SlideShare a Scribd company logo
Strategic Allocation of Ressources
in Wind Energy Projects
to Improve Project Parameters
Cotanum GmbH
Solutions for
Europe´s Clean Energy Future
Overview Major Topics

Shorter Project Development Phases

Efficient use of Finances
Overview
time/costs
Period I Period II Costs Phase I
Plan
Costs Phase I
real
Project Berlin B8 4 month 9 month 136 Mio € 167 Mio €
Project Stuttgart
NG
6 month 10
month
83 Mio € 116 mio €
Project Frankfurt
north
7 month 8 month 101 Mio € 107 Mio €
Project Neckar II 8 month open 76 Mio € open
Project Hamburg
N4
open open 83 Mio € open
Project 25
Project 28
Project 29
Mission

Target: Reduce Time for Development and
Installation about 30%

Cut Project Costs by 25%

Clear Structure and better forecasting for
Investors (Phase II and CM)
Situation

Projets take 12....19 Month for Phases I and II

Deviation in Cost plan/FC is significant
→ Investors are reluctant to invest financial
ressources
→ Project members have few control on scedule and
therefore poor planning
→ this increases Costs !!
→ this delays Projects !!
Status A

Status of A- and D-application is poor

Control of planning and production factors is
insufficient

Prognosis fail in 78 % of all projects (10% or
more deviation)

Costs/Planning poor and not applicable

Project management fails

Feedback Loop inconsistent
Status B

Proposal CM-3 for Phase I : worked out in
Jan 2016 by Cotanum GmbH for Client

Agreement of Shareholders and
Management of Holding obtained

Proposal accepted in Jan. 2016

Proposal for Phase II in progress (see S23)

Action Plan 2016/2018 in preparation
(by Cotanum GmbH, Germany)
Further Steps

Agreement to keep Update Information (see S12)

Scedule of complete Project published

Project Results Phase II to be presented by Cotanum
GmbH in Late Summer 2016

Transfer of project results to USA: end 2016

Transfer of project results to China: end2016/2017
End of Presentation
Cotanum GmbH
Glosterweg 6
30559 Hannover
www.cotanum.com

More Related Content

What's hot

Pmi processes
Pmi processesPmi processes
Pmi processes
Tim Blevins
 
Sls plan integrated with FlxGl and FM
Sls plan integrated with FlxGl and FMSls plan integrated with FlxGl and FM
Sls plan integrated with FlxGl and FM
Anatoly Ryabukha
 
4 2018
4 20184 2018
4 2018
AjeeshMT3
 
Project Timeline
Project TimelineProject Timeline
Project Timeline
Yousuf Mohammad
 
SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE intro we have a new project!
SLOPE intro we have a new project!
SLOPE Project
 
Session 10 4th edition PMP
Session   10 4th edition PMPSession   10 4th edition PMP
Session 10 4th edition PMP
محمد عصمت عبد الرازق
 
Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)
Mayur Rahangdale
 
Group presetnation 4th semesster group
Group presetnation 4th semesster groupGroup presetnation 4th semesster group
Group presetnation 4th semesster group
Vladislav Nedelev
 
Programmes of work for Core Unit 2002
Programmes of work for Core Unit 2002Programmes of work for Core Unit 2002
Programmes of work for Core Unit 2002
Steve Jarvis
 
New harquahala electric power presentation
New harquahala electric power presentation New harquahala electric power presentation
New harquahala electric power presentation
NAES Corporation
 
eresource nfra ERP - PMC module
eresource nfra ERP  - PMC moduleeresource nfra ERP  - PMC module
eresource nfra ERP - PMC module
nfra erp
 
Hot water system
Hot water systemHot water system
Hot water system
Elisha Mchelle
 
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Glen Alleman
 
Exam 5th semester group presentation
Exam 5th semester group presentationExam 5th semester group presentation
Exam 5th semester group presentation
Vladislav Nedelev
 
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
Helmut F Giesa HFG2404@gmail.com
 
Presentation of Quarterly Report_Deborah Ighagbon
Presentation of Quarterly Report_Deborah IghagbonPresentation of Quarterly Report_Deborah Ighagbon
Presentation of Quarterly Report_Deborah Ighagbon
AANUOLUWAPO D. IGHAGBON
 

What's hot (16)

Pmi processes
Pmi processesPmi processes
Pmi processes
 
Sls plan integrated with FlxGl and FM
Sls plan integrated with FlxGl and FMSls plan integrated with FlxGl and FM
Sls plan integrated with FlxGl and FM
 
4 2018
4 20184 2018
4 2018
 
Project Timeline
Project TimelineProject Timeline
Project Timeline
 
SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE intro we have a new project!
SLOPE intro we have a new project!
 
Session 10 4th edition PMP
Session   10 4th edition PMPSession   10 4th edition PMP
Session 10 4th edition PMP
 
Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)
 
Group presetnation 4th semesster group
Group presetnation 4th semesster groupGroup presetnation 4th semesster group
Group presetnation 4th semesster group
 
Programmes of work for Core Unit 2002
Programmes of work for Core Unit 2002Programmes of work for Core Unit 2002
Programmes of work for Core Unit 2002
 
New harquahala electric power presentation
New harquahala electric power presentation New harquahala electric power presentation
New harquahala electric power presentation
 
eresource nfra ERP - PMC module
eresource nfra ERP  - PMC moduleeresource nfra ERP  - PMC module
eresource nfra ERP - PMC module
 
Hot water system
Hot water systemHot water system
Hot water system
 
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
 
Exam 5th semester group presentation
Exam 5th semester group presentationExam 5th semester group presentation
Exam 5th semester group presentation
 
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
 
Presentation of Quarterly Report_Deborah Ighagbon
Presentation of Quarterly Report_Deborah IghagbonPresentation of Quarterly Report_Deborah Ighagbon
Presentation of Quarterly Report_Deborah Ighagbon
 

Viewers also liked

Proiect de lectie
Proiect de lectieProiect de lectie
Proiect de lectie
razvi1994
 
ingeneria economica en la toma de decisiones
ingeneria economica en la toma de decisionesingeneria economica en la toma de decisiones
ingeneria economica en la toma de decisiones
Jose Camejo
 
Chinese Business Tax and Accounting-Chunyee_Miot_CPA
Chinese Business Tax and Accounting-Chunyee_Miot_CPAChinese Business Tax and Accounting-Chunyee_Miot_CPA
Chinese Business Tax and Accounting-Chunyee_Miot_CPAMiot, Chunyee
 
Latest Resume pdf
Latest Resume pdfLatest Resume pdf
Latest Resume pdf
THOTHADRI SETHURAMAN
 
Proiect de lectie
Proiect de lectieProiect de lectie
Proiect de lectie
razvi1994
 
A Beginners Guide Workshop -Wellness Expo
A Beginners Guide Workshop -Wellness ExpoA Beginners Guide Workshop -Wellness Expo
A Beginners Guide Workshop -Wellness Expo
Robert L. Woods
 
Virtual Reality
Virtual Reality Virtual Reality
Proiect de lectie
Proiect de lectieProiect de lectie
Proiect de lectie
razvi1994
 
Safe Ride Pitch
Safe Ride PitchSafe Ride Pitch
Alcoholismo
AlcoholismoAlcoholismo
Alcoholismo
KarlaCajas1904
 
Blue Band Sales Promo
Blue Band Sales PromoBlue Band Sales Promo
RSN Activities Press Reports
RSN Activities Press ReportsRSN Activities Press Reports
RSN Activities Press Reports
Charles Ogutu BS, AAS, AU, AIS, API, Dip CII
 
RSN Launch & Personel
RSN Launch & PersonelRSN Launch & Personel
Field test of a locally designed inter furrow cultivator prototype
Field test of a locally designed inter furrow cultivator prototypeField test of a locally designed inter furrow cultivator prototype
Field test of a locally designed inter furrow cultivator prototype
Nabil Shaban
 
Women Empowerment- Send My Gift
Women Empowerment- Send My GiftWomen Empowerment- Send My Gift
Women Empowerment- Send My Gift
prabhakar65
 
Word
WordWord

Viewers also liked (17)

Ford Sales Promo 1
Ford Sales Promo 1Ford Sales Promo 1
Ford Sales Promo 1
 
Proiect de lectie
Proiect de lectieProiect de lectie
Proiect de lectie
 
ingeneria economica en la toma de decisiones
ingeneria economica en la toma de decisionesingeneria economica en la toma de decisiones
ingeneria economica en la toma de decisiones
 
Chinese Business Tax and Accounting-Chunyee_Miot_CPA
Chinese Business Tax and Accounting-Chunyee_Miot_CPAChinese Business Tax and Accounting-Chunyee_Miot_CPA
Chinese Business Tax and Accounting-Chunyee_Miot_CPA
 
Latest Resume pdf
Latest Resume pdfLatest Resume pdf
Latest Resume pdf
 
Proiect de lectie
Proiect de lectieProiect de lectie
Proiect de lectie
 
A Beginners Guide Workshop -Wellness Expo
A Beginners Guide Workshop -Wellness ExpoA Beginners Guide Workshop -Wellness Expo
A Beginners Guide Workshop -Wellness Expo
 
Virtual Reality
Virtual Reality Virtual Reality
Virtual Reality
 
Proiect de lectie
Proiect de lectieProiect de lectie
Proiect de lectie
 
Safe Ride Pitch
Safe Ride PitchSafe Ride Pitch
Safe Ride Pitch
 
Alcoholismo
AlcoholismoAlcoholismo
Alcoholismo
 
Blue Band Sales Promo
Blue Band Sales PromoBlue Band Sales Promo
Blue Band Sales Promo
 
RSN Activities Press Reports
RSN Activities Press ReportsRSN Activities Press Reports
RSN Activities Press Reports
 
RSN Launch & Personel
RSN Launch & PersonelRSN Launch & Personel
RSN Launch & Personel
 
Field test of a locally designed inter furrow cultivator prototype
Field test of a locally designed inter furrow cultivator prototypeField test of a locally designed inter furrow cultivator prototype
Field test of a locally designed inter furrow cultivator prototype
 
Women Empowerment- Send My Gift
Women Empowerment- Send My GiftWomen Empowerment- Send My Gift
Women Empowerment- Send My Gift
 
Word
WordWord
Word
 

Similar to Wind Energy Project Strategy - Improvements

An overview of the status quo, prospects and outlook of market mechanisms
An overview of the status quo, prospects and outlook of market mechanisms An overview of the status quo, prospects and outlook of market mechanisms
An overview of the status quo, prospects and outlook of market mechanisms
NewClimate Institute
 
Chunnel Project
Chunnel ProjectChunnel Project
Chunnel Project
Shivam Sood
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
Forbes Chanakira
 
Erp.ppt
Erp.pptErp.ppt
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development Phase
Khyati Tewari
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
Ibrahim Al-Hudhaif
 
Ignalina Nuclear Power Plant Presentation to the Assembly of Contributors
Ignalina Nuclear Power Plant Presentation to the Assembly of ContributorsIgnalina Nuclear Power Plant Presentation to the Assembly of Contributors
Ignalina Nuclear Power Plant Presentation to the Assembly of Contributors
Osvaldas Ciuksys
 
CHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfCHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdf
MartinsAras
 
Multiproject Control
Multiproject ControlMultiproject Control
Multiproject Control
Siddharth Anand
 
ev392s.pdf
ev392s.pdfev392s.pdf
ev392s.pdf
shaluka2
 
Infrastructure & PPPs - Colin Forthun, Norway
Infrastructure & PPPs - Colin Forthun, NorwayInfrastructure & PPPs - Colin Forthun, Norway
Infrastructure & PPPs - Colin Forthun, Norway
OECD Governance
 
Europeana Cloud - Progress and Financial Reporting
Europeana Cloud - Progress and Financial ReportingEuropeana Cloud - Progress and Financial Reporting
Europeana Cloud - Progress and Financial Reporting
Europeana
 
Color coded Multi-Project Monitoring (CPM)
Color coded Multi-Project Monitoring (CPM)Color coded Multi-Project Monitoring (CPM)
Color coded Multi-Project Monitoring (CPM)
Hilario Martinez
 
Minvrom 06 Mul
Minvrom 06 MulMinvrom 06 Mul
Minvrom 06 Mul
aadityaom
 
Chunnel project project cost management
Chunnel  project project cost managementChunnel  project project cost management
Chunnel project project cost management
Sagar Rana
 
Spending reviews - Rita Schutt & Ulf Rosner, Germany
Spending reviews - Rita Schutt & Ulf Rosner, GermanySpending reviews - Rita Schutt & Ulf Rosner, Germany
Spending reviews - Rita Schutt & Ulf Rosner, Germany
OECD Governance
 
Deep Retrofit: Life Cycle Cost Benefits Analysis
Deep Retrofit: Life Cycle Cost Benefits Analysis Deep Retrofit: Life Cycle Cost Benefits Analysis
Deep Retrofit: Life Cycle Cost Benefits Analysis
SustainableEnergyAut
 
Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key
Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the KeyLessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key
Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key
Association for Project Management
 
Delivering major projects in government presentation, Joanna Lewis & Chris Ba...
Delivering major projects in government presentation, Joanna Lewis & Chris Ba...Delivering major projects in government presentation, Joanna Lewis & Chris Ba...
Delivering major projects in government presentation, Joanna Lewis & Chris Ba...
Association for Project Management
 
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
KTN
 

Similar to Wind Energy Project Strategy - Improvements (20)

An overview of the status quo, prospects and outlook of market mechanisms
An overview of the status quo, prospects and outlook of market mechanisms An overview of the status quo, prospects and outlook of market mechanisms
An overview of the status quo, prospects and outlook of market mechanisms
 
Chunnel Project
Chunnel ProjectChunnel Project
Chunnel Project
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
Erp.ppt
Erp.pptErp.ppt
Erp.ppt
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development Phase
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
 
Ignalina Nuclear Power Plant Presentation to the Assembly of Contributors
Ignalina Nuclear Power Plant Presentation to the Assembly of ContributorsIgnalina Nuclear Power Plant Presentation to the Assembly of Contributors
Ignalina Nuclear Power Plant Presentation to the Assembly of Contributors
 
CHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfCHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdf
 
Multiproject Control
Multiproject ControlMultiproject Control
Multiproject Control
 
ev392s.pdf
ev392s.pdfev392s.pdf
ev392s.pdf
 
Infrastructure & PPPs - Colin Forthun, Norway
Infrastructure & PPPs - Colin Forthun, NorwayInfrastructure & PPPs - Colin Forthun, Norway
Infrastructure & PPPs - Colin Forthun, Norway
 
Europeana Cloud - Progress and Financial Reporting
Europeana Cloud - Progress and Financial ReportingEuropeana Cloud - Progress and Financial Reporting
Europeana Cloud - Progress and Financial Reporting
 
Color coded Multi-Project Monitoring (CPM)
Color coded Multi-Project Monitoring (CPM)Color coded Multi-Project Monitoring (CPM)
Color coded Multi-Project Monitoring (CPM)
 
Minvrom 06 Mul
Minvrom 06 MulMinvrom 06 Mul
Minvrom 06 Mul
 
Chunnel project project cost management
Chunnel  project project cost managementChunnel  project project cost management
Chunnel project project cost management
 
Spending reviews - Rita Schutt & Ulf Rosner, Germany
Spending reviews - Rita Schutt & Ulf Rosner, GermanySpending reviews - Rita Schutt & Ulf Rosner, Germany
Spending reviews - Rita Schutt & Ulf Rosner, Germany
 
Deep Retrofit: Life Cycle Cost Benefits Analysis
Deep Retrofit: Life Cycle Cost Benefits Analysis Deep Retrofit: Life Cycle Cost Benefits Analysis
Deep Retrofit: Life Cycle Cost Benefits Analysis
 
Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key
Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the KeyLessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key
Lessons Learned Don’t Work: Why a Data Centric Approach May Hold the Key
 
Delivering major projects in government presentation, Joanna Lewis & Chris Ba...
Delivering major projects in government presentation, Joanna Lewis & Chris Ba...Delivering major projects in government presentation, Joanna Lewis & Chris Ba...
Delivering major projects in government presentation, Joanna Lewis & Chris Ba...
 
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
Transforming Construction: Competition Launch Objectives and Scope - Simon Ha...
 

Recently uploaded

Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24
Philip Rabenok
 
AGM Presentation Probe June 11 Final.pdf
AGM Presentation Probe June 11 Final.pdfAGM Presentation Probe June 11 Final.pdf
AGM Presentation Probe June 11 Final.pdf
Probe Gold
 
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptxUnderstanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
cosmo-soil
 
Cyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdfCyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdf
CyberAgent, Inc.
 
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
f3wjr2q2
 
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
ybout
 
Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024
CollectiveMining1
 
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdfZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
SOFTTECHHUB
 
ppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.pptppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.ppt
TestOrg1
 
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUESMUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
WilliamRodrigues148
 
Mandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPTMandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPT
MandalayResources
 
Cleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is BlueCleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is Blue
Cleades Robinson
 
2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf
Sysco_Investors
 
Methanex Investor Presentation - April 2024
Methanex Investor Presentation - April 2024Methanex Investor Presentation - April 2024
Methanex Investor Presentation - April 2024
Methanex Corporation
 

Recently uploaded (14)

Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24
 
AGM Presentation Probe June 11 Final.pdf
AGM Presentation Probe June 11 Final.pdfAGM Presentation Probe June 11 Final.pdf
AGM Presentation Probe June 11 Final.pdf
 
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptxUnderstanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
 
Cyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdfCyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdf
 
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
 
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
 
Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024
 
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdfZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
 
ppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.pptppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.ppt
 
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUESMUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
 
Mandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPTMandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPT
 
Cleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is BlueCleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is Blue
 
2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf
 
Methanex Investor Presentation - April 2024
Methanex Investor Presentation - April 2024Methanex Investor Presentation - April 2024
Methanex Investor Presentation - April 2024
 

Wind Energy Project Strategy - Improvements

  • 1. Strategic Allocation of Ressources in Wind Energy Projects to Improve Project Parameters Cotanum GmbH Solutions for Europe´s Clean Energy Future
  • 2. Overview Major Topics  Shorter Project Development Phases  Efficient use of Finances Overview time/costs Period I Period II Costs Phase I Plan Costs Phase I real Project Berlin B8 4 month 9 month 136 Mio € 167 Mio € Project Stuttgart NG 6 month 10 month 83 Mio € 116 mio € Project Frankfurt north 7 month 8 month 101 Mio € 107 Mio € Project Neckar II 8 month open 76 Mio € open Project Hamburg N4 open open 83 Mio € open Project 25 Project 28 Project 29
  • 3. Mission  Target: Reduce Time for Development and Installation about 30%  Cut Project Costs by 25%  Clear Structure and better forecasting for Investors (Phase II and CM)
  • 4. Situation  Projets take 12....19 Month for Phases I and II  Deviation in Cost plan/FC is significant → Investors are reluctant to invest financial ressources → Project members have few control on scedule and therefore poor planning → this increases Costs !! → this delays Projects !!
  • 5. Status A  Status of A- and D-application is poor  Control of planning and production factors is insufficient  Prognosis fail in 78 % of all projects (10% or more deviation)  Costs/Planning poor and not applicable  Project management fails  Feedback Loop inconsistent
  • 6. Status B  Proposal CM-3 for Phase I : worked out in Jan 2016 by Cotanum GmbH for Client  Agreement of Shareholders and Management of Holding obtained  Proposal accepted in Jan. 2016  Proposal for Phase II in progress (see S23)  Action Plan 2016/2018 in preparation (by Cotanum GmbH, Germany)
  • 7. Further Steps  Agreement to keep Update Information (see S12)  Scedule of complete Project published  Project Results Phase II to be presented by Cotanum GmbH in Late Summer 2016  Transfer of project results to USA: end 2016  Transfer of project results to China: end2016/2017
  • 8. End of Presentation Cotanum GmbH Glosterweg 6 30559 Hannover www.cotanum.com