SlideShare a Scribd company logo
1 of 30
Download to read offline
Project 2 Presentation
Multi-Area Economic Dispatch Performance Using Swarm
Intelligence Technique
Student Name: Kelvin Yong Hong Chien
Student ID : MKE161159
Supervisor : Dr. Mohd Hafiz Bin Habibuddin
Content
1. Introduction
2. Problem Statement
3. Literature Review
4. Research Objectives
5. Scope of work
6. Research Methodology
7. Result
8. Conclusion
Introduction
Single Area Economic Dispatch Multi Area Economic Dispatch
Minimised fuel cost Minimised fuel cost without violating
tie-line power transfer
No interconnection between areas Tie-line constraint and area power
balance requirement
Depends on stability of generators Less gen. cost, max reliability, reserve
sharing and improved stability
Introduction
• Multi Area Economic Dispatch determine optimal
value of power generation and interchange of power
through tie-lines interconnecting areas minimized
fuel cost.
• In previous paper is using PSO but consideration is
only on single area economic dispatch. The tie-line is
not implemented.
• Number of tie-line and power transfer limit will
determine the stability and cost of production.
Problem Statement
• In paper [1], multi area economic dispatch using PSO
yields better generation cost compared to
Evolutionary Programming (EP) only. There is no
comparison between Genetic Algorithm (GA) without
consideration of losses.
• In paper [2], PSO is used to solve non-linear problem
with comparison between GA but without
considering the multi area.
Literature Review
Author/ Year/ Method Analysis Advantage/ Disadvantage
(M. K. M. Zamani, et. al.
2017)
Multi-Area Economic
Dispatch Performance
Using Swarm Intelligence
Technique Considering
Voltage Stability
PSO is employed. The algorithm is
tested on a 2-area 48-bus power
system with different case studies.
Variation in active power loading in
achieving an optimal solution is also
considered in this study.
PSO yields better results
as compared to the EP.
There is no comparison
between GA and PSO.
(Zwe-Lee Gaing, 2003)
Particle Swarm
Optimization to Solving the
Economic Dispatch
Considering the Generator
Constraints
Comparison between GA and PSO
using test set of 6 units, 15 units and
40 units with consideration of ramp
rate limits, prohibited operating zone
and non smooth cost function.
PSO yields better results
as compared to the GA.
There is no element of
multi area.
Literature Review
Author/ Year/ Method Analysis Advantage/ Disadvantage
(M. Mohammadian. et. al.
2018)
Optimization of single and
multi-areas economic
dispatch problems based
on evolutionary particle
swarm optimization
algorithm.
E PSO is designed to solve constraints
namely: valve-point effects,
prohibited operating zones, multiple
fuel usage, dynamic ramp rate limits,
transmission losses, tie-line capacity
and spinning reserve. MAED cases:
10 units, 3 tie-line and 40 units, 6 tie-
line
E PSO yields better results
as compared to the EP,
RCGA and PSO. There is no
direct comparison
between GA and PSO.
(A. V. V. Sudhakar, et. al.
2014)
Differential evolution for
solving multi area
economic dispatch
DE is employed. The algorithm is
tested on a 2-area 2units each, 4-area
4 units each and 120 units.
Comparison with Hybrid Neural
Network and EP.
DE yields best result.
However, the transmission
losses is not considered
Literature Review
Author/ Year/ Method Analysis Advantage/ Disadvantage
(M. P. Musau, N. A. O. C. W.
Wekesa 2010)
Multi area multi objective
dynamic economic dispatch
with renewable energy and
emissions
5 objective includes thermal,
renewable, tie line losses and
emissions, other constraints
RE is modeled using scenario based
method (SBM). Modified Firefly
Algorithm with Levy Flights and
Derived Mutation (MFA-LF-DM)
which is applied to validate
optimality condition decomposition
(OCD) in terms of cost and emission
reduction.
Frequent cycling by
thermal generating unit
causes thermal and
pressure stresses.
Renewable energy reserve
is for high penetration of
RE which in Malaysia still
not suitable.
(M. Basu / 2016 )
Quasi-oppositional group
search optimization for
multi-area dynamic
economic dispatch
2 case studies:
(a) multi area dynamic economic
dispatch with valve point loading,
and transmission losses
(b) multi area dynamic economic
dispatch with valve point loading
multiple fuel sources, and
transmission losses.
Method: QOGSO, GSO, GSA, BBO, DE,
Cost function of PSO is not
cheap, but the processing
time is faster.
Research Objectives
1
• To develop the multi-area economic model considering
tie-line capacity, generator limit, transmission line losses
and power balance as constraints.
2
• To optimize the model using algorithm of Particle Swarm
Optimization (PSO) using 2 area network with 3 different
case studies.
3
• To validate the efficiency by analysing between PSO and
GA in producing the generation cost and convergence
time
Scope of Work
• Proposed method to consider duration of simulation,
CPU time (Sec.) as one of the benchmark in
determining the efficiency of the system.
• Conduct the optimization of the model using Particle
Swarm Optimization (PSO).
• Conduct experiment using data of 4 units, 6 units
and 40 units system and simulate in MATLAB R2013a.
• For comparison, the same database are tested on
simple PSO and GA.
Methodology – Design MAED
Start
Determine the area
power demand
Sets the amount of power
flow through tie-line
(import/export) from Area A
Calculate output
power by PSO / GA
Model
simulation
error?
Yes
No
Evaluation:
Comparison of PSO and GA in
fuel cost and power output
generated
Check if
result can
be accept?
End
* All three case studies are using the same flow
Methodology –
Flow Chart for PSO
Case Studies
Case
studies
No. of Gen
(Area 1)
No. of Gen
(Area 2)
Tie-line limit
Transmission
line losses
Case 1 2 Units 2 Units 200MW No
Case 2 3 Units 3 Units 80MW Yes
Case 3 25 Units 15 Units 1000MW No
PSO & GA Parameters
Parameters Value
Initial position Random
Population size 50
Number of iterations 300
Acceleration constants:
C1, C2
2,2
Inertia weight:
Wmin - Wmax
0.4,0.9
Particle Swarm Optimization Genetic Algorithm
Parameters Value
Population size 50
Number of generations 300
Crossover rate, Pc 0.8
Mute rate, Pm 0.01
Crossover parameter, a 0.5
Result – Case 1: 4 Units [4]
Area Unit a
(RM)
b
(RM/MW)
c
(RM/MW2)
Pmin
(MW)
Pmax
(MW)
1 1 561 7.92 0.001562 150 600
2 78 7.97 0.00482 50 200
2 1 310 7.85 0.00194 100 400
2 250 7.50 0.00184 70 340
Fuel Cost
Tie-line: 200MW
B to A
Area A Area B
GenGen
Gen
Gen
PD1=721MW
P1=521MW
PD2=309MW
P2=509MW
Area A is buying 200 MW from Area B.
Result – Case 1: 4 Units [4]
Case 1
Area 1 Area 2
P1(MW) P2(MW) P1(MW) P2(MW)
Output powers (MW) – PSO 402.14 118.86 224.2 284.8
Output powers (MW) - GA 396.66 124.34 201.27 307.73
Generation (MW) 521 509
Area power demand (MW) 721 309
Fuel cost (RM/MW) per area – PSO 5092 4702.7
Fuel cost (RM/MW) per area - GA 5092 4700
Power flow (MW) Import (200MW) Export (200MW)
Items PSO GA
Total Fuel Cost (RM) 9785.97 9792.00
Time Convergence (s) 1.20 3.25
Summary – Result Simulation
Result – Case 2: 6 Units with losses
Area Unit a
(RM)
b
(RM/MW)
c
(RM/MW2)
Pmin
(MW)
Pmax
(MW)
1 1 550 8.10 0.00028 100 500
2 350 7.50 0.00056 50 200
3 310 8.10 0.00056 50 150
2 1 240 7.74 0.00324 80 300
2 200 8.00 0.00254 50 200
3 126 8.60 0.00284 50 120
Fuel Cost
B Coefficient Area 1 B Coefficient Area 2
Result – Case 2: 6 Units with losses
Tie-line: 80MW
A to B
Area A Area B
GenGen
Gen
Gen
PD1=770MW
P1=850MW
PD2=700MW
P2=620MW
GenGen
Losses
Losses
Area A is selling 80 MW to Area B.
Result – Case 2: 6 Units with losses
Case 2
Area 1 Area 2
P1(MW) P2(MW) P3(MW) P1(MW) P2(MW) P3(MW)
Output powers (MW) – PSO 500 200 150 300 200 120
Output powers (MW) - GA 500 200 150 300 200 120
Generation (MW) 850 620
Area power demand (MW) 770 700
Fuel cost (RM/MW) per area – PSO 8084.5 5959.7
Fuel cost (RM/MW) per area - GA 9022.7 6766.6
Power flow (MW) Export (80MW) Import (80MW)
Power losses (MW) – PSO
Power losses (MW) – GA
9.3818
9.4268
8.0693
8.1253
Items PSO GA
Total Fuel Cost (RM) 14044.20 15789.30
Total Power Losses (MW) 17.4511 17.5521
Time Convergence (s) 1.56 3.60
Summary – Result Simulation
Result – Case 3 [2]: 40 Units (Taipower)
Tie-line: 1000MW
A to B
Area A Area B
Gen
27
Gen
3
Gen
40
Gen
25
PD1=6350MW
P1=7350MW
PD2=3150MW
P2=2150MW
Gen
26Gen
2
Gen
1
.
.
.
.
.
.
Area A is selling 1000 MW to Area B.
Result –
Case 3 [2]:
40 Units
(Taipower)
Case 3
Area 1 Area 2
No. Gen
Generation
(MW) - PSO
Generation
(MW) - GA
No. Gen
Generation
(MW) - PSO
Generation
(MW) - GA
Output powers
(MW)
1 113.30 92.65 26 453.13 398.04
2 98.48 94.71 27 14.95 44.14
3 116.88 200.03 28 21.32 63.76
4 142.73 28.63 29 37.55 5.82
5 86.50 10.73 30 80.29 148.89
6 74.66 210.38 31 153.86 222.92
7 240.29 31.12 32 163.78 222.92
8 228.35 88.79 33 70.64 222.92
9 181.60 88.47 34 155.05 92.24
10 255.92 43.89 35 197.26 116.58
11 154.81 125.04 36 144.15 116.58
12 227.72 340.06 37 52.31 143.74
13 250.84 247.15 38 37.99 96.00
14 181.70 772.98 39 81.97 35.42
15 396.65 635.99 40 485.74 220.03
16 231.15 564.02
17 499.00 565.98
18 480.54 283.52
19 484.12 175.08
20 445.35 65.52
21 545.37 623.71
22 548.03 720.45
23 434.25 119.82
24 547.00 419.96
25 384.77 801.32
Generation (MW) 7350 2150
Area power demand
(MW)
6350 3150
Fuel cost (RM/MW) 87342 96100 24010 35097
Power flow (MW) Export (1000MW) Import (1000MW)
Result – Case 3 [2]: 40 Units
(Taipower)
Items PSO GA
Total Fuel Cost (RM) 112388.57 120000.00
Time Convergence (s) 4.10 6.23
Summary – Result Simulation
Result – Case 3: 40 Units
Area 1 Area 2
PSO
GA
Simulation Result - Summary
Items PSO GA
Total Fuel Cost (RM) 9785.97 9792.00
Time Convergence (s) 1.20 3.25
Items PSO GA
Total Fuel Cost (RM) 112388.57 120000.00
Time Convergence (s) 4.10 6.23
Items PSO GA
Total Fuel Cost (RM) 14044.20 15789.30
Total Power Losses (MW) 17.4511 17.5521
Time Convergence (s) 1.56 3.60
Case 1
Case 2
Case 3
Simulation Result - Summary
0
20000
40000
60000
80000
100000
120000
140000
4 Unit 6 Unit 40 Unit
Comparison of Fuel Cost for Three
Case Studies
PSO GA
0
1
2
3
4
5
6
7
4 Unit 6 Unit 40 Unit
Comparison of Convergence Time for
Three Case Studies
PSO GA
Discussion
• PSO perform better than GA. PSO in some cases
provides not accurate fuel cost due to effect of ramp
rate
• Case studies above only considered transmission
losses because this study focus on getting fast
estimated value where PSO has performed well
Conclusion
• Proposed method (PSO economic dispatch)
performs better performance than GA in multi
area environment
• PSO has short convergence time as compared
to GA
• Suggestion to conduct the experiment by
considering: ramp rate, valve-point effect,
reserve, distributed generation (wind turbine
or solar PV) in future work
References
1. M. K. M. Zamani, et. al., “Multi-Area Economic Dispatch Performance
Using Swarm Intelligence Technique Considering Voltage Stability”, in
Advanced Science Engineering Information Technology, Vol 7. 2017.
2. Zwe-Lee Gaing, “Particle Swarm Optimization to Solving the Economic
Dispatch Considering the Generator Constraints”, IEEE Transaction, 2003.
3. M. Mohammadian. et. al., “Optimization of single and multi-areas
economic dispatch problems based on evolutionary particle swarm
optimization algorithm.”, IEEE Transaction, 2018.
4. A. V. V. Sudhakar, et. al. “Differential evolution for solving multi area
economic dispatch”, 2014.
5. M. P. Musau, N. A. O. C. W. Wekesa, “Multi Area Multi Objective Dynamic
Economic Dispatch with Renewable Energy and Emissions”, in IEEE, 2016.
References
6. X. Xia, A. M. Elaiw., “Optimal dynamic economic dispatch of generation:
A review”, in Electric Power System Research, 2010.
7. M. Pandit, et. al., “Large Scale Multi-area Static / Dynamic Economic
Dispatch using Nature Inspired Optimization”, Springer, 2016.
8. M. Basu, “Quasi-oppositional group search optimization for multi-area
dynamic economic dispatch”, in Electrical Power and Energy System,
Science direct, 2016.
9. Vinay K. Jadouna et. al., “Multi-area Economic Dispatch using Improved
Particle Swarm Optimization”, The 7th International Conference on
Applied Energy – ICAE2015, Science direct, 2015.
Thank You
Question & Answer

More Related Content

What's hot

Economic Load Dispatch Optimization of Six Interconnected Generating Units Us...
Economic Load Dispatch Optimization of Six Interconnected Generating Units Us...Economic Load Dispatch Optimization of Six Interconnected Generating Units Us...
Economic Load Dispatch Optimization of Six Interconnected Generating Units Us...IOSR Journals
 
GWO-based estimation of input-output parameters of thermal power plants
GWO-based estimation of input-output parameters of thermal power plantsGWO-based estimation of input-output parameters of thermal power plants
GWO-based estimation of input-output parameters of thermal power plantsTELKOMNIKA JOURNAL
 
Compromising between-eld-&-eed-using-gatool-matlab
Compromising between-eld-&-eed-using-gatool-matlabCompromising between-eld-&-eed-using-gatool-matlab
Compromising between-eld-&-eed-using-gatool-matlabSubhankar Sau
 
Performance prediction of PV & PV/T systems using Artificial Neural Networks ...
Performance prediction of PV & PV/T systems using Artificial Neural Networks ...Performance prediction of PV & PV/T systems using Artificial Neural Networks ...
Performance prediction of PV & PV/T systems using Artificial Neural Networks ...Ali Al-Waeli
 
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...paperpublications3
 
Study of using particle swarm for optimal power flow
Study of using particle swarm for optimal power flowStudy of using particle swarm for optimal power flow
Study of using particle swarm for optimal power flowMohamed Abuella
 
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...IJERD Editor
 
Project on economic load dispatch
Project on economic load dispatchProject on economic load dispatch
Project on economic load dispatchayantudu
 
AN EFFICIENT COUPLED GENETIC ALGORITHM AND LOAD FLOW ALGORITHM FOR OPTIMAL PL...
AN EFFICIENT COUPLED GENETIC ALGORITHM AND LOAD FLOW ALGORITHM FOR OPTIMAL PL...AN EFFICIENT COUPLED GENETIC ALGORITHM AND LOAD FLOW ALGORITHM FOR OPTIMAL PL...
AN EFFICIENT COUPLED GENETIC ALGORITHM AND LOAD FLOW ALGORITHM FOR OPTIMAL PL...ijiert bestjournal
 
Economic/Emission Load Dispatch Using Artificial Bee Colony Algorithm
Economic/Emission Load Dispatch Using Artificial Bee Colony AlgorithmEconomic/Emission Load Dispatch Using Artificial Bee Colony Algorithm
Economic/Emission Load Dispatch Using Artificial Bee Colony AlgorithmIDES Editor
 
Economic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration MethodEconomic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration MethodIOSR Journals
 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Pritesh Priyadarshi
 
Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...
Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...
Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...IJMERJOURNAL
 
WFSA_IDETC_2013_Weiyang
WFSA_IDETC_2013_WeiyangWFSA_IDETC_2013_Weiyang
WFSA_IDETC_2013_WeiyangMDO_Lab
 
Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...
Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...
Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...IJECEIAES
 
OPTIMIZATION OF COST 231 MODEL FOR 3G WIRELESS COMMUNICATION SIGNAL IN SUBURB...
OPTIMIZATION OF COST 231 MODEL FOR 3G WIRELESS COMMUNICATION SIGNAL IN SUBURB...OPTIMIZATION OF COST 231 MODEL FOR 3G WIRELESS COMMUNICATION SIGNAL IN SUBURB...
OPTIMIZATION OF COST 231 MODEL FOR 3G WIRELESS COMMUNICATION SIGNAL IN SUBURB...Onyebuchi nosiri
 
Economic dipatch
Economic dipatch Economic dipatch
Economic dipatch Doni Wahyudi
 
WFO_SDM_2012_Souma
WFO_SDM_2012_SoumaWFO_SDM_2012_Souma
WFO_SDM_2012_SoumaMDO_Lab
 

What's hot (19)

Economic Load Dispatch Optimization of Six Interconnected Generating Units Us...
Economic Load Dispatch Optimization of Six Interconnected Generating Units Us...Economic Load Dispatch Optimization of Six Interconnected Generating Units Us...
Economic Load Dispatch Optimization of Six Interconnected Generating Units Us...
 
GWO-based estimation of input-output parameters of thermal power plants
GWO-based estimation of input-output parameters of thermal power plantsGWO-based estimation of input-output parameters of thermal power plants
GWO-based estimation of input-output parameters of thermal power plants
 
Compromising between-eld-&-eed-using-gatool-matlab
Compromising between-eld-&-eed-using-gatool-matlabCompromising between-eld-&-eed-using-gatool-matlab
Compromising between-eld-&-eed-using-gatool-matlab
 
Performance prediction of PV & PV/T systems using Artificial Neural Networks ...
Performance prediction of PV & PV/T systems using Artificial Neural Networks ...Performance prediction of PV & PV/T systems using Artificial Neural Networks ...
Performance prediction of PV & PV/T systems using Artificial Neural Networks ...
 
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
 
Study of using particle swarm for optimal power flow
Study of using particle swarm for optimal power flowStudy of using particle swarm for optimal power flow
Study of using particle swarm for optimal power flow
 
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
 
Project on economic load dispatch
Project on economic load dispatchProject on economic load dispatch
Project on economic load dispatch
 
AN EFFICIENT COUPLED GENETIC ALGORITHM AND LOAD FLOW ALGORITHM FOR OPTIMAL PL...
AN EFFICIENT COUPLED GENETIC ALGORITHM AND LOAD FLOW ALGORITHM FOR OPTIMAL PL...AN EFFICIENT COUPLED GENETIC ALGORITHM AND LOAD FLOW ALGORITHM FOR OPTIMAL PL...
AN EFFICIENT COUPLED GENETIC ALGORITHM AND LOAD FLOW ALGORITHM FOR OPTIMAL PL...
 
Economic/Emission Load Dispatch Using Artificial Bee Colony Algorithm
Economic/Emission Load Dispatch Using Artificial Bee Colony AlgorithmEconomic/Emission Load Dispatch Using Artificial Bee Colony Algorithm
Economic/Emission Load Dispatch Using Artificial Bee Colony Algorithm
 
Experimental Verification of the main MPPT techniques for photovoltaic system
Experimental Verification of the main MPPT techniques for photovoltaic systemExperimental Verification of the main MPPT techniques for photovoltaic system
Experimental Verification of the main MPPT techniques for photovoltaic system
 
Economic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration MethodEconomic Dispatch of Generated Power Using Modified Lambda-Iteration Method
Economic Dispatch of Generated Power Using Modified Lambda-Iteration Method
 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment
 
Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...
Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...
Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...
 
WFSA_IDETC_2013_Weiyang
WFSA_IDETC_2013_WeiyangWFSA_IDETC_2013_Weiyang
WFSA_IDETC_2013_Weiyang
 
Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...
Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...
Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...
 
OPTIMIZATION OF COST 231 MODEL FOR 3G WIRELESS COMMUNICATION SIGNAL IN SUBURB...
OPTIMIZATION OF COST 231 MODEL FOR 3G WIRELESS COMMUNICATION SIGNAL IN SUBURB...OPTIMIZATION OF COST 231 MODEL FOR 3G WIRELESS COMMUNICATION SIGNAL IN SUBURB...
OPTIMIZATION OF COST 231 MODEL FOR 3G WIRELESS COMMUNICATION SIGNAL IN SUBURB...
 
Economic dipatch
Economic dipatch Economic dipatch
Economic dipatch
 
WFO_SDM_2012_Souma
WFO_SDM_2012_SoumaWFO_SDM_2012_Souma
WFO_SDM_2012_Souma
 

Similar to Multi Area Economic Dispatch

Quantum behaved artificial bee colony based conventional controller for opti...
Quantum behaved artificial bee colony based conventional  controller for opti...Quantum behaved artificial bee colony based conventional  controller for opti...
Quantum behaved artificial bee colony based conventional controller for opti...IJECEIAES
 
Solution of Combined Heat and Power Economic Dispatch Problem Using Different...
Solution of Combined Heat and Power Economic Dispatch Problem Using Different...Solution of Combined Heat and Power Economic Dispatch Problem Using Different...
Solution of Combined Heat and Power Economic Dispatch Problem Using Different...Arkadev Ghosh
 
Power extraction from wind energy..pptx
Power extraction from wind energy..pptxPower extraction from wind energy..pptx
Power extraction from wind energy..pptxXamilMurad
 
Power extraction from wind energy..pptx
Power extraction from wind energy..pptxPower extraction from wind energy..pptx
Power extraction from wind energy..pptxMuradulkabir
 
FYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdfFYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdfsauravdesignnedits
 
stability of power flow analysis of different resources both on and off grid
stability of power flow analysis of different resources both on and off gridstability of power flow analysis of different resources both on and off grid
stability of power flow analysis of different resources both on and off gridrehman1oo
 
Multi Area Economic Dispatch Using Secant Method and Tie Line Matrix
Multi Area Economic Dispatch Using Secant Method and Tie Line MatrixMulti Area Economic Dispatch Using Secant Method and Tie Line Matrix
Multi Area Economic Dispatch Using Secant Method and Tie Line MatrixIJAPEJOURNAL
 
Multi Objective Directed Bee Colony Optimization for Economic Load Dispatch W...
Multi Objective Directed Bee Colony Optimization for Economic Load Dispatch W...Multi Objective Directed Bee Colony Optimization for Economic Load Dispatch W...
Multi Objective Directed Bee Colony Optimization for Economic Load Dispatch W...IJECEIAES
 
Combining both Plug-in Vehicles and Renewable Energy Resources for Unit Commi...
Combining both Plug-in Vehicles and Renewable Energy Resources for Unit Commi...Combining both Plug-in Vehicles and Renewable Energy Resources for Unit Commi...
Combining both Plug-in Vehicles and Renewable Energy Resources for Unit Commi...IOSR Journals
 
COSTMODEL_IDETC_2010_Jie
COSTMODEL_IDETC_2010_JieCOSTMODEL_IDETC_2010_Jie
COSTMODEL_IDETC_2010_JieMDO_Lab
 
Multi objective economic load dispatch using hybrid fuzzy, bacterial
Multi objective economic load dispatch using hybrid fuzzy, bacterialMulti objective economic load dispatch using hybrid fuzzy, bacterial
Multi objective economic load dispatch using hybrid fuzzy, bacterialIAEME Publication
 
Optimal Operation of Wind-thermal generation using differential evolution
Optimal Operation of Wind-thermal generation using differential evolutionOptimal Operation of Wind-thermal generation using differential evolution
Optimal Operation of Wind-thermal generation using differential evolutionIOSR Journals
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportalatop007
 
HYBRID PARTICLE SWARM OPTIMIZATION FOR SOLVING MULTI-AREA ECONOMIC DISPATCH P...
HYBRID PARTICLE SWARM OPTIMIZATION FOR SOLVING MULTI-AREA ECONOMIC DISPATCH P...HYBRID PARTICLE SWARM OPTIMIZATION FOR SOLVING MULTI-AREA ECONOMIC DISPATCH P...
HYBRID PARTICLE SWARM OPTIMIZATION FOR SOLVING MULTI-AREA ECONOMIC DISPATCH P...ijsc
 
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineOptimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineIJAPEJOURNAL
 
Hybrid Particle Swarm Optimization for Solving Multi-Area Economic Dispatch P...
Hybrid Particle Swarm Optimization for Solving Multi-Area Economic Dispatch P...Hybrid Particle Swarm Optimization for Solving Multi-Area Economic Dispatch P...
Hybrid Particle Swarm Optimization for Solving Multi-Area Economic Dispatch P...ijsc
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET Journal
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET-  	  Optimal Generation Scheduling for Thermal UnitsIRJET-  	  Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET Journal
 
Solar Active Power Control 8th Final.pptx
Solar Active Power Control 8th Final.pptxSolar Active Power Control 8th Final.pptx
Solar Active Power Control 8th Final.pptxUsmanIftikhar41
 
Dynamic Economic Dispatch Problems: PSO Approach
Dynamic Economic Dispatch Problems: PSO ApproachDynamic Economic Dispatch Problems: PSO Approach
Dynamic Economic Dispatch Problems: PSO ApproachTELKOMNIKA JOURNAL
 

Similar to Multi Area Economic Dispatch (20)

Quantum behaved artificial bee colony based conventional controller for opti...
Quantum behaved artificial bee colony based conventional  controller for opti...Quantum behaved artificial bee colony based conventional  controller for opti...
Quantum behaved artificial bee colony based conventional controller for opti...
 
Solution of Combined Heat and Power Economic Dispatch Problem Using Different...
Solution of Combined Heat and Power Economic Dispatch Problem Using Different...Solution of Combined Heat and Power Economic Dispatch Problem Using Different...
Solution of Combined Heat and Power Economic Dispatch Problem Using Different...
 
Power extraction from wind energy..pptx
Power extraction from wind energy..pptxPower extraction from wind energy..pptx
Power extraction from wind energy..pptx
 
Power extraction from wind energy..pptx
Power extraction from wind energy..pptxPower extraction from wind energy..pptx
Power extraction from wind energy..pptx
 
FYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdfFYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdf
 
stability of power flow analysis of different resources both on and off grid
stability of power flow analysis of different resources both on and off gridstability of power flow analysis of different resources both on and off grid
stability of power flow analysis of different resources both on and off grid
 
Multi Area Economic Dispatch Using Secant Method and Tie Line Matrix
Multi Area Economic Dispatch Using Secant Method and Tie Line MatrixMulti Area Economic Dispatch Using Secant Method and Tie Line Matrix
Multi Area Economic Dispatch Using Secant Method and Tie Line Matrix
 
Multi Objective Directed Bee Colony Optimization for Economic Load Dispatch W...
Multi Objective Directed Bee Colony Optimization for Economic Load Dispatch W...Multi Objective Directed Bee Colony Optimization for Economic Load Dispatch W...
Multi Objective Directed Bee Colony Optimization for Economic Load Dispatch W...
 
Combining both Plug-in Vehicles and Renewable Energy Resources for Unit Commi...
Combining both Plug-in Vehicles and Renewable Energy Resources for Unit Commi...Combining both Plug-in Vehicles and Renewable Energy Resources for Unit Commi...
Combining both Plug-in Vehicles and Renewable Energy Resources for Unit Commi...
 
COSTMODEL_IDETC_2010_Jie
COSTMODEL_IDETC_2010_JieCOSTMODEL_IDETC_2010_Jie
COSTMODEL_IDETC_2010_Jie
 
Multi objective economic load dispatch using hybrid fuzzy, bacterial
Multi objective economic load dispatch using hybrid fuzzy, bacterialMulti objective economic load dispatch using hybrid fuzzy, bacterial
Multi objective economic load dispatch using hybrid fuzzy, bacterial
 
Optimal Operation of Wind-thermal generation using differential evolution
Optimal Operation of Wind-thermal generation using differential evolutionOptimal Operation of Wind-thermal generation using differential evolution
Optimal Operation of Wind-thermal generation using differential evolution
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transport
 
HYBRID PARTICLE SWARM OPTIMIZATION FOR SOLVING MULTI-AREA ECONOMIC DISPATCH P...
HYBRID PARTICLE SWARM OPTIMIZATION FOR SOLVING MULTI-AREA ECONOMIC DISPATCH P...HYBRID PARTICLE SWARM OPTIMIZATION FOR SOLVING MULTI-AREA ECONOMIC DISPATCH P...
HYBRID PARTICLE SWARM OPTIMIZATION FOR SOLVING MULTI-AREA ECONOMIC DISPATCH P...
 
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineOptimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
 
Hybrid Particle Swarm Optimization for Solving Multi-Area Economic Dispatch P...
Hybrid Particle Swarm Optimization for Solving Multi-Area Economic Dispatch P...Hybrid Particle Swarm Optimization for Solving Multi-Area Economic Dispatch P...
Hybrid Particle Swarm Optimization for Solving Multi-Area Economic Dispatch P...
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET-  	  Optimal Generation Scheduling for Thermal UnitsIRJET-  	  Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
Solar Active Power Control 8th Final.pptx
Solar Active Power Control 8th Final.pptxSolar Active Power Control 8th Final.pptx
Solar Active Power Control 8th Final.pptx
 
Dynamic Economic Dispatch Problems: PSO Approach
Dynamic Economic Dispatch Problems: PSO ApproachDynamic Economic Dispatch Problems: PSO Approach
Dynamic Economic Dispatch Problems: PSO Approach
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEslot gacor bisa pakai pulsa
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĂŁo Esperancinha
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

Multi Area Economic Dispatch

  • 1. Project 2 Presentation Multi-Area Economic Dispatch Performance Using Swarm Intelligence Technique Student Name: Kelvin Yong Hong Chien Student ID : MKE161159 Supervisor : Dr. Mohd Hafiz Bin Habibuddin
  • 2. Content 1. Introduction 2. Problem Statement 3. Literature Review 4. Research Objectives 5. Scope of work 6. Research Methodology 7. Result 8. Conclusion
  • 3. Introduction Single Area Economic Dispatch Multi Area Economic Dispatch Minimised fuel cost Minimised fuel cost without violating tie-line power transfer No interconnection between areas Tie-line constraint and area power balance requirement Depends on stability of generators Less gen. cost, max reliability, reserve sharing and improved stability
  • 4. Introduction • Multi Area Economic Dispatch determine optimal value of power generation and interchange of power through tie-lines interconnecting areas minimized fuel cost. • In previous paper is using PSO but consideration is only on single area economic dispatch. The tie-line is not implemented. • Number of tie-line and power transfer limit will determine the stability and cost of production.
  • 5. Problem Statement • In paper [1], multi area economic dispatch using PSO yields better generation cost compared to Evolutionary Programming (EP) only. There is no comparison between Genetic Algorithm (GA) without consideration of losses. • In paper [2], PSO is used to solve non-linear problem with comparison between GA but without considering the multi area.
  • 6. Literature Review Author/ Year/ Method Analysis Advantage/ Disadvantage (M. K. M. Zamani, et. al. 2017) Multi-Area Economic Dispatch Performance Using Swarm Intelligence Technique Considering Voltage Stability PSO is employed. The algorithm is tested on a 2-area 48-bus power system with different case studies. Variation in active power loading in achieving an optimal solution is also considered in this study. PSO yields better results as compared to the EP. There is no comparison between GA and PSO. (Zwe-Lee Gaing, 2003) Particle Swarm Optimization to Solving the Economic Dispatch Considering the Generator Constraints Comparison between GA and PSO using test set of 6 units, 15 units and 40 units with consideration of ramp rate limits, prohibited operating zone and non smooth cost function. PSO yields better results as compared to the GA. There is no element of multi area.
  • 7. Literature Review Author/ Year/ Method Analysis Advantage/ Disadvantage (M. Mohammadian. et. al. 2018) Optimization of single and multi-areas economic dispatch problems based on evolutionary particle swarm optimization algorithm. E PSO is designed to solve constraints namely: valve-point effects, prohibited operating zones, multiple fuel usage, dynamic ramp rate limits, transmission losses, tie-line capacity and spinning reserve. MAED cases: 10 units, 3 tie-line and 40 units, 6 tie- line E PSO yields better results as compared to the EP, RCGA and PSO. There is no direct comparison between GA and PSO. (A. V. V. Sudhakar, et. al. 2014) Differential evolution for solving multi area economic dispatch DE is employed. The algorithm is tested on a 2-area 2units each, 4-area 4 units each and 120 units. Comparison with Hybrid Neural Network and EP. DE yields best result. However, the transmission losses is not considered
  • 8. Literature Review Author/ Year/ Method Analysis Advantage/ Disadvantage (M. P. Musau, N. A. O. C. W. Wekesa 2010) Multi area multi objective dynamic economic dispatch with renewable energy and emissions 5 objective includes thermal, renewable, tie line losses and emissions, other constraints RE is modeled using scenario based method (SBM). Modified Firefly Algorithm with Levy Flights and Derived Mutation (MFA-LF-DM) which is applied to validate optimality condition decomposition (OCD) in terms of cost and emission reduction. Frequent cycling by thermal generating unit causes thermal and pressure stresses. Renewable energy reserve is for high penetration of RE which in Malaysia still not suitable. (M. Basu / 2016 ) Quasi-oppositional group search optimization for multi-area dynamic economic dispatch 2 case studies: (a) multi area dynamic economic dispatch with valve point loading, and transmission losses (b) multi area dynamic economic dispatch with valve point loading multiple fuel sources, and transmission losses. Method: QOGSO, GSO, GSA, BBO, DE, Cost function of PSO is not cheap, but the processing time is faster.
  • 9. Research Objectives 1 • To develop the multi-area economic model considering tie-line capacity, generator limit, transmission line losses and power balance as constraints. 2 • To optimize the model using algorithm of Particle Swarm Optimization (PSO) using 2 area network with 3 different case studies. 3 • To validate the efficiency by analysing between PSO and GA in producing the generation cost and convergence time
  • 10. Scope of Work • Proposed method to consider duration of simulation, CPU time (Sec.) as one of the benchmark in determining the efficiency of the system. • Conduct the optimization of the model using Particle Swarm Optimization (PSO). • Conduct experiment using data of 4 units, 6 units and 40 units system and simulate in MATLAB R2013a. • For comparison, the same database are tested on simple PSO and GA.
  • 11. Methodology – Design MAED Start Determine the area power demand Sets the amount of power flow through tie-line (import/export) from Area A Calculate output power by PSO / GA Model simulation error? Yes No Evaluation: Comparison of PSO and GA in fuel cost and power output generated Check if result can be accept? End * All three case studies are using the same flow
  • 13. Case Studies Case studies No. of Gen (Area 1) No. of Gen (Area 2) Tie-line limit Transmission line losses Case 1 2 Units 2 Units 200MW No Case 2 3 Units 3 Units 80MW Yes Case 3 25 Units 15 Units 1000MW No
  • 14. PSO & GA Parameters Parameters Value Initial position Random Population size 50 Number of iterations 300 Acceleration constants: C1, C2 2,2 Inertia weight: Wmin - Wmax 0.4,0.9 Particle Swarm Optimization Genetic Algorithm Parameters Value Population size 50 Number of generations 300 Crossover rate, Pc 0.8 Mute rate, Pm 0.01 Crossover parameter, a 0.5
  • 15. Result – Case 1: 4 Units [4] Area Unit a (RM) b (RM/MW) c (RM/MW2) Pmin (MW) Pmax (MW) 1 1 561 7.92 0.001562 150 600 2 78 7.97 0.00482 50 200 2 1 310 7.85 0.00194 100 400 2 250 7.50 0.00184 70 340 Fuel Cost Tie-line: 200MW B to A Area A Area B GenGen Gen Gen PD1=721MW P1=521MW PD2=309MW P2=509MW Area A is buying 200 MW from Area B.
  • 16. Result – Case 1: 4 Units [4] Case 1 Area 1 Area 2 P1(MW) P2(MW) P1(MW) P2(MW) Output powers (MW) – PSO 402.14 118.86 224.2 284.8 Output powers (MW) - GA 396.66 124.34 201.27 307.73 Generation (MW) 521 509 Area power demand (MW) 721 309 Fuel cost (RM/MW) per area – PSO 5092 4702.7 Fuel cost (RM/MW) per area - GA 5092 4700 Power flow (MW) Import (200MW) Export (200MW) Items PSO GA Total Fuel Cost (RM) 9785.97 9792.00 Time Convergence (s) 1.20 3.25 Summary – Result Simulation
  • 17. Result – Case 2: 6 Units with losses Area Unit a (RM) b (RM/MW) c (RM/MW2) Pmin (MW) Pmax (MW) 1 1 550 8.10 0.00028 100 500 2 350 7.50 0.00056 50 200 3 310 8.10 0.00056 50 150 2 1 240 7.74 0.00324 80 300 2 200 8.00 0.00254 50 200 3 126 8.60 0.00284 50 120 Fuel Cost B Coefficient Area 1 B Coefficient Area 2
  • 18. Result – Case 2: 6 Units with losses Tie-line: 80MW A to B Area A Area B GenGen Gen Gen PD1=770MW P1=850MW PD2=700MW P2=620MW GenGen Losses Losses Area A is selling 80 MW to Area B.
  • 19. Result – Case 2: 6 Units with losses Case 2 Area 1 Area 2 P1(MW) P2(MW) P3(MW) P1(MW) P2(MW) P3(MW) Output powers (MW) – PSO 500 200 150 300 200 120 Output powers (MW) - GA 500 200 150 300 200 120 Generation (MW) 850 620 Area power demand (MW) 770 700 Fuel cost (RM/MW) per area – PSO 8084.5 5959.7 Fuel cost (RM/MW) per area - GA 9022.7 6766.6 Power flow (MW) Export (80MW) Import (80MW) Power losses (MW) – PSO Power losses (MW) – GA 9.3818 9.4268 8.0693 8.1253 Items PSO GA Total Fuel Cost (RM) 14044.20 15789.30 Total Power Losses (MW) 17.4511 17.5521 Time Convergence (s) 1.56 3.60 Summary – Result Simulation
  • 20. Result – Case 3 [2]: 40 Units (Taipower) Tie-line: 1000MW A to B Area A Area B Gen 27 Gen 3 Gen 40 Gen 25 PD1=6350MW P1=7350MW PD2=3150MW P2=2150MW Gen 26Gen 2 Gen 1 . . . . . . Area A is selling 1000 MW to Area B.
  • 21. Result – Case 3 [2]: 40 Units (Taipower) Case 3 Area 1 Area 2 No. Gen Generation (MW) - PSO Generation (MW) - GA No. Gen Generation (MW) - PSO Generation (MW) - GA Output powers (MW) 1 113.30 92.65 26 453.13 398.04 2 98.48 94.71 27 14.95 44.14 3 116.88 200.03 28 21.32 63.76 4 142.73 28.63 29 37.55 5.82 5 86.50 10.73 30 80.29 148.89 6 74.66 210.38 31 153.86 222.92 7 240.29 31.12 32 163.78 222.92 8 228.35 88.79 33 70.64 222.92 9 181.60 88.47 34 155.05 92.24 10 255.92 43.89 35 197.26 116.58 11 154.81 125.04 36 144.15 116.58 12 227.72 340.06 37 52.31 143.74 13 250.84 247.15 38 37.99 96.00 14 181.70 772.98 39 81.97 35.42 15 396.65 635.99 40 485.74 220.03 16 231.15 564.02 17 499.00 565.98 18 480.54 283.52 19 484.12 175.08 20 445.35 65.52 21 545.37 623.71 22 548.03 720.45 23 434.25 119.82 24 547.00 419.96 25 384.77 801.32 Generation (MW) 7350 2150 Area power demand (MW) 6350 3150 Fuel cost (RM/MW) 87342 96100 24010 35097 Power flow (MW) Export (1000MW) Import (1000MW)
  • 22. Result – Case 3 [2]: 40 Units (Taipower) Items PSO GA Total Fuel Cost (RM) 112388.57 120000.00 Time Convergence (s) 4.10 6.23 Summary – Result Simulation
  • 23. Result – Case 3: 40 Units Area 1 Area 2 PSO GA
  • 24. Simulation Result - Summary Items PSO GA Total Fuel Cost (RM) 9785.97 9792.00 Time Convergence (s) 1.20 3.25 Items PSO GA Total Fuel Cost (RM) 112388.57 120000.00 Time Convergence (s) 4.10 6.23 Items PSO GA Total Fuel Cost (RM) 14044.20 15789.30 Total Power Losses (MW) 17.4511 17.5521 Time Convergence (s) 1.56 3.60 Case 1 Case 2 Case 3
  • 25. Simulation Result - Summary 0 20000 40000 60000 80000 100000 120000 140000 4 Unit 6 Unit 40 Unit Comparison of Fuel Cost for Three Case Studies PSO GA 0 1 2 3 4 5 6 7 4 Unit 6 Unit 40 Unit Comparison of Convergence Time for Three Case Studies PSO GA
  • 26. Discussion • PSO perform better than GA. PSO in some cases provides not accurate fuel cost due to effect of ramp rate • Case studies above only considered transmission losses because this study focus on getting fast estimated value where PSO has performed well
  • 27. Conclusion • Proposed method (PSO economic dispatch) performs better performance than GA in multi area environment • PSO has short convergence time as compared to GA • Suggestion to conduct the experiment by considering: ramp rate, valve-point effect, reserve, distributed generation (wind turbine or solar PV) in future work
  • 28. References 1. M. K. M. Zamani, et. al., “Multi-Area Economic Dispatch Performance Using Swarm Intelligence Technique Considering Voltage Stability”, in Advanced Science Engineering Information Technology, Vol 7. 2017. 2. Zwe-Lee Gaing, “Particle Swarm Optimization to Solving the Economic Dispatch Considering the Generator Constraints”, IEEE Transaction, 2003. 3. M. Mohammadian. et. al., “Optimization of single and multi-areas economic dispatch problems based on evolutionary particle swarm optimization algorithm.”, IEEE Transaction, 2018. 4. A. V. V. Sudhakar, et. al. “Differential evolution for solving multi area economic dispatch”, 2014. 5. M. P. Musau, N. A. O. C. W. Wekesa, “Multi Area Multi Objective Dynamic Economic Dispatch with Renewable Energy and Emissions”, in IEEE, 2016.
  • 29. References 6. X. Xia, A. M. Elaiw., “Optimal dynamic economic dispatch of generation: A review”, in Electric Power System Research, 2010. 7. M. Pandit, et. al., “Large Scale Multi-area Static / Dynamic Economic Dispatch using Nature Inspired Optimization”, Springer, 2016. 8. M. Basu, “Quasi-oppositional group search optimization for multi-area dynamic economic dispatch”, in Electrical Power and Energy System, Science direct, 2016. 9. Vinay K. Jadouna et. al., “Multi-area Economic Dispatch using Improved Particle Swarm Optimization”, The 7th International Conference on Applied Energy – ICAE2015, Science direct, 2015.