SlideShare a Scribd company logo
1 of 11
Pascagoula Gas Plant Incident
Sanjeev Saraf
CSB report: https://www.csb.gov/assets/1/6/final_case_study_-_enterprise.pdf
Facility
• Pascagoula gas plant
• Gas plant receives condensate from Destin pipeline in deepwater GoM
• Gas (C1-C4) separation from NGL using cryogenic process
• Brazed aluminum heat exchanger (BAHX), which allows for the transfer of heat between
different process
• Susceptible to thermal fatigue. Weakening of braze joints between fins and parting sheets
Design PHA
• 1997 (design-stage): team did not expect the hazard to have a public impact and
anticipated only minor damage and downtime. Team assumed the likelihood of
thermal shock to be once every 50 years and labeled it as a “medium priority,” for
which the company recommended that “serious and appropriate actions should be
taken.” In response, the PHA team recommended developing procedures for the
BAHXs’ various operating modes (e.g. start-up, shutdown) to minimize the
likelihood of thermal shock events.
PHA Revalidation
2009: “high impact health/safety incident” with the potential to cause (1)
“permanent partial disability(ies),” (2) “several non-permanent injuries or health
impacts,” and (3) “days away from work.” As a consequence, the PHA team
recommended evaluating the replacement of the BAHXs with a different
exchanger design.
PHA Revalidation and follow up
2013: The 2013 PHA revalidation no longer identified health and safety consequences associated with the
exchangers. Instead, the listed potential consequences mirrored the plant’s experiences with leaks. Exchanger
repairs in the range of $60-150-k. The safeguards for minimizing BAHX damage identified in the PHA were
metal temperature sensors, operator intervention, and operating procedures.
2015: A plan to change them out within 3 years to “ensure equipment integrity.” Justification for the plan stated
that “cyclical operation causes small cracks on heat exchangers. Rapid cooling or heating of the brazed
aluminum heat exchangers has the potential to create small cracks around support pads. Small cracks result in
weeps of gas out. Potential for personnel injury is minor. Cost associated with repairs and downtime. Repair
costs vary from $80 thousand onsite to $100 thousand offsite”
BAHX failures – 9 failures in 11-years (18-operating years)
Incidents
• Incident occurred on 27 June 2016
• Operators initiating controlled shutdown
• Fire and explosion reported at 11:22 pm
• BAHX failure from thermal fatigue
• 13 different ruptures of piping and equipment during the course of the
incident
• Community evacuation
• $10.4 million of expense due to fire response activities; $7.1 million non-
cash activities
BAHX failures
BAHX failures
Comparison of the Train-B (top) and Train-A (bottom)
Be aware of normalization of risks based on past-experience.
Sanjeev Saraf
Visit the blog
Signup for newsletter
LinkedIn

More Related Content

What's hot

Vapor Compression Refrigeration System
Vapor Compression Refrigeration System Vapor Compression Refrigeration System
Vapor Compression Refrigeration System Abduljalil Al-Abidi
 
Analysis of Thermal Profiles of Various Power Extraction Limits in a PWR Hea...
Analysis of Thermal Profiles of Various Power Extraction Limits in a  PWR Hea...Analysis of Thermal Profiles of Various Power Extraction Limits in a  PWR Hea...
Analysis of Thermal Profiles of Various Power Extraction Limits in a PWR Hea...IRJET Journal
 
heat transfer performance in 3D induced finned heat pipe
heat transfer performance in 3D induced finned heat pipeheat transfer performance in 3D induced finned heat pipe
heat transfer performance in 3D induced finned heat pipeDivya Khandelwal
 
Computational model for multi alloy casting of aluminum rolling ingots
Computational model for multi alloy casting of aluminum rolling ingotsComputational model for multi alloy casting of aluminum rolling ingots
Computational model for multi alloy casting of aluminum rolling ingotsLOKESH BAVISKAR
 
Intensive Riser Cooling of casting after solidification
Intensive Riser Cooling of casting after solidificationIntensive Riser Cooling of casting after solidification
Intensive Riser Cooling of casting after solidificationLOKESH BAVISKAR
 
Million square foot building lutes aehs epa workshop ssda community leader-...
Million square foot building lutes aehs epa workshop   ssda community leader-...Million square foot building lutes aehs epa workshop   ssda community leader-...
Million square foot building lutes aehs epa workshop ssda community leader-...Chris Lutes
 
Plate and frame Heat Exchanger Sizing
Plate and frame Heat Exchanger SizingPlate and frame Heat Exchanger Sizing
Plate and frame Heat Exchanger SizingSyed Waqas Haider
 
Fabrication of Ranque Hilsch Vortex Tube
Fabrication of Ranque Hilsch Vortex TubeFabrication of Ranque Hilsch Vortex Tube
Fabrication of Ranque Hilsch Vortex TubeSUMIT CHOUDHARY
 
ANALYSIS OF VAPOR COMPRESSION REFRIGERATION SYSTEM WITH DIFFERENT CONFIGURATI...
ANALYSIS OF VAPOR COMPRESSION REFRIGERATION SYSTEM WITH DIFFERENT CONFIGURATI...ANALYSIS OF VAPOR COMPRESSION REFRIGERATION SYSTEM WITH DIFFERENT CONFIGURATI...
ANALYSIS OF VAPOR COMPRESSION REFRIGERATION SYSTEM WITH DIFFERENT CONFIGURATI...ijiert bestjournal
 
Vapor compression refrigeration cycle
Vapor compression refrigeration cycleVapor compression refrigeration cycle
Vapor compression refrigeration cyclepradosh a c
 
Flame Stabilization Techniques
Flame Stabilization TechniquesFlame Stabilization Techniques
Flame Stabilization TechniquesROSHAN SAH
 
Vapor-compression refrigeration – Effect of parameter
Vapor-compression refrigeration – Effect of parameterVapor-compression refrigeration – Effect of parameter
Vapor-compression refrigeration – Effect of parameterjani parth
 

What's hot (14)

Vapor Compression Refrigeration System
Vapor Compression Refrigeration System Vapor Compression Refrigeration System
Vapor Compression Refrigeration System
 
Analysis of Thermal Profiles of Various Power Extraction Limits in a PWR Hea...
Analysis of Thermal Profiles of Various Power Extraction Limits in a  PWR Hea...Analysis of Thermal Profiles of Various Power Extraction Limits in a  PWR Hea...
Analysis of Thermal Profiles of Various Power Extraction Limits in a PWR Hea...
 
heat transfer performance in 3D induced finned heat pipe
heat transfer performance in 3D induced finned heat pipeheat transfer performance in 3D induced finned heat pipe
heat transfer performance in 3D induced finned heat pipe
 
Computational model for multi alloy casting of aluminum rolling ingots
Computational model for multi alloy casting of aluminum rolling ingotsComputational model for multi alloy casting of aluminum rolling ingots
Computational model for multi alloy casting of aluminum rolling ingots
 
Intensive Riser Cooling of casting after solidification
Intensive Riser Cooling of casting after solidificationIntensive Riser Cooling of casting after solidification
Intensive Riser Cooling of casting after solidification
 
Million square foot building lutes aehs epa workshop ssda community leader-...
Million square foot building lutes aehs epa workshop   ssda community leader-...Million square foot building lutes aehs epa workshop   ssda community leader-...
Million square foot building lutes aehs epa workshop ssda community leader-...
 
Allen Nicholas
Allen NicholasAllen Nicholas
Allen Nicholas
 
Plate and frame Heat Exchanger Sizing
Plate and frame Heat Exchanger SizingPlate and frame Heat Exchanger Sizing
Plate and frame Heat Exchanger Sizing
 
Fabrication of Ranque Hilsch Vortex Tube
Fabrication of Ranque Hilsch Vortex TubeFabrication of Ranque Hilsch Vortex Tube
Fabrication of Ranque Hilsch Vortex Tube
 
ANALYSIS OF VAPOR COMPRESSION REFRIGERATION SYSTEM WITH DIFFERENT CONFIGURATI...
ANALYSIS OF VAPOR COMPRESSION REFRIGERATION SYSTEM WITH DIFFERENT CONFIGURATI...ANALYSIS OF VAPOR COMPRESSION REFRIGERATION SYSTEM WITH DIFFERENT CONFIGURATI...
ANALYSIS OF VAPOR COMPRESSION REFRIGERATION SYSTEM WITH DIFFERENT CONFIGURATI...
 
P1
P1P1
P1
 
Vapor compression refrigeration cycle
Vapor compression refrigeration cycleVapor compression refrigeration cycle
Vapor compression refrigeration cycle
 
Flame Stabilization Techniques
Flame Stabilization TechniquesFlame Stabilization Techniques
Flame Stabilization Techniques
 
Vapor-compression refrigeration – Effect of parameter
Vapor-compression refrigeration – Effect of parameterVapor-compression refrigeration – Effect of parameter
Vapor-compression refrigeration – Effect of parameter
 

Similar to Pascagoula gas plant incident

Good heater specifications pay off
Good heater specifications pay off Good heater specifications pay off
Good heater specifications pay off Ashutosh Garg
 
Hvac chiller Engineer Tech
Hvac chiller Engineer Tech Hvac chiller Engineer Tech
Hvac chiller Engineer Tech Kamran Saeed
 
PSV Flare system PSV Flare system PSV Flare system
PSV Flare system PSV Flare system PSV Flare systemPSV Flare system PSV Flare system PSV Flare system
PSV Flare system PSV Flare system PSV Flare systemBabaDook15
 
Thermal Stress Analysis of Casing in Cyclic Steam Injected Well
Thermal Stress Analysis of Casing in Cyclic Steam Injected WellThermal Stress Analysis of Casing in Cyclic Steam Injected Well
Thermal Stress Analysis of Casing in Cyclic Steam Injected WellIRJET Journal
 
HE-Design-Project-2016
HE-Design-Project-2016HE-Design-Project-2016
HE-Design-Project-2016Giankarl Bogle
 
The Role of the Insulation System in Optimizing value in LNG Facilities
The Role of the Insulation System in Optimizing value in LNG FacilitiesThe Role of the Insulation System in Optimizing value in LNG Facilities
The Role of the Insulation System in Optimizing value in LNG FacilitiesDyplast Products
 
The Role of the Insulation System in Optimizing value in LNG Facilities
The Role of the Insulation System in Optimizing value in LNG FacilitiesThe Role of the Insulation System in Optimizing value in LNG Facilities
The Role of the Insulation System in Optimizing value in LNG FacilitiesJoe Hughes
 
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS DynamicsHeat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS DynamicsProcess Ecology Inc
 
LNG Industry Magazine (Risk Mitigation Standards) July 2016
LNG Industry Magazine (Risk Mitigation Standards) July 2016LNG Industry Magazine (Risk Mitigation Standards) July 2016
LNG Industry Magazine (Risk Mitigation Standards) July 2016Joe Hughes
 
LNG Industry Magazine (Risk Mitigation Standards) July 2016
LNG Industry Magazine (Risk Mitigation Standards) July 2016LNG Industry Magazine (Risk Mitigation Standards) July 2016
LNG Industry Magazine (Risk Mitigation Standards) July 2016Dyplast Products
 
BVAA presentation 2015: The Use of CFD to assess valve performance and operat...
BVAA presentation 2015: The Use of CFD to assess valve performance and operat...BVAA presentation 2015: The Use of CFD to assess valve performance and operat...
BVAA presentation 2015: The Use of CFD to assess valve performance and operat...Linsley Charlton
 
Compact Heat Exchangers
Compact Heat ExchangersCompact Heat Exchangers
Compact Heat Exchangersadlinilda
 
articleHydrocarbonEngineeringSeptember2019.pdf
articleHydrocarbonEngineeringSeptember2019.pdfarticleHydrocarbonEngineeringSeptember2019.pdf
articleHydrocarbonEngineeringSeptember2019.pdfRoy Niekerk
 
Design of Heat Exchanger Network for VCM Distillation Unit Using Pinch Techno...
Design of Heat Exchanger Network for VCM Distillation Unit Using Pinch Techno...Design of Heat Exchanger Network for VCM Distillation Unit Using Pinch Techno...
Design of Heat Exchanger Network for VCM Distillation Unit Using Pinch Techno...IJERA Editor
 
PREDICTIONS AT THE BLOW END OF THE LD-KGC CONVERTER BY A SEMI-DYNAMIC CONTROL...
PREDICTIONS AT THE BLOW END OF THE LD-KGC CONVERTER BY A SEMI-DYNAMIC CONTROL...PREDICTIONS AT THE BLOW END OF THE LD-KGC CONVERTER BY A SEMI-DYNAMIC CONTROL...
PREDICTIONS AT THE BLOW END OF THE LD-KGC CONVERTER BY A SEMI-DYNAMIC CONTROL...ijmech
 
Kalepa Tech Engineering V09
Kalepa Tech Engineering V09Kalepa Tech Engineering V09
Kalepa Tech Engineering V09kceridon
 
Remaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element methodRemaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element methodBarhm Mohamad
 

Similar to Pascagoula gas plant incident (20)

Soot blowing and advantages
Soot blowing and advantagesSoot blowing and advantages
Soot blowing and advantages
 
Good heater specifications pay off
Good heater specifications pay off Good heater specifications pay off
Good heater specifications pay off
 
Hvac chiller Engineer Tech
Hvac chiller Engineer Tech Hvac chiller Engineer Tech
Hvac chiller Engineer Tech
 
PSV Flare system PSV Flare system PSV Flare system
PSV Flare system PSV Flare system PSV Flare systemPSV Flare system PSV Flare system PSV Flare system
PSV Flare system PSV Flare system PSV Flare system
 
Thermal Stress Analysis of Casing in Cyclic Steam Injected Well
Thermal Stress Analysis of Casing in Cyclic Steam Injected WellThermal Stress Analysis of Casing in Cyclic Steam Injected Well
Thermal Stress Analysis of Casing in Cyclic Steam Injected Well
 
HE-Design-Project-2016
HE-Design-Project-2016HE-Design-Project-2016
HE-Design-Project-2016
 
The Role of the Insulation System in Optimizing value in LNG Facilities
The Role of the Insulation System in Optimizing value in LNG FacilitiesThe Role of the Insulation System in Optimizing value in LNG Facilities
The Role of the Insulation System in Optimizing value in LNG Facilities
 
The Role of the Insulation System in Optimizing value in LNG Facilities
The Role of the Insulation System in Optimizing value in LNG FacilitiesThe Role of the Insulation System in Optimizing value in LNG Facilities
The Role of the Insulation System in Optimizing value in LNG Facilities
 
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS DynamicsHeat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
 
LNG Industry Magazine (Risk Mitigation Standards) July 2016
LNG Industry Magazine (Risk Mitigation Standards) July 2016LNG Industry Magazine (Risk Mitigation Standards) July 2016
LNG Industry Magazine (Risk Mitigation Standards) July 2016
 
LNG Industry Magazine (Risk Mitigation Standards) July 2016
LNG Industry Magazine (Risk Mitigation Standards) July 2016LNG Industry Magazine (Risk Mitigation Standards) July 2016
LNG Industry Magazine (Risk Mitigation Standards) July 2016
 
BVAA presentation 2015: The Use of CFD to assess valve performance and operat...
BVAA presentation 2015: The Use of CFD to assess valve performance and operat...BVAA presentation 2015: The Use of CFD to assess valve performance and operat...
BVAA presentation 2015: The Use of CFD to assess valve performance and operat...
 
Jacketed vessel design
Jacketed vessel designJacketed vessel design
Jacketed vessel design
 
Compact Heat Exchangers
Compact Heat ExchangersCompact Heat Exchangers
Compact Heat Exchangers
 
articleHydrocarbonEngineeringSeptember2019.pdf
articleHydrocarbonEngineeringSeptember2019.pdfarticleHydrocarbonEngineeringSeptember2019.pdf
articleHydrocarbonEngineeringSeptember2019.pdf
 
Design of Heat Exchanger Network for VCM Distillation Unit Using Pinch Techno...
Design of Heat Exchanger Network for VCM Distillation Unit Using Pinch Techno...Design of Heat Exchanger Network for VCM Distillation Unit Using Pinch Techno...
Design of Heat Exchanger Network for VCM Distillation Unit Using Pinch Techno...
 
PREDICTIONS AT THE BLOW END OF THE LD-KGC CONVERTER BY A SEMI-DYNAMIC CONTROL...
PREDICTIONS AT THE BLOW END OF THE LD-KGC CONVERTER BY A SEMI-DYNAMIC CONTROL...PREDICTIONS AT THE BLOW END OF THE LD-KGC CONVERTER BY A SEMI-DYNAMIC CONTROL...
PREDICTIONS AT THE BLOW END OF THE LD-KGC CONVERTER BY A SEMI-DYNAMIC CONTROL...
 
Kalepa Tech Engineering V09
Kalepa Tech Engineering V09Kalepa Tech Engineering V09
Kalepa Tech Engineering V09
 
Remaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element methodRemaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element method
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 

More from Sanjeev Saraf

H2S management including scavengers
H2S management including scavengersH2S management including scavengers
H2S management including scavengersSanjeev Saraf
 
Chemical treatment for oilfield bacteria
Chemical treatment for oilfield bacteria Chemical treatment for oilfield bacteria
Chemical treatment for oilfield bacteria Sanjeev Saraf
 
Corrosion inhibitor compatibility with other chemicals
Corrosion inhibitor compatibility with other chemicalsCorrosion inhibitor compatibility with other chemicals
Corrosion inhibitor compatibility with other chemicalsSanjeev Saraf
 
Corrosion inhibitor selection
Corrosion inhibitor selectionCorrosion inhibitor selection
Corrosion inhibitor selectionSanjeev Saraf
 
Simplified qra example, sanjeev saraf
Simplified qra example, sanjeev saraf Simplified qra example, sanjeev saraf
Simplified qra example, sanjeev saraf Sanjeev Saraf
 
Nexterra vs. exxon 2020
Nexterra vs. exxon   2020Nexterra vs. exxon   2020
Nexterra vs. exxon 2020Sanjeev Saraf
 

More from Sanjeev Saraf (7)

H2S management including scavengers
H2S management including scavengersH2S management including scavengers
H2S management including scavengers
 
Oxygen scavenger
Oxygen scavengerOxygen scavenger
Oxygen scavenger
 
Chemical treatment for oilfield bacteria
Chemical treatment for oilfield bacteria Chemical treatment for oilfield bacteria
Chemical treatment for oilfield bacteria
 
Corrosion inhibitor compatibility with other chemicals
Corrosion inhibitor compatibility with other chemicalsCorrosion inhibitor compatibility with other chemicals
Corrosion inhibitor compatibility with other chemicals
 
Corrosion inhibitor selection
Corrosion inhibitor selectionCorrosion inhibitor selection
Corrosion inhibitor selection
 
Simplified qra example, sanjeev saraf
Simplified qra example, sanjeev saraf Simplified qra example, sanjeev saraf
Simplified qra example, sanjeev saraf
 
Nexterra vs. exxon 2020
Nexterra vs. exxon   2020Nexterra vs. exxon   2020
Nexterra vs. exxon 2020
 

Recently uploaded

LITERAL RULE OF INTERPRETATION - PRIMARY RULE
LITERAL RULE OF INTERPRETATION - PRIMARY RULELITERAL RULE OF INTERPRETATION - PRIMARY RULE
LITERAL RULE OF INTERPRETATION - PRIMARY RULEsreeramsaipranitha
 
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top BoutiqueAndrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top BoutiqueSkyLaw Professional Corporation
 
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual serviceanilsa9823
 
THE FACTORIES ACT,1948 (2).pptx labour
THE FACTORIES ACT,1948 (2).pptx   labourTHE FACTORIES ACT,1948 (2).pptx   labour
THE FACTORIES ACT,1948 (2).pptx labourBhavikaGholap1
 
PPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxPPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxRRR Chambers
 
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxKEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxRRR Chambers
 
一比一原版西澳大学毕业证学位证书
 一比一原版西澳大学毕业证学位证书 一比一原版西澳大学毕业证学位证书
一比一原版西澳大学毕业证学位证书SS A
 
Debt Collection in India - General Procedure
Debt Collection in India  - General ProcedureDebt Collection in India  - General Procedure
Debt Collection in India - General ProcedureBridgeWest.eu
 
The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...James Watkins, III JD CFP®
 
Essentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmmEssentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmm2020000445musaib
 
Chp 1- Contract and its kinds-business law .ppt
Chp 1- Contract and its kinds-business law .pptChp 1- Contract and its kinds-business law .ppt
Chp 1- Contract and its kinds-business law .pptzainabbkhaleeq123
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书Sir Lt
 
Transferable and Non-Transferable Property.pptx
Transferable and Non-Transferable Property.pptxTransferable and Non-Transferable Property.pptx
Transferable and Non-Transferable Property.pptx2020000445musaib
 
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)Delhi Call girls
 
Divorce Procedure in India (Info) (1).pdf
Divorce Procedure in India (Info) (1).pdfDivorce Procedure in India (Info) (1).pdf
Divorce Procedure in India (Info) (1).pdfdigitalnikesh24
 
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhaiShashankKumar441258
 
一比一原版旧金山州立大学毕业证学位证书
 一比一原版旧金山州立大学毕业证学位证书 一比一原版旧金山州立大学毕业证学位证书
一比一原版旧金山州立大学毕业证学位证书SS A
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptjudeplata
 

Recently uploaded (20)

LITERAL RULE OF INTERPRETATION - PRIMARY RULE
LITERAL RULE OF INTERPRETATION - PRIMARY RULELITERAL RULE OF INTERPRETATION - PRIMARY RULE
LITERAL RULE OF INTERPRETATION - PRIMARY RULE
 
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top BoutiqueAndrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
 
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
 
THE FACTORIES ACT,1948 (2).pptx labour
THE FACTORIES ACT,1948 (2).pptx   labourTHE FACTORIES ACT,1948 (2).pptx   labour
THE FACTORIES ACT,1948 (2).pptx labour
 
Vip Call Girls Greater Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS Live
Vip Call Girls Greater Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS LiveVip Call Girls Greater Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS Live
Vip Call Girls Greater Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS Live
 
PPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxPPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptx
 
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxKEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
 
一比一原版西澳大学毕业证学位证书
 一比一原版西澳大学毕业证学位证书 一比一原版西澳大学毕业证学位证书
一比一原版西澳大学毕业证学位证书
 
Debt Collection in India - General Procedure
Debt Collection in India  - General ProcedureDebt Collection in India  - General Procedure
Debt Collection in India - General Procedure
 
The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...
 
Essentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmmEssentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmm
 
Chp 1- Contract and its kinds-business law .ppt
Chp 1- Contract and its kinds-business law .pptChp 1- Contract and its kinds-business law .ppt
Chp 1- Contract and its kinds-business law .ppt
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 
Transferable and Non-Transferable Property.pptx
Transferable and Non-Transferable Property.pptxTransferable and Non-Transferable Property.pptx
Transferable and Non-Transferable Property.pptx
 
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
 
Divorce Procedure in India (Info) (1).pdf
Divorce Procedure in India (Info) (1).pdfDivorce Procedure in India (Info) (1).pdf
Divorce Procedure in India (Info) (1).pdf
 
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
 
一比一原版旧金山州立大学毕业证学位证书
 一比一原版旧金山州立大学毕业证学位证书 一比一原版旧金山州立大学毕业证学位证书
一比一原版旧金山州立大学毕业证学位证书
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
 
Old Income Tax Regime Vs New Income Tax Regime
Old  Income Tax Regime Vs  New Income Tax   RegimeOld  Income Tax Regime Vs  New Income Tax   Regime
Old Income Tax Regime Vs New Income Tax Regime
 

Pascagoula gas plant incident

  • 1. Pascagoula Gas Plant Incident Sanjeev Saraf CSB report: https://www.csb.gov/assets/1/6/final_case_study_-_enterprise.pdf
  • 2. Facility • Pascagoula gas plant • Gas plant receives condensate from Destin pipeline in deepwater GoM • Gas (C1-C4) separation from NGL using cryogenic process • Brazed aluminum heat exchanger (BAHX), which allows for the transfer of heat between different process • Susceptible to thermal fatigue. Weakening of braze joints between fins and parting sheets
  • 3. Design PHA • 1997 (design-stage): team did not expect the hazard to have a public impact and anticipated only minor damage and downtime. Team assumed the likelihood of thermal shock to be once every 50 years and labeled it as a “medium priority,” for which the company recommended that “serious and appropriate actions should be taken.” In response, the PHA team recommended developing procedures for the BAHXs’ various operating modes (e.g. start-up, shutdown) to minimize the likelihood of thermal shock events.
  • 4. PHA Revalidation 2009: “high impact health/safety incident” with the potential to cause (1) “permanent partial disability(ies),” (2) “several non-permanent injuries or health impacts,” and (3) “days away from work.” As a consequence, the PHA team recommended evaluating the replacement of the BAHXs with a different exchanger design.
  • 5. PHA Revalidation and follow up 2013: The 2013 PHA revalidation no longer identified health and safety consequences associated with the exchangers. Instead, the listed potential consequences mirrored the plant’s experiences with leaks. Exchanger repairs in the range of $60-150-k. The safeguards for minimizing BAHX damage identified in the PHA were metal temperature sensors, operator intervention, and operating procedures. 2015: A plan to change them out within 3 years to “ensure equipment integrity.” Justification for the plan stated that “cyclical operation causes small cracks on heat exchangers. Rapid cooling or heating of the brazed aluminum heat exchangers has the potential to create small cracks around support pads. Small cracks result in weeps of gas out. Potential for personnel injury is minor. Cost associated with repairs and downtime. Repair costs vary from $80 thousand onsite to $100 thousand offsite”
  • 6. BAHX failures – 9 failures in 11-years (18-operating years)
  • 7. Incidents • Incident occurred on 27 June 2016 • Operators initiating controlled shutdown • Fire and explosion reported at 11:22 pm • BAHX failure from thermal fatigue • 13 different ruptures of piping and equipment during the course of the incident • Community evacuation • $10.4 million of expense due to fire response activities; $7.1 million non- cash activities
  • 10. Comparison of the Train-B (top) and Train-A (bottom)
  • 11. Be aware of normalization of risks based on past-experience. Sanjeev Saraf Visit the blog Signup for newsletter LinkedIn

Editor's Notes

  1. In Slide Show mode, select the arrows to visit links.