SlideShare a Scribd company logo
Enabling High Efficiency and Reliable Wind Power Projects
1


    Policy and Regulatory
    Maharashtra Wind Zone Classification Procedure
    In recent Wind Power Tariff Orders, Maharashtra Electricity Regulatory Commission (MERC)
    has come out with wind power tariff structure for different wind zones in the state. In these
    orders, MERC has segregated the sites into 4 different zones based on the mean annual
    wind power density (WPD) in those areas:


     Wind Energy        Mean Annual         Levellised Total       Net Levellised Tariff (upon
     Projects Zone          WPD                  Tariff            adjusting for Accelerated
                        at 50 m hub-          (FY2011-12)           Depreciation benefit) (if
                       height (W/m2)          in Rs / kWh            availed) in Rs / kWh

     Wind Zone-1           200-250                5.37                         4.56

     Wind Zone-2           250-300                4.67                         3.96

     Wind Zone-3           300-400                3.97                         3.38

     Wind Zone-4         Above 400                3.58                         3.04


    Maharashtra State Electricity Distribution Co. Ltd. (MESDCL) had raised some issues on the
    manner in which zoning of different areas was to be done. MSEDCL had also been refusing
    execution of the long term Power Purchase Agreements (PPAs) as per the MERC Order in
    effect. This had led to a lot of confusion and resentment amongst the investors, lenders and
    even the manufacturers of wind turbine generators. The outcome was a significant delay in
    investments in windfarm development in the state. Though, it has taken time, but, the
    Maharashtra Energy Development Agency (MEDA) has now come out with a clear
    procedure for classification of wind zones. The highlights of the zone wise classification are:

    Ÿ The mean annual WPD at 50 meter at the reference wind mast, declared by Centre for
        Wind Energy Technologies (C-WET) under the Ministry of New & Renewable Energy
        (MNRE) or MEDA programme or data vetted by C-WET location shall be considered to be
        the annual mean WPD for the effective area of 10 km radial distance from the location of
        the reference wind mast.

    Ÿ   If a Wind Power Project (WPP) falls within the effective areas of two different wind
        masts having different values of annual mean WPD, then the annual mean WPD of the
        nearest wind mast shall be considered for that WPP.

    Ÿ For an upcoming WPP, within the effective area, if 50% or more than 50% of the
        proposed WTG location co-ordinates are falling above or below 60 m elevation
        difference with reference to the mean sea level (MSL) of the reference wind mast, then
        investor/developer shall approach C-WET to obtain project specific annual mean WPD
        report either on MEDA's advice or permission. While signing Energy Purchase
        Agreement (EPA) with the distribution licensee, developer/investor shall have to submit
        letter issued by MEDA for wind zone classification.




                                                                                                             www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
2


    Introduction of Cross Subsidy Surcharge in Maharashtra
    Earlier in 2006, to promote Open Access (OA), MERC came with an order determining Cross
    Subsidy Surcharge (CSS) as Zero for OA Consumers from September 2006 to September
    2011. Later in August 2010, MSEDCL had filed a Petition with MERC seeking review of the
    aforesaid order in light of achievement of the same (i.e. to match the electricity demand in
    the State through OA.

    MERC has decided to re-determine the CSS due to the change in the current power
    scenario. The CSS has been computed for Open Access transactions for various consumer
    categories based on their voltage levels. The range of applicable CSS is Rs. 0.21/unit to Rs.
    2.81/unit for different DISCOMs (R-Infra, MSEDCL, BEST, Tata Power), for different
    categories of consumers (industrial, commercial etc), connected at different feeders
    (express/non-express) at different voltage levels (above/below 66 kV).

    CSS applicable to open access transactions from Renewable Energy Sources has been
    fixed at 25% of the applicable CSS of the respective consumer category. MERC has fixed a
    discounted CSS in order to promote generation from Renewable Energy sources, which is
    in line with the objectives of EA 2003


    KREDL Notification for Wind Project Developers
    Recently, MNRE has done away with the criteria for Wind Power Density (WPD) for
    installation of commercial WPPs in India. In contrast of this, KREDL has decided, not to insist
    on this parameter to approve DPRs. However, to ensure use of higher efficiency WTGs only,
    KREDL has mandated minimum generation of 20% CUF per WTG in the agreements with
    developers/ manufacturers. The clause shall include removal of those WTGs (<20% PLF) on
    the cost of manufacturers/developers.

    Rajasthan DISCOMs have increased tariff for HT consumers
    Rajasthan DISCOMs have filed ARR in RERC for the year 2011-12 and revised the applicable
    tariff for industrial and commercial consumers. Following are the new tariff for various
    categories:

                                      Existing Tariff                       New Tariff
       Type of Industry
                               Energy charges (Rs. / kWh)          Energy charges (Rs. / kWh)

     Medium Industries                       3.75                              4.75

     Large Industries                        4.01                              5.00

     Non Domestic (Commercial)

     Upto 100 units                          4.50                              5.90
     Above 100 units                         4.90

    Due to ~ 100 paisa/kWh hike in tariff, the investors who have already installed WPPs and
    those who are planning to install WPPs for captive use, will get higher benefit as their cost of
    power remain insulated for such steep hike state tariff.




                                                                                                             www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
3


    What’s New

    Draft guidelines for installation of wind turbine models in India
    The current qualification criteria for installation of WTGs in India require a certification from
    C-WET which is a time taking process even in cases wherein a certificate from
    Internationally Recognised Agency is available. This has in-turn restricted certain better
    WTG models and technology to be used in India.


    To give a boost to wind power development in India by creating the environment that
    promotes healthy business, ensures safety standards and encourages technological
    growth, MNRE has issued new draft guidelines for installation of wind turbine models in
    India and invited comments/views/suggestions on the same by 29th September 2011.


    Major highlights of these guidelines are:
    Ÿ Any new WTGs to be installed in India must possess a valid type certificate from an
       internationally accredited certification agency and fully comply with IEGC 2010.


    Ÿ Manufacturers can install up to 15 MW of a specific turbine model in India to test its
       performance in India. To sell any such model in India, they will be required to establish
       manufacturing base in the Country.


    Ÿ The self-certification guidelines for installation of WTGs, which allows installation of
       non-certified machines, have been discontinued with immediate effect.


       This guideline will cover all such machines that have already been approved under the
       RLMM scheme, but not yet installed. However, self-certified machines approved under
       the RLMM scheme and installed will be subject to guidelines issued in December 2009
       and January 2010 that required submission of the documents related to type certificate
       within the committed timeframe and other requirements.


    Ÿ The guidelines also specify four international certification programmes that will be
       accepted in addition to the revised TAPS-2000 programme of C-WET. The certification
       clauses will accelerate capacity addition by de-clogging C-WET's pipeline. The guidelines
       are applicable from 1st December 2011 in the run-up to the 12th Five Year Plan (2012-
       17), and from the same day the RLMM Committee will stand dissolved.

    The following certification schemes will be recognised when an accredited certifying body
    carries out certification:
    Ÿ IEC Certification Scheme
    Ÿ Germanisher Loyds Certification Scheme
    Ÿ The Danish Certification Scheme
    Ÿ The Dutch Certification Scheme


    Addendum to Revised List of Models and Manufacturers (RLMM)
    As per addendum to Main List (RLMM) of Wind Turbines in India dated 22.09.2011,
    following WTGs have been added viz. Kenersys K100 - 2.5 MW, Global L82 - 2.0 MW, Suzlon
    S95, S97 - 2.1 MW & S88 - 2.25 MW.



                                                                                                              www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
4


    Important Notice regarding Registration for Application

    All RE Generators are requested to furnish complete documents as mentioned in the check
    list:
    ŸHard copy of online Registration application signed and stamped on each page.
    ŸAccreditation Certificate.
    ŸCommissioning Certificate/ Commissioning Schedule.
    Ÿ Applicable clauses of the declaration given in online application that it has not entered
        into any Power Purchase Agreement at preferential tariff on the letter head of the
        company.
    ŸFees and Charges.
    ŸUndertaking to pay any service tax or any other taxes applicable on REC fees and charges.
    ŸLetter for authorised signatory if application is not signed by MD/CEO.

    If any information will be found missing and asked by central agency to furnish then it shall
    be routed through concerned state agency to central agency.


    India installed capacity in FY 12, H1
    In FY 12 H1, ~ 1445 MW of Wind capacities have been commissioned. In view of possibility
    that the accelerated depreciation benefit may not be available post 31st March 2012 a good
    portion of this capacity may have come from the accelerated depreciation seekers.
    Similarly, for IPPs also, as per current policy GBI is available for projects commissioned by
    31st March 2012 only. These two can be the key drivers for the huge investment this year. We
    expect that the total capacity to be commissioned this year shall be in the range of 2500 -
    3000 MW.

    Events
    Ÿ WinDForce attended in Power Trading Summit 2011organized by Power Markets India,
        held in Crown Plaza New Delhi. Various stakeholders of power industry participated in
        the event discussing about:
        § Trading Renewable Power, Wind and Solar Scheduling, Annual Pool Power Costs -
            Future Trends, REC Markets - Pricing beyond 2012
        § Long Term, Short Term and Medium Term Power Markets, Future of Power
            Exchanges, Bilateral Trades v/s Exchange Trades
        § Financial Risks in Trades, Project Finance Risks and Mitigations


    Ÿ Mr. Jami Hossain, Chief Mentor and Founder of WinDForce participated in Business-to-
        Business Forum on “Fostering Business Partnerships to Promote the Adoption and
        Utilizationn of Renewable Energy Technologies” 22-23 September 2011, Colombo, Sri
        Lanka. The event organised by Asian and Pacific Centre for Transfer of Technology
        (APCTT) of the United Nations - Economic and Social Commission for Asia and the Pacific
        (ESCAP) had the participation from many countries of the Asia Pacific region. Speaking
        to delegates as well as dignitaries from Sri Lanka including the Energy Minister, Hossain
        talked about the possibility of a submarine transmission link between Sri Lanka and
        India that would stabilise the Sri Lankan grid as well as enable large scale exploitation of
        wind energy in North Sri Lanka. Hossain was invited as a resource person to the meet.




                                                                                                             www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
5


    Upcoming Events
    Ÿ Workshop on Renewable Regulatory Fund (RRF) Mechanism for Southern Region
       stakeholders on 10 October 2011 and for Western Region stakeholders on 14 October
       2011 is being organised by NLDC.
    Ÿ ICCC-1: International Conclave on Climate Change from 12-14 October 2011at
       Hyderabad International Trade Expositions Limited (HITEX), Madhapur, Hyderabad, A.P,
       India.
    Ÿ Green Conclave and Green Leadership Forum 2011: Discussion on the most critical
       issues that surround the clean technologies sector and the investment opportunities it
       offers to be held on 14th October 2011 at The Leela Palace, Diplomatic Enclave,
       Chanakyapuri, New Delhi
    Ÿ RENEWTECH INDIA 2011: International Exhibition & Conference on Renewable Energy
       from 10-12 November 2011 at Bombay Exhibition Centre, Goregaon, Mumbai, India.



    Tenders
    Ÿ Karnataka Renewable Energy Development Limited (KREDL) has come out with an NIT
       inviting bids from the manufacturers with WTG capacity of more than 1500 kW for
       development of two wind power projects of 6 MW capacities each in the state of
       Karnataka on LSTK basis.
    ŸHukeri Rural Electric Co-operative Society Limited has called for Expression of Interest
      from the developers in the field of Wind Energy with our without land for a capacity of
      100 MW in stages for attaining self sustainability.



    REC Trading




    The above graph indicates that the equilibrium price of REC traded at both the exchanges is
    increasing every month. Moreover traded volume at both the exchanges is also increasing.
    In the recent trading held on 28th September 2011, there were buy bids for ~2, 27,000 RECs
    against sell bids for ~85,600 RECs, where as in the last trading held on 2nd September 2011,
    there were buy bids for ~ 1, 83,305 RECs against sell bids for ~58,052 RECs.




                                                                                                          www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
6


    Calculation of Equilibrium Price (EP) and Volume for RECs at IEX
    A matching of the buy and sell bids will take place only if there are crossing prices (Buy Price
    >= Sell Price). Accordingly, the EP is determined as per following criteria:


    Ÿ EP will be the price at which there is Maximum Tradable Volume (MTV).
    Ÿ If there is more than one price with equal value for MTV, the price that leaves the least
       volume untraded at its level (minimum unbalance) is chosen as EP.


    In price determination process, at every candidate price level (CPL), the volume is
    cumulated and the difference between cumulative buy and cumulative sell is calculated.
    This gives two values at every CPLs:


    Ÿ Tradable Volume (minimum of cumulative buy and cumulative sell)
    Ÿ Unbalance (Difference of cumulative buy and cumulative sell; positive, negative or zero.


    Following four rules are for calculating EP:


    Rule 1: If a CPL with maximum tradable volume exists, this price is an EP. This rule gives one
             or more price levels:
    Ÿ If the maximum tradable volume is zero (no crossing prices), no EP is determined.
    Ÿ If there is only one price level, this is the EP.
    Ÿ If there are multiple levels, rule 2 is applied.


    Rule 2: If there are several price levels for maximum tradable volume, the levels with
             minimum Unbalance are CPLs. This rule gives us one or more price levels:
    Ÿ If there is only one price level, this is the EP.
    Ÿ If there are multiple price levels, and the unbalance is not zero, rule 3 is applied.
    Ÿ If there are multiple price levels, and the unbalance is zero, rule 4 is applied.


    Rule 3a: If the sign(+/-) of unbalance is same for all CPLs, the price closest to the price at
              which sign of unbalance has changed (from positive to negative or negative to
              positive, as the case may be) , is chosen as EP.


    Rule 3b:If the unbalances at CPLs have different signs, the highest CPL with positive
              unbalance and the lowest CPL with negative unbalance are identified. The EP is
              then chosen randomly between these two.


    Rule 4: If there are two CPLs with unbalance = 0, then one of them is chosen randomly as EP.


    For a better understanding, we may refer the following example:
    In this graph, there are 3 different buy bids and 3 different sell bids.




                                                                                                                 www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
7


    A is the buyer who is willing to buy 1000 REC at any price =< Rs 3900/REC, B is willing to buy
    6000 REC at any price =< Rs 2300/REC and C is willing to buy 2000 REC at a price of
                                                                                                        WinDForce Services
    Rs1700/REC. Whereas D is the seller who is willing to sell 1000 RECs at any price >= Rs
                                                                                                        Ÿ Wind Resource Assessment (WRA)
    1500/REC, E is willing to sell 2000 RECs at any price >= Rs 1700/REC and F is willing to sell
                                                                                                        Ÿ Owner’s Engineer during the complete
    3000 RECs at any price >= Rs 2000/REC.
                                                                                                            p ro j e c t i m p l e m e ntat i o n & p o st
                                                                                                            commissioning
    Now Rs 2200/REC is the price level for maximum tradable volume and minimum imbalance
                                                                                                        Ÿ Detailed Project feasibility Study
    so equilibrium volume shall be 6000 RECs at an equilibrium price of Rs 2300/REC.
                                                                                                        Ÿ Detailed Project Report
                                                                                                        Ÿ Contract Advisory
                                                                                                        Ÿ Technical Due Diligence of proposed
                                                                                                            as well as existing wind farms
                                                                                                        Ÿ E nt r y st rate g i e s fo r n ew W TG s
                                                                                                            manufactures
                                                                                                        Ÿ Structuring of PPA
                                                                                                        Ÿ Sale of power and management
                                                                                                        Ÿ Environment Impact Assessment
                                                                                                        Ÿ Development/ Co-development of Wind
                                                                                                            Power Projects at Identified sites by
                                                                                                            WinDForce




                                                                                    (* Source: IEX)

    Short Term Electricity Price




    From the above graph it can clearly be said that during the last one year, most of the time,
    except 1-2 month, short term market price of electricity in bilateral arrangement is higher
    than that at power exchanges. This analysis includes only inter-State transactions.
    Electricity price in bilateral arrangements, in year 2011 is lesser than price in year 2010
    showing a decrease in prices. The ratio of electricity traded on power exchanges to that of
    total short term bilateral trades has increased from ~22% in 2009-10 to ~36% in 2010-11.


                                                                                                            www.windforce-management.com
Contact Us                                                                                Corporate Office
Kindly write to us if you have any comments on this Newsletter. Your valuable             WinDForce Management Services Pvt. Ltd.
feedback on this would motivate and help us in improving the quality and enriching        5th Floor, Universal Trade Tower
the content. We are eagerly waiting for your kind response to the articles presented in   Gurgaon - Sohna Road
this Newsletter.                                                                          Gurgaon - 122001, Haryana
                                                                                          Tel: +91 - 124-4353100
Parish Gupta                                                                              Fax: +91-124-4102980
Mob: +91 98717 11445                                                                      Web: www.windforce-management.com
E-mail: parish@windforce-management.com

Rupesh Singh
Mob: +91 96507 58884
E-mail: rupesh@windforce-management.com



A WinDForce Publication
Disclaimer - This Newsletter has been compiled by WinDForce Management Services Private Limited
for circulation among the stakeholders in the energy market. Though the contents of this bulletin are
correct to the best of our knowledge, WinDForce does not vouch for their accuracy.



                                                        www.windforce-management.com

More Related Content

What's hot

Presentation on captive power plants
Presentation on captive power plantsPresentation on captive power plants
Presentation on captive power plants
Jay Ranvir
 
Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?
IPPAI
 
Practice directions rts net metering regulations 2015
Practice directions  rts  net metering regulations 2015Practice directions  rts  net metering regulations 2015
Practice directions rts net metering regulations 2015
Jay Ranvir
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 
Power Distribution
Power Distribution Power Distribution
Power Distribution
UGL Limited
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
Gensol Engineering Limited
 
Tariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power SectorTariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power Sector
IPPAI
 
Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An Overview
IOSR Journals
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
IPPAI
 
Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India)
Gensol Engineering Limited
 
The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...
The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...
The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...IPPAI
 
2014 PV Distribution System Modeling Workshop: European codes & guidelines fo...
2014 PV Distribution System Modeling Workshop: European codes & guidelines fo...2014 PV Distribution System Modeling Workshop: European codes & guidelines fo...
2014 PV Distribution System Modeling Workshop: European codes & guidelines fo...
Sandia National Laboratories: Energy & Climate: Renewables
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
Power System Operation
 
Qc installation manual
Qc installation manualQc installation manual
Qc installation manual
DEEPAKKUMARRAUT3
 
Presentation On Salient Features Of The Electricity Act , 2003
Presentation On Salient Features Of The Electricity Act , 2003Presentation On Salient Features Of The Electricity Act , 2003
Presentation On Salient Features Of The Electricity Act , 2003
rapper44
 
DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014
Headway Solar
 
Power Grid and development in India
Power Grid and development in IndiaPower Grid and development in India
Power Grid and development in India
Sandipan Chakraborty
 
Powergrid ppt campus_v1.33 engr
Powergrid ppt campus_v1.33 engrPowergrid ppt campus_v1.33 engr
Powergrid ppt campus_v1.33 engrAbhijit Sahare
 

What's hot (20)

Presentation on captive power plants
Presentation on captive power plantsPresentation on captive power plants
Presentation on captive power plants
 
Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?
 
Practice directions rts net metering regulations 2015
Practice directions  rts  net metering regulations 2015Practice directions  rts  net metering regulations 2015
Practice directions rts net metering regulations 2015
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 
Power Distribution
Power Distribution Power Distribution
Power Distribution
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
Tariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power SectorTariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power Sector
 
Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An Overview
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
 
Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India)
 
The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...
The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...
The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...
 
Draft Feed-In Tariffs
Draft Feed-In TariffsDraft Feed-In Tariffs
Draft Feed-In Tariffs
 
2014 PV Distribution System Modeling Workshop: European codes & guidelines fo...
2014 PV Distribution System Modeling Workshop: European codes & guidelines fo...2014 PV Distribution System Modeling Workshop: European codes & guidelines fo...
2014 PV Distribution System Modeling Workshop: European codes & guidelines fo...
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
 
Qc installation manual
Qc installation manualQc installation manual
Qc installation manual
 
Presentation On Salient Features Of The Electricity Act , 2003
Presentation On Salient Features Of The Electricity Act , 2003Presentation On Salient Features Of The Electricity Act , 2003
Presentation On Salient Features Of The Electricity Act , 2003
 
DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014
 
Power Grid and development in India
Power Grid and development in IndiaPower Grid and development in India
Power Grid and development in India
 
Captive gen
Captive genCaptive gen
Captive gen
 
Powergrid ppt campus_v1.33 engr
Powergrid ppt campus_v1.33 engrPowergrid ppt campus_v1.33 engr
Powergrid ppt campus_v1.33 engr
 

Viewers also liked

Sourcing Beyond Boundries
Sourcing Beyond BoundriesSourcing Beyond Boundries
Sourcing Beyond Boundries
rd1596knl
 
About music
About musicAbout music
About musicRqzhik
 
You are very lucky03
You are very lucky03You are very lucky03
You are very lucky03
deepakstanley
 
Blueprint for success_-_copy
Blueprint for success_-_copyBlueprint for success_-_copy
Blueprint for success_-_copy
deepakstanley
 
About music
About musicAbout music
About musicRqzhik
 
Telecomunicacions
TelecomunicacionsTelecomunicacions
Telecomunicacions
Nickvdgraaf
 
Wind Force Newsletter Nov, Edition, 2011
Wind Force Newsletter   Nov, Edition, 2011Wind Force Newsletter   Nov, Edition, 2011
Wind Force Newsletter Nov, Edition, 2011rupeshsingh_1
 
Wind Force Newsletter Feb, Edition, 2012
Wind Force Newsletter   Feb, Edition, 2012Wind Force Newsletter   Feb, Edition, 2012
Wind Force Newsletter Feb, Edition, 2012rupeshsingh_1
 
Wind Force Newsletter September, Edition, 2012
Wind Force Newsletter   September, Edition, 2012Wind Force Newsletter   September, Edition, 2012
Wind Force Newsletter September, Edition, 2012rupeshsingh_1
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012rupeshsingh_1
 
You are very lucky03
You are very lucky03You are very lucky03
You are very lucky03
deepakstanley
 
Third Party Inspection Services
Third Party Inspection ServicesThird Party Inspection Services
Third Party Inspection Services
rd1596knl
 
Wind Force Newsletter Dec, Edition, 2011
Wind Force Newsletter   Dec, Edition, 2011Wind Force Newsletter   Dec, Edition, 2011
Wind Force Newsletter Dec, Edition, 2011rupeshsingh_1
 

Viewers also liked (14)

Sourcing Beyond Boundries
Sourcing Beyond BoundriesSourcing Beyond Boundries
Sourcing Beyond Boundries
 
About music
About musicAbout music
About music
 
You are very lucky03
You are very lucky03You are very lucky03
You are very lucky03
 
Blueprint for success_-_copy
Blueprint for success_-_copyBlueprint for success_-_copy
Blueprint for success_-_copy
 
About music
About musicAbout music
About music
 
Telecomunicacions
TelecomunicacionsTelecomunicacions
Telecomunicacions
 
Wind Force Newsletter Nov, Edition, 2011
Wind Force Newsletter   Nov, Edition, 2011Wind Force Newsletter   Nov, Edition, 2011
Wind Force Newsletter Nov, Edition, 2011
 
Wind Force Newsletter Feb, Edition, 2012
Wind Force Newsletter   Feb, Edition, 2012Wind Force Newsletter   Feb, Edition, 2012
Wind Force Newsletter Feb, Edition, 2012
 
Wind Force Newsletter September, Edition, 2012
Wind Force Newsletter   September, Edition, 2012Wind Force Newsletter   September, Edition, 2012
Wind Force Newsletter September, Edition, 2012
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012
 
You are very lucky03
You are very lucky03You are very lucky03
You are very lucky03
 
Epid k3sesi2
Epid k3sesi2Epid k3sesi2
Epid k3sesi2
 
Third Party Inspection Services
Third Party Inspection ServicesThird Party Inspection Services
Third Party Inspection Services
 
Wind Force Newsletter Dec, Edition, 2011
Wind Force Newsletter   Dec, Edition, 2011Wind Force Newsletter   Dec, Edition, 2011
Wind Force Newsletter Dec, Edition, 2011
 

Similar to WinD Force Newsletter October Edition

Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transition
Narinporn Malasri
 
Expert group constituted by CERC proposes draft IEGC 2020
Expert group constituted by CERC proposes draft IEGC 2020Expert group constituted by CERC proposes draft IEGC 2020
Expert group constituted by CERC proposes draft IEGC 2020
Amitava Nag
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
Harish Sharma
 
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
professionalpanorama
 
Cost appraisal of chhabra thermal
Cost appraisal of chhabra thermalCost appraisal of chhabra thermal
Cost appraisal of chhabra thermal
Tapasya123
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...electricitygovernance
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
Saurabh Mehta
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
Harish Sharma
 
Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentives
Chirag Jain
 
VENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentation
VENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentationVENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentation
VENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentation
nijamnveloor
 
Discussion paper 16.11.2015
Discussion paper 16.11.2015Discussion paper 16.11.2015
Discussion paper 16.11.2015
Krishna Ambatipudi
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
Harish Sharma
 
Bhatia small wind[1]
Bhatia small wind[1]Bhatia small wind[1]
Bhatia small wind[1]satishmnair
 
Electricity act 2003
Electricity act 2003Electricity act 2003
Electricity act 2003
Sanket Samantray
 
Wind Energy - Make In India, 2015
Wind Energy - Make In India, 2015Wind Energy - Make In India, 2015
Wind Energy - Make In India, 2015
Amalist Client Services
 
PES Wind Magazine - The development of a MV power converter for FC wind turbi...
PES Wind Magazine - The development of a MV power converter for FC wind turbi...PES Wind Magazine - The development of a MV power converter for FC wind turbi...
PES Wind Magazine - The development of a MV power converter for FC wind turbi...
Ingeteam Wind Energy
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
SHOBHIT NARAIN PANDEY
 
Discussion paper 16.11.2015
Discussion paper 16.11.2015Discussion paper 16.11.2015
Discussion paper 16.11.2015
Krishna Ambatipudi
 
K a-sivaram-chitale-policy-framework-for-transmission-distribution
K a-sivaram-chitale-policy-framework-for-transmission-distributionK a-sivaram-chitale-policy-framework-for-transmission-distribution
K a-sivaram-chitale-policy-framework-for-transmission-distributionsrinivasdeepak
 

Similar to WinD Force Newsletter October Edition (20)

storagePMR
storagePMRstoragePMR
storagePMR
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transition
 
Expert group constituted by CERC proposes draft IEGC 2020
Expert group constituted by CERC proposes draft IEGC 2020Expert group constituted by CERC proposes draft IEGC 2020
Expert group constituted by CERC proposes draft IEGC 2020
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
 
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
 
Cost appraisal of chhabra thermal
Cost appraisal of chhabra thermalCost appraisal of chhabra thermal
Cost appraisal of chhabra thermal
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
 
Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentives
 
VENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentation
VENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentationVENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentation
VENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentation
 
Discussion paper 16.11.2015
Discussion paper 16.11.2015Discussion paper 16.11.2015
Discussion paper 16.11.2015
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
 
Bhatia small wind[1]
Bhatia small wind[1]Bhatia small wind[1]
Bhatia small wind[1]
 
Electricity act 2003
Electricity act 2003Electricity act 2003
Electricity act 2003
 
Wind Energy - Make In India, 2015
Wind Energy - Make In India, 2015Wind Energy - Make In India, 2015
Wind Energy - Make In India, 2015
 
PES Wind Magazine - The development of a MV power converter for FC wind turbi...
PES Wind Magazine - The development of a MV power converter for FC wind turbi...PES Wind Magazine - The development of a MV power converter for FC wind turbi...
PES Wind Magazine - The development of a MV power converter for FC wind turbi...
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 
Discussion paper 16.11.2015
Discussion paper 16.11.2015Discussion paper 16.11.2015
Discussion paper 16.11.2015
 
K a-sivaram-chitale-policy-framework-for-transmission-distribution
K a-sivaram-chitale-policy-framework-for-transmission-distributionK a-sivaram-chitale-policy-framework-for-transmission-distribution
K a-sivaram-chitale-policy-framework-for-transmission-distribution
 

WinD Force Newsletter October Edition

  • 1.
  • 2. Enabling High Efficiency and Reliable Wind Power Projects 1 Policy and Regulatory Maharashtra Wind Zone Classification Procedure In recent Wind Power Tariff Orders, Maharashtra Electricity Regulatory Commission (MERC) has come out with wind power tariff structure for different wind zones in the state. In these orders, MERC has segregated the sites into 4 different zones based on the mean annual wind power density (WPD) in those areas: Wind Energy Mean Annual Levellised Total Net Levellised Tariff (upon Projects Zone WPD Tariff adjusting for Accelerated at 50 m hub- (FY2011-12) Depreciation benefit) (if height (W/m2) in Rs / kWh availed) in Rs / kWh Wind Zone-1 200-250 5.37 4.56 Wind Zone-2 250-300 4.67 3.96 Wind Zone-3 300-400 3.97 3.38 Wind Zone-4 Above 400 3.58 3.04 Maharashtra State Electricity Distribution Co. Ltd. (MESDCL) had raised some issues on the manner in which zoning of different areas was to be done. MSEDCL had also been refusing execution of the long term Power Purchase Agreements (PPAs) as per the MERC Order in effect. This had led to a lot of confusion and resentment amongst the investors, lenders and even the manufacturers of wind turbine generators. The outcome was a significant delay in investments in windfarm development in the state. Though, it has taken time, but, the Maharashtra Energy Development Agency (MEDA) has now come out with a clear procedure for classification of wind zones. The highlights of the zone wise classification are: Ÿ The mean annual WPD at 50 meter at the reference wind mast, declared by Centre for Wind Energy Technologies (C-WET) under the Ministry of New & Renewable Energy (MNRE) or MEDA programme or data vetted by C-WET location shall be considered to be the annual mean WPD for the effective area of 10 km radial distance from the location of the reference wind mast. Ÿ If a Wind Power Project (WPP) falls within the effective areas of two different wind masts having different values of annual mean WPD, then the annual mean WPD of the nearest wind mast shall be considered for that WPP. Ÿ For an upcoming WPP, within the effective area, if 50% or more than 50% of the proposed WTG location co-ordinates are falling above or below 60 m elevation difference with reference to the mean sea level (MSL) of the reference wind mast, then investor/developer shall approach C-WET to obtain project specific annual mean WPD report either on MEDA's advice or permission. While signing Energy Purchase Agreement (EPA) with the distribution licensee, developer/investor shall have to submit letter issued by MEDA for wind zone classification. www.windforce-management.com
  • 3. Enabling High Efficiency and Reliable Wind Power Projects 2 Introduction of Cross Subsidy Surcharge in Maharashtra Earlier in 2006, to promote Open Access (OA), MERC came with an order determining Cross Subsidy Surcharge (CSS) as Zero for OA Consumers from September 2006 to September 2011. Later in August 2010, MSEDCL had filed a Petition with MERC seeking review of the aforesaid order in light of achievement of the same (i.e. to match the electricity demand in the State through OA. MERC has decided to re-determine the CSS due to the change in the current power scenario. The CSS has been computed for Open Access transactions for various consumer categories based on their voltage levels. The range of applicable CSS is Rs. 0.21/unit to Rs. 2.81/unit for different DISCOMs (R-Infra, MSEDCL, BEST, Tata Power), for different categories of consumers (industrial, commercial etc), connected at different feeders (express/non-express) at different voltage levels (above/below 66 kV). CSS applicable to open access transactions from Renewable Energy Sources has been fixed at 25% of the applicable CSS of the respective consumer category. MERC has fixed a discounted CSS in order to promote generation from Renewable Energy sources, which is in line with the objectives of EA 2003 KREDL Notification for Wind Project Developers Recently, MNRE has done away with the criteria for Wind Power Density (WPD) for installation of commercial WPPs in India. In contrast of this, KREDL has decided, not to insist on this parameter to approve DPRs. However, to ensure use of higher efficiency WTGs only, KREDL has mandated minimum generation of 20% CUF per WTG in the agreements with developers/ manufacturers. The clause shall include removal of those WTGs (<20% PLF) on the cost of manufacturers/developers. Rajasthan DISCOMs have increased tariff for HT consumers Rajasthan DISCOMs have filed ARR in RERC for the year 2011-12 and revised the applicable tariff for industrial and commercial consumers. Following are the new tariff for various categories: Existing Tariff New Tariff Type of Industry Energy charges (Rs. / kWh) Energy charges (Rs. / kWh) Medium Industries 3.75 4.75 Large Industries 4.01 5.00 Non Domestic (Commercial) Upto 100 units 4.50 5.90 Above 100 units 4.90 Due to ~ 100 paisa/kWh hike in tariff, the investors who have already installed WPPs and those who are planning to install WPPs for captive use, will get higher benefit as their cost of power remain insulated for such steep hike state tariff. www.windforce-management.com
  • 4. Enabling High Efficiency and Reliable Wind Power Projects 3 What’s New Draft guidelines for installation of wind turbine models in India The current qualification criteria for installation of WTGs in India require a certification from C-WET which is a time taking process even in cases wherein a certificate from Internationally Recognised Agency is available. This has in-turn restricted certain better WTG models and technology to be used in India. To give a boost to wind power development in India by creating the environment that promotes healthy business, ensures safety standards and encourages technological growth, MNRE has issued new draft guidelines for installation of wind turbine models in India and invited comments/views/suggestions on the same by 29th September 2011. Major highlights of these guidelines are: Ÿ Any new WTGs to be installed in India must possess a valid type certificate from an internationally accredited certification agency and fully comply with IEGC 2010. Ÿ Manufacturers can install up to 15 MW of a specific turbine model in India to test its performance in India. To sell any such model in India, they will be required to establish manufacturing base in the Country. Ÿ The self-certification guidelines for installation of WTGs, which allows installation of non-certified machines, have been discontinued with immediate effect. This guideline will cover all such machines that have already been approved under the RLMM scheme, but not yet installed. However, self-certified machines approved under the RLMM scheme and installed will be subject to guidelines issued in December 2009 and January 2010 that required submission of the documents related to type certificate within the committed timeframe and other requirements. Ÿ The guidelines also specify four international certification programmes that will be accepted in addition to the revised TAPS-2000 programme of C-WET. The certification clauses will accelerate capacity addition by de-clogging C-WET's pipeline. The guidelines are applicable from 1st December 2011 in the run-up to the 12th Five Year Plan (2012- 17), and from the same day the RLMM Committee will stand dissolved. The following certification schemes will be recognised when an accredited certifying body carries out certification: Ÿ IEC Certification Scheme Ÿ Germanisher Loyds Certification Scheme Ÿ The Danish Certification Scheme Ÿ The Dutch Certification Scheme Addendum to Revised List of Models and Manufacturers (RLMM) As per addendum to Main List (RLMM) of Wind Turbines in India dated 22.09.2011, following WTGs have been added viz. Kenersys K100 - 2.5 MW, Global L82 - 2.0 MW, Suzlon S95, S97 - 2.1 MW & S88 - 2.25 MW. www.windforce-management.com
  • 5. Enabling High Efficiency and Reliable Wind Power Projects 4 Important Notice regarding Registration for Application All RE Generators are requested to furnish complete documents as mentioned in the check list: ŸHard copy of online Registration application signed and stamped on each page. ŸAccreditation Certificate. ŸCommissioning Certificate/ Commissioning Schedule. Ÿ Applicable clauses of the declaration given in online application that it has not entered into any Power Purchase Agreement at preferential tariff on the letter head of the company. ŸFees and Charges. ŸUndertaking to pay any service tax or any other taxes applicable on REC fees and charges. ŸLetter for authorised signatory if application is not signed by MD/CEO. If any information will be found missing and asked by central agency to furnish then it shall be routed through concerned state agency to central agency. India installed capacity in FY 12, H1 In FY 12 H1, ~ 1445 MW of Wind capacities have been commissioned. In view of possibility that the accelerated depreciation benefit may not be available post 31st March 2012 a good portion of this capacity may have come from the accelerated depreciation seekers. Similarly, for IPPs also, as per current policy GBI is available for projects commissioned by 31st March 2012 only. These two can be the key drivers for the huge investment this year. We expect that the total capacity to be commissioned this year shall be in the range of 2500 - 3000 MW. Events Ÿ WinDForce attended in Power Trading Summit 2011organized by Power Markets India, held in Crown Plaza New Delhi. Various stakeholders of power industry participated in the event discussing about: § Trading Renewable Power, Wind and Solar Scheduling, Annual Pool Power Costs - Future Trends, REC Markets - Pricing beyond 2012 § Long Term, Short Term and Medium Term Power Markets, Future of Power Exchanges, Bilateral Trades v/s Exchange Trades § Financial Risks in Trades, Project Finance Risks and Mitigations Ÿ Mr. Jami Hossain, Chief Mentor and Founder of WinDForce participated in Business-to- Business Forum on “Fostering Business Partnerships to Promote the Adoption and Utilizationn of Renewable Energy Technologies” 22-23 September 2011, Colombo, Sri Lanka. The event organised by Asian and Pacific Centre for Transfer of Technology (APCTT) of the United Nations - Economic and Social Commission for Asia and the Pacific (ESCAP) had the participation from many countries of the Asia Pacific region. Speaking to delegates as well as dignitaries from Sri Lanka including the Energy Minister, Hossain talked about the possibility of a submarine transmission link between Sri Lanka and India that would stabilise the Sri Lankan grid as well as enable large scale exploitation of wind energy in North Sri Lanka. Hossain was invited as a resource person to the meet. www.windforce-management.com
  • 6. Enabling High Efficiency and Reliable Wind Power Projects 5 Upcoming Events Ÿ Workshop on Renewable Regulatory Fund (RRF) Mechanism for Southern Region stakeholders on 10 October 2011 and for Western Region stakeholders on 14 October 2011 is being organised by NLDC. Ÿ ICCC-1: International Conclave on Climate Change from 12-14 October 2011at Hyderabad International Trade Expositions Limited (HITEX), Madhapur, Hyderabad, A.P, India. Ÿ Green Conclave and Green Leadership Forum 2011: Discussion on the most critical issues that surround the clean technologies sector and the investment opportunities it offers to be held on 14th October 2011 at The Leela Palace, Diplomatic Enclave, Chanakyapuri, New Delhi Ÿ RENEWTECH INDIA 2011: International Exhibition & Conference on Renewable Energy from 10-12 November 2011 at Bombay Exhibition Centre, Goregaon, Mumbai, India. Tenders Ÿ Karnataka Renewable Energy Development Limited (KREDL) has come out with an NIT inviting bids from the manufacturers with WTG capacity of more than 1500 kW for development of two wind power projects of 6 MW capacities each in the state of Karnataka on LSTK basis. ŸHukeri Rural Electric Co-operative Society Limited has called for Expression of Interest from the developers in the field of Wind Energy with our without land for a capacity of 100 MW in stages for attaining self sustainability. REC Trading The above graph indicates that the equilibrium price of REC traded at both the exchanges is increasing every month. Moreover traded volume at both the exchanges is also increasing. In the recent trading held on 28th September 2011, there were buy bids for ~2, 27,000 RECs against sell bids for ~85,600 RECs, where as in the last trading held on 2nd September 2011, there were buy bids for ~ 1, 83,305 RECs against sell bids for ~58,052 RECs. www.windforce-management.com
  • 7. Enabling High Efficiency and Reliable Wind Power Projects 6 Calculation of Equilibrium Price (EP) and Volume for RECs at IEX A matching of the buy and sell bids will take place only if there are crossing prices (Buy Price >= Sell Price). Accordingly, the EP is determined as per following criteria: Ÿ EP will be the price at which there is Maximum Tradable Volume (MTV). Ÿ If there is more than one price with equal value for MTV, the price that leaves the least volume untraded at its level (minimum unbalance) is chosen as EP. In price determination process, at every candidate price level (CPL), the volume is cumulated and the difference between cumulative buy and cumulative sell is calculated. This gives two values at every CPLs: Ÿ Tradable Volume (minimum of cumulative buy and cumulative sell) Ÿ Unbalance (Difference of cumulative buy and cumulative sell; positive, negative or zero. Following four rules are for calculating EP: Rule 1: If a CPL with maximum tradable volume exists, this price is an EP. This rule gives one or more price levels: Ÿ If the maximum tradable volume is zero (no crossing prices), no EP is determined. Ÿ If there is only one price level, this is the EP. Ÿ If there are multiple levels, rule 2 is applied. Rule 2: If there are several price levels for maximum tradable volume, the levels with minimum Unbalance are CPLs. This rule gives us one or more price levels: Ÿ If there is only one price level, this is the EP. Ÿ If there are multiple price levels, and the unbalance is not zero, rule 3 is applied. Ÿ If there are multiple price levels, and the unbalance is zero, rule 4 is applied. Rule 3a: If the sign(+/-) of unbalance is same for all CPLs, the price closest to the price at which sign of unbalance has changed (from positive to negative or negative to positive, as the case may be) , is chosen as EP. Rule 3b:If the unbalances at CPLs have different signs, the highest CPL with positive unbalance and the lowest CPL with negative unbalance are identified. The EP is then chosen randomly between these two. Rule 4: If there are two CPLs with unbalance = 0, then one of them is chosen randomly as EP. For a better understanding, we may refer the following example: In this graph, there are 3 different buy bids and 3 different sell bids. www.windforce-management.com
  • 8. Enabling High Efficiency and Reliable Wind Power Projects 7 A is the buyer who is willing to buy 1000 REC at any price =< Rs 3900/REC, B is willing to buy 6000 REC at any price =< Rs 2300/REC and C is willing to buy 2000 REC at a price of WinDForce Services Rs1700/REC. Whereas D is the seller who is willing to sell 1000 RECs at any price >= Rs Ÿ Wind Resource Assessment (WRA) 1500/REC, E is willing to sell 2000 RECs at any price >= Rs 1700/REC and F is willing to sell Ÿ Owner’s Engineer during the complete 3000 RECs at any price >= Rs 2000/REC. p ro j e c t i m p l e m e ntat i o n & p o st commissioning Now Rs 2200/REC is the price level for maximum tradable volume and minimum imbalance Ÿ Detailed Project feasibility Study so equilibrium volume shall be 6000 RECs at an equilibrium price of Rs 2300/REC. Ÿ Detailed Project Report Ÿ Contract Advisory Ÿ Technical Due Diligence of proposed as well as existing wind farms Ÿ E nt r y st rate g i e s fo r n ew W TG s manufactures Ÿ Structuring of PPA Ÿ Sale of power and management Ÿ Environment Impact Assessment Ÿ Development/ Co-development of Wind Power Projects at Identified sites by WinDForce (* Source: IEX) Short Term Electricity Price From the above graph it can clearly be said that during the last one year, most of the time, except 1-2 month, short term market price of electricity in bilateral arrangement is higher than that at power exchanges. This analysis includes only inter-State transactions. Electricity price in bilateral arrangements, in year 2011 is lesser than price in year 2010 showing a decrease in prices. The ratio of electricity traded on power exchanges to that of total short term bilateral trades has increased from ~22% in 2009-10 to ~36% in 2010-11. www.windforce-management.com
  • 9. Contact Us Corporate Office Kindly write to us if you have any comments on this Newsletter. Your valuable WinDForce Management Services Pvt. Ltd. feedback on this would motivate and help us in improving the quality and enriching 5th Floor, Universal Trade Tower the content. We are eagerly waiting for your kind response to the articles presented in Gurgaon - Sohna Road this Newsletter. Gurgaon - 122001, Haryana Tel: +91 - 124-4353100 Parish Gupta Fax: +91-124-4102980 Mob: +91 98717 11445 Web: www.windforce-management.com E-mail: parish@windforce-management.com Rupesh Singh Mob: +91 96507 58884 E-mail: rupesh@windforce-management.com A WinDForce Publication Disclaimer - This Newsletter has been compiled by WinDForce Management Services Private Limited for circulation among the stakeholders in the energy market. Though the contents of this bulletin are correct to the best of our knowledge, WinDForce does not vouch for their accuracy. www.windforce-management.com