NOTICE OF PUBLIC MEETING
*All times are approximate. The Permit Review Committee of the
Commission on Chicago Landmarks will meet immediately after the
conclusion of the Commission’s 12:45 p.m. meeting.
PERMIT REVIEW COMMITTEE
THURSDAY, May 13, 2015
City Hall, 121 N. LaSalle St., Room 201-A
AGENDA:
2:00 p.m.*
1. 1306 N. Dearborn Parkway 2nd
Ward
Three Arts Club
Proposed installation of exterior architectural illumination.
2. 360 N. Michigan 42nd
Ward
London Guarantee and Accident Building
Proposed 1-story retractable rooftop enclosure spanning across the historic building
and the new high-rise side addition and new architectural illumination.
3. 311-319 N. Morgan 27th
Ward
Proposed Fulton-Randolph Market District
Proposed adaptive reuse of 311 N. Morgan with a new 2-story addition into a new
hotel development. Proposed demolition of a preliminarily identified non-
contributing 1-story masonry structure at 319 N. Morgan. Proposed new construction
on the 319 N. Morgan site of a 4 and 7-story building connected to 311 N. Morgan.
Eleanor Esser Gorski, AIA
Director of Historic Preservation
Historic Preservation Division
Bureau Zoning and Land Use
Department of Planning and Development
PERMIT REVIEW COMMITTEE
Summary of projects and staff recommendations, May 13, 2015
1. 1306 N. Dearborn Parkway 2nd
Ward
Three Arts Club
Proposed installation of exterior architectural illumination.
Applicant: Restoration Hardware, applicant
Booth Hansen Architects, architect
Staff Recommendation:
Staff recommends that the Committee find that the project, with the following
condition, meets the criteria set forth in the Commission’s Rules and Regulations, the
Commission’s Guidelines for Alterations to Historic Buildings and New
Construction, and Standards 9 and 10 of the U.S. Secretary of the Interior’s
Standards for Rehabilitation of Historic Buildings and therefore, the project will not
have an adverse effect on the significant historical and architectural features of the
landmark property and approve the project with the following condition to be
reviewed for approval by the Historic Preservation staff:
1. The new exterior architectural illumination of the historic building is approved
as per drawings dated April 27, 2015, provided the illumination at the arched
openings above the main entry is adjusted to eliminate the visible “hotspot” at
the bottom of the arch.
2. 360 N. Michigan 42nd
Ward
London Guarantee and Accident Building
Proposed 1-story retractable rooftop enclosure spanning across the historic building
and the new high-rise side addition and new architectural illumination.
Applicant: John Rutledge, AG-OCG 360 North Michigan LLC - owner
Len Koroski, Goettsch Partners – architect
John Tess – Heritage Consulting
Staff Recommendation:
Staff recommends that the Committee find that the project, with the following
conditions, meets the criteria set forth in the Commission’s Rules and Regulations,
the Commission’s Guidelines for Alterations to Historic Buildings and New
Construction, and Standards 9 and 10 of the U.S. Secretary of the Interior’s
Standards for Rehabilitation of Historic Buildings and therefore, the project will not
have an adverse effect on the significant historical and architectural features of the
landmark property and approve the project with the following conditions to be
reviewed for approval by the Historic Preservation staff:
1. The new architectural illumination of the historic street facades and cupola as
per drawings dated 3/02/15 are approved as proposed;
2. The new 1-story retractable metal-and-glass rooftop addition, as shown on the
drawings dated 4/16/15, is approved as proposed. The metal mullions and
fascia shall be painted a color to match the penthouse brick color in a non-
reflective finish. Samples to be reviewed for approval by Historic
Preservation staff prior to order and installation;
3. The proposed insulated clear glazing units for the new curtain wall at the base
of the high-rise side addition (Viracon Clear VE24-2M) is approved; and,
4. All conditions of approval from the previous review of the overall project will
continue to be applicable (09/08/14).
3. 311 N. Morgan 27th
Ward
Proposed Fulton-Randolph Market District
Proposed adaptive reuse of 311 N. Morgan with a new 2-story addition into a new
hotel development. Proposed demolition of a preliminarily identified non-
contributing 1-story masonry structure at 319 N. Morgan. Proposed new construction
on the 319 N. Morgan site of a 4 and 7-story building connected to 311 N. Morgan.
Applicant: 311 North Morgan, LLC (Sterling Bay Company), owner
GREC Architects, LLC
Staff Recommendation:
Staff recommends that the Committee:
(A)Find that the 319 N. Morgan building, constructed c.1940, is non-contributing
to the proposed district and its demolition will not be an adverse effect;
(B) Find that the 311 N. Morgan building, the first floor constructed in 1921 and a
second floor added in 1923, is contributing to the proposed district.
The project is not subject to the provisions of Section 2-120-825 of the Municipal
Code of Chicago governing review of permits for the demolition of 40% or more
of any building or structure either designated as a “Chicago Landmark” or located
in any district designated as a “Chicago Landmark”.
Staff further recommends that the Committee find that the project, with the
following conditions, meets the criteria set forth in the Commission’s Rules and
Regulations, the Commission’s Guidelines for Alterations to Historic Buildings
and New Construction, and Standards 1, 2, 5, 6, 9, and 10 of the U.S. Secretary of
the Interior’s Standards for Rehabilitation of Historic Buildings and therefore, the
project will not have an adverse effect on the significant historical and
architectural features of the proposed landmark property and district and approve
the project with the following conditions:
Partial Demolition
1. Due to the deteriorated conditions of the masonry walls, highly
compressive soil conditions and extreme site constraints the proposed
demolition of the north (side), west (rear) and south (side) common brick
secondary facades of 311 N. Morgan is approved;
2. A report by a licensed structural engineer addressing the partial demolition
of the structure, relative to how the historic facade to remain in-situ should
be braced and protected during demolition and new construction, shall be
submitted for Historic Preservation staff review and approval, as part of
the permit plans. The recommended measures, sequencing, and
protections shall be incorporated in the structural and architectural
drawings.
Exterior Rehabilitation of 311 N. Morgan
3. As proposed the historic street-façade at 311 N. Morgan shall be repaired
in-situ and rehabilitated in accordance with the Commission’s standards
and guidelines as indicated by drawings prepared by BTL Architects, Inc.
and dated 4/2/15;
4. Select portions of the historic street facades that require reconstruction due
to deteriorated conditions shall use salvaged bricks as much as possible.
Any replacement brick and new mortar shall match the historic in size,
texture, color, finish, and profiles;
5. Enlarged dimensioned details of the new windows and storefronts shall be
included with the permit plans. The muntins may be simulated-divided-
lites but shall have a substantial profile with spacer bars and interior
profiles to replicate the historic profiles. The window and storefront
frames and mullions shall have a dark color/finish and the glazing shall be
clear glass;
6. Masonry repair and replacement details shall be included in the permit
application plans. Samples of any replacement stone, patching, and any
new masonry and mortar shall match the historic in size, color, profile,
texture and type and shall be reviewed and approved by Historic
Preservation staff prior to order and installation;
7. The 2-story rooftop addition, setback approximately 7’ from Morgan
Street, is approved as proposed;
New Construction
8. As proposed, the 4-story and 7-story portions of the complex, including
the 1-story enclosure, are approved as submitted;
9. Enlarged storefronts, windows details, exterior wall details and metal
finish sample shall be submitted as part of the permit application and
subject to staff review and approval;
10. Any signage shall be permitted separately and reviewed and approved by
Historic Preservation staff prior to order and installation; and,
11. Proposed brick colors and finishes are approved as submitted.

More Related Content

What's hot (18)

MRA Portfolio
MRA PortfolioMRA Portfolio
MRA Portfolio
 
Vancouver Convention Centre Vault Repairs
Vancouver Convention Centre Vault RepairsVancouver Convention Centre Vault Repairs
Vancouver Convention Centre Vault Repairs
 
190 S Orange
190 S Orange190 S Orange
190 S Orange
 
Projects presentation1
Projects presentation1Projects presentation1
Projects presentation1
 
Project List
Project ListProject List
Project List
 
Biron Resume 3
Biron Resume 3Biron Resume 3
Biron Resume 3
 
Case Study 2- June 14Ro 2016
Case Study 2-  June 14Ro  2016Case Study 2-  June 14Ro  2016
Case Study 2- June 14Ro 2016
 
Case Studies
Case StudiesCase Studies
Case Studies
 
MECS Projects _28-June-2016_
MECS Projects _28-June-2016_MECS Projects _28-June-2016_
MECS Projects _28-June-2016_
 
Big Water Visitor Center
Big Water Visitor CenterBig Water Visitor Center
Big Water Visitor Center
 
Biomed realty-emeryville-center-innovation
Biomed realty-emeryville-center-innovationBiomed realty-emeryville-center-innovation
Biomed realty-emeryville-center-innovation
 
Project list
Project listProject list
Project list
 
"Autohoods" presentation
"Autohoods" presentation"Autohoods" presentation
"Autohoods" presentation
 
2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built
2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built
2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built
 
91 Design Build Update
91 Design Build Update91 Design Build Update
91 Design Build Update
 
site monitoring project
site monitoring projectsite monitoring project
site monitoring project
 
Buildings structural repair consultant within estimated repair & painting sol...
Buildings structural repair consultant within estimated repair & painting sol...Buildings structural repair consultant within estimated repair & painting sol...
Buildings structural repair consultant within estimated repair & painting sol...
 
Collins House Melbourne eBrochures - Call +65 9189 8321 for Booking
Collins House Melbourne eBrochures - Call +65 9189 8321 for BookingCollins House Melbourne eBrochures - Call +65 9189 8321 for Booking
Collins House Melbourne eBrochures - Call +65 9189 8321 for Booking
 

Viewers also liked

Ufo's observed over norway
Ufo's observed over norwayUfo's observed over norway
Ufo's observed over norwayClifford Stone
 
презентация развивающей среды
презентация развивающей средыпрезентация развивающей среды
презентация развивающей средыlesjunia
 
Cuidados de enfermería en el preoperatorio
Cuidados de enfermería en el preoperatorioCuidados de enfermería en el preoperatorio
Cuidados de enfermería en el preoperatorioTeresa Pérez Disla
 

Viewers also liked (7)

Ufo's observed over norway
Ufo's observed over norwayUfo's observed over norway
Ufo's observed over norway
 
Ufos untold story
Ufos untold storyUfos untold story
Ufos untold story
 
Derecho informatico
Derecho informatico Derecho informatico
Derecho informatico
 
Ley de convivencia escolar
Ley de convivencia escolarLey de convivencia escolar
Ley de convivencia escolar
 
презентация развивающей среды
презентация развивающей средыпрезентация развивающей среды
презентация развивающей среды
 
K N - TW - Kolor
K N - TW - KolorK N - TW - Kolor
K N - TW - Kolor
 
Cuidados de enfermería en el preoperatorio
Cuidados de enfermería en el preoperatorioCuidados de enfermería en el preoperatorio
Cuidados de enfermería en el preoperatorio
 

Similar to Public meeting notice for Permit Review Committee

An over view of the high rise buildings
An over view of the high rise buildingsAn over view of the high rise buildings
An over view of the high rise buildingshlksd
 
Al-Nemer evaluation report.pdf
Al-Nemer evaluation report.pdfAl-Nemer evaluation report.pdf
Al-Nemer evaluation report.pdfmjnasarkhanjamal
 
IRJET-Email Tracking System
IRJET-Email Tracking SystemIRJET-Email Tracking System
IRJET-Email Tracking SystemIRJET Journal
 
Buildings structural audit and Civil repairs painting works
Buildings structural audit and Civil repairs painting worksBuildings structural audit and Civil repairs painting works
Buildings structural audit and Civil repairs painting worksCSR Consultant and Associates
 
Tarek Ewiss Resume- to date 2016 1
Tarek Ewiss Resume- to date 2016 1Tarek Ewiss Resume- to date 2016 1
Tarek Ewiss Resume- to date 2016 1Tarek Ewiss
 
Struct Audit Mktg
Struct Audit MktgStruct Audit Mktg
Struct Audit Mktgstructaudit
 
Rehab of an existing mse(1)
Rehab of an existing mse(1)Rehab of an existing mse(1)
Rehab of an existing mse(1)Dr. Ganesh Kame
 
Item # 4 - 259 Montclair
Item # 4 - 259 MontclairItem # 4 - 259 Montclair
Item # 4 - 259 Montclairahcitycouncil
 
Item # 6 - 270 E. Oakview Place
Item # 6 - 270 E. Oakview PlaceItem # 6 - 270 E. Oakview Place
Item # 6 - 270 E. Oakview Placeahcitycouncil
 
Item # 4 - 117 Claywell (Significance & Compatibility Review)
Item # 4 - 117 Claywell (Significance & Compatibility Review)Item # 4 - 117 Claywell (Significance & Compatibility Review)
Item # 4 - 117 Claywell (Significance & Compatibility Review)ahcitycouncil
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard buildingBirukYared3
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof ReplacementFairfax County
 
Case studies for strengthening of existing structures
Case studies for strengthening of existing structuresCase studies for strengthening of existing structures
Case studies for strengthening of existing structuresParamaAthmeka
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentationAKASHGARG131
 

Similar to Public meeting notice for Permit Review Committee (20)

An over view of the high rise buildings
An over view of the high rise buildingsAn over view of the high rise buildings
An over view of the high rise buildings
 
Walkie Talkie.pptx
Walkie Talkie.pptxWalkie Talkie.pptx
Walkie Talkie.pptx
 
Al-Nemer evaluation report.pdf
Al-Nemer evaluation report.pdfAl-Nemer evaluation report.pdf
Al-Nemer evaluation report.pdf
 
IRJET-Email Tracking System
IRJET-Email Tracking SystemIRJET-Email Tracking System
IRJET-Email Tracking System
 
Buildings structural audit and Civil repairs painting works
Buildings structural audit and Civil repairs painting worksBuildings structural audit and Civil repairs painting works
Buildings structural audit and Civil repairs painting works
 
Item # 3 - 321 Argo
Item # 3 - 321 ArgoItem # 3 - 321 Argo
Item # 3 - 321 Argo
 
Tarek Ewiss Resume- to date 2016 1
Tarek Ewiss Resume- to date 2016 1Tarek Ewiss Resume- to date 2016 1
Tarek Ewiss Resume- to date 2016 1
 
Struct Audit Mktg
Struct Audit MktgStruct Audit Mktg
Struct Audit Mktg
 
Rehab of an existing mse(1)
Rehab of an existing mse(1)Rehab of an existing mse(1)
Rehab of an existing mse(1)
 
Btech
BtechBtech
Btech
 
Item # 4 - 259 Montclair
Item # 4 - 259 MontclairItem # 4 - 259 Montclair
Item # 4 - 259 Montclair
 
Item # 6 - 270 E. Oakview Place
Item # 6 - 270 E. Oakview PlaceItem # 6 - 270 E. Oakview Place
Item # 6 - 270 E. Oakview Place
 
Item # 4 - 117 Claywell (Significance & Compatibility Review)
Item # 4 - 117 Claywell (Significance & Compatibility Review)Item # 4 - 117 Claywell (Significance & Compatibility Review)
Item # 4 - 117 Claywell (Significance & Compatibility Review)
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Retrofitting of buildings
Retrofitting of buildingsRetrofitting of buildings
Retrofitting of buildings
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
 
Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof Replacement
 
Case studies for strengthening of existing structures
Case studies for strengthening of existing structuresCase studies for strengthening of existing structures
Case studies for strengthening of existing structures
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 

More from West Central Association

WCA/MPC Study Community Presentation - November 30, 2016
WCA/MPC Study Community Presentation - November 30, 2016WCA/MPC Study Community Presentation - November 30, 2016
WCA/MPC Study Community Presentation - November 30, 2016West Central Association
 
West loop Parking Plan Community Meeting Presentation
West loop Parking Plan Community Meeting PresentationWest loop Parking Plan Community Meeting Presentation
West loop Parking Plan Community Meeting PresentationWest Central Association
 
Metra Presentation - A Vision for the Fulton Market Area
Metra Presentation - A Vision for the Fulton Market AreaMetra Presentation - A Vision for the Fulton Market Area
Metra Presentation - A Vision for the Fulton Market AreaWest Central Association
 
Fulton Market Taskforce Meeting 10-04-2017
Fulton Market Taskforce Meeting 10-04-2017Fulton Market Taskforce Meeting 10-04-2017
Fulton Market Taskforce Meeting 10-04-2017West Central Association
 
STALLED OUT How Empty Parking Spaces Diminish Neighborhood Affordability
STALLED OUT How Empty Parking Spaces Diminish Neighborhood AffordabilitySTALLED OUT How Empty Parking Spaces Diminish Neighborhood Affordability
STALLED OUT How Empty Parking Spaces Diminish Neighborhood AffordabilityWest Central Association
 
WCA/MPC Plan Presentation - Community Meeting
WCA/MPC Plan Presentation - Community MeetingWCA/MPC Plan Presentation - Community Meeting
WCA/MPC Plan Presentation - Community MeetingWest Central Association
 
IMDC Releases Draft Master Plan for Public Feedback Period
IMDC Releases Draft Master Plan for Public Feedback PeriodIMDC Releases Draft Master Plan for Public Feedback Period
IMDC Releases Draft Master Plan for Public Feedback PeriodWest Central Association
 
Two Fulton Market District Projects Approved!
Two Fulton Market District Projects Approved!Two Fulton Market District Projects Approved!
Two Fulton Market District Projects Approved!West Central Association
 
Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014West Central Association
 
Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14West Central Association
 
Randolph-Fulton Market Historical District Guidelines
Randolph-Fulton Market Historical District GuidelinesRandolph-Fulton Market Historical District Guidelines
Randolph-Fulton Market Historical District GuidelinesWest Central Association
 
Advancing Illinois Medical District Opportunities
Advancing Illinois Medical District OpportunitiesAdvancing Illinois Medical District Opportunities
Advancing Illinois Medical District OpportunitiesWest Central Association
 
Fulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 WorkshopFulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 WorkshopWest Central Association
 

More from West Central Association (18)

WCA/MPC Study Community Presentation - November 30, 2016
WCA/MPC Study Community Presentation - November 30, 2016WCA/MPC Study Community Presentation - November 30, 2016
WCA/MPC Study Community Presentation - November 30, 2016
 
Metra Station - Fulton Market/Kinzie
Metra Station - Fulton Market/KinzieMetra Station - Fulton Market/Kinzie
Metra Station - Fulton Market/Kinzie
 
West loop Parking Plan Community Meeting Presentation
West loop Parking Plan Community Meeting PresentationWest loop Parking Plan Community Meeting Presentation
West loop Parking Plan Community Meeting Presentation
 
Metra Presentation - A Vision for the Fulton Market Area
Metra Presentation - A Vision for the Fulton Market AreaMetra Presentation - A Vision for the Fulton Market Area
Metra Presentation - A Vision for the Fulton Market Area
 
Fulton Market Taskforce Meeting 10-04-2017
Fulton Market Taskforce Meeting 10-04-2017Fulton Market Taskforce Meeting 10-04-2017
Fulton Market Taskforce Meeting 10-04-2017
 
West Loop Design Guidelines Draft
West Loop Design Guidelines DraftWest Loop Design Guidelines Draft
West Loop Design Guidelines Draft
 
Madison Street Committee Presentation
Madison Street Committee PresentationMadison Street Committee Presentation
Madison Street Committee Presentation
 
STALLED OUT How Empty Parking Spaces Diminish Neighborhood Affordability
STALLED OUT How Empty Parking Spaces Diminish Neighborhood AffordabilitySTALLED OUT How Empty Parking Spaces Diminish Neighborhood Affordability
STALLED OUT How Empty Parking Spaces Diminish Neighborhood Affordability
 
A Future for the Near West Side
A Future for the Near West SideA Future for the Near West Side
A Future for the Near West Side
 
WCA/MPC Plan Presentation - Community Meeting
WCA/MPC Plan Presentation - Community MeetingWCA/MPC Plan Presentation - Community Meeting
WCA/MPC Plan Presentation - Community Meeting
 
IMDC Releases Draft Master Plan for Public Feedback Period
IMDC Releases Draft Master Plan for Public Feedback PeriodIMDC Releases Draft Master Plan for Public Feedback Period
IMDC Releases Draft Master Plan for Public Feedback Period
 
Two Fulton Market District Projects Approved!
Two Fulton Market District Projects Approved!Two Fulton Market District Projects Approved!
Two Fulton Market District Projects Approved!
 
Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014
 
Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14
 
Randolph-Fulton Market Historical District Guidelines
Randolph-Fulton Market Historical District GuidelinesRandolph-Fulton Market Historical District Guidelines
Randolph-Fulton Market Historical District Guidelines
 
Advancing Illinois Medical District Opportunities
Advancing Illinois Medical District OpportunitiesAdvancing Illinois Medical District Opportunities
Advancing Illinois Medical District Opportunities
 
Fulton Market Innovation District Plan
Fulton Market Innovation District PlanFulton Market Innovation District Plan
Fulton Market Innovation District Plan
 
Fulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 WorkshopFulton Market Streetscape - July 15th, 2014 Workshop
Fulton Market Streetscape - July 15th, 2014 Workshop
 

Recently uploaded

Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceHigh Profile Call Girls
 
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...Garima Khatri
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
VIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Vani 8617697112 Independent Escort Service PuneVIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Vani 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024Energy for One World
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…nishakur201
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...ResolutionFoundation
 
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...Christina Parmionova
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationEnergy for One World
 
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 

Recently uploaded (20)

Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
 
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
 
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
VIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Vani 8617697112 Independent Escort Service PuneVIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
 
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological Civilization
 
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Saswad ( 7001035870 ) HI-Fi Pune Escorts Service
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 

Public meeting notice for Permit Review Committee

  • 1.
  • 2.
  • 3.
  • 4. NOTICE OF PUBLIC MEETING *All times are approximate. The Permit Review Committee of the Commission on Chicago Landmarks will meet immediately after the conclusion of the Commission’s 12:45 p.m. meeting. PERMIT REVIEW COMMITTEE THURSDAY, May 13, 2015 City Hall, 121 N. LaSalle St., Room 201-A AGENDA: 2:00 p.m.* 1. 1306 N. Dearborn Parkway 2nd Ward Three Arts Club Proposed installation of exterior architectural illumination. 2. 360 N. Michigan 42nd Ward London Guarantee and Accident Building Proposed 1-story retractable rooftop enclosure spanning across the historic building and the new high-rise side addition and new architectural illumination. 3. 311-319 N. Morgan 27th Ward Proposed Fulton-Randolph Market District Proposed adaptive reuse of 311 N. Morgan with a new 2-story addition into a new hotel development. Proposed demolition of a preliminarily identified non- contributing 1-story masonry structure at 319 N. Morgan. Proposed new construction on the 319 N. Morgan site of a 4 and 7-story building connected to 311 N. Morgan. Eleanor Esser Gorski, AIA Director of Historic Preservation Historic Preservation Division Bureau Zoning and Land Use Department of Planning and Development
  • 5. PERMIT REVIEW COMMITTEE Summary of projects and staff recommendations, May 13, 2015 1. 1306 N. Dearborn Parkway 2nd Ward Three Arts Club Proposed installation of exterior architectural illumination. Applicant: Restoration Hardware, applicant Booth Hansen Architects, architect Staff Recommendation: Staff recommends that the Committee find that the project, with the following condition, meets the criteria set forth in the Commission’s Rules and Regulations, the Commission’s Guidelines for Alterations to Historic Buildings and New Construction, and Standards 9 and 10 of the U.S. Secretary of the Interior’s Standards for Rehabilitation of Historic Buildings and therefore, the project will not have an adverse effect on the significant historical and architectural features of the landmark property and approve the project with the following condition to be reviewed for approval by the Historic Preservation staff: 1. The new exterior architectural illumination of the historic building is approved as per drawings dated April 27, 2015, provided the illumination at the arched openings above the main entry is adjusted to eliminate the visible “hotspot” at the bottom of the arch. 2. 360 N. Michigan 42nd Ward London Guarantee and Accident Building Proposed 1-story retractable rooftop enclosure spanning across the historic building and the new high-rise side addition and new architectural illumination. Applicant: John Rutledge, AG-OCG 360 North Michigan LLC - owner Len Koroski, Goettsch Partners – architect John Tess – Heritage Consulting Staff Recommendation: Staff recommends that the Committee find that the project, with the following conditions, meets the criteria set forth in the Commission’s Rules and Regulations, the Commission’s Guidelines for Alterations to Historic Buildings and New Construction, and Standards 9 and 10 of the U.S. Secretary of the Interior’s Standards for Rehabilitation of Historic Buildings and therefore, the project will not have an adverse effect on the significant historical and architectural features of the landmark property and approve the project with the following conditions to be reviewed for approval by the Historic Preservation staff: 1. The new architectural illumination of the historic street facades and cupola as per drawings dated 3/02/15 are approved as proposed; 2. The new 1-story retractable metal-and-glass rooftop addition, as shown on the drawings dated 4/16/15, is approved as proposed. The metal mullions and
  • 6. fascia shall be painted a color to match the penthouse brick color in a non- reflective finish. Samples to be reviewed for approval by Historic Preservation staff prior to order and installation; 3. The proposed insulated clear glazing units for the new curtain wall at the base of the high-rise side addition (Viracon Clear VE24-2M) is approved; and, 4. All conditions of approval from the previous review of the overall project will continue to be applicable (09/08/14). 3. 311 N. Morgan 27th Ward Proposed Fulton-Randolph Market District Proposed adaptive reuse of 311 N. Morgan with a new 2-story addition into a new hotel development. Proposed demolition of a preliminarily identified non- contributing 1-story masonry structure at 319 N. Morgan. Proposed new construction on the 319 N. Morgan site of a 4 and 7-story building connected to 311 N. Morgan. Applicant: 311 North Morgan, LLC (Sterling Bay Company), owner GREC Architects, LLC Staff Recommendation: Staff recommends that the Committee: (A)Find that the 319 N. Morgan building, constructed c.1940, is non-contributing to the proposed district and its demolition will not be an adverse effect; (B) Find that the 311 N. Morgan building, the first floor constructed in 1921 and a second floor added in 1923, is contributing to the proposed district. The project is not subject to the provisions of Section 2-120-825 of the Municipal Code of Chicago governing review of permits for the demolition of 40% or more of any building or structure either designated as a “Chicago Landmark” or located in any district designated as a “Chicago Landmark”. Staff further recommends that the Committee find that the project, with the following conditions, meets the criteria set forth in the Commission’s Rules and Regulations, the Commission’s Guidelines for Alterations to Historic Buildings and New Construction, and Standards 1, 2, 5, 6, 9, and 10 of the U.S. Secretary of the Interior’s Standards for Rehabilitation of Historic Buildings and therefore, the project will not have an adverse effect on the significant historical and architectural features of the proposed landmark property and district and approve the project with the following conditions: Partial Demolition 1. Due to the deteriorated conditions of the masonry walls, highly compressive soil conditions and extreme site constraints the proposed demolition of the north (side), west (rear) and south (side) common brick secondary facades of 311 N. Morgan is approved; 2. A report by a licensed structural engineer addressing the partial demolition of the structure, relative to how the historic facade to remain in-situ should be braced and protected during demolition and new construction, shall be submitted for Historic Preservation staff review and approval, as part of
  • 7. the permit plans. The recommended measures, sequencing, and protections shall be incorporated in the structural and architectural drawings. Exterior Rehabilitation of 311 N. Morgan 3. As proposed the historic street-façade at 311 N. Morgan shall be repaired in-situ and rehabilitated in accordance with the Commission’s standards and guidelines as indicated by drawings prepared by BTL Architects, Inc. and dated 4/2/15; 4. Select portions of the historic street facades that require reconstruction due to deteriorated conditions shall use salvaged bricks as much as possible. Any replacement brick and new mortar shall match the historic in size, texture, color, finish, and profiles; 5. Enlarged dimensioned details of the new windows and storefronts shall be included with the permit plans. The muntins may be simulated-divided- lites but shall have a substantial profile with spacer bars and interior profiles to replicate the historic profiles. The window and storefront frames and mullions shall have a dark color/finish and the glazing shall be clear glass; 6. Masonry repair and replacement details shall be included in the permit application plans. Samples of any replacement stone, patching, and any new masonry and mortar shall match the historic in size, color, profile, texture and type and shall be reviewed and approved by Historic Preservation staff prior to order and installation; 7. The 2-story rooftop addition, setback approximately 7’ from Morgan Street, is approved as proposed; New Construction 8. As proposed, the 4-story and 7-story portions of the complex, including the 1-story enclosure, are approved as submitted; 9. Enlarged storefronts, windows details, exterior wall details and metal finish sample shall be submitted as part of the permit application and subject to staff review and approval; 10. Any signage shall be permitted separately and reviewed and approved by Historic Preservation staff prior to order and installation; and, 11. Proposed brick colors and finishes are approved as submitted.