SlideShare a Scribd company logo
Wet Ponds 
a Contech Solution for Stormwater Management 
A compilation of case studies 
highlighting the advantages of a wet 
pond solution provided by Contech 
Engineered Solutions that will meet 
(and sometimes exceed) the TSS 
mandates stipulated by the Wisconsin 
Department of Natural Resources. 
2012 | www.ContechES.com/UrbanGreen 
Stormwater Solutions from Contech®
www.ContechES.com/UrbanGreen 2 
Table of Contents 
Check out more » 
stormwater management 
solutions provided by 
Contech Engineered Solutions 
at www.ContechES.com/urbangreen 
Stormwater Solutions 
The Contech fit with WINSLAMM for TSS Removal| 4 
Underground Wet Ponds 
Modeling Options| 5 
Wisconsin Project List | 5 
Case Studies 
Sacred Heart Senior Apartments » Saint Francis, WI | 6 
Redevelopment at Main Street & Pilgrim Road » Menomonee Falls, WI | 8 
Boucher Automotive Group » Franklin, WI | 10 
© 2012 Contech Engineered Solutions LLC
A Stormwater Solution for Wet Ponds 
Contech fits WINSLAMM for TSS Removal 
with their Underground “Pond” 
www.ContechES.com/UrbanGreen 3 
Wet Ponds 
Wisconsin Department of Natural Resources (WDNR) mandates that 
New Development projects reduce Total Suspended Solids (TSS) by 
80% and a 40% TSS reduction for redevelopment projects. One 
option is to construct a Wet Pond with a permanent pool of water. 
However, for most urban-set projects this is not an option due to 
limited land resources. Contech’s economical solution to meet the 
WDNR TSS removal requirements is to construct “Underground Wet 
Ponds” using metal, plastic and concrete systems. The lower portion 
of the pipe contains a permanent water pool to remove TSS while the 
upper half of the pipe can be used for Active Storage if needed. With 
the “Pond” underground the land can be utilized for other uses, most 
often parking. 
Interested in learning more? We’d love to hear from you! 
» Eric Sturm | Project Consultant 
(608) 215-3937 
esturm@conteches.com 
» Todd Riebau | Project Consultant 
(608) 576-0109 
triebau@conteches.com 
» Keith Johnson | Sales Engineer 
(920) 860-0989 
kjohnson@conteches.com
www.ContechES.com/UrbanGreen 4 
Wet Ponds 
Underground Wet Ponds 
Modeling a Contech System in WINSLAMM 
Underground 
Wet Ponds can be 
modeled two ways 
in WINSLAMM: 
1 Catch Basin 
After entering the necessary project parameters, alter 
the catch basin size until the TSS removal rate meets 
or exceeds the project requirements. The screen 
shots to the right illustrate a project in the Milwaukee 
area, one acre of impervious area and a 40% TSS 
removal requirement. After a couple iterations in 
the catch basin routine, WINSLAMM determined that 
266 sf of surface area is required. This equates to 
38 lf of 84” dia. CMP with a 3.5’ deep permanent 
water pool. Another option would be to use 47’ of 
72” dia. CMP with a 4’ pool. 
2 Treatment/Detention System as a Pond 
The majority of the projects that Contech Engineered 
Solutions has been involved with require either a 
3.5’ or 4’ permanent water pool. Three feet of 
permanent water pool for particles to settle out of 
solution and a 0.5’ to 1’ sediment collection area. 
We have the experience to prove it. Here are a few examples! 
» Johnson Bank | Brookfield 
» UW Credit Union| West Allis 
» Walmart | Menonmonee Falls 
» West Milwaukee | West Milwaukee 
» Walmart | South Milwaukee 
» Wisconsin Veterans Home | King 
» CVS Pharmacy | De Pere 
» Cabela’s | Ashwaubenon 
» Boucher Automotive | Franklin 
» Sacred Heart | St. Francis 
» Oshkosh Correctional | Oshkosh
Case Study for Underground Wet Ponds 
Sacred Heart Senior Apartments 
Saint Francis, Wisconsin 
Project Team Members: 
Owner: 
Sacred Heart of Jesus Parish 
Engineer: 
The Sigma Group 
Contractor: 
A.W. Oakes & Son 
Technical Description: 
CMP Detention 644-ft. of 142-in. x 
91-in. CMP 
Installation Date: August 2011 
The Sacred Heart of Jesus Church, originally built in the 
early 1960s, was renovated to include a new senior living 
apartment community. The community, called the Sacred 
Heart Senior Apartments, is a non-denominational facility 
and seniors of all faiths are welcome. 
The renovated sanctuary and rectory are 19,058 sf of the 
113,735 sf project. The apartments occupied 84,081 sf in 
the renovated space above the church, which were formerly 
school classrooms, and also in the newly-built addition on 
what was parking lot. There also is a 10,595 sf common 
room shared between church and apartments 
“We’re trying to reinvent ourselves,” said Eric Stemwell, 
Sacred Heart Parish Core Team. “It’s kind of an experiment, 
teaming up with a developer to offer senior housing. Senior 
citizens are a very vital part of any community. What we’re 
trying to do is create an environment where senior citizens 
can thrive.” 
The church contacted The Sigma Group of Milwaukee to 
design the civil portion of the project which included the 
stormwater management plan for the site. 
The state Department of Natural Resources (DNR) requires 
Total Suspended Solids(TSS) reduction in stormwater 
leaving the site of 80% for new developments and 40% 
for redeveloped projects. The 4.0-acre senior apartment 
complex project was considered partially new development 
and partially redevelopment; resulting in a weighted TSS 
reduction requirement of 50%. 
Because the project was located in an urban setting, The 
Sigma Group did not have the option of an aboveground 
5 www.ContechES.com/UrbanGreen 
stormwater pond for the required TSS removal. Instead, they 
looked at “mechanical” options that would be contained 
beneath the parking lot. 
The Sigma Group contacted Contech Engineered Solutions 
for assistance in providing an economical solution to meet 
the DNR requirements. The project covered 4.0 acres. Of 
that, 2.83 acres were treated and 1.17 acres were taken 
offsite with 0% removal. Contech proposed an underground 
stormwater detention system utilizing corrugated metal pipe 
(CMP) to treat the 2.83 acreage because it could achieve 
the weighted 50% TSS reduction requirement. This solution 
also met all of the project requirements while keeping within 
budget. 
Utilizing WinSLAMM (Source Loading And Management 
Model for Windows) to evaluate sediment loading of 
the project site, the Sigma Group determined that the 
underground system needed 7,390 sf of surface area at the 
water line and 48,035 cf of active detention storage. 
The CMP detention system was constructed out of 644 feet 
of 142-in. x 91-in. CMP coated with aluminum to fulfill 
the surface area and active storage area requirements. 
Aluminized, ALT2 coating was chosen to meet the 75 year 
service life required by the owner. The system was designed 
with a 3.5’ permanent pool of water in a serpentine 
configuration to maximize the settling time. The calculated 
TSS removal rate from Contech’s “underground wet pond” 
solution was 76.61% - resulting in a net TSS removal of 
56%, greater than the 50% required, for the entire 4.0 acre 
site.
Case Study for Underground Wet Ponds 
Site Designation » 142x91 Underground Storage | Saint Francis, WI 
www.ContechES.com/UrbanGreen 6 
Case Study for Underground Wet Ponds 
Sacred Heart of Jesus 
Senior Apartments 
Take a Deeper Look, Download the Standard Detail for this Project: 
http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13288
Case Study for Underground Wet Ponds 
Redevelopment at Main Street & Pilgrim Road 
Menomonee Falls, Wisconsin 
Project Team Members: 
Owner: 
Gatlin Development Co. Inc. 
Engineer: 
R.A. Smith National, Inc. 
Contractor: 
D. F. Tomasini Contractors, Inc. 
Technical Description: 
CMP Detention 600-ft. of 108-in. dia. 
Aluminized CMP 
Installation Date: February 2012 
A $10 million development anchored by a Walmart 
Neighborhood Market Store, their smaller grocery format, 
in the Village of Menomonee Falls, Wisconsin. Construction 
design for this 40,000-sf Walmart and separate 5,000- 
sf building for other retail tenants included a stormwater 
management plan. 
The Wisconsin Department of Natural Resources (WDNR) 
requires total suspended solids (TSS) reduction in stormwater 
leaving the project — 80% for new developments and 40% 
for redevelopments. The 9.22 acre Walmart project was being 
constructed on the site of a closed supermarket, making this 
a redevelopment. Additionally, the flow rates for stormwater 
leaving the site needed to be addressed. 
Walmart contacted R.A. Smith National of Brookfield, WI, 
to design the civil portion of the project, which included the 
stormwater management plan for the site. Because this project 
is in an urban setting, R.A Smith National did not have the 
option of an aboveground stormwater pond for detention and 
TSS removal. Instead, they looked at economical “mechanical” 
options to contain stormwater beneath the parking lot to reduce 
the footprint and maximize land use. 
“Due to the dense redevelopment plan and the need to provide 
water quality, it was apparent that the only way to achieve our 
goals was to go with an underground facility”, said project 
engineer Jeremy Jeffery of R.A. Smith National. 
R.A. Smith National chose a corrugated metal pipe (CMP) 
detention and treatment system from Contech Engineered 
Solutions to satisfy the runoff release rates and TSS removal 
requirements set forth by the Village of Menomonee Falls, the 
Milwaukee Metropolitan Sewerage District and the WDNR. 
7 www.ContechES.com/UrbanGreen 
“The Contech design proved to give us the most bang for 
the buck,” said Jeffery. “We were looking for a product that 
would provide the smallest footprint, superior durability and 
service life, and easy installation, all while being cost-effective. 
But the most important of all — a product that would meet all 
regulating agencies requirements.” 
The underground wet detention facility from Contech consisted 
of 600-feet of 9-foot diameter Aluminized Type 2 (ALT2) CMP 
pipe interconnected by a header. The bottom four feet of pipe 
remains wet, and the top five feet were designed for stormwater 
storage, allowing a 21,422-cubic-foot volume to reduce the 
runoff release rate by more than 20% from the original rate for 
both the 2-year and 100-year events. 
Site water quality is attained by directing watershed to the 
underground wet detention system. The bottom four feet of 
the underground detention system functions as a large wet 
sump with a permanent wet pool area. The wet pool area was 
modeled in WinSLAMM (Source Loading And Management 
Model for Windows), and designed to settle particles and 
provide volume for sediment storage. To meet the WDNR’s 
40% TSS removal requirement, a total of 1,359 pounds 
of sediment removal was required. The underground wet 
detention system removes 1,086 pounds, more than a 60% 
removal rate. Six Catch basins with two-foot sumps were 
designed for a second drainage area to remove an additional 
275 pounds, allowing a combined total 1,361-pound TSS 
removal, which exceeded the 40% WDNR requirement. 
Contech’s underground wet pond detention and treatment 
system reduced peak runoff rate and met the sediment 
collection needs for the project, while keeping the project within 
budget.
Case Study for Underground Wet Ponds 
Site Designation » Ø108” CMP Detention | Menomonee Falls, WI 
www.ContechES.com/UrbanGreen 8 
Case Study for Underground Wet Ponds 
Redevelopment at Main Street 
at Pilgrim Road – Walmart 
Take a Deeper Look, Download the Standard Detail for this Project: 
http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13287 
Image © 2012 Google ∫ Map Data © 2012 Google
Case Study for Underground Wet Ponds 
Boucher Automotive Group 
Franklin, Wisconsin 
Project Team Members: 
Owner: 
Boucher Automotive Group 
Engineer: 
Site Engineering Services 
Contractor: 
D. F. Tomasini Contractors, Inc. 
Technical Description: 
CMP Detention 800-ft. of 72-in. dia. 
Aluminized CMP 
CMP Treatment 23 & 44-ft. of 84-in. 
Aluminized CMP 
Installation Date: February 2012 
A Milwaukee native, Gordon Boucher began his automotive 
career in 1956 in sales for a local dealership. In 1977, 
Boucher opened his first Lincoln-Mercury store, and ultimately 
grew to own 16 southeastern Wisconsin dealerships. To 
showcase additional inventory, Boucher wished to expand his 
Franklin dealership, but expansion couldn’t be complete without 
addressing state stormwater regulations. Boucher contacted 
Site Engineering Services of Hartland, WI, to design the site 
stormwater management plan and project. 
The Wisconsin Department of Natural Resources (DNR) 
mandates that redevelopment projects require a 40% Total 
Suspended Solids (TSS) reduction in the stormwater leaving the 
project. With the urban-set project and Boucher’s direction to 
expand the parking area for at least 200 cars, an aboveground 
TSS removal pond was not an option. To further complicate 
matters, the site layout was long and narrow, with a steep 
cross-slope in the middle. 
“The whole point of the expansion was to gain parking for at 
least 200 cars,” said project engineer Martin Worden of Site 
Engineering Services, referring to the challenging layout of the 
2.51-acre site. “We were really struggling to fit everything the 
client needed on this narrow parcel of land.” 
Underground pipes to store stormwater using catch basins for 
the stormwater quality were considered. When the number of 
catch basins grew to 26, it was evident another solution was 
needed. 
Site Engineering Services contacted Contech for an economical 
solution that met DNR requirements. Contech proposed using 
corrugated metal pipe (CMP) to create an underground water 
detention with two treatment systems designed to imitate 
the bay of a wet pond to conform with the DNR technical 
standards. 
9 www.ContechES.com/UrbanGreen 
“We knew we had to find another solution. The large diameter 
Contech pipe was that solution,” said Worden. “Two sections 
of 84-in. diameter pipe totaling 67-ft. in length replaced the 
26 five-foot-diameter catch basins, and restored sanity to the 
design.” 
Two treatment systems were selected to minimize the collector 
pipe use, and were designed with a 3.5-ft. -deep permanent 
water pool that acts as a pond to capture sediments that wash 
off the proposed parking lot. To maximize settling time, the inlet 
and outlet pipes were placed on each end of the treatment 
units. Another benefit of the detention system was its ability to 
reduce the flow of water leaving the site. 
Utilizing WinSLAMM (Source Loading And Management Model 
for Windows) to evaluate sediment loading of the project site, 
Site Engineering Services determined the treatment systems 
needed 161 square feet of surface area for the north 0.68 
acres and 308 square feet for the south 1.83 acres at the 
spring line of the CMP. The detention system was constructed 
out of 800-ft. of 72-in. dia. CMP to meet the requirement 
for 25,452 cubic feet of active detention storage, while the 
treatment units were constructed out of 84-in. dia. CMP. The 
23-ft. north unit achieved 45% TSS removal rate, and the 44- 
ft. south unit achieved 42%, both greater than the 40% state 
DNR requirement. Aluminized Steel Type 2 (ALT2) coating was 
chosen to meet Boucher’s required 75 year service life. 
“In order to build a pond, we would have needed lots of 
retaining walls around it,” Worden said of the long, narrow 
project site. He said the Contech detention and treatment 
system is “more competitive price wise.” 
Contech’s “underground wet pond” solution, designed using 
the ALT2 CMP detention and treatment systems, met all state 
design requirements and the owner’s specifications, while 
keeping the project within budget.
Site Designation » Ø72” Underground Detention | Franklin, WI 
www.ContechES.com/UrbanGreen 10 
Case Study for Underground Wet Ponds 
Boucher Automotive Group 
Take a Deeper Look, Download the Standard Detail for this Project: 
http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13289 
Image © 2012 Digital Globe, GeoEye, U.S. Geological Survey ∫ Map Data © 2012 Google
Site Designation » Ø48” CMP Underground Detention | De Pere, WI 
www.ContechES.com/UrbanGreen 11 
Case Study for Underground Wet Ponds 
CVS Pharmacy Store 
Take a Deeper Look, Download the Standard Detail for this Project: 
http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13285
Site Designation » Ø78” CMP Underground Detention | Oshkosh, WI 
www.ContechES.com/UrbanGreen 12 
Case Study for Underground Wet Ponds 
Oshkosh Correctional Institution 
Take a Deeper Look, Download the Standard Detail for this Project: 
http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13283
Site Designation » 32’ x 12’ CON/SPAN Detention units | Oshkosh, WI 
www.ContechES.com/UrbanGreen 13 
Case Study for Underground Wet Ponds 
Walmart - West Milwaukee 
Take a Deeper Look, Download the Standard Detail for this Project: 
http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13284
Site Designation » Ø84” CMP Underground Detention | King, WI 
www.ContechES.com/UrbanGreen 14 
Case Study for Underground Wet Ponds 
Wisconsin Veterans Home 
Take a Deeper Look, Download the Standard Detail for this Project: 
http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13286
Design Your Own Detention or Infiltration System 
DYODS is our exclusive online design tool to help you calculate the quantity of material 
needed for your detention or infiltration system. 
You can even compare between CMP, ChamberMaxx and CON/SPAN systems. 
Find all the information you need at 
www.ContechES.com, including product information, 
approvals, brochures, design guides, standard 
details and specifications and more. 
Quick Links 
• LEED information – 
www.ContechES.com/leed 
• LID Application Guide – 
www.ContechES.com/lid 
• Professional Development Articles – 
www.ContechES.com/pdh 
Connect With Us 
We're here to make your job easier – and that 
includes being able to get in touch with us when you 
need to. Search for your local rep at 
www.ContechES.com/connectwithcontech 
While you’re there, be sure to check out our 
upcoming seminar schedule or request an in-house 
technical presentation. 
Links to Other Stormwater Tools 
Check out our design toolbox for all our online tools 
and engineering resources, or to start a project at: 
www.ContechES.com/designtoolbox 
UrbanGreen™ Rainwater Harvesting Runoff 
Reduction Calculator 
www.ContechES.com/rwh-calculator 
Download the Land Value Calculator 
www.ContechES.com/l v c 
ENGINEERED SOLUTIONS 
©2012 Contech Engineered Solutions LLC 
> www.ContechES.com/DYODS 
Next Steps: Dig Deeper 
Get Social With Us! 
» Go Back

More Related Content

What's hot

Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP Ekonnect
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1Theodore McNeal
 
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdfPreliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Bappy114
 
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15Dario Gnoato
 
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
Michael Hewitt, GISP
 
WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16Tim Bail
 
Achs Case Study In Implementing Chps
Achs Case Study In Implementing ChpsAchs Case Study In Implementing Chps
Achs Case Study In Implementing Chps
aaronj
 
Save the Rain Presentation - NYSAC 2012
Save the Rain Presentation - NYSAC 2012Save the Rain Presentation - NYSAC 2012
Save the Rain Presentation - NYSAC 2012
Onondaga County Save the Rain
 
Green infrastructure policy for stormwater infiltration
Green infrastructure policy for stormwater infiltrationGreen infrastructure policy for stormwater infiltration
Green infrastructure policy for stormwater infiltration
Evan Pratt
 
Gary Merritt, Northern Star Generation LLC, “Big Yellow Taxi?…You don’t know...
Gary Merritt, Northern Star Generation LLC,  “Big Yellow Taxi?…You don’t know...Gary Merritt, Northern Star Generation LLC,  “Big Yellow Taxi?…You don’t know...
Gary Merritt, Northern Star Generation LLC, “Big Yellow Taxi?…You don’t know...Michael Hewitt, GISP
 
Optimisation of dewatering systems
Optimisation of dewatering systemsOptimisation of dewatering systems
Optimisation of dewatering systems
Martin Preene
 
Max Simnitt_03-2016_Work History Details
Max Simnitt_03-2016_Work History DetailsMax Simnitt_03-2016_Work History Details
Max Simnitt_03-2016_Work History DetailsMax Simnitt
 
Hydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the IndustryHydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the Industry
Ports-To-Plains Blog
 
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
Stephen Flood
 
LEED ND Squalicum Lofts
LEED ND Squalicum LoftsLEED ND Squalicum Lofts
LEED ND Squalicum Lofts
Cameron Plommer
 
Bob Hedin, Hedin Environmental, “Two Passive Treatment Systems that are Regio...
Bob Hedin, Hedin Environmental, “Two Passive Treatment Systems that are Regio...Bob Hedin, Hedin Environmental, “Two Passive Treatment Systems that are Regio...
Bob Hedin, Hedin Environmental, “Two Passive Treatment Systems that are Regio...
Michael Hewitt, GISP
 
Water Tank Rehabilitation For A Small Community
Water Tank Rehabilitation For A Small CommunityWater Tank Rehabilitation For A Small Community
Water Tank Rehabilitation For A Small Community
Ajay Kashi, P.E.
 
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICTGREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
U.S. Water Alliance
 
Terry Schmidt, Skelly & Loy, “Big Run Restoration: A Success Story”
Terry Schmidt, Skelly & Loy, “Big Run Restoration: A Success Story”Terry Schmidt, Skelly & Loy, “Big Run Restoration: A Success Story”
Terry Schmidt, Skelly & Loy, “Big Run Restoration: A Success Story”
Michael Hewitt, GISP
 
C8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_finalC8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_finalpublicinvolvement
 

What's hot (20)

Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1
 
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdfPreliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
 
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
Highway_40-10_Flood Repairs Report_2013_FINAL_Oct15
 
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
 
WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16
 
Achs Case Study In Implementing Chps
Achs Case Study In Implementing ChpsAchs Case Study In Implementing Chps
Achs Case Study In Implementing Chps
 
Save the Rain Presentation - NYSAC 2012
Save the Rain Presentation - NYSAC 2012Save the Rain Presentation - NYSAC 2012
Save the Rain Presentation - NYSAC 2012
 
Green infrastructure policy for stormwater infiltration
Green infrastructure policy for stormwater infiltrationGreen infrastructure policy for stormwater infiltration
Green infrastructure policy for stormwater infiltration
 
Gary Merritt, Northern Star Generation LLC, “Big Yellow Taxi?…You don’t know...
Gary Merritt, Northern Star Generation LLC,  “Big Yellow Taxi?…You don’t know...Gary Merritt, Northern Star Generation LLC,  “Big Yellow Taxi?…You don’t know...
Gary Merritt, Northern Star Generation LLC, “Big Yellow Taxi?…You don’t know...
 
Optimisation of dewatering systems
Optimisation of dewatering systemsOptimisation of dewatering systems
Optimisation of dewatering systems
 
Max Simnitt_03-2016_Work History Details
Max Simnitt_03-2016_Work History DetailsMax Simnitt_03-2016_Work History Details
Max Simnitt_03-2016_Work History Details
 
Hydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the IndustryHydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the Industry
 
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
Integrating Flood Risk Into Catchment Management - Michael Butts (DHI)
 
LEED ND Squalicum Lofts
LEED ND Squalicum LoftsLEED ND Squalicum Lofts
LEED ND Squalicum Lofts
 
Bob Hedin, Hedin Environmental, “Two Passive Treatment Systems that are Regio...
Bob Hedin, Hedin Environmental, “Two Passive Treatment Systems that are Regio...Bob Hedin, Hedin Environmental, “Two Passive Treatment Systems that are Regio...
Bob Hedin, Hedin Environmental, “Two Passive Treatment Systems that are Regio...
 
Water Tank Rehabilitation For A Small Community
Water Tank Rehabilitation For A Small CommunityWater Tank Rehabilitation For A Small Community
Water Tank Rehabilitation For A Small Community
 
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICTGREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
GREATER CLEVELAND AREA - NORTHEAST OHIO REGIONAL SEWER DISTRICT
 
Terry Schmidt, Skelly & Loy, “Big Run Restoration: A Success Story”
Terry Schmidt, Skelly & Loy, “Big Run Restoration: A Success Story”Terry Schmidt, Skelly & Loy, “Big Run Restoration: A Success Story”
Terry Schmidt, Skelly & Loy, “Big Run Restoration: A Success Story”
 
C8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_finalC8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_final
 

Similar to Underground Wet Ponds for Stormwater Management in Wisconsin

Midterm cu stormwater report.docx
Midterm cu stormwater report.docxMidterm cu stormwater report.docx
Midterm cu stormwater report.docx
cbwalke
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Iain McGregor
 
Sustainable Site Design
Sustainable Site DesignSustainable Site Design
Sustainable Site Design
Christopher Hitch
 
Construction Dewatering PowerPoint
Construction Dewatering PowerPointConstruction Dewatering PowerPoint
Construction Dewatering PowerPoint
Terry Aylward
 
Waterman Drainage Project
Waterman Drainage ProjectWaterman Drainage Project
Waterman Drainage ProjectAndrew Motycka
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACECSDES
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence AwardsACECSDES
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence Awards
ACECSDES
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For WebACECSDES
 
Feb 11 2014 public meeting show
Feb 11 2014 public meeting showFeb 11 2014 public meeting show
Feb 11 2014 public meeting show
MCDEP
 
Storm Water Utility Dev. and Master Plans
Storm Water Utility Dev. and Master PlansStorm Water Utility Dev. and Master Plans
Storm Water Utility Dev. and Master Plans
South Shore Clean Cities
 
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Joseph Merzlak
 
Cu stormwater proposal
Cu stormwater proposalCu stormwater proposal
Cu stormwater proposal
cbwalke
 
Enhancing Low Impact Development Designs Using Manufactrured BMP's
Enhancing Low Impact Development Designs Using Manufactrured BMP'sEnhancing Low Impact Development Designs Using Manufactrured BMP's
Enhancing Low Impact Development Designs Using Manufactrured BMP's
Contech Engineered Solutions
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715Max Kroschel
 
LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2
TidalInlfluence
 
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Fu Michael Justin
 
Fairfax County Flood Response Strategy
Fairfax County Flood Response StrategyFairfax County Flood Response Strategy
Fairfax County Flood Response Strategy
Fairfax County
 
Hydro International - What is HX
Hydro International - What is HXHydro International - What is HX
Hydro International - What is HX
HydroInternationalSildes
 

Similar to Underground Wet Ponds for Stormwater Management in Wisconsin (20)

Midterm cu stormwater report.docx
Midterm cu stormwater report.docxMidterm cu stormwater report.docx
Midterm cu stormwater report.docx
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014
 
Sustainable Site Design
Sustainable Site DesignSustainable Site Design
Sustainable Site Design
 
Capstone
CapstoneCapstone
Capstone
 
Construction Dewatering PowerPoint
Construction Dewatering PowerPointConstruction Dewatering PowerPoint
Construction Dewatering PowerPoint
 
Waterman Drainage Project
Waterman Drainage ProjectWaterman Drainage Project
Waterman Drainage Project
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence Awards
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence Awards
 
2009 Engineering Excellence Awards
2009 Engineering Excellence Awards2009 Engineering Excellence Awards
2009 Engineering Excellence Awards
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For Web
 
Feb 11 2014 public meeting show
Feb 11 2014 public meeting showFeb 11 2014 public meeting show
Feb 11 2014 public meeting show
 
Storm Water Utility Dev. and Master Plans
Storm Water Utility Dev. and Master PlansStorm Water Utility Dev. and Master Plans
Storm Water Utility Dev. and Master Plans
 
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
 
Cu stormwater proposal
Cu stormwater proposalCu stormwater proposal
Cu stormwater proposal
 
Enhancing Low Impact Development Designs Using Manufactrured BMP's
Enhancing Low Impact Development Designs Using Manufactrured BMP'sEnhancing Low Impact Development Designs Using Manufactrured BMP's
Enhancing Low Impact Development Designs Using Manufactrured BMP's
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715
 
LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2
 
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
 
Fairfax County Flood Response Strategy
Fairfax County Flood Response StrategyFairfax County Flood Response Strategy
Fairfax County Flood Response Strategy
 
Hydro International - What is HX
Hydro International - What is HXHydro International - What is HX
Hydro International - What is HX
 

More from Contech Engineered Solutions

Site Solutions by Contech
Site Solutions by ContechSite Solutions by Contech
Site Solutions by Contech
Contech Engineered Solutions
 
CMP Solutions by Contech
CMP Solutions by ContechCMP Solutions by Contech
CMP Solutions by Contech
Contech Engineered Solutions
 
2018 Contech Calendar
2018 Contech Calendar2018 Contech Calendar
2018 Contech Calendar
Contech Engineered Solutions
 
Contech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial MarketsContech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial Markets
Contech Engineered Solutions
 
Contech DuroMaxx Steel Reinforced Polyethylene
Contech DuroMaxx Steel Reinforced PolyethyleneContech DuroMaxx Steel Reinforced Polyethylene
Contech DuroMaxx Steel Reinforced Polyethylene
Contech Engineered Solutions
 
2017 Contech Calendar
2017 Contech Calendar2017 Contech Calendar
2017 Contech Calendar
Contech Engineered Solutions
 
2016 Contech Calendar
2016 Contech Calendar2016 Contech Calendar
2016 Contech Calendar
Contech Engineered Solutions
 
How Stormwater Treatment Trains Work
How Stormwater Treatment Trains WorkHow Stormwater Treatment Trains Work
How Stormwater Treatment Trains Work
Contech Engineered Solutions
 
Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...
Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...
Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...
Contech Engineered Solutions
 
Taking out the Trash: Setting achievable trash discharge reduction goals and ...
Taking out the Trash:Setting achievable trash discharge reduction goals and ...Taking out the Trash:Setting achievable trash discharge reduction goals and ...
Taking out the Trash: Setting achievable trash discharge reduction goals and ...
Contech Engineered Solutions
 
How Rainwater Harvesting Works
How Rainwater Harvesting WorksHow Rainwater Harvesting Works
How Rainwater Harvesting Works
Contech Engineered Solutions
 
2015 Contech Calendar
2015 Contech Calendar2015 Contech Calendar
2015 Contech Calendar
Contech Engineered Solutions
 
Maximizing Phosphorus Load Reduction
Maximizing Phosphorus Load ReductionMaximizing Phosphorus Load Reduction
Maximizing Phosphorus Load Reduction
Contech Engineered Solutions
 
Low Impact Developement Site Planner
Low Impact Developement Site Planner Low Impact Developement Site Planner
Low Impact Developement Site Planner
Contech Engineered Solutions
 
Stormwater Products Slideshow - Contech Engineered Solution
Stormwater Products Slideshow - Contech Engineered Solution Stormwater Products Slideshow - Contech Engineered Solution
Stormwater Products Slideshow - Contech Engineered Solution
Contech Engineered Solutions
 
Rainwater Harvesting Answer Book
Rainwater Harvesting Answer BookRainwater Harvesting Answer Book
Rainwater Harvesting Answer Book
Contech Engineered Solutions
 
Rehab Solutions for Today's Infrastructure
Rehab Solutions for Today's InfrastructureRehab Solutions for Today's Infrastructure
Rehab Solutions for Today's Infrastructure
Contech Engineered Solutions
 

More from Contech Engineered Solutions (17)

Site Solutions by Contech
Site Solutions by ContechSite Solutions by Contech
Site Solutions by Contech
 
CMP Solutions by Contech
CMP Solutions by ContechCMP Solutions by Contech
CMP Solutions by Contech
 
2018 Contech Calendar
2018 Contech Calendar2018 Contech Calendar
2018 Contech Calendar
 
Contech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial MarketsContech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial Markets
 
Contech DuroMaxx Steel Reinforced Polyethylene
Contech DuroMaxx Steel Reinforced PolyethyleneContech DuroMaxx Steel Reinforced Polyethylene
Contech DuroMaxx Steel Reinforced Polyethylene
 
2017 Contech Calendar
2017 Contech Calendar2017 Contech Calendar
2017 Contech Calendar
 
2016 Contech Calendar
2016 Contech Calendar2016 Contech Calendar
2016 Contech Calendar
 
How Stormwater Treatment Trains Work
How Stormwater Treatment Trains WorkHow Stormwater Treatment Trains Work
How Stormwater Treatment Trains Work
 
Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...
Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...
Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...
 
Taking out the Trash: Setting achievable trash discharge reduction goals and ...
Taking out the Trash:Setting achievable trash discharge reduction goals and ...Taking out the Trash:Setting achievable trash discharge reduction goals and ...
Taking out the Trash: Setting achievable trash discharge reduction goals and ...
 
How Rainwater Harvesting Works
How Rainwater Harvesting WorksHow Rainwater Harvesting Works
How Rainwater Harvesting Works
 
2015 Contech Calendar
2015 Contech Calendar2015 Contech Calendar
2015 Contech Calendar
 
Maximizing Phosphorus Load Reduction
Maximizing Phosphorus Load ReductionMaximizing Phosphorus Load Reduction
Maximizing Phosphorus Load Reduction
 
Low Impact Developement Site Planner
Low Impact Developement Site Planner Low Impact Developement Site Planner
Low Impact Developement Site Planner
 
Stormwater Products Slideshow - Contech Engineered Solution
Stormwater Products Slideshow - Contech Engineered Solution Stormwater Products Slideshow - Contech Engineered Solution
Stormwater Products Slideshow - Contech Engineered Solution
 
Rainwater Harvesting Answer Book
Rainwater Harvesting Answer BookRainwater Harvesting Answer Book
Rainwater Harvesting Answer Book
 
Rehab Solutions for Today's Infrastructure
Rehab Solutions for Today's InfrastructureRehab Solutions for Today's Infrastructure
Rehab Solutions for Today's Infrastructure
 

Recently uploaded

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 

Recently uploaded (20)

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 

Underground Wet Ponds for Stormwater Management in Wisconsin

  • 1. Wet Ponds a Contech Solution for Stormwater Management A compilation of case studies highlighting the advantages of a wet pond solution provided by Contech Engineered Solutions that will meet (and sometimes exceed) the TSS mandates stipulated by the Wisconsin Department of Natural Resources. 2012 | www.ContechES.com/UrbanGreen Stormwater Solutions from Contech®
  • 2. www.ContechES.com/UrbanGreen 2 Table of Contents Check out more » stormwater management solutions provided by Contech Engineered Solutions at www.ContechES.com/urbangreen Stormwater Solutions The Contech fit with WINSLAMM for TSS Removal| 4 Underground Wet Ponds Modeling Options| 5 Wisconsin Project List | 5 Case Studies Sacred Heart Senior Apartments » Saint Francis, WI | 6 Redevelopment at Main Street & Pilgrim Road » Menomonee Falls, WI | 8 Boucher Automotive Group » Franklin, WI | 10 © 2012 Contech Engineered Solutions LLC
  • 3. A Stormwater Solution for Wet Ponds Contech fits WINSLAMM for TSS Removal with their Underground “Pond” www.ContechES.com/UrbanGreen 3 Wet Ponds Wisconsin Department of Natural Resources (WDNR) mandates that New Development projects reduce Total Suspended Solids (TSS) by 80% and a 40% TSS reduction for redevelopment projects. One option is to construct a Wet Pond with a permanent pool of water. However, for most urban-set projects this is not an option due to limited land resources. Contech’s economical solution to meet the WDNR TSS removal requirements is to construct “Underground Wet Ponds” using metal, plastic and concrete systems. The lower portion of the pipe contains a permanent water pool to remove TSS while the upper half of the pipe can be used for Active Storage if needed. With the “Pond” underground the land can be utilized for other uses, most often parking. Interested in learning more? We’d love to hear from you! » Eric Sturm | Project Consultant (608) 215-3937 esturm@conteches.com » Todd Riebau | Project Consultant (608) 576-0109 triebau@conteches.com » Keith Johnson | Sales Engineer (920) 860-0989 kjohnson@conteches.com
  • 4. www.ContechES.com/UrbanGreen 4 Wet Ponds Underground Wet Ponds Modeling a Contech System in WINSLAMM Underground Wet Ponds can be modeled two ways in WINSLAMM: 1 Catch Basin After entering the necessary project parameters, alter the catch basin size until the TSS removal rate meets or exceeds the project requirements. The screen shots to the right illustrate a project in the Milwaukee area, one acre of impervious area and a 40% TSS removal requirement. After a couple iterations in the catch basin routine, WINSLAMM determined that 266 sf of surface area is required. This equates to 38 lf of 84” dia. CMP with a 3.5’ deep permanent water pool. Another option would be to use 47’ of 72” dia. CMP with a 4’ pool. 2 Treatment/Detention System as a Pond The majority of the projects that Contech Engineered Solutions has been involved with require either a 3.5’ or 4’ permanent water pool. Three feet of permanent water pool for particles to settle out of solution and a 0.5’ to 1’ sediment collection area. We have the experience to prove it. Here are a few examples! » Johnson Bank | Brookfield » UW Credit Union| West Allis » Walmart | Menonmonee Falls » West Milwaukee | West Milwaukee » Walmart | South Milwaukee » Wisconsin Veterans Home | King » CVS Pharmacy | De Pere » Cabela’s | Ashwaubenon » Boucher Automotive | Franklin » Sacred Heart | St. Francis » Oshkosh Correctional | Oshkosh
  • 5. Case Study for Underground Wet Ponds Sacred Heart Senior Apartments Saint Francis, Wisconsin Project Team Members: Owner: Sacred Heart of Jesus Parish Engineer: The Sigma Group Contractor: A.W. Oakes & Son Technical Description: CMP Detention 644-ft. of 142-in. x 91-in. CMP Installation Date: August 2011 The Sacred Heart of Jesus Church, originally built in the early 1960s, was renovated to include a new senior living apartment community. The community, called the Sacred Heart Senior Apartments, is a non-denominational facility and seniors of all faiths are welcome. The renovated sanctuary and rectory are 19,058 sf of the 113,735 sf project. The apartments occupied 84,081 sf in the renovated space above the church, which were formerly school classrooms, and also in the newly-built addition on what was parking lot. There also is a 10,595 sf common room shared between church and apartments “We’re trying to reinvent ourselves,” said Eric Stemwell, Sacred Heart Parish Core Team. “It’s kind of an experiment, teaming up with a developer to offer senior housing. Senior citizens are a very vital part of any community. What we’re trying to do is create an environment where senior citizens can thrive.” The church contacted The Sigma Group of Milwaukee to design the civil portion of the project which included the stormwater management plan for the site. The state Department of Natural Resources (DNR) requires Total Suspended Solids(TSS) reduction in stormwater leaving the site of 80% for new developments and 40% for redeveloped projects. The 4.0-acre senior apartment complex project was considered partially new development and partially redevelopment; resulting in a weighted TSS reduction requirement of 50%. Because the project was located in an urban setting, The Sigma Group did not have the option of an aboveground 5 www.ContechES.com/UrbanGreen stormwater pond for the required TSS removal. Instead, they looked at “mechanical” options that would be contained beneath the parking lot. The Sigma Group contacted Contech Engineered Solutions for assistance in providing an economical solution to meet the DNR requirements. The project covered 4.0 acres. Of that, 2.83 acres were treated and 1.17 acres were taken offsite with 0% removal. Contech proposed an underground stormwater detention system utilizing corrugated metal pipe (CMP) to treat the 2.83 acreage because it could achieve the weighted 50% TSS reduction requirement. This solution also met all of the project requirements while keeping within budget. Utilizing WinSLAMM (Source Loading And Management Model for Windows) to evaluate sediment loading of the project site, the Sigma Group determined that the underground system needed 7,390 sf of surface area at the water line and 48,035 cf of active detention storage. The CMP detention system was constructed out of 644 feet of 142-in. x 91-in. CMP coated with aluminum to fulfill the surface area and active storage area requirements. Aluminized, ALT2 coating was chosen to meet the 75 year service life required by the owner. The system was designed with a 3.5’ permanent pool of water in a serpentine configuration to maximize the settling time. The calculated TSS removal rate from Contech’s “underground wet pond” solution was 76.61% - resulting in a net TSS removal of 56%, greater than the 50% required, for the entire 4.0 acre site.
  • 6. Case Study for Underground Wet Ponds Site Designation » 142x91 Underground Storage | Saint Francis, WI www.ContechES.com/UrbanGreen 6 Case Study for Underground Wet Ponds Sacred Heart of Jesus Senior Apartments Take a Deeper Look, Download the Standard Detail for this Project: http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13288
  • 7. Case Study for Underground Wet Ponds Redevelopment at Main Street & Pilgrim Road Menomonee Falls, Wisconsin Project Team Members: Owner: Gatlin Development Co. Inc. Engineer: R.A. Smith National, Inc. Contractor: D. F. Tomasini Contractors, Inc. Technical Description: CMP Detention 600-ft. of 108-in. dia. Aluminized CMP Installation Date: February 2012 A $10 million development anchored by a Walmart Neighborhood Market Store, their smaller grocery format, in the Village of Menomonee Falls, Wisconsin. Construction design for this 40,000-sf Walmart and separate 5,000- sf building for other retail tenants included a stormwater management plan. The Wisconsin Department of Natural Resources (WDNR) requires total suspended solids (TSS) reduction in stormwater leaving the project — 80% for new developments and 40% for redevelopments. The 9.22 acre Walmart project was being constructed on the site of a closed supermarket, making this a redevelopment. Additionally, the flow rates for stormwater leaving the site needed to be addressed. Walmart contacted R.A. Smith National of Brookfield, WI, to design the civil portion of the project, which included the stormwater management plan for the site. Because this project is in an urban setting, R.A Smith National did not have the option of an aboveground stormwater pond for detention and TSS removal. Instead, they looked at economical “mechanical” options to contain stormwater beneath the parking lot to reduce the footprint and maximize land use. “Due to the dense redevelopment plan and the need to provide water quality, it was apparent that the only way to achieve our goals was to go with an underground facility”, said project engineer Jeremy Jeffery of R.A. Smith National. R.A. Smith National chose a corrugated metal pipe (CMP) detention and treatment system from Contech Engineered Solutions to satisfy the runoff release rates and TSS removal requirements set forth by the Village of Menomonee Falls, the Milwaukee Metropolitan Sewerage District and the WDNR. 7 www.ContechES.com/UrbanGreen “The Contech design proved to give us the most bang for the buck,” said Jeffery. “We were looking for a product that would provide the smallest footprint, superior durability and service life, and easy installation, all while being cost-effective. But the most important of all — a product that would meet all regulating agencies requirements.” The underground wet detention facility from Contech consisted of 600-feet of 9-foot diameter Aluminized Type 2 (ALT2) CMP pipe interconnected by a header. The bottom four feet of pipe remains wet, and the top five feet were designed for stormwater storage, allowing a 21,422-cubic-foot volume to reduce the runoff release rate by more than 20% from the original rate for both the 2-year and 100-year events. Site water quality is attained by directing watershed to the underground wet detention system. The bottom four feet of the underground detention system functions as a large wet sump with a permanent wet pool area. The wet pool area was modeled in WinSLAMM (Source Loading And Management Model for Windows), and designed to settle particles and provide volume for sediment storage. To meet the WDNR’s 40% TSS removal requirement, a total of 1,359 pounds of sediment removal was required. The underground wet detention system removes 1,086 pounds, more than a 60% removal rate. Six Catch basins with two-foot sumps were designed for a second drainage area to remove an additional 275 pounds, allowing a combined total 1,361-pound TSS removal, which exceeded the 40% WDNR requirement. Contech’s underground wet pond detention and treatment system reduced peak runoff rate and met the sediment collection needs for the project, while keeping the project within budget.
  • 8. Case Study for Underground Wet Ponds Site Designation » Ø108” CMP Detention | Menomonee Falls, WI www.ContechES.com/UrbanGreen 8 Case Study for Underground Wet Ponds Redevelopment at Main Street at Pilgrim Road – Walmart Take a Deeper Look, Download the Standard Detail for this Project: http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13287 Image © 2012 Google ∫ Map Data © 2012 Google
  • 9. Case Study for Underground Wet Ponds Boucher Automotive Group Franklin, Wisconsin Project Team Members: Owner: Boucher Automotive Group Engineer: Site Engineering Services Contractor: D. F. Tomasini Contractors, Inc. Technical Description: CMP Detention 800-ft. of 72-in. dia. Aluminized CMP CMP Treatment 23 & 44-ft. of 84-in. Aluminized CMP Installation Date: February 2012 A Milwaukee native, Gordon Boucher began his automotive career in 1956 in sales for a local dealership. In 1977, Boucher opened his first Lincoln-Mercury store, and ultimately grew to own 16 southeastern Wisconsin dealerships. To showcase additional inventory, Boucher wished to expand his Franklin dealership, but expansion couldn’t be complete without addressing state stormwater regulations. Boucher contacted Site Engineering Services of Hartland, WI, to design the site stormwater management plan and project. The Wisconsin Department of Natural Resources (DNR) mandates that redevelopment projects require a 40% Total Suspended Solids (TSS) reduction in the stormwater leaving the project. With the urban-set project and Boucher’s direction to expand the parking area for at least 200 cars, an aboveground TSS removal pond was not an option. To further complicate matters, the site layout was long and narrow, with a steep cross-slope in the middle. “The whole point of the expansion was to gain parking for at least 200 cars,” said project engineer Martin Worden of Site Engineering Services, referring to the challenging layout of the 2.51-acre site. “We were really struggling to fit everything the client needed on this narrow parcel of land.” Underground pipes to store stormwater using catch basins for the stormwater quality were considered. When the number of catch basins grew to 26, it was evident another solution was needed. Site Engineering Services contacted Contech for an economical solution that met DNR requirements. Contech proposed using corrugated metal pipe (CMP) to create an underground water detention with two treatment systems designed to imitate the bay of a wet pond to conform with the DNR technical standards. 9 www.ContechES.com/UrbanGreen “We knew we had to find another solution. The large diameter Contech pipe was that solution,” said Worden. “Two sections of 84-in. diameter pipe totaling 67-ft. in length replaced the 26 five-foot-diameter catch basins, and restored sanity to the design.” Two treatment systems were selected to minimize the collector pipe use, and were designed with a 3.5-ft. -deep permanent water pool that acts as a pond to capture sediments that wash off the proposed parking lot. To maximize settling time, the inlet and outlet pipes were placed on each end of the treatment units. Another benefit of the detention system was its ability to reduce the flow of water leaving the site. Utilizing WinSLAMM (Source Loading And Management Model for Windows) to evaluate sediment loading of the project site, Site Engineering Services determined the treatment systems needed 161 square feet of surface area for the north 0.68 acres and 308 square feet for the south 1.83 acres at the spring line of the CMP. The detention system was constructed out of 800-ft. of 72-in. dia. CMP to meet the requirement for 25,452 cubic feet of active detention storage, while the treatment units were constructed out of 84-in. dia. CMP. The 23-ft. north unit achieved 45% TSS removal rate, and the 44- ft. south unit achieved 42%, both greater than the 40% state DNR requirement. Aluminized Steel Type 2 (ALT2) coating was chosen to meet Boucher’s required 75 year service life. “In order to build a pond, we would have needed lots of retaining walls around it,” Worden said of the long, narrow project site. He said the Contech detention and treatment system is “more competitive price wise.” Contech’s “underground wet pond” solution, designed using the ALT2 CMP detention and treatment systems, met all state design requirements and the owner’s specifications, while keeping the project within budget.
  • 10. Site Designation » Ø72” Underground Detention | Franklin, WI www.ContechES.com/UrbanGreen 10 Case Study for Underground Wet Ponds Boucher Automotive Group Take a Deeper Look, Download the Standard Detail for this Project: http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13289 Image © 2012 Digital Globe, GeoEye, U.S. Geological Survey ∫ Map Data © 2012 Google
  • 11. Site Designation » Ø48” CMP Underground Detention | De Pere, WI www.ContechES.com/UrbanGreen 11 Case Study for Underground Wet Ponds CVS Pharmacy Store Take a Deeper Look, Download the Standard Detail for this Project: http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13285
  • 12. Site Designation » Ø78” CMP Underground Detention | Oshkosh, WI www.ContechES.com/UrbanGreen 12 Case Study for Underground Wet Ponds Oshkosh Correctional Institution Take a Deeper Look, Download the Standard Detail for this Project: http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13283
  • 13. Site Designation » 32’ x 12’ CON/SPAN Detention units | Oshkosh, WI www.ContechES.com/UrbanGreen 13 Case Study for Underground Wet Ponds Walmart - West Milwaukee Take a Deeper Look, Download the Standard Detail for this Project: http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13284
  • 14. Site Designation » Ø84” CMP Underground Detention | King, WI www.ContechES.com/UrbanGreen 14 Case Study for Underground Wet Ponds Wisconsin Veterans Home Take a Deeper Look, Download the Standard Detail for this Project: http://www.conteches.com/Site-Management/Document-Management.aspx?Command=Core_Download&EntryId=13286
  • 15. Design Your Own Detention or Infiltration System DYODS is our exclusive online design tool to help you calculate the quantity of material needed for your detention or infiltration system. You can even compare between CMP, ChamberMaxx and CON/SPAN systems. Find all the information you need at www.ContechES.com, including product information, approvals, brochures, design guides, standard details and specifications and more. Quick Links • LEED information – www.ContechES.com/leed • LID Application Guide – www.ContechES.com/lid • Professional Development Articles – www.ContechES.com/pdh Connect With Us We're here to make your job easier – and that includes being able to get in touch with us when you need to. Search for your local rep at www.ContechES.com/connectwithcontech While you’re there, be sure to check out our upcoming seminar schedule or request an in-house technical presentation. Links to Other Stormwater Tools Check out our design toolbox for all our online tools and engineering resources, or to start a project at: www.ContechES.com/designtoolbox UrbanGreen™ Rainwater Harvesting Runoff Reduction Calculator www.ContechES.com/rwh-calculator Download the Land Value Calculator www.ContechES.com/l v c ENGINEERED SOLUTIONS ©2012 Contech Engineered Solutions LLC > www.ContechES.com/DYODS Next Steps: Dig Deeper Get Social With Us! » Go Back