2. INITIAL STAGE
70% of dwellers from Cooperative Housing Society
Appointment of Chief Promoter / Opening of Bank
Account
Documents (land Title...etc) collected / Plot measured /
structures demarcated
Structures survey & no./Table of house no. prepared.
Developer appointed / Developers appoints architects,
surveyor, engineer etc.
Developers enter into individual agreements with
dwellers.
Proposal with Plans, annexure & documents submitted
to SRA
3. Vacating Property for Rehab
To provide the members with deposit
amount and rent incase of not providing
alternate accomodation by the developer.
Preparation of List of Allottees / Allotment of
tenements is made in joint name.
To sign individual agreement with members
Vacating Property
4. SECOND STAGE
Scrutiny by Sub-Engineer /Scrutiny Fee calculated
Scrutiny fee paid by the Developer
Annexure II submitted for Certification/Annexure III
submitted to finance Dept
Annexure I scrutinised by Engineer Dept
Annexure II & III certified by respective authorities
LOI, Layout, IOA, CC will be issued
5. THIRD STAGE
Lots of Allotment of tenements to Participating members /
subsequently for non-participants
Developers arrange for transit accommodation .either on-site or off-site
Draw of lots for allotment of transit tenements
Slum Dwellers shifted to transit camps & slums hutments
demolished /Non-participants issued notice
If non- participants do not agree within 15 days, they are physically
evicted from slum site
All structures demolished and work upto plinth level is completed
After verifying Plinth dimensions, SRA grants permission to
construct beyond Plinth level
6. FOURTH STAGE
Plan for further rehabilitation & free sale buildings approved
Building permission for free sale building given in proportion of
rehabilitation
Rehabilitation buildings completed
Lists of allotees prepared / Allotment of tenements is made in joint
name
Building completion Certificate submitted by architect
Building & compliance with IOA conditions, verified/Occupation
permitted /possession as per allotement
SRA issued identity cards to Slum dwellers
7. FIFTH STAGE
Construction of remaining buildings
commenced
Further building permissions/Occupation
permissions granted in due course
Separate property cards for rehabilitants
plot, free sale plot & reservation plots
prepared
8. OTHER Activity
• Scrutinizing the planning of Slum Rehab Scheme
& Approval to the same - issuing Letter of Intent,
layout approval & apprvoal of Building Plans -
IOA, Commecment Certificate at various stages of
construction, occupation certificate Approval of
TDR recommendation proposal Planning &
Designing of various amenties in implemented
Slum Rehabilitation schemes Suggestion the
specification regarding elevation ……… Site visit to
various Court matters….
9. Start construction activity
• Approval to start Construction Property Tax Assessment NOC
Hydraulic Engineer No Objection Certificate Strom water
Drainage No Objection Certificate Sewarage No Objection
Certificate Traffic Deptt. No Objection Certificate Tree No
Objection Certificate: (Tree Authority) Pest Control No
Objection Certificate MTNL No Objection Certificate Lift
Inspection No Objection Certificate: Inspector of Lifts, PW
Drainage Completion Certificate : (Water Department) TDR
Loading : Soil Testing Report : The Concerned Laboratory
Master Plan Approval Locational Clearance Building Plan
Approval Consent to Establish Provisional CFO NOC Electricity
Approval Water Approval During & On Completion of
Construction Plinth Completion Certificate Consent to
Operate Final CFO NOC Building Completion Certificate