“New NMR LWD Laboratory LAYOUT”
LEAN Project
By Cesar Javier Siles Saracho
Electronic Engineer
Table of Contents
1 Project Motivation
2 Project Objectives
3 Problem Definition
4 Measure
5 Analyze
6 Improve
7 Control
8 Project Cost and Benefits
9 Conclusions
10 Appendix
List of Tables and Figures
Table 1 SIPOC
Table 2 Old Layout Spaghetti
Table 3 Weighted Average Process time and process Efficiency
Table 4 Solutions to Kaizen Events
Table 5 New Weighted Average Process time and process Efficiency
Table 6 New Spaghetti Diagram
Table 7 Old Vs. New State
Table 9 Control Time Sheet
Table 8 Financial Impact
Fig 1 Old Spaghetti Diagram
Fig 2 Swinlane diagram & RACI Chart
Fig 3 VSM Old Layout
Fig 4 Time Spent in Process Lab and Service Levels
Fig 5 The New Layout
Fig 6 Mechanic WorkStation
Fig 7 Electronic workstations
Fig 8 Pedestal ,Flow Kits, Special Tools
Fig 9 Upper Chassis Electronics Rack
Fig 10 Turbines Rack
Fig 11 Magnets Rack
Fig 12 Loading - Unloading Area
Fig 13 Calibration Container
Fig 14 New Lead Time
Fig 15 VSM New Layout
Fig 16 New Spaghetti Diagram
Fig 17 Old vs New Layout
Fig 18 Control Process Time
1.Project Motivation
Monitoring the actual proVISION work process , it is possible to observe that in most of
the sub processes , there is waste , like excessive motion, transportation , defect and waiting
time ,so there are several opportunities to optimize such process.
The company did the decision to built a new bigger laboratory at the base, thus it will give
the great chance to improve the actual Layout of the proVISION Laboratory, so the
mentioned problems related to non value added time could be minimized.
This project is going to use Lean Tools and techniques to minimize the waste in a process or
just reduce the activities that not add value in the process. The first step is going to be a
define phase, when all the main problems are going to defined, Then the process need to
be measure, It means that all sub process will be measure in time, so it will analyze the
bottlenecks and calculating the efficiency and maximum capacity of tools that could being
provided. The next step will be the proposal plan to improve the process using a new Layout
that plays a crucial role in determining the flow patterns, reduce the waste , organize the
workplace and impact the safety.
The new Layout will be consider as the main problem solving tool ,however it is also
necessary use a systematic method to improve and sustain workplace organization (5S),
standardize some of the sub process and get the habilitation
of equipment strongly necessary to perform important tests.
With the implementation of this project it will increase the efficiency and capacity to cover
the future client’s demand.
It will also reduce the non value added time , will be soft saving and it will improve the
service quality and safety.
Finally the motivation factors could be summarize in the following :
• Expansion due to activity increase
• Expected Job count from 3.9 to 6.5 during 2013 (Q1-Q4)
• Reduce the non value added time
• Reduce Costs
• Provide a better service quality
2.Project Objectives
• Design a layout to optimize the flow of proVISION Tools by minimizing the times
the tools have to go back to the same workstation, reduce the distance between
stations, reduce the barriers between stations, decrease the movement of heavy
equipment such as container and design a better path to get access to shared
equipment like ovens .
• Increase also the service Quality by organizing the workplace, so adding store
places for proVISION components , such as racks, cabinets, implementing trolleys
for move heavy items and fixing turbine test setup.
• Improve the safety by reducing the mechanical lifting operations, like moving
container with a forklift, loading electronics out of a yellow line for personnel and
Rack magnets out of compliance.
• Improve the efficiency of the proVISION Laboratory by 22% and the capacity by
23 %
3.Problem Definition
The problems have seen in the actual NMR work process are :
• Excessive motion of technicians, going to the Break Out Machine , Push or The
Surface area to get a container.
• Excessive transportation of the tool , it have to travel several times long ways. The
NMR Collar goes from PUSH Area to NMR Lab to be unloaded , then it have to
return to PUSH Area to be inspected and finally go back to NMR Lab to load the
electronic. After loading the electronics, some test are performed, then the tool goes
to the BOM to torque the wear bands to be ready for calibration, Then it goes to the
calibration container, later it have to return to the BOM for assembly (Turbine , Pony )
and finally the last test (Jackstand test ) need to be performed also in the
calibration container . This is difficult to move due the tool with the pony is longer and
heavier. ( Fig 1 Old Spaghetti Layout )
• There is no specific area to place the container. There is a lot of time consuming
and waiting time, to perform the task to move the container inside the workshop with a
forklift, the use of crane to move the container from the entrance to the push area ,
placing the tool inside the container and finally doing the setup by covering the holes
with aluminum.
• The actual NMR Lab is situated next to Xceed test area. This situation is one of the key
problems affecting NMR service time due to the noise affecting NMR tests, and the
waste related to "wait time" or rework. The longest test the could avoided is the PWO
test that usually takes 3hrs.
• Actually, using Xceed Turbine test set up for NMR Turbine test adds to the wait time as
the Technicians wait for Xceed test to be completed before they can set up NMR Turbine.
• The NMR tool is seriously affected by electrical noise, so the electrical grounding need
to be improved.
• The two Ovens are shared , so it derives in a lot of waiting time and extra time in
Setup.
• Actual layout doesn’t provide a good space for loading the upper chassis due it cross
the corridor and interrupt the normal transit of people.
• The rack magnets is too close to computer setup.
• The ProVISION area doesn’t provide enough room to perform some processes
simultaneously.
RIRs Related
• 20120903163758 Sep 01, 2012 SQ
• 20121203160050 Nov 30, 2012 HSE
• 20121229182212 Dec 27, 2012 SQ
• 20130225140537 Feb 22, 2013 SQ
• 20130306122618 Mar 01, 2013 Sug
• 20130319095118 Mar 19, 2013 SQ
• InTouch Ticket 6128184, 6179781
In order to help to determine the scope of the project we are going to use the SIPOC
LEAN tool (Supplier, Input, Process, Output, and Customer) , It is also a very high level map of
a process that help to identify any quick disconnects with the supplier inputs, and identify the
project customers and their outputs.
TABLE 1 proVISION SIPOC
!
4.Measure
The collected information will allow us to make important decisions and manage the
process by facts and evidence. It will also quantify the baseline and show the improvement
after the project is completed. So for this case the issue is to calculate the actual capacity
of the proVISION work process and the efficiency in order to have a start point to know
if we could comply with the future customer capacity.
From the Spaghetti diagram below Fig1 , it is possible to observe the waste of excessive
motion of the technician and also excessive transportation of the proVISION items (Collar,
pony collar , turbine ) in the actual work process. Two shift of mechanicals and electronics
technician working on the same tool from the Beginning to the end do the job in 51
Steps , with a total distance of 1219mts .From the Table 2 is possible quantify the distance
of each step and observe the highest distances to run are to get a borrowed container
for calibration , go to Break Out Machine (BOM ) and IST are (Incoming Sytem Test )
Technic
ian
R&M
Too
Push
deliver PULL
TEAM
Figure 1 OLD SPAGHETTI LAYOUT
Table 2 Old Layout Spaghetti Service Level 3
The Swinlane diagram Fig2 show the proVISION work process and help us to understand
the interactions of the proVISION work process through the different departments, some
departments like Push and Pull have a big contribution in the tool lead time , however
we are only focus to minimize the waste in the ProVISION Lab process ( total
time of 86hrs SL3).
OLD Spaghetti Service Level 3
# Step distance (Mts) Comments
ET1 0-1 105 Take setup to IST Area
ET1 1-2 105 Return from IST
ET1 2-3 11.38 Go out side with Trolley
ET1 3-4 4.87 Install power cord ,
Et1 4-5 4.87 Remove plugs and unsolder
MT1 2-3 6.5 Go out side to remove Jamnuts with splecial tool
MT1 3-4 5.46 Search for tube to remove jamnuts
MT1 4-5 5.46 Returning with tube to remove jam nuts
MT1 5-6 5.82 Remove the LC
MT1 6-7 3.69 Place the LC in the RACK
Et1 5-6 2 help the the MT place the LC
MT1 7-8 12 take special tool to remove UC
MT1 8-9 6.4 Place Special tool to remove UC and remove UC
ET1 6-7 13.54 Search Trolley to remove UC
ET1 7-8 7.62 place the Trolley y pull together with the MT1
ET1 9-10 7.5 Remove UC with MT1
MT1 9-10 6.5 search for trolley from TST area
MT1 10-11 6.9 return with trolley and pull the UC
ET1 9-10 7.8 Return trolley from TST
ET1 10-11 6 go back to lab to work in UC
MT1 11-12 64 Move Collar to Inspection Area
MT1 12-13 64 return from push
MT1 13-14 7.6 Take the crane to lift UC
MT1 14-15 4 Place the crane and remove NMR & Power Chassis
ET1 11-12 11.6 move to get ovens
ET1 12-13 17 ET1 Returns with one oven
ET1 13-14 7 Return to get secong oven
ET1 14-15 5.6 Takes the second oven
ET1 15-16 6.5 Connects the power cord
ET1 16-17 8.3 Returns to work heat test setup
MT1 15-16 147 MT goes to surface to coordinate the container
MT1 140 MT Goes to coordinate the forklift
MT1 16-17 90 MT Return from surface to the workshop entrance
MT1 17-18 14 Move container to Calibration Area
ET1 17-18 42 ET1 goes to help the MT to move the container
ET1 18-19 12 ET1 help the MT to place the container
ET1 19-20 26 ET goes to NMR Area to lift the tool
MT1 18-19 26 MT goes to NMR Area
MT1 19-20 26 MT Return with the tool
ET1 20-21 26 ET returns with the tool
ET1 21-22 18.5 Goes to BOM to assembly Pony and Turbine
MT1 20-21 23 Goes to BOM to assembly Pony and Turbine
MT1 21-22 30 Install Shield and move tool Pull
ET1 22-23 27 Install Shield and move tool Pull
Et1 23-24 10 goes to moves the container back
MT1 22-23 10 goes to moves the container back
MT1 23-24 11 moves container
ET1 24-25 11 moves container
1219.41 MTS
Total STEP of both ET &MT is 51
The RACI Chart Fig 2 should clarify roles, as well as ensure accountability and individual
levels of participation.
NMR Supervisor
ElectonicTechncian
MechanicalTechnician
Inspection Team
ARII
ARII
IR
IRR
IIIAR
IRR
AR
IRR
IR
IR
CRR
AssemblyToolandcompleteOSTARR
PerfomTestHeatTest
LoadUpperChassis
PerformVaccumTestonCollar
PerformUCTests
ACTIVITIES
QualityCheck
AlertTeamToolarrivalinPUSH
ExplainTCO,PriorityandSL
PerformtheIST
UnloadUpperChassis
Inspection
PerformR&M
Fig2SwimLaneDiagram&RACI
Chart
Fig3VSMSL3OldLayout
In the Value Stream Map Fig 3 (see previous page) for the actual is possible to measure
the timing of the entire ProVISION Laboratory process for the maximum service level 3 ,
taking in count that the lead time of each individual process is the sum of value added
time and non value added time. However this case is only for SL3 , so we have to do
similar Value Steam Maps for the rest of services levels 0,1,2 . (Appendix A).
*Note.In the VSM Fig 3, it was not consider the rework in all the process except of heat
test and also the time spent in Failure investigation
5.Analyze
In order to calculate the weighted average of the total process time and the efficiency
we need to consider the Timing of each service level and also the contribution of each
service levels according to the statistics (Qtrac between October 2012 to Jan 2013 ) .
So from the table 3 and figure 4 below we calculate the average time to produce one tool
including the service probability as per Service Level and the efficiency of the our process.
Table 3 Actual Weighted Average Process time and process Efficiency
Now From the data above we derive in the Maximum Capacity and Takt Time
Calculating the Actual Capacity and Efficiency
!
ServiceLevels Sep2012-Dec2013 SL MRT6 MRT8
Period
TotaL
Toolsper
month SL%
VA/T
(hrs)
L/T
hrs
L/Tx %
(hrs) VAx%
MRT6UC 6007 (including one time )
SL3 or
SL4 15 6 21 1.31 21.00 47.90 86.10 18.08 10.06
SL2 25 7 32 2.00 32.00 29.00 42.00 13.44 9.28
SL1 12 5 17 1.06 17.00 6.50 16.30 2.77 1.11
SL0 24 6 30 1.88 30.00 2.75 8.80 2.64 0.83
Total 76 24 100 6.25 100
Average
L/T (hrs) 36.93
Average
VA(hrs) 21.27
Fig 4 Time Spent in Process Lab and Service Levels %
! !
Bottle Neck is the process with the highest long term utilization, so if we see again the
VSM Fig 3 it would be the heat test with an average of 39hrs (calculate below), however
the process itself only take 18,5 hrs including shop failure , so the NVA 20.5 hrs (waste
time ) it is considerable
Heat Test 67 % no rework & 33 % rework (Heat Test Statistic 3failed and 6 passed)
no rework = 10work hrs + 17.5 waitoven = 27.5hrs
rework = norework + 16hrs troubleshoot + 10workhours + 8.75waitoven = 62.25hrs
Total = 0.67 x 27.5 + 0.33 x 62.25 = 39hrs
VA = 10hrs x 0.67 + (10 + 16 + 10) x 0.33 = 18.5 hrs
NVA = 0.67 x 17.5hrs + 0.33 x ( 17.5 + 8.75) = 20.5hrs
6.Improve
The improve plan will be using the following LEAN methods, Kaizen Events, Improve
Layout, 5S and Generate improvent ideas.
As we can see from the table 4 the solution to the problem is going to be time saving
projects that will impact the efficency and the quality of the overall process. Such projects
were created with ideas generated by teamwork.
The List of Kaizen event was taken from the VSM , and the time saved in each process
in order to minimize the Non Value adde time is in base of Layout solution,
5S ,changes in procedures and getting new standard equipment.
Table 4 Solutions to Kaizen Events
!
SOLUTIONES TO KAIZEN EVENTS
OLD NEW
PROCESS
Total C/T
(hrs)
VA
(hrs)
NVA
(hrs)
NVA
(hrs)
KAIZEN EVENT
EQUIPMENT NEEDED
IST 1.5 0.5 1 0.5
Electronic workstation and calibration KIT
in PUSH Area (future Layout)
DC power suplies ,TSIM
,computer , calibration Tanks
and shields , jackstands
UNSOLDER ANTENNA,
REMOVE JAMM NUTS,LC,UC 3.5 2.25 1.25 0.75
Unloading workStation in PUSH Area
(future Layout)
Portable soldering
workstation and special tools
to remove UC
REMOVE UPPER MAGNET 0.917 0.5 0.417 0.25
New Mechanical lifting Equipment
Trolley for Magnets and
Pallet Truck
SL UC (CHANGE BATT, ORING
MOD RECAP IF NEEDED 8.2 6.7 1.5 1
New Benches Layout , easy way to move
the Upper Chassis Electronics with a
trolley (Fig 7)
Soldering workstation, Rack
for UC , Pallet Truck for upper
magnet
SETUP FOR HEAT TEST
INSTALL TANK 1.5 1 0.5 0.25
5S for cables and wires
Kit of wires for Antenna ,
Battery,RPM simultator,
Termocouple
HEAT TEST 39 18.5 20.5 17.8
Less time spent to setup due to new
layout, Turbine Test jig for NMR only, and
decreased Xceed tests interference
New Turbine Test Setup , New
TurbinesRACK
CONNECT UPPER MAGNETS &
FINALIZING UC 3.75 3.5 0.25 0.1
New Layout, less distance to Racks, and
lifting Equipment
New Rack for Magnets, Pallet
Truck and Special Trolley
LOADING UPPER CHASSIS , LC
and Torque Jamm Nuts 4.25 2 2.25 2
Loading Chassis with Ratchet Strap Best
Practice 6218607,Improved Loadingarea
Cabinets for Special Tools
New Racks for Magnets, Special
Tool for Loading UC, Cabinets for
wearbands ,flow kits
SOLDERING & INSTALL ROPs 1.5 1.5 0 0
Soldering workstation Soldering workstation
TURBINE TEST 2.25 1 1.25 0.25
Turbine Test , RACKs and New Layout
New complete turbine Test ,
New TurbineRACK
UPDATE SOFTWARE ,PWO,
RBT LTB TESTS 6.75 5.5 1.25 0.5
With New Layout less interference from
Exceed,MRT8TankbestPractice6302142 LTB Wires KIT
TORQUE PONY & WEAR
BANDS , LOADING TURBINE 3.75 1.25 2.5 1.5
Less distance to BOM due new Layout and
changeintheProcessIT6128184
Turbines ,Pedestal Racks and
Cabinets
CALIBRATION IN CONTAINER 3.8 1.5 2.3 0.5
Container already in LAB Layout , no
need to move from surface Area ,
Best practice # 6237734
NEW owned Container
Design,
JACKSTAND 3.25 1.25 2 1
Improve procedure,Configuration File
readyinTCO QUEST 20130306122618
QTRAC,OST VALIDATION ,
INSTALL SHIELD, TO PUSH 2.25 1 1.25 0
Improve Layout, not necessary remove
container , Lifting Equipment ,
TIME (hrs) 86.167 47.95 38.217 26.4
!
Fig5NewproVISIONLayout
The New Layout Fig 5
• The new Layout is designed to have a Linear Flow , so it follow as much as
posible the ProVISION work Process. This layout is designed to impact the
safety,quality, workplace organization and future expansion.
• After breaking the tool and washing the main components (Pony, turbine and MRT
collar) the turbine enter the lab first,IST is performed, then the UC have to be
unloaded in the same place, so the collar will have a shorter path to the inspection
area meanwhile the Upper Chassis enter in the lab to perform the required service
level. Later the collar enter in the laboratory and it is placed at the heat test are
were the Upper Chassis is going to be heat. (The UC have to go back a litte for
heat test)
• After heat the elecronics and at the same time the turbine could serviced , the
upper chassis is finalized, then load for testing and final calibration in container .
At last the MRT collar a the turbine leave the lab for assembly together wih the
pony in the Pull area.
• The there are two parallel long benches for the mechanic technicians Fig 6 , so it
could be placed two turbines in the 2 benches of 1.5mts x 0.7mts with easy
access of both sides and also there are two more benches for place two magnets.
Ther are also Two extra tables to place the computers technician in order to
prevent the computer damage due to magnets or vibration to hit on the same table.
• There are basically three benches for the Electronic workstation Fig 7 so it is easy
access and place the tool over the bench just using the trolley. It is also enough
space to perform maintenace of two upper chassis at the same time as in general
the trolley is used to perform this service. One extra bench is required for laptops.
• In The Fig 8, Fig 9 ,Fig 10 and Fig 10 is posible to observed to differents racks and
cabinets in order to organize the workplace ,comply with the SQ Standards by
segregating the NMR Equpment like , Pedestalls , Flow Kits , Electronics, Turbines
and Magnets . Such Racks were designed taking in mind the future activity (See
Apendix )
• The magnets have been placed away from the computer setups,far from tools and
isolated with its respective warning signs. Also a new rack for the the magnets have
been introduced in order to improve the segregation and minimize the risk of attraction
between them while are transported.Fig11
• The Loading area Fig 12 for the Upper Chassis avoid the safety issues of the
previous one where the movement of the electronics had to cross the corridor,so now
there is enough space between tools and it will be possible the perform processes
in parallel , like for example Heat Test , PWO RBT LTB and calibration and
Jackstand.
• With The Calibration container Fig 13 ( Appendix 10) inside the laboratory the use of
forklift was eliminated and also it was placed far enough to minimize the
interference between other tools. With The practical hole in the container it is
possible to setup the tool in less
time.
Fig 6 Mechanic WorkStation Before After
! !
Fig 7 Electronic workstations Before After
!
Fig 8 Pedestal & FlowKit Before After
! ! !
Fig 9 UC mixed with others Electronics Before After
! !
Fig 10 New Turbine Rack
!
Fig 11 Magnets Racks Before After
! !
Fig 12 Loading /Unloading Area Before After
! !
Fig 13 Calibration Container Before After
! !
After working in the new layout with all the required equipment it is possible to generate
a Future VSM SL3 Fig 15 (similar VSM are needed for SL0,1,2) , then we can make the
similar previous analysis in order to calculate the new efficency and maximun capacity of the
new layout. (Fig14)
Table 5 New Weighted Average Process time and process Efficiency
Fig 14 New Lead Time
Calculating the NEW Capacity
Qtrac SLevelsOct12-Aug 13 SL MRT6 MRT8
Period
TotaL
Average
per
month SL%
VA/T
(hrs)
L/T
(hrs)
L/Tx %
(hrs) VAx%
MRT6UC 6007 (including one time )
S3 or SL
4 15 6 21 1.3125 21 47.90 74.3 15.603 10.06
SL2 25 7 32 2 32 29.00 35.2 11.264 9.28
S1 12 5 17 1.0625 17 6.50 11.3 1.921 1.11
SL0 24 6 30 1.875 30 2.75 4 1.200 0.83
Total 76 24 100 6.25
Average
L/T (hrs) 29.99
VA (hrs) 21.27
New Lead Time
HRS
0
20
40
60
80
SL3 SL2 SL1 SL0
Lead Time = 30hrs (weigthed average time)
Efficiency = VA / Lead Time = 71 %
Capacity = Available time / Lead Time = 10.6 Tools/month
!
Fig15VSMSL3NewLayout
At same time we are going derive in a future Spaghetti Diagram Fig 16 & Table 6
Table 6 New Spaghetti Diagram
!
# Step distance (Mts) Comments
ET1 0-1 20 Take setup to IST Area
ET1 1-2 22 Return from IST
ET1 2-3 15 Goes to Unloading area with Trolley
ET1 3-4 8.5 Install power cord ,
ET1 4-5 3.5 Remove plugs and unsolder
MT1 0-1 6.6 Go outside to remove Jamnuts with special tools
MT1 1-2 2.5 Remove theLC
MT1 2-3 7 Place the LC in the RACK or bench
Et1 5-6 11 help the the MT place the LC
MT1 3-4 16.5 taks and Place Special tool to remove UC
Et1 6-7 21 Search Trolley to remove UC
MT1 4-5 11 Place UC collar to Inspection
ET1 7-8 26 Place UC inside the Lab for R&M
MT1 5-6 40 return to work in lab and then place the collar for heat test
ET1 8-9 14 Place the two ovens one by one
ET1 9-10 18 Place the UC inside de oven and perfrom heat
ET1 10-11 29.5 finalize ,Load Tool , Then perform calibration and tests
MT1 6-7 11 Load tool
MT1 7-8 32 Takes turbine to install the flow kit
MT1 8-9 49 Together with the ET place the tool inside container
ET1 11-12 34 Assembly tool in PULL BOM
MT1 9-10 38 Assembly tool in PULL BOM
436.1 MTS
!
Fig16NewSpaghettiDiagram
After the improvement is extremely important compare the old state, versus the future
state in order to verify and prove the improvement in efficiency and capacity
Comparison Actual Vs Future State
Fig 17 Old vs. New Layout
!
Table 7 Old Vs. New State
!
7.Control
The control is going to be implemented by :
• 5S Audit including the Layout
• Floor Lines to indicate the correct place of equipment
• Compare expected Lead Time vs. actual Lead Time . Figure 18 below shows
the Lead time of tools as per service levels during the period of Jun –July
2013. It is possible to observe that several tools the lead time was not as
expected.
• Control Time Sheet to sustaining and continuous improvement Table 9
Fig 18 CONTROL PROCESS TIME
!
!
Table 8 Control Time Sheet
!
SERVICE LEVEL CONTROLTIME SHEET
TOOl SN
UPPERCHASSISSERVICELEVEL 3
PROCESS
Expected
Time (hrs )
START TIME ENDTIME HRS DATE TECH COMMENTS
IST 1
REMOVE JAMNUT,LC,UNSOLDER
ANTENNA,UNLOAD UC 3
REMOVE UPPERMAGNET 0.75
SL UC(BATTERY,ORINGR,MR) 7.7
SETUP ForHeatTest 1.25
HEAT TEST 36.3
CONNECT UPPERMAGNETAND
FINALIZE 3.6
LOAD UC,LC,INSTALL JAMNUTS 4
SOLDERINGAND INSTALL ROP 1.5
TURBINE TEST 1.25
UPDATESOFTWARE, LTB,PWO,RBT 6
CALIBRATION 2
JACKSTAND 2.25
ASSEMBLYTOOLINBOM 2.75
INSTALLSHIELD ,CLOSEWO 1
74.35
8.Project Cost and Benefits
Table 9 Financial Impact
BENEFITS
Financial
Soft Saving 100K$us/ year
Service Quality
• Increase the Efficiency by 24% and Capacity by 23 %
• Improve Capacity from 8.6 to 10.6 Tools/ Month with the same personal
• Reduced the Distance by 783mts
• Organize Workplace with new Racks and segregating the equipment
LABOR Description
Baseline
process
New
process
Hours Saved Hourly Rate Savings
Non-exempt time per year
Redution in Total Lead Time
(7hrs/Tool) x 6 Tool /Month x
12month
2664 2160 504 $ 100.00 50,400.00$
(Old LT 37hrs , New LT 30hrs ) -$
50,400.00$
COSTAVOIDANCE/RISKREDUCTION Description
Baseline
process
New
process
Value per Unit
Number of
units per
year
Savings
SQ Event reduction
Board damaged by Store
Electronics (every 2 year )
$ 6,000.00 0.5 3,000.00$
Job count increase (when there is
market)
Increased Tool Capacity by 2 $ 186,000.00 0.25 46,500.00$
RPJ(In K$) = 186 K$us -$
49,500.00$
EQUPMENT/SOFTWARE/FOOTPRINT Description
Baseline
process
New
process
Value per Unit
Number of
units per
year
Costs
New equipment (3)Racks and (1) Cabinets $ 8,362.00 1 (8,362.00)$
New equipment Fixing Turbine Test Setup $ 1,000.00 1 (1,000.00)$
-$
(9,362.00)$
$99,900.00
9,362.00$
$90,538.00
ACTUALSOFTSAVINGS
TOTALPROJECTSAVINGS-TOTALPROJECTCOSTS
ACTUALSOFTCOSTS
SOFTSAVINGS/COSTS
Safety
• Eliminate Mechanical Forklift Operations
• New Loading Area not crossing trough Yellow personnel corridor and doors
• Magnets Racks far from Electronic Workstations , Tools, and Magnetic
equipment
• Minimize Collar transportation
Client
Improve the Turn Around Time
9.Conclusions
• The new Lab Layout plays an important role to determine the Tools flow and need
to be done according to the proVISION work process, safety and future expansion in
mind.
• The combination of a new Lean Layout and workplace organization will improve the
efficiency and safety of the process.
• The project helped the whole team to understand the impact of a Lean Layout on your
daily work
10 Appendix Diagrams
Calibration Container
!
! !
PEDESTALS RACK for 24 Units 30Kg per Arm , Total Rack Capacity = 300KG QTY 1
! !
!
!
TURBINES FOR 24 UNITS (similar to Xceed Rack) Per Arm Max 300Kg , Total Capacity = 300Kgx 8 Arms=
2400KG QTY 1
Upper Chassis RACK(Electronics ) for 7 Units Lower Arms= 1500kg , Middle arms =1
000Kg , Upper Arms =1000Kg Total Rack Capacity = 3500KG QTY 1
! !
Cabinet for Flow KITS and Special Tools , Qty 1 Total Capacity = 250 KG
!
MAGNETS RACK for 8 Units ( Made of None Magnetic
Material )

More Related Content

Viewers also liked

книжки про книжки
книжки про книжкикнижки про книжки
книжки про книжкиSvetik Svetik
 
Americano_PublicWork_April2016
Americano_PublicWork_April2016Americano_PublicWork_April2016
Americano_PublicWork_April2016Robinson Warner
 
Arsenal Grille Options 2009
Arsenal Grille Options 2009Arsenal Grille Options 2009
Arsenal Grille Options 2009Michael Jackson
 
14 NCR - Ralph Lauren 7-14
14 NCR - Ralph Lauren 7-1414 NCR - Ralph Lauren 7-14
14 NCR - Ralph Lauren 7-14Joseph Foran
 
Manohar kumar jha
Manohar kumar jhaManohar kumar jha
Manohar kumar jhaManohar jha
 
Una guía para elaborar investigaciones filosóficas
Una guía para elaborar investigaciones filosóficasUna guía para elaborar investigaciones filosóficas
Una guía para elaborar investigaciones filosóficasWilbert Tapia
 
El hombre postorgánico: un proyecto fáustico
El hombre postorgánico: un proyecto fáusticoEl hombre postorgánico: un proyecto fáustico
El hombre postorgánico: un proyecto fáusticoWilbert Tapia
 
7 Google Tag Manager Tips to Make Your Job Easier
7 Google Tag Manager Tips to Make Your Job Easier7 Google Tag Manager Tips to Make Your Job Easier
7 Google Tag Manager Tips to Make Your Job EasierWorkshop Digital
 
Reflexión acerca de la entrevista a Paula Sibilia
Reflexión acerca de la entrevista a Paula SibiliaReflexión acerca de la entrevista a Paula Sibilia
Reflexión acerca de la entrevista a Paula SibiliaMaria Belen Oro
 
G i J; TG i TJ; X i TX, -IG
G i J; TG i TJ; X i TX, -IGG i J; TG i TJ; X i TX, -IG
G i J; TG i TJ; X i TX, -IGannaasiscar
 
El mundo de Sofía 1
El mundo de Sofía 1El mundo de Sofía 1
El mundo de Sofía 1Wilbert Tapia
 
Relacion Medico Paciente Psiquiatria
Relacion Medico Paciente PsiquiatriaRelacion Medico Paciente Psiquiatria
Relacion Medico Paciente PsiquiatriaJuan N. Corpas
 

Viewers also liked (17)

Kervran3
Kervran3Kervran3
Kervran3
 
книжки про книжки
книжки про книжкикнижки про книжки
книжки про книжки
 
Americano_PublicWork_April2016
Americano_PublicWork_April2016Americano_PublicWork_April2016
Americano_PublicWork_April2016
 
Arsenal Grille Options 2009
Arsenal Grille Options 2009Arsenal Grille Options 2009
Arsenal Grille Options 2009
 
Med 560 wk2 (3)
Med 560 wk2 (3)Med 560 wk2 (3)
Med 560 wk2 (3)
 
14 NCR - Ralph Lauren 7-14
14 NCR - Ralph Lauren 7-1414 NCR - Ralph Lauren 7-14
14 NCR - Ralph Lauren 7-14
 
Manohar kumar jha
Manohar kumar jhaManohar kumar jha
Manohar kumar jha
 
Sistema nervioso
Sistema nervioso Sistema nervioso
Sistema nervioso
 
Una guía para elaborar investigaciones filosóficas
Una guía para elaborar investigaciones filosóficasUna guía para elaborar investigaciones filosóficas
Una guía para elaborar investigaciones filosóficas
 
El hombre postorgánico: un proyecto fáustico
El hombre postorgánico: un proyecto fáusticoEl hombre postorgánico: un proyecto fáustico
El hombre postorgánico: un proyecto fáustico
 
7 Google Tag Manager Tips to Make Your Job Easier
7 Google Tag Manager Tips to Make Your Job Easier7 Google Tag Manager Tips to Make Your Job Easier
7 Google Tag Manager Tips to Make Your Job Easier
 
Reflexión acerca de la entrevista a Paula Sibilia
Reflexión acerca de la entrevista a Paula SibiliaReflexión acerca de la entrevista a Paula Sibilia
Reflexión acerca de la entrevista a Paula Sibilia
 
G i J; TG i TJ; X i TX, -IG
G i J; TG i TJ; X i TX, -IGG i J; TG i TJ; X i TX, -IG
G i J; TG i TJ; X i TX, -IG
 
Rx del torax, radiografia del torax
Rx del torax, radiografia del toraxRx del torax, radiografia del torax
Rx del torax, radiografia del torax
 
Pares craneales
Pares cranealesPares craneales
Pares craneales
 
El mundo de Sofía 1
El mundo de Sofía 1El mundo de Sofía 1
El mundo de Sofía 1
 
Relacion Medico Paciente Psiquiatria
Relacion Medico Paciente PsiquiatriaRelacion Medico Paciente Psiquiatria
Relacion Medico Paciente Psiquiatria
 

Similar to Lean NMR Laboratory Layout

TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTTIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTIRJET Journal
 
IRJET- A Testbed for Real Time Water Level Control System
IRJET- 	  A Testbed for Real Time Water Level Control SystemIRJET- 	  A Testbed for Real Time Water Level Control System
IRJET- A Testbed for Real Time Water Level Control SystemIRJET Journal
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pliDhyey Shukla
 
Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Naveen K
 
Line balancing example
Line balancing exampleLine balancing example
Line balancing examplePrakash Kale
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryijmech
 
Team L - Six Sigma Project (The Sloopy's) - Revised.2
Team L - Six Sigma Project (The Sloopy's) - Revised.2Team L - Six Sigma Project (The Sloopy's) - Revised.2
Team L - Six Sigma Project (The Sloopy's) - Revised.2Baozheng (Michael) Ge
 
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...Joseph Uken
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingeSAT Publishing House
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
 
Material movement in a manufacturing plant
Material movement in a manufacturing plantMaterial movement in a manufacturing plant
Material movement in a manufacturing plantAmit Kumar
 
Final PPT Presentation
Final PPT PresentationFinal PPT Presentation
Final PPT PresentationAdam Lu
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturingJitesh Gaurav
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturingJitesh Gaurav
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET Journal
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingLean6Sigma4all
 

Similar to Lean NMR Laboratory Layout (20)

report
reportreport
report
 
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTTIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
 
IRJET- A Testbed for Real Time Water Level Control System
IRJET- 	  A Testbed for Real Time Water Level Control SystemIRJET- 	  A Testbed for Real Time Water Level Control System
IRJET- A Testbed for Real Time Water Level Control System
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
 
Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)
 
Line balancing example
Line balancing exampleLine balancing example
Line balancing example
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
Team L - Six Sigma Project (The Sloopy's) - Revised.2
Team L - Six Sigma Project (The Sloopy's) - Revised.2Team L - Six Sigma Project (The Sloopy's) - Revised.2
Team L - Six Sigma Project (The Sloopy's) - Revised.2
 
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...
 
Motion and time study
Motion and time studyMotion and time study
Motion and time study
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
 
Material movement in a manufacturing plant
Material movement in a manufacturing plantMaterial movement in a manufacturing plant
Material movement in a manufacturing plant
 
Final PPT Presentation
Final PPT PresentationFinal PPT Presentation
Final PPT Presentation
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream Mapping
 
K012556370
K012556370K012556370
K012556370
 
K012556370
K012556370K012556370
K012556370
 

Lean NMR Laboratory Layout

  • 1. “New NMR LWD Laboratory LAYOUT” LEAN Project By Cesar Javier Siles Saracho Electronic Engineer
  • 2. Table of Contents 1 Project Motivation 2 Project Objectives 3 Problem Definition 4 Measure 5 Analyze 6 Improve 7 Control 8 Project Cost and Benefits 9 Conclusions 10 Appendix List of Tables and Figures Table 1 SIPOC Table 2 Old Layout Spaghetti Table 3 Weighted Average Process time and process Efficiency Table 4 Solutions to Kaizen Events Table 5 New Weighted Average Process time and process Efficiency Table 6 New Spaghetti Diagram Table 7 Old Vs. New State Table 9 Control Time Sheet Table 8 Financial Impact Fig 1 Old Spaghetti Diagram Fig 2 Swinlane diagram & RACI Chart Fig 3 VSM Old Layout Fig 4 Time Spent in Process Lab and Service Levels Fig 5 The New Layout Fig 6 Mechanic WorkStation Fig 7 Electronic workstations Fig 8 Pedestal ,Flow Kits, Special Tools Fig 9 Upper Chassis Electronics Rack Fig 10 Turbines Rack Fig 11 Magnets Rack Fig 12 Loading - Unloading Area Fig 13 Calibration Container Fig 14 New Lead Time Fig 15 VSM New Layout Fig 16 New Spaghetti Diagram Fig 17 Old vs New Layout Fig 18 Control Process Time
  • 3. 1.Project Motivation Monitoring the actual proVISION work process , it is possible to observe that in most of the sub processes , there is waste , like excessive motion, transportation , defect and waiting time ,so there are several opportunities to optimize such process. The company did the decision to built a new bigger laboratory at the base, thus it will give the great chance to improve the actual Layout of the proVISION Laboratory, so the mentioned problems related to non value added time could be minimized. This project is going to use Lean Tools and techniques to minimize the waste in a process or just reduce the activities that not add value in the process. The first step is going to be a define phase, when all the main problems are going to defined, Then the process need to be measure, It means that all sub process will be measure in time, so it will analyze the bottlenecks and calculating the efficiency and maximum capacity of tools that could being provided. The next step will be the proposal plan to improve the process using a new Layout that plays a crucial role in determining the flow patterns, reduce the waste , organize the workplace and impact the safety. The new Layout will be consider as the main problem solving tool ,however it is also necessary use a systematic method to improve and sustain workplace organization (5S), standardize some of the sub process and get the habilitation of equipment strongly necessary to perform important tests. With the implementation of this project it will increase the efficiency and capacity to cover the future client’s demand. It will also reduce the non value added time , will be soft saving and it will improve the service quality and safety. Finally the motivation factors could be summarize in the following : • Expansion due to activity increase • Expected Job count from 3.9 to 6.5 during 2013 (Q1-Q4) • Reduce the non value added time • Reduce Costs • Provide a better service quality 2.Project Objectives • Design a layout to optimize the flow of proVISION Tools by minimizing the times the tools have to go back to the same workstation, reduce the distance between stations, reduce the barriers between stations, decrease the movement of heavy equipment such as container and design a better path to get access to shared equipment like ovens . • Increase also the service Quality by organizing the workplace, so adding store places for proVISION components , such as racks, cabinets, implementing trolleys for move heavy items and fixing turbine test setup. • Improve the safety by reducing the mechanical lifting operations, like moving container with a forklift, loading electronics out of a yellow line for personnel and
  • 4. Rack magnets out of compliance. • Improve the efficiency of the proVISION Laboratory by 22% and the capacity by 23 % 3.Problem Definition The problems have seen in the actual NMR work process are : • Excessive motion of technicians, going to the Break Out Machine , Push or The Surface area to get a container. • Excessive transportation of the tool , it have to travel several times long ways. The NMR Collar goes from PUSH Area to NMR Lab to be unloaded , then it have to return to PUSH Area to be inspected and finally go back to NMR Lab to load the electronic. After loading the electronics, some test are performed, then the tool goes to the BOM to torque the wear bands to be ready for calibration, Then it goes to the calibration container, later it have to return to the BOM for assembly (Turbine , Pony ) and finally the last test (Jackstand test ) need to be performed also in the calibration container . This is difficult to move due the tool with the pony is longer and heavier. ( Fig 1 Old Spaghetti Layout ) • There is no specific area to place the container. There is a lot of time consuming and waiting time, to perform the task to move the container inside the workshop with a forklift, the use of crane to move the container from the entrance to the push area , placing the tool inside the container and finally doing the setup by covering the holes with aluminum. • The actual NMR Lab is situated next to Xceed test area. This situation is one of the key problems affecting NMR service time due to the noise affecting NMR tests, and the waste related to "wait time" or rework. The longest test the could avoided is the PWO test that usually takes 3hrs. • Actually, using Xceed Turbine test set up for NMR Turbine test adds to the wait time as the Technicians wait for Xceed test to be completed before they can set up NMR Turbine. • The NMR tool is seriously affected by electrical noise, so the electrical grounding need to be improved. • The two Ovens are shared , so it derives in a lot of waiting time and extra time in Setup. • Actual layout doesn’t provide a good space for loading the upper chassis due it cross the corridor and interrupt the normal transit of people. • The rack magnets is too close to computer setup. • The ProVISION area doesn’t provide enough room to perform some processes simultaneously. RIRs Related • 20120903163758 Sep 01, 2012 SQ • 20121203160050 Nov 30, 2012 HSE • 20121229182212 Dec 27, 2012 SQ • 20130225140537 Feb 22, 2013 SQ • 20130306122618 Mar 01, 2013 Sug • 20130319095118 Mar 19, 2013 SQ • InTouch Ticket 6128184, 6179781
  • 5. In order to help to determine the scope of the project we are going to use the SIPOC LEAN tool (Supplier, Input, Process, Output, and Customer) , It is also a very high level map of a process that help to identify any quick disconnects with the supplier inputs, and identify the project customers and their outputs. TABLE 1 proVISION SIPOC ! 4.Measure The collected information will allow us to make important decisions and manage the process by facts and evidence. It will also quantify the baseline and show the improvement after the project is completed. So for this case the issue is to calculate the actual capacity of the proVISION work process and the efficiency in order to have a start point to know if we could comply with the future customer capacity. From the Spaghetti diagram below Fig1 , it is possible to observe the waste of excessive motion of the technician and also excessive transportation of the proVISION items (Collar, pony collar , turbine ) in the actual work process. Two shift of mechanicals and electronics technician working on the same tool from the Beginning to the end do the job in 51 Steps , with a total distance of 1219mts .From the Table 2 is possible quantify the distance of each step and observe the highest distances to run are to get a borrowed container for calibration , go to Break Out Machine (BOM ) and IST are (Incoming Sytem Test ) Technic ian R&M Too Push deliver PULL TEAM
  • 6. Figure 1 OLD SPAGHETTI LAYOUT
  • 7. Table 2 Old Layout Spaghetti Service Level 3 The Swinlane diagram Fig2 show the proVISION work process and help us to understand the interactions of the proVISION work process through the different departments, some departments like Push and Pull have a big contribution in the tool lead time , however we are only focus to minimize the waste in the ProVISION Lab process ( total time of 86hrs SL3). OLD Spaghetti Service Level 3 # Step distance (Mts) Comments ET1 0-1 105 Take setup to IST Area ET1 1-2 105 Return from IST ET1 2-3 11.38 Go out side with Trolley ET1 3-4 4.87 Install power cord , Et1 4-5 4.87 Remove plugs and unsolder MT1 2-3 6.5 Go out side to remove Jamnuts with splecial tool MT1 3-4 5.46 Search for tube to remove jamnuts MT1 4-5 5.46 Returning with tube to remove jam nuts MT1 5-6 5.82 Remove the LC MT1 6-7 3.69 Place the LC in the RACK Et1 5-6 2 help the the MT place the LC MT1 7-8 12 take special tool to remove UC MT1 8-9 6.4 Place Special tool to remove UC and remove UC ET1 6-7 13.54 Search Trolley to remove UC ET1 7-8 7.62 place the Trolley y pull together with the MT1 ET1 9-10 7.5 Remove UC with MT1 MT1 9-10 6.5 search for trolley from TST area MT1 10-11 6.9 return with trolley and pull the UC ET1 9-10 7.8 Return trolley from TST ET1 10-11 6 go back to lab to work in UC MT1 11-12 64 Move Collar to Inspection Area MT1 12-13 64 return from push MT1 13-14 7.6 Take the crane to lift UC MT1 14-15 4 Place the crane and remove NMR & Power Chassis ET1 11-12 11.6 move to get ovens ET1 12-13 17 ET1 Returns with one oven ET1 13-14 7 Return to get secong oven ET1 14-15 5.6 Takes the second oven ET1 15-16 6.5 Connects the power cord ET1 16-17 8.3 Returns to work heat test setup MT1 15-16 147 MT goes to surface to coordinate the container MT1 140 MT Goes to coordinate the forklift MT1 16-17 90 MT Return from surface to the workshop entrance MT1 17-18 14 Move container to Calibration Area ET1 17-18 42 ET1 goes to help the MT to move the container ET1 18-19 12 ET1 help the MT to place the container ET1 19-20 26 ET goes to NMR Area to lift the tool MT1 18-19 26 MT goes to NMR Area MT1 19-20 26 MT Return with the tool ET1 20-21 26 ET returns with the tool ET1 21-22 18.5 Goes to BOM to assembly Pony and Turbine MT1 20-21 23 Goes to BOM to assembly Pony and Turbine MT1 21-22 30 Install Shield and move tool Pull ET1 22-23 27 Install Shield and move tool Pull Et1 23-24 10 goes to moves the container back MT1 22-23 10 goes to moves the container back MT1 23-24 11 moves container ET1 24-25 11 moves container 1219.41 MTS Total STEP of both ET &MT is 51
  • 8. The RACI Chart Fig 2 should clarify roles, as well as ensure accountability and individual levels of participation. NMR Supervisor ElectonicTechncian MechanicalTechnician Inspection Team ARII ARII IR IRR IIIAR IRR AR IRR IR IR CRR AssemblyToolandcompleteOSTARR PerfomTestHeatTest LoadUpperChassis PerformVaccumTestonCollar PerformUCTests ACTIVITIES QualityCheck AlertTeamToolarrivalinPUSH ExplainTCO,PriorityandSL PerformtheIST UnloadUpperChassis Inspection PerformR&M Fig2SwimLaneDiagram&RACI Chart
  • 10. In the Value Stream Map Fig 3 (see previous page) for the actual is possible to measure the timing of the entire ProVISION Laboratory process for the maximum service level 3 , taking in count that the lead time of each individual process is the sum of value added time and non value added time. However this case is only for SL3 , so we have to do similar Value Steam Maps for the rest of services levels 0,1,2 . (Appendix A). *Note.In the VSM Fig 3, it was not consider the rework in all the process except of heat test and also the time spent in Failure investigation 5.Analyze In order to calculate the weighted average of the total process time and the efficiency we need to consider the Timing of each service level and also the contribution of each service levels according to the statistics (Qtrac between October 2012 to Jan 2013 ) . So from the table 3 and figure 4 below we calculate the average time to produce one tool including the service probability as per Service Level and the efficiency of the our process. Table 3 Actual Weighted Average Process time and process Efficiency Now From the data above we derive in the Maximum Capacity and Takt Time Calculating the Actual Capacity and Efficiency ! ServiceLevels Sep2012-Dec2013 SL MRT6 MRT8 Period TotaL Toolsper month SL% VA/T (hrs) L/T hrs L/Tx % (hrs) VAx% MRT6UC 6007 (including one time ) SL3 or SL4 15 6 21 1.31 21.00 47.90 86.10 18.08 10.06 SL2 25 7 32 2.00 32.00 29.00 42.00 13.44 9.28 SL1 12 5 17 1.06 17.00 6.50 16.30 2.77 1.11 SL0 24 6 30 1.88 30.00 2.75 8.80 2.64 0.83 Total 76 24 100 6.25 100 Average L/T (hrs) 36.93 Average VA(hrs) 21.27
  • 11. Fig 4 Time Spent in Process Lab and Service Levels % ! ! Bottle Neck is the process with the highest long term utilization, so if we see again the VSM Fig 3 it would be the heat test with an average of 39hrs (calculate below), however the process itself only take 18,5 hrs including shop failure , so the NVA 20.5 hrs (waste time ) it is considerable Heat Test 67 % no rework & 33 % rework (Heat Test Statistic 3failed and 6 passed) no rework = 10work hrs + 17.5 waitoven = 27.5hrs rework = norework + 16hrs troubleshoot + 10workhours + 8.75waitoven = 62.25hrs Total = 0.67 x 27.5 + 0.33 x 62.25 = 39hrs VA = 10hrs x 0.67 + (10 + 16 + 10) x 0.33 = 18.5 hrs NVA = 0.67 x 17.5hrs + 0.33 x ( 17.5 + 8.75) = 20.5hrs 6.Improve The improve plan will be using the following LEAN methods, Kaizen Events, Improve Layout, 5S and Generate improvent ideas. As we can see from the table 4 the solution to the problem is going to be time saving projects that will impact the efficency and the quality of the overall process. Such projects were created with ideas generated by teamwork. The List of Kaizen event was taken from the VSM , and the time saved in each process in order to minimize the Non Value adde time is in base of Layout solution, 5S ,changes in procedures and getting new standard equipment.
  • 12. Table 4 Solutions to Kaizen Events ! SOLUTIONES TO KAIZEN EVENTS OLD NEW PROCESS Total C/T (hrs) VA (hrs) NVA (hrs) NVA (hrs) KAIZEN EVENT EQUIPMENT NEEDED IST 1.5 0.5 1 0.5 Electronic workstation and calibration KIT in PUSH Area (future Layout) DC power suplies ,TSIM ,computer , calibration Tanks and shields , jackstands UNSOLDER ANTENNA, REMOVE JAMM NUTS,LC,UC 3.5 2.25 1.25 0.75 Unloading workStation in PUSH Area (future Layout) Portable soldering workstation and special tools to remove UC REMOVE UPPER MAGNET 0.917 0.5 0.417 0.25 New Mechanical lifting Equipment Trolley for Magnets and Pallet Truck SL UC (CHANGE BATT, ORING MOD RECAP IF NEEDED 8.2 6.7 1.5 1 New Benches Layout , easy way to move the Upper Chassis Electronics with a trolley (Fig 7) Soldering workstation, Rack for UC , Pallet Truck for upper magnet SETUP FOR HEAT TEST INSTALL TANK 1.5 1 0.5 0.25 5S for cables and wires Kit of wires for Antenna , Battery,RPM simultator, Termocouple HEAT TEST 39 18.5 20.5 17.8 Less time spent to setup due to new layout, Turbine Test jig for NMR only, and decreased Xceed tests interference New Turbine Test Setup , New TurbinesRACK CONNECT UPPER MAGNETS & FINALIZING UC 3.75 3.5 0.25 0.1 New Layout, less distance to Racks, and lifting Equipment New Rack for Magnets, Pallet Truck and Special Trolley LOADING UPPER CHASSIS , LC and Torque Jamm Nuts 4.25 2 2.25 2 Loading Chassis with Ratchet Strap Best Practice 6218607,Improved Loadingarea Cabinets for Special Tools New Racks for Magnets, Special Tool for Loading UC, Cabinets for wearbands ,flow kits SOLDERING & INSTALL ROPs 1.5 1.5 0 0 Soldering workstation Soldering workstation TURBINE TEST 2.25 1 1.25 0.25 Turbine Test , RACKs and New Layout New complete turbine Test , New TurbineRACK UPDATE SOFTWARE ,PWO, RBT LTB TESTS 6.75 5.5 1.25 0.5 With New Layout less interference from Exceed,MRT8TankbestPractice6302142 LTB Wires KIT TORQUE PONY & WEAR BANDS , LOADING TURBINE 3.75 1.25 2.5 1.5 Less distance to BOM due new Layout and changeintheProcessIT6128184 Turbines ,Pedestal Racks and Cabinets CALIBRATION IN CONTAINER 3.8 1.5 2.3 0.5 Container already in LAB Layout , no need to move from surface Area , Best practice # 6237734 NEW owned Container Design, JACKSTAND 3.25 1.25 2 1 Improve procedure,Configuration File readyinTCO QUEST 20130306122618 QTRAC,OST VALIDATION , INSTALL SHIELD, TO PUSH 2.25 1 1.25 0 Improve Layout, not necessary remove container , Lifting Equipment , TIME (hrs) 86.167 47.95 38.217 26.4
  • 14. The New Layout Fig 5 • The new Layout is designed to have a Linear Flow , so it follow as much as posible the ProVISION work Process. This layout is designed to impact the safety,quality, workplace organization and future expansion. • After breaking the tool and washing the main components (Pony, turbine and MRT collar) the turbine enter the lab first,IST is performed, then the UC have to be unloaded in the same place, so the collar will have a shorter path to the inspection area meanwhile the Upper Chassis enter in the lab to perform the required service level. Later the collar enter in the laboratory and it is placed at the heat test are were the Upper Chassis is going to be heat. (The UC have to go back a litte for heat test) • After heat the elecronics and at the same time the turbine could serviced , the upper chassis is finalized, then load for testing and final calibration in container . At last the MRT collar a the turbine leave the lab for assembly together wih the pony in the Pull area. • The there are two parallel long benches for the mechanic technicians Fig 6 , so it could be placed two turbines in the 2 benches of 1.5mts x 0.7mts with easy access of both sides and also there are two more benches for place two magnets. Ther are also Two extra tables to place the computers technician in order to prevent the computer damage due to magnets or vibration to hit on the same table. • There are basically three benches for the Electronic workstation Fig 7 so it is easy access and place the tool over the bench just using the trolley. It is also enough space to perform maintenace of two upper chassis at the same time as in general the trolley is used to perform this service. One extra bench is required for laptops. • In The Fig 8, Fig 9 ,Fig 10 and Fig 10 is posible to observed to differents racks and cabinets in order to organize the workplace ,comply with the SQ Standards by segregating the NMR Equpment like , Pedestalls , Flow Kits , Electronics, Turbines and Magnets . Such Racks were designed taking in mind the future activity (See Apendix ) • The magnets have been placed away from the computer setups,far from tools and isolated with its respective warning signs. Also a new rack for the the magnets have been introduced in order to improve the segregation and minimize the risk of attraction between them while are transported.Fig11 • The Loading area Fig 12 for the Upper Chassis avoid the safety issues of the previous one where the movement of the electronics had to cross the corridor,so now there is enough space between tools and it will be possible the perform processes in parallel , like for example Heat Test , PWO RBT LTB and calibration and Jackstand. • With The Calibration container Fig 13 ( Appendix 10) inside the laboratory the use of forklift was eliminated and also it was placed far enough to minimize the interference between other tools. With The practical hole in the container it is possible to setup the tool in less time.
  • 15. Fig 6 Mechanic WorkStation Before After ! ! Fig 7 Electronic workstations Before After ! Fig 8 Pedestal & FlowKit Before After ! ! !
  • 16. Fig 9 UC mixed with others Electronics Before After ! ! Fig 10 New Turbine Rack !
  • 17. Fig 11 Magnets Racks Before After ! ! Fig 12 Loading /Unloading Area Before After ! ! Fig 13 Calibration Container Before After ! !
  • 18. After working in the new layout with all the required equipment it is possible to generate a Future VSM SL3 Fig 15 (similar VSM are needed for SL0,1,2) , then we can make the similar previous analysis in order to calculate the new efficency and maximun capacity of the new layout. (Fig14) Table 5 New Weighted Average Process time and process Efficiency Fig 14 New Lead Time Calculating the NEW Capacity Qtrac SLevelsOct12-Aug 13 SL MRT6 MRT8 Period TotaL Average per month SL% VA/T (hrs) L/T (hrs) L/Tx % (hrs) VAx% MRT6UC 6007 (including one time ) S3 or SL 4 15 6 21 1.3125 21 47.90 74.3 15.603 10.06 SL2 25 7 32 2 32 29.00 35.2 11.264 9.28 S1 12 5 17 1.0625 17 6.50 11.3 1.921 1.11 SL0 24 6 30 1.875 30 2.75 4 1.200 0.83 Total 76 24 100 6.25 Average L/T (hrs) 29.99 VA (hrs) 21.27 New Lead Time HRS 0 20 40 60 80 SL3 SL2 SL1 SL0 Lead Time = 30hrs (weigthed average time) Efficiency = VA / Lead Time = 71 % Capacity = Available time / Lead Time = 10.6 Tools/month
  • 20. At same time we are going derive in a future Spaghetti Diagram Fig 16 & Table 6 Table 6 New Spaghetti Diagram ! # Step distance (Mts) Comments ET1 0-1 20 Take setup to IST Area ET1 1-2 22 Return from IST ET1 2-3 15 Goes to Unloading area with Trolley ET1 3-4 8.5 Install power cord , ET1 4-5 3.5 Remove plugs and unsolder MT1 0-1 6.6 Go outside to remove Jamnuts with special tools MT1 1-2 2.5 Remove theLC MT1 2-3 7 Place the LC in the RACK or bench Et1 5-6 11 help the the MT place the LC MT1 3-4 16.5 taks and Place Special tool to remove UC Et1 6-7 21 Search Trolley to remove UC MT1 4-5 11 Place UC collar to Inspection ET1 7-8 26 Place UC inside the Lab for R&M MT1 5-6 40 return to work in lab and then place the collar for heat test ET1 8-9 14 Place the two ovens one by one ET1 9-10 18 Place the UC inside de oven and perfrom heat ET1 10-11 29.5 finalize ,Load Tool , Then perform calibration and tests MT1 6-7 11 Load tool MT1 7-8 32 Takes turbine to install the flow kit MT1 8-9 49 Together with the ET place the tool inside container ET1 11-12 34 Assembly tool in PULL BOM MT1 9-10 38 Assembly tool in PULL BOM 436.1 MTS
  • 22. After the improvement is extremely important compare the old state, versus the future state in order to verify and prove the improvement in efficiency and capacity Comparison Actual Vs Future State Fig 17 Old vs. New Layout ! Table 7 Old Vs. New State !
  • 23. 7.Control The control is going to be implemented by : • 5S Audit including the Layout • Floor Lines to indicate the correct place of equipment • Compare expected Lead Time vs. actual Lead Time . Figure 18 below shows the Lead time of tools as per service levels during the period of Jun –July 2013. It is possible to observe that several tools the lead time was not as expected. • Control Time Sheet to sustaining and continuous improvement Table 9 Fig 18 CONTROL PROCESS TIME ! !
  • 24. Table 8 Control Time Sheet ! SERVICE LEVEL CONTROLTIME SHEET TOOl SN UPPERCHASSISSERVICELEVEL 3 PROCESS Expected Time (hrs ) START TIME ENDTIME HRS DATE TECH COMMENTS IST 1 REMOVE JAMNUT,LC,UNSOLDER ANTENNA,UNLOAD UC 3 REMOVE UPPERMAGNET 0.75 SL UC(BATTERY,ORINGR,MR) 7.7 SETUP ForHeatTest 1.25 HEAT TEST 36.3 CONNECT UPPERMAGNETAND FINALIZE 3.6 LOAD UC,LC,INSTALL JAMNUTS 4 SOLDERINGAND INSTALL ROP 1.5 TURBINE TEST 1.25 UPDATESOFTWARE, LTB,PWO,RBT 6 CALIBRATION 2 JACKSTAND 2.25 ASSEMBLYTOOLINBOM 2.75 INSTALLSHIELD ,CLOSEWO 1 74.35
  • 25. 8.Project Cost and Benefits Table 9 Financial Impact BENEFITS Financial Soft Saving 100K$us/ year Service Quality • Increase the Efficiency by 24% and Capacity by 23 % • Improve Capacity from 8.6 to 10.6 Tools/ Month with the same personal • Reduced the Distance by 783mts • Organize Workplace with new Racks and segregating the equipment LABOR Description Baseline process New process Hours Saved Hourly Rate Savings Non-exempt time per year Redution in Total Lead Time (7hrs/Tool) x 6 Tool /Month x 12month 2664 2160 504 $ 100.00 50,400.00$ (Old LT 37hrs , New LT 30hrs ) -$ 50,400.00$ COSTAVOIDANCE/RISKREDUCTION Description Baseline process New process Value per Unit Number of units per year Savings SQ Event reduction Board damaged by Store Electronics (every 2 year ) $ 6,000.00 0.5 3,000.00$ Job count increase (when there is market) Increased Tool Capacity by 2 $ 186,000.00 0.25 46,500.00$ RPJ(In K$) = 186 K$us -$ 49,500.00$ EQUPMENT/SOFTWARE/FOOTPRINT Description Baseline process New process Value per Unit Number of units per year Costs New equipment (3)Racks and (1) Cabinets $ 8,362.00 1 (8,362.00)$ New equipment Fixing Turbine Test Setup $ 1,000.00 1 (1,000.00)$ -$ (9,362.00)$ $99,900.00 9,362.00$ $90,538.00 ACTUALSOFTSAVINGS TOTALPROJECTSAVINGS-TOTALPROJECTCOSTS ACTUALSOFTCOSTS SOFTSAVINGS/COSTS
  • 26. Safety • Eliminate Mechanical Forklift Operations • New Loading Area not crossing trough Yellow personnel corridor and doors • Magnets Racks far from Electronic Workstations , Tools, and Magnetic equipment • Minimize Collar transportation Client Improve the Turn Around Time 9.Conclusions • The new Lab Layout plays an important role to determine the Tools flow and need to be done according to the proVISION work process, safety and future expansion in mind. • The combination of a new Lean Layout and workplace organization will improve the efficiency and safety of the process. • The project helped the whole team to understand the impact of a Lean Layout on your daily work
  • 27. 10 Appendix Diagrams Calibration Container ! ! ! PEDESTALS RACK for 24 Units 30Kg per Arm , Total Rack Capacity = 300KG QTY 1
  • 28. ! ! ! ! TURBINES FOR 24 UNITS (similar to Xceed Rack) Per Arm Max 300Kg , Total Capacity = 300Kgx 8 Arms= 2400KG QTY 1 Upper Chassis RACK(Electronics ) for 7 Units Lower Arms= 1500kg , Middle arms =1 000Kg , Upper Arms =1000Kg Total Rack Capacity = 3500KG QTY 1
  • 29. ! ! Cabinet for Flow KITS and Special Tools , Qty 1 Total Capacity = 250 KG ! MAGNETS RACK for 8 Units ( Made of None Magnetic Material )