Question 1:
An organization decided to group some programs, projects
and some other operations to achieve an enhancement in its
over all profits , the organizations is establishing a/an:
A) Organizational system
B) Management System
C) Program
D) Portfolio
Answer : (Portfolio)
Explanation:
Correct answer is ( D ). A portfolio is a collecion of projects, programs, subsidiary
portfolios, and operations managed as a group to achieve strategic objectives.
(PMBOK 6th edition. Page 13]
by eng thabet ali +966 580561327
ProjectManagement Framework
Practice Exam
Question 2:
One of your team is discussing with you that the stakeholders have the greatest effect
on the project in the planning stage as they have a lot of requirements must be taken
into consideration ,based on pmbok 6th edition the highest stakeholders effect
without changing the cost, schedule of the project is at:
A) The project closure
B) The initiating of a project
C) There is no change as the stakeholders have the same effect through the entire
project lifecycle
D) The planning stage
by eng thabet ali +966 580561327
Project Management Framework
Answer : (The initiating of a project )
Explanation:
Correct answer is (BI PMBOK 6th edition. Page 549}
by eng thabet ali +966 580561327 5
Project Management Framework
Question 3.
You were assigned to a project at which the scope , cost and schedule are determined
early in the project life cycle , this is a /an:
A) Hybrid lifecycle
B) Adaptive life cycle
C) Predictive life cycle
D) Incremental life
by eng thabet ali +966 580561327 6
Project Management Framework
Answer : (Predictive life cycle )
Explanation:
(C) Is correct . in a predictive life cycle, the scope, time, and cost
are determined in the early phases of the life cycle. [PMBOK 6th
edition. Page 19]
by eng thabet ali +966 580561327
Project Management Framework
Question 4:
In an important project Thabet is a team member , he came up with a very serious issue
,Thabet is not reporting to you directly ,hence which of the following is responsible for
solving this issue
A) The project owner
B) The project manger
C) Any key Stakeholder
D) The functional manager
by eng thabet ali +966 580561327
Project Management Framework
Answer : (The functional manager )
Explanation:
(D) The team members is not directly reporting to the Project
manager so its Functional Organization and accordingly the
functional manager will be responsible here ]pbbok 6th page 47[
by eng thabet ali +966 580561327
Project Management Framework
Question 5:
You are signed to manage a project at which the team members are working
side by side and you have to follow the owners instructions in regards to the
budget
A) PMO
B) Functional
C) Organic organization
D) Project oriented
by eng thabet ali +966 580561327
Project Management Framework
Answer : (Organic organization)
Explanation
(C)Is correct : the people wotting side-by-side and the owner
Who manage the project budget in an Organic or Simple
Organization (PMBOK 6th edition. Page 47J
by eng thabet ali +966 580561327
Project Management Framework
Question 6:
All of the following sentences are correct regarding a supportive PMO
EXCEPT
A) It provides a consultative role to project
B) It has the power to terminate the project manager
C) it provides project management training
D) It is responsible for suppling templates and best practices
by eng thabet ali +966 580561327
Project Management Framework
Answer : ( It has the power to terminate the project manager)
Explanation:
( B )is the best answer Supportive PMOs plays a consultative
role to projects by supplying templates, best practices, training,
access to information, and lessons learned from other projects
This type of PMO serves as a project repository. The degree of
control provided by the PMO is low. [PM80K 6th edition. Page
48J
by eng thabet ali +966 580561327
Project Management Framework
Question 7:
Al of the following is correct regarding a project ECEPT:
A) Usually the project is limited by budget , schedule and
resources
B) Initiated ,Planned, executed, controlled and then closed
C) Its outputs are unique
D) Has a sustainable nature
by eng thabet ali +966 580561327
Project Management Framework
Answer : (Has a sustainable nature )
Explanation:
(D) Is correct . The operations has an ongoing and sustainable
nature .lPMBOK 6th edition. Page 16]
by eng thabet ali +966 580561327
Project Management Framework
Question 8:
The main PMO role is to :
A) Mange the operational activates in the company
B) Manage human resource and risk management issues for
individual projects
C) Provide support functions to project managers in the form of
training, providing software, standardizing polices, etc.
D) Provide subject matter expertise In the functional areas of the
project
by eng thabet ali +966 580561327
Project Management Framework
Answer :
Provide support functions to project managers in the form of training, providing
software, standardizing polices, etc.
Explanation:
(C) Is correct A project management office (PMO) is an organizational
structure that standardizes the project-related governance processes and
facilitates the sharing of resources, methodologies, tools, and techniques.
The responsibilities of a PMO can range from providing project management
support functions to the direct management of one or more projects.
[PMBOK 6th edition. Page 48]
by eng thabet ali +966 580561327
Project Management Framework
Question 9:
Which of the following is NOT an organizational process asset
example :
A) Historical information
B) templates
C) Change control procedures
D) Market demands
by eng thabet ali +966 580561327
Project Management Framework
Answer : (Market demands )
Explanation:
( D) is the best answer Market demands is an EEFs external to
the organization [PMSOX 6th edition. Page 36]
by eng thabet ali +966 580561327
Project Management Framework
Question 10:
In your company you are assigned to a project at which the
organization is a weak matrix type , what option BEST describes
your role ?
A) Project expeditor
B) Project Manager
C) Project leader
D) Functional manger
by eng thabet ali +966 580561327
Project Management Framework
Answer: (Project expeditor)
Explanation:
(A) Is correct . In a weak matrix the project manager has a none
to little authority ]PMBOK 6th edition. Page 47]
by eng thabet ali +966 580561327
Project Management Framework
Question 11:
Which of the following statements is TRUE regarding the
initiating phase ?
A) The risk is the lowest in initiating stage
B) The risk is very high at the end or the project
C) The risk is the highest during the Initiating stage
D) There is no change as the risk is not appeared yet
by eng thabet ali +966 580561327
Project Management Framework
Answer: (The risk is the highest during the Initiating stage)
Explanation:
Correct answer is (C). Risk is greatest at he start of the project.
These factors decrease over the life cycle of the project as
decisions are reached and as deliverables are acccpted.jPMBOK
6th edibon, Page 549J
by eng thabet ali +966 580561327
Project Management Framework
Question 12:
All of the following are External EEF’s except
A) Market share
B) Geographic distribution of resources
C) legal regulations
D) Trademark
by eng thabet ali +966 580561327
Project Management Framework
Answer: (Geographic distribution of resources)
Explanation:
B ) is correct , Geographic distribution of facilities and resources
(PMBOK& Guide pg38. 39). it is an internal EEF because it is
about the organization itself and not an external entity. Note
that D (Trademark) is an external EEF as it is externally
registered by an organization with a right to use it
by eng thabet ali +966 580561327
Project Management Framework
Question 13:
A project is launched based on a high-level definition of the work that
could be done , the client came to you asking for so many changes in
the project work, noting that those changes don’t need any change
control procedures , accordingly this is a
A) Predictive lifecycle
B) Adaptive lifecycle
C) Hybrid lifecycle
D) Waterfall lifecycle
by eng thabet ali +966 580561327
Project Management Framework
Answer : (Adaptive lifecycle)
Explanation
(B) Adaptive life cycle. as the scope is change driven.
by eng thabet ali +966 580561327
Project Management Framework
Question 14:
The PMI talent triangle focuses on ?
A) business management Leadership and Technical project management
B) Leadership strategic and business management, soft skills and
motivation
C) Leadership strategic project management and Technical business
management
D) Leadership strategic and business management and Technical project
management
by eng thabet ali +966 580561327
Project Management Framework
Answer: (Leadership strategic and business management and
Technical project management)
Explanation
Correct answer is (D ) Leadership. Strategic and business
management and Technical project management. (PMBOKX
Guide Pg57[
by eng thabet ali +966 580561327
Project Management Framework
Question 15 :
You have been working as a team leader on a project for almost 3 months. You are
feeling demotivated because you get almost no information from the project
manager, and she seldom requests any information from you either. Yet you have to
make a lot of project decisions by yourself. You wonder if the project manager doesn't
like you. but when you speak with other team members about it. they report similar
Issues. What sort of Leadership style is the project manager using?
A) Punitive style
B) Democracy style
C) Charismatic style
D) Laissez faire style
by eng thabet ali +966 580561327
Project Management Framework
Answer : (Laissez faire style)
Explanation:
D is the correct answer , her the manager didn’t involve herself
in the project work that’s exactly the meaning of the term
laissez faire
by eng thabet ali +966 580561327
Project Management Framework
Question 16
All of the following don’t refer to the project governance EXCEPT
A) The Inputs, tools and techniques and outputs used by the Project Manager order to
create a unique product service or result to meet organizational. strategic. and
operational goals
B) The framework, functions, and processes that guide project management activities in
enter to unique product service or result to meet organizational strategic. and
operational goals
C) The potties, processes and procedures that guide project management activities in
order to create a unique product service or result to meet organizational strategic and
operational goals.
D) framework, functions, and processes that guide project management offices to create a
unique product service or result to meet organizational . strategic and operational goals
by eng thabet ali +966 580561327
Project Management Framework
Answer : (The framework, functions, and processes that guide
project management activities in enter to unique product
service or result to meet organizational strategic. and
operational goals)
Explanation:
(B). the framework, functions, and processes that guide project
management activities in order to create a unique product,
service, or result to meet organizational, strategic, and
operational goals. Pmbok 6th page 44
by eng thabet ali +966 580561327
Project Management Framework
Question 17:
In a mega project ,you are the project manager and you found that the PMO
in this organization is controlling each aspect of your project , this is typically
the
A) Controlling PMO type
B) Directive PMO type
C) Supportive PMO type
D) Dedicated PMO type
by eng thabet ali +966 580561327
Project Management Framework
Answer : (Directive PMO type)
Explanation:
Correct answer is (B). Directive, in which the PMO performs
project management for the given project Pmbok 6th page 48
by eng thabet ali +966 580561327
Project Management Framework
Question 18:
A few years ago, a large organization recognized the need for project
management and trained 100 staff members from various departments, in
project management The chief executive of the company made it dear that
though the project managers would have some authority on the project and its
resources, the budgetary control of the project would rest with functional
managers. The organization’s new structure can be termed as:
A) Functional
B) Weak matrix
C) PMO
D) Organic
by eng thabet ali +966 580561327
Project Management Framework
Answer : (Weak matrix)
Explanation:
B) is the best choice Functional managers control the budget
and project managers have some (low) authority in a Weak
Matrix organization. PMBOK* Guide. 6th Ed; Ch 2. Pg 47
by eng thabet ali +966 580561327
Project Management Framework
Question 19:
A collection of logically related project activities that culminates In the
completion of one or more deliverables is known as
A) Project phase gate
B) Project management lifecycle
C) Project lifecycle
D) Project phase
by eng thabet ali +966 580561327
Project Management Framework
Answer : (Project phase )
Explanation:
(D). A project phase is a collection of logically related project
activities that culminates in the completion of one or more
deliverables. PMBOK« Guide. 6th Ed; Ch 2. Pg 18
by eng thabet ali +966 580561327
Project Management Framework
Question 20:
All of the following arc examples of Organizational Process
Assets EXCEPT:
A) Historical information
B) Organizational structure
C) Change control procedures
D) Templates
by eng thabet ali +966 580561327
Project Management Framework
Answer : (Organizational structure )
Explanation:
B ) Historical information. Templates and Change Control
Procedures are all examples of Organizational Process Assets.
Organizational Structure is not an Organizational Process Asset
it is part of the Enterprise Environmental Factors. PMBOK 6th Ch
2. Page 38-41
by eng thabet ali +966 580561327
Project Management Framework
Question 20:
an outline of how the business value resulting from the undertaking turns
into a part of the agency's ongoing operations, together with the metrics to
be used to offer verification of the commercial enterprise cost and validation
of the venture's fulfillment is covered in which of the subsequent?
A) Change management plan
B) Both benefits management plan and project management plan
C) enterprise needs
D) Benefits management plan
Intro
Answer : (Both benefits management plan and project
management plan )
Explanation:
B) Is the correct answer The benefits management plan and the
project management plan include a description of how the
business value resulting from the project becomes part of the
organization’s ongoing operations, including the metrics to be
used. The metrics provide verification of the business value and
validation of the project’s success. Pmbok 6th page 33
Intro
Question 21:
One of the following can result to the project not to be
authorized
A) Do nothing
B) Do the minimum work possible .
C) Do more than the minimum work
D) The project is done successfully
Intro
Answer : (Do nothing )
Explanation :
A)Is the correct answer , Do nothing. This is also referred to as
the “business as usual” option. Selection of this option results
in the project not being authorized , Pmbok 6th edition Page 31
Intro
Question 22:
A temporary endeavor undertaken to fulfill objectives by
producing deliverables is the definition of:
A) Project
B) Operation
C) Product
D) Deliverable
Intro
Answer : (Project )
Explanation:
A is the correct answer , Projects are undertaken to fulfill
objectives by producing deliverables Pmbok 6th page 4
Intro
Question 23 :
Selecting the right programs or projects, prioritizing the work,
and providing the needed resources is the target of
A) Program management
B) Project management
C) Operations management
D) Portfolio management
Intro
Answer: (Portfolio management )
Explanation:
D) is correct Portfolio management aligns portfolios with
organizational strategies by selecting the right programs or
projects, prioritizing the work, and providing the needed
resources
Intro
Question 24:
All of the following are Fundamental categories for factors
acting upon organizations to initiate projects EXCEPT :
A) Meet regulatory, legal, or social requirements
B) satisfy stakeholder requests or needs
C) implement or change business or technological strategies
D) Terminating a project due to lack of funds
Intro
Answer : (Terminating a project due to lack of funds )
Explanation :
The correct answer is D , Pmbok 6th page 7
Intro
Question 25:
Combination of a predictive and an adaptive life cycle is defined
as:
A) Hybrid life cycle
B) Iterative life cycle
C) Agile life cycle
D) Incremental life cycle
Intro
Answer : (Hybrid life cycle)
Explanation :
A) is the correct answer A hybrid life cycle is a combination of a
predictive and an adaptive life cycle. Those elements of the
project that are well known or have fixed requirements follow a
predictive development life cycle, and those elements that are
still evolving follow an adaptive development life cycle
Intro
Question 26:
None of the following is an example of a product Except
A) Business function that supports production
B) An enhancement or correction to an item
C) Research that develops knowledge to determine whether a trend exists
D) The series of phases that a project passes through from its start to its
completion
Intro
Answer : (An enhancement or correction to an item)
Explanation:
The correct answer is (B) A unique product that can be either a
component of another item, an enhancement or correction to
an item, or a new end item in itself (e.g., the correction of a
defect in an end item) Pmbok 6th Page 4
Intro
Question 28:
Close Project or Phase are examples of:
A) Processes that are performed periodically as needed
B) Processes that are performed continuously throughout the
project
C) Processes used once in the project
D) Processes that are rarely used when managing a project
Intro
Answer : (Processes used once in the project)
Explanation :
C is the correct answer. Processes used once or at predefined
points in the project. The processes Develop Project Charter and
Close Project or Phase are examples.
Intro
Question 29:
Selection of the appropriate project management processes, inputs,
tools, techniques, outputs, and life cycle phases to manage a project is
the definition of:
A) Project management process groups.
B) Project phases
C) Decomposition of the project to more manageable components
D) Tailoring project management to the project
Intro
Answer : (Tailoring project management to the project )
Explanation :
D is correct The appropriate project management processes,
inputs, tools, techniques, outputs, and life cycle phases should
be selected to manage a project. This selection activity is known
as tailoring project management to the project Pmbok 6th page
28
Intro
Question 30:
One of the following is NOT contained in Work performance
information, and are all examples of:
A) Status of deliverables,
B) implementation status for change requests
C) forecasted estimate to complete the project
D) Observations found by the project team while executing
stage is going
Intro
Answer : (Observations found by the project team while
executing stage is going )
Explanation :
D is correct ,Work performance information. The performance
data collected from various controlling processes, analyzed in
context and integrated based on relationships across areas.
Examples of performance information are status of deliverables,
implementation status for change requests, and forecast
estimates to complete. Pmbok 6th edition page 26
Intro

More Related Content

What's hot

Pmp Questions and Answers series #1
Pmp Questions and Answers series #1Pmp Questions and Answers series #1
Pmp Questions and Answers series #1Knowledge Max
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1Daniel Hucks
 
Risk 9-pm study project risk management-test
Risk 9-pm study project risk management-testRisk 9-pm study project risk management-test
Risk 9-pm study project risk management-testMohamed Saeed
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes examJamil Faraj , PMP
 
One Page Problem Solving Sheet
One Page Problem Solving Sheet One Page Problem Solving Sheet
One Page Problem Solving Sheet Eda Yilmaz
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazMohamed Saeed
 
Liberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyLiberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyHarry White
 
D09 Recognize and Overcome Resistance
D09 Recognize and Overcome ResistanceD09 Recognize and Overcome Resistance
D09 Recognize and Overcome ResistanceLeanleaders.org
 
A BASELINE IS THE PROJECT'S SCOPE FIXED AT A SPECIFIC POINT IN TIME.
A BASELINE IS THE PROJECT'S SCOPE FIXED AT A SPECIFIC POINT IN TIME.A BASELINE IS THE PROJECT'S SCOPE FIXED AT A SPECIFIC POINT IN TIME.
A BASELINE IS THE PROJECT'S SCOPE FIXED AT A SPECIFIC POINT IN TIME.SophiaMorgans
 

What's hot (20)

Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp hr chapter 9
 
Pmp Questions and Answers series #1
Pmp Questions and Answers series #1Pmp Questions and Answers series #1
Pmp Questions and Answers series #1
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
Risk 9-pm study project risk management-test
Risk 9-pm study project risk management-testRisk 9-pm study project risk management-test
Risk 9-pm study project risk management-test
 
Pmstudy exam 2
Pmstudy exam 2Pmstudy exam 2
Pmstudy exam 2
 
Pmstudy exam 3
Pmstudy exam 3Pmstudy exam 3
Pmstudy exam 3
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes exam
 
One Page Problem Solving Sheet
One Page Problem Solving Sheet One Page Problem Solving Sheet
One Page Problem Solving Sheet
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbaz
 
Pmstudy exam_1
Pmstudy exam_1Pmstudy exam_1
Pmstudy exam_1
 
Being the Best We Can be Through Working Together
Being the Best We Can be Through Working TogetherBeing the Best We Can be Through Working Together
Being the Best We Can be Through Working Together
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
 
Liberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyLiberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers key
 
D09 Recognize and Overcome Resistance
D09 Recognize and Overcome ResistanceD09 Recognize and Overcome Resistance
D09 Recognize and Overcome Resistance
 
Basic Project Management Qc Session1
Basic Project Management  Qc Session1Basic Project Management  Qc Session1
Basic Project Management Qc Session1
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
The Role of Documentation & The Key to Labor Management
The Role of Documentation & The Key to Labor ManagementThe Role of Documentation & The Key to Labor Management
The Role of Documentation & The Key to Labor Management
 
A BASELINE IS THE PROJECT'S SCOPE FIXED AT A SPECIFIC POINT IN TIME.
A BASELINE IS THE PROJECT'S SCOPE FIXED AT A SPECIFIC POINT IN TIME.A BASELINE IS THE PROJECT'S SCOPE FIXED AT A SPECIFIC POINT IN TIME.
A BASELINE IS THE PROJECT'S SCOPE FIXED AT A SPECIFIC POINT IN TIME.
 
Exam1
Exam1Exam1
Exam1
 
Ibm projectmgmt-1
Ibm  projectmgmt-1Ibm  projectmgmt-1
Ibm projectmgmt-1
 

Similar to Profittme pmp framweork questions

1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
Devry proj 595 final exam set 2 new
Devry proj 595 final exam set 2 newDevry proj 595 final exam set 2 new
Devry proj 595 final exam set 2 newuopassignment
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions CompleteKareemBullard1
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfProject Cubicle
 
Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00Praveen Krishna
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkD10iT
 
Question 17 The internal and external environmental factors that su.pdf
Question 17 The internal and external environmental factors that su.pdfQuestion 17 The internal and external environmental factors that su.pdf
Question 17 The internal and external environmental factors that su.pdfezzi552
 
PROJ 595 RANK Education Your Life / proj595rank.com
PROJ 595 RANK Education Your Life / proj595rank.comPROJ 595 RANK Education Your Life / proj595rank.com
PROJ 595 RANK Education Your Life / proj595rank.comkopiko20
 
PROJ 595 RANK Education Counseling--proj595rank.com
PROJ 595 RANK Education Counseling--proj595rank.comPROJ 595 RANK Education Counseling--proj595rank.com
PROJ 595 RANK Education Counseling--proj595rank.comvenkat60045
 
PROJ 595  Focus Dreams/newtonhelp.com
PROJ 595  Focus Dreams/newtonhelp.comPROJ 595  Focus Dreams/newtonhelp.com
PROJ 595  Focus Dreams/newtonhelp.commyblue72
 
PROJ 595 RANK Redefined Education--proj595rank.com
PROJ 595 RANK Redefined Education--proj595rank.comPROJ 595 RANK Redefined Education--proj595rank.com
PROJ 595 RANK Redefined Education--proj595rank.comkopiko186
 
PROJ 595 RANK Lessons in Excellence-- proj595rank.com
PROJ 595 RANK Lessons in Excellence-- proj595rank.com	PROJ 595 RANK Lessons in Excellence-- proj595rank.com
PROJ 595 RANK Lessons in Excellence-- proj595rank.com RoelofMerwe131
 
PROJ 595 RANK Education for Service-- proj595rank.com
PROJ 595 RANK Education for Service-- proj595rank.comPROJ 595 RANK Education for Service-- proj595rank.com
PROJ 595 RANK Education for Service-- proj595rank.comKeatonJennings29
 
PROJ 595 RANK Achievement Education / proj595rank.com
PROJ 595 RANK Achievement Education / proj595rank.comPROJ 595 RANK Achievement Education / proj595rank.com
PROJ 595 RANK Achievement Education / proj595rank.comagathachristie149
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management examJamil Faraj , PMP
 

Similar to Profittme pmp framweork questions (20)

1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Devry proj 595 final exam set 2 new
Devry proj 595 final exam set 2 newDevry proj 595 final exam set 2 new
Devry proj 595 final exam set 2 new
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Pmp sample qa3
Pmp sample qa3Pmp sample qa3
Pmp sample qa3
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
 
Question 17 The internal and external environmental factors that su.pdf
Question 17 The internal and external environmental factors that su.pdfQuestion 17 The internal and external environmental factors that su.pdf
Question 17 The internal and external environmental factors that su.pdf
 
PROJ 595 RANK Education Your Life / proj595rank.com
PROJ 595 RANK Education Your Life / proj595rank.comPROJ 595 RANK Education Your Life / proj595rank.com
PROJ 595 RANK Education Your Life / proj595rank.com
 
PROJ 595 RANK Education Counseling--proj595rank.com
PROJ 595 RANK Education Counseling--proj595rank.comPROJ 595 RANK Education Counseling--proj595rank.com
PROJ 595 RANK Education Counseling--proj595rank.com
 
PROJ 595  Focus Dreams/newtonhelp.com
PROJ 595  Focus Dreams/newtonhelp.comPROJ 595  Focus Dreams/newtonhelp.com
PROJ 595  Focus Dreams/newtonhelp.com
 
PROJ 595 RANK Redefined Education--proj595rank.com
PROJ 595 RANK Redefined Education--proj595rank.comPROJ 595 RANK Redefined Education--proj595rank.com
PROJ 595 RANK Redefined Education--proj595rank.com
 
PROJ 595 RANK Lessons in Excellence-- proj595rank.com
PROJ 595 RANK Lessons in Excellence-- proj595rank.com	PROJ 595 RANK Lessons in Excellence-- proj595rank.com
PROJ 595 RANK Lessons in Excellence-- proj595rank.com
 
PROJ 595 RANK Education for Service-- proj595rank.com
PROJ 595 RANK Education for Service-- proj595rank.comPROJ 595 RANK Education for Service-- proj595rank.com
PROJ 595 RANK Education for Service-- proj595rank.com
 
PROJ 595 RANK Achievement Education / proj595rank.com
PROJ 595 RANK Achievement Education / proj595rank.comPROJ 595 RANK Achievement Education / proj595rank.com
PROJ 595 RANK Achievement Education / proj595rank.com
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Free PMP® Practice Exam Questions
 Free PMP® Practice Exam Questions Free PMP® Practice Exam Questions
Free PMP® Practice Exam Questions
 

Recently uploaded

/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...lizamodels9
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 

Recently uploaded (20)

/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 

Profittme pmp framweork questions

  • 1. Practice Exam 1 ProjectManagement Framework Prepared BY : Eng.Thabt Ali Powered By : Profittme.com
  • 2. Question 1: An organization decided to group some programs, projects and some other operations to achieve an enhancement in its over all profits , the organizations is establishing a/an: A) Organizational system B) Management System C) Program D) Portfolio
  • 3. Answer : (Portfolio) Explanation: Correct answer is ( D ). A portfolio is a collecion of projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives. (PMBOK 6th edition. Page 13] by eng thabet ali +966 580561327 ProjectManagement Framework Practice Exam
  • 4. Question 2: One of your team is discussing with you that the stakeholders have the greatest effect on the project in the planning stage as they have a lot of requirements must be taken into consideration ,based on pmbok 6th edition the highest stakeholders effect without changing the cost, schedule of the project is at: A) The project closure B) The initiating of a project C) There is no change as the stakeholders have the same effect through the entire project lifecycle D) The planning stage by eng thabet ali +966 580561327 Project Management Framework
  • 5. Answer : (The initiating of a project ) Explanation: Correct answer is (BI PMBOK 6th edition. Page 549} by eng thabet ali +966 580561327 5 Project Management Framework
  • 6. Question 3. You were assigned to a project at which the scope , cost and schedule are determined early in the project life cycle , this is a /an: A) Hybrid lifecycle B) Adaptive life cycle C) Predictive life cycle D) Incremental life by eng thabet ali +966 580561327 6 Project Management Framework
  • 7. Answer : (Predictive life cycle ) Explanation: (C) Is correct . in a predictive life cycle, the scope, time, and cost are determined in the early phases of the life cycle. [PMBOK 6th edition. Page 19] by eng thabet ali +966 580561327 Project Management Framework
  • 8. Question 4: In an important project Thabet is a team member , he came up with a very serious issue ,Thabet is not reporting to you directly ,hence which of the following is responsible for solving this issue A) The project owner B) The project manger C) Any key Stakeholder D) The functional manager by eng thabet ali +966 580561327 Project Management Framework
  • 9. Answer : (The functional manager ) Explanation: (D) The team members is not directly reporting to the Project manager so its Functional Organization and accordingly the functional manager will be responsible here ]pbbok 6th page 47[ by eng thabet ali +966 580561327 Project Management Framework
  • 10. Question 5: You are signed to manage a project at which the team members are working side by side and you have to follow the owners instructions in regards to the budget A) PMO B) Functional C) Organic organization D) Project oriented by eng thabet ali +966 580561327 Project Management Framework
  • 11. Answer : (Organic organization) Explanation (C)Is correct : the people wotting side-by-side and the owner Who manage the project budget in an Organic or Simple Organization (PMBOK 6th edition. Page 47J by eng thabet ali +966 580561327 Project Management Framework
  • 12. Question 6: All of the following sentences are correct regarding a supportive PMO EXCEPT A) It provides a consultative role to project B) It has the power to terminate the project manager C) it provides project management training D) It is responsible for suppling templates and best practices by eng thabet ali +966 580561327 Project Management Framework
  • 13. Answer : ( It has the power to terminate the project manager) Explanation: ( B )is the best answer Supportive PMOs plays a consultative role to projects by supplying templates, best practices, training, access to information, and lessons learned from other projects This type of PMO serves as a project repository. The degree of control provided by the PMO is low. [PM80K 6th edition. Page 48J by eng thabet ali +966 580561327 Project Management Framework
  • 14. Question 7: Al of the following is correct regarding a project ECEPT: A) Usually the project is limited by budget , schedule and resources B) Initiated ,Planned, executed, controlled and then closed C) Its outputs are unique D) Has a sustainable nature by eng thabet ali +966 580561327 Project Management Framework
  • 15. Answer : (Has a sustainable nature ) Explanation: (D) Is correct . The operations has an ongoing and sustainable nature .lPMBOK 6th edition. Page 16] by eng thabet ali +966 580561327 Project Management Framework
  • 16. Question 8: The main PMO role is to : A) Mange the operational activates in the company B) Manage human resource and risk management issues for individual projects C) Provide support functions to project managers in the form of training, providing software, standardizing polices, etc. D) Provide subject matter expertise In the functional areas of the project by eng thabet ali +966 580561327 Project Management Framework
  • 17. Answer : Provide support functions to project managers in the form of training, providing software, standardizing polices, etc. Explanation: (C) Is correct A project management office (PMO) is an organizational structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques. The responsibilities of a PMO can range from providing project management support functions to the direct management of one or more projects. [PMBOK 6th edition. Page 48] by eng thabet ali +966 580561327 Project Management Framework
  • 18. Question 9: Which of the following is NOT an organizational process asset example : A) Historical information B) templates C) Change control procedures D) Market demands by eng thabet ali +966 580561327 Project Management Framework
  • 19. Answer : (Market demands ) Explanation: ( D) is the best answer Market demands is an EEFs external to the organization [PMSOX 6th edition. Page 36] by eng thabet ali +966 580561327 Project Management Framework
  • 20. Question 10: In your company you are assigned to a project at which the organization is a weak matrix type , what option BEST describes your role ? A) Project expeditor B) Project Manager C) Project leader D) Functional manger by eng thabet ali +966 580561327 Project Management Framework
  • 21. Answer: (Project expeditor) Explanation: (A) Is correct . In a weak matrix the project manager has a none to little authority ]PMBOK 6th edition. Page 47] by eng thabet ali +966 580561327 Project Management Framework
  • 22. Question 11: Which of the following statements is TRUE regarding the initiating phase ? A) The risk is the lowest in initiating stage B) The risk is very high at the end or the project C) The risk is the highest during the Initiating stage D) There is no change as the risk is not appeared yet by eng thabet ali +966 580561327 Project Management Framework
  • 23. Answer: (The risk is the highest during the Initiating stage) Explanation: Correct answer is (C). Risk is greatest at he start of the project. These factors decrease over the life cycle of the project as decisions are reached and as deliverables are acccpted.jPMBOK 6th edibon, Page 549J by eng thabet ali +966 580561327 Project Management Framework
  • 24. Question 12: All of the following are External EEF’s except A) Market share B) Geographic distribution of resources C) legal regulations D) Trademark by eng thabet ali +966 580561327 Project Management Framework
  • 25. Answer: (Geographic distribution of resources) Explanation: B ) is correct , Geographic distribution of facilities and resources (PMBOK& Guide pg38. 39). it is an internal EEF because it is about the organization itself and not an external entity. Note that D (Trademark) is an external EEF as it is externally registered by an organization with a right to use it by eng thabet ali +966 580561327 Project Management Framework
  • 26. Question 13: A project is launched based on a high-level definition of the work that could be done , the client came to you asking for so many changes in the project work, noting that those changes don’t need any change control procedures , accordingly this is a A) Predictive lifecycle B) Adaptive lifecycle C) Hybrid lifecycle D) Waterfall lifecycle by eng thabet ali +966 580561327 Project Management Framework
  • 27. Answer : (Adaptive lifecycle) Explanation (B) Adaptive life cycle. as the scope is change driven. by eng thabet ali +966 580561327 Project Management Framework
  • 28. Question 14: The PMI talent triangle focuses on ? A) business management Leadership and Technical project management B) Leadership strategic and business management, soft skills and motivation C) Leadership strategic project management and Technical business management D) Leadership strategic and business management and Technical project management by eng thabet ali +966 580561327 Project Management Framework
  • 29. Answer: (Leadership strategic and business management and Technical project management) Explanation Correct answer is (D ) Leadership. Strategic and business management and Technical project management. (PMBOKX Guide Pg57[ by eng thabet ali +966 580561327 Project Management Framework
  • 30. Question 15 : You have been working as a team leader on a project for almost 3 months. You are feeling demotivated because you get almost no information from the project manager, and she seldom requests any information from you either. Yet you have to make a lot of project decisions by yourself. You wonder if the project manager doesn't like you. but when you speak with other team members about it. they report similar Issues. What sort of Leadership style is the project manager using? A) Punitive style B) Democracy style C) Charismatic style D) Laissez faire style by eng thabet ali +966 580561327 Project Management Framework
  • 31. Answer : (Laissez faire style) Explanation: D is the correct answer , her the manager didn’t involve herself in the project work that’s exactly the meaning of the term laissez faire by eng thabet ali +966 580561327 Project Management Framework
  • 32. Question 16 All of the following don’t refer to the project governance EXCEPT A) The Inputs, tools and techniques and outputs used by the Project Manager order to create a unique product service or result to meet organizational. strategic. and operational goals B) The framework, functions, and processes that guide project management activities in enter to unique product service or result to meet organizational strategic. and operational goals C) The potties, processes and procedures that guide project management activities in order to create a unique product service or result to meet organizational strategic and operational goals. D) framework, functions, and processes that guide project management offices to create a unique product service or result to meet organizational . strategic and operational goals by eng thabet ali +966 580561327 Project Management Framework
  • 33. Answer : (The framework, functions, and processes that guide project management activities in enter to unique product service or result to meet organizational strategic. and operational goals) Explanation: (B). the framework, functions, and processes that guide project management activities in order to create a unique product, service, or result to meet organizational, strategic, and operational goals. Pmbok 6th page 44 by eng thabet ali +966 580561327 Project Management Framework
  • 34. Question 17: In a mega project ,you are the project manager and you found that the PMO in this organization is controlling each aspect of your project , this is typically the A) Controlling PMO type B) Directive PMO type C) Supportive PMO type D) Dedicated PMO type by eng thabet ali +966 580561327 Project Management Framework
  • 35. Answer : (Directive PMO type) Explanation: Correct answer is (B). Directive, in which the PMO performs project management for the given project Pmbok 6th page 48 by eng thabet ali +966 580561327 Project Management Framework
  • 36. Question 18: A few years ago, a large organization recognized the need for project management and trained 100 staff members from various departments, in project management The chief executive of the company made it dear that though the project managers would have some authority on the project and its resources, the budgetary control of the project would rest with functional managers. The organization’s new structure can be termed as: A) Functional B) Weak matrix C) PMO D) Organic by eng thabet ali +966 580561327 Project Management Framework
  • 37. Answer : (Weak matrix) Explanation: B) is the best choice Functional managers control the budget and project managers have some (low) authority in a Weak Matrix organization. PMBOK* Guide. 6th Ed; Ch 2. Pg 47 by eng thabet ali +966 580561327 Project Management Framework
  • 38. Question 19: A collection of logically related project activities that culminates In the completion of one or more deliverables is known as A) Project phase gate B) Project management lifecycle C) Project lifecycle D) Project phase by eng thabet ali +966 580561327 Project Management Framework
  • 39. Answer : (Project phase ) Explanation: (D). A project phase is a collection of logically related project activities that culminates in the completion of one or more deliverables. PMBOK« Guide. 6th Ed; Ch 2. Pg 18 by eng thabet ali +966 580561327 Project Management Framework
  • 40. Question 20: All of the following arc examples of Organizational Process Assets EXCEPT: A) Historical information B) Organizational structure C) Change control procedures D) Templates by eng thabet ali +966 580561327 Project Management Framework
  • 41. Answer : (Organizational structure ) Explanation: B ) Historical information. Templates and Change Control Procedures are all examples of Organizational Process Assets. Organizational Structure is not an Organizational Process Asset it is part of the Enterprise Environmental Factors. PMBOK 6th Ch 2. Page 38-41 by eng thabet ali +966 580561327 Project Management Framework
  • 42. Question 20: an outline of how the business value resulting from the undertaking turns into a part of the agency's ongoing operations, together with the metrics to be used to offer verification of the commercial enterprise cost and validation of the venture's fulfillment is covered in which of the subsequent? A) Change management plan B) Both benefits management plan and project management plan C) enterprise needs D) Benefits management plan Intro
  • 43. Answer : (Both benefits management plan and project management plan ) Explanation: B) Is the correct answer The benefits management plan and the project management plan include a description of how the business value resulting from the project becomes part of the organization’s ongoing operations, including the metrics to be used. The metrics provide verification of the business value and validation of the project’s success. Pmbok 6th page 33 Intro
  • 44. Question 21: One of the following can result to the project not to be authorized A) Do nothing B) Do the minimum work possible . C) Do more than the minimum work D) The project is done successfully Intro
  • 45. Answer : (Do nothing ) Explanation : A)Is the correct answer , Do nothing. This is also referred to as the “business as usual” option. Selection of this option results in the project not being authorized , Pmbok 6th edition Page 31 Intro
  • 46. Question 22: A temporary endeavor undertaken to fulfill objectives by producing deliverables is the definition of: A) Project B) Operation C) Product D) Deliverable Intro
  • 47. Answer : (Project ) Explanation: A is the correct answer , Projects are undertaken to fulfill objectives by producing deliverables Pmbok 6th page 4 Intro
  • 48. Question 23 : Selecting the right programs or projects, prioritizing the work, and providing the needed resources is the target of A) Program management B) Project management C) Operations management D) Portfolio management Intro
  • 49. Answer: (Portfolio management ) Explanation: D) is correct Portfolio management aligns portfolios with organizational strategies by selecting the right programs or projects, prioritizing the work, and providing the needed resources Intro
  • 50. Question 24: All of the following are Fundamental categories for factors acting upon organizations to initiate projects EXCEPT : A) Meet regulatory, legal, or social requirements B) satisfy stakeholder requests or needs C) implement or change business or technological strategies D) Terminating a project due to lack of funds Intro
  • 51. Answer : (Terminating a project due to lack of funds ) Explanation : The correct answer is D , Pmbok 6th page 7 Intro
  • 52. Question 25: Combination of a predictive and an adaptive life cycle is defined as: A) Hybrid life cycle B) Iterative life cycle C) Agile life cycle D) Incremental life cycle Intro
  • 53. Answer : (Hybrid life cycle) Explanation : A) is the correct answer A hybrid life cycle is a combination of a predictive and an adaptive life cycle. Those elements of the project that are well known or have fixed requirements follow a predictive development life cycle, and those elements that are still evolving follow an adaptive development life cycle Intro
  • 54. Question 26: None of the following is an example of a product Except A) Business function that supports production B) An enhancement or correction to an item C) Research that develops knowledge to determine whether a trend exists D) The series of phases that a project passes through from its start to its completion Intro
  • 55. Answer : (An enhancement or correction to an item) Explanation: The correct answer is (B) A unique product that can be either a component of another item, an enhancement or correction to an item, or a new end item in itself (e.g., the correction of a defect in an end item) Pmbok 6th Page 4 Intro
  • 56. Question 28: Close Project or Phase are examples of: A) Processes that are performed periodically as needed B) Processes that are performed continuously throughout the project C) Processes used once in the project D) Processes that are rarely used when managing a project Intro
  • 57. Answer : (Processes used once in the project) Explanation : C is the correct answer. Processes used once or at predefined points in the project. The processes Develop Project Charter and Close Project or Phase are examples. Intro
  • 58. Question 29: Selection of the appropriate project management processes, inputs, tools, techniques, outputs, and life cycle phases to manage a project is the definition of: A) Project management process groups. B) Project phases C) Decomposition of the project to more manageable components D) Tailoring project management to the project Intro
  • 59. Answer : (Tailoring project management to the project ) Explanation : D is correct The appropriate project management processes, inputs, tools, techniques, outputs, and life cycle phases should be selected to manage a project. This selection activity is known as tailoring project management to the project Pmbok 6th page 28 Intro
  • 60. Question 30: One of the following is NOT contained in Work performance information, and are all examples of: A) Status of deliverables, B) implementation status for change requests C) forecasted estimate to complete the project D) Observations found by the project team while executing stage is going Intro
  • 61. Answer : (Observations found by the project team while executing stage is going ) Explanation : D is correct ,Work performance information. The performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas. Examples of performance information are status of deliverables, implementation status for change requests, and forecast estimates to complete. Pmbok 6th edition page 26 Intro