AT&T Turf Project
B&V PROJECT NO. 122000.0044
PREPARED FOR
AT&T Turf Project
18 MARCH 2014
CONFIDENTIAL ÂŽ
ÂŽ
ŠBlack & Veatch Holding Company 2013. All rights reserved.
2.
3. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Table of Contents
Overview ................................................................................................................... 5
Background ..................................................................................................................... 5
Generations of Development .......................................................................................... 6
Business Process / Functional Requirements ............................................................... 7
Requirements - SMART (Scope Management and Requisition Tool) ............................. 7
Glossary ........................................................................................................................... 8
B&V to AT&T Terminology Cross-Reference ................................................................... 8
Business Process Flows .............................................................................................. 9
Scope Management Overview ........................................................................................ 9
Sub Process Flows ......................................................................................................... 10
Initial Scoping for Bulk Projects ................................................................................ 10
Initial Scoping for Individual Projects ....................................................................... 11
Site Acq & Engineering Scope Changes .................................................................... 12
Initial Construction Scoping ...................................................................................... 13
Final Construction Scoping w/ Assign Vendors ......................................................... 14
PM-Created Construction Change Order with Assign Vendor .................................. 15
Vendor-Created Construction Change Order ........................................................... 16
Scoping Process / SMART Functional Requirements .................................................. 17
Assumptions .................................................................................................................. 17
A. Process new Jobs received from AT&T ................................................................. 18
1. Job Create / Select ............................................................................................ 18
B. Create Initial Bulk Scope Requests ........................................................................ 19
2. Initial Bulk Request Create ................................................................................ 19
C. Create Individual Scope Request .......................................................................... 20
3. Individual Request Create/Select ...................................................................... 21
4. Scope Maintenance â Add / Change ..................................................................... 24
D. Preview and Submit for NORAD Processing ......................................................... 30
5. Preview ............................................................................................................. 30
6. Attach / Upload Docs ........................................................................................ 32
7. Approve & Submit ............................................................................................. 34
E. Review and Submit to AT&T for PO ...................................................................... 34
8. NORAD OOM Entry & Record OOM ID ............................................................. 34
Overview of AT&T Processing ................................................................................... 35
F. Assign Work to Vendors ........................................................................................ 36
9. Assign Vendor ................................................................................................... 37
BLACK & VEATCH | Table of Contents i
4. Scope Management and Requisition Tool | AT&T Turf Project
10. Export VPOR .................................................................................................. 40
Maintenance & Supporting Processes ....................................................................... 42
Supporting Processes .................................................................................................... 42
User Information & Log on ....................................................................................... 42
Initial User Screen ..................................................................................................... 43
My Work Queue ........................................................................................................ 43
Build Templates ........................................................................................................ 44
Master Data .................................................................................................................. 45
Master Job & Site Information .................................................................................. 45
Master Contract Driver Information by Market ....................................................... 45
Master Contract WA Information by Market ........................................................... 46
Master Vendor Information ...................................................................................... 47
Master Job Information ............................................................................................ 47
Additional Reports ........................................................................................................ 48
Job Scope Reports: .................................................................................................... 48
Vendor Assignment ................................................................................................... 48
Integration .............................................................................................................. 49
Integration Considerations ........................................................................................... 49
Data Record Characteristics .......................................................................................... 49
Document Control.................................................................................................... 50
Reference documents & sample of current data files .................................................. 50
Appendix â Data Descriptions ................................................................................... 51
Master Job & Site Information ...................................................................................... 51
Job Selection ................................................................................................................. 52
Request Create/Select .................................................................................................. 53
User Driver Selection .................................................................................................... 54
User WA Selection......................................................................................................... 56
Master Contract WA Information ................................................................................. 58
Master Contract Driver Information ............................................................................. 59
Master Vendor Information .......................................................................................... 61
AT&T PO Request History ............................................................................................. 62
Vendor PO Request History .......................................................................................... 63
Scoping & Order Management Life Cycle ..................................................................... 64
Sample: Authority and Approval matrix ....................................................................... 65
ii MARCH 2014
5. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
LIST OF TABLES
Table 1: Request Type Values ........................................................................................... 22
Table 2: Request Status Values ......................................................................................... 22
Table 3 Function Type ....................................................................................................... 24
Table 4: Quantity Processing ............................................................................................ 25
Table 5: Previous Quantity Scenarios ............................................................................... 25
Table 6: Driver Rules ......................................................................................................... 26
Table 7 WA Category ........................................................................................................ 28
Table 8 PM Drivers ............................................................................................................ 29
Table 9 Report Options ..................................................................................................... 31
Table 10: Document Type Upload .................................................................................... 32
Table 11: NORAD Work Queue ......................................................................................... 34
Table 12: User Information ............................................................................................... 42
Table 13: Initial User Screen ............................................................................................. 43
Table 14: PM and Vendor Request Status Work Queue Flow .......................................... 44
LIST OF FIGURES
Figure 1: Scope & Order Mgmt High Level Flow ................................................................. 5
Figure 2: Today: Generation 0 Overview ............................................................................ 6
Figure 3: Scope Management Overview Process Flow ....................................................... 9
Figure 4: Initial Scoping for Bulk Projects ......................................................................... 10
Figure 5: Initial Scoping for Individual Projects ................................................................. 11
Figure 6: Site Acq & Engineering Scope Changes .............................................................. 12
Figure 7: Initial Construction Scoping ............................................................................... 13
Figure 8: Final Construction Scoping ................................................................................. 14
Figure 9: PM Initiated Change Order ................................................................................ 15
Figure 10: Vendor Initiated Change Order ........................................................................ 16
Figure 11: Scope Maintenance & Assign Vendor .............................................................. 17
Figure 12: Main Menu Example ........................................................................................ 17
Figure 13: Job Selection .................................................................................................... 18
Figure 14: Bulk Request Selection ..................................................................................... 19
Figure 15: Bulk Request Suffix .......................................................................................... 19
Figure 16: Bulk Request Preview ...................................................................................... 20
Figure 17: Scope Request and VPOR Overview ................................................................ 20
Figure 18: Update Existing Request .................................................................................. 21
BLACK & VEATCH | Table of Contents iii
6. Scope Management and Requisition Tool | AT&T Turf Project
Figure 19: Request Type Choices ...................................................................................... 21
Figure 20: Create New From Template ............................................................................. 21
Figure 21: Copy New from Existing ................................................................................... 22
Figure 22: Job Information Header for Add / Change ....................................................... 24
Figure 23: Scope Maintenance ......................................................................................... 24
Figure 24: Driver Exceptions ............................................................................................. 26
Figure 25: WA Selection Area ........................................................................................... 27
Figure 26: Norad Work Queue .......................................................................................... 34
Figure 27: Example NORAD Entry Format......................................................................... 35
Figure 28: NORAD OOMID Entry ....................................................................................... 36
Figure 29: Assign Vendor view from Main Menu ............................................................. 37
Figure 30: Assign Vendor - Select Request ....................................................................... 37
Figure 31: Detailed Assignment of Primary Vendor ......................................................... 38
Figure 32: Assign Vendor - Assign by Request .................................................................. 38
Figure 33 Assign Vendor - View all un-assigned scope ..................................................... 39
Figure 34: Add /Change Scope Vendor PO History ........................................................... 39
Figure 35: Job Initiative Work Queue Selection ................................................................ 43
Figure 36: Master Driver Excel Sample ............................................................................. 45
Figure 37: WA Excel Sample .............................................................................................. 46
Figure 38: Approved Vendor Data .................................................................................... 47
iv MARCH 2014
7. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Overview
The purpose of this document is to define the business process and technology requirements for AT&T Turf
Scope Management. Its role is to describe the current issues or problems to be solved, and provide
business process overviews for intended processes enabled by a âScope Management Toolâ. This document
briefly describes the business system and details about the business rules and functional dependencies.
BACKGROUND
The AT&T Turf program currently uses Quickbase by Intuit, a web-based database platform to track:
ďˇ Date/Milestone related data
ďˇ Project information
ďˇ Project scoping and client bid requests
ďˇ Closeout document upload and approval
ďˇ VPOR (Vendor Purchase Order Request) upload and approval
ďˇ Vendor communication
The Turf program currently consists of eight different markets, each with its own copy of the Quickbase
(QB) application. One program office application exists and additional market QB applications can be
created if needed. Each includes several thousand projects at various stages of completion. Each project
may have a dozen (typically less than twenty) individual purchase order requests (PORs) to multiple
vendors, which may include revisions to previous PORs. Currently Microsoft Excel POR forms are uploaded
as attachments to records created in Quickbase.
The current process limitations identified include:
ďˇ No ability to track total scope of project
ďˇ No ability to implement ârulesâ, preventing certain action based on scope selection
ďˇ Unable to keep AT&T price and vendor budget separated in all documents, necessitating the
manual transfer of data between forms, and the use of multiple scope entries and forms
ďˇ Difficulty keeping current forms updated with latest information due to the number of forms used
(6 forms per market x 9 pricing markets = 54 different forms).
Original Goal Statement: The Turf project requested a standardized process enabled by a web-based or
centralized database system to improve scoping, bidding,
and vendor purchase order process. âImplement a new
system to allow us to automate tasks where possible,
allowing us to scope more efficiently and accurately,
submit bids to our client, and issue purchase orders to
our vendors.â
Scope and order management are inter-connected
processes which connect the client work authorized
through completion (See Figure 1 and Appendix Scoping
and Order Management Life Cycle).
Scope Management is defined as the identification and
translation of site build requirements to pre-defined
âdriversâ and work authorizations with price and budget
based on the site design created from general
Figure 1: Scope & Order Mgmt High Level
Flow
BLACK & VEATCH | Overview 5
8. Scope Management and Requisition Tool | AT&T Turf Project
requirements. This includes approval from AT&T to perform identified work, and the assignment and
release of contractors to perform the work.
Order Management is the process of submitting vendor purchase order requests (VPOR) and the creation
of vendor purchase orders (VPO) for both services and materials to complete a job.
GENERATIONS OF DEVELOPMENT
Due to the complexity of the process and
touch points with other processes and
systems, the team created a âMulti-
Generation Project Planâ to divide the
desired state of the scoping system into
manageable phases or âgenerationsâ. The
components of the whole process were
reviewed and divided into â0 â xâ
generations that will result in an integrated,
enterprise process and solution.
0. Today: Microsoft Excel-based Feed Sheet to capture
Figure 2: Today: Generation 0 Overview
initial scope and final scope. Bill of Material (BOM)
Form to capture material requirements. VPOR and change order forms to capture revisions once work
begins (Figure 2).
1. Capture service scoping in a central database that can manage driver updates and requirement
changes. Rules setup to allow or prevent actions. Track scope status and NORAD approvals. Includes
NORAD work queue, export VPOR for entry into QB to further process of vendor purchase orders.
2. Capture BV-supplied material scoping.
3. Direct link of information between tool and iProcurement, so that vendor PO requests do not need to
be exported from the tool, processed in Quickbase, and manually entered into Procurementâs systems.
4. Obtain client authorization and request AT&T purchase orders via direct communication between the
tool and NORAD.
5. Addition of closeout document upload and tracking, in order to link driver to document automatically
and eliminate the need for document upload, review and processing via Quickbase. The document will
not be stored in the tool, but upload via the tool, and status of required docs tracked.
x. Enterprise system combines schedule management, scope management, order management, material
management, and financial information (PO, cost, billings, etc.). Valid for all programs, not just Turf.
Functional requirements for Generation 1 solution will be created to:
ďˇ Define the scope of business objectives, functions and stakeholders
ďˇ Identify business processes that the solution must facilitate
ďˇ Facilitate a common understanding of functional requirements for all stakeholders
ďˇ Establish a basis for defining the acceptance tests and to confirm that what is delivered meets
requirements.
6 MARCH 2014
9. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Business Process / Functional Requirements
Generation 1: Capture service scoping in a central database that can manage driver updates and
requirement changes. Rules are setup to allow or prevent actions. Track scope status and NORAD approvals.
Generation 1 includes NORAD work queue and export VPOR for entry into QB.
REQUIREMENTS - SMART (SCOPE MANAGEMENT AND REQUISITION TOOL)
Scope Master - Eliminate multiple spreadsheets
ďˇ Create a repository for client drivers, rules, market pricing, vendor budget and related information
to enable the scoping process. This will reflect the NORAD identifier and a B&V identifier
ďˇ AT&T pricing and vendor budget is based on markets (currently 9 â can increase or decrease)
ďˇ Ability to create templates for scoping of services
ďˇ Integration with existing enterprise solutions where possible (Procurement, ePOM, CMS)
Scoping Process â Single point of data entry
ďˇ Replace âFeed sheetâ Excel spreadsheets used today to capture scope and quantities (See
supporting docs 2.0 Feed Sheet_LA.xlsx; 2.0 Feed Sheet_NCAL.xlsx)
ďˇ Ability to create new scope for a âjobâ
ďˇ Provide existing scope information in order for scoping teams to accurately add / change scope
ďˇ Ability to see cumulative job scope (request history) in one list
ďˇ Upload approval emails, bids and receipts (supporting documents) upon entry
ďˇ Need to capture AT&T approval (email or OOM approval) on an individual request level
ďˇ Ability to assign multiple vendors to individual drivers and WAâs for purchase order requests
Scoping Interfaces â Multiple ways to access and various reporting capabilities
ďˇ Web-based for ease of access
ďˇ Accessibility required outside of B&V firewall for vendors
ďˇ Fast and easy to use â single point of entry
ďˇ Ability to apply changing vendor business rules to application when received
ďˇ Scope selection (drivers, WA's, and GC-provided material) in tabular format for efficient entry
ďˇ Secured access with specific user roles (based on DOR between scoping and execution)
ďˇ Exports scope with AT&T pricing, vendor pricing, or both to PDF and/or Excel
ďˇ Generate a vendor purchase order request and Change Order Request Form for submittal to AT&T
(See supporting docs 2.0 Change Order Request Form_Subcontractor_LA.xlsx; 2.0 Work
Authorization Form_LA.xlsx)
ďˇ Upload or auto-update transactions where possible (i.e. Bulk uploads; OOM ID update via csv, xlsx)
Scope Management/Reporting - Data driven activities that simplify, eliminate and automate work.
ďˇ Track assignment of each scope item to a vendor (or no vendor)
ďˇ Report of project scope to be used for true-up, which should include scope identified and scope
assigned to vendors
ďˇ Include NORAD work queue. Ability to tie OOMID to scope request for visibility to status of OOM
ďˇ Accumulation of scope with a total AT&T price of less than $5,000 per AT&T revision rules
ďˇ âAuditâ of scope based on current driver rules for updates that occur after driver submitted
BLACK & VEATCH | Business Process / Functional Requirements 7
10. Scope Management and Requisition Tool | AT&T Turf Project
GLOSSARY
Term Definition
AT&T Customer
project ID
Types of project IDs used by AT&T - CASPR Capital; CASPR Other (PTN); Expense ID
CASPR (#)
PACE (# )
The unique identifier assigned to a Job in CASPR#. CASPR (AT&Tâs old scheduling and
site information database) is being used by AT&T prior to PACE.
Drivers Indiv idual work items common to many Jobs, for which pricing has been set between
AT&T and B&V, and B&V and the contractor.
FA Location AT&T reference for physical location where work is being performed. One FA Location
may have multiple concurrent Jobs in process.
Initiative Type of work being performed at a site (ie. LTE, New Site Build, UMTS 1st Carrier).
Each Job will have one Initiative.
Job (#) The unique identifier assigned to a Job (An individual work project on a particular
AT&T site). After transition to PACE (AT&Tâs new scheduling and site information
database), this will be the PACE#.
Market The region where work is being performed. There are 9 pricing markets. Typical users
will have access to one or more markets but some may have access to two or more.
NORAD DBA The employee(s) tasked with taking the work identified by the Project Manager and
inputting the work into NORAD (AT&Tâs bidding system).
POR Purchase Order Request â A request for a purchase order to be submitted to a vendor
in order to perform a scope of work.
Project Mgr.
The B&V or OCI employee who is in charge of determining what work is needed on a
job and submitting work into the tool for approval and purchase order processing.
Quickbase B&Vâs user interface for schedule information and POR processing
Request The identification and bid of a portion of work to be done for a Job. Typically, multiple
requests are needed to complete a job. New requests are created as new work is
identified. A request can be for NORAD entry, a vendor purchase order, or both.
Site ID Secondary reference for physical location where work is being performed. In most
cases there is one Site ID per FA Location.
Vendor A company that subcontracts with B&V to perform work. They companies are allowed
limited access to B&V information (see Appendix Authority and Approval Matrix)
Work Author-izations
(WA)
All work items not foreseen nor previously negotiated. Typically specific to an
individual site and job.
B&V TO AT&T TERMINOLOGY CROSS-REFERENCE
B&V AT&T
Client ID â Many contracts per client AT&T â Vendor
Contract â Super Revenue Package (ie â Turf) Contract
Revenue Package â Market Region â Market/Sub-Market
B&V Project Number â Sub-Market
Unique Site Location (ie Lat / Long) Site = FA Location â Location
Phase = Job# (Initiative Type/Location/Site ID) = PACE#
= CASPR# = OOM/PO â many jobs for a site
Job # (Initiative/Site ID) = PACE# = CASPR# =
OOM/PO â many Jobs for a site
Request = Rev -> many requests per Job Request = OOM Rev -> Many requests per Job
ďˇ Drivers & WAs - many per request ďˇ Many drivers and WAs per request
ďˇ Vendors - many per request
ďˇ One vendor per Driver / WA
8 MARCH 2014
11. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Business Process Flows
SCOPE MANAGEMENT OVERVIEW
Receive Request for
Work from AT&T
Request AT&T
Approval for Site
Acq and Engineering
Work
Determine Site Acq
& Engineering
Requirements
Issue POâs for Site
Acq and Engineering
Work to Vendors
Determine Prelim
Construction and
Material
Requirements
Request AT&T
Approval for Prelim
Construction Work
and Materials
Determine Final
Construction and
Material
Requirements
Request AT&T
Approval for Final
Construction Work
and Materials
Issue POâs for
Construction Work
to Vendors
Identify Site Acq &
Engineering Change
Orders
Identify
Construction Change
Orders
Request AT&T
Approval for Site
Acq & Engineering
Change Orders
Request AT&T
Approval for
Construction Change
Orders
Complete
Construction and
True Up Site
Figure 3: Scope Management Overview Process Flow
Scope Management business process activities require the support for capture of scope requirements in
the following cases.
1. Job Creation
2. Initial Bulk Request Create
3. Individual Request Create/Select
4. Scope Maintenance â Add / Change
5. Attach / Upload docs
6. Preview & approve scope
7. NORAD OOMID entry
8. Assign Vendor
9. Export VPOR
Sub-Process Name
SMART System Components
Request
Scope
Maintenanc
e
Attach /
Upload
PdMoc s
Approve
scope
NORAD
OOMID
eAnsstrigyn
Vendor
Export
VPOR
Initial Scoping for Bulk Projects Create
Create
Initial
x x
Initial Scoping for Individual Projects Create
Create
Initial
x x
Assign Initial Vendors Select
Add/
Change
x x x
Site Acq & Engineering Scope Changes Select
Add/
Change
x x x x
Initial Construction Scoping Select
Add/
Change
x x x
Final Construction Scoping Select
Add/
Change
x x x x x
PM-Created Construction Change Order Select
Add/
Change
x x x x x
Vendor-Created Construction Change
Order
Select
Add/
Change
x x x x x
BLACK & VEATCH | Business Process Flows 9
12. Scope Management and Requisition Tool | AT&T Turf Project
SUB PROCESS FLOWS
Initial Scoping for Bulk Projects
Narrative: Initial scoping for services and construction based on type of site (LTE, NSB, UMTS, etc.)
1) AT&T informs B&V of new project(s) coming. (Email, phone, various)
2) B&V is assigned as vendor in CASPR. (daily report from CASPR)
3) CASPR person communicates new projects to the PM (via email or meeting)
4) New project(s) created in tool (CASPR report, email, etc.)
5) PM creates initial scope based on project type (draft mode?/using templates?/mass upload?).
6) PM approves scope.
7) NORAD DBA reviews queue (approved OOMs) and creates the base OOM in NORAD
8) NORAD DBA enters the OOMID into the tool.
9) AT&T PM approves base OOM.
10) NORAD DBA creates bulk OOM based on NORAD bulk upload procedure.
11) NORAD DBA updates bulk projects with OOMID(s) (automatic based on CASPR#, driver, and Rev 0?)
12) AT&T PM approves bulk OOM submittal.
13) AT&T processes OOM submittals for PO.
14) Black & Veatch receives PO(s) via ePOM. Tool links AT&T PO with NORAD OOM using the OOMID.
15) PM assigns vendor(s) to existing scope.
16) PM exports VPOR form from tool and uploads to project in Quickbase. (VPOR Workflow)
Figure 4: Initial Scoping for Bulk Projects
Blue = Activity
Yellow = Outputs
10 MARCH 2014
13. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Initial Scoping for Individual Projects
Narrative:
1) AT&T informs B&V of new project(s) coming. (Email, phone, various)
2) B&V is assigned as vendor in CASPR. (daily report from CASPR)
3) CASPR person communicates new projects to the PM (via email or meeting)
4) New project(s) created in tool (CASPR report, email, etc.)
5) PM creates initial scope based on project type
6) PM approves scope.
7) NORAD DBA reviews queue (approved OOMs) and creates the OOM in NORAD
8) NORAD DBA enters the OOMID into the tool.
9) AT&T PM approves OOM.
10) AT&T processes OOM submittal for PO.
11) Black & Veatch receives PO via ePOM. Tool links AT&T PO with NORAD OOM using the OOMID
12) PM assigns vendor(s) to existing scope.
13) NORAD DBA(PM?) exports VPOR form from tool and uploads to project in Quickbase. (VPOR
Workflow)
Figure 5: Initial Scoping for Individual Projects
BLACK & VEATCH | Business Process Flows 11
14. Scope Management and Requisition Tool | AT&T Turf Project
Site Acq & Engineering Scope Changes
Narrative:
1) PM or Vendor identifies additional work required (drivers, WAâs, and site fees) on the project based
on project progression.
2) PM requests approval from AT&T PM via email (<$5,000). If >$5,000, skip to step 4.
3) AT&T approves additional scope via email.
4) PM creates additional scope in the tool, uploads emails approval (if <$5,000) and assigns vendor
who will perform (requests VPOR).
5) PM approves scope.
6) NORAD DBA reviews queue and updates OOM (if >$5,000), updates OOMID in tool and obtains
OOM approval before exporting VPOR from tool and importing into Quickbase (VPOR Workflow).
7) NORAD DBA reviews AT&T PM email approval (if <$5,000) before exporting VPOR from tool and
importing into Quickbase (VPOR Workflow).
Figure 6: Site Acq & Engineering Scope Changes
12 MARCH 2014
15. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Initial Construction Scoping
Narrative:
1) PM attends design review meeting.
2) PM reviews Zoning Drawings and RFDS.
3) PM determines drivers, estimated WAâs, estimated crane costs, and long lead materials (not input
to Generation 1).
4) PM creates additional scope in the tool via free-form or template.
5) PM approves scope.
6) NORAD DBA reviews queue and updates OOM, updates OOMID in tool, submits to AT&T.
7) NORAD DBA exports Long-Lead BOM (if applicable) and uploads to project in Quickbase (VPOR
Workflow)
8) If the OOM is approved, ePOM communicates with the tool, and the scope connected with the
OOMID is marked as approved.
9) If the OOM is disapproved or auto-cancelled, ePOM communicates with the tool, and the scope
connected with the OOMID is marked as invalid.
Figure 7: Initial Construction Scoping
BLACK & VEATCH | Business Process Flows 13
16. Scope Management and Requisition Tool | AT&T Turf Project
Final Construction Scoping w/ Assign Vendors
Narrative:
1) PM exports existing construction scope from tool to be used when performing site/bid walk.
2) After building permit is approved, PM walks site with GC(s) and identifies changes and/or additions
to original project scope.
3) GC(s) provides WA bids to PM.
4) PM fills out Purchasing Decision Statement (Appendix E) and submits to AT&T for vendor selection.
If AT&T does not respond, BV will use a copy of the email request as an attachment to Appendix E.
5) PM revises original construction scoping in tool, adds actual WA costs, additional drivers and
material required (material not part of Gen 1).
6) PM assigns vendor, uploads GC bids and a copy of the PDS into the tool.
7) NORAD DBA reviews queue and updates OOM, updates OOMID in tool and obtains OOM approval
before exporting VPOR from tool and importing into Quickbase (VPOR Workflow).
Figure 8: Final Construction Scoping
14 MARCH 2014
17. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
PM-Created Construction Change Order with Assign Vendor
Narrative:
1) PM or vendor identifies additional scope required.
2) The PM creates the additional scope in the tool (or see âVendor-Created Construction Change
Orderâ process below).
3) The PM will export a Change Order Request Form from the tool and will email this form to the
AT&T PM.
4) The AT&T PM approves or disapproves the change order request and responds via email.
5) If the AT&T PM approves the change order, the PM will upload/attach the AT&T approval email to
the scope.
6) PM approves scope.
7) NORAD DBA reviews queue and updates OOM, updates OOMID in tool, and uploads the AT&T
approval email before exporting VPOR from tool and importing into Quickbase (VPOR Workflow).
8) If the AT&T PM disapproves the change order, the PM will inform the vendor, and the PM will
update the scope request in the tool.
Figure 9: PM Initiated Change Order
BLACK & VEATCH | Business Process Flows 15
18. Scope Management and Requisition Tool | AT&T Turf Project
Vendor-Created Construction Change Order
Narrative:
1) The vendor identifies additional scope required.
2) The vendor logs into the tool and selects the job.
3) The vendor adds additional scope (driver, WA, material, etc., positive quantity or negative quantity)
and approves request.
4) The PM reviews the change order request, and if approved, continues with the âPM-Initiated
Construction Change Orderâ process.
5) If the GC-Initiated change order request is not approved, the GC will correct and resubmit.
Figure 10: Vendor Initiated Change Order
16 MARCH 2014
19. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Scoping Process / SMART Functional Requirements
This document, we will refer to the tool as the Scope Management and Requisition Tool (SMART).
Functional requirements are grouped in two sections. First, transaction-based requirements grouped by
activities (Figure 11: 1 â 10) that manage scope detail, grouped into categories of work (Figure 11: A â F).
Figure 11: Scope Maintenance & Assign Vendor
Second, maintenance and supporting processes in the next section describe activities and functionality
related to master data and supporting processes.
For all activities, security access permissions required to control what is seen by users include:
ďˇ User role â level of authority
ďˇ Function type â Work code(s) = Master Driver /WA Work Code
ďˇ Geographic location â Assigned Market(s)
These requirements are further outlined in the User Information & Log on section.
ASSUMPTIONS
ďˇ Screens and examples are included to convey concepts and
relationships. Technical solution may include a different look but
fulfill entry requirements (Figure 12)
ďˇ System validates business rules which can be easily modified
due to changes by client and/or process owner. Rules must
correspond to Vendor system requirements such as NORAD
ďˇ B&V âJobâ information from PACE is available to validate/
update job data
ďˇ Access is defined by roles and permissions
ďˇ AT&T PO data can be obtained from ePOM or NORAD
ďˇ NORAD data and status can be obtained from system interface.
Figure 12: Main Menu Example
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 17
20. Scope Management and Requisition Tool | AT&T Turf Project
A. PROCESS NEW JOBS RECEIVED FROM AT&T
Summary: A Job is assigned to Black & Veatch in PACE (or CASPR). Scope requests for AT&T Drivers and
WAâs are added to the job as the work is completed. Each Job is related to an AT&T PO assigned upon initial
NORAD OOM approval. These are used in the process of matching OOM submittal and AT&T PO receipt in
B&Vâs ePOM system.
Job requirements include:
Automation Question:
Is interface possible
with AT&T systems
which create / initiate
the job(s)?
ďˇ Ability to enter jobs manually or via automated process
ďˇ An option to create a non-PACE Job type
ďˇ Ability to create one job individually
ďˇ Ability to create multiple jobs through bulk uploads
ďˇ Provide search capabilities to ensure the job has a Proj_status = Active or Authorized in CASPR or
does not already exist. Jobs may exist in the Job Information table once. New jobs must be able to
be created that will not exist in CASPR or PACE. (See Supporting docs Example CASPR data.xlsx)
Inputs: There is no automatic feed of new sites released from AT&T today. CASPR reports, emails and
correspondence from AT&T indicate a new Job is to be created for scoping.
1. Job Create / Select
Selecting a job to scope is the first step in all scoping sub-processes. The PM selects an individual Job from a
list of Jobs limited by:
ďˇ Security authorizations based on their login information by market
ďˇ Status = Active
ďˇ User search by attributes such as Job Initiative, Job Sub-Initiative, Market, Project, etc.
Jobs should be created from new PACE information. An entry screen will be needed to enter jobs that
cannot be automatically created. The first step in creating a request is to select a job from the Job
Information (See Appendix Master Job & Site Information and Job Selection tables). User will search for Job
to be scoped (Figure 13).
Figure 13: Job Selection
Select Job to Scope Search for Job or choose a filter
SEARCH
Job ID# Job Name BV Initiative BV Sub-Initiative Project Status FA CODE Site ID Project # Phase # Market
3755336583 E-470 & 120TH COU1030 CO Modif ications 10XC Active 10093758 COU1030 169867 8208 Colorado
3755336595 ILIFF & PARKER COU1071 CO Modif ications 10XC Active 10093655 COU1071 169867 8220 Colorado
3755336599 UNIVERSITY & ORCHARD New Site Build NSB Active 10102184 COU1088 169867 8224 Colorado
3755336600 BROADWAY & BELLEVIEW RELO LTE Wave 2 Active 10110733 COU1090 169867 8225 Colorado
3755336620 MARSHALL COU1242 CO LTE Wave 2 Active 10093736 COU1242 169867 8245 Colorado
3755336628 HAMPDEN & I25 COU1289 CO LTE Wave 5 Active 10093821 COU1289 169867 8253 Colorado
3755336634 36 & SHERIDAN COU1300 CO UMTS 1st Carrier Active 10093837 COU1300 169867 8259 Colorado
3755336640 60TH & WADSWORTH COU1323 COUMTS 2nd Carrier Active 10093859 COU1323 169867 8265 Colorado
3755336648 WESTMOOR TECH CENTER UMTS 2nd Carrier Cancelled 10130168 COU1341 169867 8273 Colorado
3755336657 KEN CARYL VALLEY COU1424 COUMTS 4th Carrier Active 10099268 COU1424 169867 8282 Colorado
3755336658 PARKER & ARAPAHOE COU1427 COUMTS 4th Carrier Active 10099272 COU1427 169867 8283 Colorado
3755336659 CASTLE PINE GOLF COURSE UMTS 4th Carrier Active 10099210 COU1430 169867 8284 Colorado
3755336669-109798435 FITZSIMONS COMPLEX UMTS 4th Carrier Authorized 10123002 COU5066 169867 8294 Colorado
3755336670 GATEWAY COU5091 CO Modif ications Sector Add Active 10127029 COU5091 169867 8295 Colorado
3755336574 LINCOLN & 3RD CO Modif ications Relo Active 10102201 COU1350 169867 8327 Colorado
MRUTH123958 SUNDANCE COW Modif ications Generator Active 10129420 COU4995 169867 8554 Colorado
MRUTH123959 HAMPDEN & UNIVERSITY RELO Modif ications Structure Mod Active 10093766 DN1223 169867 8661 Colorado
MRUTH123960 COZY CORNER RELO 2 New Site Build NSB Active 11575885 1/0/00 122061 6013 Colorado
MRUTH123961 ASPEN Modif ications Structure Mod Complete 10093732 DN4036 122061 6032 Colorado
MRUTH123962 SOUTH AIR FORCE ACADEMY Modif ications Structure Mod Complete 10099184 DN2088 122061 6034 Colorado
MRUTH123963 BEAVER CREEK 850 GSM Modif ications Structure Mod Complete 10093673 DN4061 122061 6035 Colorado
MRUTH123964 DILLON Modif ications Structure Mod Complete 10093725 DN4028 122061 6036 Colorado
18 MARCH 2014
21. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
B. CREATE INITIAL BULK SCOPE REQUESTS
Summary: Current NORAD functionality allows an upload to create a group of requests in bulk for initial
scoping. SMART should mirror NORAD bulk order entry process which contains the ability to take an
existing request and scope of one âbase jobâ and copy it to multiple other jobs as initial requests.
Bulk Job Creation â Load Job information
Job information would be automatically loaded from client data/system and available to SMART for initial
entry of scope. Processing for this activity currently happens via spreadsheet.
Initial Scoping for Bulk Jobs
Current NORAD functionality allows an upload to NORAD to create a group of requests in bulk for initial
scoping. The NORAD bulk creation process is as follows:
1. The B&V PM provides the NORAD DBA with a list of jobs and a list of drivers and WAâs that need to
be requested for those jobs. The NORAD DBA creates an initial âbase OOMâ for one of the jobs, and
adds the initial drivers and WAâs. It is submitted to the AT&T PM to approve and process for PO.
2. Once the base OOM is approved by the AT&T PM, the NORAD DBA creates a template to be
uploaded to NORAD (See supporting docs NEW Bulk Upload Template 07-11-2013.xlsx; Example
NORAD Bulk Upload.xlsx), which consists of the Job ID#âs of the remaining bulk jobs and the
identification of the base OOM to copy. Once uploaded, NORAD then mirrors the scope of work
submitted on the base job to the group of bulk jobs.
2. Initial Bulk Request Create
Adding requests in bulk to SMART tool
would require:
A. Ability to mirror (copy) an
existing request to create an
initial request for multiple Jobs
B. Upload / import data for
identified Jobs in bulk upload
with initial request detail
Figure 14: Bulk Request Selection
Each individual job assigned to a bulk request will get an individual request ID#, however, that ID# will be
followed with a âBâ suffix to delineate that the request was created via the bulk process. AT&T assigns one
OOMID per job so one bulk request will create many OOMâs and OOMIDâs. There should be a mechanism
for a NORAD DBA to import many OOMIDâs back into the tool with reference to the job # in order to create
the link between the Request in the tool and the OOM.(See NORAD OOM Entry & Record OOM ID in Review
and Submit to AT&T for PO).
Figure 15: Bulk Request Suffix
Request Type Request Status Req# OOMID# AT&T PO# PO Rev#
Driver Request
Amount
WA Request
Amount
Total AT&T
Request Amount
AT&T PO
Amount OOM Status
SAQ/ENG - Initial Scoping Approved 10001B 2631443 520135 0 $1,237.95 $1,236.00 $2,473.95 $2,473.95 Approved
SAQ/ENG - Change Order OOM Rejected 10042 2632001 $3,200.00 $0.00 $3,200.00 Disapproved
SAQ/ENG - Vendor Change Order OOM Submitted 10043 2632008 $1,600.00 $0.00 $1,600.00 Waiting on Craig Coney
Create New
Create New Services
Create New Services
A âBulkâ Services Request
identifier Request
for requests Request
created via bulk, such as a âBâ suffix to the system-created Request # is
(From Template)
(Copy from Existing)
required for tracking (Figure 15).
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 19
22. Scope Management and Requisition Tool | AT&T Turf Project
Figure 16: Bulk Request Preview
Inputs: PM will apply âstandardâ initial market
drivers to jobs released from AT&T. These drivers
are chosen by the individual PMs and applied to
requests âin bulkâ on selected jobs as described
above. Selections are limited to Jobs currently
with
OOM Revision = 0,
OOM Status = Approved,
Request Type = SAQ/ENG â Initial Scoping
or Construction â Initial Scoping
Once bulk requests are created, they will be
available to create individual scope (Figure 14
and 16).
C. CREATE INDIVIDUAL SCOPE REQUEST
Summary: Project managers will create requests that assign pre-negotiated âdriversâ (catalog items) and
WAs (non-catalog items) following processes were defined in the Business Processes Flows section.
ď§ Site Acq & Engineering Scope Changes
ď§ Initial Construction Scoping
ď§ Final Construction Scoping
ď§ PM-Created Construction Change Order
ď§ Vendor-Created Construction Change Order
Each request initiates a NORAD OOM revision request, for which Black & Veatch receives a revised AT&T
PO. A request may also necessitate one or more B&V vendor purchase order requests (VPOR) to assign the
work.
AT&T assigns
Job in
CASPR/PACE
Identify New
Requirements
Create Scope
Request(s) by
Job
Process OOM
and PO
Revisions
Inputs: Analysis and identification of the requirements for work and the related AT&T drivers to complete
are compiled by PMs. Knowledge of each area is needed to apply the correct drivers to the request to
AT&T. Work is not started until AT&T representative approves via email or a revision to the PO is received.
20 MARCH 2014
Work
Progresses
Assign work to
Vendors
Process Vendor
PO Request and
issue PO
Figure 17: Scope Request and VPOR Overview
23. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
3. Individual Request Create/Select
Once a job is selected, display all related requests and information. Request history for Job is displayed to
update an existing request See Appendix Request Create/Select; Figure 18).
Req# is âopen for revisionâ if status =
Draft or NORAD DBA Rejected. User
would âclickâ number to choose. In
addition, ability to click previous non-editable
req#âs would go to a Read-
Only display of the request.
Update an existing request - Link on Req# in History if in Draft or Rejected takes user to Scope Maintenance
â Add / Change for that request.
Create New - Request type controls values displayed during Scope Maintenance based on access
permissions reflected in Table 1 Request Type Values to reflect work requested to date. Request types are
not sequential but can be done simultaneously by different functional areas with the follow exceptions:
ďˇ No SAQ/ENG requests should be allowed if âSAQ/ENG - Initial Scopingâ has not been created
ďˇ No Construction requests should be allowed if âConstruction - Initial Scopingâ has not been created
Figure 19: Request Type Choices
Select appropriate Request type (See Figure 19 and Table 1), then
choose an activity:
1. Create New Services Request (From Template) - Templates
provide âpre-tailoredâ models for various build configurations
and site types or existing Job /Revision. (See Build Templates in
Supporting processes and Figure 20).
Figure 20: Create New From Template
Select
Templat
e Template # Template Name
Total Request
Amount Created Date Created By:
1 NSB Watertank Construction $ 97,017.00 12/1/2013 Brad Bryant
2 NSB Rooftop Construction $ 30,465.00 12/6/2013 Devin Morris
3 Standard LTE Rooftop $ 42,000.00 12/6/2013 Scott Rickard
4 Standard UMTS 1C $ 9,465.00 12/9/2013 Neil Eft
Use Template Preview Template Cancel
Figure 18: Update Existing Request
2. Create New Services Request (Copy
from Existing) â Display historical
requests, limited to the type of request
(Site Acq/Eng or Construction) and
their market location (Figure 21).
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 21
24. Scope Management and Requisition Tool | AT&T Turf Project
Figure 21: Copy New from Existing
Create New Services Request takes user to Scope Maintenance â Add / Change (Figure 22) for that request.
Table 1: Request Type Values
Request Type Value
Description
Business Rules
Role
Function
Type
Drivers/
WA Work
Code
SAQ/ENG -Initial
Scoping
Typically the first request on a job.
Available when no other request exists
for Job
not equal
to Vendor
âSâ or âEâ âSâ or âEâ
SAQ/ENG -Change
Order
Available once a SAQ/ENG Initial
Scoping request has already been
submitted. Created by internal PM.
not equal
to Vendor
âSâ or âEâ âSâ or âEâ
SAQ/ENG -Vendor
Change Order
Available once a SAQ/ENG Initial
Scoping request has already been
submitted. Created by external vendor.
equal to
Vendor
âSâ or âEâ âSâ or âEâ
SAQ/ENG âFinal True
Up
Available once a SAQ/ENG Initial
Scoping request has already been
submitted. Created by internal PM.
not equal
to Vendor
âSâ or âEâ âSâ or âEâ
Construction - Initial
Scoping
Available for Initial construction
scoping. Available when no
construction requests exists for Job
not equal
to Vendor
âCâ or âMâ âCâ or âMâ
Construction - Final
Scoping
Available when Job has had a
Construction â Initial Scoping request
created before work starts .
not equal
to Vendor
âCâ or âMâ âCâ or âMâ
Construction - Change
Order
Available when Job has had a
Construction â Initial Scoping request
created. Created by internal PM.
not equal
to Vendor
âCâ or âMâ âCâ or âMâ
Construction - Vendor
Change Order
Only available when Job has had a
Construction â Initial Scoping request
created. Created by vendor.
equal to
Vendor
âCâ or âMâ âCâ or âMâ
Construction â Final
True Up
Available when Job has had a
Construction â Initial Scoping request
created. Created by internal PM.
not equal
to Vendor
âCâ or âMâ âCâ or âMâ
Request status indicates the âWork Queueâ of requests. See Table 2 Request Status Value and section My
Work Queue for details relating to Request Status work queue flows.
Table 2: Request Status Values
Request
Status
Value
Description (meaning &
purpose explicit)
Business Rules
Work
Queue
Location
22 MARCH 2014
Edit
Possible
?
Draft
Request created but not yet
submitted.
ďˇ Request created, saved in draft PM
Y
25. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Request
Status
Value
Description (meaning &
purpose explicit)
Business Rules
Work
Queue
Location
Edit
Possible
?
Vendor
Submitted
Request created by Vendor
but not yet approved by PM
ďˇ Request created by vendor,
submitted to PM
PM,
Vendor
(Status
Only)
N
PM
Approved
Request approved by the PM ďˇ PM Approves
NORAD,
Vendor
(Status
Only)
N
PM
Rejected
Request rejected by the PM ďˇ PM Rejects and vendor must
correct
ďˇ
Vendor
Y
Voided
Request created, but no
longer needed
ďˇ PM may void a Draft or PM
Rejected request.
None N
NORAD DBA
Rejected
Request rejected by NORAD
DBA
ďˇ Request rejected by NORAD DBA
â Documents; wrong job;
comments
PM
Y
Accumulate
Request approved by NORAD
DBA. Total value of this and
previous requests not
exported <$5,000.
ďˇ Request has been approved by
NORAD DBA
ďˇ Total value of this and previous
requests not exported <$5,000
ďˇ Not âInitial Scopingâ request
NORAD
N
Accumulate-
Ready to
Submit
Request approved by NORAD
DBA. Total value of this and
previous requests not
exported >=$5,000.
ďˇ Request has been approved by
NORAD DBA
ďˇ Total value of this and previous
requests not exported >=$5,000
NORAD
N
Exported
Request has been approved
by NORAD DBA and is
currently being entered into
NORAD.
ďˇ OOMID has NOT been entered
ďˇ Request has been approved by
NORAD DBA
NORAD
N
OOM
Submitted
Request has been approved
by NORAD DBA and is waiting
on approval by AT&T PM
ďˇ OOMID has been entered
ďˇ OOM Status = âWaiting on
xxxxxxâ where xxxx = the name of
the AT&T PM (variable)
NORAD
N
OOM
Rejected
Request has been
disapproved by AT&T PM or
NORAD DBA
ďˇ OOMID has been entered
ďˇ OOM Status = Disapproved or
Auto-Cancelled
PM
N
OOM
Approved
Request has been approved
by AT&T PM in NORAD
ďˇ OOMID has been entered
ďˇ OOM Status = Approved (is OOM
Status needed?
None,
Vendor
(Status
Only)
N
When a Request changed status from OOM Submitted to OOM Rejected, the system should automatically
send an email notice to the Request Creator notifying them that the OOM has been rejected.
Scenario deviations: (Describe scenarios that may impact or change process due to client requirements.)
A. Non-NORAD projects
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 23
26. Scope Management and Requisition Tool | AT&T Turf Project
B. Ability to edit and/or create new requests limited based on ??? (job status/task/etc.)
C. Ability to create scope that gets put onto a vendor PO request but does not get submitted to
NORAD.
4. Scope Maintenance â Add / Change
Summary: After a request is selected, the user will Add or Change âDriversâ and âWAâsâ (items of work) to
the request by Function type (Table 3) according to role (ie. Site Acq, Engineering, Construction). Access
permissions control data displayed to users during Scope Maintenance. Users in the âVendorâ role will be
limited to the site information in *THEIR* previous request history for that job. They are not allowed to see
AT&T PO Requests or Vendor PO Requests for other vendors.
Job Request History Information: Display information pertaining to the entire job. Ability to drill to details
for job would be ideal but not required for
first build.
Header information is stored or
accumulated as indicated in Figure 22. (See
Appendix AT&T PO Request History and
Vendor PO Request History).
Table 3 Function Type
Function
Corresponding
Work code
Site Acquisition S
Engineering E
Construction C
Materials M
Figure 22: Job Information Header for Add / Change
Scope Maintenance â Driver Display
Valid market Driver IDs will be shown sorted A-Z by (1) NORAD Driver Category, and then A-Z by (2) Driver
ID# (Figure 23). User should be able to filter Driver Selection area by Category, Type, and Work Code (See
Appendix User Driver Selection).
Figure 23: Scope Maintenance
24 MARCH 2014
27. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Driver ID Driver Name Request Qty
AT&T Price
(This
Request)
AT&T Price
(Total
Scope)
Vendor
Assignment
Vendor
Budget (Each)
Vendor
Budget
(This Request)
Vendor
Budget
(Total Scope) Driver Exception Comment
AE01
Architectural and Engineering
Drawing
* Zoning Drawing (ZD) - Only 0 $ - $ 1,237.95
CHARLES STECKLY
ARCHITECTURE INC $ 1,015.60 $ - $ 1,015.60
AE02
Architectural and Engineering
Drawing
* Cons truction Drawing (CD) - Only 0 $ - $ - $ 1,800.00 $ - $ -
Primary candidate backed out after ZD's
were completed. New candidate did not
requi re zoning approval , CD's only.
Please see attached approval emai l .
Architectural and Engineering
Drawing
* Drawings Upgrade - (ZD) to (CD) 1 $ 3,224.93 $ 3,224.93
Request Qty:
CHARLES STECKLY
ARCHITECTURE INC $ 1,800.00 $ 1,800.00 $ 1,800.00
Drivers are added and changed by adding new Qty to a chosen Driver (See Table 4 Quantity Processing).
Table 4: Quantity Processing
Field Processing Potential features
Previous Qty* Sum total of driver quantities from
previous requests for Job - Scenario
logic detailed below in Table 7 Previous
Quantity
Functionality to drill down (display)
previous scope requests? Approved
in tool? ePOM?
AE03
Request Qty Quantity requested (incremental
amount - positive or negative based on
need)
Cannot drive Total Qty below 0.
Total Qty Previous + Request = Total
* NOTE - Special handling is necessary for requests if an OOM is disapproved, since AT&Tâs NORAD system
does not automatically remove the disapproved items from the OOM. If items are disapproved in the OOM,
then need to be manually removed in NORAD on the next revision. Therefore, in order for the âPrevious
Qtyâ field to show a legitimate *Approved* Previous Qty, the disapproved items must be included with the
NORAD export of the next request (Table 5). Change in process will be addressed in training.
Table 5: Previous Quantity Scenarios
Scenario Scenario Description
Previous
Qty
Approved
Previous Qty
Disapproved
1
Draft, Vendor Submitted, PM Approved
Accumulate, Accumulate - Ready to
Submit, Exported, OOM Submitted,
OOM Approved
Yes N/A
2 NORAD DBA Rejected No Disregard request in Prev Qty
3 OOM Rejected No
The first request after the OOM
Rejected request must add the rejected
items as negative amounts. The NORAD
DBA removes the items rejected from
the OOM while adding the new items
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 25
28. Scope Management and Requisition Tool | AT&T Turf Project
Error Checking and Handling
A driver exception comment is linked to the request and the driver. It is displayed on the screen unless
there no Driver Exceptions, then it can be hidden. This will occur real time as quantities are entered.
Changes due to master driver updates will not be flagged?
The Master driver list will
contain ârulesâ to follow when
choosing drivers. As quantities
are entered, if rule is broken
(Table 6 and Appendix Driver &
WA Masters), highlight Request
Qty or Total Qty, and show
popup box with rule that was
broken (Figure 24).
Table 6: Driver Rules
Figure 24: Driver Exceptions
Title Description Error Handling Calculation
Should
Maximum permissible
Qty highlighted / changeable
Not
quantity of this driver
User comment is highlighted
Exceed
without requiring an
and required.
Qty
explanation
If total qty for driver (sum of
all requests for a JOB ID#)
exceeds this amount
Must Not
Exceed
Qty
Maximum permissible
quantity of this driver
Qty highlighted / changeable
Error message shown.
Request not allowed to be
submitted with error
If total qty for driver (sum of
all requests for a JOB ID#)
exceeds this amount
Should Not
Be Used
With
A list of drivers that cannot
be used in the same scope
(historical) with this driver
without an explanation
Qty highlighted / changeable
User comment is highlighted
and required.
If a driver listed in this field is
selected at the same time as
this driver
Must Not
Be Used
With
A list of drivers that cannot
be used in the same scope
(historical) with this driver
Qty highlighted / changeable
Error message shown.
Request not allowed to be
submitted with error
If a driver listed in this field is
selected at the same time as
this driver
26 MARCH 2014
29. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
âMust Notâ logic takes precedence over âShould Notâ logic. Therefore, if a driver fails the logic test for
both, the system will not prompt for a comment but rather will follow the âMust Notâ rules.
Driver exception comments will need to be input by the user for any drivers that fail the âShould Notâ tests.
Each driver that fails the logic test will need the user to enter data in 5 fields, "Who", "What", "When",
"Where", "Why". Individual fields should not be marked as required, but user will need to enter information
in at least 2 fields to proceed. System should combine entries into one "Driver Comments" field in the
format:
(Who) General Contractor
(What) Antenna Removal
(When) 1/24/14
(Where) Site
(Why) RFDS calls for removal of existing antennas and installation of new antennas. AN19 relocate driver
specifies relocation of existing antennas.
Scope Maintenance â WA Display and Selection
Below the Driver Selection section is the WA Selection area (Figure 25). Considered a non-catalog request,
users can choose one or more WA(s) as many times as needed from approximately thirty (30) different WA
categories (WA ID# & WA Name). (See Appendix User WA Selection).
Inputs: Work to be performed outside normal Drivers must have quantity, cost and additional information
input for submission to AT&T and Vendor purchase orders. Processing requirements include:
⢠Ability to add an unknown number of WA lines for multiple categories
⢠User will select from a list of WA ID#âs, and then enter Request Qty, WA Description, Vendor Cost,
Inclusion, and Exclusions
⢠The user should be allowed to change the quantity of a WA line item added on a previous request.
The system should keep track of the change and submit just the change to the NORAD DBA for
processing into NORAD.
⢠Instead of a single user-entry WA âInclusionsâ field, each WA will need the user to enter data in 5
fields, "Who", "What", "When", "Where", "Why". Individual fields should not be marked as
required, but user will need to enter information in at least 3 fields to proceed. System should
combine entries into one "Inclusions" field in the format:
⢠(Who) General Contractor
⢠(What) Snowcat rental
⢠(When) 1/24/14
⢠(Where) Site is 1/2 mile from nearest plowed road
⢠(Why) Snowed 5 feet on 1/22/14, needed to access the site
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 27
Figure 25: WA Selection Area
30. Scope Management and Requisition Tool | AT&T Turf Project
To add a WA to the request:
Table 7 WA Category
⢠Drop-down of selection from 35+ WAID#âs which describe the category of WA work to be done
⢠WAID populates WA Name, UOM, Markup % information from master
⢠Request Qty, Vendor Cost, WA Description, Inclusions (from 5 Wâs), and Exclusions are entered
⢠Select Category from drop down listing options (Table 7)
⢠Add multiple WA lines as required. As last open line is used, a new open line should appear.
A general comments section should be available for user input in the bottom portion of the Scope
Maintenance Add/Change screen.
28 MARCH 2014
31. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Check Project Management (PM Drivers) Handling
AT&T contract allows up to two additional âPMâ drivers (one for Site Acq work, and one for Construction
based on the total AT&T price of the project. A field in the Master Driver and Master WA Information tables
indicates if it is included in calculating total price which determines PM Driver eligibility (Table 8). Each
request needs to calculate if the PM driver needs to be adjusted, and the system should automatically add
a PM driver if none exists, or delete one PM driver and add another as the scope changes. The PM driver
should only be shown on reports where AT&T pricing is shown. Vendor-Only reports should not show the
PM driver.
Table 8 PM Drivers
Driver
ID
Category Driver Name
PM
Driver
Minimum
Amount
Maximum
Amount
PM01
Front
End
Project Management - SAQ
* Projected Order Value by end of SAQ
paypoints. Value: $0 - $5,000
SAQ $0.01 $5,000.00
PM02
Front
End
Project Management - SAQ
* Projected Order Value by end of SAQ
paypoints. Value: $5,001 -$30,000
SAQ $5,000.01 $30,000.00
PM03
Front
End
Project Management - SAQ
* Projected Order Value by end of SAQ
paypoints. Value: more than $30,000
SAQ $30,000.01 No Max
PM04
Front
End
Project Management - CON
* Projected Order Value by end of CON
paypoints. Value: $0 - $5,000
CON $0.01 $5,000.00
PM05
Front
End
Project Management - CON
* Projected Order Value by end of CON
paypoints. Value: $5,001 -$30,000
CON $5,000.01 $30,000.00
PM06
Front
End
Project Management - CON
* Projected Order Value by end of CON
paypoints. Value: $30,001 - $60,000
CON $30,000.01 $60,000.00
PM07
Front
End
Project Management - CON
* Projected Order Value by end of CON
paypoints. Value: $60,001 - $120,000
CON $60,000.01 $120,000.00
PM08
Front
End
Project Management - CON
* Projected Order Value by end of CON
paypoints. Value: $120,001 - $250,000
CON
$120,000.0
1
$250,000.00
PM09
Front
End
Project Management - CON
* Projected Order Value by end of CON
paypoints. Value: $250,001 - $500,000
CON
$250,000.0
1
$500,000.00
PM10
Front
End
Project Management - CON
* Projected Order Value by end of CON
paypoints. Value: more than $500,000
CON
$500,000.0
1
No Max
Example: Since only one SAQ PM driver and one CON PM driver are allowed, the system must make that
calculation and indicate to the NORAD DBA any changes necessary to previous submissions. The PM driver
should be automatically added to the Request based on the scope total price. For example, if an initial
scope is created, for which the sum of the SAQ scope is $3,500, the PM driver will be a PM01. If a
subsequent request is created which adds $3,000 of SAQ scope for a total of $6,500, the system should add
a negative PM01 to the second request, and add a positive PM02. This will indicate to the NORAD DBA that
the PM01 currently in the OOM needs to be removed and a PM02 needs to be added.
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 29
32. Scope Management and Requisition Tool | AT&T Turf Project
Vendor-Submitted Scope
Summary: Users in the role of âVendorâ should be allowed to choose from all Active jobs in the market
where they are assigned as Vendor. They will be able to create a Request using the âScope Maintenance â
Create Initial/Add/Changeâ procedure. However, when they âApprove and Submitâ, the request would go
to the Project Managerâs work queue for approval, rather than the NORAD DBAâs queue. Once approved by
the Project Manager, the request would follow the same process as a Project Manager created request.
Request type will be recorded as âSAQ/ENG â Vendor Change Orderâ or âConstruction â Vendor Change
Orderâ then follows the same process as B&V initiated process after PM Approval. Is Change order different
output?
Other Scenarios: (Description of scenarios that may impact or change the process due to client
requirements.)
D. PREVIEW AND SUBMIT FOR NORAD PROCESSING
5. Preview
Upon completion of selection process for driver and WAs, the user will select the âPreview Before
Submittingâ button on the Scope Maintenance screen. Displays details of request based on two options
1) Only the drivers with Total Quantity not equal to zero, eliminating drivers not requested on this job
Or 2) Request Quantity not equal to zero displayed, eliminating drivers not on this request
Then the âPreviewâ screen should pop-up in a new (?) window or next screen. âPreviewâ will display results
of the scoping request with drivers and WAs to be submitted in summary as well.
Select Primary Vendor Total AT&T Job Price $ 10,255.23 Vendor Assignment Budget Amount
Assign all Site Acq to Primary Vendor AT&T Request Price $ 8,543.41 CENTERLINE SOLUTIONS $ 4,017.96
Assign all Engineering to Primary Vendor
Assign all Construction to Primary Vendor CENTERLINE SOLUTIONS LLC
Driver ID Driver Name
Request
Qty
Previous
Qty Total Qty UOM Category Type
Work
Code
Vendor
Assignment
Vendor
Budget (Each)
Vendor Budget
(This Request)
Vendor
Budget
(Full Job)
AT&T Price
(Each)
AT&T Price
(This Request)
30 MARCH 2014
AT&T Price
(Full Job)
AN01
RF Antenna Ins ta l l
* Fi rs t antenna 1 0 1 EA Ins ta l l Antenna C
CENTERLINE
SOLUTIONS LLC $ 377.53 $ 377.53 $ 377.53 $ 621.40 $ 621.40 $ 621.40
AN02
RF Antenna Ins ta l l
* Each add'l antenna 2 3 5 EA Ins ta l l Antenna C
CENTERLINE
SOLUTIONS LLC $ 106.61 $ 213.22 $ 533.05 $ 175.48 $ 350.96 $ 877.40
AN03 GPS/BCCH Antenna Ins ta l l 1 0 1 EA Ins ta l l Antenna C
CENTERLINE
SOLUTIONS LLC $ 200.32 $ 200.32 $ 200.32 $ 329.72 $ 329.72 $ 329.72
AN04
RRH (Remote Radio Head)
* Tower Mounted 1 0 1 EA Ins ta l l Antenna C
CENTERLINE
SOLUTIONS LLC $ 235.89 $ 235.89 $ 235.89 $ 388.26 $ 388.26 $ 388.26
CA06
OEM RF Cabinet Ins ta l l
* Indoor
* Each add'l cabinet 1 0 1 EA Ins ta l l Cabinet C
CENTERLINE
SOLUTIONS LLC $ 149.17 $ 149.17 $ 149.17 $ 245.52 $ 245.52 $ 245.52
CA70
Cabinet De-Ins ta l l
* 1s t Cabinet 1 0 1 EA Decom Cabinet C
CENTERLINE
SOLUTIONS LLC $ 502.00 $ 502.00 $ 502.00 $ 826.26 $ 826.26 $ 826.26
PM04
Project Management - CON
* Projected Order Value by end
of CON paypoints . Value: $0 -
$5,000 -1 1 0 EA Front End
Project
Manage $ - $ - $ - $1,185.38 $ (1,185.38) $ -
PM05
Project Management - CON
* Projected Order Value by end
of CON paypoints . Value: $5,001 -
$30,000 1 0 1 EA Front End
Project
Manage $ - $ - $ - $4,886.07 $ 4,886.07 $ 4,886.07
WA ID# WA Name
Request
Qty
Previous
Qty Total Qty UOM Category
Work
Code
Vendor
Assignment Vendor Cost Markup AT&T Price Inclusions Exclusions
CAWA Cabinet - Work Authorization (WA1)0 0 10 EA Cost-Plus C
CENTERLINE
SOLUTIONS LLC $ 150.00 $ 45.00 $ 1,545.00
Painting
Cabinets
CBWA Cabling - Work Authorization (WA1)00 0 100 EA Cost-Plus C
CENTERLINE
SOLUTIONS LLC $ 5.20 $ 15.60 $ 535.60
Remove tray
from rooftop,
add coax,
replace tray.
Paint tray.
Documents:
Award Amount
$ 3,500.00
C:Usersfri59577
DocumentsAT&T
Approval Email.pdf
Reports
Scope Work
Format Price Display Selection Code
Excel AT&T-Only Current Request w/ Blanks All
Create Report
Actions
Approve &
Submit
Save as Draft
Save as Template
Back to Scoping
Screen
Attach / Upload
Docs
Main Menu
2
1
3
5
4
33. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Areas of information circled above display:
1. Budget / Award amount
ďˇ As scope is assigned to a vendor, the sum total of the Vendor Budget for that vendor should be
displayed on the screen. If there are multiple vendors assigned, the sum total of the Vendor
Budget for each vendor should be shown. The âUnassignedâ budget amount should also be
shown to the user in this manner.
ďˇ In addition, the âVendor Budget Amountâ is not always the amount of money given to a vendor
for the scope of work. Therefore, for all âConstructionâ requests, an âAward Amountâ can be
manually input by the user, which should be tracked separately, and be included in any VPOR
request exported from the system for processing into a vendor PO using the VPOR Workflow
process. It is possible that a user may assign a vendor for most, but not all, scope items at the
same time. The user would then input an Award Amount to the total of the scope that has been
assigned. If at a later time, the user assigned the remaining items to the same vendor, the
system should increase the Award Amount by the Budget Amount of the additional assigned
scope, unless the user over-rides the Award Amount. In both cases, the additional items
assigned, the change in Award Amount, and the Total Award Amount should be exported with
the VPOR request.
ďˇ For all âSite Acq/Engineeringâ requests, the Vendor Budget Amount must be able to be
overridden with an âAward Amountâ on a line-by-line level. This is used in circumstances where
the vendor budget in the system is not acceptable (vendor will take less than budget, or will not
do the work for the budget price). In the case when the vendor budget amount is overridden,
the user should not be able to enter an award amount that exceeds the AT&T Price from the
Master Driver Table (i.e. we cannot pay more than what we get from AT&T).
2. Vendor Assignment at Request level â Ability to assign a vendor using this screen. This process is
detailed in Assign work to Vendors Section below.
ďˇ When âAssign all xxxxx to Primary Vendorâ is checked, all drivers/WAâs with corresponding work
code âSâ, âEâ, or âCâ are automatically assigned to that vendor. Otherwise, the Vendor
Assignment would happen line by line. Users would not see nor be allowed to select the Primary
Vendor for work codes they do not have permissions for.
Table 9 Report Options
3. Summary information â Recap
totals for review
1. Total AT&T Job Price (sum total
of AT&T Price for all requests on
job)
2. AT&T Request Price (sum total
of AT&T Price for this request
only)
4. Report information â Several
Criteria Display Options
Format(s) 1 Excel or CSV / PDF (Blue Beam?
Price
Displayed
2
Option
Selection
3
Work Code 4 All, S, E or C
reports will be available to the user
on the scoping screen limited by user permissions (Table 9).
AT&T Only
Vendor Pricing
Vendor & AT&T Pricing
Quantity Only â No Pricing
Current Request with or w/o Blanks
Total Scope with or w/o Blanks
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 31
34. Scope Management and Requisition Tool | AT&T Turf Project
5. Navigation actions
ďˇ Approve & Submit (Vendor should select which PM to direct for approval)
ďˇ Back to Scoping Screen
ďˇ Attach / Upload Docs
ďˇ Main Menu
ďˇ Save as Draft
ďˇ Save as Template
Users in the âVendorâ role should not see the âRequest Recapâ, âRequest Level Vendor Assignment
Optionâ, or the âSummary Informationâ. In addition, users in the âVendorâ role require the ability to select
a user in the PM role for the associated market, and their request should be submitted to that user for
review and approval. The request would appear in the PMâs work queue.
6. Attach / Upload Docs
Summary: A general area for document upload should be available. Some requests will require documents
for verification and submission to AT&T. These documents will need to be exported along with the
VPOR/OOM requests, typically uploaded to NORAD by the NORAD DBA.
Inputs: If a certain combination of WA ID, Category, and AT&T Price is selected by the user, a document
upload will be required. The document upload process should require the user to select a âtype of
documentâ (Table 10).
If one or more of these document types are flagged as required due to WA selection, the system should
check if the corresponding document has been uploaded in order for the user to submit the request.
Documents uploaded to the system should be auto-named per FileNET naming conventions.
Ideal solution would upload directly to document repository system â documentum for upload to FileNET,
reducing the amount of document redundancy and duplication.
Table 10: Document Type Upload
Type of Document
Description
(meaning & purpose
explicit)
Business Rules â Tool requires document
upload if âYâ is selected in this column in
the Master WA Information table.
Appendix E Purchasing Decision
Statement
Requires Appendix E Upload if >$5,000
Fixed Price Quote Fixed price quote Requires Quote if Category = Fixed
AT&T Approval
AT&T Approval Email Available, but not required.
Email
Site Fee Receipt Site Fee Requires Receipt if WA ID# = SIFE_SAQ
32 MARCH 2014
35. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
or SIFE_CON
Other General placeholder for
documents not fitting the
above descriptions
Available, but not required
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 33
36. Scope Management and Requisition Tool | AT&T Turf Project
7. Approve & Submit
Summary: Once the scope has been entered into the Driver and the WA sections, the Preview process has
been completed, the PM will Approve & Submit. The Request Status âPM Submittedâ will appear in the
NORAD DBA work queue (See Table 2 Request Status Values).
Inputs: Authority / Workflow - See Request Type status above.
Scenarios: (Description of scenarios that impact the process due to changing client requirements.)
A. Request is no longer needed. Should there be a Delete Req button if the request has not been
submitted yet? This is different from a âVoidedâ request, which has been submitted but is no
longer needed.
E. REVIEW AND SUBMIT TO AT&T FOR PO
8. NORAD OOM Entry & Record OOM ID
Table 11: NORAD Work Queue
NORAD Work Queue Current Request Status NORAD Actions Next Request Status
NORAD Entry PM Approved Export file to NORAD Exported or
Accumulate
Accumulate-Ready to
Submit
Export file to NORAD Exported or
Accumulate
PM Approved Audit entries and document
compliance
NORAD DBA Rejected
(back to PM Queue)
Hold for Accumulate Accumulate No Action until greater than
$5,000 or approved to submit
Accumulate- Ready
to Submit
Waiting for Approval Exported Entry to NORAD is in Progress
Enter OOMID into Scoping
tool when complete
OOM Submitted
OOM Submitted Submit and receive AT&T PM
for approval
OOM Approved
Summary: NORAD DBA Work
Queue is divided into 3 action
areas:
1. NORAD Entry: Review for
accuracy and proper
supporting documents, then
export for entry to NORAD
system. See NORAD
Processing below.
2. Hold for Accumulate:
o If all âPM Approvedâ un-submitted
Figure 26: NORAD Work Queue
requests total less than $5,000
o Request type is not Initial Scoping or Final True Up.
34 MARCH 2014
37. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
o AT&T PO has been received
o Initial Scoping request on same job is status = Approved
Hold in this status until
another request is
created and the total of
accumulated requests
exceeds $5,000.
1. Waiting for approval:
NORAD DBA initiates an
âApprove Scope & Enter
into NORADâ which
creates a PDF entry form
for NORAD, which
include the Request
Quantity (highlighted for
ease of entry), Previous
Quantity, and Total
Quantity.
10085 FA LOCATION: 10978044
REQUEST #
REQUEST STATUS Draft SITE ID#: COU4584
COORS FIELD MARKET: Colorado
LTE PROJECT # 122061
WAVE 2 PHASE # 8345
MRUTH123948
Active Total AT&T Job Price $ 10,255.23
AT&T Request Price $ 7,328.89
SITE NAME:
BV INITIATIVE:
BV SUB-INITIATIVE:
JOB ID#
JOB STATUS:
Driver ID Driver Name Request Qty UOM Category Type
Figure 27: Example NORAD Entry Format
Work
Code
Previous
Qty Total Qty
AT&T Price
(Each)
AT&T Price
(This Request)
AT&T Price
(Full Job) Driver Exception Comment
AN01
RF Antenna Ins ta l l
* Fi rs t antenna 1 EA Ins ta l l Antenna C 0 1 $ 621.40 $ 621.40 $ 621.40
AN02
RF Antenna Ins ta l l
* Each add'l antenna 2 EA Ins ta l l Antenna C 3 5 $ 175.48 $ 350.96 $ 877.40
AN03 GPS/BCCH Antenna Ins ta l l 1 EA Ins ta l l Antenna C 0 1 $ 329.72 $ 329.72 $ 329.72
AN04
RRH (Remote Radio Head)
* Tower Mounted 0 EA Ins ta l l Antenna C 1 1 $ 388.26 $ - $ 388.26
CA06
OEM RF Cabinet Ins ta l l
* Indoor
* Each add'l cabinet 1 EA Ins ta l l Cabinet C 0 1 $ 245.52 $ 245.52 $ 245.52
CA70
Cabinet De-Ins ta l l
* 1s t Cabinet 0 EA Decom Cabinet C 0 1 $ 826.26 $ - $ 826.26
2nd cabinet de-ins ta l l
reques ted after original s cope
completed. Emai l approval
attached.
PM04
Project Management - CON
* Projected Order Value by end
of CON paypoints . Value: $0 -
$5,000 -1 EA Front End Project Manage C 1 0 $1,185.38 $ (1,185.38) $ -
PM05
Project Management - CON
* Projected Order Value by end
of CON paypoints . Value: $5,001 -
$30,000 1 EA Front End Project Manage C 0 1 $4,886.07 $ 4,886.07 $ 4,886.07
WA ID# WA Name Request Qty UOM Category
Work
Code
Previous
Qty Total Qty Vendor Cost
AT&T Price
(This Request)
AT&T Price
(Full Job) Inclusions Exclusions
CAWA Cabinet - Work Authorization (WA) 10 EA Cost-Plus C 0 10 $ 150.00 $ 1,545.00 $ 1,545.00 Painting Cabinets
CBWA Cabling - Work Authorization (WA) 100 EA Cost-Plus C 0 100 $ 5.20 $ 535.60 $ 535.60
Remove tray from rooftop,
add coax, replace tray. Paint
tray.
Documents:
C:Usersfri59577
DocumentsAT&T
Approval Email.pdf
Approve Scope &
Enter Into NORAD Reject Print to PDF Export to Excel
A future generation of this project will interface directly with the NORAD system, removing the need for
Request export and manual NORAD entry.
Overview of AT&T Processing
When a PM-Approved Request enters the NORAD DBAâs work queue, the NORAD DBA will review for
accuracy and proper supporting documents, and make sure the WA Inclusions (5 Wâs) and Driver Exception
Comments are proper and include all the information required by AT&T. Due to this requirement, the
NORAD DBA should have modify access to edit the inclusions and exclusions section of the Request. Once
reviewed and deemed correct, the NORAD DBA will then export the request for entry to NORAD system.
The NORAD DBA will open a new revision in NORAD for the job, input the scope listed on the Request, and
submit to AT&T for approval. The NORAD DBA will also upload any backup documents provided with the
Request into NORAD. They will also enter the OOMID provided by NORAD into the system per the OOMID
Entry process (Figure 28).
If AT&T OOM Status Value ď SMART Request Status
= OOM Approved; Archived; Archived-Approved,
then ď OOM Approved
= OOM â Disapproved; Archived-Disapproved; Auto
Cancelled, then ď OOM Rejected
= Waiting âon AT&T Nameâ, then ď OOM Submitted
= Draft, then ď Exported
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 35
38. Scope Management and Requisition Tool | AT&T Turf Project
After âApprove Scope & Enter into NORADâ button is
pressed on prior screen NORAD DBA will enter OOMID
assigned to the request by NORAD.
NORAD DBA Rejected: If the Request is missing backup documents, has incomplete driver exception
comments, or was submitted on the wrong project, the NORAD DBA will click the âRejectâ button, which
will then change the Request Status to âNORAD DBA Rejectedâ. The NORAD DBA should reject a Request
due to:
⢠Missing backup documents
⢠Incomplete driver exception comments
⢠Submittal on wrong project
Figure 28: NORAD OOMID Entry
After a Request has been rejected by the NORAD DBA, it should go back into the PMâs Work Queue for
adjustments and resubmittal.
Bulk upload of OOMIDâs: There should be the ability for the NORAD DBA to upload multiple OOMIDâs at
the same time, so bulk requests can be assigned OOMIDâs.
Final True up
If the Request Type = âSAQ/ENG â Final True Upâ, any other âSAQ/ENGâ requests currently in Accumulate
status for that job will be processed for OOM entry along with the Final True Up request. If the Request
Type = âConstruction â Final True Upâ, ALL requests currently in Accumulate status for that job will be
processed for OOM entry along with the Final True Up request in order to make sure that any scope in
accumulate status is included on a final OOM true up.
F. ASSIGN WORK TO VENDORS
Summary: Each driver and WA on a request will need to be assigned to an external or internal âvendorâ to
perform the work. A Vendor is assigned to the work, and then a VPOR âform is exportedâ for import into
Quickbase (See Example Example VPOR.xlsx) The VPOR is âprocessedâ via the QB PO Request Workflow.
(See Supporting Docs Quickbase VPOR Workflow training_Execution_130401.pdf). The Vendor PO #, Status
and Amount of the Vendor PO Request will need to be brought back into the tool if possible:
Vendor Selection Rules
36 MARCH 2014
39. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
ďˇ Vendor is approved for type of work as indicated in the Vendor Information Master Table (See
Master Vendor Information section)
ďˇ Vendor is approved for the Jobâs market
ďˇ Work type code = Vendor work type code (C = Construction Vendor; S = Site Acq Vendor; E =
Engineering Vendor)
ďˇ Request Status is not in Rejected Status
Vendor Assignment rules
ďˇ Assignment of Vendors will be related to user permissions which relate Engineering, Site Acq, or
Construction work codes and restrict activity to equal work codes for 1) user permissions, 2)
Vendor assignment and 3) line item driver and/or WA scope. Only those drivers/WAâs with a work
code matching the corresponding Vendor work code is allowed to be selected/modified.
ďˇ User must be able to enter an âAward Amountâ for all scope assigned to a specific vendor. Value in
the âAward Amountâ will override the âBudget Amountâ exported to total vendor PO amount
requested from procurement.
9. Assign Vendor
There are four ways a user may assign scope to a vendor:
1. Preview view (See Scope Maintenance Add/Change section)
2. Assign Vendor view from Main Menu
a. Assign By Request
(Figure 30-32)
b. View All Un-Assigned
Scope (Figure 33)
c. Recent Requisitions
Without Vendor
Assignments (Figure 29)
Detail assignment in the Preview
view can be selected in two ways:
ďˇ Assign vendor by choosing Primary Vendor
ďˇ Assign vendor by individual driver or WA
Figure 29: Assign Vendor view from Main Menu
Assign By Request
All requests that have any line item with un-assigned scope are listed on the âSelect Requestâ screen. Users
select a request to add vendor assignments to.
*Only shows
requests that have
drivers and WAâs
that are unassigned.
Figure 30: Assign Vendor - Select Request
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 37
40. Scope Management and Requisition Tool | AT&T Turf Project
Detailed Assignment of Primary Vendor
The âPreviewâ screen
functionality in the Scope
Maintenance Add/Change
process can be leveraged to
assign a Vendor to the
work when Primary Vendor
is checked. Primary vendor
assignment automatically
assigns all unassigned
drivers and WAâs with the
corresponding work code
to that vendor. Vendor
assignments for individual
lines become read-only. The Primary Vendor exists on a Job level, so any subsequent requests created on
that Job for that work code are automatically assigned to the primary vendor for the work type/code
selected. Only the âAssign all Construction to Primary Vendorâ checkbox will be selected by default.
If a Primary Vendor has been selected, and drivers have been assigned to that vendor and the Primary
Vendor checkbox then gets un-checked, the vendors assigned to those drivers should stay as-is until
manually changed.
Detailed Assignment of Vendor by Line Item
When the Assign Primary Vendor checkboxes are not checked, the user is able to select a vendor line-by-line,
Figure 31: Detailed Assignment of Primary Vendor
for each driver and WA with a quantity greater than 0.
As one or more vendors are
chosen, the Total Vendor
Budget Amount for that
vendor should be displayed on
the screen. If there are
multiple vendors assigned, the
sum total of the Vendor
Budget for each vendor
should be shown. The
âUnassignedâ budget amount
should also be shown to the
user in this manner. The
Vendor Budget and Award
Amount should be treated on
a *By Vendor â By Job* basis
Figure 32: Assign Vendor - Assign by Request
38 MARCH 2014
41. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
in all circumstances, and vendors will only be receiving one PO for the whole Job. This PO will be
incrementally adjusted to account for additions and reductions in scope.
The system must be able to assign multiple vendors to a particular driver line item. For example, in some
markets, drivers PW11 and TL01 may be assigned to multiple vendors concurrently.
View All Un-Assigned Scope
If the user selects âView All Un-
Assigned Scopeâ from the
âAssign Vendorâ screen, they
will be taken to a report that
shows all scope that has not
been assigned to a vendor yet.
The user can filter by various
attributes to narrow down the
choices, and then they can
assign vendors to each driver or WA. One PO per job, with tracking of what has been exported
Figure 33 Assign Vendor - View all un-assigned scope
for VPOR (See Export VPOR Section). Recap screen gives ability to change the Award amount
that will be sent to procurement for purchase order.
Figure 34: Add /Change Scope Vendor PO History
Scenarios: (Description of scenarios that may impact or change the process due to changing client
requirements.)
A. Same driver in multiple quantities needs to be given to different vendors.
B. Multiple quantities of the same driver need to be given to different vendors. One or more of these
drivers will not be requested from AT&T.
C. Individual driver pricing over-rides.
D. Original GC does not finish site. New GC needs to be brought in and receives new PO. Original GC
gets paid partial driver/WA amount for work complete. New GC gets other portion.
E. Multiple vendors for one driver (i.e. 1 vendor doing 1 AE03, another vendor doing another AE03).
F. Vendor POs that do not go to into the OOM.
G. AT&T Driver and Vendor Driver do not match 1 to 1 (i.e. Get ST02 from AT&T, give ST02A, ST02B, or
ST02C to vendor)
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 39
42. Scope Management and Requisition Tool | AT&T Turf Project
10. Export VPOR
Summary: Once scope has been assigned to one or more vendors, it needs to be exported from the tool
and imported into QB for processing through the Quickbase VPOR Workflow (Automatic export?). An
example of a current VPOR request is located in supporting documents.
Inputs: The scope should be exported once it fulfills the following rules:
Vendor Assignment = Not Blank
Request Status = Accumulate, OOM Approved
Line Item Export Status = Not Exported
All new drivers and WAâs assigned to a vendor for a Job should be exported at one time, regardless if they
are on multiple Requests. The export should reference the existing Vendor PO # (if one has been created)
to allow Procurement to edit an existing PO, rather than create a new PO. (See Supporting Docs Example
VPOR.xlsx)
For example, a user may create a Request with 30 scope items. 18 of these items may be assigned at the
time the request was created and submitted for processing and entry into NORAD. Once the OOM has been
approved, the system needs to export a VPOR request for the vendor(s) assigned to those 18 items. The
VPOR request would flow through the VPOR Workflow outside of the tool, and Procurement will create a
vendor PO for each vendor and assign those POs numbers. That number needs to be known to the tool, so
at a later time, if the user assigns some or all of the remaining 12 items to the same vendor, the VPOR
request that is exported from the tool includes the indication to Procurement that the vendor has already
been assigned a PO number, and the additional scope needs to be added to the existing vendor purchase
order.
In the example above, if a user assigns additional scope to a vendor after the initial VPOR request has been
exported, the system should recognize that a new VPOR request with the remaining 12 items needs to be
exported because the status of those line items has changed from Vendor Assignment = Blank to Vendor
Assignment â Blank and the Line Item Export Status = Not Exported.
Future discussions will need to take place on how the VPOR export will be imported into Quickbase for
processing. If automatic export and import can be accomplished, it is acceptable to batch exports to every
hour or two, rather than immediately.
If a vendor is assigned to a scope line item, either via the âPrimary Vendorâ process, or individually, the line
item has been exported to a VPOR, and a user with the proper permissions then selects a DIFFERENT
vendor for that line, the system should treat that action as a re-assignment of the work to a different
vendor, which will cause two actions to take place:
1. The system will export a VPOR with negative quantities for the previously assigned vendor,
causing the VPOR to flow through the VPOR Workflow and Procurement to cancel or reduce
the previously assigned vendorâs purchase order.
2. The system will export a VPOR with positive quantities for the newly assigned vendor, similar to
the standard VPOR export process.
40 MARCH 2014
43. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
A future generation of this project will consist of additional review and approval by Project Controls in the
tool, and direct communication to iProcurement for processing. This will eliminate the need for processing
via Quickbase.
BLACK & VEATCH | Scoping Process / SMART Functional Requirements 41
44. Scope Management and Requisition Tool | AT&T Turf Project
Maintenance & Supporting Processes
SUPPORTING PROCESSES
User Information & Log on
New users will be added to the User Information list by an Administrator. The administrator will then send
an âinviteâ to the user with a request to setup an account. Users will login with a standard username and
password. Out of scope for this project is methodology for external access to B&V systems.
The username will be based on the userâs email address or B&V sign on access methodology that will allow
external users to sign on without delay. Access to the system will only be granted after the userâs account
has been setup by an Administrator and the proper role, authority, and market have been selected. The
password will initially be system-generated with users allowed to change their passwords.
Access is required to grant access activities are based on the combination of:
ďˇ User role â level of authority (See Appendix Sample Authority and Approval Matrix)
a. Administrator â Full access to add / change all master and transaction data
b. Project Manager â Entry of request and scope. Authority to submit requests.
c. Project Facilitator â Entry of request and scope. No authority to submit requests.
d. Project Controls - Responsible for reviewing scope for accuracy
e. NORAD DBA - Responsible for entry of NORAD information and exporting VPORâs from tool
and uploading to Quickbase workflow
f. Vendor â Restricted to access to add / change scope assigned via change order request
screen. Users in Vendor role may only view existing scopes that have been assigned to that
vendor.
g. View only â display and reporting only capability
ďˇ Type of function - controls type of data displayed by
corresponding work code
ďˇ Geographic location â
a. Access to site information and pricing for only
those markets they have permission to see
b. Currently 9 market areas but could increase or
decrease as contracts change. These will
correspond to markets defined in masters.
Users must input the following information into the tool:
Table 12: User Information
Function
Corresponding
Work code
Site Acquisition S
Engineering E
Construction C
Materials M
User Information
User Profile
Data
Element
Description
(meaning & purpose
explicit)
(M /
O)
Business Rules
First
Name
M User Defined
Last M User Defined
42 MARCH 2014
45. AT&T Turf Project | SCOPE MANAGEMENT AND REQUISITION TOOL
Name
Vendor
Name
M Administrator-defined during initial user setup
and invite. Must either be B&V, OCI, or tie to a
vendor available in the scope maintenance tool
(allowable vendors)
Email M Administrator-defined during initial user setup
and invite. Used as login.
Address
Line 1
M User Defined
Address
Line 2
M User Defined
City M User Defined
State M User Defined
Zip M User Defined
Phone
M User Defined
Number
Initial User Screen
The initial user screen should have the following selection options:
Initial User Screen
Data Element
Description
(meaning & purpose
explicit)
(M / O) Business Rules
Scope
Maintenance
Request Create/Select M Takes user to Job Selection screen.
Work Queue Shows current in-process
requests
M See My Work Queue
Master
Information
Submenu of maintenance
and supporting
information/tables
M See Master Data
Table 13: Initial User Screen
My Work Queue
The Work Queue is the screen where the user will see all
requests that have been created but have not been exported
by the NORAD DBA based on request status. There are three
Work Queues, one for the PM, one for the Vendor, and one
for the NORAD DBA (see Review and Submit to AT&T for PO
Section). Inside the work queue, the user should have the
ability to filter which Job Initiative(s) they see or do not see.
This information should be saved with the user information,
so if a user unchecks âLTEâ, they will never see any LTE
Select Job Initiatives to View in your Work Queue
JOB INITIATIVE
LTE 1st Carrier
LTE 2nd Carrier
UMTS 1st Carrier
UMTS 2nd Carrier
UMTS 3rd Carrier
UMTS 4th Carrier
UMTS 5th Carrier
New Site Build
Site Acq Only
Sector Add
Antenna mod
Generator
ETTCS
Microwave
BLACK & VEATCH | Maintenance & Supporting Processes 43
Save Cancel
Figure 35: Job Initiative Work Queue Selection
46. Scope Management and Requisition Tool | AT&T Turf Project
projects in their work queue. (See Table 2 Request Status Values).
Table 14: PM and Vendor Request Status Work Queue Flow
Work Queue Current Request
Status
Actions Next Request
Status
PM Draft Assigning drivers/WAs to
request
PM Approved
Vendor Submitted Review PM Approved
PM Rejected
PM Rejected? Wait for Vendor corrections Vendor Submitted
NORAD DBA Rejected Correct and re-submit PM Approved
OOM Rejected Correct & Resubmit or Cancel? PM Approved
Vendor
Queue
Draft Assigning drivers/WAs by
Vendor
Vendor Submitted
Vendor Submitted Wait for PM Approval PM Approved
PM Rejected
PM Rejected Correct & Resubmit Vendor Submitted
* NOTE: Assumptions â (See Request Status Table 2)
1 Daily report from ePOM can update OOM Status Value
2 When entered into NORAD an OOMID is manually entered by NORAD DBA
Build Templates
A mechanism for creation and modification of Driver and WA templates is necessary to speed up scope
entry. The Master Template Information table will be a repository where users can create and save scopes
for repeated use in the Scope Maintenance Screen. Created templates should be visible to other users with
the proper user rights and market rights. Users in the role of Project Manages and the role of
Administrator will need access to save an existing scope to a template to be retrieved during request select
input (See Preview Section).