for the client and failing to make explicit: 
● Delivery of business value 
● Means to measure progress in terms of business value 
● Providing context for design performance requirements and constraints 
(e.g. usability, security, reliability) connected to business value. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
A brief history 
of 
Energized Work 
(part 2) 
2009 - 2013 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Inspirations 
Customer Development /Lean Startup - Steve Blank/Eric Reis 
● Clear goal: Discover and execute a viable product/business 
● Puts the entire business in the PDCA cycle 
● Forces us to confront business assumptions and risk 
● Focuses on key business/product metrics (innovation accounting) 
● Optimized for learning/discovery 
Book recommendation: Lean Analytics by Alistair Croll & Benjamin Yoskovitz 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Inspirations 
Lean Product Development, Cost of Delay, CD3 - Don Reinertsen 
● Economic re-evaluation of lean principles taken from manufacturing 
● Insights into the effects of uncertainty, variability and risk. 
● Powerful prioritisation tool, CD3, that optimises for value over time. 
● value has to be quantified (avoid/reduce costs, increase/protect revenue) 
Book recommendation: The Principles of Product Development Flow by Don 
Reinertsen 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Inspirations 
Tom Gilb – EVO 
● Approach and method optimised for stakeholder outcomes/value 
● Numeric, quantified outcomes 
● Separation of requirements (ends) and designs (means) 
● Powerful design engineering methods 
● 12 Tough Questions 
● No Cure, No Pay 
Book recommendation: Competitive Engineering by Tom Gilb 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
History of EW: Strategy Discovery 
Defining a strategy was the outcome required by the client. Strategy in the 
time horizon of 2-5 years could only be defined in terms of business 
outcomes. 
This time the supporters and dissenters roles were reversed: 
● Brought clarity to the function of the business and could understand what 
they needed to do in terms of outcomes. 
● Rejection by IT management who wanted a plan of what to do, as they 
feared leaving design of solutions in the hands of the masses. 
This raised a big question - how do we design/engineer, particularly at scale. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
History of EW: Legacy 
Replacement 
Discovery engagement to define strategy to replace legacy system. 
This time we applied EVO methods to: 
● Define and quantify stakeholder goals 
● Evaluate design options for discovery of information 
● Evaluate best technical approach to replace the legacy system 
Providing frame for legacy replacement in terms of outcomes for the 
business. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
History of EW: Lean Startups 
Delivery an MVP of a mobile POS iPad app. 
We help define business and product goals to bring their product to market 
successfully. 
e.g. Number of sales, NPS score and merchants ability to complete biz 
functions (e.g. how well a merchant could complete a transaction with their 
customers) 
This allowed us to then quantify our contribution as their technology partner. 
We tied part of our payment to meeting those goals! 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Outcome-based approach: Why 
● Shared, defined understanding of what is valuable (and to who) that 
focuses the everyone on realising positive outcomes for the business 
● Reduce the risk of subjective and emotive stakeholder judgment by 
providing a more factual basis for analysing progress. 
● Allows us to measure progress in terms realising outcomes/biz value 
● Good outcomes change far less than good feature specifications. 
● More design freedom with feedback loop so we can learn what will 
produce the biggest impact. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Outcome-based approach: Why not 
● You can fail and you can't hide it (but everyone can learn from it) 
● It’s hard (but very valuable) to reduce an engagement down to a set of 
outcomes that can be clearly understood by stakeholders. 
● It can surface conflicts between stakeholders that result in paralysis and 
politicking. 
● Some clients find more value in seeing people busy rather than 
delivering value - the "activity trap" 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
If outcomes are the deliverable… 
Then we should attempt to put them in the contract. 
Our Strategy: 
● Every engagement must have engagement goals defined as outcomes 
for the client. 
● Client outcomes will be part of our contractual agreements. 
And we are trying to go a step further: 
● We will try sell risk and reward-based engagements and not just our 
time. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
An example of what’s in our contract 
Investor outcome: (external 
stakeholder 
management) 
Investors are satisfied with the 
Investment Service provided 
Goal: avg. Acceptable – 15thOct 2014 
Goal: avg. Good – 15th Dec 2014 
Goal: avg. Excellent – 15th Feb 2015 
Process outcome: (capability) 
1. Quantify Risk per 
Investment 
● Goal: First Product 
Set – 15th Sept 2014 
● Goal: All 
Investments – 1st 
Jan 2015 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com 
Product uptake outcome: 
Onboard Partners: 
1 Partner by Q2 2014 
2-4 by Q4 2014 
5 - 20 by Q2 2015 
Reduce Opex Hosting Costs: 
50K/month - Q1 2013 
10K/month - Q4 2013 
Scale: 
<150 (<800 peak) requests/sec 
- Q2 2014 
<300 (<1400 peak) 
requests/sec - Q4 2014 
Reduce the Average Length of 
Stay: 
● Medical 
○ Complexity < 3: 1.6 
days 
● Surgical 
○ Gastro: 2.2days 
○ Neuro: 6 days 
Outcomes are a) a future state and b) measurable and independently verifiable by some means. They 
can vary wildly with context (product, usage, performance, efficiency, capability etc.)
An idea worth spreading? 
We believe that we are reaching a critical mass as people reach similar conclusions. 
(Some people reached them many years ago!) 
Agile has been mainstream for some time and we see that many people are 
experiencing a disconnect between “building all the things” faster and the meaning in 
their work – i.e. how it creates value. 
We believe that having well defined outcomes are the foundation of success which 
promote trust and collaboration and freeing us all to creatively design better solutions 
to realise them. Outcomes can also be the bedrock of better commercial relationships. 
ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
Feedback !
Questions ?

More Related Content

Viewers also liked

Governance - Friend or Foe?
Governance - Friend or Foe?Governance - Friend or Foe?
Governance - Friend or Foe?Energized Work
 
Profession: Agile Coach
Profession: Agile CoachProfession: Agile Coach
Profession: Agile CoachPierre E. NEIS
 
Managing time in agile
Managing time in agileManaging time in agile
Managing time in agilePierre E. NEIS
 
Giving sense to complexity PMI Lebanon
Giving sense to complexity PMI LebanonGiving sense to complexity PMI Lebanon
Giving sense to complexity PMI LebanonPierre E. NEIS
 
Introduction of the Agile Digital Enterprise Framework
Introduction of the Agile Digital Enterprise FrameworkIntroduction of the Agile Digital Enterprise Framework
Introduction of the Agile Digital Enterprise FrameworkPierre E. NEIS
 
Rising to the Agility Challenge
Rising to the Agility ChallengeRising to the Agility Challenge
Rising to the Agility ChallengeDragan Jojic
 
Ignition team - creating agile companies
Ignition team - creating agile companiesIgnition team - creating agile companies
Ignition team - creating agile companiesAgileOnTheBeach
 
Waltzing with Branches [Agile o/t Beach]
Waltzing with Branches [Agile o/t Beach]Waltzing with Branches [Agile o/t Beach]
Waltzing with Branches [Agile o/t Beach]Chris Oldwood
 
Do It Right then Do the Right Thing
Do It Right then Do the Right ThingDo It Right then Do the Right Thing
Do It Right then Do the Right Thingallan kelly
 
Can You Be Agile and Compliant?
Can You Be Agile and Compliant?Can You Be Agile and Compliant?
Can You Be Agile and Compliant?IDBS
 
Winning clients' trust with Agile project management
Winning clients' trust with Agile project management Winning clients' trust with Agile project management
Winning clients' trust with Agile project management cameronandwilding
 
23 Things to know before starting an agile organisational transformation
23 Things to know before starting an agile organisational transformation 23 Things to know before starting an agile organisational transformation
23 Things to know before starting an agile organisational transformation Pierre E. NEIS
 
Awesome People Management with Agile
Awesome People Management with AgileAwesome People Management with Agile
Awesome People Management with AgileMeri Williams
 
Le contrat agile ce n'est pas si simple que ça
Le contrat agile ce n'est pas si simple que çaLe contrat agile ce n'est pas si simple que ça
Le contrat agile ce n'est pas si simple que çaFranck Beulé
 

Viewers also liked (20)

Governance - Friend or Foe?
Governance - Friend or Foe?Governance - Friend or Foe?
Governance - Friend or Foe?
 
Agile Verträge
Agile VerträgeAgile Verträge
Agile Verträge
 
Profession: Agile Coach
Profession: Agile CoachProfession: Agile Coach
Profession: Agile Coach
 
Managing time in agile
Managing time in agileManaging time in agile
Managing time in agile
 
Giving sense to complexity PMI Lebanon
Giving sense to complexity PMI LebanonGiving sense to complexity PMI Lebanon
Giving sense to complexity PMI Lebanon
 
Introduction of the Agile Digital Enterprise Framework
Introduction of the Agile Digital Enterprise FrameworkIntroduction of the Agile Digital Enterprise Framework
Introduction of the Agile Digital Enterprise Framework
 
Rising to the Agility Challenge
Rising to the Agility ChallengeRising to the Agility Challenge
Rising to the Agility Challenge
 
Ignition team - creating agile companies
Ignition team - creating agile companiesIgnition team - creating agile companies
Ignition team - creating agile companies
 
Waltzing with Branches [Agile o/t Beach]
Waltzing with Branches [Agile o/t Beach]Waltzing with Branches [Agile o/t Beach]
Waltzing with Branches [Agile o/t Beach]
 
Test-Driven SQL
Test-Driven SQLTest-Driven SQL
Test-Driven SQL
 
Do It Right then Do the Right Thing
Do It Right then Do the Right ThingDo It Right then Do the Right Thing
Do It Right then Do the Right Thing
 
Agile Contracts
Agile ContractsAgile Contracts
Agile Contracts
 
Can You Be Agile and Compliant?
Can You Be Agile and Compliant?Can You Be Agile and Compliant?
Can You Be Agile and Compliant?
 
Smart Metrics
Smart Metrics  Smart Metrics
Smart Metrics
 
Winning clients' trust with Agile project management
Winning clients' trust with Agile project management Winning clients' trust with Agile project management
Winning clients' trust with Agile project management
 
23 Things to know before starting an agile organisational transformation
23 Things to know before starting an agile organisational transformation 23 Things to know before starting an agile organisational transformation
23 Things to know before starting an agile organisational transformation
 
System Error
System ErrorSystem Error
System Error
 
Open Communication wins
Open Communication winsOpen Communication wins
Open Communication wins
 
Awesome People Management with Agile
Awesome People Management with AgileAwesome People Management with Agile
Awesome People Management with Agile
 
Le contrat agile ce n'est pas si simple que ça
Le contrat agile ce n'est pas si simple que çaLe contrat agile ce n'est pas si simple que ça
Le contrat agile ce n'est pas si simple que ça
 

Similar to Agile on the beach 2014: Contracted to deliver outcomes

Carbon60 Business Overview
Carbon60 Business OverviewCarbon60 Business Overview
Carbon60 Business OverviewDaniel Fenton
 
Tenant Focus: Winning Efficiency Projects in the Commercial Space
Tenant Focus: Winning Efficiency Projects in the Commercial SpaceTenant Focus: Winning Efficiency Projects in the Commercial Space
Tenant Focus: Winning Efficiency Projects in the Commercial SpaceZondits
 
Rainbow Developers With Blue Background
Rainbow  Developers With  Blue  BackgroundRainbow  Developers With  Blue  Background
Rainbow Developers With Blue Backgroundguest470ea8
 
Rainbow Developers With Blue Background
Rainbow  Developers With  Blue  BackgroundRainbow  Developers With  Blue  Background
Rainbow Developers With Blue BackgroundMansoor Chandio
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
Reinvent your sports and leisure building
Reinvent your sports and leisure buildingReinvent your sports and leisure building
Reinvent your sports and leisure buildingGraham Ford
 
Rainbow Developers Profile
Rainbow Developers ProfileRainbow Developers Profile
Rainbow Developers ProfileMansoor Chandio
 
Introduction to soft landings 2
Introduction to soft landings 2Introduction to soft landings 2
Introduction to soft landings 2Marie Orritt
 
RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...
RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...
RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...EMEX
 
Contract Management - Generating Real Value from your Contracts
Contract Management - Generating Real Value from your ContractsContract Management - Generating Real Value from your Contracts
Contract Management - Generating Real Value from your ContractsTejari
 
brochure template (Autosaved)
brochure template (Autosaved)brochure template (Autosaved)
brochure template (Autosaved)Russell Myers
 
Woodford Capability Document 2017
Woodford Capability Document 2017Woodford Capability Document 2017
Woodford Capability Document 2017Roy Alderslade
 
Agile business development
Agile business developmentAgile business development
Agile business developmentSmartOrg
 
paul_jubb cv 16May15
paul_jubb cv  16May15paul_jubb cv  16May15
paul_jubb cv 16May15Paul Jubb
 
Generating Real Value from your Contracts
Generating Real Value from your ContractsGenerating Real Value from your Contracts
Generating Real Value from your ContractsBravoSolution
 
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Андрій Просов  “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...Андрій Просов  “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...Lviv Startup Club
 

Similar to Agile on the beach 2014: Contracted to deliver outcomes (20)

Carbon60 Business Overview
Carbon60 Business OverviewCarbon60 Business Overview
Carbon60 Business Overview
 
Tenant Focus: Winning Efficiency Projects in the Commercial Space
Tenant Focus: Winning Efficiency Projects in the Commercial SpaceTenant Focus: Winning Efficiency Projects in the Commercial Space
Tenant Focus: Winning Efficiency Projects in the Commercial Space
 
Rainbow Developers With Blue Background
Rainbow  Developers With  Blue  BackgroundRainbow  Developers With  Blue  Background
Rainbow Developers With Blue Background
 
Rainbow Developers With Blue Background
Rainbow  Developers With  Blue  BackgroundRainbow  Developers With  Blue  Background
Rainbow Developers With Blue Background
 
Green line profile
Green line profile Green line profile
Green line profile
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Reinvent your sports and leisure building
Reinvent your sports and leisure buildingReinvent your sports and leisure building
Reinvent your sports and leisure building
 
Rainbow Developers Profile
Rainbow Developers ProfileRainbow Developers Profile
Rainbow Developers Profile
 
Rainbow Developers
Rainbow  DevelopersRainbow  Developers
Rainbow Developers
 
Introduction to soft landings 2
Introduction to soft landings 2Introduction to soft landings 2
Introduction to soft landings 2
 
RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...
RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...
RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...
 
Contract Management - Generating Real Value from your Contracts
Contract Management - Generating Real Value from your ContractsContract Management - Generating Real Value from your Contracts
Contract Management - Generating Real Value from your Contracts
 
brochure template (Autosaved)
brochure template (Autosaved)brochure template (Autosaved)
brochure template (Autosaved)
 
Credicon Introduction
Credicon  IntroductionCredicon  Introduction
Credicon Introduction
 
Woodford Capability Document 2017
Woodford Capability Document 2017Woodford Capability Document 2017
Woodford Capability Document 2017
 
Agile business development
Agile business developmentAgile business development
Agile business development
 
paul_jubb cv 16May15
paul_jubb cv  16May15paul_jubb cv  16May15
paul_jubb cv 16May15
 
Blue Ocean Ventures
Blue Ocean VenturesBlue Ocean Ventures
Blue Ocean Ventures
 
Generating Real Value from your Contracts
Generating Real Value from your ContractsGenerating Real Value from your Contracts
Generating Real Value from your Contracts
 
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Андрій Просов  “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...Андрій Просов  “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
 

Recently uploaded

Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 

Recently uploaded (20)

Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 

Agile on the beach 2014: Contracted to deliver outcomes

  • 1. Contracted to deliver outcomes Agile on the Beach - September 2014
  • 2. Introduction Kris Lander / @EnergizedKris www.energizedwork.com / @energizedwork ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 3. Outcomes for this presentation ● An understanding of how and why Energized Work’s approach to creating value for our clients has evolved over its history. ● An understanding of how Energized Work is trying to create a contract model that aligns with its current outcomes-based approach. ● An understanding of commercial contracts and typical contract models for software procurement ● An understanding of the clash between an agile software delivery and traditional software contract models ● An understanding of the most common agile contract model approaches ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 4. A teaser: What we do today We help companies design, manage and deliver programs of work which revolve around technology. We focus on aligning our engagements with the business strategy of our clients to achieve positive outcomes. Realising outcomes forms the basis of our contractual obligation to our clients and part of our payment is determined by measuring our impact on business outcomes. We are contracted to deliver outcomes. Let’s explore how we got there. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 5. A brief history of Energized Work 2006 - 2009 ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 6. History of EW: Agile Warriors Problem: Repeatable, predictable delivery Early 2000s ● Professional software development wasn’t much fun. At least for me. ● Began adoption of agile practices and methods. Learning and increasingly competent in applying process and technical practices. 2006: In the right place, at the right time with the right people. ● Step change in terms of speed, predictability and quality. ● Success of team led Simon and Gus to found Energized Work. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 7. History of EW: Got ROI? Problem: Understanding the value delivered by teams 2007: Project rescue ● Macro measures of value/effectiveness became focused on £ invested vs user growth. ● Adoption of Lean and ToC methods to focus on managing/measuring WIP, cycle time, queues, etc which made case for delivering more value over time. 2008: Governance / PMO ● Business and product strategy across portfolio lived outside of agile delivery and carried unvalidated assumptions about market and customer needs which was a far bigger risk to ROI. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 8. History of EW: Making hard choices Problem: Successful business strategy is more than just following the money. 2009: Evaluation of IT strategy ● Assessment of IT delivery capability and existing trading platform ● Difficult to quantify return on investment in simple £ ● Big gap in terms of expressing value to board led to realisation that there was a gap in our ability to express the value we were delivering (Irony: Financial industry has great tools for pricing information and risk management) ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 9. Our Agile Journey Picking on a few of principles from the agile manifesto: “Our highest priority is to satisfy the customer through early and continuous delivery of valuable software.” “Working software is the primary measure of progress.” “Continuous attention to technical excellence and good design enhances agility.” (We had tended to do better with the terms on the left, as opposed to the terms on the right.) ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 10. We’d come along way… Technical excellence to achieve early and continuous delivery of working software. More responsive and predictable: ● Just enough, just in time: small stories, short iterations and constraining work in process ● Reduced cycle time/lead times, shipping regularly. Disciplined techniques produced working, maintainable software: ● Test and deployment automation (CI/CD) ● BDD/TDD Self organising teams have promoted collaboration, transparency and visibility. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 11. But we had some way to go… Measuring progress ● Being judged/focused on output (Velocity, Features, etc) as a proxy for productivity. Good design ● Agile methods have never explicitly addressed design, be it user experience design or technical design. Valuable work/software ● Value needs to be based on more than subjective judgments and is more complicated than simple ROI (e.g. balancing multiple stakeholder needs) See Simon Baker’s paper No Bull. http://nobull.energizedwork.com/ ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 12. Making a sale. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 13. A Request for Proposal Client makes a request for proposal: ● Provides a brief: requirement spec (stories), wireframes, etc. ● Client RFP covers wide area of ground. Client wants the supplier to demonstrate that they can deliver everything they want within their budget. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 14. “Requirements” “As a user, I am able to login to the application using the email/password credentials with which I registered with, so that I can access my account details.” We have 50 requirements like these. Performance requirements: The website must have an availability of 99.999% ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 15. How much and how long? The supplier knows that unless they have built something very similar before: ● estimation of cost and time is very difficult with sparse information ● performance requirements and dependencies are potential icebergs. ● they don’t have a good understanding of what is more or less valuable to the client’s customers and other stakeholders So the supplier makes other promises as an alternative to committing to the unknown: ● Early delivery of working software into production first week, every week. ● Short statements of work (investment cycle), start and stop when it suits you. ● Pay us for Time and Materials and take a leap of faith. But the client needs to know: How much and how long?! ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 16. Time to get on with it… Client and supplier attempt to improve the existing requirements, clarify the unknowns and agree to cut down the scope in the hope that an agreement can be reached. Time is against both parties. The client has deadlines and the supplier’s cost of sales is spiraling out of control. Luckily, the client and supplier have developed a good relationship. The supplier has impressed with their expertise and insights and the client has been pragmatic and accommodating. It doesn't always work out that way. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 17. Bounded by the contract The supplier wants to iterate in partnership with the client to discover and deliver what is valuable, but they know it’s very risky to deviate from the features specified in the contract. The client appreciates the focus on value the supplier brings, but they have to hit their deadlines and can’t go over budget. When things get tough will contract help or hinder? ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 18. Contracts ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 19. Contracts - Definition What is a contract? “a written or spoken agreement, especially one concerning employment, sales, or tenancy, that is intended to be enforceable by law.” “an agreement with specific terms between two or more persons or entities in which there is a promise to do something in return for a valuable benefit known as consideration.” The elements: ● Offer and acceptance (meeting of minds) ● Promise to perform (with commitments e.g. by date) ● Consideration (payment) ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 20. Contracts - The basic types Performance: But typical a definition of what is to be done. Pricing Models ● Fixed Price variants ● Cost Reimbursement variants ● Time (Labour) and materials ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 21. Contract model FAIL Why it doesn’t work: Traditional contracts, especially fixed price, fixed scope create many if the same problems as waterfall software development. ● Specification of what is to be done, by when and makes the assumption that we know everything. ● Risk for client isn’t just getting what they want done, but what they need (ROI) ● Contract makes responding to change undesirable and expensive ● Fixed scope, fixed cost, fixed time (we know what happens to quality) ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 22. Fixed Price, Fixed Scope for Software We asked a 100 agile practitioners name reasons that fixed price, fixed scope contracts continue to be the most common form of contract for software procurement. ● Easy to understand, I will get X for £Y by date ● Prevailing belief that building software is like other construction industries. ● Easiest to align with traditional business planning and budgeting ● Constrained by policies of legal and procurement dept. ● Client believes definition of what is to be done, is what they need, and this can be made transferrable & understandable in contract ● Client feels that they are safely offloading responsibility and risk to supplier ● Client gets to beat down supplier on price, supplier gets to claw back in changes ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 23. IT Programmes 60% do not meet schedule, budget or quality goals. IBM 50% fail to achieve what they set out to achieve. KPMG 17% go so badly they can threaten the existence of the company. McKinsey & Company ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 24. The clash: Agile vs Contracts Evolutionary vs. Big Bang: One single contract for the expected lifetime of the project where delivery is only contractually enforceable at the end. Value vs. Scope: Contract typically specify a set of features without describing how they create value for the client. Initiative vs. Control: Business/product owner relationship is client/supplier and promote top-down management rather than collaboration. Satisfaction vs. Compliance: Supplier is incentivised to optimise for contractual compliance over customer satisfaction. Solutions vs. Retribution : Implicit design of solutions are legally bound into contract. Alternatives could be considered non-compliance and potentially punished. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 25. Agile contracts Attempt to align better around agile methods: ● Fixed price or time & materials as typical pricing model ● Iterative/incremental statements of work define shorter chucks of scope ● Provisions for scope of work to change or finish early ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 26. Agile contracts: some examples Optional Scope Contracts (Short fixed price iterations, with fixed “quality”, time but variable scope) Money For Nothing, Change For Free (scope/priorty can change each iteration, client get to cut project short if there is no further ROI) Fixed Price per Story Point ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 27. Agile contracts... Focus on what we’ve been good at doing: ● Iterative, incremental delivery of working software ● Responding to change Still a leap (albeit smaller) of faith for the client and failing to make explicit: ● Delivery of business value ● Means to measure progress in terms of business value ● Providing context for design performance requirements and constraints (e.g. usability, security, reliability) connected to business value. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 28. A brief history of Energized Work (part 2) 2009 - 2013 ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 29. Inspirations Customer Development /Lean Startup - Steve Blank/Eric Reis ● Clear goal: Discover and execute a viable product/business ● Puts the entire business in the PDCA cycle ● Forces us to confront business assumptions and risk ● Focuses on key business/product metrics (innovation accounting) ● Optimized for learning/discovery Book recommendation: Lean Analytics by Alistair Croll & Benjamin Yoskovitz ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 30. Inspirations Lean Product Development, Cost of Delay, CD3 - Don Reinertsen ● Economic re-evaluation of lean principles taken from manufacturing ● Insights into the effects of uncertainty, variability and risk. ● Powerful prioritisation tool, CD3, that optimises for value over time. ● value has to be quantified (avoid/reduce costs, increase/protect revenue) Book recommendation: The Principles of Product Development Flow by Don Reinertsen ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 31. Inspirations Tom Gilb – EVO ● Approach and method optimised for stakeholder outcomes/value ● Numeric, quantified outcomes ● Separation of requirements (ends) and designs (means) ● Powerful design engineering methods ● 12 Tough Questions ● No Cure, No Pay Book recommendation: Competitive Engineering by Tom Gilb ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 32. History of EW: Strategy Discovery Defining a strategy was the outcome required by the client. Strategy in the time horizon of 2-5 years could only be defined in terms of business outcomes. This time the supporters and dissenters roles were reversed: ● Brought clarity to the function of the business and could understand what they needed to do in terms of outcomes. ● Rejection by IT management who wanted a plan of what to do, as they feared leaving design of solutions in the hands of the masses. This raised a big question - how do we design/engineer, particularly at scale. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 33. History of EW: Legacy Replacement Discovery engagement to define strategy to replace legacy system. This time we applied EVO methods to: ● Define and quantify stakeholder goals ● Evaluate design options for discovery of information ● Evaluate best technical approach to replace the legacy system Providing frame for legacy replacement in terms of outcomes for the business. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 34. History of EW: Lean Startups Delivery an MVP of a mobile POS iPad app. We help define business and product goals to bring their product to market successfully. e.g. Number of sales, NPS score and merchants ability to complete biz functions (e.g. how well a merchant could complete a transaction with their customers) This allowed us to then quantify our contribution as their technology partner. We tied part of our payment to meeting those goals! ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 35. Outcome-based approach: Why ● Shared, defined understanding of what is valuable (and to who) that focuses the everyone on realising positive outcomes for the business ● Reduce the risk of subjective and emotive stakeholder judgment by providing a more factual basis for analysing progress. ● Allows us to measure progress in terms realising outcomes/biz value ● Good outcomes change far less than good feature specifications. ● More design freedom with feedback loop so we can learn what will produce the biggest impact. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 36. Outcome-based approach: Why not ● You can fail and you can't hide it (but everyone can learn from it) ● It’s hard (but very valuable) to reduce an engagement down to a set of outcomes that can be clearly understood by stakeholders. ● It can surface conflicts between stakeholders that result in paralysis and politicking. ● Some clients find more value in seeing people busy rather than delivering value - the "activity trap" ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 37. If outcomes are the deliverable… Then we should attempt to put them in the contract. Our Strategy: ● Every engagement must have engagement goals defined as outcomes for the client. ● Client outcomes will be part of our contractual agreements. And we are trying to go a step further: ● We will try sell risk and reward-based engagements and not just our time. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com
  • 38. An example of what’s in our contract Investor outcome: (external stakeholder management) Investors are satisfied with the Investment Service provided Goal: avg. Acceptable – 15thOct 2014 Goal: avg. Good – 15th Dec 2014 Goal: avg. Excellent – 15th Feb 2015 Process outcome: (capability) 1. Quantify Risk per Investment ● Goal: First Product Set – 15th Sept 2014 ● Goal: All Investments – 1st Jan 2015 ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com Product uptake outcome: Onboard Partners: 1 Partner by Q2 2014 2-4 by Q4 2014 5 - 20 by Q2 2015 Reduce Opex Hosting Costs: 50K/month - Q1 2013 10K/month - Q4 2013 Scale: <150 (<800 peak) requests/sec - Q2 2014 <300 (<1400 peak) requests/sec - Q4 2014 Reduce the Average Length of Stay: ● Medical ○ Complexity < 3: 1.6 days ● Surgical ○ Gastro: 2.2days ○ Neuro: 6 days Outcomes are a) a future state and b) measurable and independently verifiable by some means. They can vary wildly with context (product, usage, performance, efficiency, capability etc.)
  • 39. An idea worth spreading? We believe that we are reaching a critical mass as people reach similar conclusions. (Some people reached them many years ago!) Agile has been mainstream for some time and we see that many people are experiencing a disconnect between “building all the things” faster and the meaning in their work – i.e. how it creates value. We believe that having well defined outcomes are the foundation of success which promote trust and collaboration and freeing us all to creatively design better solutions to realise them. Outcomes can also be the bedrock of better commercial relationships. ENERGIZED WORK / HMS President Victoria Embankment London EC4Y 0HJ / www.energizedwork.com