Network Maintenance Sydney Trains
Working in Summer Instructions
ALL staff working or planning work that will affect track or track stability in the defined summer
period MUST know the requirements for working in summer months - MN T 20211.
The defined summer period is from 1 November to 31 March.
Special maintenance practices are adopted for welded track when the AIR temperature reaches
38°C OR is forecast (by the Bureau of Meteorology) to reach 38°C (35°C prior to 15 November).
All proposed work that affects track stability should be postponed if this temperature is forecast
and stop immediately if these temperatures are reached during work.
Green Card “Safety Net” provisions apply for Manual Resleepering, Mechanised Resleepering,
Mechanised Resurfacing, and Manual Fettling. DO NOT start work unless the maximum forecast
AIR temperature is less than 35°C. And STOP work immediately if the Rail Temperature reaches
38°C or the track shows any sign of moving.
DO NOT carry out ballast cleaning, track jacking, reconditioning etc when the rail temperature is
above 38°C. In the case that WOLO is applied ALL work which may affect track stability MUST
STOP and the track reinstated.
STOP WORK if the temperature exceeds 38°C or WOLO is applied
Before commencing any work that may affect track stability in summer, you MUST request a
“Permission to Disturb” assessment be carried out.
Work that reduces track stability and increases the risk of a misalignment includes:
• Any disturbance to rails, sleepers or ballast.
• Resurfacing.
• Rerailing.
• Resleepering.
• Ballast cleaning.
• Earthworks and drainage.
• Welding & CWR.
• Trenching or installing cables under or alongside the track.
• Repairing rail defects.
• Damaging ballast shoulder/profile with plant/road vehicles
All work that reduces track stability and increases the risk of a misalignment must be assessed
by the local Technical Officer. Work that creates a WTSA P1 or P2 must be authorised by the
Territory Track Engineer.
email: PermissionToDisturb@transport.nsw.gov.au
Authorisation must be received from the local Territory before work may commence.
Working In Summer Instructions – Network Maintenance
If the track shows any sign of movement or high temperature limits are exceeded
and the work cannot be stopped. Contact the local Territory Engineer immediately
During and after work, maintenance staff must be satisfied that the track has been maintained to
its maximum stability and must comply with the requirements detailed in MN T 20211. Any staff
carrying out work affecting track stability MUST report full details of the work to the Territory, In
particular:
 Welding/adjustment returns MUST show steel in / steel out measurements
 Any disturbances
 Alignment measurements (at the time of adjustment)
Report immediately any incidents or unplanned works that occur without the prior knowledge of
the Territory.
 Bumping or disturbing track.
 Uncontrolled rail welding.
 Disturbing ballast.
 Changing track alignment on curves.
 Failing to complete planned rail adjustment.
Authorised Work Outside Green Card Provisions
Clear written authorisation is required before working outside green card provisions.
Mechanised Resurfacing Concrete Sleepered Track and Turnouts
Resurfacing on concrete sleepered track and concrete turnouts may continue under the following
conditions:
 The supervisor in charge has written authorisation from the Territory Track Engineer.
 There is enough ballast to restore a full ballast profile.
 Appropriate speed restrictions are applied following the work in accordance with
MNT20211 (confirm in writing that arrangements for temporary speed have been made).
 Minimum maintenance lifts of no more than 20mm are to be applied.
The supervisor in charge of the resurfacing is to cease work immediately if the rail temperature
exceeds 50°C or the track shows any signs of loss of stability.
Mechanised Resurfacing Timber Sleepered Track and Turnouts (CWR only)
Resurfacing on timber sleepered CWR track may continue under the following conditions:
 The supervisor in charge has written authorisation from the Territory Track Engineer
 Welded Track Stability calculations DO NOT produce a WTSA P2 or higher priority.
 There is enough ballast to restore a full ballast profile.
 Appropriate speed restrictions are applied following the work in accordance with
MNT20211 (confirm in writing that arrangements for temporary speed have been made).
 Minimum maintenance lifts of no more than 20mm are to be applied.
The supervisor in charge of the resurfacing is to cease work immediately if the rail temperature
exceeds 40°C or the track shows any signs of loss of stability.
Working In Summer Instructions – Network Maintenance
Document History
The history of changes made to this document are shown below.
Version Date Author
Description / changes from
previous version
1 22/08/2014 Peter George Initial draft
2 01/10/2014 Peter George Green Card details added
3 06/02/2015 Peter George Approvals changed.
4 01/08/2017 Peter George Work outside Green Card

More Related Content

Similar to Wtsa working in summer instructions

Rts 3648 maintenance of welded track
Rts 3648  maintenance of welded trackRts 3648  maintenance of welded track
Rts 3648 maintenance of welded track
NECB
 
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
anishdani
 
Eti 06-07- responding to buckles
Eti 06-07- responding to bucklesEti 06-07- responding to buckles
Eti 06-07- responding to buckles
NECB
 
Perwaja Steel Job Scop
Perwaja Steel Job ScopPerwaja Steel Job Scop
Perwaja Steel Job Scop
eone iwan
 
Student Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docxStudent Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docx
florriezhamphrey3065
 
ONYEJOSE CHUKWUMA CONTRL ROOM OPERATOR.
ONYEJOSE CHUKWUMA CONTRL ROOM OPERATOR.ONYEJOSE CHUKWUMA CONTRL ROOM OPERATOR.
ONYEJOSE CHUKWUMA CONTRL ROOM OPERATOR.
splendidchuy
 
Stephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioningStephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioning
Stephen Barkwitch
 
julian sharman CV 2016
julian sharman CV 2016julian sharman CV 2016
julian sharman CV 2016
Julian Sharman
 

Similar to Wtsa working in summer instructions (20)

04-3-TS_Vol-II_,Sec-IV,_Pre_Comm_R1.pdf
04-3-TS_Vol-II_,Sec-IV,_Pre_Comm_R1.pdf04-3-TS_Vol-II_,Sec-IV,_Pre_Comm_R1.pdf
04-3-TS_Vol-II_,Sec-IV,_Pre_Comm_R1.pdf
 
Rts 3648 maintenance of welded track
Rts 3648  maintenance of welded trackRts 3648  maintenance of welded track
Rts 3648 maintenance of welded track
 
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
 
Appraisal ppt ankur
Appraisal ppt ankurAppraisal ppt ankur
Appraisal ppt ankur
 
Raghu Resume
Raghu Resume Raghu Resume
Raghu Resume
 
Eti 06-07- responding to buckles
Eti 06-07- responding to bucklesEti 06-07- responding to buckles
Eti 06-07- responding to buckles
 
EDGAR P AGUILAR
EDGAR  P AGUILAREDGAR  P AGUILAR
EDGAR P AGUILAR
 
Basic load out methodologies introduction
Basic load out methodologies introductionBasic load out methodologies introduction
Basic load out methodologies introduction
 
Perwaja Steel Job Scop
Perwaja Steel Job ScopPerwaja Steel Job Scop
Perwaja Steel Job Scop
 
Student Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docxStudent Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docx
 
PHIL VAN DEVENTER RESUME
PHIL VAN DEVENTER RESUMEPHIL VAN DEVENTER RESUME
PHIL VAN DEVENTER RESUME
 
ONYEJOSE CHUKWUMA CONTRL ROOM OPERATOR.
ONYEJOSE CHUKWUMA CONTRL ROOM OPERATOR.ONYEJOSE CHUKWUMA CONTRL ROOM OPERATOR.
ONYEJOSE CHUKWUMA CONTRL ROOM OPERATOR.
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Resume
ResumeResume
Resume
 
PWHT
PWHTPWHT
PWHT
 
SMBITStillRx50-10.pdf
SMBITStillRx50-10.pdfSMBITStillRx50-10.pdf
SMBITStillRx50-10.pdf
 
Stephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioningStephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioning
 
Level 3 ais-manual-12kv
Level 3 ais-manual-12kvLevel 3 ais-manual-12kv
Level 3 ais-manual-12kv
 
Catalog FR-D700 Instruction manual (applied)-Beeteco.com
Catalog FR-D700 Instruction manual (applied)-Beeteco.comCatalog FR-D700 Instruction manual (applied)-Beeteco.com
Catalog FR-D700 Instruction manual (applied)-Beeteco.com
 
julian sharman CV 2016
julian sharman CV 2016julian sharman CV 2016
julian sharman CV 2016
 

More from Garry Pepper

Plumbers sydney water work completions memo
Plumbers sydney water work completions memoPlumbers sydney water work completions memo
Plumbers sydney water work completions memo
Garry Pepper
 
Alert riw transition from pegasus to mta
Alert riw transition from pegasus to mtaAlert riw transition from pegasus to mta
Alert riw transition from pegasus to mta
Garry Pepper
 

More from Garry Pepper (20)

September 2019 amendments flyer
September 2019 amendments flyerSeptember 2019 amendments flyer
September 2019 amendments flyer
 
Safe tracks 2019 08-network rules amendments
Safe tracks 2019 08-network rules amendmentsSafe tracks 2019 08-network rules amendments
Safe tracks 2019 08-network rules amendments
 
Laha memo
Laha memoLaha memo
Laha memo
 
Infraworks social media policy v1.0
Infraworks social media policy v1.0Infraworks social media policy v1.0
Infraworks social media policy v1.0
 
Safe notice 2019 003
Safe notice 2019 003Safe notice 2019 003
Safe notice 2019 003
 
Artc safety alert no. 112
Artc safety alert no. 112Artc safety alert no. 112
Artc safety alert no. 112
 
Safe notice permanent 009
Safe notice permanent 009Safe notice permanent 009
Safe notice permanent 009
 
Changes to css script for toa
Changes to css script for toaChanges to css script for toa
Changes to css script for toa
 
Safe tracks july 07
Safe tracks july 07Safe tracks july 07
Safe tracks july 07
 
S afe notice 193 194 204
S afe notice 193 194 204S afe notice 193 194 204
S afe notice 193 194 204
 
Plumbers sydney water work completions memo
Plumbers sydney water work completions memoPlumbers sydney water work completions memo
Plumbers sydney water work completions memo
 
Lessons learnt electrical incident penrith wrp july 2019
Lessons learnt electrical incident penrith wrp july 2019Lessons learnt electrical incident penrith wrp july 2019
Lessons learnt electrical incident penrith wrp july 2019
 
Alert riw transition from pegasus to mta
Alert riw transition from pegasus to mtaAlert riw transition from pegasus to mta
Alert riw transition from pegasus to mta
 
Safe notice 192 191
Safe notice 192 191Safe notice 192 191
Safe notice 192 191
 
Safe notice telegram 1027
Safe notice telegram 1027Safe notice telegram 1027
Safe notice telegram 1027
 
Infraworks induction presentaion v4.0
Infraworks induction presentaion v4.0Infraworks induction presentaion v4.0
Infraworks induction presentaion v4.0
 
Safe notice 178 189 206
Safe notice 178 189 206Safe notice 178 189 206
Safe notice 178 189 206
 
Safe notice permanent 008 2019
Safe notice permanent 008 2019Safe notice permanent 008 2019
Safe notice permanent 008 2019
 
Reminder to vote EA
Reminder to vote EAReminder to vote EA
Reminder to vote EA
 
Safe notice 160 231 176 175
Safe notice 160 231 176 175Safe notice 160 231 176 175
Safe notice 160 231 176 175
 

Recently uploaded

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Dipal Arora
 

Recently uploaded (20)

Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 

Wtsa working in summer instructions

  • 1. Network Maintenance Sydney Trains Working in Summer Instructions ALL staff working or planning work that will affect track or track stability in the defined summer period MUST know the requirements for working in summer months - MN T 20211. The defined summer period is from 1 November to 31 March. Special maintenance practices are adopted for welded track when the AIR temperature reaches 38°C OR is forecast (by the Bureau of Meteorology) to reach 38°C (35°C prior to 15 November). All proposed work that affects track stability should be postponed if this temperature is forecast and stop immediately if these temperatures are reached during work. Green Card “Safety Net” provisions apply for Manual Resleepering, Mechanised Resleepering, Mechanised Resurfacing, and Manual Fettling. DO NOT start work unless the maximum forecast AIR temperature is less than 35°C. And STOP work immediately if the Rail Temperature reaches 38°C or the track shows any sign of moving. DO NOT carry out ballast cleaning, track jacking, reconditioning etc when the rail temperature is above 38°C. In the case that WOLO is applied ALL work which may affect track stability MUST STOP and the track reinstated. STOP WORK if the temperature exceeds 38°C or WOLO is applied Before commencing any work that may affect track stability in summer, you MUST request a “Permission to Disturb” assessment be carried out. Work that reduces track stability and increases the risk of a misalignment includes: • Any disturbance to rails, sleepers or ballast. • Resurfacing. • Rerailing. • Resleepering. • Ballast cleaning. • Earthworks and drainage. • Welding & CWR. • Trenching or installing cables under or alongside the track. • Repairing rail defects. • Damaging ballast shoulder/profile with plant/road vehicles All work that reduces track stability and increases the risk of a misalignment must be assessed by the local Technical Officer. Work that creates a WTSA P1 or P2 must be authorised by the Territory Track Engineer. email: PermissionToDisturb@transport.nsw.gov.au Authorisation must be received from the local Territory before work may commence.
  • 2. Working In Summer Instructions – Network Maintenance If the track shows any sign of movement or high temperature limits are exceeded and the work cannot be stopped. Contact the local Territory Engineer immediately During and after work, maintenance staff must be satisfied that the track has been maintained to its maximum stability and must comply with the requirements detailed in MN T 20211. Any staff carrying out work affecting track stability MUST report full details of the work to the Territory, In particular:  Welding/adjustment returns MUST show steel in / steel out measurements  Any disturbances  Alignment measurements (at the time of adjustment) Report immediately any incidents or unplanned works that occur without the prior knowledge of the Territory.  Bumping or disturbing track.  Uncontrolled rail welding.  Disturbing ballast.  Changing track alignment on curves.  Failing to complete planned rail adjustment. Authorised Work Outside Green Card Provisions Clear written authorisation is required before working outside green card provisions. Mechanised Resurfacing Concrete Sleepered Track and Turnouts Resurfacing on concrete sleepered track and concrete turnouts may continue under the following conditions:  The supervisor in charge has written authorisation from the Territory Track Engineer.  There is enough ballast to restore a full ballast profile.  Appropriate speed restrictions are applied following the work in accordance with MNT20211 (confirm in writing that arrangements for temporary speed have been made).  Minimum maintenance lifts of no more than 20mm are to be applied. The supervisor in charge of the resurfacing is to cease work immediately if the rail temperature exceeds 50°C or the track shows any signs of loss of stability. Mechanised Resurfacing Timber Sleepered Track and Turnouts (CWR only) Resurfacing on timber sleepered CWR track may continue under the following conditions:  The supervisor in charge has written authorisation from the Territory Track Engineer  Welded Track Stability calculations DO NOT produce a WTSA P2 or higher priority.  There is enough ballast to restore a full ballast profile.  Appropriate speed restrictions are applied following the work in accordance with MNT20211 (confirm in writing that arrangements for temporary speed have been made).  Minimum maintenance lifts of no more than 20mm are to be applied. The supervisor in charge of the resurfacing is to cease work immediately if the rail temperature exceeds 40°C or the track shows any signs of loss of stability.
  • 3. Working In Summer Instructions – Network Maintenance Document History The history of changes made to this document are shown below. Version Date Author Description / changes from previous version 1 22/08/2014 Peter George Initial draft 2 01/10/2014 Peter George Green Card details added 3 06/02/2015 Peter George Approvals changed. 4 01/08/2017 Peter George Work outside Green Card