- 1 -
CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC
30th
November 2016
RE-DESIGN GROUP 1 | Re-design of a timber frame facade system
Assignment
Re-design group 1 is asked to design several reuse applications on how the existing building
components and elements of the facade of Building Hs could be reused, based on the following
scenarios:
- Component reuse, direct reuse in different building
- Element reuse, reuse in different application
- Reuse after systems reconfiguration
The existing building components and elements are presented on the next page(s).
At the end of the workshop you are asked to present the reuse design scenarios in a pitch of
2-3 minutes to the other groups. To support the pitch, a photo will be made of the final reuse
design scenarios, which will be projected with the beamer on a large screen, see page 5.
1st
2nd
3rd
4th
5th
6th
-1st
Hs
- 2 -
CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC
30th
November 2016
Wooden facade frame (68x available), Rc 5,1
Wooden parts (retrieved from one facade frame)
Amount		 Length (mm)	 Section		 Material
2		5630		46x196		wood
7		3525		46x196		wood
4		1850		46x196		wood
4		1185		46x196		wood
4		724		46x196		wood
4		3525		46x59		wood
4		180		46x59		wood
4		1478		34x146		wood
2		1770		34x146		wood
2		1850		40x146		wood
5650180 180
6010
3617
Technical specification
Vertical section wooden facade frame
- 3 -
CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC
30th
November 2016
1782
1478
PVC window frames
Delivery date	 09-03-2004
Type	 	 insulation glass 6-15-4 mm 	
	 	 *HR++  U=1,2 W/m2
K	
		 ZTA = 39%
		 LTA = 70%
Color 		 inside 	 Ral 9010
		outside	Ral 7021
* complies with current building code in NL,
    minimum is average of 1,65 W/m2
K
Trespa panels
Amount (times 68)	Size		 label	
2		 1802 x 856	 A	
2		 1802 x 1285	 B	
1		 1184 x 856	 C	
1		 1184 x 1520	 D	
1		 1184 x 1285	 E
1		 1162 x 856	 F	
1		 1162 x 1520	 G	
1		 1162 x 1285	 H	
A
B
C
D
E
A
B
F
G
H
Technical specification
- 4 -
CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC
30th
November 2016
installations
Floor level
+ 2700
Technical specification
Main facade frame cluster
Step 13
Step 14
Step 12
Step 11
Step 10
Step 9
Step 8
Step 7
Step 6
Disassemblysequence
Step 5
Step 4
Step 3
Step 2
Step 1 E23
E23 cab
E22
E22 lowe
E21
E21 radia
E20 E20 insta
& data
E19
E19 inter
C18
C18 Sola
E17
E17 wallE16
E16 exte
E15
E15 wind
E14
E14 clad
C13
C13 wind
E12
E12 woo
E11 E11 Flash
M10
M10 anh
E9 facad
E9
C8
C8 small
C7
C7 main
C6
C6 adjacE5
E5 fire re
E4
E4 facad
M3
M3 in-situE2
E2 prefaE1
E1 steel s
Main facade frame cluster
Step 13
Step 14
Step 12
Step 11
Step 10
Step 9
Step 8
Step 7
Step 6
Disassemblysequence
Step 5
Step 4
Step 3
Step 2
Step 1 E23
E23 cable gutter
E22
E22 lowered ceiling
E21
E21 radiator
E20 E20 installations (air distribution, electa
& data distribution, water distribution)
E19
E19 interior partitioning
C18
C18 Solar shading
E17
E17 wall finishE16
E16 exterior facade cladding panels
E15
E15 windowsill
E14
E14 cladding around window frame
C13
C13 window frame
E12
E12 wooden cladding suspension bar
E11 E11 Flashing profile
M10
M10 anhydrite floor
E9 facade connection
E9
C8
C8 small facade frame
C7
C7 main facade frame
C6
C6 adjacent facade componentE5
E5 fire resistant material
E4
E4 facade connection device
M3
M3 in-situ concrete floorE2
E2 prefab concrete floorE1
E1 steel structure
Main facade frame cluster
E23
E23 cable gutter
E22
E22 lowered ceiling
E21
E21 radiator
E20 E20 installations (air distribution, electa
& data distribution, water distribution)
E19
E19 interior partitioning
C18
C18 Solar shading
E17
E17 wall finishE16
E16 exterior facade cladding panels
E15
E15 windowsill
E14
E14 cladding around window frame
C13
C13 window frame
E12
E12 wooden cladding suspension bar
E11 E11 Flashing profile
M10
M10 anhydrite floor
E9 facade connection
E9
C8
C8 small facade frame
C7
C7 main facade frame
C6
C6 adjacent facade componentE5
E5 fire resistant material
E4
E4 facade connection device
M3
M3 in-situ concrete floor
E2 prefab concrete floor
E1 steel structure
- 5 -
CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC
30th
November 2016
Component reuse, direct reuse in different building
Element reuse, reuse in different application
Reuse after systems reconfiguration

More Related Content

Similar to 20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Redesign group 1

Detail behind the proposal
Detail behind the proposalDetail behind the proposal
Detail behind the proposallauracarcano2
 
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdfHansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdfCanberra Institute of technology
 
Aerocon Panels: An Alternative Building Walling Solution for the Modern Age
Aerocon Panels: An Alternative Building Walling Solution for the Modern AgeAerocon Panels: An Alternative Building Walling Solution for the Modern Age
Aerocon Panels: An Alternative Building Walling Solution for the Modern AgeIRJET Journal
 
Progressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC StructuresProgressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC StructuresIRJET Journal
 
Study of Seismic Performance of RC Building with Flat Plate Influenced by Con...
Study of Seismic Performance of RC Building with Flat Plate Influenced by Con...Study of Seismic Performance of RC Building with Flat Plate Influenced by Con...
Study of Seismic Performance of RC Building with Flat Plate Influenced by Con...IRJET Journal
 
Building technology 1 Project 1 Drawing compilation
Building technology 1 Project 1 Drawing compilationBuilding technology 1 Project 1 Drawing compilation
Building technology 1 Project 1 Drawing compilationTan Jaden
 
Seismic Analysis of Multistorey Building with Different Slab Types on Plain a...
Seismic Analysis of Multistorey Building with Different Slab Types on Plain a...Seismic Analysis of Multistorey Building with Different Slab Types on Plain a...
Seismic Analysis of Multistorey Building with Different Slab Types on Plain a...IRJET Journal
 
A new facade concept for an existing office building
A new facade concept for an existing office buildingA new facade concept for an existing office building
A new facade concept for an existing office buildingMardi Rahardjo
 
Reinforced concrete Course assignments, 2019
Reinforced concrete Course assignments, 2019Reinforced concrete Course assignments, 2019
Reinforced concrete Course assignments, 2019JanneHanka
 
IRJET- Seismic Excitation using Lead Rubber Bearing in Low Rise to High Rise ...
IRJET- Seismic Excitation using Lead Rubber Bearing in Low Rise to High Rise ...IRJET- Seismic Excitation using Lead Rubber Bearing in Low Rise to High Rise ...
IRJET- Seismic Excitation using Lead Rubber Bearing in Low Rise to High Rise ...IRJET Journal
 
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad ProComputer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad ProIRJET Journal
 
Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...
Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...
Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...IRJET Journal
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2Gali Suresh
 

Similar to 20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Redesign group 1 (20)

20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Re-manufactu...
20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Re-manufactu...20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Re-manufactu...
20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Re-manufactu...
 
20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Re-finance g...
20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Re-finance g...20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Re-finance g...
20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Re-finance g...
 
Detail behind the proposal
Detail behind the proposalDetail behind the proposal
Detail behind the proposal
 
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdfHansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
 
Hansens Lodge Take-off.pdf
Hansens Lodge Take-off.pdfHansens Lodge Take-off.pdf
Hansens Lodge Take-off.pdf
 
Hansens Lodge for Plan and Organise
Hansens Lodge for Plan and OrganiseHansens Lodge for Plan and Organise
Hansens Lodge for Plan and Organise
 
Aerocon Panels: An Alternative Building Walling Solution for the Modern Age
Aerocon Panels: An Alternative Building Walling Solution for the Modern AgeAerocon Panels: An Alternative Building Walling Solution for the Modern Age
Aerocon Panels: An Alternative Building Walling Solution for the Modern Age
 
Progressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC StructuresProgressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC Structures
 
Study of Seismic Performance of RC Building with Flat Plate Influenced by Con...
Study of Seismic Performance of RC Building with Flat Plate Influenced by Con...Study of Seismic Performance of RC Building with Flat Plate Influenced by Con...
Study of Seismic Performance of RC Building with Flat Plate Influenced by Con...
 
Facade Research Document
Facade Research DocumentFacade Research Document
Facade Research Document
 
Building technology 1 Project 1 Drawing compilation
Building technology 1 Project 1 Drawing compilationBuilding technology 1 Project 1 Drawing compilation
Building technology 1 Project 1 Drawing compilation
 
3. Hansons lodge.pdf
3. Hansons lodge.pdf3. Hansons lodge.pdf
3. Hansons lodge.pdf
 
Seismic Analysis of Multistorey Building with Different Slab Types on Plain a...
Seismic Analysis of Multistorey Building with Different Slab Types on Plain a...Seismic Analysis of Multistorey Building with Different Slab Types on Plain a...
Seismic Analysis of Multistorey Building with Different Slab Types on Plain a...
 
A new facade concept for an existing office building
A new facade concept for an existing office buildingA new facade concept for an existing office building
A new facade concept for an existing office building
 
Reinforced concrete Course assignments, 2019
Reinforced concrete Course assignments, 2019Reinforced concrete Course assignments, 2019
Reinforced concrete Course assignments, 2019
 
IRJET- Seismic Excitation using Lead Rubber Bearing in Low Rise to High Rise ...
IRJET- Seismic Excitation using Lead Rubber Bearing in Low Rise to High Rise ...IRJET- Seismic Excitation using Lead Rubber Bearing in Low Rise to High Rise ...
IRJET- Seismic Excitation using Lead Rubber Bearing in Low Rise to High Rise ...
 
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad ProComputer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
 
Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...
Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...
Performance of RC Frame Structure with Floating Column and Soft Storey in Dif...
 
Analysis of industrial shed
Analysis of industrial shedAnalysis of industrial shed
Analysis of industrial shed
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 

More from Booosting platform voor koplopers in bouwinnovatie

More from Booosting platform voor koplopers in bouwinnovatie (20)

Interview Rutger Snoek Circulair Isolatieglas
Interview Rutger Snoek Circulair IsolatieglasInterview Rutger Snoek Circulair Isolatieglas
Interview Rutger Snoek Circulair Isolatieglas
 
200305 Booosting Goood Woood - Pieters Bouwtechniek Delft Rob Doomen
200305 Booosting Goood Woood - Pieters Bouwtechniek Delft Rob Doomen200305 Booosting Goood Woood - Pieters Bouwtechniek Delft Rob Doomen
200305 Booosting Goood Woood - Pieters Bouwtechniek Delft Rob Doomen
 
200305 Booosting Goood Woood - cepezedbouwteam Jan Houtekamer
200305 Booosting Goood Woood - cepezedbouwteam Jan Houtekamer200305 Booosting Goood Woood - cepezedbouwteam Jan Houtekamer
200305 Booosting Goood Woood - cepezedbouwteam Jan Houtekamer
 
200305 Booosting Goood Woood - MetsäWood Bas Meeuwissen
200305 Booosting Goood Woood - MetsäWood Bas Meeuwissen200305 Booosting Goood Woood - MetsäWood Bas Meeuwissen
200305 Booosting Goood Woood - MetsäWood Bas Meeuwissen
 
200305 Booosting Goood Woood - cepezedprojects Menno Rubbens
200305 Booosting Goood Woood - cepezedprojects Menno Rubbens200305 Booosting Goood Woood - cepezedprojects Menno Rubbens
200305 Booosting Goood Woood - cepezedprojects Menno Rubbens
 
20200305 Booosting Goood Woood - Mathew Vola Arup
20200305 Booosting Goood Woood - Mathew Vola Arup20200305 Booosting Goood Woood - Mathew Vola Arup
20200305 Booosting Goood Woood - Mathew Vola Arup
 
200207 Cobouw-artikel over het glazen Co-Creation Centre
200207 Cobouw-artikel over het glazen Co-Creation Centre 200207 Cobouw-artikel over het glazen Co-Creation Centre
200207 Cobouw-artikel over het glazen Co-Creation Centre
 
200130 Second life - Thijs Asselbergs TUD - Gevel2020
200130 Second life - Thijs Asselbergs TUD - Gevel2020200130 Second life - Thijs Asselbergs TUD - Gevel2020
200130 Second life - Thijs Asselbergs TUD - Gevel2020
 
200211 Booosting @Co-Creation Centre - Tegenlezing
200211 Booosting @Co-Creation Centre - Tegenlezing200211 Booosting @Co-Creation Centre - Tegenlezing
200211 Booosting @Co-Creation Centre - Tegenlezing
 
200211 Booosting @Co-Creation Centre - Dow Silicones
200211 Booosting @Co-Creation Centre - Dow Silicones200211 Booosting @Co-Creation Centre - Dow Silicones
200211 Booosting @Co-Creation Centre - Dow Silicones
 
200211 Booosting @Co-Creation Centre - ABT
200211 Booosting @Co-Creation Centre - ABT200211 Booosting @Co-Creation Centre - ABT
200211 Booosting @Co-Creation Centre - ABT
 
200211 Booosting @Co-Creation Centre - Si-X
200211 Booosting @Co-Creation Centre - Si-X200211 Booosting @Co-Creation Centre - Si-X
200211 Booosting @Co-Creation Centre - Si-X
 
200211 Booosting @Co-Creation Centre - Mecanoo
200211 Booosting @Co-Creation Centre - Mecanoo200211 Booosting @Co-Creation Centre - Mecanoo
200211 Booosting @Co-Creation Centre - Mecanoo
 
200211 Booosting @Co-Creation Centre - Welkomstwoord van The Green Village
200211 Booosting @Co-Creation Centre - Welkomstwoord van The Green Village200211 Booosting @Co-Creation Centre - Welkomstwoord van The Green Village
200211 Booosting @Co-Creation Centre - Welkomstwoord van The Green Village
 
200211 Booosting @Co-Creation Centre - Introductie
200211 Booosting @Co-Creation Centre - Introductie200211 Booosting @Co-Creation Centre - Introductie
200211 Booosting @Co-Creation Centre - Introductie
 
200116 Bouwtex eindevent - Clemens Bernardt Hanze HS
200116 Bouwtex eindevent - Clemens Bernardt Hanze HS200116 Bouwtex eindevent - Clemens Bernardt Hanze HS
200116 Bouwtex eindevent - Clemens Bernardt Hanze HS
 
200115 Bouwtex Eindpresentatie - Aldus Bouwinnovatie Texflex
200115 Bouwtex Eindpresentatie - Aldus Bouwinnovatie Texflex 200115 Bouwtex Eindpresentatie - Aldus Bouwinnovatie Texflex
200115 Bouwtex Eindpresentatie - Aldus Bouwinnovatie Texflex
 
200115 Bouwtex Eindevent - Christian Struck
200115 Bouwtex Eindevent - Christian Struck200115 Bouwtex Eindevent - Christian Struck
200115 Bouwtex Eindevent - Christian Struck
 
200115 Bouwtex Eindpresentatie - Internal roomdivider
200115 Bouwtex Eindpresentatie - Internal roomdivider200115 Bouwtex Eindpresentatie - Internal roomdivider
200115 Bouwtex Eindpresentatie - Internal roomdivider
 
200115 Bouwtex Eindevent - Flexitex presentatie
200115 Bouwtex Eindevent - Flexitex presentatie200115 Bouwtex Eindevent - Flexitex presentatie
200115 Bouwtex Eindevent - Flexitex presentatie
 

Recently uploaded

Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 

Recently uploaded (20)

Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 

20161130 - Booosting Circular Demolition @Erasmus MC Rotterdam - Redesign group 1

  • 1. - 1 - CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC 30th November 2016 RE-DESIGN GROUP 1 | Re-design of a timber frame facade system Assignment Re-design group 1 is asked to design several reuse applications on how the existing building components and elements of the facade of Building Hs could be reused, based on the following scenarios: - Component reuse, direct reuse in different building - Element reuse, reuse in different application - Reuse after systems reconfiguration The existing building components and elements are presented on the next page(s). At the end of the workshop you are asked to present the reuse design scenarios in a pitch of 2-3 minutes to the other groups. To support the pitch, a photo will be made of the final reuse design scenarios, which will be projected with the beamer on a large screen, see page 5. 1st 2nd 3rd 4th 5th 6th -1st Hs
  • 2. - 2 - CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC 30th November 2016 Wooden facade frame (68x available), Rc 5,1 Wooden parts (retrieved from one facade frame) Amount Length (mm) Section Material 2 5630 46x196 wood 7 3525 46x196 wood 4 1850 46x196 wood 4 1185 46x196 wood 4 724 46x196 wood 4 3525 46x59 wood 4 180 46x59 wood 4 1478 34x146 wood 2 1770 34x146 wood 2 1850 40x146 wood 5650180 180 6010 3617 Technical specification Vertical section wooden facade frame
  • 3. - 3 - CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC 30th November 2016 1782 1478 PVC window frames Delivery date 09-03-2004 Type insulation glass 6-15-4 mm *HR++ U=1,2 W/m2 K ZTA = 39% LTA = 70% Color inside Ral 9010 outside Ral 7021 * complies with current building code in NL, minimum is average of 1,65 W/m2 K Trespa panels Amount (times 68) Size label 2 1802 x 856 A 2 1802 x 1285 B 1 1184 x 856 C 1 1184 x 1520 D 1 1184 x 1285 E 1 1162 x 856 F 1 1162 x 1520 G 1 1162 x 1285 H A B C D E A B F G H Technical specification
  • 4. - 4 - CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC 30th November 2016 installations Floor level + 2700 Technical specification Main facade frame cluster Step 13 Step 14 Step 12 Step 11 Step 10 Step 9 Step 8 Step 7 Step 6 Disassemblysequence Step 5 Step 4 Step 3 Step 2 Step 1 E23 E23 cab E22 E22 lowe E21 E21 radia E20 E20 insta & data E19 E19 inter C18 C18 Sola E17 E17 wallE16 E16 exte E15 E15 wind E14 E14 clad C13 C13 wind E12 E12 woo E11 E11 Flash M10 M10 anh E9 facad E9 C8 C8 small C7 C7 main C6 C6 adjacE5 E5 fire re E4 E4 facad M3 M3 in-situE2 E2 prefaE1 E1 steel s Main facade frame cluster Step 13 Step 14 Step 12 Step 11 Step 10 Step 9 Step 8 Step 7 Step 6 Disassemblysequence Step 5 Step 4 Step 3 Step 2 Step 1 E23 E23 cable gutter E22 E22 lowered ceiling E21 E21 radiator E20 E20 installations (air distribution, electa & data distribution, water distribution) E19 E19 interior partitioning C18 C18 Solar shading E17 E17 wall finishE16 E16 exterior facade cladding panels E15 E15 windowsill E14 E14 cladding around window frame C13 C13 window frame E12 E12 wooden cladding suspension bar E11 E11 Flashing profile M10 M10 anhydrite floor E9 facade connection E9 C8 C8 small facade frame C7 C7 main facade frame C6 C6 adjacent facade componentE5 E5 fire resistant material E4 E4 facade connection device M3 M3 in-situ concrete floorE2 E2 prefab concrete floorE1 E1 steel structure Main facade frame cluster E23 E23 cable gutter E22 E22 lowered ceiling E21 E21 radiator E20 E20 installations (air distribution, electa & data distribution, water distribution) E19 E19 interior partitioning C18 C18 Solar shading E17 E17 wall finishE16 E16 exterior facade cladding panels E15 E15 windowsill E14 E14 cladding around window frame C13 C13 window frame E12 E12 wooden cladding suspension bar E11 E11 Flashing profile M10 M10 anhydrite floor E9 facade connection E9 C8 C8 small facade frame C7 C7 main facade frame C6 C6 adjacent facade componentE5 E5 fire resistant material E4 E4 facade connection device M3 M3 in-situ concrete floor E2 prefab concrete floor E1 steel structure
  • 5. - 5 - CIRCULAR DEMOLITION OF THE HOSPITAL BUILDINGS ERASMUS MC 30th November 2016 Component reuse, direct reuse in different building Element reuse, reuse in different application Reuse after systems reconfiguration