Looming Mandates. Energy insecurity. Shrinking budgets. Discover solutions available today to help you tackle your energy dilemma. Take a 30K foot tour of solutions to increase energy efficiency and reliability, maximize energy ROI and enhance mission assurance. Get tips for navigating the event to make the most of your Xperience.
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Energy solutions for federal facilities : How to harness sustainable savings and increased resiliency
1. Schneider Electric 1
Energy Solutions for Federal Facilities
How to Harness Sustainable Savings and Increased Resiliency
Jeff Sherman
Director, Federal Professional Services
Jay Owen
VP, IT Federal Solutions
Jim Plourde
Program Manager, Government Solutions
Tweet Live!
#SchneiderXE
2. Schneider Electric 2
Agenda
●The Federal energy dilemma and what it means
to you.
●Utilizing the Energy Management Lifecycle to
improve energy surety in your Agency
●Maximize your Xperience
3. Schneider Electric 3
Increase energy security and operational resiliency
Meet energy and operational goals in a budget constrained environment
Execute a Data Center consolidation initiative that is largely unfunded
a new organization
21st Century threats to
people, property & data
Aging facilities
infrastructure
Budget deficit & national
debt
Traditional energy
approach is volatile
Climate
change
Digitization core to
mission
Six-mega trends shaping Federal energy
dilemma
4. 4
How will you deal with this dilemma?
Scale back your
mission?
Fail to comply?
Do more while using less
energy?
7. Schneider Electric 7
The FDCCI Challenge
Eliminate 800
data centers by
2015
Reduce
Cost
Manage
Risk
Overcome
capital
constraints
Increase
productivity
• Optimize utilization
• Improve energy efficiency
• Eliminate redundant resources
• Ability to deliver new service
more swiftly, at reduced
capital cost
• Ensure required availability
• More efficient protection system
• Meet FDCCI goals in declining
budget environment
8. Schneider Electric 8
Consolidation options
●Traditional:
●Move IT to the cloud
●Move IT to Co-Location
●Build new larger data centers and consolidate into
them
●New Concept: Upgrade selected existing data
centers and consolidate into them
Why:
• Much lower capital investment
• No new real estate acquisition
• Can be phased to match IT refreshes
• Can be done while receiving data center is live
9. High density pods for existing Data Centers
● High Density / High Efficiency Zone
● Can be net-neutral to other facility
infrastructure (cooling, UPS, etc.)
● Increase PUE of entire facility
● Redundancy tailored to application
● Pods can be added quickly
175
White
paper
10. The High-Density Pod Overlay Method
●Method for upgrading existing data centers, best when. . .
• Consolidating 2-5 data centers into one
• Some existing IT moving to cloud or co-location
• Consolidations operated within independent departments
●Self contained “Pods” of data center infrastructure are placed in existing data
center space
● Pod size typically 10-20 cabinets
● Typically includes integrated air conditioning and power distribution
● Optionally contains integrated UPS
●Pods operate with superior performance
● Much higher energy efficiency (typical PUE less than 1.4)
● Much higher power density (up to 20 KW per cabinet)
●Pod does not need to rely on existing infrastructure
● Does not require raised floor
● Does not require air supply
12. Schneider Electric 12
Leverage private sector financing to meet
your goals
●Move ahead immediately without waiting for appropriations
●Pay for project through guaranteed savings
●Leverage support from DOE/FEMP
●Implement a broad range of ECMs in one project
●Savings are measured and verified
13. What is an ESPC?
Before After
Guaranteed
Payment
Operations
Energy Bill
Cost
Operations
Energy Bill
Cost
13
Energy savings
performance contracts
(ESPCs) allow Federal
agencies to conduct
energy projects with no
upfront capital
costs, minimizing the
need for Congressional
appropriations.
An ESPC is a
partnership between a
Federal agency and an
energy service company
(ESCO).
15. Schneider Electric 15
We’ll help you choose the best option
●DOE ESPC IDIQ
●ESPC ENABLE (FEMP assistance, GSA Schedule 84)
●Utility Energy Services Contract (UESC) – working with
local utility
Resources & Training: (click links in slideshow mode)
FEMP Project Funding:
http://www1.eere.energy.gov/femp/financing/mechanisms.html
ESPC for Data Centers WP
ESPC for Data Centers Blog
ESPC ENABLE Blog
FEMP Training: http://apps1.eere.energy.gov/femp/training/