SlideShare a Scribd company logo
1 of 22
Download to read offline
EE-471 HIGH VOLTAGE ENGINEERING
Voltage Testing & Partial Discharge
Measurement For Power Cable Accessories
PRESENTED BY : SYED ATIF CHISHTI
SUBMITEDTO : PROF DOC :BULENT BILIR
1
PRESENTATION SEQUENCE
2
 OBECTIVE
 INTRODUCTION
 ACTESTAFTER INSTALLATION
 ACRF TEST SYSTEM
 SCHEMATIC DIAGRAM OFTEST SYSTEM
 PARALLEL OPERATION MODE OFTEST SYSTEM
 PARTIAL DISCHARGE METHODS & PRINCIPLE.
 DISCUSSION & CONCLUSION.
OBJECTIVE :
 To compare best practices for cable testing.
 Predictive diagnostic programs to aging cable.
 To determine the faulty joints cable defects
INTRODUCTION
 Using Frequency tuned resonance
Test system (20-300 Hz) to calculate
PD measurement.
 PD measurement method are
necessary to trace defect and
insulation of cable.
 Voltage testing provide information
about defect in the insulation is
dangerous or not for later operation.
 Calibration is done through PD
calibrator on the cable termination.
3
 Power Cables importance in
Transmission & Distribution
system
 Consist of :
 Cable
 Joint
 Termination
 Identification & Localization of
partial discharge.
AC TEST AFTER INSTALLATION
4
 Follow the international standards IEC 60840 and IEC
62067 for testing of Power cable insulation and their
accessories.
 Apply : sinusoidal waveform, frequency: 20 and 300 Hz,
voltage applied for 1.7 U0 /1 hour
Methods of Voltage Generated
5
 By a reactor with variable inductance and fixed excitation
frequency 50 or 60 Hz (ACRL) test system.
 By a reactor with fixed inductance and frequency tuned
voltage excitation (ACRF) test systems.
ACRF TEST SYSTEM
6
 HV Reactor
 ExciterTransformer
 Control Unit
 Feeding Unit
 Blocking Impedance
 Voltage Divider & Software
 Frequency Convertor + Protection Impedance.
7
SCHEMATIC DIAGRAM OF TEST
SYSTEM
PARALLEL OPERATION MODE OF TEST
SYSTEM
8
OPERATING RANGE OF THE RESONANT TEST
SYSTEM (ACRF)
9
PARTIAL DISCHARGE
 Partial discharges are a sensitive measure of local electrical
stress and the measurement is often used as a quality check of
the insulation.
Cable has small voids, cavities, insulating contaminant
conductive protrusions in different interfaces or mechanical cuts.
 Erosion by ion bombardment and chemical effects gradually
change small defects to electrical trees with consequent final
breakdown.
10
METHODS OF PD MEASUREMENTS
11
 HIGH FREQUENCY CURRENTTRANSFORMER
HFCT method at cross bonding box for 220 kV or earth wire of 66 kV for XLPE cable
systems Showed high sensitivity and calibration is possible using PD calibrator on the
cable terminations.
 COUPLING CAPACITOR
PD detection of high frequency signal generated from PD activities. Measurement by use of
a coupling capacitor is physically limited to a maximum detectable cable length of
approximately 2 km, depending on cable parameters and PD background noise.
WORKING PRINCIPLE
12
 The sensitivity of the partial discharge detector has to be modified until the
detector shows the calibration charge.
 For 220 kV, PD measurements carried out during HV tests, using a test
sequence providing several increase the voltage in steps of 127 Kv (U0) and take
a PD-measurement recording during 1 minute and afterwards increase the voltage in
further steps until 216 kV
 At each step note the measured PD value.
 Once reaching 216 kV leave this voltage applied for 1 hour and observes if
there is a change in the recorded PD pattern and value.
 While ramp the test voltage down, take another PD measurement for 1 minute
at 127 kV.
Time characteristic of the 216 kV
Voltage test
13
PARTIAL DISCHARGE
MEASUREMENT
14
 Internal sensors integrated in each accessory or external
sensors HFCT placed inside bonding link boxes.
 The PD sensitivity using HFCT the central measuring
frequency is recommended is to lie between 2 MHz and 10
MHz in a flat zone of the frequency spectrum.
CROSS BONDING LINKS WITH MOUNTED THREE
HFCT SENSORS FOR PD
15
16
 Test carried out on two cables having specification
1x3x1600 mm2,CU /XLPE/LEAD/HDPE ,220 kV with approximately 13 km long,19
joints/phase, 3 straight joint box and 16 insulated joint box which are divided into two
sections by means of joints and it is terminated by composite three outdoor and three
GIS sealing ends per circuit.
 The result was a resonant frequency of 35.53 Hz for test voltage 216 kV.
 Inject a calibration pulse with known quantity of charge at the outdoor system
termination (i.e., between HV and ground terminals), the sensitivity of the PD detector
has to be modified until the detector shows the calibration charge.
 PD pulses occur in very short time, the width and rise time of the pulses are in the
nanosecond region. Consequently, PD pulses with energy frequency up to hundred
MHZ are generated these PD pulses will travel through the cable earth conductor and
finally can be recorded by the sensors
TEST RESULT & DISCUSSION
PARTIAL DISCHARGE RESULTS FOR
CIRCUIT 1 & 2
17
variation OF PC pattern during
PD measurement
PD measurement OF pattern
with some noise
18
19
EXAMPLE OF JOINT FAILURE DURING
WITH STAND TEST BY USING RESONANT TEST
SYSTEM
CONCLUSION
20
 After installation of cable , test for HV/EHV XLPE cables system
by using resonant test system of (20 Hz -300 Hz) combined with
PD detection is performed by using HFCT sensors at each cross
bonding (CB) link boxes reduces the risk from the service.
 After detecting the location of fault and repair the cables and
their accessories was done exactly in the same place given good
results.
 The experiences also show that the test voltage with U0 for 24 h
is not feasible for incidence of failure after the test could be
occurred.
21
22

More Related Content

What's hot

High voltage cable insulation systems
High voltage cable insulation systemsHigh voltage cable insulation systems
High voltage cable insulation systems
Sanket Tambakhe
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
Dinesh Sarda
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testing
michaeljmack
 

What's hot (20)

Earthing test report for dg
Earthing test report for dgEarthing test report for dg
Earthing test report for dg
 
Partial discharge testing
Partial discharge testingPartial discharge testing
Partial discharge testing
 
Principles of Cable Selection
Principles of Cable SelectionPrinciples of Cable Selection
Principles of Cable Selection
 
High voltage cable insulation systems
High voltage cable insulation systemsHigh voltage cable insulation systems
High voltage cable insulation systems
 
Chapter 09 - Measurement of Partial Discharge
Chapter 09 - Measurement of Partial DischargeChapter 09 - Measurement of Partial Discharge
Chapter 09 - Measurement of Partial Discharge
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
Installation & maintenance of power cable
Installation & maintenance of power cableInstallation & maintenance of power cable
Installation & maintenance of power cable
 
Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 
Corona Effect
Corona EffectCorona Effect
Corona Effect
 
Basics of electrical control panel
Basics of electrical control panelBasics of electrical control panel
Basics of electrical control panel
 
Insulation Resistance Test
Insulation Resistance TestInsulation Resistance Test
Insulation Resistance Test
 
Frank Conte Arc flash program
Frank Conte Arc flash programFrank Conte Arc flash program
Frank Conte Arc flash program
 
testing formats
testing formatstesting formats
testing formats
 
Tests on insulators
Tests on insulatorsTests on insulators
Tests on insulators
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniques
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testing
 
Descarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia VirtualDescarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia Virtual
 
Underground Cables
Underground Cables Underground Cables
Underground Cables
 

Similar to Insulation testing of power cable

P D Measurements On H V Joints
P D  Measurements On  H V JointsP D  Measurements On  H V Joints
P D Measurements On H V Joints
Aol_Amil
 
H2PToday1201_design_IR
H2PToday1201_design_IRH2PToday1201_design_IR
H2PToday1201_design_IR
Parviz Parto
 

Similar to Insulation testing of power cable (20)

IRJET- Underground Cable Fault Distance Locator
IRJET- Underground Cable Fault Distance LocatorIRJET- Underground Cable Fault Distance Locator
IRJET- Underground Cable Fault Distance Locator
 
B1102030610
B1102030610B1102030610
B1102030610
 
P D Measurements On H V Joints
P D  Measurements On  H V JointsP D  Measurements On  H V Joints
P D Measurements On H V Joints
 
under grund fault ppt (1).pptx
under grund fault ppt (1).pptxunder grund fault ppt (1).pptx
under grund fault ppt (1).pptx
 
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATORUNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
 
report-paper-bheesette
report-paper-bheesettereport-paper-bheesette
report-paper-bheesette
 
A Frequency-based RF Partial Discharge Detector for Low-power Wireless Sens...
A Frequency-based  RF Partial Discharge Detector  for Low-power Wireless Sens...A Frequency-based  RF Partial Discharge Detector  for Low-power Wireless Sens...
A Frequency-based RF Partial Discharge Detector for Low-power Wireless Sens...
 
1960 09
1960 091960 09
1960 09
 
H2PToday1201_design_IR
H2PToday1201_design_IRH2PToday1201_design_IR
H2PToday1201_design_IR
 
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCEEXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
 
Grid synchronisation
Grid synchronisationGrid synchronisation
Grid synchronisation
 
A 60 GHz CMOS Power Amplifier for Wireless Communications
A 60 GHz CMOS Power Amplifier for Wireless CommunicationsA 60 GHz CMOS Power Amplifier for Wireless Communications
A 60 GHz CMOS Power Amplifier for Wireless Communications
 
Cyclic voltammetry readout circuitry for DNA biosensor application
Cyclic voltammetry readout circuitry for DNA biosensor applicationCyclic voltammetry readout circuitry for DNA biosensor application
Cyclic voltammetry readout circuitry for DNA biosensor application
 
Bender rc48 c
Bender rc48 cBender rc48 c
Bender rc48 c
 
Senior Project Students' Presentation on ECG Monitoring
Senior Project Students' Presentation on ECG MonitoringSenior Project Students' Presentation on ECG Monitoring
Senior Project Students' Presentation on ECG Monitoring
 
Paper 2
Paper 2Paper 2
Paper 2
 
Electrical testing
Electrical testingElectrical testing
Electrical testing
 
RBEFC Magnetic Flow Converter/Transmitter Catalog 2016
RBEFC Magnetic Flow Converter/Transmitter Catalog 2016RBEFC Magnetic Flow Converter/Transmitter Catalog 2016
RBEFC Magnetic Flow Converter/Transmitter Catalog 2016
 
Design of Ota-C Filter for Biomedical Applications
Design of Ota-C Filter for Biomedical ApplicationsDesign of Ota-C Filter for Biomedical Applications
Design of Ota-C Filter for Biomedical Applications
 
Simulation and Partial Discharge Measurement in 400kv Typical GIS Substation
Simulation and Partial Discharge Measurement in 400kv Typical GIS SubstationSimulation and Partial Discharge Measurement in 400kv Typical GIS Substation
Simulation and Partial Discharge Measurement in 400kv Typical GIS Substation
 

More from Syed Atif Naseem

Deblurring of Digital Image PPT
Deblurring of Digital Image PPTDeblurring of Digital Image PPT
Deblurring of Digital Image PPT
Syed Atif Naseem
 

More from Syed Atif Naseem (20)

Electrical Safety Audit
Electrical Safety AuditElectrical Safety Audit
Electrical Safety Audit
 
Asset Integrity _ Asset Managment ISO 55001 Certification
Asset Integrity _ Asset Managment ISO 55001 CertificationAsset Integrity _ Asset Managment ISO 55001 Certification
Asset Integrity _ Asset Managment ISO 55001 Certification
 
EMS ISO 50001
EMS ISO 50001 EMS ISO 50001
EMS ISO 50001
 
Electrical & Energy Audit 22 Nov.pptx
Electrical & Energy Audit 22 Nov.pptxElectrical & Energy Audit 22 Nov.pptx
Electrical & Energy Audit 22 Nov.pptx
 
Electrical & Energy Audit (2).pptx
Electrical & Energy Audit (2).pptxElectrical & Energy Audit (2).pptx
Electrical & Energy Audit (2).pptx
 
Electrical FM Compiled.pdf
Electrical  FM Compiled.pdfElectrical  FM Compiled.pdf
Electrical FM Compiled.pdf
 
Energy Audit..pptx
Energy Audit..pptxEnergy Audit..pptx
Energy Audit..pptx
 
Electrical Safety Audit - FM Pvt ltd.pptx
Electrical Safety Audit - FM Pvt ltd.pptxElectrical Safety Audit - FM Pvt ltd.pptx
Electrical Safety Audit - FM Pvt ltd.pptx
 
Electrical Audit (Bill's Inc ).pptx
Electrical Audit (Bill's Inc ).pptxElectrical Audit (Bill's Inc ).pptx
Electrical Audit (Bill's Inc ).pptx
 
Neural Network to identify fault in distribution network of smart grid
Neural Network to identify fault in distribution network of smart gridNeural Network to identify fault in distribution network of smart grid
Neural Network to identify fault in distribution network of smart grid
 
ELECTRIC VEHICLE
ELECTRIC VEHICLEELECTRIC VEHICLE
ELECTRIC VEHICLE
 
Energy storage Technologies
Energy storage TechnologiesEnergy storage Technologies
Energy storage Technologies
 
Asset management
Asset managementAsset management
Asset management
 
Probability Estimation for the Fault Detection and Isolation of PMU-Based Tra...
Probability Estimation for the Fault Detection and Isolation of PMU-Based Tra...Probability Estimation for the Fault Detection and Isolation of PMU-Based Tra...
Probability Estimation for the Fault Detection and Isolation of PMU-Based Tra...
 
Formal verification of FDIR
Formal verification of FDIRFormal verification of FDIR
Formal verification of FDIR
 
Reduction in Current leakage in CMOS VLSI Circuits
Reduction in Current leakage in CMOS VLSI CircuitsReduction in Current leakage in CMOS VLSI Circuits
Reduction in Current leakage in CMOS VLSI Circuits
 
SMART GRID
SMART GRIDSMART GRID
SMART GRID
 
Monitoring System
Monitoring SystemMonitoring System
Monitoring System
 
SAUDI FRENCH
SAUDI FRENCHSAUDI FRENCH
SAUDI FRENCH
 
Deblurring of Digital Image PPT
Deblurring of Digital Image PPTDeblurring of Digital Image PPT
Deblurring of Digital Image PPT
 

Insulation testing of power cable

  • 1. EE-471 HIGH VOLTAGE ENGINEERING Voltage Testing & Partial Discharge Measurement For Power Cable Accessories PRESENTED BY : SYED ATIF CHISHTI SUBMITEDTO : PROF DOC :BULENT BILIR 1
  • 2. PRESENTATION SEQUENCE 2  OBECTIVE  INTRODUCTION  ACTESTAFTER INSTALLATION  ACRF TEST SYSTEM  SCHEMATIC DIAGRAM OFTEST SYSTEM  PARALLEL OPERATION MODE OFTEST SYSTEM  PARTIAL DISCHARGE METHODS & PRINCIPLE.  DISCUSSION & CONCLUSION. OBJECTIVE :  To compare best practices for cable testing.  Predictive diagnostic programs to aging cable.  To determine the faulty joints cable defects
  • 3. INTRODUCTION  Using Frequency tuned resonance Test system (20-300 Hz) to calculate PD measurement.  PD measurement method are necessary to trace defect and insulation of cable.  Voltage testing provide information about defect in the insulation is dangerous or not for later operation.  Calibration is done through PD calibrator on the cable termination. 3  Power Cables importance in Transmission & Distribution system  Consist of :  Cable  Joint  Termination  Identification & Localization of partial discharge.
  • 4. AC TEST AFTER INSTALLATION 4  Follow the international standards IEC 60840 and IEC 62067 for testing of Power cable insulation and their accessories.  Apply : sinusoidal waveform, frequency: 20 and 300 Hz, voltage applied for 1.7 U0 /1 hour
  • 5. Methods of Voltage Generated 5  By a reactor with variable inductance and fixed excitation frequency 50 or 60 Hz (ACRL) test system.  By a reactor with fixed inductance and frequency tuned voltage excitation (ACRF) test systems.
  • 6. ACRF TEST SYSTEM 6  HV Reactor  ExciterTransformer  Control Unit  Feeding Unit  Blocking Impedance  Voltage Divider & Software  Frequency Convertor + Protection Impedance.
  • 8. PARALLEL OPERATION MODE OF TEST SYSTEM 8
  • 9. OPERATING RANGE OF THE RESONANT TEST SYSTEM (ACRF) 9
  • 10. PARTIAL DISCHARGE  Partial discharges are a sensitive measure of local electrical stress and the measurement is often used as a quality check of the insulation. Cable has small voids, cavities, insulating contaminant conductive protrusions in different interfaces or mechanical cuts.  Erosion by ion bombardment and chemical effects gradually change small defects to electrical trees with consequent final breakdown. 10
  • 11. METHODS OF PD MEASUREMENTS 11  HIGH FREQUENCY CURRENTTRANSFORMER HFCT method at cross bonding box for 220 kV or earth wire of 66 kV for XLPE cable systems Showed high sensitivity and calibration is possible using PD calibrator on the cable terminations.  COUPLING CAPACITOR PD detection of high frequency signal generated from PD activities. Measurement by use of a coupling capacitor is physically limited to a maximum detectable cable length of approximately 2 km, depending on cable parameters and PD background noise.
  • 12. WORKING PRINCIPLE 12  The sensitivity of the partial discharge detector has to be modified until the detector shows the calibration charge.  For 220 kV, PD measurements carried out during HV tests, using a test sequence providing several increase the voltage in steps of 127 Kv (U0) and take a PD-measurement recording during 1 minute and afterwards increase the voltage in further steps until 216 kV  At each step note the measured PD value.  Once reaching 216 kV leave this voltage applied for 1 hour and observes if there is a change in the recorded PD pattern and value.  While ramp the test voltage down, take another PD measurement for 1 minute at 127 kV.
  • 13. Time characteristic of the 216 kV Voltage test 13
  • 14. PARTIAL DISCHARGE MEASUREMENT 14  Internal sensors integrated in each accessory or external sensors HFCT placed inside bonding link boxes.  The PD sensitivity using HFCT the central measuring frequency is recommended is to lie between 2 MHz and 10 MHz in a flat zone of the frequency spectrum.
  • 15. CROSS BONDING LINKS WITH MOUNTED THREE HFCT SENSORS FOR PD 15
  • 16. 16  Test carried out on two cables having specification 1x3x1600 mm2,CU /XLPE/LEAD/HDPE ,220 kV with approximately 13 km long,19 joints/phase, 3 straight joint box and 16 insulated joint box which are divided into two sections by means of joints and it is terminated by composite three outdoor and three GIS sealing ends per circuit.  The result was a resonant frequency of 35.53 Hz for test voltage 216 kV.  Inject a calibration pulse with known quantity of charge at the outdoor system termination (i.e., between HV and ground terminals), the sensitivity of the PD detector has to be modified until the detector shows the calibration charge.  PD pulses occur in very short time, the width and rise time of the pulses are in the nanosecond region. Consequently, PD pulses with energy frequency up to hundred MHZ are generated these PD pulses will travel through the cable earth conductor and finally can be recorded by the sensors TEST RESULT & DISCUSSION
  • 17. PARTIAL DISCHARGE RESULTS FOR CIRCUIT 1 & 2 17
  • 18. variation OF PC pattern during PD measurement PD measurement OF pattern with some noise 18
  • 19. 19 EXAMPLE OF JOINT FAILURE DURING WITH STAND TEST BY USING RESONANT TEST SYSTEM
  • 20. CONCLUSION 20  After installation of cable , test for HV/EHV XLPE cables system by using resonant test system of (20 Hz -300 Hz) combined with PD detection is performed by using HFCT sensors at each cross bonding (CB) link boxes reduces the risk from the service.  After detecting the location of fault and repair the cables and their accessories was done exactly in the same place given good results.  The experiences also show that the test voltage with U0 for 24 h is not feasible for incidence of failure after the test could be occurred.
  • 21. 21
  • 22. 22