SlideShare a Scribd company logo
1 of 64
WINNER PLATINUM AWARD
BUILDING TEAM OWNER / DEVELOPER ARCHITECT INTERIOR ARCHITECT (KITCHENS) STRUCTURAL ENGINEER MECHANICAL ENGINEER ELECTRICAL ENGINEER PLUMBING ENGINEER GENERAL CONTRACTOR University of California, Irvine Hellmuth, Obata + Kassabaum, Inc. Dave Keaggy & Associates Nabih Youseff & Associates TMAD-Taylor & Gaines TMAD-Taylor & Gaines TMAD-Taylor & Gaines Hensel Phelps Construction Co.
ACCOLADE “We’re out here doing our inspections and observations as we always do. What’s different is the effort by the Owner, the Architect and the Contractor … all working together to make it happen.” Tom Crowder OSHPD Regional Compliance Officer
BUDGET HISTORY
BUDGET HISTORY November 2000 January 2003 February 2004 June 2004 Sept/Oct 2004 December 2004 January 2005 September 2008 UC Regents set aside $235M Lease Revenue Bonds for a Replacement Hospital UC Regents certify the EIR and approve a $243M Construction Budget Lowest Bid exceeds Construction Budget by 25% UC Regents establish a Maximum Acceptance Cost (MAC) of $250M UC Regents establish a MAC for additional Scope of Work (Even more scope of work is added to the project at a later date) Second Bid $246M ($4Mbelow$250M MAC) Project is awarded with added scope of work (Ultimately the scope of work reaches $285M) Notice to Proceed is issued to the Design-Build Contractor OSHPD issues Certificate of Occupancy (4 months early) Project is completed for $283M ($2M below cost ceiling) Project savings extend beyond construction costs: Due to early construction completion, no claims, savings in equipment purchasing, and other project management efficiencies, UCI Project Team returns $26M to the University.
PROJECT DELIVERY METHOD COMPARED
WHY FIRST BID FAILED Why was the first bid over budget? ,[object Object]
Secondly, there are only a few mechanical, electrical and plumbing (MEP) subcontractors that can handle a mega-project of this scale, where MEP systems represent more than 50 percent of the total construction budget.
Contractors were fearful of the risks associated with the job: experiences on other UC campuses, OSHPD changes in the field, and the sudden, escalating market volatility.
Subcontractors added high contingencies to their bids which were not anticipated by UCI, the cost estimator, and even the general contractors.,[object Object]
It has been used by the federal government to build all types of construction, including power plants and hospitals.
However, its application to replacement hospitals in California under SB 1953 is new. Is design-build a problem for OSHPD? ,[object Object]
OSHPD has adopted a policy of support for design-build.* Ref. Rand Corporation, April 2004
WHY SECOND BID SUCCEEDED What changes have been made to the bid documents to reduce uncertainty and to enable better pricing? ,[object Object]
Architectural plans revised to reflect all floor plan and elevation changes.
Pre-qualification requirements relaxed for 10 subcontractor trades.
Problematic specifications revised.
Bid documents streamlined from 58 alternates to 3.
Technical submittal requirements reduced by 70 percent.
Field information and decision making process with OSHPD streamlined to reduce risks.
“Best and Final Offer” (BAFO) process added to bid documents. ,[object Object]
Another independent cost estimator was hired to prepare sealed cost estimate to be opened at time of bid.
Third-party general contractor to review subcontractor bids and provide advice during BAFO negotiations.
This is an open bid process, with all subcontractor bids subject to review for fair market value and re-bid as necessary. How did the “Best and Final Offer” process work ? ,[object Object],[object Object]
Reduce building height by 7 feet
Opt for precast building skin in lieu of stone
Save 1,600 tons of steel by introducing seismic bracing
Delete roof-mounted cooling towers in favor of air-cooled towers on the ground
Delete mechanical space on 3rd floor by placing OR air handlers in the basement
Delete a planned campus circulation arcade from scope
Defer roof-top gardens to a future project
Defer outdoor dining to Phase 2 Project
Defer future growth TIs to Phase 2 Project
$35M saved by the VE Process
$23M deferred to future projects
$5M in scope reductions,[object Object]
LEAN INCREMENTALPERMITS & CONSTRUCTION
DESIGN-BUILD TIMELINE
DESIGN-BUILD CONTRACT
DESIGN-BUILD CONTRACTUAL RELATIONSHIPS OF THIS PROJECT
ACCOLADE Design Build Institute of America awarded our project its  most prestigious Western Pacific Region Award  					           for a large public building
IPD  TEAM DYNAMICS
COMPARE Traditional Project Delivery Integrated Project Delivery Our project’s Design-Build Integrated Project Delivery
UCI’S COMMITMENT TO  IPD For the last 11 years, UCI’s Design & Construction Services has hosted the DESIGN BUILD Symposium; most recently renamed ALIGN 2 REDEFINE. Showcases the continuous refinement of the integrated interdisciplinary project delivery approach.  Designed to encourage and inspire participants to discover new ways to enhance outcomes, process, production and timeline. The Design & Construction Services team has earned 15 top industry awards since 2007, including: ,[object Object]
DBIA Design Build Best Project Award, Merit Award, and Excellence Award
The US Green Building Council Gold LEED Award,[object Object]
IPD  TEAM DYNAMICS DELIVERS WINDFALL VE moved OR air handlers to the Basement VE modified the structural design TEAM reconfigured the foundation system and created a full building footprint basement TEAM created 27,000SF Bonus Shell Space for a new Radiology Department in Phase 2
IPD  BETTERS THE PROJECT Better drawings Design enhancements OSHPD accelerated review BIM integration Construction efficiencies Punch List approach Subcontractors, vendors and their engineers have direct access to OSHPD reviewers Stone clad 2-story lobby – first time stone is used in an OSHPD project Shoulder-to-shoulder quality assurance review by Owner’s professional staff warms up OSHPD to accelerated review time ,[object Object]
New design solutions that are feasible only in a 3D environment:
Pre-fabricated supports for OR booms and lights
Pre-fabricated universal structural support for all ceiling and ceiling mounted building systems at OR interstitial spaceMedical gas trees pre-assembled, tested and inspected at factory –  another first for OSHPD Enhanced and better coordinated effort with highly committed staff completes the effort in record time
IPD  VALUE TO THE DESIGN PROCESS The Design-Build contractual framework enabled an integrated, interdisciplinary process that achieved LEAN characteristics: Impeccable coordination: Each of the Engineers of Record came to the design table with their respective major subcontractors and all the vendors and vendors’ engineers. Vendors and contractors designed and resolvedthe constructability of all the designs and construction/installation details they had a vested interest in. Their designs and drawings were directly incorporated in the Permit Set – no deferred approvals. Project as Production System:The incremental design and permit process, the just-in-time documents delivery schedule, the concerted effort to anticipate and mitigate risk through design coordination, by necessity, focused the team to design jointly to exacting tolerancesand embrace pre-fabricationto an unprecedented level under OSHPD. Project as Collective Enterprise:The Mission Controlmetaphor provides a very accurate image of what took place daily in design, coordination, constructability, plan review, schedule, budget, and QC sessions that took place in the job-site trailer from day one until the Certificate of Occupancy was obtained.
COLLABORATIVE DESIGN INNOVATION Stone ,[object Object]
Close coordination between main frame structural designers, stone subcontractor, structural engineers for the for the steel stud systems, light gauge steel subcontractor, specialty steel and glass vendors, and the rest of the team at large.
All stone pieces (up to 4 inch thick) have soft joints to allow individual movement in case of a seismic event.
All the fabricator details are part of the permit.
Creative solution made possible by the collaborative effort.
Designed in 3D.
Stone was cut off-site to precise tolerances.,[object Object]
Creative solution made possible by collaborative effort with vision beyond first cost.
Project-wide, the crane concept cost $350k more than the typical install, BUT made the above ceiling coordination effort much more manageable, saving costs for those activities.
Mechanical systems manufactured off-site to precise tolerances
Assembled entirely off-site
Installed in reduced time on-siteA TYPICAL HOSPITAL APPLICATION

More Related Content

What's hot

Development Financial Study
Development Financial StudyDevelopment Financial Study
Development Financial StudyPloutus Advisors
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity SurveyingLIJI A
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016teohwooisin
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsNam N.N Tran M.Eng, PMP
 
Project Construction of 5 star hotel
Project Construction of 5 star hotelProject Construction of 5 star hotel
Project Construction of 5 star hotelMuhammad Farhan Javed
 
House construction company Feasibility report
House construction company Feasibility report House construction company Feasibility report
House construction company Feasibility report MuhammadImran1161
 
Project brief
Project briefProject brief
Project briefkerneng
 
PMC Proposal.docx
PMC Proposal.docxPMC Proposal.docx
PMC Proposal.docxManuSood11
 
Construction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation SlidesConstruction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation SlidesSlideTeam
 
Integration Project 1 - Quantity Surveyor
Integration Project 1 - Quantity SurveyorIntegration Project 1 - Quantity Surveyor
Integration Project 1 - Quantity SurveyorNatalie Yunxian
 
Civil Engineering Construction Proposal PowerPoint Presentation Slides
Civil Engineering Construction Proposal PowerPoint Presentation SlidesCivil Engineering Construction Proposal PowerPoint Presentation Slides
Civil Engineering Construction Proposal PowerPoint Presentation SlidesSlideTeam
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 
Project management
Project managementProject management
Project managementBenjamin Tan
 
Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group AssignmentArissa Loh
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentationemdad bhuiyan
 
Highway Project Schedule
Highway Project Schedule Highway Project Schedule
Highway Project Schedule Akram Suleiman
 
Real Estate Development Case Presentation
Real Estate Development Case PresentationReal Estate Development Case Presentation
Real Estate Development Case PresentationDaniel Mandel
 

What's hot (20)

EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Model
 
Development Financial Study
Development Financial StudyDevelopment Financial Study
Development Financial Study
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
Real Estate Development Modeling Basics
Real Estate Development Modeling BasicsReal Estate Development Modeling Basics
Real Estate Development Modeling Basics
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Project Construction of 5 star hotel
Project Construction of 5 star hotelProject Construction of 5 star hotel
Project Construction of 5 star hotel
 
House construction company Feasibility report
House construction company Feasibility report House construction company Feasibility report
House construction company Feasibility report
 
Project brief
Project briefProject brief
Project brief
 
PMC Proposal.docx
PMC Proposal.docxPMC Proposal.docx
PMC Proposal.docx
 
Construction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation SlidesConstruction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation Slides
 
Integration Project 1 - Quantity Surveyor
Integration Project 1 - Quantity SurveyorIntegration Project 1 - Quantity Surveyor
Integration Project 1 - Quantity Surveyor
 
Civil Engineering Construction Proposal PowerPoint Presentation Slides
Civil Engineering Construction Proposal PowerPoint Presentation SlidesCivil Engineering Construction Proposal PowerPoint Presentation Slides
Civil Engineering Construction Proposal PowerPoint Presentation Slides
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
Project management
Project managementProject management
Project management
 
Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group Assignment
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentation
 
Highway Project Schedule
Highway Project Schedule Highway Project Schedule
Highway Project Schedule
 
Real Estate Development Case Presentation
Real Estate Development Case PresentationReal Estate Development Case Presentation
Real Estate Development Case Presentation
 

Viewers also liked

2012 Hum Specification Presentation
2012 Hum Specification Presentation2012 Hum Specification Presentation
2012 Hum Specification PresentationAlibia de Vente
 
2011.04.19 allegro mail.ru-charity
2011.04.19 allegro mail.ru-charity2011.04.19 allegro mail.ru-charity
2011.04.19 allegro mail.ru-charityMolotok.Ru
 
Edenspiekermann agency presentation 2012
Edenspiekermann agency presentation 2012Edenspiekermann agency presentation 2012
Edenspiekermann agency presentation 2012Edo van Dijk
 
Rediseño Curricular
Rediseño CurricularRediseño Curricular
Rediseño Curricularead1943
 
解读信息设计
解读信息设计解读信息设计
解读信息设计dasiyjun
 
Iksula Magento Solutions
Iksula Magento SolutionsIksula Magento Solutions
Iksula Magento SolutionsIksula
 
Presentación Edwin Wong
Presentación Edwin Wong Presentación Edwin Wong
Presentación Edwin Wong IAB México
 
58638 01
58638 0158638 01
58638 01icenemo
 
American Oil & Gas Reporter December 2010
American Oil & Gas Reporter December 2010American Oil & Gas Reporter December 2010
American Oil & Gas Reporter December 2010jwvitalone
 
2011-02 ClickAsiaSummit Metrics, Analysis, Action!
2011-02 ClickAsiaSummit Metrics, Analysis, Action!2011-02 ClickAsiaSummit Metrics, Analysis, Action!
2011-02 ClickAsiaSummit Metrics, Analysis, Action!Gillian Muessig
 
2011 07 oms atlanta-gillian-muessig-topic-modeling
2011 07 oms atlanta-gillian-muessig-topic-modeling2011 07 oms atlanta-gillian-muessig-topic-modeling
2011 07 oms atlanta-gillian-muessig-topic-modelingGillian Muessig
 
Wedding Pp For Email
Wedding Pp For EmailWedding Pp For Email
Wedding Pp For Emailguestb75bf7e
 

Viewers also liked (20)

2012 Hum Specification Presentation
2012 Hum Specification Presentation2012 Hum Specification Presentation
2012 Hum Specification Presentation
 
2011.04.19 allegro mail.ru-charity
2011.04.19 allegro mail.ru-charity2011.04.19 allegro mail.ru-charity
2011.04.19 allegro mail.ru-charity
 
David kenneth waldman's_2012_cv_mayv31
David kenneth waldman's_2012_cv_mayv31David kenneth waldman's_2012_cv_mayv31
David kenneth waldman's_2012_cv_mayv31
 
Ur-Energy February 2013 Corporate Presentation
Ur-Energy February 2013 Corporate PresentationUr-Energy February 2013 Corporate Presentation
Ur-Energy February 2013 Corporate Presentation
 
20110118 ure corporate presentation (january 18 2011)
20110118 ure corporate presentation (january 18 2011)20110118 ure corporate presentation (january 18 2011)
20110118 ure corporate presentation (january 18 2011)
 
Edenspiekermann agency presentation 2012
Edenspiekermann agency presentation 2012Edenspiekermann agency presentation 2012
Edenspiekermann agency presentation 2012
 
Rediseño Curricular
Rediseño CurricularRediseño Curricular
Rediseño Curricular
 
解读信息设计
解读信息设计解读信息设计
解读信息设计
 
Iksula Magento Solutions
Iksula Magento SolutionsIksula Magento Solutions
Iksula Magento Solutions
 
DVCP presentation
DVCP presentationDVCP presentation
DVCP presentation
 
Presentación Edwin Wong
Presentación Edwin Wong Presentación Edwin Wong
Presentación Edwin Wong
 
20110506 ure corporate presentation (may 2011)
20110506 ure corporate presentation (may 2011)20110506 ure corporate presentation (may 2011)
20110506 ure corporate presentation (may 2011)
 
58638 01
58638 0158638 01
58638 01
 
August 2011 Ur-Energy Corporate Presentation
August 2011 Ur-Energy Corporate PresentationAugust 2011 Ur-Energy Corporate Presentation
August 2011 Ur-Energy Corporate Presentation
 
American Oil & Gas Reporter December 2010
American Oil & Gas Reporter December 2010American Oil & Gas Reporter December 2010
American Oil & Gas Reporter December 2010
 
2011-02 ClickAsiaSummit Metrics, Analysis, Action!
2011-02 ClickAsiaSummit Metrics, Analysis, Action!2011-02 ClickAsiaSummit Metrics, Analysis, Action!
2011-02 ClickAsiaSummit Metrics, Analysis, Action!
 
2010 Cetra
2010 Cetra2010 Cetra
2010 Cetra
 
2011 07 oms atlanta-gillian-muessig-topic-modeling
2011 07 oms atlanta-gillian-muessig-topic-modeling2011 07 oms atlanta-gillian-muessig-topic-modeling
2011 07 oms atlanta-gillian-muessig-topic-modeling
 
Aim Final Plans Book
Aim Final Plans BookAim Final Plans Book
Aim Final Plans Book
 
Wedding Pp For Email
Wedding Pp For EmailWedding Pp For Email
Wedding Pp For Email
 

Similar to 2010 uci douglas hospital team platinum award by bdc

project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxssuser5fc1e7
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxLisa Cooley, LEED AP
 
Keep your project moving with aconex contract administration webinar slides
Keep your project moving with aconex contract administration webinar slidesKeep your project moving with aconex contract administration webinar slides
Keep your project moving with aconex contract administration webinar slidesAconex
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability EngineerAngela Lopez
 
Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioningjeff_ranson
 
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote Shanti Pless
 
Optimize Process Management to Improve Business Outcomes - Webinar, September...
Optimize Process Management to Improve Business Outcomes - Webinar, September...Optimize Process Management to Improve Business Outcomes - Webinar, September...
Optimize Process Management to Improve Business Outcomes - Webinar, September...Aconex
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Bonny Resume ( Proc)
Bonny Resume ( Proc)Bonny Resume ( Proc)
Bonny Resume ( Proc)Bonny Sam
 
Smart Agreements and Green Litigation Risks
Smart Agreements and Green Litigation RisksSmart Agreements and Green Litigation Risks
Smart Agreements and Green Litigation RisksScott Wolfe
 
BDC Leed Commissioning Presentation
BDC Leed Commissioning PresentationBDC Leed Commissioning Presentation
BDC Leed Commissioning PresentationBDC Engineering
 
COST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptxCOST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptxabedamtie
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy systempriyang2004
 
glossary-of-construction-terms.pdf
glossary-of-construction-terms.pdfglossary-of-construction-terms.pdf
glossary-of-construction-terms.pdfCarlStevenAtencio
 
Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)Dylan Gonsalves
 

Similar to 2010 uci douglas hospital team platinum award by bdc (20)

project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
Keep your project moving with aconex contract administration webinar slides
Keep your project moving with aconex contract administration webinar slidesKeep your project moving with aconex contract administration webinar slides
Keep your project moving with aconex contract administration webinar slides
 
Innovation technique in construction
Innovation technique in constructionInnovation technique in construction
Innovation technique in construction
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
 
Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioning
 
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
 
Optimize Process Management to Improve Business Outcomes - Webinar, September...
Optimize Process Management to Improve Business Outcomes - Webinar, September...Optimize Process Management to Improve Business Outcomes - Webinar, September...
Optimize Process Management to Improve Business Outcomes - Webinar, September...
 
REEP[1]
REEP[1]REEP[1]
REEP[1]
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Bonny Resume ( Proc)
Bonny Resume ( Proc)Bonny Resume ( Proc)
Bonny Resume ( Proc)
 
2013 Federal D-B Downsized
2013 Federal D-B Downsized2013 Federal D-B Downsized
2013 Federal D-B Downsized
 
Smart Agreements and Green Litigation Risks
Smart Agreements and Green Litigation RisksSmart Agreements and Green Litigation Risks
Smart Agreements and Green Litigation Risks
 
BDC Leed Commissioning Presentation
BDC Leed Commissioning PresentationBDC Leed Commissioning Presentation
BDC Leed Commissioning Presentation
 
AEC Controls SOQ
AEC Controls SOQAEC Controls SOQ
AEC Controls SOQ
 
COST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptxCOST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptx
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
glossary-of-construction-terms.pdf
glossary-of-construction-terms.pdfglossary-of-construction-terms.pdf
glossary-of-construction-terms.pdf
 
BDC LEED Cx Preso
BDC LEED Cx PresoBDC LEED Cx Preso
BDC LEED Cx Preso
 
Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)
 

Recently uploaded

The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Recently uploaded (20)

The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 

2010 uci douglas hospital team platinum award by bdc

  • 2. BUILDING TEAM OWNER / DEVELOPER ARCHITECT INTERIOR ARCHITECT (KITCHENS) STRUCTURAL ENGINEER MECHANICAL ENGINEER ELECTRICAL ENGINEER PLUMBING ENGINEER GENERAL CONTRACTOR University of California, Irvine Hellmuth, Obata + Kassabaum, Inc. Dave Keaggy & Associates Nabih Youseff & Associates TMAD-Taylor & Gaines TMAD-Taylor & Gaines TMAD-Taylor & Gaines Hensel Phelps Construction Co.
  • 3. ACCOLADE “We’re out here doing our inspections and observations as we always do. What’s different is the effort by the Owner, the Architect and the Contractor … all working together to make it happen.” Tom Crowder OSHPD Regional Compliance Officer
  • 5. BUDGET HISTORY November 2000 January 2003 February 2004 June 2004 Sept/Oct 2004 December 2004 January 2005 September 2008 UC Regents set aside $235M Lease Revenue Bonds for a Replacement Hospital UC Regents certify the EIR and approve a $243M Construction Budget Lowest Bid exceeds Construction Budget by 25% UC Regents establish a Maximum Acceptance Cost (MAC) of $250M UC Regents establish a MAC for additional Scope of Work (Even more scope of work is added to the project at a later date) Second Bid $246M ($4Mbelow$250M MAC) Project is awarded with added scope of work (Ultimately the scope of work reaches $285M) Notice to Proceed is issued to the Design-Build Contractor OSHPD issues Certificate of Occupancy (4 months early) Project is completed for $283M ($2M below cost ceiling) Project savings extend beyond construction costs: Due to early construction completion, no claims, savings in equipment purchasing, and other project management efficiencies, UCI Project Team returns $26M to the University.
  • 7.
  • 8. Secondly, there are only a few mechanical, electrical and plumbing (MEP) subcontractors that can handle a mega-project of this scale, where MEP systems represent more than 50 percent of the total construction budget.
  • 9. Contractors were fearful of the risks associated with the job: experiences on other UC campuses, OSHPD changes in the field, and the sudden, escalating market volatility.
  • 10.
  • 11. It has been used by the federal government to build all types of construction, including power plants and hospitals.
  • 12.
  • 13. OSHPD has adopted a policy of support for design-build.* Ref. Rand Corporation, April 2004
  • 14.
  • 15. Architectural plans revised to reflect all floor plan and elevation changes.
  • 16. Pre-qualification requirements relaxed for 10 subcontractor trades.
  • 18. Bid documents streamlined from 58 alternates to 3.
  • 19. Technical submittal requirements reduced by 70 percent.
  • 20. Field information and decision making process with OSHPD streamlined to reduce risks.
  • 21.
  • 22. Another independent cost estimator was hired to prepare sealed cost estimate to be opened at time of bid.
  • 23. Third-party general contractor to review subcontractor bids and provide advice during BAFO negotiations.
  • 24.
  • 26. Opt for precast building skin in lieu of stone
  • 27. Save 1,600 tons of steel by introducing seismic bracing
  • 28. Delete roof-mounted cooling towers in favor of air-cooled towers on the ground
  • 29. Delete mechanical space on 3rd floor by placing OR air handlers in the basement
  • 30. Delete a planned campus circulation arcade from scope
  • 31. Defer roof-top gardens to a future project
  • 32. Defer outdoor dining to Phase 2 Project
  • 33. Defer future growth TIs to Phase 2 Project
  • 34. $35M saved by the VE Process
  • 35. $23M deferred to future projects
  • 36.
  • 41. ACCOLADE Design Build Institute of America awarded our project its most prestigious Western Pacific Region Award for a large public building
  • 42. IPD TEAM DYNAMICS
  • 43. COMPARE Traditional Project Delivery Integrated Project Delivery Our project’s Design-Build Integrated Project Delivery
  • 44.
  • 45. DBIA Design Build Best Project Award, Merit Award, and Excellence Award
  • 46.
  • 47. IPD TEAM DYNAMICS DELIVERS WINDFALL VE moved OR air handlers to the Basement VE modified the structural design TEAM reconfigured the foundation system and created a full building footprint basement TEAM created 27,000SF Bonus Shell Space for a new Radiology Department in Phase 2
  • 48.
  • 49. New design solutions that are feasible only in a 3D environment:
  • 50. Pre-fabricated supports for OR booms and lights
  • 51. Pre-fabricated universal structural support for all ceiling and ceiling mounted building systems at OR interstitial spaceMedical gas trees pre-assembled, tested and inspected at factory – another first for OSHPD Enhanced and better coordinated effort with highly committed staff completes the effort in record time
  • 52. IPD VALUE TO THE DESIGN PROCESS The Design-Build contractual framework enabled an integrated, interdisciplinary process that achieved LEAN characteristics: Impeccable coordination: Each of the Engineers of Record came to the design table with their respective major subcontractors and all the vendors and vendors’ engineers. Vendors and contractors designed and resolvedthe constructability of all the designs and construction/installation details they had a vested interest in. Their designs and drawings were directly incorporated in the Permit Set – no deferred approvals. Project as Production System:The incremental design and permit process, the just-in-time documents delivery schedule, the concerted effort to anticipate and mitigate risk through design coordination, by necessity, focused the team to design jointly to exacting tolerancesand embrace pre-fabricationto an unprecedented level under OSHPD. Project as Collective Enterprise:The Mission Controlmetaphor provides a very accurate image of what took place daily in design, coordination, constructability, plan review, schedule, budget, and QC sessions that took place in the job-site trailer from day one until the Certificate of Occupancy was obtained.
  • 53.
  • 54. Close coordination between main frame structural designers, stone subcontractor, structural engineers for the for the steel stud systems, light gauge steel subcontractor, specialty steel and glass vendors, and the rest of the team at large.
  • 55. All stone pieces (up to 4 inch thick) have soft joints to allow individual movement in case of a seismic event.
  • 56. All the fabricator details are part of the permit.
  • 57. Creative solution made possible by the collaborative effort.
  • 59.
  • 60. Creative solution made possible by collaborative effort with vision beyond first cost.
  • 61. Project-wide, the crane concept cost $350k more than the typical install, BUT made the above ceiling coordination effort much more manageable, saving costs for those activities.
  • 62. Mechanical systems manufactured off-site to precise tolerances
  • 64. Installed in reduced time on-siteA TYPICAL HOSPITAL APPLICATION
  • 65.
  • 66. Creative solution made possible by collaborative effort
  • 68. Manufactured off-site to precise tolerances.
  • 69. Legs installed first. Then ductwork, electrical and medical gas systems.
  • 70. Afterwards, the inverted table is assembled on the floor, lifted with 4 forklifts, positioned with lasers, and welded in place.
  • 71.
  • 72.
  • 76. Pride investment by all participating team members creates an environment of excellence.
  • 77. Each panel was hand-painted with grout during the assembly process.
  • 78. Integral Repel-Plus instead of topical application.
  • 79.
  • 80. Reduced construction time through panelization
  • 81. Panels cast off-site to precise tolerances.
  • 82. Precast panelization was approved early with NO deferred approvals.
  • 83. Collaboration and review made possible three distinct panel assemblies.
  • 84.
  • 85. Conflicts in the field were avoided
  • 86. Material take offs reduce waste
  • 87. Increased speed & coordination during installation
  • 88.
  • 89. Manufactured off-site to precise tolerances
  • 90.
  • 91. The VE reduced floor height from 18’ to 15’
  • 92. The Gusset Plates block 60% of the above ceiling space in the corridors.
  • 93.
  • 94. More than 11,000 conflicts were identified and resolved.
  • 95. Each Field Conflict = minimum 2 week delay
  • 99. Type of Conflicts caught and corrected:
  • 100. ADA clearances in Med Surg bathrooms
  • 101. Cable trays & ductwork
  • 102. Wall and door conflicts
  • 103. The valves at roof air handlers
  • 104. The sizing of valves at Basement Mechanical Room
  • 105.
  • 107. ACCOLADE “On many projects, our role as a regulatory agency results in adversarial relationships. The UCI Hospital is a success in no small part due to the efforts put forth by Hensel Phelps and their sub-contractors, with the support and guidance of UCI.” Gary Dunger OSHPD Chief Fire Life Safety Officer
  • 108.
  • 109. UCI visited and consulted with other UC Campuses to learn from their hospital building experience, and of their working relationships with OSHPD.
  • 110.
  • 111. UCI and OSHPD committed to a design submittal schedule.
  • 112.
  • 113. To manage and coordinate all OSHPD related activities: change orders, weekly site visits, etc.
  • 114.
  • 115. UCI staffed the review team with professional architects and engineers.
  • 116. UCI’s in-house Quality Assurance teamprocessed all RFIs in a prompt manner.
  • 117.
  • 118. So did the Architect of Record and the Structural Engineer of Record.
  • 119.
  • 120. UCI hired a Lead IOR with extensive experience to lead a team of five IORs approved by OSHPD.
  • 121. A web based inspection request process was designed by the University for DB team to submit and track inspections.
  • 122.
  • 123. Avoided the need for OSHPD to keep the project open and susceptible to additional scrutiny and delays for a Construction Final.
  • 124. UCI’s IORs, the Design-Builder and OSHPD staff collaborated to staff appropriately and schedule the sequence for all the inspection activities to a very tight timetable. For example, fire alarm testing required 15 people for several days.
  • 125. OSHPD allowed all other UCI Campus IORs with OSHPD certification to join the inspection team.
  • 126. In the last three weeks, OSHPD Chief Fire Life Safety Officer dispatched six Fire Marshal Academy staff to conduct fire alarm, door contact hardware, stair pressurization and above ceiling fire stopping inspections.
  • 127.
  • 142. INTERIORS GRAND LOBBY MEDITATION ROOM DONOR WALL ADMINISTRATION WAITING
  • 143. INTERIORS TYPICAL NICU PATIENT ROOM NICU NURSE STATION TYPICAL MED-SURG PATIENT ROOM NURSE STATION
  • 144. INTERIORS REGISTRATION WAITING WAITING FOOD SERVICE
  • 146. ACCOLADE “It has been a pleasure to be part of a project that truly epitomizes the concept of partnering.” Gary Dunger OSHPD Chief Fire Life Safety Officer
  • 147. WINNER OF THE 2010 PLATINUM AWARD “Congratulations!   Judging has been completed for BD+C’s 13th Annual Building Team Awards, and our expert panel of judges—architects, engineers, contractors, and educators—have selected Douglas Hospital for a Platinum Award.   The winning projects will be featured in BD+C’s May 2010 issue.” Jay W. Schneider Senior Editor, Building Design+Construction REED CONSTRUCTION MEDIA “On April 16, 2010, we announced the closure of the remaining publishing brands and their associated products and services. Consequently, the April 2010 issue was the final issue of Building Design & Construction and our web sites will cease operating as of April 30, 2010.” The Staff of Building Design & Construction